SlideShare ist ein Scribd-Unternehmen logo
1 von 6
Downloaden Sie, um offline zu lesen
International Refereed Journal of Engineering and Science (IRJES)
ISSN (Online) 2319-183X, (Print) 2319-1821
Volume 6, Issue 6 (June 2017), PP.42-47
www.irjes.com 42 | Page
A Study in Construction Delays of Residential Structures
Ansari Hassaan1
, Fakih Hamza2
, Manjrekar Nikhil3
, Sunasra Sufyan4
1,2,3,4
(Civil Department, M.H. Saboo Siddik College of Engineering/Mumbai University , Maharashtra, India)
Abstract: Delays are one of the most common problem faced by the construction industry in India and around
the world. Construction delays can be caused by several reasons which can be related to owner, design, labor or
could be caused by some external factors such as bad weather. The delay in construction causes time overrun
which implies that the project requires additional time for completion than originally anticipated. Time overrun
in turn leads to cost overrun which causes huge monetary losses. This study focuses on finding out the most
common causes of construction delays in Indian context. The study was carried out in South and Central
Mumbai region. A questionnaire based survey was conducted based on 43 questions spread across 9 different
categories. The findings were evaluated with Relative Importance Index technique. The aim of the study was to
identify various causes of delays in construction and their importance.
Keywords: Time Overrun, Cost Overrun, Relative Importance Index, Construction Delays, Construction
Industry.
I. INTRODUCTION
The construction industry is the second largest industry in India after agriculture. It makes a significant
contribution to the national economy and provides employment to large number of people. However, the
construction industry is volatile and requires massive financial investment. Typically, the work offers low rate
of returns in relation to the amount of risk involved. In construction, delay could be defined as the time overrun
either beyond completion date specified in a contract, or beyond the date that the parties agreed upon for
delivery of a project. Delays occur in every construction project and the significant of these delays varies
considerably from project to project. Delays on the project are universal phenomenon.
1.1 Causes of Delay:
 Owner: Owner related delay caused due to reasons such as late payment and poor communications between
owner and other parties.
 Contractor: Delays caused due to difficulty in financing the project by contractor, improper site
management, conflicts between contractor and other parties, poor planning and scheduling of activities.
 Consultant: Delay in performing inspection, delay in reviewing and approving design documents.
 Design: Revisions in design documents, improper design and subsequent redesigning.
 Labor: Shortage of labors, unskilled workforce.
 Equipment: Shortage of equipment, low productivity and efficiency of equipment.
 Project: Contract duration is too short, legal disputes between various parties.
 Materials: Delay in material delivery, availability of materials, changes in type and specifications of
materials.
 External: Delay in obtaining permits from municipalities, accidents, bad weather, changes government rules
and regulations, social and cultural factors.
1.2 Effects of Delays:
 Time Overrun
 Cost Overrun
 Reduction in profits for contractor
 Losses for owner due to extended construction phase
 Distrust between owner and contractor
 Legal disputes between various parties
 Total Abandonment of project
A Study in Construction Delays of Residential Structures
www.irjes.com 43 | Page
II. RESEARCH METHODOLOGY
The study was based on a questionnaire survey which consisted the following steps.
 Preparation of Questionnaire
 Conducting Pilot studies
 Data Collection
 Data Processing and Analysis
2.1 Preparation of Questionnaire:
A questionnaire was designed based on object of the study i.e. finding out causes of construction delays
of residential projects, finding out opinions to minimize the construction delays. The questionnaire was prepared
in such a way as to get the opinions and understandings from experienced respondents.
The questionnaires are classified into 2 categories:
a) Respondent Background
In this section, we try to obtain the respondents information. This questionnaire includes:
 The respondent organization
 The position of the respondent in the company
 The experience of the respondent in the construction project
b) Causes of Construction Delays
This section of questionnaire evaluates the factors that contribute to the cause of construction delays. The factors
are divided into 9 groups namely:
 Owner
 Contractor
 Consultant
 Design
 Equipment
 Project
 Labours
 Materials
 External factors
The questionnaire is based on Likert’s scale of 5 ordinal measures from 1 to 5 according to the contribution
 (5) = Very High Effective
 (4) = High Effective
 (3) = Effective
 (2) = Low Effective
 (1) = Very Low Effective
The Questionnaire Consisted of 43 questions divided into 9 categories mentioned above.
Table 1
NO
.
Group Cause of delay Very
high
effective
High
effective
Effective Low
effective
Very low
effective
1 Owner Delay in progress payments by
owner
2 Owner Late in revising and approving
design documents by owner
3 Owner Poor communication and
coordination by owner and
other parties
4 Owner Unavailability of incentives for
contractor
5 Owner Suspension of work by owner
6 Contractor Difficulties in financing project
by contractor
7 Contractor Poor site management and
supervision by contractor
8 Contractor Poor communication and
coordination by contractor with
A Study in Construction Delays of Residential Structures
www.irjes.com 44 | Page
other parties.
9 Contractor Delay in site mobilization
10 Contractor Rework due to errors during
construction
11 Contractor Conflicts b/w contractor and
other parties
12 Contractor Ineffective planning and
scheduling of project by
contractor
13 Contractor Improper construction methods
implemented by contractor
14 Contractor Inadequate contractor’s work
15 Consultant Inadequate experience of
consultant
16 Consultant Delay in performing inspection
and testing by consultant
17 Consultant Delay in approving major
changes in the scope of work by
consultant
18 Consultant Late in reviewing and
approving design documents by
consultant
19 Design Revisions in design documents
20 Design Delays in producing design
documents
21 Design Misunderstanding of owner’s
requirements by architect
22 Labor Shortage of labors
23 Labor Unskilled workforce
24 Equipment Shortage of equipment
25 Equipment Low level of equipment-
operator’s skill
26 Equipment Low productivity and efficiency
of equipment
27 Project Ineffective delay penalties
28 Project Original planned contract
duration is unrealistic
29 Project Disputes between various
parties
30 Materials Changes in material types and
specifications during
construction
31 Materials Delay in material delivery
32 Materials Housekeeping of materials
33 Materials Delay in
manufacturing/processing
special building
materials
34 Materials Late in selection of finishing
materials due to
availability of many types in
market
35 External Delay in obtaining permissions
from municipality
36 External Rain effect on construction
activities
37 External Effect of social and cultural
factors
38 External Traffic control and restriction at
job site (Job layout)
39 External Accident during construction
