OLIVER MASSMANN – GBA Board Member
Partner, General Director
DUANE MORRIS VIETNAM LLC
In Solarenergie in Vietnam investieren
Wie macht man es richtig?
1
www.duanemorris.com
Tagesordnung
•Hintergrund zur (Solar-) Energie Branche in Vietnam
•Regulatorische Rahmenbedingungen von erneuerbarer
(Solar-) Energie
•Investitionsrichtlinien für Investoren
•Empfehlungen
2
www.duanemorris.com
Hintergrund zum Energiebereich
• Nachfrage an Elektrizität soll
laut Erwartungen um bis zu
11.4 Prozent im Zeitraum
2016-2020 zunehmen und um
das 7-fache bis zu 800
Milliarde Kwh bis 2030
• Laut Prognosen wird der
Elektrizitätsverbrauch von
85,932 Gigawattstunde
(GWh) in 2010 zu 251,763
GWh bis 2020 zunehmen
3
www.duanemorris.com
Potenzial der Solarenergie-Branche in Vietnam
• Gesamtzahl der Sonnenscheinstunden bis zu 1400 – 3000
Stunden/Jahr
• Potenzial: 4-6 kWh/m2
• Aktuelle Nutzung: 5 MW
• Solarenergie kann zum Wasser sieden, Energieerzeugung
und zu anderen Zwecken wie z.B. Trocknung, Kochen
etc. verwendet werden
4
www.duanemorris.com
Regulatorische Rahmenbedingungen der
Solarenergie
• Elektrizitätsgesetz 2004 und 2012
• Der überarbeitete Stromentwicklungsplan 2011-2020 (überarbeitet
PDP VII) genehmigt durch Premierminister in dem Beschluss
428/QD-TTg vom 18 März 2016
• Beschluss 2068/QD-TTg vom 25 November 2015 auf
Entwicklungsstrategie und Vision der RE bis 2050.
• Beschluss 11/2017/QD-TTg vom 11 April 2017 von dem PM
zum Beistandsmechanismus für die Entwicklung von Solarenergie
Projekten in Vietnam
• Entwurf des Anforderungsrundschreiben zu Entwicklungsschutz
und Muster PPA für Solarenergie-Projekte vom 29 April 2017
durch die MOIT5
www.duanemorris.com
Neugefasster Energie Entwicklungsplan VII durch die
Entwicklung der Elektrizität in Vietnam
• Neugefasster Entwicklungsplan VII fokussiert auf Energiesicherheit, Energieeffizienz,
Entwicklung der erneuerbaren Energien und der Energie Markt Liberalisierung
• Ziele:
• Die Gesamtleistung von importierter und produzierter Elektrizität zu 235-245 Milliarden
kWh bis zu 2020; 352 – 379 Milliarden kWh bis zu 2025 und 506 – 559 Milliarden kWh
bis zu 2030, zu steigern
• Die Entwicklung der Erzeugung von erneuerbare Energie zu priorisieren, sodass das
Verhältnis der Energieerzeugung von erneuerbarer Energie von momentan 3.5% der
insgesamten Elektrizitätsproduktion zu 7% in 2020 und 10% in 2030 zunimmt
• Das ländliche Elektrifizierungsprogramm zu fördern damit die meisten ländlichen
Haushalte Anschluss zur Elektrizität bis 2020 haben
• Flexible Funktionsweise des Stromnetzes zu bauen, hohe Automatisierung der
Übertragung zum Verteilungsprozess, Entwicklung des Umspannwerks ohne
Anforderungen des durchführenden Personals.
6
www.duanemorris.com
Neugefasster Energie Entwicklungsplan VII
• Strategien:
• Höhere Qualität der Elektrizitätsversorgung und ein akzeptablerer Elektrizitätspreis
• Erweiterung von inländischen Quellen für Energieerzeugung
• Entwickeln von neuen erneuerbaren Energiequellen und Technologien auf den neusten
Stand bringen, die in bestehenden Anlagen verwendet wird
• Verteilung der Investitionsmittel um den Mangel an finanziellen und technischen Mitteln
zu überwinden und außerdem die wirtschaftliche Effizienz zu verbessern
• Investitionskapitalbedarf:
• Circa 40 Milliarde US Dollar bis zu 2020: Zweidrittel für Energieerzeugungsentwicklung
und ein Drittel für Energienetzentwicklung
• Ungefähr 108 Milliarde US Dollar für den Zeitraum von 2021 bis 2030: 74% für
Energieerzeugung und 26% für Energienetzentwicklung
7
www.duanemorris.com
Neugefasster Energieentwicklungsplan VII
• Vorbringen um das Monopol der Übertragung zu
erhalten
• Priorisierung der Entwicklung für erneuerbare
Energie
• Zieleinschätzung der erneuerbaren Energie bei 7 %
der Gesamtenergieleistung bis 2020 und mehr als 10
% bis 2030.
• Zunahme der Solarenergieproduktion zu 850 MW bis
2020, 4,000 MW bis 2025 und 12,000 MW in 2030.
8
www.duanemorris.com
Vietnams Elektroenergiemix
• Vietnams Strategie betont das Erfordernis die Energiekombination des Landes
aufzuteilen während die Nutzung der lokalen Energiereserven maximiert wird
• Aktuell entwickelt Vietnam einen Energiemix Bereich mit Kohlekraft als
Hauptsäule
9
www.duanemorris.com
Solarentscheidung
• FIT:
• Stromnetzprojekte: 9.35 US Cents/kWh. Der Preis in VND wird angepasst
übereinstimmend zur Schwankung des VND/USD Wechselkurses. Jedoch
beinhaltet der Entwurf PPA keinen Bezug zu den
Lebenserhaltungskostenindex, Wechselkurs oder Inflationsrisiken.
• Kein FIT für Dachprojekte außerhalb des Stromnetzes
• Nettomessung: anwendbar für Dachprojekte. Betrag der Überlieferung wird
im Folgemonat gutgeschrieben. Zum Ende des Jahres oder
Außerkrafttreten des PPA, wird der überschrittene Betrag an EVN zu 9.35
US Cents / kWh verkauft.
100
www.duanemorris.com
Entwurf PPA
• Nicht verhandelbare PPA und verbindliche Anwendung für Netzverbundene
Solarprojekte
• EVN hat die Verpflichtung die gesamte Elektrizität, erzeugt durch Solarenergie
Projekte, zu kaufen. Jedoch könnte EVN, nach dem Entwurf PPA, den Ankauf
von Elektrizität unter bestimmten Umständen die jenseits vernünftiger
Kontrolle durch den Verkäufer liegen, beenden, ohne irgendeine Entschädigung
oder Bezahlung an den Verkäufer / Projektentwickler.
• Der Käufer muss den Verkäufer nur für die tatsächlich erhaltene Elektrizität
bezahlen. Der Entwurf PPA beinhaltet keine Regelung in der es dem Käufer
nicht möglich ist die produzierte Elektrizität anzunehmen.
• Konfliktlösung: Durch Prozess vor Vietnamesischer Gerichte oder Mediation /
Lösung vor autorisierten Energiestaatsstellen von Vietnam. Kein internationales
Schiedsgericht ist genannt!
111
www.duanemorris.com
Bestätigung der Regierung bezüglich des PPA
• In den kürzlich abgeschlossenen Wind PPAs,
subventionierte die Regierung EVN 1 US Cent / kWh in
Bezug auf die gesamte Energieleistung, die an EVN
verkauft wurde
• Diese Subventionierung bestand nicht mehr in der
letzten Solarentscheidung
• Entwurf Solar PPA: Keine Regelung irgendeiner Art von
Regierungsgarantie um die Glaubwürdigkeit von EVN zu
verbessern
