SlideShare ist ein Scribd-Unternehmen logo
1 von 34
A PRESENTATION ON
 GROUTING SYSTEMS
 FREEZING METHODS
 SHAFT DRILLING AND BORING
 SHAFT SINKING
Grouting Systems
Applicability –1.Water bearing, competent but fractured rocks.
Sealed Zone is formed to arrest water reflow.
2.Voids also can be filled behind lining for improving lining
` tightness.
From surface
Hole specifications.
• Diameter—3 to 5” or 75 to 150 mm
• Radius—3 to 4m longer than the shaft radius
• Distance between holes—2 to 4m
• Entering of hole(3-5m)--- cement guiding like
• Grouting length ---25 to 50 m
After 24 hrs. /redrilling in soft grout /extended.
From Face
• Section length ---12 to 25 m
• When water bearing strata is below 100m.
• Drilled in an angle ---1-2 away from front face.
• Tangential fitting to cover longer area.
• Hole spacing (0.8 to 1.5 m)
Size of hole (mm):
50-75 mm  initially
30-50 mm  finally
no. of holes ∞ 1. Rock character
2. Shaft diameter
3. Hydrological condition
Normally(10 to 20 to 30)
Size of hole (mm):
50-75 mm  initially
30-50 mm  finally
Sequence of grouting: -
 First half are drilled & grouted. While these are getting hardened rest are drilled.
 All are drilled & grouted one after the other starting with the hole with the largest
inflow.
 Pairs of holes are drilled & grouted & then perpendicular to these are drilled and
grouted.
Selection of cement and grout parameters
1. Character of water(salt or fresh)
2. Mineralisation and chemical corrosives
3. Value of the titration factor
Density of grout ∞ water absorbability
Water absorbability, q = Q/(Hh)
Q: water volume (in litres / min).
H: water need
h: height of hole section (in m).
•Large fractures: 25 to 30%
•Small fractures: 3 to 5%
Optimum grouting regime has to be established first.
Cement : clay 1 : 2
1 : 3
1 : 4
Cement : clay : sand 1 : 1 : 15
1 : 1 : 2
Equipment
• Cementation pumps for grout injection.
• Mechanical mixtures for grout preparation.
• Grout tanks.
• Flexible pressure hoses
• Injectors
• Pipes, valve pressure gauges, tools etc.
Pressure p= Hgk
H= depth from surface to top of strata
g= 1.5 to 2 t/m3
k = 2 to 3 (coefficient of cohesion of the strata above the grouting zone)
Normally ---1-3 MPa
Check ---water absorbability < 0.05 L/min/m
Grout consumption
SST ---- 3.3 to16.5 t/m.
Dolomite ---2.2 to 4.4 t/m
8 to 15 m/month (35 to 50 % more time)
30 to 50% more costly.
Excavation :
1 to 1.5 m long holes
Quantity of charge is reduced .
SST—1.3kg/cu.m. Shale:1.1 kg/m3 Coal:0.6 kg/m3
Testing of water presence is done and sinking proceeds .
Freezing Method:
SUITABLE DESIGN PROCEDURE REQUIRES SOLN OF FOLLOWING PROBLEMS:
• Calculation of the wall thickness of the frozen rock cylinder.
• Diameter of the freezing circle, no., depth & spacing control holes.
• Drilling system for freezing holes, specification of the equipment, freezing pipes
diameter and freezing time.
• Design of temporary shaft head with a freezing basement.
• Planning of the freezing procedure in active & passive periods.
-freezing temperature, heat balance, ‘h’ of freezing installation, time.
• System and time of Thawing.
• Freezing tech planning, shaft sinking and lining.
Normally 5 to 5.5 metres.
In the above formula, we have:
P: MPC (external pressure)
r: Shaft Radius
KC : Allowable Stress
Freezing Holes
Thickness of frozen cylinder: 5 to 5.5 m.
(Where, H: Depth up to shaft bottom.)
• Dm is larger by 2 m to the shaft. (80m)
• Dm is larger by 2.5 m to the shaft. (150m)
• Dm is larger by 3 m to the shaft. (>150m)
 Distance between freezing holes – 0.9 to 1.1m. More 1.25 for deep.
 The chord of overlapping circles should be equal to the calculated thickness of
frozen wall.
 Depth of holes  5m below water bearing strata (55m).
 Verticality of holes is the biggest problem.(Additional holes may be required)
 2 to 3 rigs / mud fluid drilling medium /
Freezing hole equipment:
There are two columns of tubing –
1. Outside: 102 to 152m.
2. Inside : 32 to 51mm (steel) or (polyethylene)*
* Polyethylene has an advantage over steel because:
• It has a lower weight.
• It is cheaper.
• It is easier to install.
• It has a lower thermal conductivity.
• Specific gravity is same as the brine.
We hence prefer polyethylene more over steel for the tubing purpose.
Process:
Freezing brine flows at high velocity down the inner pipe. It rises more slowly in the
annulus absorbing heat from the surrounding rocks.
 The type of flow is different depending on the region of flow. There are basically
two flow regions:
1. Moderate depths  Laminar flow.
2. Deeper regions/clay/organic  Turbulent flow.
 It needs 2 to 8 months time for freezing. The freezing in the moderate depths take