40 External Differing site (ground)
conditions
41 External Changes in government
A Study in Construction Delays of Residential Structures
www.irjes.com 45 | Page
regulations and laws
42 External Delay in providing services
from utilities (such as water,
electricity)
43 External Delay in performing final
inspection and certification by a
third party
2.2 Conducting Pilot studies:
The main goal of this was to eliminate misunderstanding the questions that were mentioned in the
questionnaire. Every respondent was asked about each and every question's meaning in order to ensure that
there was no confusions with the questions. Further they were asked on their opinions on the questions and
wordings of the question and their importance with respect to our study thereby eliminating questions which
held no significance. This also allowed us to simplify the questions as it would be very important when the
questionnaire would be mailed to respondents which we could not personally interview thus minimizing the
confusion and getting more accurate results.
2.3 Data Collection:
The Data Collection for our study was done in two ways:
a) Personal Interviews
b) Mailing Questionnaire
a) Personal Interviews
An appointment was taken with Project Managers, Consultants, Site Engineers & Owners (Developers). And the
questionnaire was presented in order to get our data.
b) Mailing Questionnaire
In the case of being unable to visit Respondents we mailed them soft copies of questionnaire which was filled up
by them and mailed back to us.
The table below gives us the details of the respondents such as positions held by them in the organization and no
of years of experience.
Table 2
SITE NO. POSTION HELD NO. OF YEARS OF
EXPERIENCE
SITE 1 SITE ENGINEER 2 YEARS
SITE 2 PROJECT MANAGER 11 YEARS
SITE 3 SENIOR ENGINEER 7 YEARS
SITE 4 ASSISTANT DIRECTOR 6 YEARS
SITE 5 SITE ENGINEER 2 YEARS
SITE 6 SENIOR ENGINEER 6 YEARS
SITE 7 SITE ENGINEER 6 YEARS
SITE 8 OWNER 10 YEARS
SITE 9 SITE ENGINEER 2 YEARS
SITE 10 QUANTITY SURVEYOR 2 YEARS
SITE 11 DESIGN ENGINEER 7 YEARS
SITE 12 PROJECT ENGINEER 8 YEARS
SITE 13 SITE ENGINEER 2 YEARS
SITE 14 SENIOR ENGINEER 7 YEARS
2.4 Data Processing and Analysis:
The study utilized method to analyze the respondent’s data to identify the critical attributes among the
categories owner, contractor, consultant, design, labor, equipment, project, materials and external. The analysis
and processing of the data was done using Relative Importance Index technique.
2.4.1 Relative Importance Index
Relative index has been widely used in construction research for measuring attributes with respect to surveyed
variables. Likert’s scaling was used for ranking questions that have an agreement levels. The respondents were
required to rate the importance of each factor on a 5-point Likert’s scale using:
(5) = Very High Effective
(4) = High Effective
A Study in Construction Delays of Residential Structures
www.irjes.com 46 | Page
(3) = Effective
(2) = Low Effective
(1) = Very Low Effective
Then the relative importance index was computed using the following formula:
Where, “W” is the weighting given to each factor by the respondent, ranging from 1 to 5, ( = number
of respondent for very low effective, = number of respondent for low effective, number of respondent
for effective, = number of respondent for high effective, = number of respondent for very high effective).
“A” is the highest weight (i.e. 5 in the study) and “N” is the total number of samples. The relative importance
index ranges from 0 to 1.
III. CONCLUSION
From the data collected by us during the questionnaire survey we found that:
 The most important cause of construction delay of residential structures occurs due to the owner related
causes. Out of all owner related causes, the respondents cited that the most important cause of delay was
due to late payment by owners. The least cause of delay in this category was due to incentives for
contractors.
 The second most important cause of delay was design related with misunderstanding of owner’s
requirement by design engineer as the most important in the category. The other two causes that is revision
in design documents and delays in producing design documents were equally important but were ranked
below in the second place within the category.
 Third ranked category was of external causes with delay in obtaining permits from municipality as the
highest rated cause and accidents during construction as the least important cause of delay.
 Coming in at number four was Labor category with shortage of labors as the most important cause and
unskilled workforce as the least important cause of delay.
 Number fifth category was Contractor with difficulty in financing project by contractor as the most
important reason and delay due to site mobilization was rated as the least cause of delay.
 Sixth and Seventh place was a tie between Consultant and Project category with late in reviewing and
approving design documents by consultant as the most important cause and delay in performing inspection
and testing by consultant as least important for Consultant category and in the Project category, legal
disputes between various parts as the most important cause and ineffective delay penalties as the least cause
of delay.
 Eight place goes to Equipment category with shortage of equipment as the most important cause. The other
causes in this category received equal ratings.
 The least important category according to respondents was Material category with delay due to
manufacturing of special materials as most important cause and changes in material types and specifications
during construction as least important cause.
Table 3
Category Relative Importance Index (Category Average)
Owner 0.677
Contractor 0.603
Consultant 0.571
Design 0.667
Labor 0.621
Equipment 0.566
Project 0.571
Materials 0.554
External 0.66
A Study in Construction Delays of Residential Structures
www.irjes.com 47 | Page
Fig. 1
ACKNOWLEDGEMENTS
We sincerely appreciate Dr. Shagufta Sayed for giving us an opportunity to work on this topic. We are grateful
for her support and guidance which has helped us to expand our horizon of thoughts and experience.
REFERENCES
[1]. Megha, Desai, and Bhatt Rajiv. "A methodology for ranking of causes of delay for residential
construction projects in Indian context." International Journal of Emerging Technology and Advanced
Engineering 3.3 (2013): 396-404.
[2]. Rathod, Aradhana, and S. Pimplikar. "Delays In Residential Building Construction." International
Journal of Innovative Research and Development|| ISSN 2278–0211 2.5 (2013).
[3]. Rao, Prakash B., and Culas Joseph Camron. "Causes of Delays in Construction Projects-A case
study." International Journal of Current Research 6.6 (2014): 7219-7222.
[4]. Thomas, Anu V., and J. Sudhakumar. "Factors influencing construction labour productivity: an Indian
case study." Journal of Construction in Developing Countries 19.1 (2014): 53.
[5]. Chaphalkar, Nitin Balkrishna, and K. C. Iyer. "Factors influencing decisions on delay claims in
construction contracts for Indian scenario." Construction Economics and Building 14.1 (2014): 32-44.
[6]. Mustapha, F. H., and S. Naoum. "Factors influencing the effectiveness of construction site
managers." International Journal of Project Management 16.1 (1998): 1-8.
[7]. Fellows, Richard F., and Anita MM Liu. Research methods for construction. John Wiley & Sons, 2015.

