SlideShare ist ein Scribd-Unternehmen logo
1 von 5
Downloaden Sie, um offline zu lesen
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 123
AN EMPIRICAL STUDY ON KEY DETERMINANTS OF CONSTRUCTION
DELAY
E.Abinayasri1, Dr.S.Anandakumar2, Dr.V.Krishnamoorthy3
1Final year M.E., Department of Civil Engineering, Kongu Engineering College,Perundurai, India
2 Professor and Head ,Department of Civil Engineering, Kongu Engineering College, Perundurai, India
3 Assistant Professor ,School of management Studies, Kongu Engineering College, Perundurai, India
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - The purpose of this study is to investigate the
causes of construction delay and its impact on client
dissatisfaction. The factors are identified from literature
and using these factors questionnaire is prepared and it
consists of total of 40 factors causing delay. In order to
collect data from the respondents, questionnaire method is
used. The structured questionnaire form is send to various
construction companies through email. This studyhasbeen
conducted in and around Erode districtforaperiodofseven
months from July 2016 to January 2017. The study
identified nine dimensions of construction delay.
Key Words: design, equipment, personal,
manpower, experience, government, material,
finance, owner.
1.INTRODUCTION
Delay factors are considered to be significant role in the
delivery of a construction project on time, within budget
and at the required quality [26]. The success of the
construction project requires sound strategies, good
practices and careful judgement for completion ofproject
on schedule and with estimates cost [1]. Delays are the
most common and costly problem encountered on
construction projects. Construction delays are significant
part of the project’s construction life. Even with present
advanced technology, and management understandingof
project management techniques, construction delay
projects continue to suffer incase of delays and project
completion dates. The major reasons for delay includes
strikes, rework,deficitorganization,shortageofmaterials,
machinery failure, change orders. Delays are costly to all
parties involving in the construction industry and often
result in litigation. The time and expense incurred to
produce a claims document initselfissubstantial.Thereis
room for improvement in present practices for keeping
track of delays. Therefore, introducing a exible and more
accurate delay analysis technique can be valuable [23].
2. REVIEW OF LITERATURE
The following are the overview of literatures collected
from past research and studies. The most noteworthy of
them are relevant to the current study are being
reviewed.
Adnan Enshassi et al (2016) assess the factors leading
to time and cost overruns in construction projects, Gaza
Strip. The survey included 110 delay factors, 42 cost
overrun factors. This study concluded that the major
causes could beremovedby bettermanagementpractices.
Remon F. Aziz et al (2016) lists the construction delay
causes. The questionnaire was prepared and distributed
to 500 construction from the identified 293 delay causes.
Relative Importance Index (RII). The most contributing
causes and groups to delays were identified, and some
future suggestions were proposed.
Majed Alzara et al (2016) identifies the major causes of
project delays in northern Saudi Arabia The delay factors
were collected from the University ProjectsDirector were
then compared to Saudi construction projects. It gives a
solution to minimize delay factors and improve its
performance using Performance Information
Procurement System.
Samer Alsharif and Aslihan Karatas (2016) analyzed a
framework for identifying causal factors of delay for
operable nuclear power plants projects.
Greeshma b Suresh and Dr.S.Kanchana (2015) had
done a study on quantification of delay factors in
construction industry in Kerala region. Top 10 major
causes of construction delays in constructionindustryare
identified.
Prakash Rao and Joseph CamronCulas(2015) outlines
the major causes of construction delays, the effects of
delays, and methods of minimizing construction delays.
Site management and supervision, effective strategic
planning, and clear information and communication
channel are the methods to minimize delays.
Michal Gluzak and Agnieszka Lesniak (2015) outlines
the findings of a survey aimed at identifying the most
important causes of delaysinconstructionworksfromthe
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 124
client’s perspective. A factor analysis was allow to
interpret the dependencies between them.
K.L.Ravisankar et al (2014) conducted a study on the
quantification of delay factors in construction industry.
The questionnaire is formed consisting of total 50 delay
factors and is sent to various construction companies by
email and in by personal.
3. RESEARCH GAP
Although several studies have been conducted with
regard to study on key determinants of construction
delay, most of the studies havebeenconductedinwestern
perspective. Only few studies have been conducted in
Indian context. Therefore the researcher would like to fill
the gap by way of studying the engineers, supervisor’s
views on construction delays.
With this background, the researcheres intend to identify
the various dimensions of construction delay.
4. RESEARCH METHODOLOGY
4.1 Scope
The scope of the study is confined only to the engineer’s,
supervisor’s views on construction delays in Erode
district.
4.2 Period of study
The period of study is conducted during the period of
September 2016 to January 2017.
4.3 Data collection methods
Primary data collection was done through questionnaire
method. The first part of the questionnaire consists of the
demographic profile of the respondents. The second part
of the questionnaire was relating to factors that causes
delay in construction sites.
4.4 Sampling method
The researchers adopted convenience sampling method
for collecting data from the respondents.
Table-1: Number of questionnaire’s distributed and
received
S.No. Taluks in
erode
Distributed
questionnaire’s
Received
response
Response
rate
1 Erode 45 30 66%
2 Perundurai 45 30 67%