place at round two months while those in the deeper regions take longer time up to 8
months.
 Holes of larger diameter are needed for greater depths.
 Complete tightness of joints among individual segments of pipes is necessary.
*Gases used and the temperature at which they are used to serve
the purpose:
1. Ammonia (NH3):
(-)20o C – For one stage compression.
(-)40oC – For double stage compression.
2. Carbon Dioxide (CO2): Used at (-)50oC.
Periods:
oActive: - 3 units min. full capacity till the desired frozen cylinder forms.
oPassive: - Maintaining frozen rock mass at desired temperature during sinking &
lining. 1/2 to 1/3 times the capacity is sufficient.
Heat Losses:
Heat from outside the frozen material.
Losses in freezing installation due to imperfect insulation.
Frost Penetration Velocity: -
The penetration occurs at the rate of: (i) 25mm per day in sand.
(ii) 10-15mm per day in clay.
On a larger scale, the penetration rate is: (i) 2-4 months per 250 metres of depth
(ii) 9-10 months per 500 metres of depth
EQUIPMENT FOR SHAFT SINKING
(A)Site preparation
above HFL(100 years record)
1. Construction of roads and material storage areas
2. Grading of the terrain(while sinking also this can be done)
3. Water supply(drinking, industrial use and fire extinguishing)
80 - 120m3 / day 40 - 60m3 / day 80-100m3 / day
plant water tap water fire tank
( adequate ditch for storm water )
4. Electrical power supply(2 stages)
Preparatory - 260 KVA transformers - Diesel generator stand bye
Sinking - 1200 KVA, 500 V - Diesel generator stand bye
5. REQUIREMENTS:-
 Storage space for material
 Ramp for unloading heavy machinery
 Telephone lines
 Temperature buildings and head gear foundation
 Installation of sinking equipment
 Surveying of shaft elevation, centering
(B) Temporary Buildings
1. Office, first aid room, heating and cooling units, ware house
2. Lamp house(in accordance with MSHA standards)
3. Mechanical and blacksmith shop(for minor repair work)
4. Compressor sheds
5. Transformer station
6. Shed for concreting, mucking and other equipment
7. Shed for cement storage
8. Winch building for shaft stage
9. Fan housing
10.Flammable supplies ware house
11.Hoist Buildings
12.Storage for explosives(Magazine)
13.Accommodation for sinking crew.
1) SHAFT COLLAR CONSTRUCTION(8-12m)
• Air Channel
• Channel for water pipes, air pipes
• Ladder Compartment
• Basement for pushers
2) D & B in Shafts : supposed to ensure-
(a) Correct size and shape of planned excavation
(b) Even shape of the surface
(c) Uniform size of broken rock
(d) Safe and economical operation
3) Mucking Shaft :- 50- 60% of cycle time
Mucking ‘η’
Depth
Muckers
Several type of muckers are in use depending on-
Shaft shape, size, depth and location
1. Scrapers- rectangular shafts
large dia shafts (U/G bunkers)
2. Overshot loaders on caterpillars
3. Cryderman Muckers
4. Cactus Grab (light)
5. Cactus Grab (heavy) Central Pivot (1.3cu)
Hanging from platform/hand guided
Attached to shaft wall(3)type
Large cap muckers for deep min/larger dia
- electric, pneumatic or hydraulic
Capacity:-
Pt= 3600 k Vb / t
where
Pt = Thermal Capacity in cubic meter per hour
k = Fill factor (0.8 to 0.9-sandstone
1.1 to 1.2-shale)
Vb = Bucket Capacity in cubic meter
t = mucking time
 Lowering
 Templing
 Cleaning
DEWATERING OF SHAFTS
REQUIRED WHEN THERE IS:
Intersection of water courses
1. Changing water inflow
2. Changing pump head
3. Changing rock and mud contained water
4. Periodic changes in positioning of devices
WATER INFLOW into the shaft can be reduced by:
 Pumping
 Initial drainage / sealing / tapping
DEVICES FOR PUMPING
 KIBBLES: Capacity:3cum/min
Depth- upto 150 m
Two types of kibbles- normal kibbles and special kibbles
 Face pumps: based on compressed air principle
 Centrifugal pumps
 Reciprocating pumps- higher pumping head
-but they make a lot of noise
 Multistage pumps: stationary pumps in convention with face pumps
uses stage pumping
 Hanging pumps:-used to control large inflows
- pumping head of 200-400m
DEVICES FOR PUMPING
 Intermediate pump: especially for deep shafts
 Airlifts:-powered by compressed air
-most popular for small depths
Two main system for these pumps are:
i. parallel:- where the air pipe runs beside the water pipe
ii. concentric:-where the air pipe is inside the water pipe
t. Pumps
Deep/ Stages/overflow chamber
3 combinaton
Equipment Nos.
• Winders -400Kw-6600v 1 Main One Mineral
BB-3000
• BB-2200-130kw-500v 1 Auxiliary One Man
Winder
• Fans -6kw/500m3 2
• Air Compressors- 2
• Winches Sufficient No.
• Housing/Pumps
• Shaft Fittings
(1)Burtons
(2)Ventilator Tubes (700mmø)
