SlideShare ist ein Scribd-Unternehmen logo
1 von 26
UTMUNIVERSITI TEKNOLOGI MALAYSIA
Fault Analysis Using PSCAD/EMTDC
for 150 kV South Sulawesi Transmission System
M. Saini, A.A. Mohd Zin, M.W. Mustafa, A.R. Sultan.
Faculty of Electrical Engineering, Universiti Teknologi Malaysia, 81310
UTM Johor Bahru, Johor.
TABLE OF CONTENT
1. INTRODUCTION
2. Overview Short Circuit Fault Analysis
3. RESEARCH METHOD
4. ANALYSIS OF THE SIMULATION RESULTS
5. RESULTS
6.CONCLUSION
Introduction
In analyzing the problems in South Sulawesi
transmission system, simulations of PSCAD /
EMTDC [5-6] and PWS (Power World Simulator) [7]
software were used to simulate changes in electrical
current and voltage during a disturbance.
-Single phase to Ground,
-Line to Fault Line,
-Double Line to Ground
-Three phase Short Circuit
Introduction
Since 2002, the transmission system of South
Sulawesi has introduced Intelligent Electronic
Devices (IEDs) such as Digital Protective
Relays (DPRs) and the Digital Fault
Recorders (DFRs) on all feeder transmission
[8].
In the simulations of this total Power Plant
591.3 MW and the total Load of 568.9 MW.
Overview Short Circuit Fault Analysis
Short circuit interruption is one of the disorders of
electric power system transient characteristics that
must be addressed by the safety equipment.
The occurrence of short circuit current spikes
results in a higher magnitude than the normal state
and the voltage at the site to be very low can result
-Damage to the insulation
-Mechanical damage to the conductor
-Electrical sparks
-The worst is the failure of the overall system operation
[9].
RESEARCH METHOD
A. PSCAD/EMTDC
This research analysis using PSCAD (Power System CAD) is
to simulate fault conditions of the transmission system in
South Sulawesi were presented by using the transmission-
line model line Bergeron of PSCAD / EMTDC [11] . PSCAD
enables users to build a circuit schematic, running
simulations, analyzing results, manage data in a fully
integrated graphical environment, control and meter so that
users can change system parameters during the simulation
run and can obtain immediate results [11].
RESEARCH METHOD
PSCAD comes with a library of models that
have been programmed and tested, ranging
from simple passive elements, control
functions and more complex models such as
electric machines, FACTS devise,
transmission lines, transformers and cables.
EMTDC (Electromagnetic Transient,
Including DC) proposes and solves
differential equations in time domain.
RESEARCH METHOD
B. PWS ( Power Worlds Simulator)
PSW is a power system simulation package
consists of a number of integrated products. This
simulator allows the user to visualize the system
through the use of color charts online, complete
with animated zooming capabilities and planning.
System models can be modified and quickly built
from scratch using a full-featured graphics editor
special simulator. Transmission lines can be
switched in or out of service, the new transmission
line can be added and created.
.
RESEARCH METHOD
This simulation package capable of solving the
power system consists of up to 100,000 buses
covering of Integrated Economic Dispatch, Power
transfer distribution factor Computation, Short
Circuit Analysis, and contingency analysis.
PWS had the ability to import data from all sources
of data, Moreover, in order to power flow model of
PWS, a text file interface to exchange data and
execute command scripts BATCH .
ANALYSIS OF THE SIMULATION RESULTS
Simulation System
Simulation system is performed during a short circuit on the
150 kV transmission system south Sulawesi as shown in
Figure 3. Transmission line simulation between bus PPKEP
and bus PPARE fault lines to ground (LG), three-phase
(LLL), double fault line (LL) and double fault line to ground
(LLG) by fault impedance 0 ohm and 45 km from Pangkep
to Pare-Pare. During the simulation, load flow data is the
total power plan 591.3 MW, the total load, 568,9 MW and
the power loss 22.4 MW with a base of 150 kV and 100
MVA.
Single Line Diagram of 150 kV Transmission South Sulawesi
Pre-Fault Voltage and Current Waveform between Bus PPKEP
and Bus PPARE
Voltage and current waveform of Line to Ground Fault (LG)
between Bus PPKE and Bus PPARE
Voltage and current waveform of Line-Line to Ground Fault
(LLG) Between Bus PPKE and Bus PPARE
Voltage and current waveform of Line-Line Fault (LL)
Between Bus PPKE and Bus PPARE
Voltage and current waveform of Line-Line-Line Fault (LLL)
Between Bus PPKE and Bus PPARE
RESULTS
From the simulation results it can be
analyzed from the characteristics of electric
current and voltage at Bus PKEP, that bus
signal waveform of PPARE has a peak
value of electric current equal to 509
Amperes when a fault line to ground (LG),
three-phase fault (LLL), double line fault (LL)
and double line to ground faults (LLG),
Table 1. Short circuit Current Without Fault Impedance Z= 0
Table 2. Short circuit Current With Fault Impedance Z= 10 Ohm
Table 3. Short circuit Current With Fault Impedance Z= 15 Ohm
Table 4. Fault Voltage With Fault Impedance Z= 0 Ohm
Table 5. Fault Voltage With Fault Impedance Z= 10 Ohm
Table 6. Fault Voltage With Fault Impedance Z= 15 Ohm
CONCLUSION
For short circuit fault with impedance Z = 0, the fault
tends to electrical current higher than the short circuit
fault using impedance Z = 10 ohm and Z =15 ohm,
this is due to the absence of resistance to the flow of
electric short circuit fault. The interference voltage at Z
= 15 Ohm tends to be greater than the voltage at Z =
0 ohm impedance and Z = 10 Ohm, this is due to
large resistance causes a very small electric current
flows so that the voltage is higher
CONCLUSION
For a distance fault of 22.5 km obtained by the fault
current from the biggest bus PKEP, while at a
distance of 66.5 km, it is acquired by the fault current
of the largest from the bus PPARE, four types of
errors are analyzed in which the Z = 0 ohm is the
largest short circuit interruption occurs in three phase
fault (LLL). While at Z = 10 ohm = 15 ohm Z, the
biggest mistakes of the line short-circuit line is ground
faults (LLG).
26

