Dynamic Scheduling Methodology (DSM)
with
Primavera™ P6
A whitepaper
by
Ej (Ted) Lister
Dynamic Scheduling Methodology (DSM) with Primavera™ P6
A whitepaper by Ej (Ted) Lister
1 of page 10 Copyright© 2014 – Ej (Ted) Lister
Contents
Introduction ..................................................................................................................................................2
Computer Technology and the Project Management Office (PMO) ....................................................2
Why Dynamic Scheduling Methodology (DSM)?......................................................................................2
Key benefits of DSM..............................................................................................................................3
Premise .....................................................................................................................................................4
The 3 Principles of a High-performance PMO: Methodology, Technology and People ...............................5
Methodology.........................................................................................................................................5
Technology............................................................................................................................................6
People ...................................................................................................................................................7
Risk Mitigation and Change Management....................................................................................................7
Risk Mitigation ......................................................................................................................................7
Change Management............................................................................................................................8
Project Plan...............................................................................................................................................8
Data Integrity and Document Control (DIDC).......................................................................................8
Illustrations .................................................................................................................................................10
Illustration 1.1: Dynamic Scheduling with Primavera™ P6 .................................................................10
Illustration 1.2: EvPM Curves..............................................................................................................10
Dynamic Scheduling Methodology (DSM) with Primavera™ P6
A whitepaper by Ej (Ted) Lister
2 of page 10 Copyright© 2014 – Ej (Ted) Lister
Introduction
Computer Technology and the Project Management Office (PMO)
In the past two decades advancements in computer technology have enhanced the capability
of a Project Scheduler to produce a very detailed Project Plan1
, with the added bonus of nice-
looking Gantt Charts, KPI Dashboards, and impressive reports and graphs. Advancements in
computer technology also made possible, for scheduling software such as Primavera™ P6, to
self-perform the scheduling function through a series of dynamic programming algorithms
capable of scheduling up to eighty percent of a project’s activities, with the speed and accuracy
needed to keep pace with the ever-changing environment of construction or maintenance
projects—more so than any Project Scheduler could ever dream of doing manually. So why is it
that most Project Schedulers insist on creating Project Plans using manual, static scheduling
techniques? Why is it that many PMO/Project Controls Teams struggle to control work and
manage costs and resources?
This paper explores how dynamic scheduling has the significant potential to become the
defining methodology in project management and controls, as well as the optimal way to balance
the benefits of dynamic scheduling against static scheduling in an effort to control direct and
indirect project activities in real-time using the latest technology.
For the past sixteen years I have been experimenting with creating scheduling methodologies
designed to control each phase of complex and risky projects—such as STO (Shutdowns,
Turnarounds and Outages), Commissioning and Startup, and EPC (Engineering, Procurement
and Construction)—across a variety of industries, cultures and geographical regions on projects
ranging from $100M USD to $5B USD. My goal was to maximize the usefulness of technology
to do what the human brain was not capable of doing—calculating multiple fields of data to
produce an optimized Project Plan (lowest cost, shortest duration, least amount of resources)
with the ability to perform ‘what-if’ scenarios and generate revised Project Plans—in real-time.
Why Dynamic Scheduling Methodology (DSM)?
Outside of Activity logic2
, no project ever goes according to plan. That is to say, which
Activities have been planned (objectively with logic, and subjectively with estimates) may be
more-or-less true. When the Activities have been scheduled, however, is more often than not
false, given that no crystal ball has yet been invented to allow Project Schedulers a glimpse into
the future—the very reason why Project Schedulers should look-away from the so called Look-
ahead Schedules that torment Project and Construction Managers, and diminish the Project
1
Project Plans are often referred to as Schedules; however, schedule is a verb, an action required to produce a
Project Plan (noun, product) – Ej Lister
2
Activity logic succeeds the planning of Activities in a Work Order or Construction Work Package and precedes the
estimation process. Activity logic is not the same as Task Relationships; the latter being created during manual
scheduling by the Project Scheduler.
Dynamic Scheduling Methodology (DSM) with Primavera™ P6
A whitepaper by Ej (Ted) Lister
3 of page 10 Copyright© 2014 – Ej (Ted) Lister
Scheduler’s value—as conditions change and their ability to react to changing conditions and
mitigate risk are limited—in the absence of DSM. Only on a Level I Plan (see Illustration 1.2:
Dynamic Scheduling with Primavera™ P6, p.8) should Activities remain fixed—these are the
contractually agree upon Milestone Scorecards, Level-of-Effort Activities and dependent [CPM]
Tasks that demand the practice of DSM—because without DSM the chances of meeting these
Milestone Scorecards is substantially reduced.
The current paradigms which exist within most PMO’s is that planning and scheduling are
functions practiced by people with experience in Project Management Software; P6 Jockeys, as it
were—whose experience in Project Management and/or Construction Management in the real-
world is often limited. To make matters worse, the Project Scheduler’s role does not include the
responsibilities associated with project controls; often they are not integrated into the Project
Controls Team as a vital contributor to Risk Mitigation and Change Management. To compound
this problem even further is the fact that most Project Schedulers have been self-taught (or
coached by incompetent cohorts); creating what many refer to as Schedules, using static
scheduling techniques—such as: Relationships, Constraints, and Milestone Hammocks—where
no formal methodology exists, let alone, DSM. This ultimately produces a rigid Project Plan;
often not optimized, and never flexible or dynamic.
There exists a significant lack of methodology, policies, procedures and guidelines from
industry practices when it comes to scheduling in the project environment these days, even
though the technology is now available to support it, (Which came first, the methodology or the
technology?).
Key benefits of DSM
1. DSM establishes a process (roadmap), allowing the PMO to navigate—focusing on
efficiency and change management—during the Planning, Scheduling and Project