(3)Pipe Line for Concrete
(4)Compressed Air Tanks
(5)Steel Shutters
(6)Brackets
(7)Ropes for Winders
(8)Winches
(9)Hoisting Buckets (1.25m3/2 m3 )
(10)Grab
(11)Grab Loaders
(12)Drilling Machines
(13)Lighting Arrangement.
• Pumping Accessories
• Scaffolding
• Shotcreting Equipment (mixer/nozzle/pipeline)
• Exploder
Purpose
1) Production 2) Service 3) Ventilation 4) Exploration
5) Escape 6) Combination
Brakes:
 Holding of hoist drum
 Electrical (mechanical breaking system )
(Normal/emergency operation)
 Electric breaking
1. Regenerative energy returned to system / induction generator developer
2. Breaking torque
3. Counter torque
4. Dynamic
 Mechanical breaking
1. To slow down the drum
2. Holds the drum at rest
Jaw /parallel motion /disk brakes –friction hoists
Drum /friction hoists
 Calliper brakes
1. Speed /force of breaks
2. Controlled by oil flow
Drum hoist
1. Over wind /rope breakage
2. Safety dog
Friction hoist
Over wind: Arrestor Gear
Ventilation
Ducting is hung in the shaft by two steel ropes connected periodically to collars
round the pipe.
Lights
-safety
-output
-flood light charters
-suspended stage and tensor frame special reflector and sealed cover
-hang on ropes(special cable)
-100W lamps and even 40-50m of water.
SHAFT DRILLING AND BORING
 Boring of shafts/large diameter holes/ foundation of off-shore drilling.
 Shaft sinking is slow, tedious, hazardous and uncomfortable.
 Drilling is possible up to depths 1000m.
 Diameter - 10m
 Weak and moderate - Strength rock (300MPC)
 Cope with difficult hydro geological conditions.
STEPS IN DESIGNING
 Geotechnical and hydro geological parameters.
 Planned shaft diameter, depth, adequate cutters for the type of rock, stages of reams
and properties of drilling fluid.
 Design of shaft head.
 Living placement methodology/sealing.
 Sealing of water.
 Organization of the drilling site, location of ponds, storage of living components.
DRILLING FLUID
Water and natural clay / SG - 1.15 to 1.25
DRILLING EQUIPMENT
Drilling equipment consists of Heavy drill rigs having sufficient capacity to provide the
required torque and the hoisting capacity.
Ex: - CSD 300 (Hughes Micon)
6 Hydraulic motors, 70 KNm Torque
Shaft Alignment is 1 in 1000
CUTTERS
• Milled steel tooth cutters - Soft rock
• Tungsten carbide cutters - harder rock (abrasive)
• Disk cutters - not needed for (blind hole drilling)
LINING
200mm/ Shot Crete / Bolts / Wire mesh/ concrete/prepared and placed.
SHAFT BORING
• New / least matured (1960’s)
• SBM’s (vertical TBM’s)(personnel travel log inboard)
• Picking up the cutting is the major problem.
• Wirth m/c - successful with pilot hole for free much removal to a lower face.
• Blind shafts were driven with limited success only.
• SBM’s (2cutter motors of 261 KW / disc cutters)
• Carboniferous rock is the most suited one.
• Grouting of water bearing strata is mandatory before shaft boring.
SHAFT RAISING
• Raise boring m/c’s in place of conventional methods are common today
• Raise climbers
• Lower level is developed
• When sinking is not possible due to lack of space or lack of room for production
• Only on competent rocks
• Without water inflow
ADVANTAGES
 Influence on mine performance is minimum
 Loading of muck into buckets is avoided
 Blasting efficiency is greater
 No water pumping is required
DISADVANTAGES
 Height of rising limited (100 to 120m)
 Ladder climbing inconvenient for men and material transport.
 Potential hazard of pieces of rock falling from face
 Potential threat of much jamming on chute
 Surveying is difficult
 Time and cost for preparing the opening for raising purpose.
EQUIPMENT
 Chute
 Hoist
 Ladder
 Brattice
 Heavy load bearing wooden platform with steel girders
 F.O.S - 6
 Face to platform 1.5m-3.0m, 5m(at a go) (in strong rocks)
 Ventilation through a (200 - 300m) diameter hole drilled above.
ALTERNATIVES (3)
 Raising the diameter up to 4m(Temperature/permanent)
 Permanent lining is done at every short interval.
 Diameter > 4m. Pilot hole is then widened.
MECHANICAL RAISE CLIMBERS:
 For hard rock (Alimah- Swedish)
 Runs on a guide rail (Pin rock) (through rock bolts)
ADVANTAGES:
 Permits the driving of very long raises, vertical or inclined, straight or curved.
 When travelling to the head of the raise, personnel are well protected in a cage under
the platform.
 Miners work on a platform whose height/angles can be adjusted.
 Risks of gases are reduced(through ventilation)
 All the material can be transported easily.
 Timbering avoided / rock bolting and mesh may be used.
 Usable up to 8m2 area.
DISADVANTAGES:
 Cost for short stretches not justified.
Final grouting freezing

