THE CONSTRUCTION PROCEDURE AND ADVANTAGE OF THE RAIL CABLE-LIFTING CONSTRUCTION METHOD AND THE CABLE-HOISTING METHOD

International Journal of Technical Research & Application
International Journal of Technical Research & ApplicationInternational Journal of Technical Research & Application

The cable-hoisting method and rail cable-lifting method are widely used in the construction of suspension bridge. This paper takes a suspension bridge in Hunan as an example, and expounds the two construction methods, and analyzes their respective merits and disadvantages.

International Journal of Technical Research and Applications e-ISSN: 2320-8163,
www.ijtra.com Volume 3, Issue 4 (July-August 2015), PP. 21-23
21 | P a g e
THE CONSTRUCTION PROCEDURE AND
ADVANTAGE OF THE RAIL CABLE-LIFTING
CONSTRUCTION METHOD AND THE
CABLE-HOISTING METHOD
Ji Ce Zeng
School of civil engineering and architecture
Chongqing Jiaotong University
Chongqing, China
277199895@qq.com
Abstract:The cable-hoisting method and rail cable-lifting
method are widely used in the construction of suspension bridge.
This paper takes a suspension bridge in Hunan as an example,
and expounds the two construction methods, and analyzes their
respective merits and disadvantages.
Key words : suspension bridge rail cable-lifting
cable-hoisting
I. ENGINEERING SITUATION
The bridge is steel truss girder suspension bridge, the
main bridge spans to 900 meters, truss width is 27.0 meters,
truss height is 8 meters, approach bridge(5*30m) is designed
in south shore , another approach bridge(8*30m) is also
designed in north shore; both sides of the Straits are used with
gravity anchor, door-type reinforce concrete tower, dig
cast-in-place circular pile foundation.
Deck to the bottom of the River, vertical distance is about
200m, river width of maximum is 400m, accounting for the
main cross 44.4%, average slope rate of gully length is about
0.66 (height / length).
Lifting saddle is arranged in perpetual suspended cable,
which dose not occupy the sling steel truss connecting holes.
It is convenient for connection of cable head and segmental
beam. Meanwhile, it can reduce operation steps of removing
suspended saddle and installing the main girder when beam
section is being installed saddle. It is also can be able to
reduce the lifting height of steel truss girder and improve
construction efficiency.
II. CABLE-HOISTING CONSTRUCTION METHOD
A. Design of cable-hoisting system
The main cable crane spans to 900m, the side span is
155m in south shore, the side span is 258m in north shore,
both sides of the anchorage are anchored by gravity anchor.
The steel tower is assembled by steel tubes. The section
weight of steel truss girder is calculated by 160t.
Working principle of the cable crane machine is along
the cross bridge to arrange two sets of main cable, each main
cable is composed of steel wire rope 10 Phi 60.5, both ends of
which are anchored in the gravity anchor on both sides of
bridge. Each main cable respectively hangs the two supporting
car in midair. At both ends of the bridge, the traction winch
and lift winch pull lifting trolley in the bearing cable to roll
and lift steel truss girder, which makes girder construction
completed. There are 8 sports cars during the working frame
of the cable crane, and the erection of each section of the steel
truss girder is shared 4 sports cars (i.e., 4 lifting points) and
hoisted synchronously
Suspension rope design and related parameters of single cable
Project
Specification
for wire rope
(mm)
form for wire
rope
Unit weight
(kg.m﹣¹)
Breaking
tension(kN)
Modulus
elasticity
(MPa)
Load-bearing cable 10×Φ60.5 6×37S+IWR 1284.3 2075 10500
the sling Φ32 6×37S+IWR 389.0 546.5 10500
Traction cable 2×Φ36 6×37S+IWR 437.0 701.9 10500
B. Cable crane tower Cable crane tower is used in scheme that assembles
International Journal of Technical Research and Applications e-ISSN: 2320-8163,
www.ijtra.com Volume 3, Issue 4 (July-August 2015), PP. 21-23
22 | P a g e
steel pipe column in bridge tower, each tower with 4 Phi 600
* 10 is made of seamless steel pipe column, flat joint by phi
300 x 8 of the seamless steel pipe, bracing by Phi 200 x 8
seamless steel tube composed of space lattice system, which
plays a part in supporting in bridge cable tower, tower has
height of 13m. tower is made of the total amount of 54t steel.
Its material is Q345 steel. Steel tube tower is connected with
the tower frame, in order to increase the overall stability of
the tower. At the same time, a transverse eight wind is
designed, wind-bearing wire rope with 4 Phi 32 per bank is
selected. In order to reduce the longitudinal direction of the
bridge tower deviation, unilateral set Phi 60.5 pressure
tower wire rope.
C. Hoisting construction
Steel truss girder in assembling field is assembled,
when steel truss girder ships load- segment, with floating
box controlling the water-level, the top of floating box lies
alongside the wharf, and pressure from the ship's load levels
system position. At the same time, the floating box and
wharves should be fixed and connected, waiting for flat car
on board.
III. RAIL CABLE-LIFTING CONSTRUCTION
METHOD
A. Equipment And Assembling
The equipment mainly composed of the following parts:
beam-transporting trolley, saddle, cable, crane, zenith trolley,
a winch etc.
The beam-transporting trolley is the most core
equipment in this project, which composed of the pulley
group, the triangular distribution beam and the rectangular
distribution beam.
B. Saddle
The effect of cable saddle is to provide support, and
will convert load from cable to cable. The design of crane
