http://www.iaeme.com/IJCIET/index.asp 22 editor@iaeme.com
International Journal of Civil Engineering and Technology (IJCIET)
Volume 7, Issue 2, March-April 2016, pp. 22-33, Article ID: IJCIET_07_02_002
Available online at
http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=7&IType=2
Journal Impact Factor (2016): 9.7820 (Calculated by GISI) www.jifactor.com
ISSN Print: 0976-6308 and ISSN Online: 0976-6316
© IAEME Publication
FACTORS AFFECTING DELAYS ON
PRIVATE CONSTRUCTION PROJECTS
Jamal M. Assbeihat
Al- Balqa’ Applied University- Faculty of Engineering and Technology, Jordan
ABSTRACT
Construction Delays is a major of concern in the private projects
construction industry in Jordan. With the fact that construction delays are
nothing but loss of time and money such study was conducted to identify the
factors that causes the construction delays. Therefore three groups consist of
consultants, contractors and owners were questioned, Shortage of manpower
(skilled, semiskilled, unskilled labor), Delay in the approval of contractor
submissions by the engineer, Shortage of materials, The relationship between
different subcontractors’ schedules were the most important factors that cause
delays in private projects sector in Jordan. Furthermore one way ANOVA
analysis conducted to select factors that share agreement between the three
groups.
Key words: Construction Delays; Construction Projects; Jordanian
Construction Sector.
Cite this Article: Jamal M. Assbeihat, Factors Affecting Delays on Private
Construction Projects, International Journal of Civil Engineering and
Technology, 7(2), 2016, pp. 22-33.
http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=7&IType=2
1. INTRODUCTION
In construction, delay could be defined as the time overrun either beyond completion
date specified in a contract, or beyond the date that the parties agreed upon for
delivery of a project. It is a project slipping over its planned schedule and is
considered as common problem in construction projects. To the owner, delay means
loss of revenue through lack of production facilities and rent-able space or a
dependence on present facilities. In some cases, to the contractor, delay means higher
overhead costs because of longer work period, higher material costs through inflation,
and due to labor cost increases and maybe lost opportunities for new projects because
of diminished financial capabilities (Assaf and Al-Hejji 2006).
The successful execution of construction projects and keeping them within
estimated cost and prescribed schedules depend on a methodology that requires sound
engineering judgment. To the dislike of all the participants (owners, contractors, and
Factors Affecting Delays on Private Construction Projects
http://www.iaeme.com/IJCIET/index.asp 23 editor@iaeme.com
consultants), however, many projects experience extensive delays and there by exceed
initial time and cost estimates (Odeh and Battaineh, 2002).
Recently, the Jordanian construction industry has been undergoing a boom (Sweis
et al., 2008). A huge number of large-scale private projects are currently under
construction or in the planning and contract-awarding phase. Therefore understanding
the causes of delays and their importance is a major of concern in order to minimize
and avoid the delays and their corresponding expenses in the field of private projects
construction industry in Jordan. The main objectives of this study include the
following:
• To identify the causes of delays in private projects construction in Jordan.
• To identify the importance of each delay cause in private projects construction in
Jordan.
• To study the differences in perceptions of the three major parties in any constructions:
(consultants, contractors, and owners).
2. LITERATURE REVIEW
Many studies were conducted on the causes of delays in construction projects in
different developing countries, including Middle East. Several articles have discussed
causes of delay in construction projects in numerous manners. Some studies identified
the main causes of delay in several countries and various project types, while other
studies discussed the delay analysis methods and the proposed ways to mitigate it.
Kumaraswamy Moha and Chan Daniel ( 1998) in their study provides pointers to
appropriate strategies and particular measures that may be adopted to avoid and/or
mitigate project delays by focusing on the direct and indirect common contributors to
same, such as delays in design information and productivity levels. To them, the main
reasons behind projects delays in Hong Kong are : unforeseen ground conditions,
poor site management and supervision, low speed in decision making involving all
project teams, client- initiated variations, necessary variations of works, Inadequate
contractor experience. Investigating the causes and effects of delays facing in the
Malaysian construction industry Sambasivan Murali and Soon Yau Wen (2007) found
that the most important delay factors are: contractor’s improper planning, contractor’s
poor site management, inadequate contractor experience, inadequate client’s finance
and payments for completed work, problems with subcontractors. Frimpong Yaw et
al. (2003) in their study identifies and examines the causes of delay and cost overruns
in the construction of groundwater projects in Ghana. The results of this study were
that the reasons behind the delays are respectively: poor contractor management,
monthly payment difficulties from agencies, material procurement, poor technical
performances, and escalation of material prices according to their degree of influence.
The major sources of delays on highrise building construction projects in Thailand are
identified by Ogunlana Stephen and Promkuntong Krit (1996): shortage of
construction materials, shortage of site workers, incomplete drawings by designers,
materials management problems by contractors, deficiencies in organization. Kalib
Chabota et al. (2009) in their study about schedule delays in road construction in
Zambia found that the most important causes of delays are: delayed payment,
protracted financial processes in client organization, financial difficulties, contract
modification, and economic hardships. Kaming Peter et al. (1997) studied about time
and cost overruns in high-rise construction in Indonesia. The results of this study were
that the major causes of time overruns are: design changes, inadequate planning,
Jamal M. Assbeihat
http://www.iaeme.com/IJCIET/index.asp 24 editor@iaeme.com
inaccuracy of materials estimating, poor labor productivity, inaccurate prediction of
craftsmen production rate.
Toor Shamas-Ur-Rehman and Ogunlana Stephen (2008) studied the Problems
causing delays in major construction projects in Thailand. The findings showed that
most problems related to designers, clients, contractors and finance were rated among
the top problems; whereas a multicultural and multilingual environment, large
numbers of project participants and the involvement of foreign designers were
perceived as not very significant problems.
Many studies have been conducted in the same manner in the region of the middle
east. Koushki et al. (2005) studied the problems experienced during the construction
of private residences in the state of Kuwait. The results of the study were that the
main reasons that cause the delays in the construction of private residential projects in
Kuwait are: the number of change orders, financial constraints, and owners’ lack of
experience in construction, material-related problems, and weather related problems.
In Egypt, Marzouk Mohamed (2008) in their study highlighted the importance and the
effect of each of the causes of delays and focused upon the most important causes.
The causes are included the delay in receiving design documents, delay in the
preparation process due to lack of (resources, experience, and management),
unforeseen conditions, mistakes/changes in the design documents provided by the
employer, delay in responding to contractor’s queries. In Egypt also, Abd El-Razek et
al. (2008) in their studied the actual causes of delay that affect building projects in
Egypt in order to minimize and avoid the delays and their corresponding expenses.
The results of this study were that the major delay causes in building projects in Egypt
are respectively: financing by contractor during construction, delays in contractor’s
payment by owner, design changes by owner or his agent during construction, partial
payments during construction, non utilization of professional construction/contractual
management. Assaf Sadi and Al-Hejji Sadiq (2006) in their study identified the causes
of delays in construction in Eastern Province of Saudi Arabia. They found that the
major delay causes in large construction projects are: change orders by owner during
construction, delay in progress payments, ineffective planning and scheduling by
contractor, poor site management and supervision by contractor, difficulties in
financing by contractor. Another study in Saudi Arabia done by Al-Kharashi and
Skitmore (2009) stated that, in the case where the project is a public building or
facility, the complications increase as the client is a government department. Then the
main reasons that causes the delays in construction projects in Saudi Arabian public
sector are: delay in progress payments by the owner, non-payment of the contractor
claim, lack of finance to complete the work by the client, late in revising and
approving design documents by owner, delay in approving sample materials by
owner.
Faridi and El-Sayegh (2006) in their study identified the most significant causes of
delay in the UAE construction industry to be able to find ways to avoid them, or at
least, mitigate their impact. The results of this study were that the critical factors that
causes the delays in the UAE construction industry are respectively: preparation and
approval of drawings, inadequate early planning of the project, slowness of the
owner's decision-making process, shortage of manpower, poor supervision and poor
site management. On th other hand, Zaneldin (2006) identified several problem areas
in the construction process in UAE. The causes by this study are: delayed payments,
protracted financial processes in client organizations, financial difficulties that
Factors Affecting Delays on Private Construction Projects
http://www.iaeme.com/IJCIET/index.asp 25 editor@iaeme.com
accompany the delayed release of funds by client organizations, contract
modification, and economic hardships.
In Jordan, less attention have been paid. Odeh and Battaineh (2002) in their study
-in which the objective of it was to identify the major causes of delay in the
construction industry and to assess the relative importance of these causes for the
traditional adversarial type of contracts from the viewpoint of construction contractors
and consultants. The results of their study were that the most important factors of
delay according to the contractor are respectively: Labor productivity, Owner
interference, and inadequate contractor experience. While the factors of delay
according to the consultant are: Inadequate contractor experience, Finance and
payments of completed work, and Subcontractors. Sweis et al. (2008) in their study
stated that delays in construction projects are common in the Jordanian construction
industry and that the most important reasons behind the construction delays in Jordan
are respectively: financial difficulties faced by the contractor, too many change orders
from owner, poor planning and scheduling of the project by the contractor, presence
of unskilled labor, shortage of technical professionals in the contractor’s organization.
3. METHODOLOGY
Based on the results of all the reviewed studies, specially the Jordanian ones, we
develop a list of factors, which might affect the delays in the Jordanian private
projects and categorized them into three main groups. A questionnaire was developed
in order to evaluate the frequency of occurrence and importance of the identified
causes. The design of the questionnaire has been based on Assaf and Al-Hejji (2006)
and Sweis (2008) refrences, and the study questionnaire is based on Open Conversion
System proposed by Drewin. According to Drewin the construction process
influenced by technologies and both external and internal environments. Therefore, a