Control Phases, with each phase of the DSM supported by Key Deliverables, Milestone
Scorecards, Policies, Procedures, Templates, and Checklist Tools.
2. Data Integrity and Document Control (DIDC). No PMO will ever be successful
controlling their Project Plan in the absence of DIDC. Using DSM, with its technology
partner, e.g., Primavera™ P6, will ensure all data and documents are controlled in a
dynamic environment by a custodian whose relationship with the PMO team members is
one-to-many.
3. The ability to perform ‘what-if’ analysis and risk mitigation scenarios in real-time using
DSM as opposed to SSM (Static Scheduling Methodology) to produce an optimized
Project Plan (Lowest Cost, Shortest Duration, Least amount of Resources).
4. Each time the Project Plan slips during ‘Updating and Progressing’, the Project Scheduler
must manually determine the ‘Driving Activities’ and find solutions to minimize
Variance using SSM, often taking a great deal of time to execute static simulations to
mitigate risk and recover their Project Plan. With DSM much of the problem-solving can
be done by the computer using the Project Schedulers input, which takes a fraction of the
Dynamic Scheduling Methodology (DSM) with Primavera™ P6
A whitepaper by Ej (Ted) Lister
4 of page 10 Copyright© 2014 – Ej (Ted) Lister
time—in fact, it can often be done during a workshop exercise with the PMO members
present, in real-time.
5. Creating the Project Plan using DSM, in conjunction with the PMO Stakeholders ensures
they work from a Strategic Plan (effective), which includes Risk Mitigation and Change
Management Methodologies to create a Project Plan based on Safety, Quality and
Efficiency.
6. Project Plans can be re-scheduled within minutes of changes and variances being
reported, as opposed to hours or days using SSM during the Project Execution
(Construction) Phase.
7. On complex, risky and high-activity projects like maintenance shutdowns, or during
project phases like commissioning and startup DSM is invaluable. These projects are
scheduled down to a Level V [Resourced] Plan using Work Orders (WO), Factory
Acceptance Testing (FAT) and/or Turn-over Packages (TOP) in conjunction with a true-
geographical/physical process WBS and updated and re-scheduled daily. You cannot do
this type of work using SSM.
Note: DSM does not encourage changes in the Project Plan, nor does it encourage updates to
the Project Baseline; rather, DSM is used as a proactive risk-mitigation tool prior to
establishing the PPBL and used as a reactive change management tool after establishing the
PPBL. DSM does not change the rules that pertain to CPM (Critical Path Method) on a Level I –
Level III Plan.
Premise
The DSM I have developed, in conjunction with Primavera™ P6, is based on the premise that
scheduling is a verb—an action performed by the Project Scheduler using manual scheduling
techniques such as relationships and constraints then refreshing the data using the F9 function
key; or, an action performed by Primavera™ P6 using its Resource Levelling function to produce
an optimized Project Plan (noun). The latter, however, is a misnomer; no project should ever be
scheduled by simply levelling resources since Earned-value Performance Management (EvPM)
is dependent on efficient utilization of resources based on strategic planning for effective
scheduling of work and commodities. More importantly, the basis for controlling a Project Plan
is to ensure its Activity logic is retained, while Activity start and finish times remain flexible
enough to adjust to changing conditions where float exists. My point here is that there are two
Project Schedulers in the room, responsible for creating the Project Plan: the human (static
scheduling), and the computer (dynamic scheduling). Understanding who does what, when, is a
vital principle to the premise of explaining and implementing DSM.
Dynamic Scheduling Methodology (DSM) with Primavera™ P6
A whitepaper by Ej (Ted) Lister
5 of page 10 Copyright© 2014 – Ej (Ted) Lister
The 3 Principles of a High-performance PMO: Methodology, Technology and People
Methodology
A Project Management Office, abbreviated to PMO, is a group or department within a
business, agency or enterprise that defines and maintains standards for project management
within the organization. The PMO strives to standardize and introduce economies of repetition in
the execution of projects.
The PMO is the source of documentation, guidance and metrics on the practice of project
management and execution. In some organizations this is known as the Program Management
Office3
(sometimes abbreviated to PgMO to differentiate); the subtle difference is that program
management relates to governing the management of several related projects. DSM fits into the
PgMO.
DSM forms the backbone of project scheduling, designed to support the PMO with formal
language, terminology, policies, procedures, guidelines, and templates—including training and
coaching programs—through which a timeline of milestones, events and steps are practiced.
Technology is then configured to support the DSM, followed by training and coaching of people
in both methodology and technology to enhance the level of competence required to add value to
the PMO.
It is surprising to me the number of companies that rely on technology and people to manage
projects using no formal methodology; making it difficult to mitigate risk, manage change, run
‘what-if’ scenarios for analysis, or to meet project targets. No Project Scheduler can successfully
do these using traditional, manual and static scheduling methodologies. Is it any wonder
inefficiencies and lack of control stretch project limits? No amount of technology or competent
people can make up for a lack of methodology.
Once the DSM is developed it must be seamlessly implemented into its technology partners4
(ERP, CMMS, PS, DC, etc.) and consistently practiced by its people partners5
(PMO, PM, CM,
PS, etc.) where data integrity, document control and dynamic measurement systems combine to
create a high-performance culture within the PMO.
DSM provides the PMO with a roadmap designed to establish the best possible, optimized
Project Plan using ‘what-if’ scenarios and risk-mitigation techniques, while providing the Project
Scheduler with the ability to generate change management options for the PMO to choose from
when variances from the PPBL are reported. Again, the key benefit is reaction-time. A Project
Scheduler can react to changing conditions and variance within hours; more often than not,
within minutes of the PMO requesting solutions. This cannot be done through traditional SSM.
3
http://www.slideshare.net/KYLUCAS/the-effective-program-management-office-pgmo-c-2010
4
SAP®, JDE®, Maximo®, Microsoft® Project, Primavera™, Oracle, Aconex®
5
Project Management Team, Project Scheduler, Project Manager, Construction Manager
Dynamic Scheduling Methodology (DSM) with Primavera™ P6
A whitepaper by Ej (Ted) Lister
6 of page 10 Copyright© 2014 – Ej (Ted) Lister
DSM is dependent on the following indirect actions executed by the various PMO Disciplines
and Stakeholders:
Actions/Responsibility
 Scope of Work/Budget - PMO
 Strategic Planning - PMO
 Work Breakdown Structure (WBS) – Project Scheduler
 Based on a geographical, physical breakdown of the finished project, e.g., a gas plant
with utilities and processes where the WBS is created as a hierarchy of units, systems,
sub-systems, and equipment/lines (the lowest level of the WBS hierarchy). There is no
time (timeline) associated with the WBS, i.e., do not use WBS to phase your project,
e.g., Pre, Post, Commission, etc.
 Organizational Breakdown Structure (OBS) - PMO
 Phase Calendars – PMO/Project Scheduler
 Based on a timeline of Disciplines and/or Stakeholders, and if applicable, to WBS
elements, e.g., Earthworks, Civil, Structural, Steam System, Commissioning, etc.
 Detailed Planning - Engineering/Planning
 Tasks, Activities & Logic
 Estimating – Engineering/Planning