3 Modakkurichi 40 20 50%
4 Kodumudi 35 20 57%
5 Sathy 20 10 50%
6 Bhavani 20 15 75%
7 Anthiyur 15 12 67%
8 Gobi 40 35 78%
9 Thalavadi 10 6 60%
10 Total 250 178 65%
4.5 Construct development
The variables relating to the present study is drawn from
the previous work done by-(Shebob et al, 2007), (Adnan
Enshassi et al, 2016), (Sabah Alkass et al, 1996), (Arshi
Shakeel Faridi et al, 2006), (Sadi A. Assaf and Sadiq Al-
Hejji, 2006),(Remon F. Aziz et al 2016),(Greeshma b
Suresh and Dr.S.Kanchana 2015).Suitable modification
was made in the existing questionnaire to suit the
requirements of the current study.
4.6 Descriptive statistics
The demographic profile in the questionnairefeaturesthe
experience level of the respondent,theirsalarylevel,their
level of designation in the department they are working
in. The total survey was conducted in 250 out of whom
only 178 questionnaires could be collected. The response
rate of the survey was 65 percent. The survey were
conducted among deputy managers, structural engineers,
quantified engineers, safety officers,designengineers,site
engineers, supervisors, assistant engineers.
5. ANALYSIS AND DISCUSSIONS
5.1 Reliability statistics
.
There is a number of diverse methods towardsevaluating
reliability of a scale. In this study the method hired is
cronbach‟s reliability.
Cronbach‟s α is the most normally used procedure to
estimate reliability. It is highly precise and has the
advantage of only requiring a single application of the
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 125
scale. Hence cronbach‟s α was obtainedandfoundto beof
adequate magnitude[16].
Table-2: Reliability Statistics
Cronbach's Alpha N of Items
.901 40
Table-3: Reliabilities of various dimensions of
construction delay
S.No. Dimensions Reliability statistics
1
Design
0.89
2
Equipment
0.86
3 Personal 0.85
4 Manpower 0.852
5 Experience 0.845
6 Government 0.862
7 Material 0.898
8 Finance 0.875
9 Owner 0.862
5.2 Exploratory factor analysis
The researcher studiedthe measureddelayitemsbyusing
exploratory factor analysis via principal component
analysis in order to examine whether the items in fact
measure the pre-specified constructs.
Prior to conducting the factor analysis, the two testswere
achieved in order to check the possible existenceofmulti-
collinearity or correlation among the items and the
appropriateness of factor analysis. Initially, inspection of
the correlation matrix exposed the presence of many
coefficients of 0.3 and above, which supports the
factorability of the correlation matrix .Then, to verify if
the dataset was appropriate for factor analysis, the
Kaiser-Meyer-Olkin(KMO) measureofsamplingadequacy
value has to be equal to, or greater than, 0.6 and that the
Barlett’s test of sphericity value is important, where the
significant value should be 0.05 or smaller. However, for
this study, the KMO value is 0.652 and Bartlett’s test is
significant therefore, it is appropriate to conduct the
factor analysis.
Table -4: KMO and Bartlett's Test
Kaiser-Meyer-Olkin Measure of Sampling Adequacy. 0.652
Bartlett's Test of Sphericity
Approx. Chi-Square 1110.3
Df 378
Sig. 0.000
The next stage of analysis was to evaluate the delay
elements. In order to examine whether the items of a
construct shared a single underlying factor and to
establish the discriminant validity oftheconstructsunder
investigation, an exploratory factor analysis (EFA) was
achieved.
Exploratory factor analysis using a principal component
analysis (PCA). Varimax with Kaiser normalisation was
applied prior to factor rotation, thus keeping factors with
an eigenvalue of 1 or greater.
The 40 items measured the key determinants of
construction delay in and around Erode district. The
research model is subjectedtothePCAusingSPSSVersion
16. The exploratory factor analysis of delay reveals the
presence of 9 components with eigenvalues exceeding 1;
these 9 components accounted for 69.657 per cent of the
total variance.
The underlying factors were labelled as follows:
Factor 1: Design – This encompasses 6 items that
represent 27.940 percentofthevariance. Theitemsareall
related to delay in construction industry.
Factor 2: Equipment – This includes 6 items that account
for 7.454 per cent of the variance. This itemdealswiththe
importance of support from the top management for
reducing delay in construction industry and to enhance
quality practices and for achieving company excellence.
Factor 3: Personal – This consists of 6 items. This
construct focuses on the construction qualityinformation
that influences company performance. This factor
signifies 6.633 per cent of the variance.
Factor 4: Manpower – This comprises 4 items that deal
with the importance of management of materials. It
accounts for 5.928 per cent of the variance.
Factor 5: Experience– This includes 4 items that are
associated key determinants of delay in construction
industry. This factor explains 5.4 percent of the variance.
Factor 6: Government – This includes 2 items that are
related to the practice of delay as a means of attaining
high standards of organisational performance.Thisfactor
explains 4.903 per cent of the variance.
Factor 7: Material –This component accounts for 4.409
per cent of the variance with 4 items.
Factor 8: Finance– Only 1 item are included in this
component.This component is significant with factor
explains 3.817 per cent of the variance.
Factor 9: Owner– Here 7 items are included. This
component is significant with factor explains 3.173 per
cent of the variance [8].
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 126
Table -5: Total Variance explained
S.No.
Factors
Initial
Eigen
Values
Variance
Explained
Cumulative
Percent
1 Design 10.33 27.940 27.940
2 Equipment 2.758 7.454 39.394
3 Personal 2.454 6.633 42.028
4 Manpower 2.193 5.928 47.956
5 Experience 1.998 5.400 53.356
6 Government 1.814 4.903 58.258
7 Material 1.631 4.409 62.667
8 Finance 1.412 3.817 66.484
9 Owner 1.174 3.173 69.657
Initially, all the 40 variables were used. After rejecting
those items that have inadequate loadings, we reduced to
nine factors. The identified factors explainpercentoftotal
variance. The factors are named as follows:
 Design related factors
 Equipment related factors
 Personal related factors
 Manpower related factors
 Experience related factors
 Government related factors
 Material related factors
 Finance related factors
 Owner related factors
6. CONCLUSIONS
The purpose of this study was to identify the important
dimensions of construction delay. For this, the
researchers employed exploratory factor analysis. This
study identified nine dimensions. These are design,
equipment,personal,manpower,experience,government,
material, finance, owner. These study findingswouldhelp
the policy makers to identify the important dimensionsof
construction delay. Eventhough thestudyhasachievedits
objectives, it has certain limitations (i.e) the researchers
adopted convenient sampling method. In future, similar
study could be conducted by adopting some other
sampling methods. This study adopted only exploratory
factor analysis for identifying important dimensions of
construction delay and in future confirmatory factor
analysis could be used.
REFERENCES
[1] Adan Enshassi (2009), ‘Delays and cost overruns in
the construction projects in the Gaza Strip’, Journal
of Financial Management of property and
Construction, Vol.14 No.02, pp. 126-151.
[2] Arshi Shakeel Faridi and Sameh Monir El-Sayegh
(2006), ‘Significant factors causing delayingtheUAE
construction industry’, Journal of Construction
Management and Economics, Vol.24,pp.1167-1176.
[3] Arshi Shakeel Faridi and Sameh Monir El‐Sayegh
(2006), ‘Significant factors causing delay in the UAE
construction industry’, Construction Management
and Economics, Vol. 24, pp. 1167-1176.
[4] Ayman H and Al-Momani (2000), ‘Construction
delay: a quantitative analysis’, International Journal
of Project Management, Vol. 18, pp. 51-59.
[5] Charles Teye Amoatey, Yaa Asabea Ameyaw,
Ebenezer Adaku and Samuel Famiyeh (2015),
‘Analysing delay causes and effectsinGhanaianstate
housing construction projects’,International Journal
of Managing Projects in Business, Vol.8,pp.198-214.
[6] David Cooke Thomas Rohleder Paul Rogers, (2010),
‘A dynamic model of the systemic causes for patient
treatment delays in emergency departments’,
Journal of Modelling in Management, Vol.5, pp. 287 -
301.
[7] Greeshma B Suresh and Dr. S. Kanchana (2015) ‘A
study on quantification of delay factors in
construction industry (Kerala region)’ International
journal on engineering technology and sciences, vol.
2, pp. 96-103.
[8] Hayati Habibah Abdul Talib Khairul Anuar Mohd Ali
Fazli Idris (2014),’Critical success factors of quality
management practices among SMEs in the food
processing industry in Malaysia’, Journal of Small
Business and Enterprise Development, Vol. 21, pp.
152 – 176.
[9] Ibrahim Mahamid (2011), ‘Risk matrix for factors
affecting time delay in road construction projects:
owners' perspective’, Engineering Construction and
Architectural Management, Vol. 18, pp. 609 – 617.
[10] Kikwasi, G.J (2012), ‘Causesandeffectsofdelaysand
disruptions in construction projects in Tanzania’,
Australasian Journal of Construction Economics and
Building, Conference Series, Vol.1, pp. 52-59.
[11] Majed Alzara, Jacob Kashiwagib, Kashiwagic,
Abdulrahman Al-Tassand (2016), ‘Using PIPS to
minimize causes of delay in Saudi Arabian
construction projects: university case study’
International Conference on Sustainable Design,
Engineering and Construction, pp. 932 – 939.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 127
[12] Michal Gluzak and Agnieszka Lesniak (2015),
‘Construction delays in clients opinion –multivariate
statistical analysis’ Creative Construction
Conference, Vol.123, pp. 182 – 189.
[13] Mohamed M. Marzouk and Tarek I. El-Rasas (2014),
‘Analyzing delay causes in Egyptian construction
projects’. Journal of Advancer Research, Vol. 5, pp.
49-55.
[14] Murali Sambasivan and Yau Wen Soon (2006),
‘Causes and effects of delays in Malaysian
construction industry’, Graduate School of
Management, Vol.25, pp. 517-526.
[15] N. Hamzaha, M.A. Khoirya, I. Arshada, N. M. Tawilb
and A. I. Che Anib (2011), ‘Cause of Construction
Delay – Theoretical Framework’, The 2nd
International Building Control Conference, Vol. 20,
pp. 490-495.
[16] Nunnally J.C. (1978),Psychometric Theory,McGraw-
Hill, New York, NY.
[17] Pablo Gonzalez, Vicente González, Keith Molenaar
and Francisco Orozco(2013), ‘Analysis of Causes of
Delay and Time Performance in Construction
Projects’, Journal of Construction Engineering
Management, Vol. 140, pp.1-9.
[18] Prakash Rao and Joseph Camron Culas (2014),
‘Causes of delay in construction projects- review
article’ International journal ofcurrent research,Vol.
6, pp.7219-7222.
[19] Ravisankar, K.L, S. Ananda Kumar and V.
Krishnamoorthy (2014), ‘Studyonthe quantification
of delay factors in construction industry’
International journal of emerging technology and
advanced engineering, Vol.4, pp.105-113.
[20] Remon F. Aziz and Asmaa A. Abdel-Hakam (2016),
‘Exploring delay causesofroadconstructionprojects
in Egypt’, Alexandria Engineering Journal, pp. 4-25.
[21] Remon Fayek Aziz (2013), ‘Ranking of delay factors
in construction projects after Egyptian revolution’,
Alexandria EngineeringJournal,Vol.52,pp.387-406.
[22] Sabah Alkass, Mark Mazerolle and Frank Harris
(1996), ‘Construction delay analysis techniques’,
Construction Management and Economics, Vol. 14,
pp. 375- 394.
[23] Sadi A. Assaf and Mohammed Al-Khalil (1995),
‘Causes of delay in large building construction
projects’, Journal of Management in Engineering,
Vol.11 No.2, pp. 45-50.
[24] Sadi A. Assaf, Mohammed AI-Khalil and Muhammad
AI-Hazmi (2006), ‘Causes of delay in large
construction projects’, International Journal of
Project Management, Vol. 24, pp. 349-357.
[25] Samer Alsharif and Aslihan Karatas (2016), ‘A
Framework for IdentifyingCausal FactorsofDelayin
Nuclear Power Plant Projects’ International
Conference on Sustainable Design, Engineering and
Construction, pp. 1486 – 1492.
[26] Shebob, N. Dawood, R.K. Shah and Q. Xu (2012),
‘Comparitive study of delay factors in Libyanandthe
UK construction industry’, International Journal of
Construction Engineering and Architectural
Management, Vol.19 No.06, pp. 688-712.