Weitere ähnliche Inhalte

Ähnlich wie A Study in Construction Delays of Residential Structures

Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsDr. Amarjeet Singh
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 
1616-5398-2-PB.pdf
1616-5398-2-PB.pdf1616-5398-2-PB.pdf
1616-5398-2-PB.pdfEyobMiteku
 
journalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfjournalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfKarthikeyanP288430
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...IJMER
 
GP2-presentation (1).pptx
GP2-presentation (1).pptxGP2-presentation (1).pptx
GP2-presentation (1).pptxSuman Jain
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET Journal
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Sankalp Swarnkar
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...IRJET Journal
 
Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...ijtsrd
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"Abhishek Shah
 
IRJET- Dispute Resolution Mechanism in Construction Project
IRJET-  	  Dispute Resolution Mechanism in Construction ProjectIRJET-  	  Dispute Resolution Mechanism in Construction Project
IRJET- Dispute Resolution Mechanism in Construction ProjectIRJET Journal
 
An Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in BahrainAn Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in BahrainIJRES Journal
 
causes and implication of delay in construction
causes and implication of delay in constructioncauses and implication of delay in construction
causes and implication of delay in constructionsudinak
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsRick Vogel
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET Journal
 

Ähnlich wie A Study in Construction Delays of Residential Structures (20)

B012140812
B012140812B012140812
B012140812
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
1616-5398-2-PB.pdf
1616-5398-2-PB.pdf1616-5398-2-PB.pdf
1616-5398-2-PB.pdf
 
journalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfjournalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdf
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
 
GP2-presentation (1).pptx
GP2-presentation (1).pptxGP2-presentation (1).pptx
GP2-presentation (1).pptx
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
 
Ijciet 10 01_088
Ijciet 10 01_088Ijciet 10 01_088
Ijciet 10 01_088
 
Time overruns
Time overrunsTime overruns
Time overruns
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...
 