Weitere ähnliche Inhalte

Was ist angesagt?

Industrial chimneys
Industrial chimneysIndustrial chimneys
Industrial chimneys
Manjunath Sn
 
BIMETALLIC STRIPPER&PRE-CONC.
BIMETALLIC STRIPPER&PRE-CONC.BIMETALLIC STRIPPER&PRE-CONC.
BIMETALLIC STRIPPER&PRE-CONC.
vipul srivastava
 
Chimney present
Chimney presentChimney present
Chimney present
mathusaran
 
Chapter 7 conveyance of water
Chapter 7 conveyance of waterChapter 7 conveyance of water
Chapter 7 conveyance of water
Gokul Saud
 
Ln clinker cooler golden rules 2010 11 17
Ln clinker cooler golden rules 2010 11 17Ln clinker cooler golden rules 2010 11 17
Ln clinker cooler golden rules 2010 11 17
mkpq pasha
 

Was ist angesagt? (20)

Sewer joint
Sewer jointSewer joint
Sewer joint
 
Pipe materials and types of joints [autosaved]
Pipe materials and types of joints [autosaved]Pipe materials and types of joints [autosaved]
Pipe materials and types of joints [autosaved]
 
Various types of pressure pipes
Various types of pressure pipes Various types of pressure pipes
Various types of pressure pipes
 
Pipe flange fittings by Madhur
Pipe flange fittings by MadhurPipe flange fittings by Madhur
Pipe flange fittings by Madhur
 
Tube expansion
Tube expansionTube expansion
Tube expansion
 
Pipeline construction management
Pipeline construction managementPipeline construction management
Pipeline construction management
 
Chimney design
Chimney designChimney design
Chimney design
 
Industrial chimneys
Industrial chimneysIndustrial chimneys
Industrial chimneys
 
Dynamic behaviour of tall chimneys
Dynamic behaviour of tall chimneysDynamic behaviour of tall chimneys
Dynamic behaviour of tall chimneys
 
BIMETALLIC STRIPPER&PRE-CONC.
BIMETALLIC STRIPPER&PRE-CONC.BIMETALLIC STRIPPER&PRE-CONC.
BIMETALLIC STRIPPER&PRE-CONC.
 
Chimney present
Chimney presentChimney present
Chimney present
 
Chapter 7 conveyance of water
Chapter 7 conveyance of waterChapter 7 conveyance of water
Chapter 7 conveyance of water
 
Traps and sewers
Traps and sewersTraps and sewers
Traps and sewers
 
PPRC piping presentation
PPRC piping presentationPPRC piping presentation
PPRC piping presentation
 
Tube expansion
Tube expansionTube expansion
Tube expansion
 
MEASURING, CUTTING, AND JOINING PIPES
MEASURING, CUTTING, AND JOINING PIPESMEASURING, CUTTING, AND JOINING PIPES
MEASURING, CUTTING, AND JOINING PIPES
 
Pipes and pipe joints
Pipes and pipe jointsPipes and pipe joints
Pipes and pipe joints
 
Analysis of Self Supported Steel Chimney as Per Indian Standard
Analysis of Self Supported Steel Chimney as Per Indian StandardAnalysis of Self Supported Steel Chimney as Per Indian Standard
Analysis of Self Supported Steel Chimney as Per Indian Standard
 
Piping presentation (master)
Piping presentation (master)Piping presentation (master)
Piping presentation (master)
 
Ln clinker cooler golden rules 2010 11 17
Ln clinker cooler golden rules 2010 11 17Ln clinker cooler golden rules 2010 11 17
Ln clinker cooler golden rules 2010 11 17
 

Ähnlich wie Final grouting freezing

Production of tubes and pipes
Production of tubes and pipesProduction of tubes and pipes
Production of tubes and pipes
Mahesh Bang
 

Ähnlich wie Final grouting freezing (20)

Raise boring,organisation of shaft sinking,lining
Raise boring,organisation of shaft sinking,liningRaise boring,organisation of shaft sinking,lining
Raise boring,organisation of shaft sinking,lining
 
Shaft sinking operation
Shaft sinking operationShaft sinking operation
Shaft sinking operation
 
Conventional shaft sinking by manual means
Conventional shaft sinking by manual meansConventional shaft sinking by manual means
Conventional shaft sinking by manual means
 
3. sequances of drilling operations
3. sequances of drilling operations3. sequances of drilling operations
3. sequances of drilling operations
 
Dimapur-Kohima Rail Project Site Visit Report (1).docx
Dimapur-Kohima Rail Project Site Visit Report (1).docxDimapur-Kohima Rail Project Site Visit Report (1).docx
Dimapur-Kohima Rail Project Site Visit Report (1).docx
 
Trenchless Technology
Trenchless TechnologyTrenchless Technology
Trenchless Technology
 
Ntpc summer training 2017
Ntpc summer training 2017Ntpc summer training 2017
Ntpc summer training 2017
 