combination between Drewin's open conversion system and delay causes identified in
previous studies results in 45 potential delay factors were summarized into three
major categories:
Production Elements (PE) includes: Labor (L), Materials (M) and Equipment (E)
related factors.
Internal Environment (IE) includes: Consultant, Contractor and Owner related factors.
External Environment (EE) includes: Weather, Government Regulations and Other
reasons
The consultants, contractors, and owners of an accomplished sixty projects in year
2014, with a cost more than 1.3 million dollars were targeted. Then the questionnaire
was distributed by hand. Therefore a sample consists of 60 consultants, 60
contractors, and 35 owners selected (many residential and trade buildings have the
same owner- organization). Responses to the questionnaire were then collected and
analyzed. The responses consisted of 50 consultants, 50 contractors, and 20 owners.
They were asked to grade each delay cause from a scale of 1 to 5 in which number 5
indicates a very strong affecting cause on the construction projects and number 1
indicates a minor cause of delays in the construction projects.
4. DATA ANALYSIS AND RESULTS
The delay causes was ranked by taking the average of the respondents for each
individual group/participant (consultant, contractor, owner), then the average of the
three groups was calculated separately. The resulting averages were ranked in
Jamal M. Assbeihat
http://www.iaeme.com/IJCIET/index.asp 26 editor@iaeme.com
descending order according to the highest average in the group response. The ranks
are presented in tables 4.1, 4.2 and 4.3 respectively.
Table 4.1 Reasons’ Ranking for Consultant
REASON Category Sub Category
Avg.
rate
Shortage of manpower (skilled, semiskilled,
unskilled labor)
Productive elements Labor ( L ) 3.5
Too many change orders from owner Internal Environment (IE) Owner 3.4
Delays in contractor’s payment by owner Internal Environment (IE) Owner 3.3
Insufficient coordination among the parties by the
contractor
Internal Environment (IE) Contractor 3.3
Shortage of equipments Productive elements Equipments ( E ) 3.3
Slowness of the owner decision making process Internal Environment (IE) Owner 3.3
Financing by owner during construction Internal Environment (IE) Contractor 3.2
Shortage of materials Productive elements Materials ( M ) 3.2
Delay in the approval of contractor submissions
by the engineer
Internal Environment (IE) Consultant / Designer 3.1
Preparation and waiting for approval of shop
drawings and material samples
Internal Environment (IE) Consultant / Designer 3.1
Delays in contractor's payments to subcontractors Internal Environment (IE) Contractor 3.1
Delay in materials delivery Productive elements Materials ( M ) 3.1
Labor productivity Productive elements Labor ( L ) 3.1
Poor planning and scheduling of the project by the
contractor
Internal Environment (IE) Contractor 3.0
The relationship between different subcontractors’
schedules
Internal Environment (IE) Contractor 3.0
Shortage of technical professionals in the
contractor's organization
Internal Environment (IE) Contractor 3.0
Insufficient equipments Productive elements Equipments ( E ) 3.0
Shortage in labor Productive elements Labor ( L ) 3.0
Severe weather conditions on the job site External Environment Weather 2.9
Mistakes in soil investigation Internal Environment (IE) Consultant / Designer 2.9
Unexpected foundation conditions encountered in
the field
Internal Environment (IE) Consultant / Designer 2.9
Slow response by the consultant engineer
regarding testing and inspection
Internal Environment (IE) Consultant / Designer 2.9
Financing by contractor during construction Internal Environment (IE) Owner 2.9
Over-design increasing the overall cost Internal Environment (IE) Consultant / Designer 2.7
Failure to utilize tools to manage the project
symmetrically
Internal Environment (IE) Owner 2.7
Delays in site preparation Internal Environment (IE) Owner 2.7
Unrealistic project schedule Internal Environment (IE) Contractor 2.7
Poor leadership on part of the sub-contractors Internal Environment (IE) Contractor 2.7
Poor communication with the suppliers Internal Environment (IE) Contractor 2.7
Use of unacceptable construction techniques by
the contractor
Internal Environment (IE) Contractor 2.7
Failure of equipments Productive elements Equipments ( E ) 2.7
Factors Affecting Delays on Private Construction Projects
http://www.iaeme.com/IJCIET/index.asp 27 editor@iaeme.com
REASON Category Sub Category
Avg.
rate
Changes in materials types and specifications
during construction
Productive elements Materials ( M ) 2.7
Improper technical study by the contractor during
the bidding stage
Internal Environment (IE) Contractor 2.6
Difficulties in obtaining work permits External Environment Government Regulations 2.6
Improper project feasibility study Internal Environment (IE) Consultant / Designer 2.6
Lack of communication with consultant / owner Internal Environment (IE) Contractor 2.6
Poorly written contracts Internal Environment (IE) Consultant / Designer 2.5
Lack of database in estimating activity duration
and resources
Internal Environment (IE) Contractor 2.5
Delay in mobilization Internal Environment (IE) Contractor 2.5
Changes in government regulations and laws External Environment Government Regulations 2.4
Using obsolete technology Internal Environment (IE) Contractor 2.4
Accidents during construction External Environment Other 2.2
Large number of participants of project
implementation
Internal Environment (IE) Contractor 2.2
Safely rules and regulations aren’t followed within
the contractors organization
Internal Environment (IE) Contractor 2.0
Problem with neighbors External Environment Other 1.8
Table 4, 2 Reason Ranking for Contractor
REASON Category Sub Category
Avg.
rate
Shortage of manpower (skilled, semiskilled,
unskilled labor)
Productive elements Labor ( L ) 3.6
Delay in the approval of contractor submissions
by the engineer
Internal Environment (IE) Consultant / Designer 3.4
Difficulties in obtaining work permits External Environment Government Regulations 3.3
Slowness of the owner decision making process Internal Environment (IE) Owner 3.3
Too many change orders from owner Internal Environment (IE) Owner 3.3
Preparation and waiting for approval of shop
drawings and material samples
Internal Environment (IE) Consultant / Designer 3.3
Shortage of equipments Productive elements Equipments ( E ) 3.3
Shortage of materials Productive elements Materials ( M ) 3.3
Labor productivity Productive elements Labor ( L ) 3.3
Shortage in labor Productive elements Labor ( L ) 3.2
Financing by owner during construction Internal Environment (IE) Contractor 3.1
Poor leadership on part of the sub-contractors Internal Environment (IE) Contractor 3.1
Delay in materials delivery Productive elements Materials ( M ) 3.1
Improper technical study by the contractor during
the bidding stage
Internal Environment (IE) Contractor 3.0
Slow response by the consultant engineer
regarding testing and inspection
Internal Environment (IE) Consultant / Designer 3.0
Financing by contractor during construction Internal Environment (IE) Owner 3.0
Insufficient coordination among the parties by the
contractor
Internal Environment (IE) Contractor 3.0
Shortage of technical professionals in the Internal Environment (IE) Contractor 3.0
Jamal M. Assbeihat
http://www.iaeme.com/IJCIET/index.asp 28 editor@iaeme.com
REASON Category Sub Category
Avg.
rate
contractor's organization
Failure of equipments Productive elements Equipments ( E ) 3.0
Unexpected foundation conditions encountered in
the field
Internal Environment (IE) Consultant / Designer 2.9
Delays in contractor's payments to subcontractors Internal Environment (IE) Contractor 2.9
Use of unacceptable construction techniques by
the contractor
Internal Environment (IE) Contractor 2.9
Insufficient equipments Productive elements Equipments ( E ) 2.9
Delays in contractor’s payment by owner Internal Environment (IE) Owner 2.8
Over-design increasing the overall cost Internal Environment (IE) Consultant / Designer 2.8
Poor planning and scheduling of the project by
the contractor
Internal Environment (IE) Contractor 2.8
Delay in mobilization Internal Environment (IE) Contractor 2.8
Changes in materials types and specifications
during construction
Productive elements Materials ( M ) 2.8
Changes in government regulations and laws External Environment Government Regulations 2.7
Severe weather conditions on the job site External Environment Weather 2.7
Unrealistic project schedule Internal Environment (IE) Contractor 2.7
The relationship between different
subcontractors’ schedules
Internal Environment (IE) Contractor 2.7
Lack of database in estimating activity duration
and resources
Internal Environment (IE) Contractor 2.7
Delays in site preparation Internal Environment (IE) Owner 2.6
Poorly written contracts Internal Environment (IE) Consultant / Designer 2.6
Improper project feasibility study Internal Environment (IE) Consultant / Designer 2.6
Mistakes in soil investigation Internal Environment (IE) Consultant / Designer 2.6
Large number of participants of project
implementation
Internal Environment (IE) Contractor 2.6
Lack of communication with consultant / owner Internal Environment (IE) Contractor 2.6
Safely rules and regulations aren’t followed
within the contractors organization
Internal Environment (IE) Contractor 2.6
Poor communication with the suppliers Internal Environment (IE) Contractor 2.4
Problem with neighbors External Environment Other 2.4
Failure to utilize tools to manage the project
symmetrically
Internal Environment (IE) Owner 2.4
Using obsolete technology Internal Environment (IE) Contractor 2.4
Accidents during construction External Environment Other 2.3
Table 4.3 Reason’s Ranking for Owner
REASON Category Sub Category
Avg.
rate
Shortage of materials Productive elements Materials ( M ) 3.3
The relationship between different
subcontractors’ schedules
Internal Environment (IE) Contractor 3.3
Over-design increasing the overall cost Internal Environment (IE) Consultant / Designer 3.2
Delay in the approval of contractor submissions
by the engineer
Internal Environment (IE) Consultant / Designer 3.1
Preparation and waiting for approval of shop Internal Environment (IE) Consultant / Designer 3.1
Factors Affecting Delays on Private Construction Projects
http://www.iaeme.com/IJCIET/index.asp 29 editor@iaeme.com
REASON Category Sub Category
Avg.
rate
drawings and material samples
Slowness of the owner decision making process Internal Environment (IE) Owner 3.0
Insufficient coordination among the parties by
the contractor
Internal Environment (IE) Contractor 3.0
Financing by owner during construction Internal Environment (IE) Owner 2.9
Too many change orders from owner Internal Environment (IE) Owner 2.9
Slow response by the consultant engineer
regarding testing and inspection
Internal Environment (IE) Consultant / Designer 2.9
Large number of participants of project
implementation
Internal Environment (IE) Contractor 2.9
Shortage of manpower (skilled, semiskilled,
unskilled labor)
Productive elements Labor ( L ) 2.8
Poorly written contracts Internal Environment (IE) Consultant / Designer 2.8
Unexpected foundation conditions encountered
in the field
Internal Environment (IE) Consultant / Designer 2.8
Poor communication with the suppliers Internal Environment (IE) Contractor 2.8
Labor productivity Productive elements Labor ( L ) 2.8
Shortage in labor Productive elements Labor ( L ) 2.7
Delays in contractor’s payment by owner Internal Environment (IE) Owner 2.7
Lack of database in estimating activity duration
and resources
Internal Environment (IE) Contractor 2.7
Use of unacceptable construction techniques by
the contractor
Internal Environment (IE) Contractor 2.7
Delay in mobilization Internal Environment (IE) Contractor 2.6
Difficulties in obtaining work permits External Environment Government Regulations 2.6
Severe weather conditions on the job site External Environment Weather 2.6
Improper technical study by the contractor
during the bidding stage
Internal Environment (IE) Contractor 2.6
Failure of equipments Productive elements Equipments ( E ) 2.6
Changes in materials types and specifications
during construction
Productive elements Materials ( M ) 2.5
Delay in materials delivery Productive elements Materials ( M ) 2.5