Weitere ähnliche Inhalte

Was ist angesagt?

Power quality notes unit 1
Power quality notes unit  1 Power quality notes unit  1
Power quality notes unit 1 Dilip kumar
 
Multi terminal dc systems (mtdc)
Multi terminal dc systems (mtdc)Multi terminal dc systems (mtdc)
Multi terminal dc systems (mtdc)jawaharramaya
 
Small signal stability analysis
Small signal stability analysisSmall signal stability analysis
Small signal stability analysisbhupendra kumar
 
Harmonic analysis procedure
Harmonic analysis procedureHarmonic analysis procedure
Harmonic analysis proceduresrini09
 
Power system voltage stability
Power system voltage stabilityPower system voltage stability
Power system voltage stabilityAkash Choudhary
 
Vector Control of AC Induction Motors
Vector Control of AC Induction MotorsVector Control of AC Induction Motors
Vector Control of AC Induction MotorsPranjal Barman
 
Unit 4 Automatic Generation Control
Unit 4 Automatic Generation ControlUnit 4 Automatic Generation Control
Unit 4 Automatic Generation ControlSANTOSH GADEKAR
 
Voltage sag and it’s mitigation
Voltage sag and it’s mitigationVoltage sag and it’s mitigation
Voltage sag and it’s mitigationMayur Dhande
 
EE8701-High Voltage Engineering (1).pptx
EE8701-High Voltage Engineering (1).pptxEE8701-High Voltage Engineering (1).pptx
EE8701-High Voltage Engineering (1).pptxsai karthick
 
power flow and optimal power flow
power flow and optimal power flowpower flow and optimal power flow
power flow and optimal power flowAhmed M. Elkholy
 
TOWNSEND"S (FIRST)PRIMARY & SECONDARY IONIZATION COEFFICIENT|DERIVATION|HIGH ...
TOWNSEND"S (FIRST)PRIMARY & SECONDARY IONIZATION COEFFICIENT|DERIVATION|HIGH ...TOWNSEND"S (FIRST)PRIMARY & SECONDARY IONIZATION COEFFICIENT|DERIVATION|HIGH ...
TOWNSEND"S (FIRST)PRIMARY & SECONDARY IONIZATION COEFFICIENT|DERIVATION|HIGH ...Prasant Kumar
 
STREAMER THEORY|BREAKDOWN IN GAS|HIGH VOLTAGE ENGINEERING
STREAMER THEORY|BREAKDOWN IN GAS|HIGH VOLTAGE ENGINEERINGSTREAMER THEORY|BREAKDOWN IN GAS|HIGH VOLTAGE ENGINEERING
STREAMER THEORY|BREAKDOWN IN GAS|HIGH VOLTAGE ENGINEERINGPrasant Kumar
 
GENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGEGENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGEJamil Abdullah
 
Voltage and Frequency Control of the Grid
Voltage and Frequency Control of the GridVoltage and Frequency Control of the Grid
Voltage and Frequency Control of the GridLeonardo ENERGY
 
Flexible ac transmission system
Flexible ac transmission systemFlexible ac transmission system
Flexible ac transmission systemUday Wankar
 
Voltage stability using Series FACTS devices
Voltage stability using Series FACTS devicesVoltage stability using Series FACTS devices
Voltage stability using Series FACTS devicesSAI SREE
 
TREEING & TRACKING|BREAKDOWN IN SOLIDS|HIGH VOLTAGE ENGINEERING
TREEING & TRACKING|BREAKDOWN IN SOLIDS|HIGH VOLTAGE ENGINEERINGTREEING & TRACKING|BREAKDOWN IN SOLIDS|HIGH VOLTAGE ENGINEERING
TREEING & TRACKING|BREAKDOWN IN SOLIDS|HIGH VOLTAGE ENGINEERINGPrasant Kumar
 