saddle incorporate characteristics of pin type sling, with
moving the saddle to the direction of top and using the cable
clamp as a fulcrum to place it at the top, which make saddle
not occupy space of connecting hole of the lower cable
clamp. It also uses both sides of the longitudinal
positioning lock to ensure the lateral stability and it is
convenient for construction. The saddle is composed of a
longitudinal beam and a saddle beam.
C. Cable
Rail cable is considered as beam-transporting orbit and
the lifeline of the whole system, it is also the parts that has
highest safety risk coefficient. Its internal force changes
complexly and shows different characteristics on various
construction conditions, in order to meet need of its function
and have enough safety and operability, after calculating, the
staff used Phi 60 wire rope galvanized and sealed. Four
single, independent of each other, one end fixedly, one end
through the pulley group + keeping four rail cable force
basically the same and remain constant with counterweight
block.
D. Crane
The bridge had two sets of hydraulic loading crane for
lifting type cable, a cable carrier crane by a steel truss beam,
two pedrail-walking mechanism on the main cable, two sets
of hydraulic lifting equipment (including lifting and traction
jacks, hydraulic pump station, control system and steel wire
take-up device), with a lifting pole beam, power generation
equipment parts.
E. Construction Procedure
The installation and construction method of flexible
cable net steel truss beam is used for erection of steel truss
beam in the section of hoisting. The main construction steps
are:
1. The main cable and permanent slings are used for
supporting, horizontal cable is set up , with
anchored in the rock mass.
2. A steel pipe Bailey platform is built at the pile cap
on both sides, steel truss girder assembling
platform is made of Bailey platform and the rest
space of pile cap.
3. After lifting section that has been assembled, and
then those sections are suspended under the
carriage beam trolley.
4. Transporting vertically to the corresponding sling
by rail sling
5. The section of the steel truss girder is suspended
from the cable borne crane, and the carriage beam
carriage is exited.
6. Adjusting spatial position of the segment, and beam
butt has been installed, and pin sling.
7. The beam in mid of bridge is first installed and then
symmetrically installed from mid of bridge to the
sides of bank until the full bridge is linked.
The advantages of rail cable-lifting construction method
and cable-hoisting method
1. The assembling field of the steel truss is arranged
International Journal of Technical Research and Applications e-ISSN: 2320-8163,
www.ijtra.com Volume 3, Issue 4 (July-August 2015), PP. 21-23
23 | P a g e
on the platform. Compared with the cable hoisting,
it can reduce the lifting height of the steel truss
girder and the construction time, and improve the
safety of the construction. At the same time, two
pieces of steel truss girder can be installed, which
can shorten the construction time and bring the
recessive economic benefits.
2. Transport and erection of the steel truss girder have
high construction efficiency, cost savings.
3. The rail cable is used as the main cable as the
support, with the good wind stability, the quality of
construction can be controllable
4. Compared to the cables, rail cable needs less
bearing steel wire rope.
5. When using cable-hoisting method, it needs more
operators, and cable-hoisting system technology is
complex, it has high demands for the operation and
personnel quality . Rail cable has a high degree of
automation, it needs less operators when moving
the beam. Construction technology is stable, the
impact of environment is small, easy to
standardized operation.
IV. CONCLUSION
Rail cable-lifting construction method and
cable-hoisting construction method is more and more mature,
but there are still many places should be improved, such as
whether rail cable-lifting construction method can cancel
cable carrying crane or not, in terms with controlling the
main cable wire linearity in cable-hoisting construction
method
REFERENCES
[1]. Jianhui Lv. Hui Zhang. long span concrete filled steel tube
arch bridge cable-hoisting construction technology [J] -
Science and technology and engineering 2009,9 (4)
[2]. Shiming Liu. Yongjian Liu. Xiaorong Yao. concrete filled
steel tubular arch bridge cable- hoisting construction
optimization [J] - Highway Traffic Science and technology
in 2012, 29 (7)
[3]. Jinming Huang. cable hoisting system in steel truss arch
bridge hook in construction application [journal article] -
the western traffic science and technology 2012 (2)
[4]. Dong liang Zhou. Construction control study [J] highway
and 2012 trucks hoisting of long span arch bridge (1)
Huaqiang
[5]. Jian gen Lv. The main span of 368m Zhang Hui lifting
Maocaojie Bridge Construction Technology [J] 2009 rib
arch construction technology, 40 (2)
[6]. Zheng zhou Cao. Yu tao Feng. Chongqing Chaoyang
complex bridge hoisting cable tower, tower integration
research [J] 2010 (07) of bridge construction.
[7]. Jun wei Tian. large span concrete filled steel tubular arch
bridge construction control [J] highway and automotive
2012 rib hoisting (1)
[8]. Hong tian Du. Zhong Ming. concrete filled steel tube arch
bridge arch rib hoisting process temperature change on Rib
Alignment Effect [J] - Railway Standard arch design 2008
(3)
[9]. Jian hong LI . Jing Sheng. cable hoisting method of
reinforced concrete arch bridge construction error analysis
[J] - Sichuan building 2009,29 (6)