• Kein Hinweis um die Solar PPA profitabel zu machen.122
www.duanemorris.com
Die EVN
• PPA ist verpflichtet einem bestimmten Muster zu folgen,
das nicht profitabel ist.
• Es ist unklar, ob das PPA Muster eine „nimm oder
bezahl“ Vereinbarung ist.
• Keine Abänderung des PPA Musters ist möglich, außer
die Ergänzung zur Klarstellung der Rechte und Pflichten
der Parteien, vorausgesetzt dass sie keine Grundinhalte
des PPA Musters verändert
133
www.duanemorris.com144
Ich bin nur EVN (Mensch)Ich bin nur EVN (Mensch)
Beschuldigte nicht mich dafür!
www.duanemorris.com
Investitionsrichtlinien für ausländische Inverstoren
155
www.duanemorris.com
Marktzugang und Formen der Investition
• Keine ausländischen Eigentumsbeschränkungen
• Investierungsarten:
• Ein Unternehmen mit ausschließlich ausländischer
Beteiligung
• Ein Gemeinschaftsunternehmen zwischen ausländischen-
und inländischen Investoren
• Investition entsprechend der BOT Gesetzeslage
• Durch den Kauf von Anteilen in entweder eine EVN
Tochtergesellschaft oder durch Ausgleich oder einen privaten
IPP vermögenswerten Energieanteil.
166
www.duanemorris.com
BOT – Beste Investierungsart
• Verordnung der Regierung Nr. 15/2015/ND-CP auf öffentlich-
privaten Partnerschaft: Projekte profitabler machen
• Einfacher vorteilhaftere Elektrizitätsraten auszuhandeln.
• Einfacher mehr Staatsgarantien zu erhalten, speziell in Bezug auf
EVN´s Verpflichtung die gesamte Elektrizität des Projekts zu
erwerben.
• Mehr steuerliche und finanzielle Anreize.
• Vorangehende umfangreiche BOT Energieprojekte in Vietnam:
• Phu My, Vung Ang, Mong Duong 2
177
www.duanemorris.com
Investierungsanreize
• Nach Maßgabe der Entscheidung des örtlichen Personenkomitee, wo das
Projekt gelegen ist
• Land: Befreiung von Grundstücksvermietung innerhalb von 3 Jahren von dem
Betriebsdatum des Projects an, etc.
• CIT 10 %
• 15 Jahre für neue Unternehmen die in Energieanlagenprojekte investieren
• Steuerliche Befreiungen innerhalb von 4 Jahren und Steuerermäßigungen von
50% in den nächsten 9 Jahren.
• Befreiung des Einfuhrzolls
• Auf Güter die importiert wurden um Anlagegegenstände des Projekts zu
schaffen; Komponenten, Materialien und halbfertige Produkte, die nicht in der
Heimat verfügbar sind für den Betrieb des Projekts.
188
www.duanemorris.com
Projektplanung
• Investoren müssen vorher die EVN Vereinbarung erhalten bezogen auf den Energiekauf
vor dem Zulassungsverfahren.
• Verpflichtung der Banken oder Kreditinstitute das Projekt zu finanzieren, müssen
vorliegen vor der Ausgabe des Zertifikats für Investitionszulassung.
• Grundsätzlich Genehmigung des örtlichen Personenkomitee vorausgesetzt, bevor die
Ausgabe des Zertifikats für Investitionszulassung abhängig von der Projektgröße erfolgt
• Eine Solarenergieanlage muss eine Genehmigung zur Energieerzeugung von den
zuständigen staatlichen Behörden erhalten, um Energieerzeugungsbetrieb in Vietnam
durchzuführen
• Laufzeit der Genehmigung: Maximal 20 Jahre für große Energieanlagen mit bestimmter
wichtiger Bedeutung an der Wirtschaft, Gesellschaft, nationale Verteidigung und
Sicherheit gemäß der Liste anerkannt durch den Premierminister; und 10 Jahre für andere
Energieanlagen Projekte.
• Die Genehmigung kann nicht erneuert werden, aber der Investor kann eine neue
beantragen innerhalb von 60 Tagen vor dem Ablaufdatum der aktuellen Genehmigung.
199
www.duanemorris.com
Projektzulassung
• Schritt 1: Der Investor erhält die Genehmigung von der zuständigen Landesbehörde
(z.B. Premierminister, MOIT) zustimmend der Solarenergieanlage als Teil des
Energieentwicklungsgesamtplans (wenn vorausgesetzt).
• Schritt 2: Der Investor erhält die Grundsatzgenehmigung von dem zuständigen
Personenkomitee (oder andere zuständige Stellen nach Maßgabe der Einzelheiten des
Projekts) zustimmend dem Solarenergieanlagen Projekt, Landnachfrage / Standort,
Umwelt, Bauplan, anderen Bedingungen des Projekts.
• Schritt 3: Anmeldung für die Ausgabe des Investitionszulassung Zertifikats und des
Unternehmenszulassung Zertifikats
• Schritt 4: Vorbereitung der Konstruktion / Betrieb der Solarenergieanlage (zum Beispiel,
Beschaffung von Landfläche, Grundstücksräumung, Vorbereitung, Landerforschung,
Ausführung von Umweltstudien)
• Schritt 5: Das Projektunternehmen erhält die notwendigen Genehmigungen (z.B.
Genehmigung für Elektrizitätserzeugung) und relevanten Vereinbarungen (z.B. PPA) für
ihren und den Energieanlagenbetrieb
• Schritt 6: Konstruktion der Solarenergieanlage und Betrieb
200
www.duanemorris.com
Empfehlungen für Investoren
• Öffentlich private Partnerschaften (z.B. – BOT) sollten die erste Wahl sein.
• Mit gebotener Sorgfalt der Verhandlungen des PPA und Stromnetzverbindung
Vereinbarung mit EVN
• Veräußerung von Elektrizität in Gebieten außerhalb des Stromnetzes kann eine gute Wahl
sein
• Vernünftige Finanzierungsstruktur, gutes Geschäftsmodell und umfangreiche
Rechtsberatung sind Schlüssel zum Erfolg.
• Präzise Prognose in welche Richtung sich der Markt bewegt, im Zusammenhang mit
Vietnams kritischer Energieunterversorgung, sollte berücksichtigt werden.
• Mehr Druck auf die Regierung um angemessen die Schlüsselprobleme anzugehen auf
Zollerhöhung, Entmonopolisierung des Energiemarktes und Staatsgarantie.
• Vietnams Markt benötigt dringend Finanzierung und EPC Leistungsfähigkeit. Es gibt
Räume für kostengünstige und hochqualitative EPC Auftragnehmer und einfallsreiche
Kreditgeber.
• In vielen Fällen kann man „sich erproben“ mit einem kleinen Energieanlagen Projekt.
211
www.duanemorris.com
DUANE MORRIS VIETNAM LLC
Vielen Dank!
HANOI OFFICE HO CHI MINH CITY OFFICE
Pacific Place, Unit V1307/08, 13th
Floor, Suite 1503/04, Saigon Tower
83B Ly Thuong Kiet, Hoan Kiem District 29 Le Duan Street, District 1
Hanoi, Vietnam Ho Chi Minh City, Vietnam
Tel.: +84 4 39462200 Tel.: +84 8 3824 0240
Fax: +84 4 3946 1311 Fax: +84 8 3824 0241
Contact email:
omassmann@duanemorris.com
222
www.duanemorris.com
References (1)
233
www.duanemorris.com
References (2)
244
www.duanemorris.com
References (3)
255
www.duanemorris.com
References (4)
266