Weitere ähnliche Inhalte

Was ist angesagt?

Bx2423262330
Bx2423262330Bx2423262330
Bx2423262330
IJMER
 
Improvement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal regionImprovement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal region
eSAT Publishing House
 
A practical approach to eliminate defects in gravity die cast al alloy castin...
A practical approach to eliminate defects in gravity die cast al alloy castin...A practical approach to eliminate defects in gravity die cast al alloy castin...
A practical approach to eliminate defects in gravity die cast al alloy castin...
eSAT Journals
 

Was ist angesagt? (20)

IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
 
IRJET- Development of Conceptual Model for Effective Selection of Subcontract...
IRJET- Development of Conceptual Model for Effective Selection of Subcontract...IRJET- Development of Conceptual Model for Effective Selection of Subcontract...
IRJET- Development of Conceptual Model for Effective Selection of Subcontract...
 
Application of Quality Tools in Manufacturing Industries in simple ways: A Ca...
Application of Quality Tools in Manufacturing Industries in simple ways: A Ca...Application of Quality Tools in Manufacturing Industries in simple ways: A Ca...
Application of Quality Tools in Manufacturing Industries in simple ways: A Ca...
 
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
 
Senstivity Analysis of Project Scheduling using Fuzzy Set Theory
Senstivity Analysis of Project Scheduling using Fuzzy Set TheorySenstivity Analysis of Project Scheduling using Fuzzy Set Theory
Senstivity Analysis of Project Scheduling using Fuzzy Set Theory
 
IRJET- Construction Equipment Monitoring: By using Relative Important Ind...
IRJET-  	  Construction Equipment Monitoring: By using Relative Important Ind...IRJET-  	  Construction Equipment Monitoring: By using Relative Important Ind...
IRJET- Construction Equipment Monitoring: By using Relative Important Ind...
 
Bx2423262330
Bx2423262330Bx2423262330
Bx2423262330
 
IRJET- Real Time Construction and Analyze of School Building at Nagapattinam
IRJET- Real Time Construction and Analyze of School Building at NagapattinamIRJET- Real Time Construction and Analyze of School Building at Nagapattinam
IRJET- Real Time Construction and Analyze of School Building at Nagapattinam
 
Improvement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal regionImprovement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal region
 
Multivariate approach to benchmarking quality prediction parameters in buildi...
Multivariate approach to benchmarking quality prediction parameters in buildi...Multivariate approach to benchmarking quality prediction parameters in buildi...
Multivariate approach to benchmarking quality prediction parameters in buildi...
 
A practical approach to eliminate defects in gravity die cast al alloy castin...
A practical approach to eliminate defects in gravity die cast al alloy castin...A practical approach to eliminate defects in gravity die cast al alloy castin...
A practical approach to eliminate defects in gravity die cast al alloy castin...
 