Recomendados

Bridge construction atlas von
Bridge construction atlasBridge construction atlas
Bridge construction atlasjose bonifacio de souza leite cuadros
1.1K views113 Folien
Steel truss ppt von
Steel truss pptSteel truss ppt
Steel truss pptSourav Pradhan
3.3K views35 Folien
Bridge construction methods aug 2007 von
Bridge construction methods aug 2007Bridge construction methods aug 2007
Bridge construction methods aug 2007jose bonifacio de souza leite cuadros
1.3K views107 Folien
Advanced Cable Stayed Bridge Construction Process Analysis with ANSYS von
Advanced Cable Stayed Bridge Construction Process Analysis  with ANSYS Advanced Cable Stayed Bridge Construction Process Analysis  with ANSYS
Advanced Cable Stayed Bridge Construction Process Analysis with ANSYS IJMER
890 views6 Folien
Railway over bridge von
Railway over bridgeRailway over bridge
Railway over bridgeSaurabhSingh20590
2.2K views32 Folien
4. STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE von
4.	STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE4.	STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
4. STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGEAELC
4.4K views14 Folien

Más contenido relacionado

Was ist angesagt?

Steel structures failure von
Steel structures failureSteel structures failure
Steel structures failureService_supportAssignment
1.7K views16 Folien
Railway engineering von
Railway engineeringRailway engineering
Railway engineeringHAMMAD BASHIR
965 views20 Folien
STATIC AND DYNAMIC ANALYSIS OF CABLE-STAYED SUSPENSION HYBRID BRIDGE & VALIDA... von
STATIC AND DYNAMIC ANALYSIS OF CABLE-STAYED SUSPENSION HYBRID BRIDGE & VALIDA...STATIC AND DYNAMIC ANALYSIS OF CABLE-STAYED SUSPENSION HYBRID BRIDGE & VALIDA...
STATIC AND DYNAMIC ANALYSIS OF CABLE-STAYED SUSPENSION HYBRID BRIDGE & VALIDA...IAEME Publication
505 views8 Folien
BUILDING STRUCTURE ASSIGNMENT 1 von
BUILDING STRUCTURE ASSIGNMENT 1BUILDING STRUCTURE ASSIGNMENT 1
BUILDING STRUCTURE ASSIGNMENT 1Nur Zaas
1.5K views84 Folien
Final report design of a pedestrian bridge - fall 2009 von
Final report   design of a pedestrian bridge - fall 2009Final report   design of a pedestrian bridge - fall 2009
Final report design of a pedestrian bridge - fall 2009Sanamau Waitogu
4K views119 Folien
Cable stay bridge construction von
Cable stay bridge constructionCable stay bridge construction
Cable stay bridge constructionBalkrishan Kushwah
5K views6 Folien

Was ist angesagt?(20)

STATIC AND DYNAMIC ANALYSIS OF CABLE-STAYED SUSPENSION HYBRID BRIDGE & VALIDA... von IAEME Publication
STATIC AND DYNAMIC ANALYSIS OF CABLE-STAYED SUSPENSION HYBRID BRIDGE & VALIDA...STATIC AND DYNAMIC ANALYSIS OF CABLE-STAYED SUSPENSION HYBRID BRIDGE & VALIDA...
STATIC AND DYNAMIC ANALYSIS OF CABLE-STAYED SUSPENSION HYBRID BRIDGE & VALIDA...
IAEME Publication505 views
BUILDING STRUCTURE ASSIGNMENT 1 von Nur Zaas
BUILDING STRUCTURE ASSIGNMENT 1BUILDING STRUCTURE ASSIGNMENT 1
BUILDING STRUCTURE ASSIGNMENT 1
Nur Zaas1.5K views
Final report design of a pedestrian bridge - fall 2009 von Sanamau Waitogu
Final report   design of a pedestrian bridge - fall 2009Final report   design of a pedestrian bridge - fall 2009
Final report design of a pedestrian bridge - fall 2009
Sanamau Waitogu4K views
Cable stayed bridges of prestressed concrete. von Franco Bontempi
Cable stayed bridges of prestressed concrete.Cable stayed bridges of prestressed concrete.
Cable stayed bridges of prestressed concrete.
Franco Bontempi707 views
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi... von Rajesh Prasad
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
Rajesh Prasad2.8K views
Munger rail cum road bridge von jaiveer singh
Munger rail cum road bridgeMunger rail cum road bridge
Munger rail cum road bridge
jaiveer singh1.6K views
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ... von Rajesh Prasad
Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...
Rajesh Prasad1.9K views
my project on chenab bridge von Taseem mir
my project on chenab bridge my project on chenab bridge
my project on chenab bridge
Taseem mir265 views
IRJET- Design of Railway Foot Over Bridge (Shelu) von IRJET Journal
IRJET- Design of Railway Foot Over Bridge (Shelu)IRJET- Design of Railway Foot Over Bridge (Shelu)
IRJET- Design of Railway Foot Over Bridge (Shelu)
IRJET Journal237 views
Final Report (Balsa Wood Bridge Design) von Josia Tannos, EIT
Final Report (Balsa Wood Bridge Design)Final Report (Balsa Wood Bridge Design)
Final Report (Balsa Wood Bridge Design)
Josia Tannos, EIT10.4K views
Building structure project 1 report von Adelinetingg
Building structure project 1 reportBuilding structure project 1 report
Building structure project 1 report
Adelinetingg4.5K views
Calculation note suez canal cable stayed bridge von Mohammed Abdelkawy
Calculation note suez canal cable stayed bridgeCalculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridge
Mohammed Abdelkawy8.4K views
accelerated bridge construction(ABC) von varun km
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
varun km181 views