 Time/Duration, Resources, Indirects, Materials, Cranes, etc.
 Scheduling (Level I – Level III) – Project Scheduler
 Programming – PMO/Project Scheduler
 Resource Limits
 Calendars
 Task Priority
 Activity Levelling Priority
 Project and Levelling Defaults/Settings/Calculations
 Scheduling (Level IV & Level V) – Primavera™ P6
Technology
Both MS Project®
and Primavera™ P6, to name the two most widely used project scheduling
applications can be customized (configured) to support DSM. Myself, I prefer to use
Primavera™ P6 due to its Oracle®
database, powerful algorithms, customizable data fields and
views, and its import/export and report writing capabilities. But do not be fooled, neither one of
these applications was designed specifically for DSM. Much of their design and programming is
focused on a SSM. Perhaps this is the reason why so many Project Schedulers never push these
applications to their limits by configuring them to meet the expectations of a DSM environment;
either that, or they do not understand DSM to begin with (see People).
Despite having a powerful project scheduling tool like Primavera™ P6, most PMO team
members believe it is a Project Scheduler’s tool, meant solely for creating a nice-looking Project
Plan (Gantt Chart) while they [PMO team members] use a multitude of applications like,
Windows Explorer®
, MS Excel®
, MS Access®
, SAP®
, Oracle ®-
JDE®
, Access®
, and Document
Control Apps (DCas), etc. to manage data—data which may or may not be compatible, accurate
Dynamic Scheduling Methodology (DSM) with Primavera™ P6
A whitepaper by Ej (Ted) Lister
7 of page 10 Copyright© 2014 – Ej (Ted) Lister
or accessible to everyone; one of the key benefits of DSM is DIDC. Primavera™ P6 can manage
and control cost, schedule, resources, timesheets, indirects, directs, work procedures & document
links, risks, issues, notes, comments, roles & responsibilities, EvPM, and much more, making it
ideal for the PMO and its team members (people) who simply need only be educated, certified
and qualified in its functionality to ensure DIDC is established using the most appropriate
platform integration.
People
There are two types of people involved in a project; those who are directly involved in the
execution of the project activities, i.e., constructing or creating to deliver a product or service,
e.g., Trades, Engineers, Laborers, etc., and those who are indirectly involved, e.g., Managers,
Supervisors, Administrators, etc., all of whom have a defined role, with related responsibilities.
However, unlike methodology and/or technology, both of which belong to the Organization
(people come and go, bringing with them, and taking with them their experiences, attitude,
competence and skills—which may or may not align with the existing PMO culture or its
methodology and/or technology). It is therefore easy to see how the absence of a formal
methodology for project scheduling may result in a Project Scheduler—whose level of
experience and competence in technology (Primavera™ P6, for example) may not be
sufficient—creating a less than satisfactory Project Plan.
People must be certified (trained) and qualified (coached) on a formal methodology and its
supporting technology by experience personnel, i.e., Instructors, Coaches, Supervisors or
Managers using a defined competency matrix for each individual, for each role, e.g., Project
Scheduler, Project Planner, Planning Engineering.
To ensure a high-performing PMO people must be competent, and the PMO culture must be
firmly valued in principles of a formal methodology and its supporting technology. DSM is just
one of the best-practices associated with a high-performing PMO.
Risk Mitigation and Change Management
Risk Mitigation
An effective PMO will use Risk Mitigation to minimize the probability and consequence
associated with executing a Project Plan. Using DSM to generate ‘what-if’ scenarios prior to
approving the Baseline Project Plan (BLPP) allows the PMO to set realistic KPI targets with
achievable objects for obtaining them. By using Productivity Factors (Pf) based on Probability
and Consequence the PMO can generate Lagging Indicators using a fifteen-day moving average
to forecast (Leading Indicators) the burn-rate (cash flow) and the Earned-value Performance.
Note: Earned-value Performance is equal to the % complete of an Activity, whereas Actual-
value Performance is equal to the $ spent; both measured against Planned/Budgeted to report on
the Cost Performance Index (CPI) and Schedule Performance Index (SPI), which takes into
Dynamic Scheduling Methodology (DSM) with Primavera™ P6
A whitepaper by Ej (Ted) Lister
8 of page 10 Copyright© 2014 – Ej (Ted) Lister
account Variance at the Level I, II, and III Plans related to slippage, where no client/contractual
float is available.
Using the Risk Module in Primavera™ P6 in conjunction with the Issues Table can
significantly help the PMO mitigate and manage risk; simultaneously managing changing
conditions.
Change Management
An efficient PMO will use Change Management to enhance daily Earned-value Performance,
avoiding costly float and below average Actual-value Performance (high-cost for low effort).
Change Management refers to (1) a Scope of Work (SOW) reduction or increase, or (2) a
variance in Level I – III Plans where Milestone Scorecards, Level-of-Effort ($) and/or Task
Dependent Activities with no float—or Client/Owner float—are compromised; or forecasted to
be compromised with Leading Indicators as indicated on the EvPM curves (see Illustration 1.2:
EvPM Curves, p.8).
In reference to (1) and (2) it will be necessary for the PMO to submit a Change Request to the
Client/Owner indicating the impact on CPI and SPI and the risk mitigation plan intended to make
the change. If the change affects only Level IV – V Plans where the PMO owns the float, no
formal Change Request is required.
Project Plan
Most, if not all PMO’s—and their respective clients—refer to the Project Plan as a Schedule;
which, in its simplest form—a nice-looking Gantt chart—it is. But do not let this fool you. As
I’ve previously mentioned, schedule is a verb used to convert strategic plans into to the overall
Project Plan. The Project Plan itself is a culmination of each stakeholder’s (Client/Investor,
Engineering, Materials Management, Cost Control, QA/QC, Document Control, Logistics, PMO,
GIS, Permitting, Safety/Environment, etc.) strategic plans, objectives, milestones, etc., integrated
into a system like Primavera™ P6 to produce a Project Plan for the management, measurement
and control of all activities—direct and indirect—required to deliver on the PMO’s primary goal:
Project Completion in adherence to the Project Key Performance Indices (KPI’s) and Key
Deliverable Targets (KDT’s).
Data Integrity and Document Control (DIDC)
“If the PM is the captain of your PMO ship, DIDC is its rudder. Lose the rudder, lose the
ship…”
—Ej (Ted) Lister
The Project Plan provides the roadmap for the PMO to follow to reach their intended
destination; therefore, it is absolutely critical that information flows into the Project Plan with
integrity, and flows along its designed route in such a way that we can know in real-time where
we are, and where we need to be. All data and documents related to the Project Plan must be
controlled when adding, editing, revising, deleting, and/or analyzing, through a defined DIDC
Dynamic Scheduling Methodology (DSM) with Primavera™ P6
A whitepaper by Ej (Ted) Lister
9 of page 10 Copyright© 2014 – Ej (Ted) Lister
process with standards, templates, tools, procedures and policies. This is how a high-
performance PMO operates.
Ej (Ted) Lister
Project Controls Professional
Email: ejlister@cpmsolutions.ca
Linkedin: http://ca.linkedin.com/in/ejlister
Dynamic Scheduling Methodology (DSM) with Primavera™ P6
A whitepaper by Ej (Ted) Lister
10 of page 10 Copyright© 2014 – Ej (Ted) Lister
Illustrations
Illustration 1.1: Dynamic Scheduling with Primavera™ P6
Illustration 1.2: EvPM Curves