Risk management
Risk managementRisk management
Risk management
 
Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
 
IRJET- Dispute Resolution Mechanism in Construction Project
IRJET-  	  Dispute Resolution Mechanism in Construction ProjectIRJET-  	  Dispute Resolution Mechanism in Construction Project
IRJET- Dispute Resolution Mechanism in Construction Project
 
An Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in BahrainAn Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in Bahrain
 
causes and implication of delay in construction
causes and implication of delay in constructioncauses and implication of delay in construction
causes and implication of delay in construction
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
 

Mehr von IRJESJOURNAL

Drying of agricultural products using forced convection indirect solar dryer
Drying of agricultural products using forced convection indirect solar dryerDrying of agricultural products using forced convection indirect solar dryer
Drying of agricultural products using forced convection indirect solar dryerIRJESJOURNAL
 
The Problems of Constructing Optimal Onboard Colored RGB Depicting UAV Systems
The Problems of Constructing Optimal Onboard Colored RGB Depicting UAV SystemsThe Problems of Constructing Optimal Onboard Colored RGB Depicting UAV Systems
The Problems of Constructing Optimal Onboard Colored RGB Depicting UAV SystemsIRJESJOURNAL
 
Flexible Design Processes to Reduce the Early Obsolescence of Buildings
Flexible Design Processes to Reduce the Early Obsolescence of BuildingsFlexible Design Processes to Reduce the Early Obsolescence of Buildings
Flexible Design Processes to Reduce the Early Obsolescence of BuildingsIRJESJOURNAL
 
Study on Performance Enhancement of Solar Ejector Cooling System
Study on Performance Enhancement of Solar Ejector Cooling SystemStudy on Performance Enhancement of Solar Ejector Cooling System
Study on Performance Enhancement of Solar Ejector Cooling SystemIRJESJOURNAL
 
Flight Safety Case Study: Adi Sucipto Airport Jogjakarta - Indonesia
Flight Safety Case Study: Adi Sucipto Airport Jogjakarta - IndonesiaFlight Safety Case Study: Adi Sucipto Airport Jogjakarta - Indonesia
Flight Safety Case Study: Adi Sucipto Airport Jogjakarta - IndonesiaIRJESJOURNAL
 
A Review of Severe Plastic Deformation
A Review of Severe Plastic DeformationA Review of Severe Plastic Deformation
A Review of Severe Plastic DeformationIRJESJOURNAL
 
Annealing Response of Aluminum Alloy AA6014 Processed By Severe Plastic Defor...
Annealing Response of Aluminum Alloy AA6014 Processed By Severe Plastic Defor...Annealing Response of Aluminum Alloy AA6014 Processed By Severe Plastic Defor...
Annealing Response of Aluminum Alloy AA6014 Processed By Severe Plastic Defor...IRJESJOURNAL
 
Evaluation of Thresholding Based Noncontact Respiration Rate Monitoring using...
Evaluation of Thresholding Based Noncontact Respiration Rate Monitoring using...Evaluation of Thresholding Based Noncontact Respiration Rate Monitoring using...
Evaluation of Thresholding Based Noncontact Respiration Rate Monitoring using...IRJESJOURNAL
 
Correlation of True Boiling Point of Crude Oil
Correlation of True Boiling Point of Crude OilCorrelation of True Boiling Point of Crude Oil
Correlation of True Boiling Point of Crude OilIRJESJOURNAL
 
Combined Geophysical And Geotechnical Techniques For Assessment Of Foundation...
Combined Geophysical And Geotechnical Techniques For Assessment Of Foundation...Combined Geophysical And Geotechnical Techniques For Assessment Of Foundation...
Combined Geophysical And Geotechnical Techniques For Assessment Of Foundation...IRJESJOURNAL
 
ICT governance in Higher Education
ICT governance in Higher EducationICT governance in Higher Education
ICT governance in Higher EducationIRJESJOURNAL
 
Gobernanzade las TIC en la Educacion Superior
Gobernanzade las TIC en la Educacion SuperiorGobernanzade las TIC en la Educacion Superior
Gobernanzade las TIC en la Educacion SuperiorIRJESJOURNAL
 
The Analysis and Perspective on Development of Chinese Automotive Heavy-duty ...
The Analysis and Perspective on Development of Chinese Automotive Heavy-duty ...The Analysis and Perspective on Development of Chinese Automotive Heavy-duty ...
The Analysis and Perspective on Development of Chinese Automotive Heavy-duty ...IRJESJOURNAL
 
Research on The Bottom Software of Electronic Control System In Automobile El...
Research on The Bottom Software of Electronic Control System In Automobile El...Research on The Bottom Software of Electronic Control System In Automobile El...
Research on The Bottom Software of Electronic Control System In Automobile El...IRJESJOURNAL
 
Evaluation of Specialized Virtual Health Libraries in Scholar Education Evalu...
Evaluation of Specialized Virtual Health Libraries in Scholar Education Evalu...Evaluation of Specialized Virtual Health Libraries in Scholar Education Evalu...
Evaluation of Specialized Virtual Health Libraries in Scholar Education Evalu...IRJESJOURNAL
 