Weitere ähnliche Inhalte

Was ist angesagt?

Nachhaltigkeit bei Wohngebäuden: ökologisch - ökonomisch - sozial
Nachhaltigkeit bei Wohngebäuden: ökologisch - ökonomisch - sozialNachhaltigkeit bei Wohngebäuden: ökologisch - ökonomisch - sozial
Nachhaltigkeit bei Wohngebäuden: ökologisch - ökonomisch - sozialMieterbund Bodensee
 
CO2-neutrale Gebäude bis spätestens 2045 – eine ambitionierte und sozialvertr...
CO2-neutrale Gebäude bis spätestens 2045 – eine ambitionierte und sozialvertr...CO2-neutrale Gebäude bis spätestens 2045 – eine ambitionierte und sozialvertr...
CO2-neutrale Gebäude bis spätestens 2045 – eine ambitionierte und sozialvertr...Mieterbund Bodensee
 
Vietnam _ Bahnbrechender Einspeisungstarif für Abfallenergieanlagen in Vietnam
Vietnam _ Bahnbrechender Einspeisungstarif für Abfallenergieanlagen in VietnamVietnam _ Bahnbrechender Einspeisungstarif für Abfallenergieanlagen in Vietnam
Vietnam _ Bahnbrechender Einspeisungstarif für Abfallenergieanlagen in VietnamDr. Oliver Massmann
 
Wohnungsbestand klimagerecht? Wer zahlt und wie weit sind wir?
Wohnungsbestand klimagerecht? Wer zahlt und wie weit sind wir?Wohnungsbestand klimagerecht? Wer zahlt und wie weit sind wir?
Wohnungsbestand klimagerecht? Wer zahlt und wie weit sind wir?Mieterbund Bodensee
 
Anwalt in Vietnam Dr. Oliver Massmann - Reform im Energiesektor Wettbewerbsm...
Anwalt in Vietnam Dr. Oliver Massmann - Reform im Energiesektor  Wettbewerbsm...Anwalt in Vietnam Dr. Oliver Massmann - Reform im Energiesektor  Wettbewerbsm...
Anwalt in Vietnam Dr. Oliver Massmann - Reform im Energiesektor Wettbewerbsm...Dr. Oliver Massmann
 
Energiestrategie 2050 - Erstes Massnahmenpaket und Ausblick
Energiestrategie 2050 - Erstes Massnahmenpaket und AusblickEnergiestrategie 2050 - Erstes Massnahmenpaket und Ausblick
Energiestrategie 2050 - Erstes Massnahmenpaket und AusblickHochschule für Technik FHNW
 
Vortrag kunze win wind 2018 12-10
Vortrag kunze win wind 2018 12-10Vortrag kunze win wind 2018 12-10
Vortrag kunze win wind 2018 12-10WinWind Project
 

Was ist angesagt? (7)

Nachhaltigkeit bei Wohngebäuden: ökologisch - ökonomisch - sozial
Nachhaltigkeit bei Wohngebäuden: ökologisch - ökonomisch - sozialNachhaltigkeit bei Wohngebäuden: ökologisch - ökonomisch - sozial
Nachhaltigkeit bei Wohngebäuden: ökologisch - ökonomisch - sozial
 
CO2-neutrale Gebäude bis spätestens 2045 – eine ambitionierte und sozialvertr...
CO2-neutrale Gebäude bis spätestens 2045 – eine ambitionierte und sozialvertr...CO2-neutrale Gebäude bis spätestens 2045 – eine ambitionierte und sozialvertr...
CO2-neutrale Gebäude bis spätestens 2045 – eine ambitionierte und sozialvertr...
 
Vietnam _ Bahnbrechender Einspeisungstarif für Abfallenergieanlagen in Vietnam
Vietnam _ Bahnbrechender Einspeisungstarif für Abfallenergieanlagen in VietnamVietnam _ Bahnbrechender Einspeisungstarif für Abfallenergieanlagen in Vietnam
Vietnam _ Bahnbrechender Einspeisungstarif für Abfallenergieanlagen in Vietnam
 
Wohnungsbestand klimagerecht? Wer zahlt und wie weit sind wir?
Wohnungsbestand klimagerecht? Wer zahlt und wie weit sind wir?Wohnungsbestand klimagerecht? Wer zahlt und wie weit sind wir?
Wohnungsbestand klimagerecht? Wer zahlt und wie weit sind wir?
 