IRJET- Analysis of Ceiling Cable Holder Base
IRJET- Analysis of Ceiling Cable Holder BaseIRJET- Analysis of Ceiling Cable Holder Base
IRJET- Analysis of Ceiling Cable Holder Base
 
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
 
Time, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast BuildingsTime, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast Buildings
 
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
 
Bf34357368
Bf34357368Bf34357368
Bf34357368
 
IRJET- Quality Assurance & Project Scheduling for Residential Building
IRJET-  	  Quality Assurance & Project Scheduling for Residential BuildingIRJET-  	  Quality Assurance & Project Scheduling for Residential Building
IRJET- Quality Assurance & Project Scheduling for Residential Building
 
INVESTAGATION OF THE PROCESS CAPABILITY OF WATER PUMP PLASTIC COVER MANUFACTU...
INVESTAGATION OF THE PROCESS CAPABILITY OF WATER PUMP PLASTIC COVER MANUFACTU...INVESTAGATION OF THE PROCESS CAPABILITY OF WATER PUMP PLASTIC COVER MANUFACTU...
INVESTAGATION OF THE PROCESS CAPABILITY OF WATER PUMP PLASTIC COVER MANUFACTU...
 
IRJET-Understanding the Structural Audit
IRJET-Understanding the Structural AuditIRJET-Understanding the Structural Audit
IRJET-Understanding the Structural Audit
 
IRJET-A Review on Precast Concrete
IRJET-A Review on Precast ConcreteIRJET-A Review on Precast Concrete
IRJET-A Review on Precast Concrete
 

Ähnlich wie An empirical study on key determinants of construction Delay

Ähnlich wie An empirical study on key determinants of construction Delay (20)

Delay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodDelay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index Method
 
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
 
Time delay and cost escalation in construction works
Time delay and cost escalation in construction worksTime delay and cost escalation in construction works
Time delay and cost escalation in construction works
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
 
IRJET- Identification of Crucial Factor Affecting to Sustainable Construc...
IRJET-  	  Identification of Crucial Factor Affecting to Sustainable Construc...IRJET-  	  Identification of Crucial Factor Affecting to Sustainable Construc...
IRJET- Identification of Crucial Factor Affecting to Sustainable Construc...
 
Antecedents Of Migrated Construction Workers Stress – An Indian Perspective
Antecedents Of Migrated Construction Workers Stress – An Indian PerspectiveAntecedents Of Migrated Construction Workers Stress – An Indian Perspective
Antecedents Of Migrated Construction Workers Stress – An Indian Perspective
 
­­Construction Quality Auditing
­­Construction Quality Auditing­­Construction Quality Auditing
­­Construction Quality Auditing
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road project
 
Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...
Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...
Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...
 
IRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction ProjectIRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction Project
 
D012261521
D012261521D012261521
D012261521
 
IRJET- A Review Paper on Lean Management in Construction Sites
IRJET-  	  A Review Paper on Lean Management in Construction SitesIRJET-  	  A Review Paper on Lean Management in Construction Sites
IRJET- A Review Paper on Lean Management in Construction Sites
 
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
 
IRJET- Improvement of Labour Productivity in Construction Industry- Review
IRJET- Improvement of Labour Productivity in Construction Industry- ReviewIRJET- Improvement of Labour Productivity in Construction Industry- Review
IRJET- Improvement of Labour Productivity in Construction Industry- Review
 
Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis
 
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
 
Developing an effective workflow module for productivity analysis using stati...
Developing an effective workflow module for productivity analysis using stati...Developing an effective workflow module for productivity analysis using stati...
Developing an effective workflow module for productivity analysis using stati...
 
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction Project
 

Mehr von IRJET Journal

Mehr von IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Kürzlich hochgeladen

Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
jaanualu31
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 

Kürzlich hochgeladen (20)

Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptx
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 