Linking Ab Initio-Calphad for the Assessment of the AluminiumLutetium System
Linking Ab Initio-Calphad for the Assessment of the AluminiumLutetium SystemLinking Ab Initio-Calphad for the Assessment of the AluminiumLutetium System
Linking Ab Initio-Calphad for the Assessment of the AluminiumLutetium SystemIRJESJOURNAL
 
Thermodynamic Assessment (Suggestions) Of the Gold-Rubidium System
Thermodynamic Assessment (Suggestions) Of the Gold-Rubidium SystemThermodynamic Assessment (Suggestions) Of the Gold-Rubidium System
Thermodynamic Assessment (Suggestions) Of the Gold-Rubidium SystemIRJESJOURNAL
 
Elisa Test for Determination of Grapevine Viral Infection in Rahovec, Kosovo
Elisa Test for Determination of Grapevine Viral Infection in Rahovec, KosovoElisa Test for Determination of Grapevine Viral Infection in Rahovec, Kosovo
Elisa Test for Determination of Grapevine Viral Infection in Rahovec, KosovoIRJESJOURNAL
 
Modelling of Sealing Elements Wearing
Modelling of Sealing Elements WearingModelling of Sealing Elements Wearing
Modelling of Sealing Elements WearingIRJESJOURNAL
 
Determining Loss of Liquid from Different Types of Mud by Various Addictives ...
Determining Loss of Liquid from Different Types of Mud by Various Addictives ...Determining Loss of Liquid from Different Types of Mud by Various Addictives ...
Determining Loss of Liquid from Different Types of Mud by Various Addictives ...IRJESJOURNAL
 

Mehr von IRJESJOURNAL (20)

Drying of agricultural products using forced convection indirect solar dryer
Drying of agricultural products using forced convection indirect solar dryerDrying of agricultural products using forced convection indirect solar dryer
Drying of agricultural products using forced convection indirect solar dryer
 
The Problems of Constructing Optimal Onboard Colored RGB Depicting UAV Systems
The Problems of Constructing Optimal Onboard Colored RGB Depicting UAV SystemsThe Problems of Constructing Optimal Onboard Colored RGB Depicting UAV Systems
The Problems of Constructing Optimal Onboard Colored RGB Depicting UAV Systems
 
Flexible Design Processes to Reduce the Early Obsolescence of Buildings
Flexible Design Processes to Reduce the Early Obsolescence of BuildingsFlexible Design Processes to Reduce the Early Obsolescence of Buildings
Flexible Design Processes to Reduce the Early Obsolescence of Buildings
 
Study on Performance Enhancement of Solar Ejector Cooling System
Study on Performance Enhancement of Solar Ejector Cooling SystemStudy on Performance Enhancement of Solar Ejector Cooling System
Study on Performance Enhancement of Solar Ejector Cooling System
 
Flight Safety Case Study: Adi Sucipto Airport Jogjakarta - Indonesia
Flight Safety Case Study: Adi Sucipto Airport Jogjakarta - IndonesiaFlight Safety Case Study: Adi Sucipto Airport Jogjakarta - Indonesia
Flight Safety Case Study: Adi Sucipto Airport Jogjakarta - Indonesia
 
A Review of Severe Plastic Deformation
A Review of Severe Plastic DeformationA Review of Severe Plastic Deformation
A Review of Severe Plastic Deformation
 
Annealing Response of Aluminum Alloy AA6014 Processed By Severe Plastic Defor...
Annealing Response of Aluminum Alloy AA6014 Processed By Severe Plastic Defor...Annealing Response of Aluminum Alloy AA6014 Processed By Severe Plastic Defor...
Annealing Response of Aluminum Alloy AA6014 Processed By Severe Plastic Defor...
 
Evaluation of Thresholding Based Noncontact Respiration Rate Monitoring using...
Evaluation of Thresholding Based Noncontact Respiration Rate Monitoring using...Evaluation of Thresholding Based Noncontact Respiration Rate Monitoring using...
Evaluation of Thresholding Based Noncontact Respiration Rate Monitoring using...
 
Correlation of True Boiling Point of Crude Oil
Correlation of True Boiling Point of Crude OilCorrelation of True Boiling Point of Crude Oil
Correlation of True Boiling Point of Crude Oil
 
Combined Geophysical And Geotechnical Techniques For Assessment Of Foundation...
Combined Geophysical And Geotechnical Techniques For Assessment Of Foundation...Combined Geophysical And Geotechnical Techniques For Assessment Of Foundation...
Combined Geophysical And Geotechnical Techniques For Assessment Of Foundation...
 
ICT governance in Higher Education
ICT governance in Higher EducationICT governance in Higher Education
ICT governance in Higher Education
 
Gobernanzade las TIC en la Educacion Superior
Gobernanzade las TIC en la Educacion SuperiorGobernanzade las TIC en la Educacion Superior
Gobernanzade las TIC en la Educacion Superior
 
The Analysis and Perspective on Development of Chinese Automotive Heavy-duty ...
The Analysis and Perspective on Development of Chinese Automotive Heavy-duty ...The Analysis and Perspective on Development of Chinese Automotive Heavy-duty ...
The Analysis and Perspective on Development of Chinese Automotive Heavy-duty ...
 