Anwalt in Vietnam Dr. Oliver Massmann - Reform im Energiesektor Wettbewerbsm...
Anwalt in Vietnam Dr. Oliver Massmann - Reform im Energiesektor  Wettbewerbsm...Anwalt in Vietnam Dr. Oliver Massmann - Reform im Energiesektor  Wettbewerbsm...
Anwalt in Vietnam Dr. Oliver Massmann - Reform im Energiesektor Wettbewerbsm...
 
Energiestrategie 2050 - Erstes Massnahmenpaket und Ausblick
Energiestrategie 2050 - Erstes Massnahmenpaket und AusblickEnergiestrategie 2050 - Erstes Massnahmenpaket und Ausblick
Energiestrategie 2050 - Erstes Massnahmenpaket und Ausblick
 
Vortrag kunze win wind 2018 12-10
Vortrag kunze win wind 2018 12-10Vortrag kunze win wind 2018 12-10
Vortrag kunze win wind 2018 12-10
 

Ähnlich wie Rechtsanwalt in Vietnam Dr. Oliver Massmann Investieren in Solarenergie - Wie macht man es richtig !

Anwalt in Vietnam Dr. Oliver Massmann INVESTIEREN IN SOLARENERGIE IN VIETNAM ...
Anwalt in Vietnam Dr. Oliver Massmann INVESTIEREN IN SOLARENERGIE IN VIETNAM ...Anwalt in Vietnam Dr. Oliver Massmann INVESTIEREN IN SOLARENERGIE IN VIETNAM ...
Anwalt in Vietnam Dr. Oliver Massmann INVESTIEREN IN SOLARENERGIE IN VIETNAM ...Dr. Oliver Massmann
 
Vietnam Windenergie Investitionsleitfaden
Vietnam Windenergie InvestitionsleitfadenVietnam Windenergie Investitionsleitfaden
Vietnam Windenergie InvestitionsleitfadenDr. Oliver Massmann
 
Anwalt in Vietnam Dr. Oliver Massmann - STROMENERGIE - NON-RECOURSE-FINANZIER...
Anwalt in Vietnam Dr. Oliver Massmann - STROMENERGIE - NON-RECOURSE-FINANZIER...Anwalt in Vietnam Dr. Oliver Massmann - STROMENERGIE - NON-RECOURSE-FINANZIER...
Anwalt in Vietnam Dr. Oliver Massmann - STROMENERGIE - NON-RECOURSE-FINANZIER...Dr. Oliver Massmann
 
ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...
ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...
ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...Dr. Oliver Massmann
 
Das Erneuerbare Energien Gesetz (EEG): Entwicklung und Wissenswertes zur EEG-...
Das Erneuerbare Energien Gesetz (EEG): Entwicklung und Wissenswertes zur EEG-...Das Erneuerbare Energien Gesetz (EEG): Entwicklung und Wissenswertes zur EEG-...
Das Erneuerbare Energien Gesetz (EEG): Entwicklung und Wissenswertes zur EEG-...greenXmoney
 
2016.11.15 energie der alpen italien workshop
2016.11.15 energie der alpen italien workshop2016.11.15 energie der alpen italien workshop
2016.11.15 energie der alpen italien workshopSvenja Bartels
 
Rechtsanwalt in Vietnam Dr. Oliver Massmann - Aktionsplan für Energie - Mit A...
Rechtsanwalt in Vietnam Dr. Oliver Massmann - Aktionsplan für Energie - Mit A...Rechtsanwalt in Vietnam Dr. Oliver Massmann - Aktionsplan für Energie - Mit A...
Rechtsanwalt in Vietnam Dr. Oliver Massmann - Aktionsplan für Energie - Mit A...Dr. Oliver Massmann
 
Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...
Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...
Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...Dr. Oliver Massmann
 
Bm wi eckpunkte-papier-eeg
Bm wi eckpunkte-papier-eegBm wi eckpunkte-papier-eeg
Bm wi eckpunkte-papier-eegmetropolsolar
 
Vietnam – Wasser Projekt – Gesetze für öffentlich private Partnerschaften (ÖP...
Vietnam – Wasser Projekt – Gesetze für öffentlich private Partnerschaften (ÖP...Vietnam – Wasser Projekt – Gesetze für öffentlich private Partnerschaften (ÖP...
Vietnam – Wasser Projekt – Gesetze für öffentlich private Partnerschaften (ÖP...Dr. Oliver Massmann
 
2018 11-28 - csu ake - energiesammelgesetz - public
2018 11-28 - csu ake - energiesammelgesetz - public2018 11-28 - csu ake - energiesammelgesetz - public
2018 11-28 - csu ake - energiesammelgesetz - publicCSU
 
Der Gebäudebestand als Erfolgsfaktor der Energiestrategie 2050
Der Gebäudebestand als Erfolgsfaktor der Energiestrategie 2050Der Gebäudebestand als Erfolgsfaktor der Energiestrategie 2050
Der Gebäudebestand als Erfolgsfaktor der Energiestrategie 2050Vorname Nachname
 
Bwe position eeg-novelle_20101025
Bwe position eeg-novelle_20101025Bwe position eeg-novelle_20101025
Bwe position eeg-novelle_20101025metropolsolar
 
Die energetische Optimierung des Gebäudebestandes als Erfolgsfaktor | von Dan...
Die energetische Optimierung des Gebäudebestandes als Erfolgsfaktor | von Dan...Die energetische Optimierung des Gebäudebestandes als Erfolgsfaktor | von Dan...
Die energetische Optimierung des Gebäudebestandes als Erfolgsfaktor | von Dan...Vorname Nachname
 
Zipf 20191025 vortrag win wind
Zipf 20191025 vortrag win windZipf 20191025 vortrag win wind
Zipf 20191025 vortrag win windWinWind Project
 
Auf gutem kurs_-_ein_jahr_gruen-rote_energiepolitik_fuer_bw
Auf gutem kurs_-_ein_jahr_gruen-rote_energiepolitik_fuer_bwAuf gutem kurs_-_ein_jahr_gruen-rote_energiepolitik_fuer_bw
Auf gutem kurs_-_ein_jahr_gruen-rote_energiepolitik_fuer_bwmetropolsolar
 
Infoblatt_Pituaçu
Infoblatt_PituaçuInfoblatt_Pituaçu
Infoblatt_PituaçuPeter Krenz
 

Ähnlich wie Rechtsanwalt in Vietnam Dr. Oliver Massmann Investieren in Solarenergie - Wie macht man es richtig ! (20)

Anwalt in Vietnam Dr. Oliver Massmann INVESTIEREN IN SOLARENERGIE IN VIETNAM ...
Anwalt in Vietnam Dr. Oliver Massmann INVESTIEREN IN SOLARENERGIE IN VIETNAM ...Anwalt in Vietnam Dr. Oliver Massmann INVESTIEREN IN SOLARENERGIE IN VIETNAM ...
Anwalt in Vietnam Dr. Oliver Massmann INVESTIEREN IN SOLARENERGIE IN VIETNAM ...
 