An empirical study on key determinants of construction Delay

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 123 AN EMPIRICAL STUDY ON KEY DETERMINANTS OF CONSTRUCTION DELAY E.Abinayasri1, Dr.S.Anandakumar2, Dr.V.Krishnamoorthy3 1Final year M.E., Department of Civil Engineering, Kongu Engineering College,Perundurai, India 2 Professor and Head ,Department of Civil Engineering, Kongu Engineering College, Perundurai, India 3 Assistant Professor ,School of management Studies, Kongu Engineering College, Perundurai, India ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - The purpose of this study is to investigate the causes of construction delay and its impact on client dissatisfaction. The factors are identified from literature and using these factors questionnaire is prepared and it consists of total of 40 factors causing delay. In order to collect data from the respondents, questionnaire method is used. The structured questionnaire form is send to various construction companies through email. This studyhasbeen conducted in and around Erode districtforaperiodofseven months from July 2016 to January 2017. The study identified nine dimensions of construction delay. Key Words: design, equipment, personal, manpower, experience, government, material, finance, owner. 1.INTRODUCTION Delay factors are considered to be significant role in the delivery of a construction project on time, within budget and at the required quality [26]. The success of the construction project requires sound strategies, good practices and careful judgement for completion ofproject on schedule and with estimates cost [1]. Delays are the most common and costly problem encountered on construction projects. Construction delays are significant part of the project’s construction life. Even with present advanced technology, and management understandingof project management techniques, construction delay projects continue to suffer incase of delays and project completion dates. The major reasons for delay includes strikes, rework,deficitorganization,shortageofmaterials, machinery failure, change orders. Delays are costly to all parties involving in the construction industry and often result in litigation. The time and expense incurred to produce a claims document initselfissubstantial.Thereis room for improvement in present practices for keeping track of delays. Therefore, introducing a exible and more accurate delay analysis technique can be valuable [23]. 2. REVIEW OF LITERATURE The following are the overview of literatures collected from past research and studies. The most noteworthy of them are relevant to the current study are being reviewed. Adnan Enshassi et al (2016) assess the factors leading to time and cost overruns in construction projects, Gaza Strip. The survey included 110 delay factors, 42 cost overrun factors. This study concluded that the major causes could beremovedby bettermanagementpractices. Remon F. Aziz et al (2016) lists the construction delay causes. The questionnaire was prepared and distributed to 500 construction from the identified 293 delay causes. Relative Importance Index (RII). The most contributing causes and groups to delays were identified, and some future suggestions were proposed. Majed Alzara et al (2016) identifies the major causes of project delays in northern Saudi Arabia The delay factors were collected from the University ProjectsDirector were then compared to Saudi construction projects. It gives a solution to minimize delay factors and improve its performance using Performance Information Procurement System. Samer Alsharif and Aslihan Karatas (2016) analyzed a framework for identifying causal factors of delay for operable nuclear power plants projects. Greeshma b Suresh and Dr.S.Kanchana (2015) had done a study on quantification of delay factors in construction industry in Kerala region. Top 10 major causes of construction delays in constructionindustryare identified. Prakash Rao and Joseph CamronCulas(2015) outlines the major causes of construction delays, the effects of delays, and methods of minimizing construction delays. Site management and supervision, effective strategic planning, and clear information and communication channel are the methods to minimize delays. Michal Gluzak and Agnieszka Lesniak (2015) outlines the findings of a survey aimed at identifying the most important causes of delaysinconstructionworksfromthe
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 124 client’s perspective. A factor analysis was allow to interpret the dependencies between them. K.L.Ravisankar et al (2014) conducted a study on the quantification of delay factors in construction industry. The questionnaire is formed consisting of total 50 delay factors and is sent to various construction companies by email and in by personal. 3. RESEARCH GAP Although several studies have been conducted with regard to study on key determinants of construction delay, most of the studies havebeenconductedinwestern perspective. Only few studies have been conducted in Indian context. Therefore the researcher would like to fill the gap by way of studying the engineers, supervisor’s views on construction delays. With this background, the researcheres intend to identify the various dimensions of construction delay. 4. RESEARCH METHODOLOGY 4.1 Scope The scope of the study is confined only to the engineer’s, supervisor’s views on construction delays in Erode district. 4.2 Period of study The period of study is conducted during the period of September 2016 to January 2017. 4.3 Data collection methods Primary data collection was done through questionnaire method. The first part of the questionnaire consists of the demographic profile of the respondents. The second part of the questionnaire was relating to factors that causes delay in construction sites. 