Shortage of technical professionals in the
contractor's organization
Internal Environment (IE) Contractor 2.5
Insufficient equipments Productive elements Equipments ( E ) 2.4
Failure to utilize tools to manage the project
symmetrically
Internal Environment (IE) Owner 2.4
Poor leadership on part of the sub-contractors Internal Environment (IE) Contractor 2.4
Financing by contractor during construction Internal Environment (IE) Contractor 2.4
Poor planning and scheduling of the project by
the contractor
Internal Environment (IE) Contractor 2.3
Changes in government regulations and laws External Environment Government Regulations 2.3
Delays in site preparation Internal Environment (IE) Owner 2.3
Improper project feasibility study Internal Environment (IE) Consultant / Designer 2.3
Safely rules and regulations aren’t followed
within the contractors organization
Internal Environment (IE) Contractor 2.3
Shortage of equipments Productive elements Equipments ( E ) 2.3
Mistakes in soil investigation Internal Environment (IE) Consultant / Designer 2.2
Jamal M. Assbeihat
http://www.iaeme.com/IJCIET/index.asp 30 editor@iaeme.com
REASON Category Sub Category
Avg.
rate
Using obsolete technology Internal Environment (IE) Contractor 2.2
Lack of communication with consultant / owner Internal Environment (IE) Contractor 2.2
Delays in contractor's payments to
subcontractors
Internal Environment (IE) Contractor 2.1
Problem with neighbors External Environment Other 2.0
Unrealistic project schedule Internal Environment (IE) Contractor 2.0
Accidents during construction External Environment Other 1.9
We notice that the Shortage of man power (skilled, semiskilled, unskilled) were
considered to be the first and the most frequent causes of delay in private projects in
Jordan from the view point of the consultants and contractors and it’s the first
according to the average of the three groups. For the owner, the shortage of materials
was the most frequent cause, and it was one of the most important four causes for the
three groups.
The Jordanian construction industry suffers from the shortage of skilled man
power because of the high wages demanded by the skilled foreign man power, and
that is why the contractor depends on cheap, unskilled labor.
Delay in the approval of contractor submissions by the engineer and that’s a very
important factor that the contractor complains from, and it’s the second most
important reason in the contractor points of view. In general the contractor can't start
any work or finish it without the approval of the engineer, so in general that process
delays the project. In some cases we notice that in some contracts the engineer got a
specific time to give the approval to the contractor (24 hours as an example) and
that’s cause a lot of delay in the project because the contractor can't work before
getting that approval. And in some other cases the contractor starts his work without
the engineer approval and in that case the engineer has the right to make the
contractor does that work again.
Shortage of materials is the third most frequent cause according to the point of
view of the contractor consultant and owner and it’s the most frequent reason among
the owners point of view. And the critical importance of this cause might come from a
sudden increase in the cost of materials, and that might be a result of the increasing in
demand on a specific material, monopoly of a specific material or import and export
problems, so it's hard to get the enough quantity of that material.
The relationship between different subcontractors’ schedules was one of the most
important delay causes according to the average of the three groups .The critical
importance of this cause can be seen clearly by noticing that one of the most
important delay causes by the consultant was "Insufficient coordination among the
parties by the contractor", and by the owner was " The relationship between different
subcontractors’ schedules ". Therefore both consultant and owner are blaming the
contractor for his poor project implementation, coordination and planning. In
addition, there is a strong agreement among the respondents on some of the lowest
causes which are: "Accidents during construction'', "Problem with neighbors "and"
Changes in government regulations and laws".
A one-way analysis of variance ANOVA was conducted among the means of
responses from the three groups to check for any significant differences among the
groups perceptions regarding the importance of the various delay causes.
Factors Affecting Delays on Private Construction Projects
http://www.iaeme.com/IJCIET/index.asp 31 editor@iaeme.com
The mean values under the three groups, F statistics, and the P values at which
hypothesis of equality of mean values across different groups could be rejected were
calculated .
The tabular critical F value at the 0.05 level for 2° and 117° degree of freedom is
approximately (3.074).
From the analysis, it was found that there were statistically non-significant
differences among the respondent groups over the following sample of causes:
• Shortage in labor (F = 1.65, P = 0.196)
• Labor productivity (F = 1.93, P = 0.15)
• Shortage of materials (F = 0.08, P = 0.923)
• Delay in materials delivery (F = 2.27, P = 0.108)
• Changes in materials types and specifications during construction. (F = 0.4, P =
0.674)
The following causes have the highest F values which indicate a very strong
agreement between the respondents from the three groups over the following sample
of causes:
• Shortage of manpower (skilled, semiskilled, unskilled labor), (F = 3.33, P = 0.039)
• Shortage of equipments (F = 5.96, P = 0.003)
• Safely rules and regulations aren't followed within the contractors organization (F =
4.47, P = 0.013)
• Delays in contractor's payments to subcontractors. (F = 5.81, P = 0.004)
• Large number of participants of project implementation. (F = 3.73, P = 0.027)
5. CONCLUSIONS AND RECOMMENDATIONS
The stated objective of this paper is to identify the causes of delay that produce the
greatest effects and the extent to which these effects can be ameliorated in the private
construction industry in Jordan. A literature review was conducted to identify the
causes of delay stipulated in the literature.
The importance index of each cause is calculated as an average of the frequency
indices of each cause. 45 causes of delay were identified through research. The
identified causes are combined into three categories. The field survey included 50
consultants, 50 contractors, and 20 owners. Data then collected were analyzed by
frequency and importance.
However, the result of this study indicated that Shortage of manpower (skilled,
semiskilled, unskilled labor), Delay in the approval of contractor submissions by the
engineer, Shortage of materials and the relationship between different subcontractors’
schedules are the major causes of delays in private projects in Jordan.
Owners specified that causes of delay are related to consultant and contractor; the
consultants specified that the causes of delay are related to the contractor and the
owners, and the contractors specified that the causes of delay are related to the
consultants and owners, so we notice that each party of the project is blaming the
other two parties.
In general, two of the three parties (Consultant and Contractor) had an agreement
over the most important cause which is Shortage of manpower (skilled, semiskilled,
unskilled labor), and there was an agreement between two parties on the other top
ranked causes.
Jamal M. Assbeihat
http://www.iaeme.com/IJCIET/index.asp 32 editor@iaeme.com
All parties agree that the following causes are the least important: accidents during
construction and problems with neighbors.
The following points can be recommended by all parties in order to minimize and
control delays in construction projects:
Consultants should look to the following points:
• Avoid delay in reviewing and approving design documents.
• Avoid the delay in giving the approval for the contractor to precede the work.
Contractors should consider the following factors:
• Shortage and low productivity of labor: enough number of labors should be assigned
and be motivated to improve productivity.
• Do some more coordination between subcontractors’ schedules.
• Avoid insufficient coordination among the parties by the contractor.
• Financial and cash flow problems: contractor should manage his financial resources
and plan cash flow by utilizing progress payment.
Owners should give special attention to the following factors:
• Avoid too many changes in orders in the project after the bidding period.
• Be faster in his decision making so he won't delay the project.
• Avoid the delay in payments for each of the contractor and consultant.
• Check for resources and capabilities, before awarding the contract to the lowest
bidder.
REFERENCES
[1] Assaf SA, Al-Hejji Sadiq. Causes of delay in large construction projects.
International Journal of Project Management 2006; 24(4):349-357.
[2] Odeh AM, Battaineh H T. Causes of construction delay: traditional contracts.
International Journal of Project Management 2002; 20(1):67-73.
[3] Sweis G., Sweis R., Abu Hammad A. and Shboul A. Delays in construction
projects: The case of Jordan. International Journal of Project Management
2008;26(7):665-674.
[4] Kumaraswamy Mohan M, Chan Daniel W. M. Contributors to construction
delays. Construction Management and Economics 1998; 16 (1):17-29.
[5] Sambasivan Murali, Soon Yau Wen. Causes and effects of delays in Malaysian
construction industry. International Journal of Project Management 2007;25
(5):517-526.
[6] Frimponga Yaw, Oluwoyeb Jacob, Crawford Lynn. Causes of delay and cost
overruns in construction of groundwater projects in a developing countries;
Ghana as a case study. International Journal of Project Management 2003; 21
(4):321-326.
[7] Ogunlana Stephen O, Promkuntong Krit. Construction delays in a fast-growing
economy: comparing Thailand with other economies. International Journal of
Project Management 1996;14(1):37–45.
[8] Kalib Chabota, Muya Mundia and Mumba Kanyuka. Cost escalation and
schedule delays in road construction projects in Zambia. International Journal of
Project Management 2009; 27(5):522-531.
Factors Affecting Delays on Private Construction Projects
http://www.iaeme.com/IJCIET/index.asp 33 editor@iaeme.com
[9] Kaming Peter F., Olomolaiye Paul O., Holt Gary D., Harris Frank C. Factors
influencing construction time and cost overruns on high-rise projects in
Indonesia. Construction Management and Economics 1997; 15(1):83-94.
[10] Toor Shamas-Ur-Rehman, Ogunlana Stephen O. Problems causing delays in
major construction projects in Thailand. Construction Management and
Economics 2008; 26(4):395-408.
[11] Koushki P. A , Al-Rashid K. and Kartam N. Delays and cost increases in the
construction of private residential projects in Kuwait. Construction Management
and Economics 2005; 23(3):285-294.
[12] Marzouk Mohamed, El-Dokhmasey Ahmed, El-Said Moheeb. Assessing
Construction Engineering-Related Delays: Egyptian Perspective. Journal of
Professional Issues in Engineering Education and Practice 2008; 134(3):315-326.
[13] Abd El-Razek M. E, Bassioni H. A, Mobarak A. M. Causes of Delay in Building
Construction Projects in Egypt. Egyptian Perspective. Journal of Professional
Issues in Engineering Education and Practice 2008; 134(11):831-841.
[14] Al-Kharashi Adel, Skitmore Martin. Causes of delays in Saudi Arabian public
sector construction projects. Construction Management and Economics 2009;
27(1):3-23.
[15] Faridi Arshi Shakeel, El-Sayegh Sameh Monir. Significant factors causing delay
in the UAE construction industry. Construction Management and Economics
2006; 24(11):1167–1176.
[16] S.R. Kannan and R. Vinodhinisri, Work Quantity Based Decision Support
Scheduling Model For Large Construction Projects, International Journal of Civil
Engineering and Technology, 5(3), 2014, pp. 226-232.
[17] Paul Louzolo-Kimbembe and Benoîtromaric Mampika-Bathy, Improvement of
The Model of Minimization of The Costs in A Time-Overrun Context: Case of
Construction Projects, International Journal of Civil Engineering and
Technology, 5(9), 2014, pp. 114-134.
[18] Zaneldin Essam K. Construction claims in United Arab Emirates: Types, causes,
and frequency. International Journal of Project Management 2006; 24(5):453–
459.