Weitere ähnliche Inhalte

Was ist angesagt?

Resource Scheduling
Resource SchedulingResource Scheduling
Resource SchedulingNicola2903
 
Project Time Management
Project Time ManagementProject Time Management
Project Time ManagementSerdar Temiz
 
project time management
 project time management project time management
project time managementHira Atiq
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Managementrielaantonio
 
Project Management 4 Schedule Management
Project Management 4 Schedule ManagementProject Management 4 Schedule Management
Project Management 4 Schedule Managementgrmkslideshare
 
06 project time management
06  project time management06  project time management
06 project time managementAla Ibrahim
 
Project Scheduling
Project Scheduling Project Scheduling
Project Scheduling Reema
 
Project Scheduling and Control Projects
Project Scheduling and Control ProjectsProject Scheduling and Control Projects
Project Scheduling and Control Projectsharoldtaylor1113
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentationNithin Dev
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimationReetesh Gupta
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery SchedulingChris Carson
 
Ch 9 project monitoring & control updated
Ch 9 project monitoring & control updatedCh 9 project monitoring & control updated
Ch 9 project monitoring & control updatedFarhana Rehman
 

Was ist angesagt? (20)

Project time management
Project time managementProject time management
Project time management
 
Primavera Training P6
Primavera Training P6Primavera Training P6
Primavera Training P6
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource Scheduling
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
project time management
 project time management project time management
project time management
 
Chap06 project time management
Chap06 project time managementChap06 project time management
Chap06 project time management
 
105 project time management
105 project time management105 project time management
105 project time management
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 
3. project time management
3. project time management3. project time management
3. project time management
 
PERT MBO GANTT CHART
PERT MBO GANTT CHARTPERT MBO GANTT CHART
PERT MBO GANTT CHART
 
Project Management 4 Schedule Management
Project Management 4 Schedule ManagementProject Management 4 Schedule Management
Project Management 4 Schedule Management
 
06 project time management
06  project time management06  project time management
06 project time management
 
Project Scheduling
Project Scheduling Project Scheduling
Project Scheduling
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Project Scheduling and Control Projects
Project Scheduling and Control ProjectsProject Scheduling and Control Projects
Project Scheduling and Control Projects
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
Introduction to schedule management
Introduction to schedule managementIntroduction to schedule management
Introduction to schedule management
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimation
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery Scheduling
 
Ch 9 project monitoring & control updated
Ch 9 project monitoring & control updatedCh 9 project monitoring & control updated
Ch 9 project monitoring & control updated
 

Andere mochten auch

Briefing - Dynamic Workers for Scheduling
Briefing - Dynamic Workers for SchedulingBriefing - Dynamic Workers for Scheduling
Briefing - Dynamic Workers for SchedulingBernie Chiu
 
Genetic Algorithm for task scheduling in Cloud Computing Environment
Genetic Algorithm for task scheduling in Cloud Computing EnvironmentGenetic Algorithm for task scheduling in Cloud Computing Environment
Genetic Algorithm for task scheduling in Cloud Computing EnvironmentSwapnil Shahade
 
Particle Swarm optimization
Particle Swarm optimizationParticle Swarm optimization
Particle Swarm optimizationmidhulavijayan
 
Particle Swarm Optimization
Particle Swarm OptimizationParticle Swarm Optimization
Particle Swarm OptimizationStelios Petrakis
 
Particle Swarm Optimization: The Algorithm and Its Applications
Particle Swarm Optimization: The Algorithm and Its ApplicationsParticle Swarm Optimization: The Algorithm and Its Applications
Particle Swarm Optimization: The Algorithm and Its Applicationsadil raja
 
State of the Word 2011
State of the Word 2011State of the Word 2011
State of the Word 2011photomatt
 

Andere mochten auch (7)

Briefing - Dynamic Workers for Scheduling
Briefing - Dynamic Workers for SchedulingBriefing - Dynamic Workers for Scheduling
Briefing - Dynamic Workers for Scheduling
 
Genetic Algorithm for task scheduling in Cloud Computing Environment
Genetic Algorithm for task scheduling in Cloud Computing EnvironmentGenetic Algorithm for task scheduling in Cloud Computing Environment
Genetic Algorithm for task scheduling in Cloud Computing Environment
 