Research on The Bottom Software of Electronic Control System In Automobile El...
Research on The Bottom Software of Electronic Control System In Automobile El...Research on The Bottom Software of Electronic Control System In Automobile El...
Research on The Bottom Software of Electronic Control System In Automobile El...
 
Evaluation of Specialized Virtual Health Libraries in Scholar Education Evalu...
Evaluation of Specialized Virtual Health Libraries in Scholar Education Evalu...Evaluation of Specialized Virtual Health Libraries in Scholar Education Evalu...
Evaluation of Specialized Virtual Health Libraries in Scholar Education Evalu...
 
Linking Ab Initio-Calphad for the Assessment of the AluminiumLutetium System
Linking Ab Initio-Calphad for the Assessment of the AluminiumLutetium SystemLinking Ab Initio-Calphad for the Assessment of the AluminiumLutetium System
Linking Ab Initio-Calphad for the Assessment of the AluminiumLutetium System
 
Thermodynamic Assessment (Suggestions) Of the Gold-Rubidium System
Thermodynamic Assessment (Suggestions) Of the Gold-Rubidium SystemThermodynamic Assessment (Suggestions) Of the Gold-Rubidium System
Thermodynamic Assessment (Suggestions) Of the Gold-Rubidium System
 
Elisa Test for Determination of Grapevine Viral Infection in Rahovec, Kosovo
Elisa Test for Determination of Grapevine Viral Infection in Rahovec, KosovoElisa Test for Determination of Grapevine Viral Infection in Rahovec, Kosovo
Elisa Test for Determination of Grapevine Viral Infection in Rahovec, Kosovo
 
Modelling of Sealing Elements Wearing
Modelling of Sealing Elements WearingModelling of Sealing Elements Wearing
Modelling of Sealing Elements Wearing
 
Determining Loss of Liquid from Different Types of Mud by Various Addictives ...
Determining Loss of Liquid from Different Types of Mud by Various Addictives ...Determining Loss of Liquid from Different Types of Mud by Various Addictives ...
Determining Loss of Liquid from Different Types of Mud by Various Addictives ...
 

Kürzlich hochgeladen

Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 

Kürzlich hochgeladen (20)

Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 

A Study in Construction Delays of Residential Structures

  • 1. International Refereed Journal of Engineering and Science (IRJES) ISSN (Online) 2319-183X, (Print) 2319-1821 Volume 6, Issue 6 (June 2017), PP.42-47 www.irjes.com 42 | Page A Study in Construction Delays of Residential Structures Ansari Hassaan1 , Fakih Hamza2 , Manjrekar Nikhil3 , Sunasra Sufyan4 1,2,3,4 (Civil Department, M.H. Saboo Siddik College of Engineering/Mumbai University , Maharashtra, India) Abstract: Delays are one of the most common problem faced by the construction industry in India and around the world. Construction delays can be caused by several reasons which can be related to owner, design, labor or could be caused by some external factors such as bad weather. The delay in construction causes time overrun which implies that the project requires additional time for completion than originally anticipated. Time overrun in turn leads to cost overrun which causes huge monetary losses. This study focuses on finding out the most common causes of construction delays in Indian context. The study was carried out in South and Central Mumbai region. A questionnaire based survey was conducted based on 43 questions spread across 9 different categories. The findings were evaluated with Relative Importance Index technique. The aim of the study was to identify various causes of delays in construction and their importance. Keywords: Time Overrun, Cost Overrun, Relative Importance Index, Construction Delays, Construction Industry. I. INTRODUCTION The construction industry is the second largest industry in India after agriculture. It makes a significant contribution to the national economy and provides employment to large number of people. However, the construction industry is volatile and requires massive financial investment. Typically, the work offers low rate of returns in relation to the amount of risk involved. In construction, delay could be defined as the time overrun either beyond completion date specified in a contract, or beyond the date that the parties agreed upon for delivery of a project. Delays occur in every construction project and the significant of these delays varies considerably from project to project. Delays on the project are universal phenomenon. 1.1 Causes of Delay:  Owner: Owner related delay caused due to reasons such as late payment and poor communications between owner and other parties.  Contractor: Delays caused due to difficulty in financing the project by contractor, improper site management, conflicts between contractor and other parties, poor planning and scheduling of activities.  Consultant: Delay in performing inspection, delay in reviewing and approving design documents.  Design: Revisions in design documents, improper design and subsequent redesigning.  Labor: Shortage of labors, unskilled workforce.  Equipment: Shortage of equipment, low productivity and efficiency of equipment.  Project: Contract duration is too short, legal disputes between various parties.  Materials: Delay in material delivery, availability of materials, changes in type and specifications of materials.  External: Delay in obtaining permits from municipalities, accidents, bad weather, changes government rules and regulations, social and cultural factors. 1.2 Effects of Delays:  Time Overrun  Cost Overrun  Reduction in profits for contractor  Losses for owner due to extended construction phase  Distrust between owner and contractor  Legal disputes between various parties  Total Abandonment of project
  • 2. A Study in Construction Delays of Residential Structures www.irjes.com 43 | Page II. RESEARCH METHODOLOGY The study was based on a questionnaire survey which consisted the following steps.  Preparation of Questionnaire  Conducting Pilot studies  Data Collection  Data Processing and Analysis 2.1 Preparation of Questionnaire: A questionnaire was designed based on object of the study i.e. finding out causes of construction delays of residential projects, finding out opinions to minimize the construction delays. The questionnaire was prepared in such a way as to get the opinions and understandings from experienced respondents. The questionnaires are classified into 2 categories: a) Respondent Background In this section, we try to obtain the respondents information. This questionnaire includes:  The respondent organization  The position of the respondent in the company  The experience of the respondent in the construction project b) Causes of Construction Delays This section of questionnaire evaluates the factors that contribute to the cause of construction delays. The factors are divided into 9 groups namely:  Owner  Contractor  Consultant  Design  Equipment  Project  Labours  Materials  External factors The questionnaire is based on Likert’s scale of 5 ordinal measures from 1 to 5 according to the contribution  (5) = Very High Effective  (4) = High Effective  (3) = Effective  (2) = Low Effective  (1) = Very Low Effective The Questionnaire Consisted of 43 questions divided into 9 categories mentioned above. Table 1 NO . Group Cause of delay Very high effective High effective Effective Low effective Very low effective 1 Owner Delay in progress payments by owner 2 Owner Late in revising and approving design documents by owner 3 Owner Poor communication and coordination by owner and other parties 4 Owner Unavailability of incentives for contractor 5 Owner Suspension of work by owner 6 Contractor Difficulties in financing project by contractor 7 Contractor Poor site management and supervision by contractor 8 Contractor Poor communication and coordination by contractor with
  • 3. A Study in Construction Delays of Residential Structures www.irjes.com 44 | Page other parties. 9 Contractor Delay in site mobilization 10 Contractor Rework due to errors during construction 11 Contractor Conflicts b/w contractor and other parties 12 Contractor Ineffective planning and scheduling of project by contractor 13 Contractor Improper construction methods implemented by contractor 14 Contractor Inadequate contractor’s work 15 Consultant Inadequate experience of consultant 16 Consultant Delay in performing inspection and testing by consultant 17 Consultant Delay in approving major changes in the scope of work by consultant 18 Consultant Late in reviewing and approving design documents by consultant 19 Design Revisions in design documents 20 Design Delays in producing design documents 21 Design Misunderstanding of owner’s requirements by architect 22 Labor Shortage of labors 23 Labor Unskilled workforce 24 Equipment Shortage of equipment 25 Equipment Low level of equipment- operator’s skill 26 Equipment Low productivity and efficiency of equipment 27 Project Ineffective delay penalties 28 Project Original planned contract duration is unrealistic 29 Project Disputes between various parties 30 Materials Changes in material types and specifications during construction 31 Materials Delay in material delivery 32 Materials Housekeeping of materials 33 Materials Delay in manufacturing/processing special building materials 34 Materials Late in selection of finishing materials due to availability of many types in market 35 External Delay in obtaining permissions from municipality 36 External Rain effect on construction activities 37 External Effect of social and cultural factors 38 External Traffic control and restriction at job site (Job layout) 39 External Accident during construction 40 External Differing site (ground) conditions 41 External Changes in government