Destacado

Using powerpoint at exhibitions presentation von
Using powerpoint at exhibitions presentationUsing powerpoint at exhibitions presentation
Using powerpoint at exhibitions presentationLorna Rose
222 views7 Folien
Tipos de traducción von
Tipos de traducciónTipos de traducción
Tipos de traducciónLeiram Azul
324 views6 Folien
KEY DETERMINANTS FOR SUCCESSFUL PROJECT IMPLEMENTATION IN THE INDUSTRIAL AREA... von
KEY DETERMINANTS FOR SUCCESSFUL PROJECT IMPLEMENTATION IN THE INDUSTRIAL AREA...KEY DETERMINANTS FOR SUCCESSFUL PROJECT IMPLEMENTATION IN THE INDUSTRIAL AREA...
KEY DETERMINANTS FOR SUCCESSFUL PROJECT IMPLEMENTATION IN THE INDUSTRIAL AREA...International Journal of Technical Research & Application
411 views7 Folien
Abledate von
AbledateAbledate
AbledateAbledate Online Dating
424 views9 Folien
A STUDY OF DECISION TREE ENSEMBLES AND FEATURE SELECTION FOR STEEL PLATES FAU... von
A STUDY OF DECISION TREE ENSEMBLES AND FEATURE SELECTION FOR STEEL PLATES FAU...A STUDY OF DECISION TREE ENSEMBLES AND FEATURE SELECTION FOR STEEL PLATES FAU...
A STUDY OF DECISION TREE ENSEMBLES AND FEATURE SELECTION FOR STEEL PLATES FAU...International Journal of Technical Research & Application
215 views5 Folien
Royal catalogue von
Royal catalogueRoyal catalogue
Royal catalogueNavy9393
201 views17 Folien

Destacado(20)

Using powerpoint at exhibitions presentation von Lorna Rose
Using powerpoint at exhibitions presentationUsing powerpoint at exhibitions presentation
Using powerpoint at exhibitions presentation
Lorna Rose222 views
Tipos de traducción von Leiram Azul
Tipos de traducciónTipos de traducción
Tipos de traducción
Leiram Azul324 views
Royal catalogue von Navy9393
Royal catalogueRoyal catalogue
Royal catalogue
Navy9393201 views
My last vacations Leonardo castro malaver von leonik2510
My last vacations Leonardo castro malaverMy last vacations Leonardo castro malaver
My last vacations Leonardo castro malaver
leonik2510317 views
Caterer | Asian Restaurants - Chef Patricks Kitchen von Lance Libot
Caterer | Asian Restaurants - Chef Patricks KitchenCaterer | Asian Restaurants - Chef Patricks Kitchen
Caterer | Asian Restaurants - Chef Patricks Kitchen
Lance Libot421 views
Material Testing Equipments - Gemarc Enterprises von Lance Libot
Material Testing Equipments - Gemarc EnterprisesMaterial Testing Equipments - Gemarc Enterprises
Material Testing Equipments - Gemarc Enterprises
Lance Libot416 views
TheBigBreakdu proposal-C(incNoor) von Richard Pope
TheBigBreakdu proposal-C(incNoor)TheBigBreakdu proposal-C(incNoor)
TheBigBreakdu proposal-C(incNoor)
Richard Pope230 views

Similar a THE CONSTRUCTION PROCEDURE AND ADVANTAGE OF THE RAIL CABLE-LIFTING CONSTRUCTION METHOD AND THE CABLE-HOISTING METHOD

Case study on signature bridge ppt (1) von
Case study on signature bridge ppt (1)Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)varun km
214 views16 Folien
Gaurav-Jhalani-Seminar-ppt.pptx von
Gaurav-Jhalani-Seminar-ppt.pptxGaurav-Jhalani-Seminar-ppt.pptx
Gaurav-Jhalani-Seminar-ppt.pptxSanjeevGupta660170
22 views47 Folien
Calculation Note Final von
Calculation Note FinalCalculation Note Final
Calculation Note FinalMohamed Elfike
771 views74 Folien
Design and Analysis of Transmission Tower at Allahabad von
Design and Analysis of Transmission Tower at AllahabadDesign and Analysis of Transmission Tower at Allahabad
Design and Analysis of Transmission Tower at AllahabadAbhijit Kumar
4.6K views50 Folien
Design of Transmission Tower von
Design of Transmission TowerDesign of Transmission Tower
Design of Transmission TowerAbhijit Kumar
23.8K views15 Folien
Bandra worli sealink pdf von
Bandra worli sealink pdfBandra worli sealink pdf
Bandra worli sealink pdfDesireddy Manasa
12.1K views24 Folien