Distribution and control of mine air standards of ventilation
Distribution and control of mine air standards of ventilationDistribution and control of mine air standards of ventilation
Distribution and control of mine air standards of ventilation
 
Bond log theory and interpretation
Bond log theory and interpretationBond log theory and interpretation
Bond log theory and interpretation
 
AWS Profile EN IR
AWS Profile EN IRAWS Profile EN IR
AWS Profile EN IR
 
Trenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe InstallationsTrenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe Installations
 
Production of tubes and pipes
Production of tubes and pipesProduction of tubes and pipes
Production of tubes and pipes
 
B3 Sverrir Þórhallsson Slim wells for geothermal exploration
B3 Sverrir Þórhallsson Slim wells for geothermal explorationB3 Sverrir Þórhallsson Slim wells for geothermal exploration
B3 Sverrir Þórhallsson Slim wells for geothermal exploration
 
GERES presentation
GERES presentationGERES presentation
GERES presentation
 
Extending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine PlanningExtending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine Planning
 
Method of working of continuous miner in underground coal
Method of working of     continuous miner in underground coalMethod of working of     continuous miner in underground coal
Method of working of continuous miner in underground coal
 
Metal Mines Blasting
Metal Mines BlastingMetal Mines Blasting
Metal Mines Blasting
 
Heat pipe Best PPT
Heat pipe Best PPTHeat pipe Best PPT
Heat pipe Best PPT
 
Cement ball mill process calculation pdf
Cement ball mill process calculation pdfCement ball mill process calculation pdf
Cement ball mill process calculation pdf
 
TEK.FS.MED.004-M 1.docx
TEK.FS.MED.004-M 1.docxTEK.FS.MED.004-M 1.docx
TEK.FS.MED.004-M 1.docx
 

Mehr von Safdar Ali

Mehr von Safdar Ali (20)

Safety in mines
Safety in minesSafety in mines
Safety in mines
 
Tunneling
TunnelingTunneling
Tunneling
 
Explosives and accesories
Explosives and accesoriesExplosives and accesories
Explosives and accesories
 
Role of management information systems in a mine.
Role of management information systems in a mine.Role of management information systems in a mine.
Role of management information systems in a mine.
 
Basting
BastingBasting
Basting
 
Pre requisites of marine operations
Pre requisites of marine operationsPre requisites of marine operations
Pre requisites of marine operations
 
Nuclear devices for mining
Nuclear devices for miningNuclear devices for mining
Nuclear devices for mining
 
Mining of manganese nodules from sea floor
Mining of manganese nodules from sea floorMining of manganese nodules from sea floor
Mining of manganese nodules from sea floor
 
Mine water risk in open pit slope stability
Mine water risk in open pit slope stabilityMine water risk in open pit slope stability
Mine water risk in open pit slope stability
 
Innovations and trend in metal mining &amp; tunnellng
Innovations and trend in metal mining &amp; tunnellngInnovations and trend in metal mining &amp; tunnellng
Innovations and trend in metal mining &amp; tunnellng
 
Lighting terminlologyand their units
Lighting terminlologyand their unitsLighting terminlologyand their units
Lighting terminlologyand their units
 
Evaluation of slope stability for waste rock dumps in a mine
Evaluation of slope stability for waste rock dumps in a mineEvaluation of slope stability for waste rock dumps in a mine
Evaluation of slope stability for waste rock dumps in a mine
 
Digitization and 3d modelling of a mine plan
Digitization and 3d modelling of a mine planDigitization and 3d modelling of a mine plan
Digitization and 3d modelling of a mine plan
 
Variety of mine plans and sections &amp; second schedule
Variety of mine plans and sections &amp; second scheduleVariety of mine plans and sections &amp; second schedule
Variety of mine plans and sections &amp; second schedule
 
Statutory provisions for the preaparation of mine plans and sections
Statutory provisions for the preaparation of mine plans and sectionsStatutory provisions for the preaparation of mine plans and sections
Statutory provisions for the preaparation of mine plans and sections
 
Gps &amp; its applications in opencast mine surveying
Gps &amp; its applications in opencast mine surveyingGps &amp; its applications in opencast mine surveying
Gps &amp; its applications in opencast mine surveying
 
Laser and its mining applications
Laser and its mining applicationsLaser and its mining applications
Laser and its mining applications
 
Gyrotheodolite
GyrotheodoliteGyrotheodolite
Gyrotheodolite
 
Gps2
Gps2Gps2
Gps2
 
Gps1
Gps1Gps1
Gps1
 

Kürzlich hochgeladen

Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
KarakKing
 

Kürzlich hochgeladen (20)

HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
Plant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptxPlant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptx
 
Tatlong Kwento ni Lola basyang-1.pdf arts
Tatlong Kwento ni Lola basyang-1.pdf artsTatlong Kwento ni Lola basyang-1.pdf arts
Tatlong Kwento ni Lola basyang-1.pdf arts
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
Philosophy of china and it's charactistics
Philosophy of china and it's charactisticsPhilosophy of china and it's charactistics
Philosophy of china and it's charactistics
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
Basic Intentional Injuries Health Education
Basic Intentional Injuries Health EducationBasic Intentional Injuries Health Education
Basic Intentional Injuries Health Education
 
latest AZ-104 Exam Questions and Answers
latest AZ-104 Exam Questions and Answerslatest AZ-104 Exam Questions and Answers
latest AZ-104 Exam Questions and Answers
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17
 