Vietnam Windenergie Investitionsleitfaden
Vietnam Windenergie InvestitionsleitfadenVietnam Windenergie Investitionsleitfaden
Vietnam Windenergie Investitionsleitfaden
 
Anwalt in Vietnam Dr. Oliver Massmann - STROMENERGIE - NON-RECOURSE-FINANZIER...
Anwalt in Vietnam Dr. Oliver Massmann - STROMENERGIE - NON-RECOURSE-FINANZIER...Anwalt in Vietnam Dr. Oliver Massmann - STROMENERGIE - NON-RECOURSE-FINANZIER...
Anwalt in Vietnam Dr. Oliver Massmann - STROMENERGIE - NON-RECOURSE-FINANZIER...
 
ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...
ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...
ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...
 
Das Erneuerbare Energien Gesetz (EEG): Entwicklung und Wissenswertes zur EEG-...
Das Erneuerbare Energien Gesetz (EEG): Entwicklung und Wissenswertes zur EEG-...Das Erneuerbare Energien Gesetz (EEG): Entwicklung und Wissenswertes zur EEG-...
Das Erneuerbare Energien Gesetz (EEG): Entwicklung und Wissenswertes zur EEG-...
 
2016.11.15 energie der alpen italien workshop
2016.11.15 energie der alpen italien workshop2016.11.15 energie der alpen italien workshop
2016.11.15 energie der alpen italien workshop
 
Rechtsanwalt in Vietnam Dr. Oliver Massmann - Aktionsplan für Energie - Mit A...
Rechtsanwalt in Vietnam Dr. Oliver Massmann - Aktionsplan für Energie - Mit A...Rechtsanwalt in Vietnam Dr. Oliver Massmann - Aktionsplan für Energie - Mit A...
Rechtsanwalt in Vietnam Dr. Oliver Massmann - Aktionsplan für Energie - Mit A...
 
Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...
Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...
Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...
 
Bm wi eckpunkte-papier-eeg
Bm wi eckpunkte-papier-eegBm wi eckpunkte-papier-eeg
Bm wi eckpunkte-papier-eeg
 
Vietnam – Wasser Projekt – Gesetze für öffentlich private Partnerschaften (ÖP...
Vietnam – Wasser Projekt – Gesetze für öffentlich private Partnerschaften (ÖP...Vietnam – Wasser Projekt – Gesetze für öffentlich private Partnerschaften (ÖP...
Vietnam – Wasser Projekt – Gesetze für öffentlich private Partnerschaften (ÖP...
 
2018 11-28 - csu ake - energiesammelgesetz - public
2018 11-28 - csu ake - energiesammelgesetz - public2018 11-28 - csu ake - energiesammelgesetz - public
2018 11-28 - csu ake - energiesammelgesetz - public
 
Vietnam _Energiewende
Vietnam _EnergiewendeVietnam _Energiewende
Vietnam _Energiewende
 
Der Gebäudebestand als Erfolgsfaktor der Energiestrategie 2050
Der Gebäudebestand als Erfolgsfaktor der Energiestrategie 2050Der Gebäudebestand als Erfolgsfaktor der Energiestrategie 2050
Der Gebäudebestand als Erfolgsfaktor der Energiestrategie 2050
 
Bwe position eeg-novelle_20101025
Bwe position eeg-novelle_20101025Bwe position eeg-novelle_20101025
Bwe position eeg-novelle_20101025
 
Vietnam Infrastruktur
Vietnam InfrastrukturVietnam Infrastruktur
Vietnam Infrastruktur
 
Die energetische Optimierung des Gebäudebestandes als Erfolgsfaktor | von Dan...
Die energetische Optimierung des Gebäudebestandes als Erfolgsfaktor | von Dan...Die energetische Optimierung des Gebäudebestandes als Erfolgsfaktor | von Dan...
Die energetische Optimierung des Gebäudebestandes als Erfolgsfaktor | von Dan...
 
Zipf 20191025 vortrag win wind
Zipf 20191025 vortrag win windZipf 20191025 vortrag win wind
Zipf 20191025 vortrag win wind
 
Auf gutem kurs_-_ein_jahr_gruen-rote_energiepolitik_fuer_bw
Auf gutem kurs_-_ein_jahr_gruen-rote_energiepolitik_fuer_bwAuf gutem kurs_-_ein_jahr_gruen-rote_energiepolitik_fuer_bw
Auf gutem kurs_-_ein_jahr_gruen-rote_energiepolitik_fuer_bw
 
Infoblatt_Pituaçu
Infoblatt_PituaçuInfoblatt_Pituaçu
Infoblatt_Pituaçu
 
Energie-Agenda 2015
Energie-Agenda 2015Energie-Agenda 2015
Energie-Agenda 2015
 

Mehr von Dr. Oliver Massmann

Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Dr. Oliver Massmann
 
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTSVIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTSDr. Oliver Massmann
 
Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...
Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...
Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...Dr. Oliver Massmann
 
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...Dr. Oliver Massmann
 
OMassmann - Investment into the grid and transmission system in Vietnam (2024...
OMassmann - Investment into the grid and transmission system in Vietnam (2024...OMassmann - Investment into the grid and transmission system in Vietnam (2024...
OMassmann - Investment into the grid and transmission system in Vietnam (2024...Dr. Oliver Massmann
 
Vietnam's Plan for Implementation of PDP8 – Key Highlights
Vietnam's Plan for Implementation of PDP8 – Key HighlightsVietnam's Plan for Implementation of PDP8 – Key Highlights
Vietnam's Plan for Implementation of PDP8 – Key HighlightsDr. Oliver Massmann
 
VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:
VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:
VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:Dr. Oliver Massmann
 
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Dr. Oliver Massmann
 
VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...
VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...
VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...Dr. Oliver Massmann
 
Vietnam's National Energy Development Strategy – Key Highlights
Vietnam's National Energy Development Strategy – Key HighlightsVietnam's National Energy Development Strategy – Key Highlights
Vietnam's National Energy Development Strategy – Key HighlightsDr. Oliver Massmann
 
Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...
Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...
Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...Dr. Oliver Massmann
 
ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...
ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...
ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...Dr. Oliver Massmann
 
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Dr. Oliver Massmann
 
Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...
Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...
Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...Dr. Oliver Massmann
 
POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...
POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...
POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...Dr. Oliver Massmann
 
KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...
KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...
KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...Dr. Oliver Massmann
 