Similar a THE CONSTRUCTION PROCEDURE AND ADVANTAGE OF THE RAIL CABLE-LIFTING CONSTRUCTION METHOD AND THE CABLE-HOISTING METHOD(20)

Case study on signature bridge ppt (1) von varun km
Case study on signature bridge ppt (1)Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)
varun km214 views
Design and Analysis of Transmission Tower at Allahabad von Abhijit Kumar
Design and Analysis of Transmission Tower at AllahabadDesign and Analysis of Transmission Tower at Allahabad
Design and Analysis of Transmission Tower at Allahabad
Abhijit Kumar4.6K views
Design of Transmission Tower von Abhijit Kumar
Design of Transmission TowerDesign of Transmission Tower
Design of Transmission Tower
Abhijit Kumar23.8K views
Analysis of cable stayed bridges von ParamaAthmeka
Analysis of cable stayed bridgesAnalysis of cable stayed bridges
Analysis of cable stayed bridges
ParamaAthmeka658 views
Building Structure Project 1 Fettuccine Bridge von Colby Hooi
Building Structure Project 1 Fettuccine BridgeBuilding Structure Project 1 Fettuccine Bridge
Building Structure Project 1 Fettuccine Bridge
Colby Hooi1.3K views
Presentation on construction of cable stay bridge - a modern technique for su... von Rajesh Prasad
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
Rajesh Prasad32.2K views
Millau via duct presentation full analysis von Mohammad Ali
Millau via duct presentation full analysisMillau via duct presentation full analysis
Millau via duct presentation full analysis
Mohammad Ali111 views
Bandra Worli sea link von KAVYA H
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea link
KAVYA H519 views
Huangpu Sports Center.ppt von ssuser886252
Huangpu Sports Center.pptHuangpu Sports Center.ppt
Huangpu Sports Center.ppt
ssuser88625252 views
Analyze and design of suspension bridge using sap2000 von vivatechijri
Analyze and design of suspension bridge using sap2000Analyze and design of suspension bridge using sap2000
Analyze and design of suspension bridge using sap2000
vivatechijri418 views
Parametric Study on Curved Bridges Subjected to Seismic Loading von IRJET Journal
Parametric Study on Curved Bridges Subjected to Seismic LoadingParametric Study on Curved Bridges Subjected to Seismic Loading
Parametric Study on Curved Bridges Subjected to Seismic Loading
IRJET Journal50 views
The Performance Evaluation of Concrete Filled Steel Tubular Arch Bridge von IJERA Editor
The Performance Evaluation of Concrete Filled Steel Tubular Arch BridgeThe Performance Evaluation of Concrete Filled Steel Tubular Arch Bridge
The Performance Evaluation of Concrete Filled Steel Tubular Arch Bridge
IJERA Editor140 views
The Performance Evaluation of Concrete Filled Steel Tubular Arch Bridge von IJERA Editor
The Performance Evaluation of Concrete Filled Steel Tubular Arch BridgeThe Performance Evaluation of Concrete Filled Steel Tubular Arch Bridge
The Performance Evaluation of Concrete Filled Steel Tubular Arch Bridge
IJERA Editor222 views
Chenab bridge ppt von Ravi Panchal
Chenab bridge pptChenab bridge ppt
Chenab bridge ppt
Ravi Panchal14.1K views
steelstructures-130906015820-.pdf von rubini32
steelstructures-130906015820-.pdfsteelstructures-130906015820-.pdf
steelstructures-130906015820-.pdf
rubini323 views

Más de International Journal of Technical Research & Application

EXPONENTIAL SMOOTHING OF POSTPONEMENT RATES IN OPERATION THEATRES OF ADVANCED... von
EXPONENTIAL SMOOTHING OF POSTPONEMENT RATES IN OPERATION THEATRES OF ADVANCED...EXPONENTIAL SMOOTHING OF POSTPONEMENT RATES IN OPERATION THEATRES OF ADVANCED...
EXPONENTIAL SMOOTHING OF POSTPONEMENT RATES IN OPERATION THEATRES OF ADVANCED...International Journal of Technical Research & Application
294 views7 Folien
POSTPONEMENT OF SCHEDULED GENERAL SURGERIES IN A TERTIARY CARE HOSPITAL - A T... von
POSTPONEMENT OF SCHEDULED GENERAL SURGERIES IN A TERTIARY CARE HOSPITAL - A T...POSTPONEMENT OF SCHEDULED GENERAL SURGERIES IN A TERTIARY CARE HOSPITAL - A T...
POSTPONEMENT OF SCHEDULED GENERAL SURGERIES IN A TERTIARY CARE HOSPITAL - A T...International Journal of Technical Research & Application
312 views6 Folien
ENERGY GAP INVESTIGATION AND CHARACTERIZATION OF KESTERITE CU2ZNSNS4 THIN FIL... von
ENERGY GAP INVESTIGATION AND CHARACTERIZATION OF KESTERITE CU2ZNSNS4 THIN FIL...ENERGY GAP INVESTIGATION AND CHARACTERIZATION OF KESTERITE CU2ZNSNS4 THIN FIL...
ENERGY GAP INVESTIGATION AND CHARACTERIZATION OF KESTERITE CU2ZNSNS4 THIN FIL...International Journal of Technical Research & Application
222 views4 Folien