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxOn_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
 

Final grouting freezing

  • 1.
  • 2. A PRESENTATION ON  GROUTING SYSTEMS  FREEZING METHODS  SHAFT DRILLING AND BORING  SHAFT SINKING
  • 3. Grouting Systems Applicability –1.Water bearing, competent but fractured rocks. Sealed Zone is formed to arrest water reflow. 2.Voids also can be filled behind lining for improving lining ` tightness.
  • 4. From surface Hole specifications. • Diameter—3 to 5” or 75 to 150 mm • Radius—3 to 4m longer than the shaft radius • Distance between holes—2 to 4m • Entering of hole(3-5m)--- cement guiding like • Grouting length ---25 to 50 m After 24 hrs. /redrilling in soft grout /extended.
  • 5. From Face • Section length ---12 to 25 m • When water bearing strata is below 100m. • Drilled in an angle ---1-2 away from front face. • Tangential fitting to cover longer area. • Hole spacing (0.8 to 1.5 m) Size of hole (mm): 50-75 mm  initially 30-50 mm  finally no. of holes ∞ 1. Rock character 2. Shaft diameter 3. Hydrological condition Normally(10 to 20 to 30) Size of hole (mm): 50-75 mm  initially 30-50 mm  finally
  • 6. Sequence of grouting: -  First half are drilled & grouted. While these are getting hardened rest are drilled.  All are drilled & grouted one after the other starting with the hole with the largest inflow.  Pairs of holes are drilled & grouted & then perpendicular to these are drilled and grouted. Selection of cement and grout parameters 1. Character of water(salt or fresh) 2. Mineralisation and chemical corrosives 3. Value of the titration factor Density of grout ∞ water absorbability Water absorbability, q = Q/(Hh) Q: water volume (in litres / min). H: water need h: height of hole section (in m).
  • 7. •Large fractures: 25 to 30% •Small fractures: 3 to 5% Optimum grouting regime has to be established first. Cement : clay 1 : 2 1 : 3 1 : 4 Cement : clay : sand 1 : 1 : 15 1 : 1 : 2
  • 8. Equipment • Cementation pumps for grout injection. • Mechanical mixtures for grout preparation. • Grout tanks. • Flexible pressure hoses • Injectors • Pipes, valve pressure gauges, tools etc. Pressure p= Hgk H= depth from surface to top of strata g= 1.5 to 2 t/m3 k = 2 to 3 (coefficient of cohesion of the strata above the grouting zone) Normally ---1-3 MPa Check ---water absorbability < 0.05 L/min/m Grout consumption SST ---- 3.3 to16.5 t/m. Dolomite ---2.2 to 4.4 t/m 8 to 15 m/month (35 to 50 % more time) 30 to 50% more costly. Excavation : 1 to 1.5 m long holes Quantity of charge is reduced . SST—1.3kg/cu.m. Shale:1.1 kg/m3 Coal:0.6 kg/m3
  • 9. Testing of water presence is done and sinking proceeds .
  • 10. Freezing Method: SUITABLE DESIGN PROCEDURE REQUIRES SOLN OF FOLLOWING PROBLEMS: • Calculation of the wall thickness of the frozen rock cylinder. • Diameter of the freezing circle, no., depth & spacing control holes. • Drilling system for freezing holes, specification of the equipment, freezing pipes diameter and freezing time. • Design of temporary shaft head with a freezing basement. • Planning of the freezing procedure in active & passive periods. -freezing temperature, heat balance, ‘h’ of freezing installation, time. • System and time of Thawing. • Freezing tech planning, shaft sinking and lining. Normally 5 to 5.5 metres. In the above formula, we have: P: MPC (external pressure) r: Shaft Radius KC : Allowable Stress
  • 11.
  • 12. Freezing Holes Thickness of frozen cylinder: 5 to 5.5 m. (Where, H: Depth up to shaft bottom.) • Dm is larger by 2 m to the shaft. (80m) • Dm is larger by 2.5 m to the shaft. (150m) • Dm is larger by 3 m to the shaft. (>150m)
  • 13.  Distance between freezing holes – 0.9 to 1.1m. More 1.25 for deep.  The chord of overlapping circles should be equal to the calculated thickness of frozen wall.  Depth of holes  5m below water bearing strata (55m).  Verticality of holes is the biggest problem.(Additional holes may be required)  2 to 3 rigs / mud fluid drilling medium / Freezing hole equipment: There are two columns of tubing – 1. Outside: 102 to 152m. 2. Inside : 32 to 51mm (steel) or (polyethylene)* * Polyethylene has an advantage over steel because: • It has a lower weight. • It is cheaper. • It is easier to install. • It has a lower thermal conductivity. • Specific gravity is same as the brine. We hence prefer polyethylene more over steel for the tubing purpose.