Particle Swarm optimization
Particle Swarm optimizationParticle Swarm optimization
Particle Swarm optimization
 
Particle Swarm Optimization
Particle Swarm OptimizationParticle Swarm Optimization
Particle Swarm Optimization
 
Particle Swarm Optimization: The Algorithm and Its Applications
Particle Swarm Optimization: The Algorithm and Its ApplicationsParticle Swarm Optimization: The Algorithm and Its Applications
Particle Swarm Optimization: The Algorithm and Its Applications
 
Practical Swarm Optimization (PSO)
Practical Swarm Optimization (PSO)Practical Swarm Optimization (PSO)
Practical Swarm Optimization (PSO)
 
State of the Word 2011
State of the Word 2011State of the Word 2011
State of the Word 2011
 

Ähnlich wie Dynamic Scheduling Methodology

Best Project Scheduling Techniques.
Best Project Scheduling Techniques.Best Project Scheduling Techniques.
Best Project Scheduling Techniques.NIILM University
 
Definition Of Project Management
Definition Of Project ManagementDefinition Of Project Management
Definition Of Project ManagementMostafa Ewees
 
New approach for solving software project scheduling problem using differenti...
New approach for solving software project scheduling problem using differenti...New approach for solving software project scheduling problem using differenti...
New approach for solving software project scheduling problem using differenti...ijfcstjournal
 
Project management
Project managementProject management
Project managementArnab Ghosh
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project ManagementAnil Singh
 
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceWhy Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceAcumen
 
5 project management project planning
5 project management  project planning5 project management  project planning
5 project management project planningYasirHamour
 
Chapitulo 5
Chapitulo 5Chapitulo 5
Chapitulo 5ITSP
 
Ch5 - Project Management
Ch5 - Project ManagementCh5 - Project Management
Ch5 - Project ManagementJomel Penalba
 
Project management (A Basic Approach)
Project management (A Basic Approach)Project management (A Basic Approach)
Project management (A Basic Approach)Jed Concepcion
 
PM scheduling techniques
PM scheduling techniquesPM scheduling techniques
PM scheduling techniquesNazish khalid
 

Ähnlich wie Dynamic Scheduling Methodology (20)

final1139bye
final1139byefinal1139bye
final1139bye
 
Best Project Scheduling Techniques.
Best Project Scheduling Techniques.Best Project Scheduling Techniques.
Best Project Scheduling Techniques.
 
Project Management
Project ManagementProject Management
Project Management
 
PROJECT PLANNING
PROJECT PLANNINGPROJECT PLANNING
PROJECT PLANNING
 
Definition Of Project Management
Definition Of Project ManagementDefinition Of Project Management
Definition Of Project Management
 
New approach for solving software project scheduling problem using differenti...
New approach for solving software project scheduling problem using differenti...New approach for solving software project scheduling problem using differenti...
New approach for solving software project scheduling problem using differenti...
 
Project management
Project managementProject management
Project management
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceWhy Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
 
5 project management project planning
5 project management  project planning5 project management  project planning
5 project management project planning
 
PERT
PERTPERT
PERT
 
Chapitulo 5
Chapitulo 5Chapitulo 5
Chapitulo 5
 
Ch5
Ch5Ch5
Ch5
 
Ch5
Ch5Ch5
Ch5
 
Ch5 - Project Management
Ch5 - Project ManagementCh5 - Project Management
Ch5 - Project Management
 
Ch5
Ch5Ch5
Ch5
 
Ch5
Ch5Ch5
Ch5
 
Stopping the insanity
Stopping the insanityStopping the insanity
Stopping the insanity
 
Project management (A Basic Approach)
Project management (A Basic Approach)Project management (A Basic Approach)
Project management (A Basic Approach)
 
PM scheduling techniques
PM scheduling techniquesPM scheduling techniques
PM scheduling techniques
 

Mehr von Edmund (Ted) Lister

Mehr von Edmund (Ted) Lister (7)

The perfect st orm presentation ej lister
The perfect st orm presentation ej listerThe perfect st orm presentation ej lister
The perfect st orm presentation ej lister
 
Sto 3 Day Course Presentation
Sto 3 Day Course PresentationSto 3 Day Course Presentation
Sto 3 Day Course Presentation
 
Change Management 2
Change Management 2Change Management 2
Change Management 2
 
Human Resources
Human ResourcesHuman Resources
Human Resources
 
Wrench Time
Wrench TimeWrench Time
Wrench Time
 
Kpi Lister Sto 061411
Kpi Lister Sto 061411Kpi Lister Sto 061411
Kpi Lister Sto 061411
 
Keynote Lister Sto 061411
Keynote Lister Sto 061411Keynote Lister Sto 061411
Keynote Lister Sto 061411
 

Kürzlich hochgeladen

(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 

Kürzlich hochgeladen (20)