Más de International Journal of Technical Research & Application(20)

Último

Art of Writing Research article slide share.pptx von
Art of Writing Research article slide share.pptxArt of Writing Research article slide share.pptx
Art of Writing Research article slide share.pptxsureshc91
14 views42 Folien
SWM L1-L14_drhasan (Part 1).pdf von
SWM L1-L14_drhasan (Part 1).pdfSWM L1-L14_drhasan (Part 1).pdf
SWM L1-L14_drhasan (Part 1).pdfMahmudHasan747870
48 views150 Folien
CHI-SQUARE ( χ2) TESTS.pptx von
CHI-SQUARE ( χ2) TESTS.pptxCHI-SQUARE ( χ2) TESTS.pptx
CHI-SQUARE ( χ2) TESTS.pptxssusera597c5
20 views33 Folien
Machine Element II Course outline.pdf von
Machine Element II Course outline.pdfMachine Element II Course outline.pdf
Machine Element II Course outline.pdfodatadese1
6 views2 Folien
LFA-NPG-Paper.pdf von
LFA-NPG-Paper.pdfLFA-NPG-Paper.pdf
LFA-NPG-Paper.pdfharinsrikanth
40 views13 Folien
NEW SUPPLIERS SUPPLIES (copie).pdf von
NEW SUPPLIERS SUPPLIES (copie).pdfNEW SUPPLIERS SUPPLIES (copie).pdf
NEW SUPPLIERS SUPPLIES (copie).pdfgeorgesradjou
7 views30 Folien

Último(20)

Art of Writing Research article slide share.pptx von sureshc91
Art of Writing Research article slide share.pptxArt of Writing Research article slide share.pptx
Art of Writing Research article slide share.pptx
sureshc9114 views
CHI-SQUARE ( χ2) TESTS.pptx von ssusera597c5
CHI-SQUARE ( χ2) TESTS.pptxCHI-SQUARE ( χ2) TESTS.pptx
CHI-SQUARE ( χ2) TESTS.pptx
ssusera597c520 views
Machine Element II Course outline.pdf von odatadese1
Machine Element II Course outline.pdfMachine Element II Course outline.pdf
Machine Element II Course outline.pdf
odatadese16 views
NEW SUPPLIERS SUPPLIES (copie).pdf von georgesradjou
NEW SUPPLIERS SUPPLIES (copie).pdfNEW SUPPLIERS SUPPLIES (copie).pdf
NEW SUPPLIERS SUPPLIES (copie).pdf
georgesradjou7 views
performance uploading.pptx von SanthiS10
performance uploading.pptxperformance uploading.pptx
performance uploading.pptx
SanthiS107 views
DevOps to DevSecOps: Enhancing Software Security Throughout The Development L... von Anowar Hossain
DevOps to DevSecOps: Enhancing Software Security Throughout The Development L...DevOps to DevSecOps: Enhancing Software Security Throughout The Development L...
DevOps to DevSecOps: Enhancing Software Security Throughout The Development L...
Anowar Hossain10 views
Informed search algorithms.pptx von Dr.Shweta
Informed search algorithms.pptxInformed search algorithms.pptx
Informed search algorithms.pptx
Dr.Shweta12 views
Literature review and Case study on Commercial Complex in Nepal, Durbar mall,... von AakashShakya12
Literature review and Case study on Commercial Complex in Nepal, Durbar mall,...Literature review and Case study on Commercial Complex in Nepal, Durbar mall,...
Literature review and Case study on Commercial Complex in Nepal, Durbar mall,...
AakashShakya1245 views
7_DVD_Combinational_MOS_Logic_Circuits.pdf von Usha Mehta
7_DVD_Combinational_MOS_Logic_Circuits.pdf7_DVD_Combinational_MOS_Logic_Circuits.pdf
7_DVD_Combinational_MOS_Logic_Circuits.pdf
Usha Mehta50 views
Thermal aware task assignment for multicore processors using genetic algorithm von IJECEIAES
Thermal aware task assignment for multicore processors using genetic algorithm Thermal aware task assignment for multicore processors using genetic algorithm
Thermal aware task assignment for multicore processors using genetic algorithm
IJECEIAES29 views
Multi-objective distributed generation integration in radial distribution sy... von IJECEIAES
Multi-objective distributed generation integration in radial  distribution sy...Multi-objective distributed generation integration in radial  distribution sy...
Multi-objective distributed generation integration in radial distribution sy...
IJECEIAES15 views
9_DVD_Dynamic_logic_circuits.pdf von Usha Mehta
9_DVD_Dynamic_logic_circuits.pdf9_DVD_Dynamic_logic_circuits.pdf
9_DVD_Dynamic_logic_circuits.pdf
Usha Mehta21 views