Weitere ähnliche Inhalte

Was ist angesagt?

Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Charles Abraham Scheck
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libreUTHM
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Managementijsrd.com
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Sankalp Swarnkar
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...World-Academic Journal
 
Causes and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in KuwaitCauses and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in KuwaitIJERA Editor
 
Causes of Variation Orders 1268
Causes of Variation Orders 1268Causes of Variation Orders 1268
Causes of Variation Orders 1268HASHIM HANIF
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...iosrjce
 
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )Engr_Emad Khan
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...IJERA Editor
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A ReviewIRJET Journal
 
Delay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodDelay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodIRJET Journal
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET Journal
 
TIME AND COST OVERRUN IN DELIVERY OF GOVERNMENT BUILDINGS IN UTTAR PRADESH: T...
TIME AND COST OVERRUN IN DELIVERY OF GOVERNMENT BUILDINGS IN UTTAR PRADESH: T...TIME AND COST OVERRUN IN DELIVERY OF GOVERNMENT BUILDINGS IN UTTAR PRADESH: T...
TIME AND COST OVERRUN IN DELIVERY OF GOVERNMENT BUILDINGS IN UTTAR PRADESH: T...IAEME Publication
 

Was ist angesagt? (18)

Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libre
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Management
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
 
Causes and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in KuwaitCauses and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in Kuwait
 
Causes of Variation Orders 1268
Causes of Variation Orders 1268Causes of Variation Orders 1268
Causes of Variation Orders 1268
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
 
D012261521
D012261521D012261521
D012261521
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A Review
 
33 article text-127-1-10-20181005
33 article text-127-1-10-2018100533 article text-127-1-10-20181005
33 article text-127-1-10-20181005
 
Ijciet 10 01_088
Ijciet 10 01_088Ijciet 10 01_088
Ijciet 10 01_088
 
Delay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodDelay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index Method
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
TIME AND COST OVERRUN IN DELIVERY OF GOVERNMENT BUILDINGS IN UTTAR PRADESH: T...
TIME AND COST OVERRUN IN DELIVERY OF GOVERNMENT BUILDINGS IN UTTAR PRADESH: T...TIME AND COST OVERRUN IN DELIVERY OF GOVERNMENT BUILDINGS IN UTTAR PRADESH: T...
TIME AND COST OVERRUN IN DELIVERY OF GOVERNMENT BUILDINGS IN UTTAR PRADESH: T...
 