Lawyer in Vietnam Dr. Oliver Massmann - Doing Business and Getting Deals Done...
Lawyer in Vietnam Dr. Oliver Massmann - Doing Business and Getting Deals Done...Lawyer in Vietnam Dr. Oliver Massmann - Doing Business and Getting Deals Done...
Lawyer in Vietnam Dr. Oliver Massmann - Doing Business and Getting Deals Done...Dr. Oliver Massmann
 
Anwalt in Vietnam Dr. Oliver Massmann im Interview mit Asia Business Law Jour...
Anwalt in Vietnam Dr. Oliver Massmann im Interview mit Asia Business Law Jour...Anwalt in Vietnam Dr. Oliver Massmann im Interview mit Asia Business Law Jour...
Anwalt in Vietnam Dr. Oliver Massmann im Interview mit Asia Business Law Jour...Dr. Oliver Massmann
 
Lawyer in Vietnam Dr Oliver Massmann - Vietnam and the World
Lawyer in Vietnam Dr Oliver Massmann - Vietnam and the WorldLawyer in Vietnam Dr Oliver Massmann - Vietnam and the World
Lawyer in Vietnam Dr Oliver Massmann - Vietnam and the WorldDr. Oliver Massmann
 
VIETNAM - INSURANCE - Regulatory Update Asia Insurance Review interviewing Dr...
VIETNAM - INSURANCE - Regulatory Update Asia Insurance Review interviewing Dr...VIETNAM - INSURANCE - Regulatory Update Asia Insurance Review interviewing Dr...
VIETNAM - INSURANCE - Regulatory Update Asia Insurance Review interviewing Dr...Dr. Oliver Massmann
 

Mehr von Dr. Oliver Massmann (20)

Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
 
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTSVIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
 
Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...
Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...
Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...
 
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
 
OMassmann - Investment into the grid and transmission system in Vietnam (2024...
OMassmann - Investment into the grid and transmission system in Vietnam (2024...OMassmann - Investment into the grid and transmission system in Vietnam (2024...
OMassmann - Investment into the grid and transmission system in Vietnam (2024...
 
Vietnam's Plan for Implementation of PDP8 – Key Highlights
Vietnam's Plan for Implementation of PDP8 – Key HighlightsVietnam's Plan for Implementation of PDP8 – Key Highlights
Vietnam's Plan for Implementation of PDP8 – Key Highlights
 
VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:
VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:
VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:
 
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
 
VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...
VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...
VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...
 
Vietnam's National Energy Development Strategy – Key Highlights
Vietnam's National Energy Development Strategy – Key HighlightsVietnam's National Energy Development Strategy – Key Highlights
Vietnam's National Energy Development Strategy – Key Highlights
 
Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...
Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...
Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...
 
ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...
ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...
ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...
 
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
 
Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...
Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...
Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...
 
POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...
POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...
POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...
 
KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...
KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...
KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...
 
Lawyer in Vietnam Dr. Oliver Massmann - Doing Business and Getting Deals Done...
Lawyer in Vietnam Dr. Oliver Massmann - Doing Business and Getting Deals Done...Lawyer in Vietnam Dr. Oliver Massmann - Doing Business and Getting Deals Done...
Lawyer in Vietnam Dr. Oliver Massmann - Doing Business and Getting Deals Done...
 
Anwalt in Vietnam Dr. Oliver Massmann im Interview mit Asia Business Law Jour...
Anwalt in Vietnam Dr. Oliver Massmann im Interview mit Asia Business Law Jour...Anwalt in Vietnam Dr. Oliver Massmann im Interview mit Asia Business Law Jour...
Anwalt in Vietnam Dr. Oliver Massmann im Interview mit Asia Business Law Jour...
 
Lawyer in Vietnam Dr Oliver Massmann - Vietnam and the World
Lawyer in Vietnam Dr Oliver Massmann - Vietnam and the WorldLawyer in Vietnam Dr Oliver Massmann - Vietnam and the World
Lawyer in Vietnam Dr Oliver Massmann - Vietnam and the World
 
VIETNAM - INSURANCE - Regulatory Update Asia Insurance Review interviewing Dr...
VIETNAM - INSURANCE - Regulatory Update Asia Insurance Review interviewing Dr...VIETNAM - INSURANCE - Regulatory Update Asia Insurance Review interviewing Dr...
VIETNAM - INSURANCE - Regulatory Update Asia Insurance Review interviewing Dr...
 

Rechtsanwalt in Vietnam Dr. Oliver Massmann Investieren in Solarenergie - Wie macht man es richtig !