THE CONSTRUCTION PROCEDURE AND ADVANTAGE OF THE RAIL CABLE-LIFTING CONSTRUCTION METHOD AND THE CABLE-HOISTING METHOD

  • 1. International Journal of Technical Research and Applications e-ISSN: 2320-8163, www.ijtra.com Volume 3, Issue 4 (July-August 2015), PP. 21-23 21 | P a g e THE CONSTRUCTION PROCEDURE AND ADVANTAGE OF THE RAIL CABLE-LIFTING CONSTRUCTION METHOD AND THE CABLE-HOISTING METHOD Ji Ce Zeng School of civil engineering and architecture Chongqing Jiaotong University Chongqing, China 277199895@qq.com Abstract:The cable-hoisting method and rail cable-lifting method are widely used in the construction of suspension bridge. This paper takes a suspension bridge in Hunan as an example, and expounds the two construction methods, and analyzes their respective merits and disadvantages. Key words : suspension bridge rail cable-lifting cable-hoisting I. ENGINEERING SITUATION The bridge is steel truss girder suspension bridge, the main bridge spans to 900 meters, truss width is 27.0 meters, truss height is 8 meters, approach bridge(5*30m) is designed in south shore , another approach bridge(8*30m) is also designed in north shore; both sides of the Straits are used with gravity anchor, door-type reinforce concrete tower, dig cast-in-place circular pile foundation. Deck to the bottom of the River, vertical distance is about 200m, river width of maximum is 400m, accounting for the main cross 44.4%, average slope rate of gully length is about 0.66 (height / length). Lifting saddle is arranged in perpetual suspended cable, which dose not occupy the sling steel truss connecting holes. It is convenient for connection of cable head and segmental beam. Meanwhile, it can reduce operation steps of removing suspended saddle and installing the main girder when beam section is being installed saddle. It is also can be able to reduce the lifting height of steel truss girder and improve construction efficiency. II. CABLE-HOISTING CONSTRUCTION METHOD A. Design of cable-hoisting system The main cable crane spans to 900m, the side span is 155m in south shore, the side span is 258m in north shore, both sides of the anchorage are anchored by gravity anchor. The steel tower is assembled by steel tubes. The section weight of steel truss girder is calculated by 160t. Working principle of the cable crane machine is along the cross bridge to arrange two sets of main cable, each main cable is composed of steel wire rope 10 Phi 60.5, both ends of which are anchored in the gravity anchor on both sides of bridge. Each main cable respectively hangs the two supporting car in midair. At both ends of the bridge, the traction winch and lift winch pull lifting trolley in the bearing cable to roll and lift steel truss girder, which makes girder construction completed. There are 8 sports cars during the working frame of the cable crane, and the erection of each section of the steel truss girder is shared 4 sports cars (i.e., 4 lifting points) and hoisted synchronously Suspension rope design and related parameters of single cable Project Specification for wire rope (mm) form for wire rope Unit weight (kg.m﹣¹) Breaking tension(kN) Modulus elasticity (MPa) Load-bearing cable 10×Φ60.5 6×37S+IWR 1284.3 2075 10500 the sling Φ32 6×37S+IWR 389.0 546.5 10500 Traction cable 2×Φ36 6×37S+IWR 437.0 701.9 10500 B. Cable crane tower Cable crane tower is used in scheme that assembles
  • 2. International Journal of Technical Research and Applications e-ISSN: 2320-8163, www.ijtra.com Volume 3, Issue 4 (July-August 2015), PP. 21-23 22 | P a g e steel pipe column in bridge tower, each tower with 4 Phi 600 * 10 is made of seamless steel pipe column, flat joint by phi 300 x 8 of the seamless steel pipe, bracing by Phi 200 x 8 seamless steel tube composed of space lattice system, which plays a part in supporting in bridge cable tower, tower has height of 13m. tower is made of the total amount of 54t steel. Its material is Q345 steel. Steel tube tower is connected with the tower frame, in order to increase the overall stability of the tower. At the same time, a transverse eight wind is designed, wind-bearing wire rope with 4 Phi 32 per bank is selected. In order to reduce the longitudinal direction of the bridge tower deviation, unilateral set Phi 60.5 pressure tower wire rope. C. Hoisting construction Steel truss girder in assembling field is assembled, when steel truss girder ships load- segment, with floating box controlling the water-level, the top of floating box lies alongside the wharf, and pressure from the ship's load levels system position. At the same time, the floating box and wharves should be fixed and connected, waiting for flat car on board. III. RAIL CABLE-LIFTING CONSTRUCTION METHOD A. Equipment And Assembling The equipment mainly composed of the following parts: beam-transporting trolley, saddle, cable, crane, zenith trolley, a winch etc. The beam-transporting trolley is the most core equipment in this project, which composed of the pulley group, the triangular distribution beam and the rectangular distribution beam. B. Saddle The effect of cable saddle is to provide support, and will convert load from cable to cable. The design of crane saddle incorporate characteristics of pin type sling, with moving the saddle to the direction of top and using the cable clamp as a fulcrum to place it at the top, which make saddle not occupy space of connecting hole