Ähnlich wie FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS

IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...IRJET Journal
 
CSCM Causes of project delay
CSCM Causes of project delayCSCM Causes of project delay
CSCM Causes of project delayEst
 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET Journal
 
10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docx10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docxEbrahimJemal4
 
An Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in BahrainAn Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in BahrainIJRES Journal
 
Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...Associate Professor in VSB Coimbatore
 
Management of government funded construction projects in ghana
Management of government funded construction projects in ghanaManagement of government funded construction projects in ghana
Management of government funded construction projects in ghanaAlexander Decker
 
Prospects of building information modeling (bim) in malaysian construction in...
Prospects of building information modeling (bim) in malaysian construction in...Prospects of building information modeling (bim) in malaysian construction in...
Prospects of building information modeling (bim) in malaysian construction in...Alexander Decker
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET Journal
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsRick Vogel
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET Journal
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTIRJET Journal
 
Factors Affecting Cost Escalation in Construction Projects in Gaza Strip
Factors Affecting Cost Escalation in Construction Projects in Gaza StripFactors Affecting Cost Escalation in Construction Projects in Gaza Strip
Factors Affecting Cost Escalation in Construction Projects in Gaza StripDr. Amarjeet Singh
 
Literature Review - Final
Literature Review - FinalLiterature Review - Final
Literature Review - FinalRifan Fhazi
 
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...IAEME Publication
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...IRJET Journal
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsDr. Amarjeet Singh
 

Ähnlich wie FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS (20)

IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
 
CSCM Causes of project delay
CSCM Causes of project delayCSCM Causes of project delay
CSCM Causes of project delay
 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
 
20320140503023
2032014050302320320140503023
20320140503023
 
10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docx10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docx
 
An Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in BahrainAn Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in Bahrain
 
Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...
 
Management of government funded construction projects in ghana
Management of government funded construction projects in ghanaManagement of government funded construction projects in ghana
Management of government funded construction projects in ghana
 
Prospects of building information modeling (bim) in malaysian construction in...
Prospects of building information modeling (bim) in malaysian construction in...Prospects of building information modeling (bim) in malaysian construction in...
Prospects of building information modeling (bim) in malaysian construction in...
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
Ijetr012001
Ijetr012001Ijetr012001
Ijetr012001
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
 
Factors Affecting Cost Escalation in Construction Projects in Gaza Strip
Factors Affecting Cost Escalation in Construction Projects in Gaza StripFactors Affecting Cost Escalation in Construction Projects in Gaza Strip
Factors Affecting Cost Escalation in Construction Projects in Gaza Strip
 
Literature Review - Final
Literature Review - FinalLiterature Review - Final
Literature Review - Final
 
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
 
Ijciet 08 02_005
Ijciet 08 02_005Ijciet 08 02_005
Ijciet 08 02_005
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 

Mehr von IAEME Publication

IAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME_Publication_Call_for_Paper_September_2022.pdfIAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME_Publication_Call_for_Paper_September_2022.pdfIAEME Publication
 
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...IAEME Publication
 
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURSA STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURSIAEME Publication
 
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURSBROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURSIAEME Publication
 
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONSDETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONSIAEME Publication
 
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONSANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONSIAEME Publication
 
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINOVOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINOIAEME Publication
 
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...IAEME Publication
 
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMYVISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMYIAEME Publication
 
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...IAEME Publication
 
GANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICEGANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICEIAEME Publication
 
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...IAEME Publication
 
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...IAEME Publication
 
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...IAEME Publication
 
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...IAEME Publication
 
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...IAEME Publication
 
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...IAEME Publication
 
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...IAEME Publication
 
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...IAEME Publication
 
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENTA MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENTIAEME Publication
 

Mehr von IAEME Publication (20)

IAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME_Publication_Call_for_Paper_September_2022.pdfIAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME_Publication_Call_for_Paper_September_2022.pdf
 
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
 
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURSA STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
 
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURSBROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
 
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONSDETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
 
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONSANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
 
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINOVOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
 
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
 
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMYVISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
 
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
 
GANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICEGANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICE
 
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
 
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
 
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
 
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
 
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
 
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
 
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
 
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
 
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENTA MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
 

Kürzlich hochgeladen

notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdfSuman Jyoti
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfRagavanV2
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01KreezheaRecto
 

Kürzlich hochgeladen (20)

notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 

FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS

  • 1. http://www.iaeme.com/IJCIET/index.asp 22 editor@iaeme.com International Journal of Civil Engineering and Technology (IJCIET) Volume 7, Issue 2, March-April 2016, pp. 22-33, Article ID: IJCIET_07_02_002 Available online at http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=7&IType=2 Journal Impact Factor (2016): 9.7820 (Calculated by GISI) www.jifactor.com ISSN Print: 0976-6308 and ISSN Online: 0976-6316 © IAEME Publication FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS Jamal M. Assbeihat Al- Balqa’ Applied University- Faculty of Engineering and Technology, Jordan ABSTRACT Construction Delays is a major of concern in the private projects construction industry in Jordan. With the fact that construction delays are nothing but loss of time and money such study was conducted to identify the factors that causes the construction delays. Therefore three groups consist of consultants, contractors and owners were questioned, Shortage of manpower (skilled, semiskilled, unskilled labor), Delay in the approval of contractor submissions by the engineer, Shortage of materials, The relationship between different subcontractors’ schedules were the most important factors that cause delays in private projects sector in Jordan. Furthermore one way ANOVA analysis conducted to select factors that share agreement between the three groups. Key words: Construction Delays; Construction Projects; Jordanian Construction Sector. Cite this Article: Jamal M. Assbeihat, Factors Affecting Delays on Private Construction Projects, International Journal of Civil Engineering and Technology, 7(2), 2016, pp. 22-33. http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=7&IType=2 1. INTRODUCTION In construction, delay could be defined as the time overrun either beyond completion date specified in a contract, or beyond the date that the parties agreed upon for delivery of a project. It is a project slipping over its planned schedule and is considered as common problem in construction projects. To the owner, delay means loss of revenue through lack of production facilities and rent-able space or a dependence on present facilities. In some cases, to the contractor, delay means higher overhead costs because of longer work period, higher material costs through inflation, and due to labor cost increases and maybe lost opportunities for new projects because of diminished financial capabilities (Assaf and Al-Hejji 2006). The successful execution of construction projects and keeping them within estimated cost and prescribed schedules depend on a methodology that requires sound engineering judgment. To the dislike of all the participants (owners, contractors, and
  • 2. Factors Affecting Delays on Private Construction Projects http://www.iaeme.com/IJCIET/index.asp 23 editor@iaeme.com consultants), however, many projects experience extensive delays and there by exceed initial time and cost estimates (Odeh and Battaineh, 2002). Recently, the Jordanian construction industry has been undergoing a boom (Sweis et al., 2008). A huge number of large-scale private projects are currently under construction or in the planning and contract-awarding phase. Therefore understanding the causes of delays and their importance is a major of concern in order to minimize and avoid the delays and their corresponding expenses in the field of private projects construction industry in Jordan. The main objectives of this study include the following: • To identify the causes of delays in private projects construction in Jordan. • To identify the importance of each delay cause in private projects construction in Jordan. • To study the differences in perceptions of the three major parties in any constructions: (consultants, contractors, and owners). 2. LITERATURE REVIEW Many studies were conducted on the causes of delays in construction projects in different developing countries, including Middle East. Several articles have discussed causes of delay in construction projects in numerous manners. Some studies identified the main causes of delay in several countries and various project types, while other studies discussed the delay analysis methods and the proposed ways to mitigate it. Kumaraswamy Moha and Chan Daniel ( 1998) in their study provides pointers to appropriate strategies and particular measures that may be adopted to avoid and/or mitigate project delays by focusing on the direct and indirect common contributors to same, such as delays in design information and productivity levels. To them, the main reasons behind projects delays in Hong Kong are : unforeseen ground conditions, poor site management and supervision, low speed in decision making involving all project teams, client- initiated variations, necessary variations of works, Inadequate contractor experience. Investigating the causes and effects of delays facing in the Malaysian construction industry Sambasivan Murali and Soon Yau Wen (2007) found that the most important delay factors are: contractor’s improper planning, contractor’s poor site management, inadequate contractor experience, inadequate client’s finance and payments for completed work, problems with subcontractors. Frimpong Yaw et al. (2003) in their study identifies and examines the causes of delay and cost overruns in the construction of groundwater projects in Ghana. The results of this study were that the reasons behind the delays are respectively: poor contractor management, monthly payment difficulties from agencies, material procurement, poor technical performances, and escalation of material prices according to their degree of influence. The major sources of delays on highrise building construction projects in Thailand are identified by Ogunlana Stephen and Promkuntong Krit (1996): shortage of construction materials, shortage of site workers, incomplete drawings by designers, materials management problems by contractors, deficiencies in organization. Kalib Chabota et al. (2009) in their study about schedule delays in road construction in Zambia found that the most important causes of delays are: delayed payment, protracted financial processes in client organization, financial difficulties, contract modification, and economic hardships. Kaming Peter et al. (1997) studied about time and cost overruns in high-rise construction in Indonesia. The results of this study were that the major causes of time overruns are: design changes, inadequate planning,
  • 3. Jamal M. Assbeihat http://www.iaeme.com/IJCIET/index.asp 24 editor@iaeme.com inaccuracy of materials estimating, poor labor productivity, inaccurate prediction of craftsmen production rate. Toor Shamas-Ur-Rehman and Ogunlana Stephen (2008) studied the Problems causing delays in major construction projects in Thailand. The findings showed that most problems related to designers, clients, contractors and finance were rated among the top problems; whereas a multicultural and multilingual environment, large numbers of project participants and the involvement of foreign designers were perceived as not very significant problems. Many studies have been conducted in the same manner in the region of the middle east. Koushki et al. (2005) studied the problems experienced during the construction of private residences in the state of Kuwait. The results of the study were that the main reasons that cause the delays in the construction of private residential projects in Kuwait are: the number of change orders, financial constraints, and owners’ lack of experience in construction, material-related problems, and weather related problems. In Egypt, Marzouk Mohamed (2008) in their study highlighted the importance and the effect of each of the causes of delays and focused upon the most important causes. The causes are included the delay in receiving design documents, delay in the preparation process due to lack of (resources, experience, and management), unforeseen conditions, mistakes/changes in the design documents provided by the employer, delay in responding to contractor’s queries. In Egypt also, Abd El-Razek et al. (2008) in their studied the actual causes of delay that affect building projects in Egypt in order to minimize and avoid the delays and their corresponding expenses. The results of this study were that the major delay causes in building projects in Egypt are respectively: financing by contractor during construction, delays in contractor’s payment by owner, design changes by owner or his agent during construction, partial payments during construction, non utilization of professional construction/contractual management. Assaf Sadi and Al-Hejji Sadiq (2006) in their study identified the causes of delays in construction in Eastern Province of Saudi Arabia. They found that the major delay causes in large construction projects are: change orders by owner during construction, delay in progress payments, ineffective planning and scheduling by contractor, poor site management and supervision by contractor, difficulties in financing by contractor. Another study in Saudi Arabia done by Al-Kharashi and Skitmore (2009) stated that, in the case where the project is a public building or facility, the complications increase as the client is a government department. Then the main reasons that causes the delays in construction projects in Saudi Arabian public sector are: delay in progress payments by the owner, non-payment of the contractor claim, lack of finance to complete the work by the client, late in revising and approving design documents by owner, delay in approving sample materials by owner. Faridi and El-Sayegh (2006) in their study identified the most significant causes of delay in the UAE construction industry to be able to find ways to avoid them, or at least, mitigate their impact. The results of this study were that the critical factors that causes the delays in the UAE construction industry are respectively: preparation and approval of drawings, inadequate early planning of the project, slowness of the owner's decision-making process, shortage of manpower, poor supervision and poor site management. On th other hand, Zaneldin (2006) identified several problem areas in the construction process in UAE. The causes by this study are: delayed payments, protracted financial processes in client organizations, financial difficulties that
  • 4. Factors Affecting Delays on Private Construction Projects http://www.iaeme.com/IJCIET/index.asp 25 editor@iaeme.com accompany the delayed release of funds by client organizations, contract modification, and economic hardships. In Jordan, less attention have been paid. Odeh and Battaineh (2002) in their study -in which the objective of it was to identify the major causes of delay in the construction industry and to assess the relative importance of these causes for the traditional adversarial type of contracts from the viewpoint of construction contractors and consultants. The results of their study were that the most important factors of delay according to the contractor are respectively: Labor productivity, Owner interference, and inadequate contractor experience. While the factors of delay according to the consultant are: Inadequate contractor experience, Finance and payments of completed work, and Subcontractors. Sweis et al. (2008) in their study stated that delays in construction projects are common in the Jordanian construction industry and that the most important reasons behind the construction delays in Jordan are respectively: financial difficulties faced by the contractor, too many change orders from owner, poor planning and scheduling of the project by the contractor, presence of unskilled labor, shortage of technical professionals in the contractor’s organization. 3. METHODOLOGY Based on the results of all the reviewed studies, specially the Jordanian ones, we develop a list of factors, which might affect the delays in the Jordanian private projects and categorized them into three main groups. A questionnaire was developed in order to evaluate the frequency of occurrence and importance of the identified causes. The design of the questionnaire has been based on Assaf and Al-Hejji (2006) and Sweis (2008) refrences, and the study questionnaire is based on Open Conversion System proposed by Drewin. According to Drewin the construction process influenced by technologies and both external and internal environments. Therefore, a combination between Drewin's open conversion system and delay causes identified in previous studies results in 45 potential delay factors were summarized into three major categories: Production Elements (PE) includes: Labor (L), Materials (M) and Equipment (E) related factors. Internal Environment (IE) includes: Consultant, Contractor and Owner related factors. External Environment (EE) includes: Weather, Government Regulations and Other reasons The consultants, contractors, and owners of an accomplished sixty projects in year 2014, with a cost more than 1.3 million dollars were targeted. Then the questionnaire was distributed by hand. Therefore a sample consists of 60 consultants, 60 contractors, and 35 owners selected (many residential and trade buildings have the same owner- organization). Responses to the questionnaire were then collected and analyzed. The responses consisted of 50 consultants, 50 contractors, and 20 owners. They were asked to grade each delay cause from a scale of 1 to 5 in which number 5 indicates a very strong affecting cause on the construction projects and number 1 indicates a minor cause of delays in the construction projects. 4. DATA ANALYSIS AND RESULTS The delay causes was ranked by taking the average of the respondents for each individual group/participant (consultant, contractor, owner), then the average of the three groups was calculated separately. The resulting averages were ranked in