(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 

Dynamic Scheduling Methodology

  • 1. Dynamic Scheduling Methodology (DSM) with Primavera™ P6 A whitepaper by Ej (Ted) Lister
  • 2. Dynamic Scheduling Methodology (DSM) with Primavera™ P6 A whitepaper by Ej (Ted) Lister 1 of page 10 Copyright© 2014 – Ej (Ted) Lister Contents Introduction ..................................................................................................................................................2 Computer Technology and the Project Management Office (PMO) ....................................................2 Why Dynamic Scheduling Methodology (DSM)?......................................................................................2 Key benefits of DSM..............................................................................................................................3 Premise .....................................................................................................................................................4 The 3 Principles of a High-performance PMO: Methodology, Technology and People ...............................5 Methodology.........................................................................................................................................5 Technology............................................................................................................................................6 People ...................................................................................................................................................7 Risk Mitigation and Change Management....................................................................................................7 Risk Mitigation ......................................................................................................................................7 Change Management............................................................................................................................8 Project Plan...............................................................................................................................................8 Data Integrity and Document Control (DIDC).......................................................................................8 Illustrations .................................................................................................................................................10 Illustration 1.1: Dynamic Scheduling with Primavera™ P6 .................................................................10 Illustration 1.2: EvPM Curves..............................................................................................................10
  • 3. Dynamic Scheduling Methodology (DSM) with Primavera™ P6 A whitepaper by Ej (Ted) Lister 2 of page 10 Copyright© 2014 – Ej (Ted) Lister Introduction Computer Technology and the Project Management Office (PMO) In the past two decades advancements in computer technology have enhanced the capability of a Project Scheduler to produce a very detailed Project Plan1 , with the added bonus of nice- looking Gantt Charts, KPI Dashboards, and impressive reports and graphs. Advancements in computer technology also made possible, for scheduling software such as Primavera™ P6, to self-perform the scheduling function through a series of dynamic programming algorithms capable of scheduling up to eighty percent of a project’s activities, with the speed and accuracy needed to keep pace with the ever-changing environment of construction or maintenance projects—more so than any Project Scheduler could ever dream of doing manually. So why is it that most Project Schedulers insist on creating Project Plans using manual, static scheduling techniques? Why is it that many PMO/Project Controls Teams struggle to control work and manage costs and resources? This paper explores how dynamic scheduling has the significant potential to become the defining methodology in project management and controls, as well as the optimal way to balance the benefits of dynamic scheduling against static scheduling in an effort to control direct and indirect project activities in real-time using the latest technology. For the past sixteen years I have been experimenting with creating scheduling methodologies designed to control each phase of complex and risky projects—such as STO (Shutdowns, Turnarounds and Outages), Commissioning and Startup, and EPC (Engineering, Procurement and Construction)—across a variety of industries, cultures and geographical regions on projects ranging from $100M USD to $5B USD. My goal was to maximize the usefulness of technology to do what the human brain was not capable of doing—calculating multiple fields of data to produce an optimized Project Plan (lowest cost, shortest duration, least amount of resources) with the ability to perform ‘what-if’ scenarios and generate revised Project Plans—in real-time. Why Dynamic Scheduling Methodology (DSM)? Outside of Activity logic2 , no project ever goes according to plan. That is to say, which Activities have been planned (objectively with logic, and subjectively with estimates) may be more-or-less true. When the Activities have been scheduled, however, is more often than not false, given that no crystal ball has yet been invented to allow Project Schedulers a glimpse into the future—the very reason why Project Schedulers should look-away from the so called Look- ahead Schedules that torment Project and Construction Managers, and diminish the Project 1 Project Plans are often referred to as Schedules; however, schedule is a verb, an action required to produce a Project Plan (noun, product) – Ej Lister 2 Activity logic succeeds the planning of Activities in a Work Order or Construction Work Package and precedes the estimation process. Activity logic is not the same as Task Relationships; the latter being created during manual scheduling by the Project Scheduler.
  • 4. Dynamic Scheduling Methodology (DSM) with Primavera™ P6 A whitepaper by Ej (Ted) Lister 3 of page 10 Copyright© 2014 – Ej (Ted) Lister Scheduler’s value—as conditions change and their ability to react to changing conditions and mitigate risk are limited—in the absence of DSM. Only on a Level I Plan (see Illustration 1.2: Dynamic Scheduling with Primavera™ P6, p.8) should Activities remain fixed—these are the contractually agree upon Milestone Scorecards, Level-of-Effort Activities and dependent [CPM] Tasks that demand the practice of DSM—because without DSM the chances of meeting these Milestone Scorecards is substantially reduced. The current paradigms which exist within most PMO’s is that planning and scheduling are functions practiced by people with experience in Project Management Software; P6 Jockeys, as it were—whose experience in Project Management and/or Construction Management in the real- world is often limited. To make matters worse, the Project Scheduler’s role does not include the responsibilities associated with project controls; often they are not integrated into the Project Controls Team as a vital contributor to Risk Mitigation and Change Management. To compound this problem even further is the fact that most Project Schedulers have been self-taught (or coached by incompetent cohorts); creating what many refer to as Schedules, using static scheduling techniques—such as: Relationships, Constraints, and Milestone Hammocks—where no formal methodology exists, let alone, DSM. This ultimately produces a rigid Project Plan; often not optimized, and never flexible or dynamic. There exists a significant lack of methodology, policies, procedures and guidelines from industry practices when it comes to scheduling in the project environment these days, even though the technology is now available to support it, (Which came first, the methodology or the technology?). Key benefits of DSM 1. DSM establishes a process (roadmap), allowing the PMO to navigate—focusing on efficiency and change management—during the Planning, Scheduling and Project Control Phases, with each phase of the DSM supported by Key Deliverables, Milestone Scorecards, Policies, Procedures, Templates, and Checklist Tools. 