4.4 Sampling method The researchers adopted convenience sampling method for collecting data from the respondents. Table-1: Number of questionnaire’s distributed and received S.No. Taluks in erode Distributed questionnaire’s Received response Response rate 1 Erode 45 30 66% 2 Perundurai 45 30 67% 3 Modakkurichi 40 20 50% 4 Kodumudi 35 20 57% 5 Sathy 20 10 50% 6 Bhavani 20 15 75% 7 Anthiyur 15 12 67% 8 Gobi 40 35 78% 9 Thalavadi 10 6 60% 10 Total 250 178 65% 4.5 Construct development The variables relating to the present study is drawn from the previous work done by-(Shebob et al, 2007), (Adnan Enshassi et al, 2016), (Sabah Alkass et al, 1996), (Arshi Shakeel Faridi et al, 2006), (Sadi A. Assaf and Sadiq Al- Hejji, 2006),(Remon F. Aziz et al 2016),(Greeshma b Suresh and Dr.S.Kanchana 2015).Suitable modification was made in the existing questionnaire to suit the requirements of the current study. 4.6 Descriptive statistics The demographic profile in the questionnairefeaturesthe experience level of the respondent,theirsalarylevel,their level of designation in the department they are working in. The total survey was conducted in 250 out of whom only 178 questionnaires could be collected. The response rate of the survey was 65 percent. The survey were conducted among deputy managers, structural engineers, quantified engineers, safety officers,designengineers,site engineers, supervisors, assistant engineers. 5. ANALYSIS AND DISCUSSIONS 5.1 Reliability statistics . There is a number of diverse methods towardsevaluating reliability of a scale. In this study the method hired is cronbach‟s reliability. Cronbach‟s α is the most normally used procedure to estimate reliability. It is highly precise and has the advantage of only requiring a single application of the
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 125 scale. Hence cronbach‟s α was obtainedandfoundto beof adequate magnitude[16]. Table-2: Reliability Statistics Cronbach's Alpha N of Items .901 40 Table-3: Reliabilities of various dimensions of construction delay S.No. Dimensions Reliability statistics 1 Design 0.89 2 Equipment 0.86 3 Personal 0.85 4 Manpower 0.852 5 Experience 0.845 6 Government 0.862 7 Material 0.898 8 Finance 0.875 9 Owner 0.862 5.2 Exploratory factor analysis The researcher studiedthe measureddelayitemsbyusing exploratory factor analysis via principal component analysis in order to examine whether the items in fact measure the pre-specified constructs. Prior to conducting the factor analysis, the two testswere achieved in order to check the possible existenceofmulti- collinearity or correlation among the items and the appropriateness of factor analysis. Initially, inspection of the correlation matrix exposed the presence of many coefficients of 0.3 and above, which supports the factorability of the correlation matrix .Then, to verify if the dataset was appropriate for factor analysis, the Kaiser-Meyer-Olkin(KMO) measureofsamplingadequacy value has to be equal to, or greater than, 0.6 and that the Barlett’s test of sphericity value is important, where the significant value should be 0.05 or smaller. However, for this study, the KMO value is 0.652 and Bartlett’s test is significant therefore, it is appropriate to conduct the factor analysis. Table -4: KMO and Bartlett's Test Kaiser-Meyer-Olkin Measure of Sampling Adequacy. 0.652 Bartlett's Test of Sphericity Approx. Chi-Square 1110.3 Df 378 Sig. 0.000 The next stage of analysis was to evaluate the delay elements. In order to examine whether the items of a construct shared a single underlying factor and to establish the discriminant validity oftheconstructsunder investigation, an exploratory factor analysis (EFA) was achieved. Exploratory factor analysis using a principal component analysis (PCA). Varimax with Kaiser normalisation was applied prior to factor rotation, thus keeping factors with an eigenvalue of 1 or greater. The 40 items measured the key determinants of construction delay in and around Erode district. The research model is subjectedtothePCAusingSPSSVersion 16. The exploratory factor analysis of delay reveals the presence of 9 components with eigenvalues exceeding 1; these 9 components accounted for 69.657 per cent of the total variance. The underlying factors were labelled as follows: Factor 1: Design – This encompasses 6 items that represent 27.940 percentofthevariance. Theitemsareall related to delay in construction industry. Factor 2: Equipment – This includes 6 items that account for 7.454 per cent of the variance. This itemdealswiththe importance of support from the top management for reducing delay in construction industry and to enhance quality practices and for achieving company excellence. Factor 3: Personal – This consists of 6 items. This construct focuses on the construction qualityinformation that influences company performance. This factor signifies 6.633 per cent of the variance. Factor 4: Manpower – This comprises 4 items that deal with the importance of management of materials. It accounts for 5.928 per cent of the variance. Factor 5: Experience– This includes 4 items that are associated key determinants of delay in construction industry. This factor explains 5.4 percent of the variance. Factor 6: Government – This includes 2 items that are related to the practice of delay as a means of attaining high standards of organisational performance.Thisfactor explains 4.903 per cent of the variance. Factor 7: Material –This component accounts for 4.409 per cent of the variance with 4 items. Factor 8: Finance– Only 1 item are included in this component.This component is significant with factor explains 3.817 per cent of the variance. Factor 9: Owner– Here 7 items are included. This component is significant with factor explains 3.173 per cent of the variance [8].