  • 14. Process: Freezing brine flows at high velocity down the inner pipe. It rises more slowly in the annulus absorbing heat from the surrounding rocks.  The type of flow is different depending on the region of flow. There are basically two flow regions: 1. Moderate depths  Laminar flow. 2. Deeper regions/clay/organic  Turbulent flow.  It needs 2 to 8 months time for freezing. The freezing in the moderate depths take place at round two months while those in the deeper regions take longer time up to 8 months.  Holes of larger diameter are needed for greater depths.  Complete tightness of joints among individual segments of pipes is necessary. *Gases used and the temperature at which they are used to serve the purpose: 1. Ammonia (NH3): (-)20o C – For one stage compression. (-)40oC – For double stage compression. 2. Carbon Dioxide (CO2): Used at (-)50oC.
  • 15. Periods: oActive: - 3 units min. full capacity till the desired frozen cylinder forms. oPassive: - Maintaining frozen rock mass at desired temperature during sinking & lining. 1/2 to 1/3 times the capacity is sufficient. Heat Losses: Heat from outside the frozen material. Losses in freezing installation due to imperfect insulation. Frost Penetration Velocity: - The penetration occurs at the rate of: (i) 25mm per day in sand. (ii) 10-15mm per day in clay. On a larger scale, the penetration rate is: (i) 2-4 months per 250 metres of depth (ii) 9-10 months per 500 metres of depth
  • 16. EQUIPMENT FOR SHAFT SINKING (A)Site preparation above HFL(100 years record) 1. Construction of roads and material storage areas 2. Grading of the terrain(while sinking also this can be done) 3. Water supply(drinking, industrial use and fire extinguishing) 80 - 120m3 / day 40 - 60m3 / day 80-100m3 / day plant water tap water fire tank ( adequate ditch for storm water ) 4. Electrical power supply(2 stages) Preparatory - 260 KVA transformers - Diesel generator stand bye Sinking - 1200 KVA, 500 V - Diesel generator stand bye 5. REQUIREMENTS:-  Storage space for material  Ramp for unloading heavy machinery  Telephone lines  Temperature buildings and head gear foundation  Installation of sinking equipment  Surveying of shaft elevation, centering
  • 17. (B) Temporary Buildings 1. Office, first aid room, heating and cooling units, ware house 2. Lamp house(in accordance with MSHA standards) 3. Mechanical and blacksmith shop(for minor repair work) 4. Compressor sheds 5. Transformer station 6. Shed for concreting, mucking and other equipment 7. Shed for cement storage 8. Winch building for shaft stage 9. Fan housing 10.Flammable supplies ware house 11.Hoist Buildings 12.Storage for explosives(Magazine) 13.Accommodation for sinking crew.
  • 18. 1) SHAFT COLLAR CONSTRUCTION(8-12m) • Air Channel • Channel for water pipes, air pipes • Ladder Compartment • Basement for pushers 2) D & B in Shafts : supposed to ensure- (a) Correct size and shape of planned excavation (b) Even shape of the surface (c) Uniform size of broken rock (d) Safe and economical operation 3) Mucking Shaft :- 50- 60% of cycle time Mucking ‘η’ Depth
  • 19. Muckers Several type of muckers are in use depending on- Shaft shape, size, depth and location 1. Scrapers- rectangular shafts large dia shafts (U/G bunkers) 2. Overshot loaders on caterpillars 3. Cryderman Muckers 4. Cactus Grab (light) 5. Cactus Grab (heavy) Central Pivot (1.3cu) Hanging from platform/hand guided Attached to shaft wall(3)type Large cap muckers for deep min/larger dia - electric, pneumatic or hydraulic Capacity:- Pt= 3600 k Vb / t where Pt = Thermal Capacity in cubic meter per hour k = Fill factor (0.8 to 0.9-sandstone 1.1 to 1.2-shale) Vb = Bucket Capacity in cubic meter t = mucking time  Lowering  Templing  Cleaning
  • 20. DEWATERING OF SHAFTS REQUIRED WHEN THERE IS: Intersection of water courses 1. Changing water inflow 2. Changing pump head 3. Changing rock and mud contained water 4. Periodic changes in positioning of devices WATER INFLOW into the shaft can be reduced by:  Pumping  Initial drainage / sealing / tapping
  • 21. DEVICES FOR PUMPING  KIBBLES: Capacity:3cum/min Depth- upto 150 m Two types of kibbles- normal kibbles and special kibbles  Face pumps: based on compressed air principle  Centrifugal pumps  Reciprocating pumps- higher pumping head -but they make a lot of noise  Multistage pumps: stationary pumps in convention with face pumps uses stage pumping  Hanging pumps:-used to control large inflows - pumping head of 200-400m
  • 22. DEVICES FOR PUMPING  Intermediate pump: especially for deep shafts  Airlifts:-powered by compressed air -most popular for small depths Two main system for these pumps are: i. parallel:- where the air pipe runs beside the water pipe ii. concentric:-where the air pipe is inside the water pipe t. Pumps Deep/ Stages/overflow chamber 3 combinaton