  • 5. Jamal M. Assbeihat http://www.iaeme.com/IJCIET/index.asp 26 editor@iaeme.com descending order according to the highest average in the group response. The ranks are presented in tables 4.1, 4.2 and 4.3 respectively. Table 4.1 Reasons’ Ranking for Consultant REASON Category Sub Category Avg. rate Shortage of manpower (skilled, semiskilled, unskilled labor) Productive elements Labor ( L ) 3.5 Too many change orders from owner Internal Environment (IE) Owner 3.4 Delays in contractor’s payment by owner Internal Environment (IE) Owner 3.3 Insufficient coordination among the parties by the contractor Internal Environment (IE) Contractor 3.3 Shortage of equipments Productive elements Equipments ( E ) 3.3 Slowness of the owner decision making process Internal Environment (IE) Owner 3.3 Financing by owner during construction Internal Environment (IE) Contractor 3.2 Shortage of materials Productive elements Materials ( M ) 3.2 Delay in the approval of contractor submissions by the engineer Internal Environment (IE) Consultant / Designer 3.1 Preparation and waiting for approval of shop drawings and material samples Internal Environment (IE) Consultant / Designer 3.1 Delays in contractor's payments to subcontractors Internal Environment (IE) Contractor 3.1 Delay in materials delivery Productive elements Materials ( M ) 3.1 Labor productivity Productive elements Labor ( L ) 3.1 Poor planning and scheduling of the project by the contractor Internal Environment (IE) Contractor 3.0 The relationship between different subcontractors’ schedules Internal Environment (IE) Contractor 3.0 Shortage of technical professionals in the contractor's organization Internal Environment (IE) Contractor 3.0 Insufficient equipments Productive elements Equipments ( E ) 3.0 Shortage in labor Productive elements Labor ( L ) 3.0 Severe weather conditions on the job site External Environment Weather 2.9 Mistakes in soil investigation Internal Environment (IE) Consultant / Designer 2.9 Unexpected foundation conditions encountered in the field Internal Environment (IE) Consultant / Designer 2.9 Slow response by the consultant engineer regarding testing and inspection Internal Environment (IE) Consultant / Designer 2.9 Financing by contractor during construction Internal Environment (IE) Owner 2.9 Over-design increasing the overall cost Internal Environment (IE) Consultant / Designer 2.7 Failure to utilize tools to manage the project symmetrically Internal Environment (IE) Owner 2.7 Delays in site preparation Internal Environment (IE) Owner 2.7 Unrealistic project schedule Internal Environment (IE) Contractor 2.7 Poor leadership on part of the sub-contractors Internal Environment (IE) Contractor 2.7 Poor communication with the suppliers Internal Environment (IE) Contractor 2.7 Use of unacceptable construction techniques by the contractor Internal Environment (IE) Contractor 2.7 Failure of equipments Productive elements Equipments ( E ) 2.7
  • 6. Factors Affecting Delays on Private Construction Projects http://www.iaeme.com/IJCIET/index.asp 27 editor@iaeme.com REASON Category Sub Category Avg. rate Changes in materials types and specifications during construction Productive elements Materials ( M ) 2.7 Improper technical study by the contractor during the bidding stage Internal Environment (IE) Contractor 2.6 Difficulties in obtaining work permits External Environment Government Regulations 2.6 Improper project feasibility study Internal Environment (IE) Consultant / Designer 2.6 Lack of communication with consultant / owner Internal Environment (IE) Contractor 2.6 Poorly written contracts Internal Environment (IE) Consultant / Designer 2.5 Lack of database in estimating activity duration and resources Internal Environment (IE) Contractor 2.5 Delay in mobilization Internal Environment (IE) Contractor 2.5 Changes in government regulations and laws External Environment Government Regulations 2.4 Using obsolete technology Internal Environment (IE) Contractor 2.4 Accidents during construction External Environment Other 2.2 Large number of participants of project implementation Internal Environment (IE) Contractor 2.2 Safely rules and regulations aren’t followed within the contractors organization Internal Environment (IE) Contractor 2.0 Problem with neighbors External Environment Other 1.8 Table 4, 2 Reason Ranking for Contractor REASON Category Sub Category Avg. rate Shortage of manpower (skilled, semiskilled, unskilled labor) Productive elements Labor ( L ) 3.6 Delay in the approval of contractor submissions by the engineer Internal Environment (IE) Consultant / Designer 3.4 Difficulties in obtaining work permits External Environment Government Regulations 3.3 Slowness of the owner decision making process Internal Environment (IE) Owner 3.3 Too many change orders from owner Internal Environment (IE) Owner 3.3 Preparation and waiting for approval of shop drawings and material samples Internal Environment (IE) Consultant / Designer 3.3 Shortage of equipments Productive elements Equipments ( E ) 3.3 Shortage of materials Productive elements Materials ( M ) 3.3 Labor productivity Productive elements Labor ( L ) 3.3 Shortage in labor Productive elements Labor ( L ) 3.2 Financing by owner during construction Internal Environment (IE) Contractor 3.1 Poor leadership on part of the sub-contractors Internal Environment (IE) Contractor 3.1 Delay in materials delivery Productive elements Materials ( M ) 3.1 Improper technical study by the contractor during the bidding stage Internal Environment (IE) Contractor 3.0 Slow response by the consultant engineer regarding testing and inspection Internal Environment (IE) Consultant / Designer 3.0 Financing by contractor during construction Internal Environment (IE) Owner 3.0 Insufficient coordination among the parties by the contractor Internal Environment (IE) Contractor 3.0 Shortage of technical professionals in the Internal Environment (IE) Contractor 3.0
  • 7. Jamal M. Assbeihat http://www.iaeme.com/IJCIET/index.asp 28 editor@iaeme.com REASON Category Sub Category Avg. rate contractor's organization Failure of equipments Productive elements Equipments ( E ) 3.0 Unexpected foundation conditions encountered in the field Internal Environment (IE) Consultant / Designer 2.9 Delays in contractor's payments to subcontractors Internal Environment (IE) Contractor 2.9 Use of unacceptable construction techniques by the contractor Internal Environment (IE) Contractor 2.9 Insufficient equipments Productive elements Equipments ( E ) 2.9 Delays in contractor’s payment by owner Internal Environment (IE) Owner 2.8 Over-design increasing the overall cost Internal Environment (IE) Consultant / Designer 2.8 Poor planning and scheduling of the project by the contractor Internal Environment (IE) Contractor 2.8 Delay in mobilization Internal Environment (IE) Contractor 2.8 Changes in materials types and specifications during construction Productive elements Materials ( M ) 2.8 Changes in government regulations and laws External Environment Government Regulations 2.7 Severe weather conditions on the job site External Environment Weather 2.7 Unrealistic project schedule Internal Environment (IE) Contractor 2.7 The relationship between different subcontractors’ schedules Internal Environment (IE) Contractor 2.7 Lack of database in estimating activity duration and resources Internal Environment (IE) Contractor 2.7 Delays in site preparation Internal Environment (IE) Owner 2.6 Poorly written contracts Internal Environment (IE) Consultant / Designer 2.6 Improper project feasibility study Internal Environment (IE) Consultant / Designer 2.6 Mistakes in soil investigation Internal Environment (IE) Consultant / Designer 2.6 Large number of participants of project implementation Internal Environment (IE) Contractor 2.6 Lack of communication with consultant / owner Internal Environment (IE) Contractor 2.6 Safely rules and regulations aren’t followed within the contractors organization Internal Environment (IE) Contractor 2.6 Poor communication with the suppliers Internal Environment (IE) Contractor 2.4 Problem with neighbors External Environment Other 2.4 Failure to utilize tools to manage the project symmetrically Internal Environment (IE) Owner 2.4 Using obsolete technology Internal Environment (IE) Contractor 2.4 Accidents during construction External Environment Other 2.3 Table 4.3 Reason’s Ranking for Owner REASON Category Sub Category Avg. rate Shortage of materials Productive elements Materials ( M ) 3.3 The relationship between different subcontractors’ schedules Internal Environment (IE) Contractor 3.3 Over-design increasing the overall cost Internal Environment (IE) Consultant / Designer 3.2 Delay in the approval of contractor submissions by the engineer Internal Environment (IE) Consultant / Designer 3.1 Preparation and waiting for approval of shop Internal Environment (IE) Consultant / Designer 3.1
  • 8. Factors Affecting Delays on Private Construction Projects http://www.iaeme.com/IJCIET/index.asp 29 editor@iaeme.com REASON Category Sub Category Avg. rate drawings and material samples Slowness of the owner decision making process Internal Environment (IE) Owner 3.0 Insufficient coordination among the parties by the contractor Internal Environment (IE) Contractor 3.0 Financing by owner during construction Internal Environment (IE) Owner 2.9 Too many change orders from owner Internal Environment (IE) Owner 2.9 Slow response by the consultant engineer regarding testing and inspection Internal Environment (IE) Consultant / Designer 2.9 Large number of participants of project implementation Internal Environment (IE) Contractor 2.9 Shortage of manpower (skilled, semiskilled, unskilled labor) Productive elements Labor ( L ) 2.8 Poorly written contracts Internal Environment (IE) Consultant / Designer 2.8 Unexpected foundation conditions encountered in the field Internal Environment (IE) Consultant / Designer 2.8 Poor communication with the suppliers Internal Environment (IE) Contractor 2.8 Labor productivity Productive elements Labor ( L ) 2.8 Shortage in labor Productive elements Labor ( L ) 2.7 Delays in contractor’s payment by owner Internal Environment (IE) Owner 2.7 Lack of database in estimating activity duration and resources Internal Environment (IE) Contractor 2.7 Use of unacceptable construction techniques by the contractor Internal Environment (IE) Contractor 2.7 Delay in mobilization Internal Environment (IE) Contractor 2.6 Difficulties in obtaining work permits External Environment Government Regulations 2.6 Severe weather conditions on the job site External Environment Weather 2.6 Improper technical study by the contractor during the bidding stage Internal Environment (IE) Contractor 2.6 Failure of equipments Productive elements Equipments ( E ) 2.6 Changes in materials types and specifications during construction Productive elements Materials ( M ) 2.5 Delay in materials delivery Productive elements Materials ( M ) 2.5 Shortage of technical professionals in the contractor's organization Internal Environment (IE) Contractor 2.5 Insufficient equipments Productive elements Equipments ( E ) 2.4 Failure to utilize tools to manage the project symmetrically Internal Environment (IE) Owner 2.4 Poor leadership on part of the sub-contractors Internal Environment (IE) Contractor 2.4 Financing by contractor during construction Internal Environment (IE) Contractor 2.4 Poor planning and scheduling of the project by the contractor Internal Environment (IE) Contractor 2.3 Changes in government regulations and laws External Environment Government Regulations 2.3 Delays in site preparation Internal Environment (IE) Owner 2.3 Improper project feasibility study Internal Environment (IE) Consultant / Designer 2.3 Safely rules and regulations aren’t followed within the contractors organization Internal Environment (IE) Contractor 2.3 Shortage of equipments Productive elements Equipments ( E ) 2.3 Mistakes in soil investigation Internal Environment (IE) Consultant / Designer 2.2