2. Data Integrity and Document Control (DIDC). No PMO will ever be successful controlling their Project Plan in the absence of DIDC. Using DSM, with its technology partner, e.g., Primavera™ P6, will ensure all data and documents are controlled in a dynamic environment by a custodian whose relationship with the PMO team members is one-to-many. 3. The ability to perform ‘what-if’ analysis and risk mitigation scenarios in real-time using DSM as opposed to SSM (Static Scheduling Methodology) to produce an optimized Project Plan (Lowest Cost, Shortest Duration, Least amount of Resources). 4. Each time the Project Plan slips during ‘Updating and Progressing’, the Project Scheduler must manually determine the ‘Driving Activities’ and find solutions to minimize Variance using SSM, often taking a great deal of time to execute static simulations to mitigate risk and recover their Project Plan. With DSM much of the problem-solving can be done by the computer using the Project Schedulers input, which takes a fraction of the
  • 5. Dynamic Scheduling Methodology (DSM) with Primavera™ P6 A whitepaper by Ej (Ted) Lister 4 of page 10 Copyright© 2014 – Ej (Ted) Lister time—in fact, it can often be done during a workshop exercise with the PMO members present, in real-time. 5. Creating the Project Plan using DSM, in conjunction with the PMO Stakeholders ensures they work from a Strategic Plan (effective), which includes Risk Mitigation and Change Management Methodologies to create a Project Plan based on Safety, Quality and Efficiency. 6. Project Plans can be re-scheduled within minutes of changes and variances being reported, as opposed to hours or days using SSM during the Project Execution (Construction) Phase. 7. On complex, risky and high-activity projects like maintenance shutdowns, or during project phases like commissioning and startup DSM is invaluable. These projects are scheduled down to a Level V [Resourced] Plan using Work Orders (WO), Factory Acceptance Testing (FAT) and/or Turn-over Packages (TOP) in conjunction with a true- geographical/physical process WBS and updated and re-scheduled daily. You cannot do this type of work using SSM. Note: DSM does not encourage changes in the Project Plan, nor does it encourage updates to the Project Baseline; rather, DSM is used as a proactive risk-mitigation tool prior to establishing the PPBL and used as a reactive change management tool after establishing the PPBL. DSM does not change the rules that pertain to CPM (Critical Path Method) on a Level I – Level III Plan. Premise The DSM I have developed, in conjunction with Primavera™ P6, is based on the premise that scheduling is a verb—an action performed by the Project Scheduler using manual scheduling techniques such as relationships and constraints then refreshing the data using the F9 function key; or, an action performed by Primavera™ P6 using its Resource Levelling function to produce an optimized Project Plan (noun). The latter, however, is a misnomer; no project should ever be scheduled by simply levelling resources since Earned-value Performance Management (EvPM) is dependent on efficient utilization of resources based on strategic planning for effective scheduling of work and commodities. More importantly, the basis for controlling a Project Plan is to ensure its Activity logic is retained, while Activity start and finish times remain flexible enough to adjust to changing conditions where float exists. My point here is that there are two Project Schedulers in the room, responsible for creating the Project Plan: the human (static scheduling), and the computer (dynamic scheduling). Understanding who does what, when, is a vital principle to the premise of explaining and implementing DSM.
  • 6. Dynamic Scheduling Methodology (DSM) with Primavera™ P6 A whitepaper by Ej (Ted) Lister 5 of page 10 Copyright© 2014 – Ej (Ted) Lister The 3 Principles of a High-performance PMO: Methodology, Technology and People Methodology A Project Management Office, abbreviated to PMO, is a group or department within a business, agency or enterprise that defines and maintains standards for project management within the organization. The PMO strives to standardize and introduce economies of repetition in the execution of projects. The PMO is the source of documentation, guidance and metrics on the practice of project management and execution. In some organizations this is known as the Program Management Office3 (sometimes abbreviated to PgMO to differentiate); the subtle difference is that program management relates to governing the management of several related projects. DSM fits into the PgMO. DSM forms the backbone of project scheduling, designed to support the PMO with formal language, terminology, policies, procedures, guidelines, and templates—including training and coaching programs—through which a timeline of milestones, events and steps are practiced. Technology is then configured to support the DSM, followed by training and coaching of people in both methodology and technology to enhance the level of competence required to add value to the PMO. It is surprising to me the number of companies that rely on technology and people to manage projects using no formal methodology; making it difficult to mitigate risk, manage change, run ‘what-if’ scenarios for analysis, or to meet project targets. No Project Scheduler can successfully do these using traditional, manual and static scheduling methodologies. Is it any wonder inefficiencies and lack of control stretch project limits? No amount of technology or competent people can make up for a lack of methodology. Once the DSM is developed it must be seamlessly implemented into its technology partners4 (ERP, CMMS, PS, DC, etc.) and consistently practiced by its people partners5 (PMO, PM, CM, PS, etc.) where data integrity, document control and dynamic measurement systems combine to create a high-performance culture within the PMO. DSM provides the PMO with a roadmap designed to establish the best possible, optimized Project Plan using ‘what-if’ scenarios and risk-mitigation techniques, while providing the Project Scheduler with the ability to generate change management options for the PMO to choose from when variances from the PPBL are reported. Again, the key benefit is reaction-time. A Project Scheduler can react to changing conditions and variance within hours; more often than not, within minutes of the PMO requesting solutions. This cannot be done through traditional SSM. 3 http://www.slideshare.net/KYLUCAS/the-effective-program-management-office-pgmo-c-2010 4 SAP®, JDE®, Maximo®, Microsoft® Project, Primavera™, Oracle, Aconex® 5 Project Management Team, Project Scheduler, Project Manager, Construction Manager