  • 23. Equipment Nos. • Winders -400Kw-6600v 1 Main One Mineral BB-3000 • BB-2200-130kw-500v 1 Auxiliary One Man Winder • Fans -6kw/500m3 2 • Air Compressors- 2 • Winches Sufficient No. • Housing/Pumps • Shaft Fittings (1)Burtons (2)Ventilator Tubes (700mmø) (3)Pipe Line for Concrete (4)Compressed Air Tanks (5)Steel Shutters (6)Brackets (7)Ropes for Winders (8)Winches (9)Hoisting Buckets (1.25m3/2 m3 ) (10)Grab (11)Grab Loaders (12)Drilling Machines (13)Lighting Arrangement. • Pumping Accessories • Scaffolding • Shotcreting Equipment (mixer/nozzle/pipeline) • Exploder
  • 24. Purpose 1) Production 2) Service 3) Ventilation 4) Exploration 5) Escape 6) Combination Brakes:  Holding of hoist drum  Electrical (mechanical breaking system ) (Normal/emergency operation)  Electric breaking 1. Regenerative energy returned to system / induction generator developer 2. Breaking torque 3. Counter torque 4. Dynamic  Mechanical breaking 1. To slow down the drum 2. Holds the drum at rest Jaw /parallel motion /disk brakes –friction hoists Drum /friction hoists  Calliper brakes 1. Speed /force of breaks 2. Controlled by oil flow
  • 25. Drum hoist 1. Over wind /rope breakage 2. Safety dog Friction hoist Over wind: Arrestor Gear
  • 26. Ventilation Ducting is hung in the shaft by two steel ropes connected periodically to collars round the pipe. Lights -safety -output -flood light charters -suspended stage and tensor frame special reflector and sealed cover -hang on ropes(special cable) -100W lamps and even 40-50m of water.
  • 27.
  • 28. SHAFT DRILLING AND BORING  Boring of shafts/large diameter holes/ foundation of off-shore drilling.  Shaft sinking is slow, tedious, hazardous and uncomfortable.  Drilling is possible up to depths 1000m.  Diameter - 10m  Weak and moderate - Strength rock (300MPC)  Cope with difficult hydro geological conditions. STEPS IN DESIGNING  Geotechnical and hydro geological parameters.  Planned shaft diameter, depth, adequate cutters for the type of rock, stages of reams and properties of drilling fluid.  Design of shaft head.  Living placement methodology/sealing.  Sealing of water.  Organization of the drilling site, location of ponds, storage of living components. DRILLING FLUID Water and natural clay / SG - 1.15 to 1.25
  • 29. DRILLING EQUIPMENT Drilling equipment consists of Heavy drill rigs having sufficient capacity to provide the required torque and the hoisting capacity. Ex: - CSD 300 (Hughes Micon) 6 Hydraulic motors, 70 KNm Torque Shaft Alignment is 1 in 1000 CUTTERS • Milled steel tooth cutters - Soft rock • Tungsten carbide cutters - harder rock (abrasive) • Disk cutters - not needed for (blind hole drilling) LINING 200mm/ Shot Crete / Bolts / Wire mesh/ concrete/prepared and placed.
  • 30. SHAFT BORING • New / least matured (1960’s) • SBM’s (vertical TBM’s)(personnel travel log inboard) • Picking up the cutting is the major problem. • Wirth m/c - successful with pilot hole for free much removal to a lower face. • Blind shafts were driven with limited success only. • SBM’s (2cutter motors of 261 KW / disc cutters) • Carboniferous rock is the most suited one. • Grouting of water bearing strata is mandatory before shaft boring. SHAFT RAISING • Raise boring m/c’s in place of conventional methods are common today • Raise climbers • Lower level is developed • When sinking is not possible due to lack of space or lack of room for production • Only on competent rocks • Without water inflow
  • 31. ADVANTAGES  Influence on mine performance is minimum  Loading of muck into buckets is avoided  Blasting efficiency is greater  No water pumping is required DISADVANTAGES  Height of rising limited (100 to 120m)  Ladder climbing inconvenient for men and material transport.  Potential hazard of pieces of rock falling from face  Potential threat of much jamming on chute  Surveying is difficult  Time and cost for preparing the opening for raising purpose.
  • 32. EQUIPMENT  Chute  Hoist  Ladder  Brattice  Heavy load bearing wooden platform with steel girders  F.O.S - 6  Face to platform 1.5m-3.0m, 5m(at a go) (in strong rocks)  Ventilation through a (200 - 300m) diameter hole drilled above. ALTERNATIVES (3)  Raising the diameter up to 4m(Temperature/permanent)  Permanent lining is done at every short interval.  Diameter > 4m. Pilot hole is then widened.
  • 33. MECHANICAL RAISE CLIMBERS:  For hard rock (Alimah- Swedish)  Runs on a guide rail (Pin rock) (through rock bolts) ADVANTAGES:  Permits the driving of very long raises, vertical or inclined, straight or curved.  When travelling to the head of the raise, personnel are well protected in a cage under the platform.  Miners work on a platform whose height/angles can be adjusted.  Risks of gases are reduced(through ventilation)  All the material can be transported easily.  Timbering avoided / rock bolting and mesh may be used.  Usable up to 8m2 area. DISADVANTAGES:  Cost for short stretches not justified.