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 126 Table -5: Total Variance explained S.No. Factors Initial Eigen Values Variance Explained Cumulative Percent 1 Design 10.33 27.940 27.940 2 Equipment 2.758 7.454 39.394 3 Personal 2.454 6.633 42.028 4 Manpower 2.193 5.928 47.956 5 Experience 1.998 5.400 53.356 6 Government 1.814 4.903 58.258 7 Material 1.631 4.409 62.667 8 Finance 1.412 3.817 66.484 9 Owner 1.174 3.173 69.657 Initially, all the 40 variables were used. After rejecting those items that have inadequate loadings, we reduced to nine factors. The identified factors explainpercentoftotal variance. The factors are named as follows:  Design related factors  Equipment related factors  Personal related factors  Manpower related factors  Experience related factors  Government related factors  Material related factors  Finance related factors  Owner related factors 6. CONCLUSIONS The purpose of this study was to identify the important dimensions of construction delay. For this, the researchers employed exploratory factor analysis. This study identified nine dimensions. These are design, equipment,personal,manpower,experience,government, material, finance, owner. These study findingswouldhelp the policy makers to identify the important dimensionsof construction delay. Eventhough thestudyhasachievedits objectives, it has certain limitations (i.e) the researchers adopted convenient sampling method. In future, similar study could be conducted by adopting some other sampling methods. This study adopted only exploratory factor analysis for identifying important dimensions of construction delay and in future confirmatory factor analysis could be used. REFERENCES [1] Adan Enshassi (2009), ‘Delays and cost overruns in the construction projects in the Gaza Strip’, Journal of Financial Management of property and Construction, Vol.14 No.02, pp. 126-151. [2] Arshi Shakeel Faridi and Sameh Monir El-Sayegh (2006), ‘Significant factors causing delayingtheUAE construction industry’, Journal of Construction Management and Economics, Vol.24,pp.1167-1176. [3] Arshi Shakeel Faridi and Sameh Monir El‐Sayegh (2006), ‘Significant factors causing delay in the UAE construction industry’, Construction Management and Economics, Vol. 24, pp. 1167-1176. [4] Ayman H and Al-Momani (2000), ‘Construction delay: a quantitative analysis’, International Journal of Project Management, Vol. 18, pp. 51-59. [5] Charles Teye Amoatey, Yaa Asabea Ameyaw, Ebenezer Adaku and Samuel Famiyeh (2015), ‘Analysing delay causes and effectsinGhanaianstate housing construction projects’,International Journal of Managing Projects in Business, Vol.8,pp.198-214. [6] David Cooke Thomas Rohleder Paul Rogers, (2010), ‘A dynamic model of the systemic causes for patient treatment delays in emergency departments’, Journal of Modelling in Management, Vol.5, pp. 287 - 301. [7] Greeshma B Suresh and Dr. S. Kanchana (2015) ‘A study on quantification of delay factors in construction industry (Kerala region)’ International journal on engineering technology and sciences, vol. 2, pp. 96-103. [8] Hayati Habibah Abdul Talib Khairul Anuar Mohd Ali Fazli Idris (2014),’Critical success factors of quality management practices among SMEs in the food processing industry in Malaysia’, Journal of Small Business and Enterprise Development, Vol. 21, pp. 152 – 176. [9] Ibrahim Mahamid (2011), ‘Risk matrix for factors affecting time delay in road construction projects: owners' perspective’, Engineering Construction and Architectural Management, Vol. 18, pp. 609 – 617. [10] Kikwasi, G.J (2012), ‘Causesandeffectsofdelaysand disruptions in construction projects in Tanzania’, Australasian Journal of Construction Economics and Building, Conference Series, Vol.1, pp. 52-59. [11] Majed Alzara, Jacob Kashiwagib, Kashiwagic, Abdulrahman Al-Tassand (2016), ‘Using PIPS to minimize causes of delay in Saudi Arabian construction projects: university case study’ International Conference on Sustainable Design, Engineering and Construction, pp. 932 – 939.
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 02 | Feb -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 127 [12] Michal Gluzak and Agnieszka Lesniak (2015), ‘Construction delays in clients opinion –multivariate statistical analysis’ Creative Construction Conference, Vol.123, pp. 182 – 189. [13] Mohamed M. Marzouk and Tarek I. El-Rasas (2014), ‘Analyzing delay causes in Egyptian construction projects’. Journal of Advancer Research, Vol. 5, pp. 49-55. [14] Murali Sambasivan and Yau Wen Soon (2006), ‘Causes and effects of delays in Malaysian construction industry’, Graduate School of Management, Vol.25, pp. 517-526. [15] N. Hamzaha, M.A. Khoirya, I. Arshada, N. M. Tawilb and A. I. Che Anib (2011), ‘Cause of Construction Delay – Theoretical Framework’, The 2nd International Building Control Conference, Vol. 20, pp. 490-495. [16] Nunnally J.C. (1978),Psychometric Theory,McGraw- Hill, New York, NY. [17] Pablo Gonzalez, Vicente González, Keith Molenaar and Francisco Orozco(2013), ‘Analysis of Causes of Delay and Time Performance in Construction Projects’, Journal of Construction Engineering Management, Vol. 140, pp.1-9. [18] Prakash Rao and Joseph Camron Culas (2014), ‘Causes of delay in construction projects- review article’ International journal ofcurrent research,Vol. 6, pp.7219-7222. [19] Ravisankar, K.L, S. Ananda Kumar and V. Krishnamoorthy (2014), ‘Studyonthe quantification of delay factors in construction industry’ International journal of emerging technology and advanced engineering, Vol.4, pp.105-113. [20] Remon F. Aziz and Asmaa A. Abdel-Hakam (2016), ‘Exploring delay causesofroadconstructionprojects in Egypt’, Alexandria Engineering Journal, pp. 4-25. [21] Remon Fayek Aziz (2013), ‘Ranking of delay factors in construction projects after Egyptian revolution’, Alexandria EngineeringJournal,Vol.52,pp.387-406. [22] Sabah Alkass, Mark Mazerolle and Frank Harris (1996), ‘Construction delay analysis techniques’, Construction Management and Economics, Vol. 14, pp. 375- 394. [23] Sadi A. Assaf and Mohammed Al-Khalil (1995), ‘Causes of delay in large building construction projects’, Journal of Management in Engineering, Vol.11 No.2, pp. 45-50. [24] Sadi A. Assaf, Mohammed AI-Khalil and Muhammad AI-Hazmi (2006), ‘Causes of delay in large construction projects’, International Journal of Project Management, Vol. 24, pp. 349-357. [25] Samer Alsharif and Aslihan Karatas (2016), ‘A Framework for IdentifyingCausal FactorsofDelayin Nuclear Power Plant Projects’ International Conference on Sustainable Design, Engineering and Construction, pp. 1486 – 1492. [26] Shebob, N. Dawood, R.K. Shah and Q. Xu (2012), ‘Comparitive study of delay factors in Libyanandthe UK construction industry’, International Journal of Construction Engineering and Architectural Management, Vol.19 No.06, pp. 688-712.