  • 1. www.duanemorris.com ©2010 Duane Morris LLP. All Rights Reserved. Duane Morris is a registered service mark of Duane Morris LLP. Duane Morris – Firm and Affiliate Offices | New York | London | Singapore | Los Angeles | Chicago | Houston | Hanoi | Philadelphia | San Diego | San Francisco | Baltimore | Boston | Washington, D.C. Las Vegas | Atlanta | Miami | Pittsburgh | Newark | Boca Raton | Wilmington | Cherry Hill | Princeton | Lake Tahoe | Ho Chi Minh City | Duane Morris LLP – A Delaware limited liability partnership OLIVER MASSMANN – GBA Board Member Partner, General Director DUANE MORRIS VIETNAM LLC In Solarenergie in Vietnam investieren Wie macht man es richtig? 1
  • 2. www.duanemorris.com Tagesordnung •Hintergrund zur (Solar-) Energie Branche in Vietnam •Regulatorische Rahmenbedingungen von erneuerbarer (Solar-) Energie •Investitionsrichtlinien für Investoren •Empfehlungen 2
  • 3. www.duanemorris.com Hintergrund zum Energiebereich • Nachfrage an Elektrizität soll laut Erwartungen um bis zu 11.4 Prozent im Zeitraum 2016-2020 zunehmen und um das 7-fache bis zu 800 Milliarde Kwh bis 2030 • Laut Prognosen wird der Elektrizitätsverbrauch von 85,932 Gigawattstunde (GWh) in 2010 zu 251,763 GWh bis 2020 zunehmen 3
  • 4. www.duanemorris.com Potenzial der Solarenergie-Branche in Vietnam • Gesamtzahl der Sonnenscheinstunden bis zu 1400 – 3000 Stunden/Jahr • Potenzial: 4-6 kWh/m2 • Aktuelle Nutzung: 5 MW • Solarenergie kann zum Wasser sieden, Energieerzeugung und zu anderen Zwecken wie z.B. Trocknung, Kochen etc. verwendet werden 4
  • 5. www.duanemorris.com Regulatorische Rahmenbedingungen der Solarenergie • Elektrizitätsgesetz 2004 und 2012 • Der überarbeitete Stromentwicklungsplan 2011-2020 (überarbeitet PDP VII) genehmigt durch Premierminister in dem Beschluss 428/QD-TTg vom 18 März 2016 • Beschluss 2068/QD-TTg vom 25 November 2015 auf Entwicklungsstrategie und Vision der RE bis 2050. • Beschluss 11/2017/QD-TTg vom 11 April 2017 von dem PM zum Beistandsmechanismus für die Entwicklung von Solarenergie Projekten in Vietnam • Entwurf des Anforderungsrundschreiben zu Entwicklungsschutz und Muster PPA für Solarenergie-Projekte vom 29 April 2017 durch die MOIT5
  • 6. www.duanemorris.com Neugefasster Energie Entwicklungsplan VII durch die Entwicklung der Elektrizität in Vietnam • Neugefasster Entwicklungsplan VII fokussiert auf Energiesicherheit, Energieeffizienz, Entwicklung der erneuerbaren Energien und der Energie Markt Liberalisierung • Ziele: • Die Gesamtleistung von importierter und produzierter Elektrizität zu 235-245 Milliarden kWh bis zu 2020; 352 – 379 Milliarden kWh bis zu 2025 und 506 – 559 Milliarden kWh bis zu 2030, zu steigern • Die Entwicklung der Erzeugung von erneuerbare Energie zu priorisieren, sodass das Verhältnis der Energieerzeugung von erneuerbarer Energie von momentan 3.5% der insgesamten Elektrizitätsproduktion zu 7% in 2020 und 10% in 2030 zunimmt • Das ländliche Elektrifizierungsprogramm zu fördern damit die meisten ländlichen Haushalte Anschluss zur Elektrizität bis 2020 haben • Flexible Funktionsweise des Stromnetzes zu bauen, hohe Automatisierung der Übertragung zum Verteilungsprozess, Entwicklung des Umspannwerks ohne Anforderungen des durchführenden Personals. 6
  • 7. www.duanemorris.com Neugefasster Energie Entwicklungsplan VII • Strategien: • Höhere Qualität der Elektrizitätsversorgung und ein akzeptablerer Elektrizitätspreis • Erweiterung von inländischen Quellen für Energieerzeugung • Entwickeln von neuen erneuerbaren Energiequellen und Technologien auf den neusten Stand bringen, die in bestehenden Anlagen verwendet wird • Verteilung der Investitionsmittel um den Mangel an finanziellen und technischen Mitteln zu überwinden und außerdem die wirtschaftliche Effizienz zu verbessern • Investitionskapitalbedarf: • Circa 40 Milliarde US Dollar bis zu 2020: Zweidrittel für Energieerzeugungsentwicklung und ein Drittel für Energienetzentwicklung • Ungefähr 108 Milliarde US Dollar für den Zeitraum von 2021 bis 2030: 74% für Energieerzeugung und 26% für Energienetzentwicklung 7
  • 8. www.duanemorris.com Neugefasster Energieentwicklungsplan VII • Vorbringen um das Monopol der Übertragung zu erhalten • Priorisierung der Entwicklung für erneuerbare Energie • Zieleinschätzung der erneuerbaren Energie bei 7 % der Gesamtenergieleistung bis 2020 und mehr als 10 % bis 2030. • Zunahme der Solarenergieproduktion zu 850 MW bis 2020, 4,000 MW bis 2025 und 12,000 MW in 2030. 8
  • 9. www.duanemorris.com Vietnams Elektroenergiemix • Vietnams Strategie betont das Erfordernis die Energiekombination des Landes aufzuteilen während die Nutzung der lokalen Energiereserven maximiert wird • Aktuell entwickelt Vietnam einen Energiemix Bereich mit Kohlekraft als Hauptsäule 9
  • 10. www.duanemorris.com Solarentscheidung • FIT: • Stromnetzprojekte: 9.35 US Cents/kWh. Der Preis in VND wird angepasst übereinstimmend zur Schwankung des VND/USD Wechselkurses. Jedoch beinhaltet der Entwurf PPA keinen Bezug zu den Lebenserhaltungskostenindex, Wechselkurs oder Inflationsrisiken. • Kein FIT für Dachprojekte außerhalb des Stromnetzes • Nettomessung: anwendbar für Dachprojekte. Betrag der Überlieferung wird im Folgemonat gutgeschrieben. Zum Ende des Jahres oder Außerkrafttreten des PPA, wird der überschrittene Betrag an EVN zu 9.35 US Cents / kWh verkauft. 100
  • 11. www.duanemorris.com Entwurf PPA • Nicht verhandelbare PPA und verbindliche Anwendung für Netzverbundene Solarprojekte • EVN hat die Verpflichtung die gesamte Elektrizität, erzeugt durch Solarenergie Projekte, zu kaufen. Jedoch könnte EVN, nach dem Entwurf PPA, den Ankauf von Elektrizität unter bestimmten Umständen die jenseits vernünftiger Kontrolle durch den Verkäufer liegen, beenden, ohne irgendeine Entschädigung oder Bezahlung an den Verkäufer / Projektentwickler. • Der Käufer muss den Verkäufer nur für die tatsächlich erhaltene Elektrizität bezahlen. Der Entwurf PPA beinhaltet keine Regelung in der es dem Käufer nicht möglich ist die produzierte Elektrizität anzunehmen. • Konfliktlösung: Durch Prozess vor Vietnamesischer Gerichte oder Mediation / Lösung vor autorisierten Energiestaatsstellen von Vietnam. Kein internationales Schiedsgericht ist genannt! 111