  • 7. Dynamic Scheduling Methodology (DSM) with Primavera™ P6 A whitepaper by Ej (Ted) Lister 6 of page 10 Copyright© 2014 – Ej (Ted) Lister DSM is dependent on the following indirect actions executed by the various PMO Disciplines and Stakeholders: Actions/Responsibility  Scope of Work/Budget - PMO  Strategic Planning - PMO  Work Breakdown Structure (WBS) – Project Scheduler  Based on a geographical, physical breakdown of the finished project, e.g., a gas plant with utilities and processes where the WBS is created as a hierarchy of units, systems, sub-systems, and equipment/lines (the lowest level of the WBS hierarchy). There is no time (timeline) associated with the WBS, i.e., do not use WBS to phase your project, e.g., Pre, Post, Commission, etc.  Organizational Breakdown Structure (OBS) - PMO  Phase Calendars – PMO/Project Scheduler  Based on a timeline of Disciplines and/or Stakeholders, and if applicable, to WBS elements, e.g., Earthworks, Civil, Structural, Steam System, Commissioning, etc.  Detailed Planning - Engineering/Planning  Tasks, Activities & Logic  Estimating – Engineering/Planning  Time/Duration, Resources, Indirects, Materials, Cranes, etc.  Scheduling (Level I – Level III) – Project Scheduler  Programming – PMO/Project Scheduler  Resource Limits  Calendars  Task Priority  Activity Levelling Priority  Project and Levelling Defaults/Settings/Calculations  Scheduling (Level IV & Level V) – Primavera™ P6 Technology Both MS Project® and Primavera™ P6, to name the two most widely used project scheduling applications can be customized (configured) to support DSM. Myself, I prefer to use Primavera™ P6 due to its Oracle® database, powerful algorithms, customizable data fields and views, and its import/export and report writing capabilities. But do not be fooled, neither one of these applications was designed specifically for DSM. Much of their design and programming is focused on a SSM. Perhaps this is the reason why so many Project Schedulers never push these applications to their limits by configuring them to meet the expectations of a DSM environment; either that, or they do not understand DSM to begin with (see People). Despite having a powerful project scheduling tool like Primavera™ P6, most PMO team members believe it is a Project Scheduler’s tool, meant solely for creating a nice-looking Project Plan (Gantt Chart) while they [PMO team members] use a multitude of applications like, Windows Explorer® , MS Excel® , MS Access® , SAP® , Oracle ®- JDE® , Access® , and Document Control Apps (DCas), etc. to manage data—data which may or may not be compatible, accurate
  • 8. Dynamic Scheduling Methodology (DSM) with Primavera™ P6 A whitepaper by Ej (Ted) Lister 7 of page 10 Copyright© 2014 – Ej (Ted) Lister or accessible to everyone; one of the key benefits of DSM is DIDC. Primavera™ P6 can manage and control cost, schedule, resources, timesheets, indirects, directs, work procedures & document links, risks, issues, notes, comments, roles & responsibilities, EvPM, and much more, making it ideal for the PMO and its team members (people) who simply need only be educated, certified and qualified in its functionality to ensure DIDC is established using the most appropriate platform integration. People There are two types of people involved in a project; those who are directly involved in the execution of the project activities, i.e., constructing or creating to deliver a product or service, e.g., Trades, Engineers, Laborers, etc., and those who are indirectly involved, e.g., Managers, Supervisors, Administrators, etc., all of whom have a defined role, with related responsibilities. However, unlike methodology and/or technology, both of which belong to the Organization (people come and go, bringing with them, and taking with them their experiences, attitude, competence and skills—which may or may not align with the existing PMO culture or its methodology and/or technology). It is therefore easy to see how the absence of a formal methodology for project scheduling may result in a Project Scheduler—whose level of experience and competence in technology (Primavera™ P6, for example) may not be sufficient—creating a less than satisfactory Project Plan. People must be certified (trained) and qualified (coached) on a formal methodology and its supporting technology by experience personnel, i.e., Instructors, Coaches, Supervisors or Managers using a defined competency matrix for each individual, for each role, e.g., Project Scheduler, Project Planner, Planning Engineering. To ensure a high-performing PMO people must be competent, and the PMO culture must be firmly valued in principles of a formal methodology and its supporting technology. DSM is just one of the best-practices associated with a high-performing PMO. Risk Mitigation and Change Management Risk Mitigation An effective PMO will use Risk Mitigation to minimize the probability and consequence associated with executing a Project Plan. Using DSM to generate ‘what-if’ scenarios prior to approving the Baseline Project Plan (BLPP) allows the PMO to set realistic KPI targets with achievable objects for obtaining them. By using Productivity Factors (Pf) based on Probability and Consequence the PMO can generate Lagging Indicators using a fifteen-day moving average to forecast (Leading Indicators) the burn-rate (cash flow) and the Earned-value Performance. Note: Earned-value Performance is equal to the % complete of an Activity, whereas Actual- value Performance is equal to the $ spent; both measured against Planned/Budgeted to report on the Cost Performance Index (CPI) and Schedule Performance Index (SPI), which takes into
  • 9. Dynamic Scheduling Methodology (DSM) with Primavera™ P6 A whitepaper by Ej (Ted) Lister 8 of page 10 Copyright© 2014 – Ej (Ted) Lister account Variance at the Level I, II, and III Plans related to slippage, where no client/contractual float is available. Using the Risk Module in Primavera™ P6 in conjunction with the Issues Table can significantly help the PMO mitigate and manage risk; simultaneously managing changing conditions. Change Management An efficient PMO will use Change Management to enhance daily Earned-value Performance, avoiding costly float and below average Actual-value Performance (high-cost for low effort). Change Management refers to (1) a Scope of Work (SOW) reduction or increase, or (2) a variance in Level I – III Plans where Milestone Scorecards, Level-of-Effort ($) and/or Task Dependent Activities with no float—or Client/Owner float—are compromised; or forecasted to be compromised with Leading Indicators as indicated on the EvPM curves (see Illustration 1.2: EvPM Curves, p.8). In reference to (1) and (2) it will be necessary for the PMO to submit a Change Request to the Client/Owner indicating the impact on CPI and SPI and the risk mitigation plan intended to make the change. If the change affects only Level IV – V Plans where the PMO owns the float, no formal Change Request is required. Project Plan Most, if not all PMO’s—and their respective clients—refer to the Project Plan as a Schedule; which, in its simplest form—a nice-looking Gantt chart—it is. But do not let this fool you. As I’ve previously mentioned, schedule is a verb used to convert strategic plans into to the overall Project Plan. The Project Plan itself is a culmination of each stakeholder’s (Client/Investor, Engineering, Materials Management, Cost Control, QA/QC, Document Control, Logistics, PMO, GIS, Permitting, Safety/Environment, etc.) strategic plans, objectives, milestones, etc., integrated into a system like Primavera™ P6 to produce a Project Plan for the management, measurement and control of all activities—direct and indirect—required to deliver on the PMO’s primary goal: Project Completion in adherence to the Project Key Performance Indices (KPI’s) and Key Deliverable Targets (KDT’s). Data Integrity and Document Control (DIDC) “If the PM is the captain of your PMO ship, DIDC is its rudder. Lose the rudder, lose the ship…” —Ej (Ted) Lister The Project Plan provides the roadmap for the PMO to follow to reach their intended destination; therefore, it is absolutely critical that information flows into the Project Plan with integrity, and flows along its designed route in such a way that we can know in real-time where we are, and where we need to be. All data and documents related to the Project Plan must be controlled when adding, editing, revising, deleting, and/or analyzing, through a defined DIDC
  • 10. Dynamic Scheduling Methodology (DSM) with Primavera™ P6 A whitepaper by Ej (Ted) Lister 9 of page 10 Copyright© 2014 – Ej (Ted) Lister process with standards, templates, tools, procedures and policies. This is how a high- performance PMO operates. Ej (Ted) Lister Project Controls Professional Email: ejlister@cpmsolutions.ca Linkedin: http://ca.linkedin.com/in/ejlister
  • 11. Dynamic Scheduling Methodology (DSM) with Primavera™ P6 A whitepaper by Ej (Ted) Lister 10 of page 10 Copyright© 2014 – Ej (Ted) Lister Illustrations Illustration 1.1: Dynamic Scheduling with Primavera™ P6 Illustration 1.2: EvPM Curves