  • 4. A Study in Construction Delays of Residential Structures www.irjes.com 45 | Page regulations and laws 42 External Delay in providing services from utilities (such as water, electricity) 43 External Delay in performing final inspection and certification by a third party 2.2 Conducting Pilot studies: The main goal of this was to eliminate misunderstanding the questions that were mentioned in the questionnaire. Every respondent was asked about each and every question's meaning in order to ensure that there was no confusions with the questions. Further they were asked on their opinions on the questions and wordings of the question and their importance with respect to our study thereby eliminating questions which held no significance. This also allowed us to simplify the questions as it would be very important when the questionnaire would be mailed to respondents which we could not personally interview thus minimizing the confusion and getting more accurate results. 2.3 Data Collection: The Data Collection for our study was done in two ways: a) Personal Interviews b) Mailing Questionnaire a) Personal Interviews An appointment was taken with Project Managers, Consultants, Site Engineers & Owners (Developers). And the questionnaire was presented in order to get our data. b) Mailing Questionnaire In the case of being unable to visit Respondents we mailed them soft copies of questionnaire which was filled up by them and mailed back to us. The table below gives us the details of the respondents such as positions held by them in the organization and no of years of experience. Table 2 SITE NO. POSTION HELD NO. OF YEARS OF EXPERIENCE SITE 1 SITE ENGINEER 2 YEARS SITE 2 PROJECT MANAGER 11 YEARS SITE 3 SENIOR ENGINEER 7 YEARS SITE 4 ASSISTANT DIRECTOR 6 YEARS SITE 5 SITE ENGINEER 2 YEARS SITE 6 SENIOR ENGINEER 6 YEARS SITE 7 SITE ENGINEER 6 YEARS SITE 8 OWNER 10 YEARS SITE 9 SITE ENGINEER 2 YEARS SITE 10 QUANTITY SURVEYOR 2 YEARS SITE 11 DESIGN ENGINEER 7 YEARS SITE 12 PROJECT ENGINEER 8 YEARS SITE 13 SITE ENGINEER 2 YEARS SITE 14 SENIOR ENGINEER 7 YEARS 2.4 Data Processing and Analysis: The study utilized method to analyze the respondent’s data to identify the critical attributes among the categories owner, contractor, consultant, design, labor, equipment, project, materials and external. The analysis and processing of the data was done using Relative Importance Index technique. 2.4.1 Relative Importance Index Relative index has been widely used in construction research for measuring attributes with respect to surveyed variables. Likert’s scaling was used for ranking questions that have an agreement levels. The respondents were required to rate the importance of each factor on a 5-point Likert’s scale using: (5) = Very High Effective (4) = High Effective
  • 5. A Study in Construction Delays of Residential Structures www.irjes.com 46 | Page (3) = Effective (2) = Low Effective (1) = Very Low Effective Then the relative importance index was computed using the following formula: Where, “W” is the weighting given to each factor by the respondent, ranging from 1 to 5, ( = number of respondent for very low effective, = number of respondent for low effective, number of respondent for effective, = number of respondent for high effective, = number of respondent for very high effective). “A” is the highest weight (i.e. 5 in the study) and “N” is the total number of samples. The relative importance index ranges from 0 to 1. III. CONCLUSION From the data collected by us during the questionnaire survey we found that:  The most important cause of construction delay of residential structures occurs due to the owner related causes. Out of all owner related causes, the respondents cited that the most important cause of delay was due to late payment by owners. The least cause of delay in this category was due to incentives for contractors.  The second most important cause of delay was design related with misunderstanding of owner’s requirement by design engineer as the most important in the category. The other two causes that is revision in design documents and delays in producing design documents were equally important but were ranked below in the second place within the category.  Third ranked category was of external causes with delay in obtaining permits from municipality as the highest rated cause and accidents during construction as the least important cause of delay.  Coming in at number four was Labor category with shortage of labors as the most important cause and unskilled workforce as the least important cause of delay.  Number fifth category was Contractor with difficulty in financing project by contractor as the most important reason and delay due to site mobilization was rated as the least cause of delay.  Sixth and Seventh place was a tie between Consultant and Project category with late in reviewing and approving design documents by consultant as the most important cause and delay in performing inspection and testing by consultant as least important for Consultant category and in the Project category, legal disputes between various parts as the most important cause and ineffective delay penalties as the least cause of delay.  Eight place goes to Equipment category with shortage of equipment as the most important cause. The other causes in this category received equal ratings.  The least important category according to respondents was Material category with delay due to manufacturing of special materials as most important cause and changes in material types and specifications during construction as least important cause. Table 3 Category Relative Importance Index (Category Average) Owner 0.677 Contractor 0.603 Consultant 0.571 Design 0.667 Labor 0.621 Equipment 0.566 Project 0.571 Materials 0.554 External 0.66
  • 6. A Study in Construction Delays of Residential Structures www.irjes.com 47 | Page Fig. 1 ACKNOWLEDGEMENTS We sincerely appreciate Dr. Shagufta Sayed for giving us an opportunity to work on this topic. We are grateful for her support and guidance which has helped us to expand our horizon of thoughts and experience. REFERENCES [1]. Megha, Desai, and Bhatt Rajiv. "A methodology for ranking of causes of delay for residential construction projects in Indian context." International Journal of Emerging Technology and Advanced Engineering 3.3 (2013): 396-404. [2]. Rathod, Aradhana, and S. Pimplikar. "Delays In Residential Building Construction." International Journal of Innovative Research and Development|| ISSN 2278–0211 2.5 (2013). [3]. Rao, Prakash B., and Culas Joseph Camron. "Causes of Delays in Construction Projects-A case study." International Journal of Current Research 6.6 (2014): 7219-7222. [4]. Thomas, Anu V., and J. Sudhakumar. "Factors influencing construction labour productivity: an Indian case study." Journal of Construction in Developing Countries 19.1 (2014): 53. [5]. Chaphalkar, Nitin Balkrishna, and K. C. Iyer. "Factors influencing decisions on delay claims in construction contracts for Indian scenario." Construction Economics and Building 14.1 (2014): 32-44. [6]. Mustapha, F. H., and S. Naoum. "Factors influencing the effectiveness of construction site managers." International Journal of Project Management 16.1 (1998): 1-8. [7]. Fellows, Richard F., and Anita MM Liu. Research methods for construction. John Wiley & Sons, 2015.