  • 12. www.duanemorris.com Bestätigung der Regierung bezüglich des PPA • In den kürzlich abgeschlossenen Wind PPAs, subventionierte die Regierung EVN 1 US Cent / kWh in Bezug auf die gesamte Energieleistung, die an EVN verkauft wurde • Diese Subventionierung bestand nicht mehr in der letzten Solarentscheidung • Entwurf Solar PPA: Keine Regelung irgendeiner Art von Regierungsgarantie um die Glaubwürdigkeit von EVN zu verbessern • Kein Hinweis um die Solar PPA profitabel zu machen.122
  • 13. www.duanemorris.com Die EVN • PPA ist verpflichtet einem bestimmten Muster zu folgen, das nicht profitabel ist. • Es ist unklar, ob das PPA Muster eine „nimm oder bezahl“ Vereinbarung ist. • Keine Abänderung des PPA Musters ist möglich, außer die Ergänzung zur Klarstellung der Rechte und Pflichten der Parteien, vorausgesetzt dass sie keine Grundinhalte des PPA Musters verändert 133
  • 14. www.duanemorris.com144 Ich bin nur EVN (Mensch)Ich bin nur EVN (Mensch) Beschuldigte nicht mich dafür!
  • 16. www.duanemorris.com Marktzugang und Formen der Investition • Keine ausländischen Eigentumsbeschränkungen • Investierungsarten: • Ein Unternehmen mit ausschließlich ausländischer Beteiligung • Ein Gemeinschaftsunternehmen zwischen ausländischen- und inländischen Investoren • Investition entsprechend der BOT Gesetzeslage • Durch den Kauf von Anteilen in entweder eine EVN Tochtergesellschaft oder durch Ausgleich oder einen privaten IPP vermögenswerten Energieanteil. 166
  • 17. www.duanemorris.com BOT – Beste Investierungsart • Verordnung der Regierung Nr. 15/2015/ND-CP auf öffentlich- privaten Partnerschaft: Projekte profitabler machen • Einfacher vorteilhaftere Elektrizitätsraten auszuhandeln. • Einfacher mehr Staatsgarantien zu erhalten, speziell in Bezug auf EVN´s Verpflichtung die gesamte Elektrizität des Projekts zu erwerben. • Mehr steuerliche und finanzielle Anreize. • Vorangehende umfangreiche BOT Energieprojekte in Vietnam: • Phu My, Vung Ang, Mong Duong 2 177
  • 18. www.duanemorris.com Investierungsanreize • Nach Maßgabe der Entscheidung des örtlichen Personenkomitee, wo das Projekt gelegen ist • Land: Befreiung von Grundstücksvermietung innerhalb von 3 Jahren von dem Betriebsdatum des Projects an, etc. • CIT 10 % • 15 Jahre für neue Unternehmen die in Energieanlagenprojekte investieren • Steuerliche Befreiungen innerhalb von 4 Jahren und Steuerermäßigungen von 50% in den nächsten 9 Jahren. • Befreiung des Einfuhrzolls • Auf Güter die importiert wurden um Anlagegegenstände des Projekts zu schaffen; Komponenten, Materialien und halbfertige Produkte, die nicht in der Heimat verfügbar sind für den Betrieb des Projekts. 188
  • 19. www.duanemorris.com Projektplanung • Investoren müssen vorher die EVN Vereinbarung erhalten bezogen auf den Energiekauf vor dem Zulassungsverfahren. • Verpflichtung der Banken oder Kreditinstitute das Projekt zu finanzieren, müssen vorliegen vor der Ausgabe des Zertifikats für Investitionszulassung. • Grundsätzlich Genehmigung des örtlichen Personenkomitee vorausgesetzt, bevor die Ausgabe des Zertifikats für Investitionszulassung abhängig von der Projektgröße erfolgt • Eine Solarenergieanlage muss eine Genehmigung zur Energieerzeugung von den zuständigen staatlichen Behörden erhalten, um Energieerzeugungsbetrieb in Vietnam durchzuführen • Laufzeit der Genehmigung: Maximal 20 Jahre für große Energieanlagen mit bestimmter wichtiger Bedeutung an der Wirtschaft, Gesellschaft, nationale Verteidigung und Sicherheit gemäß der Liste anerkannt durch den Premierminister; und 10 Jahre für andere Energieanlagen Projekte. • Die Genehmigung kann nicht erneuert werden, aber der Investor kann eine neue beantragen innerhalb von 60 Tagen vor dem Ablaufdatum der aktuellen Genehmigung. 199
  • 20. www.duanemorris.com Projektzulassung • Schritt 1: Der Investor erhält die Genehmigung von der zuständigen Landesbehörde (z.B. Premierminister, MOIT) zustimmend der Solarenergieanlage als Teil des Energieentwicklungsgesamtplans (wenn vorausgesetzt). • Schritt 2: Der Investor erhält die Grundsatzgenehmigung von dem zuständigen Personenkomitee (oder andere zuständige Stellen nach Maßgabe der Einzelheiten des Projekts) zustimmend dem Solarenergieanlagen Projekt, Landnachfrage / Standort, Umwelt, Bauplan, anderen Bedingungen des Projekts. • Schritt 3: Anmeldung für die Ausgabe des Investitionszulassung Zertifikats und des Unternehmenszulassung Zertifikats • Schritt 4: Vorbereitung der Konstruktion / Betrieb der Solarenergieanlage (zum Beispiel, Beschaffung von Landfläche, Grundstücksräumung, Vorbereitung, Landerforschung, Ausführung von Umweltstudien) • Schritt 5: Das Projektunternehmen erhält die notwendigen Genehmigungen (z.B. Genehmigung für Elektrizitätserzeugung) und relevanten Vereinbarungen (z.B. PPA) für ihren und den Energieanlagenbetrieb • Schritt 6: Konstruktion der Solarenergieanlage und Betrieb 200
  • 21. www.duanemorris.com Empfehlungen für Investoren • Öffentlich private Partnerschaften (z.B. – BOT) sollten die erste Wahl sein. • Mit gebotener Sorgfalt der Verhandlungen des PPA und Stromnetzverbindung Vereinbarung mit EVN • Veräußerung von Elektrizität in Gebieten außerhalb des Stromnetzes kann eine gute Wahl sein • Vernünftige Finanzierungsstruktur, gutes Geschäftsmodell und umfangreiche Rechtsberatung sind Schlüssel zum Erfolg. • Präzise Prognose in welche Richtung sich der Markt bewegt, im Zusammenhang mit Vietnams kritischer Energieunterversorgung, sollte berücksichtigt werden. • Mehr Druck auf die Regierung um angemessen die Schlüsselprobleme anzugehen auf Zollerhöhung, Entmonopolisierung des Energiemarktes und Staatsgarantie. • Vietnams Markt benötigt dringend Finanzierung und EPC Leistungsfähigkeit. Es gibt Räume für kostengünstige und hochqualitative EPC Auftragnehmer und einfallsreiche Kreditgeber. • In vielen Fällen kann man „sich erproben“ mit einem kleinen Energieanlagen Projekt. 211
  • 22. www.duanemorris.com DUANE MORRIS VIETNAM LLC Vielen Dank! HANOI OFFICE HO CHI MINH CITY OFFICE Pacific Place, Unit V1307/08, 13th Floor, Suite 1503/04, Saigon Tower 83B Ly Thuong Kiet, Hoan Kiem District 29 Le Duan Street, District 1 Hanoi, Vietnam Ho Chi Minh City, Vietnam Tel.: +84 4 39462200 Tel.: +84 8 3824 0240 Fax: +84 4 3946 1311 Fax: +84 8 3824 0241 Contact email: omassmann@duanemorris.com 222