  • 9. Jamal M. Assbeihat http://www.iaeme.com/IJCIET/index.asp 30 editor@iaeme.com REASON Category Sub Category Avg. rate Using obsolete technology Internal Environment (IE) Contractor 2.2 Lack of communication with consultant / owner Internal Environment (IE) Contractor 2.2 Delays in contractor's payments to subcontractors Internal Environment (IE) Contractor 2.1 Problem with neighbors External Environment Other 2.0 Unrealistic project schedule Internal Environment (IE) Contractor 2.0 Accidents during construction External Environment Other 1.9 We notice that the Shortage of man power (skilled, semiskilled, unskilled) were considered to be the first and the most frequent causes of delay in private projects in Jordan from the view point of the consultants and contractors and it’s the first according to the average of the three groups. For the owner, the shortage of materials was the most frequent cause, and it was one of the most important four causes for the three groups. The Jordanian construction industry suffers from the shortage of skilled man power because of the high wages demanded by the skilled foreign man power, and that is why the contractor depends on cheap, unskilled labor. Delay in the approval of contractor submissions by the engineer and that’s a very important factor that the contractor complains from, and it’s the second most important reason in the contractor points of view. In general the contractor can't start any work or finish it without the approval of the engineer, so in general that process delays the project. In some cases we notice that in some contracts the engineer got a specific time to give the approval to the contractor (24 hours as an example) and that’s cause a lot of delay in the project because the contractor can't work before getting that approval. And in some other cases the contractor starts his work without the engineer approval and in that case the engineer has the right to make the contractor does that work again. Shortage of materials is the third most frequent cause according to the point of view of the contractor consultant and owner and it’s the most frequent reason among the owners point of view. And the critical importance of this cause might come from a sudden increase in the cost of materials, and that might be a result of the increasing in demand on a specific material, monopoly of a specific material or import and export problems, so it's hard to get the enough quantity of that material. The relationship between different subcontractors’ schedules was one of the most important delay causes according to the average of the three groups .The critical importance of this cause can be seen clearly by noticing that one of the most important delay causes by the consultant was "Insufficient coordination among the parties by the contractor", and by the owner was " The relationship between different subcontractors’ schedules ". Therefore both consultant and owner are blaming the contractor for his poor project implementation, coordination and planning. In addition, there is a strong agreement among the respondents on some of the lowest causes which are: "Accidents during construction'', "Problem with neighbors "and" Changes in government regulations and laws". A one-way analysis of variance ANOVA was conducted among the means of responses from the three groups to check for any significant differences among the groups perceptions regarding the importance of the various delay causes.
  • 10. Factors Affecting Delays on Private Construction Projects http://www.iaeme.com/IJCIET/index.asp 31 editor@iaeme.com The mean values under the three groups, F statistics, and the P values at which hypothesis of equality of mean values across different groups could be rejected were calculated . The tabular critical F value at the 0.05 level for 2° and 117° degree of freedom is approximately (3.074). From the analysis, it was found that there were statistically non-significant differences among the respondent groups over the following sample of causes: • Shortage in labor (F = 1.65, P = 0.196) • Labor productivity (F = 1.93, P = 0.15) • Shortage of materials (F = 0.08, P = 0.923) • Delay in materials delivery (F = 2.27, P = 0.108) • Changes in materials types and specifications during construction. (F = 0.4, P = 0.674) The following causes have the highest F values which indicate a very strong agreement between the respondents from the three groups over the following sample of causes: • Shortage of manpower (skilled, semiskilled, unskilled labor), (F = 3.33, P = 0.039) • Shortage of equipments (F = 5.96, P = 0.003) • Safely rules and regulations aren't followed within the contractors organization (F = 4.47, P = 0.013) • Delays in contractor's payments to subcontractors. (F = 5.81, P = 0.004) • Large number of participants of project implementation. (F = 3.73, P = 0.027) 5. CONCLUSIONS AND RECOMMENDATIONS The stated objective of this paper is to identify the causes of delay that produce the greatest effects and the extent to which these effects can be ameliorated in the private construction industry in Jordan. A literature review was conducted to identify the causes of delay stipulated in the literature. The importance index of each cause is calculated as an average of the frequency indices of each cause. 45 causes of delay were identified through research. The identified causes are combined into three categories. The field survey included 50 consultants, 50 contractors, and 20 owners. Data then collected were analyzed by frequency and importance. However, the result of this study indicated that Shortage of manpower (skilled, semiskilled, unskilled labor), Delay in the approval of contractor submissions by the engineer, Shortage of materials and the relationship between different subcontractors’ schedules are the major causes of delays in private projects in Jordan. Owners specified that causes of delay are related to consultant and contractor; the consultants specified that the causes of delay are related to the contractor and the owners, and the contractors specified that the causes of delay are related to the consultants and owners, so we notice that each party of the project is blaming the other two parties. In general, two of the three parties (Consultant and Contractor) had an agreement over the most important cause which is Shortage of manpower (skilled, semiskilled, unskilled labor), and there was an agreement between two parties on the other top ranked causes.
  • 11. Jamal M. Assbeihat http://www.iaeme.com/IJCIET/index.asp 32 editor@iaeme.com All parties agree that the following causes are the least important: accidents during construction and problems with neighbors. The following points can be recommended by all parties in order to minimize and control delays in construction projects: Consultants should look to the following points: • Avoid delay in reviewing and approving design documents. • Avoid the delay in giving the approval for the contractor to precede the work. Contractors should consider the following factors: • Shortage and low productivity of labor: enough number of labors should be assigned and be motivated to improve productivity. • Do some more coordination between subcontractors’ schedules. • Avoid insufficient coordination among the parties by the contractor. • Financial and cash flow problems: contractor should manage his financial resources and plan cash flow by utilizing progress payment. Owners should give special attention to the following factors: • Avoid too many changes in orders in the project after the bidding period. • Be faster in his decision making so he won't delay the project. • Avoid the delay in payments for each of the contractor and consultant. • Check for resources and capabilities, before awarding the contract to the lowest bidder. REFERENCES [1] Assaf SA, Al-Hejji Sadiq. Causes of delay in large construction projects. International Journal of Project Management 2006; 24(4):349-357. [2] Odeh AM, Battaineh H T. Causes of construction delay: traditional contracts. International Journal of Project Management 2002; 20(1):67-73. [3] Sweis G., Sweis R., Abu Hammad A. and Shboul A. Delays in construction projects: The case of Jordan. International Journal of Project Management 2008;26(7):665-674. [4] Kumaraswamy Mohan M, Chan Daniel W. M. Contributors to construction delays. Construction Management and Economics 1998; 16 (1):17-29. [5] Sambasivan Murali, Soon Yau Wen. Causes and effects of delays in Malaysian construction industry. International Journal of Project Management 2007;25 (5):517-526. [6] Frimponga Yaw, Oluwoyeb Jacob, Crawford Lynn. Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study. International Journal of Project Management 2003; 21 (4):321-326. [7] Ogunlana Stephen O, Promkuntong Krit. Construction delays in a fast-growing economy: comparing Thailand with other economies. International Journal of Project Management 1996;14(1):37–45. [8] Kalib Chabota, Muya Mundia and Mumba Kanyuka. Cost escalation and schedule delays in road construction projects in Zambia. International Journal of Project Management 2009; 27(5):522-531.
  • 12. Factors Affecting Delays on Private Construction Projects http://www.iaeme.com/IJCIET/index.asp 33 editor@iaeme.com [9] Kaming Peter F., Olomolaiye Paul O., Holt Gary D., Harris Frank C. Factors influencing construction time and cost overruns on high-rise projects in Indonesia. Construction Management and Economics 1997; 15(1):83-94. [10] Toor Shamas-Ur-Rehman, Ogunlana Stephen O. Problems causing delays in major construction projects in Thailand. Construction Management and Economics 2008; 26(4):395-408. [11] Koushki P. A , Al-Rashid K. and Kartam N. Delays and cost increases in the construction of private residential projects in Kuwait. Construction Management and Economics 2005; 23(3):285-294. [12] Marzouk Mohamed, El-Dokhmasey Ahmed, El-Said Moheeb. Assessing Construction Engineering-Related Delays: Egyptian Perspective. Journal of Professional Issues in Engineering Education and Practice 2008; 134(3):315-326. [13] Abd El-Razek M. E, Bassioni H. A, Mobarak A. M. Causes of Delay in Building Construction Projects in Egypt. Egyptian Perspective. Journal of Professional Issues in Engineering Education and Practice 2008; 134(11):831-841. [14] Al-Kharashi Adel, Skitmore Martin. Causes of delays in Saudi Arabian public sector construction projects. Construction Management and Economics 2009; 27(1):3-23. [15] Faridi Arshi Shakeel, El-Sayegh Sameh Monir. Significant factors causing delay in the UAE construction industry. Construction Management and Economics 2006; 24(11):1167–1176. [16] S.R. Kannan and R. Vinodhinisri, Work Quantity Based Decision Support Scheduling Model For Large Construction Projects, International Journal of Civil Engineering and Technology, 5(3), 2014, pp. 226-232. [17] Paul Louzolo-Kimbembe and Benoîtromaric Mampika-Bathy, Improvement of The Model of Minimization of The Costs in A Time-Overrun Context: Case of Construction Projects, International Journal of Civil Engineering and Technology, 5(9), 2014, pp. 114-134. [18] Zaneldin Essam K. Construction claims in United Arab Emirates: Types, causes, and frequency. International Journal of Project Management 2006; 24(5):453– 459.