of the lower cable clamp. It also uses both sides of the longitudinal positioning lock to ensure the lateral stability and it is convenient for construction. The saddle is composed of a longitudinal beam and a saddle beam. C. Cable Rail cable is considered as beam-transporting orbit and the lifeline of the whole system, it is also the parts that has highest safety risk coefficient. Its internal force changes complexly and shows different characteristics on various construction conditions, in order to meet need of its function and have enough safety and operability, after calculating, the staff used Phi 60 wire rope galvanized and sealed. Four single, independent of each other, one end fixedly, one end through the pulley group + keeping four rail cable force basically the same and remain constant with counterweight block. D. Crane The bridge had two sets of hydraulic loading crane for lifting type cable, a cable carrier crane by a steel truss beam, two pedrail-walking mechanism on the main cable, two sets of hydraulic lifting equipment (including lifting and traction jacks, hydraulic pump station, control system and steel wire take-up device), with a lifting pole beam, power generation equipment parts. E. Construction Procedure The installation and construction method of flexible cable net steel truss beam is used for erection of steel truss beam in the section of hoisting. The main construction steps are: 1. The main cable and permanent slings are used for supporting, horizontal cable is set up , with anchored in the rock mass. 2. A steel pipe Bailey platform is built at the pile cap on both sides, steel truss girder assembling platform is made of Bailey platform and the rest space of pile cap. 3. After lifting section that has been assembled, and then those sections are suspended under the carriage beam trolley. 4. Transporting vertically to the corresponding sling by rail sling 5. The section of the steel truss girder is suspended from the cable borne crane, and the carriage beam carriage is exited. 6. Adjusting spatial position of the segment, and beam butt has been installed, and pin sling. 7. The beam in mid of bridge is first installed and then symmetrically installed from mid of bridge to the sides of bank until the full bridge is linked. The advantages of rail cable-lifting construction method and cable-hoisting method 1. The assembling field of the steel truss is arranged
  • 3. International Journal of Technical Research and Applications e-ISSN: 2320-8163, www.ijtra.com Volume 3, Issue 4 (July-August 2015), PP. 21-23 23 | P a g e on the platform. Compared with the cable hoisting, it can reduce the lifting height of the steel truss girder and the construction time, and improve the safety of the construction. At the same time, two pieces of steel truss girder can be installed, which can shorten the construction time and bring the recessive economic benefits. 2. Transport and erection of the steel truss girder have high construction efficiency, cost savings. 3. The rail cable is used as the main cable as the support, with the good wind stability, the quality of construction can be controllable 4. Compared to the cables, rail cable needs less bearing steel wire rope. 5. When using cable-hoisting method, it needs more operators, and cable-hoisting system technology is complex, it has high demands for the operation and personnel quality . Rail cable has a high degree of automation, it needs less operators when moving the beam. Construction technology is stable, the impact of environment is small, easy to standardized operation. IV. CONCLUSION Rail cable-lifting construction method and cable-hoisting construction method is more and more mature, but there are still many places should be improved, such as whether rail cable-lifting construction method can cancel cable carrying crane or not, in terms with controlling the main cable wire linearity in cable-hoisting construction method REFERENCES [1]. Jianhui Lv. Hui Zhang. long span concrete filled steel tube arch bridge cable-hoisting construction technology [J] - Science and technology and engineering 2009,9 (4) [2]. Shiming Liu. Yongjian Liu. Xiaorong Yao. concrete filled steel tubular arch bridge cable- hoisting construction optimization [J] - Highway Traffic Science and technology in 2012, 29 (7) [3]. Jinming Huang. cable hoisting system in steel truss arch bridge hook in construction application [journal article] - the western traffic science and technology 2012 (2) [4]. Dong liang Zhou. Construction control study [J] highway and 2012 trucks hoisting of long span arch bridge (1) Huaqiang [5]. Jian gen Lv. The main span of 368m Zhang Hui lifting Maocaojie Bridge Construction Technology [J] 2009 rib arch construction technology, 40 (2) [6]. Zheng zhou Cao. Yu tao Feng. Chongqing Chaoyang complex bridge hoisting cable tower, tower integration research [J] 2010 (07) of bridge construction. [7]. Jun wei Tian. large span concrete filled steel tubular arch bridge construction control [J] highway and automotive 2012 rib hoisting (1) [8]. Hong tian Du. Zhong Ming. concrete filled steel tube arch bridge arch rib hoisting process temperature change on Rib Alignment Effect [J] - Railway Standard arch design 2008 (3) [9]. Jian hong LI . Jing Sheng. cable hoisting method of reinforced concrete arch bridge construction error analysis [J] - Sichuan building 2009,29 (6)