Was ist angesagt? (20)

Power quality notes unit 1
Power quality notes unit  1 Power quality notes unit  1
Power quality notes unit 1
 
Multi terminal dc systems (mtdc)
Multi terminal dc systems (mtdc)Multi terminal dc systems (mtdc)
Multi terminal dc systems (mtdc)
 
Small signal stability analysis
Small signal stability analysisSmall signal stability analysis
Small signal stability analysis
 
Harmonic analysis procedure
Harmonic analysis procedureHarmonic analysis procedure
Harmonic analysis procedure
 
Power system voltage stability
Power system voltage stabilityPower system voltage stability
Power system voltage stability
 
Vector Control of AC Induction Motors
Vector Control of AC Induction MotorsVector Control of AC Induction Motors
Vector Control of AC Induction Motors
 
Unit 4 Automatic Generation Control
Unit 4 Automatic Generation ControlUnit 4 Automatic Generation Control
Unit 4 Automatic Generation Control
 
Voltage sag and it’s mitigation
Voltage sag and it’s mitigationVoltage sag and it’s mitigation
Voltage sag and it’s mitigation
 
EE8701-High Voltage Engineering (1).pptx
EE8701-High Voltage Engineering (1).pptxEE8701-High Voltage Engineering (1).pptx
EE8701-High Voltage Engineering (1).pptx
 
power flow and optimal power flow
power flow and optimal power flowpower flow and optimal power flow
power flow and optimal power flow
 
Computer Application in Power system chapter one - introduction
Computer Application in Power system chapter one - introductionComputer Application in Power system chapter one - introduction
Computer Application in Power system chapter one - introduction
 
TOWNSEND"S (FIRST)PRIMARY & SECONDARY IONIZATION COEFFICIENT|DERIVATION|HIGH ...
TOWNSEND"S (FIRST)PRIMARY & SECONDARY IONIZATION COEFFICIENT|DERIVATION|HIGH ...TOWNSEND"S (FIRST)PRIMARY & SECONDARY IONIZATION COEFFICIENT|DERIVATION|HIGH ...
TOWNSEND"S (FIRST)PRIMARY & SECONDARY IONIZATION COEFFICIENT|DERIVATION|HIGH ...
 
STREAMER THEORY|BREAKDOWN IN GAS|HIGH VOLTAGE ENGINEERING
STREAMER THEORY|BREAKDOWN IN GAS|HIGH VOLTAGE ENGINEERINGSTREAMER THEORY|BREAKDOWN IN GAS|HIGH VOLTAGE ENGINEERING
STREAMER THEORY|BREAKDOWN IN GAS|HIGH VOLTAGE ENGINEERING
 
GENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGEGENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGE
 
Voltage and Frequency Control of the Grid
Voltage and Frequency Control of the GridVoltage and Frequency Control of the Grid
Voltage and Frequency Control of the Grid
 
Hvdc circuit breaker
Hvdc circuit breakerHvdc circuit breaker
Hvdc circuit breaker
 
Flexible ac transmission system
Flexible ac transmission systemFlexible ac transmission system
Flexible ac transmission system
 
Voltage stability using Series FACTS devices
Voltage stability using Series FACTS devicesVoltage stability using Series FACTS devices
Voltage stability using Series FACTS devices
 
MTDC SYSTEMS
MTDC SYSTEMSMTDC SYSTEMS
MTDC SYSTEMS
 
TREEING & TRACKING|BREAKDOWN IN SOLIDS|HIGH VOLTAGE ENGINEERING
TREEING & TRACKING|BREAKDOWN IN SOLIDS|HIGH VOLTAGE ENGINEERINGTREEING & TRACKING|BREAKDOWN IN SOLIDS|HIGH VOLTAGE ENGINEERING
TREEING & TRACKING|BREAKDOWN IN SOLIDS|HIGH VOLTAGE ENGINEERING
 

Andere mochten auch

Simulation and analysis of HVDC on MATLAB and PSCAD
Simulation and analysis of HVDC on MATLAB and PSCADSimulation and analysis of HVDC on MATLAB and PSCAD
Simulation and analysis of HVDC on MATLAB and PSCADVishal Bhimani
 
PSCAD Final Report
PSCAD Final ReportPSCAD Final Report
PSCAD Final ReportJeff Ge
 
Major Project, HVDC Thesis - Saurabh Saxena
Major Project, HVDC Thesis - Saurabh SaxenaMajor Project, HVDC Thesis - Saurabh Saxena
Major Project, HVDC Thesis - Saurabh SaxenaSaurabh Saxena
 
S bueckert sdecmobile
S bueckert sdecmobileS bueckert sdecmobile
S bueckert sdecmobilesdeconf
 
Pscad agile adoption
Pscad agile adoptionPscad agile adoption
Pscad agile adoptionsdeconf
 
VSC based HVDC system
VSC based HVDC systemVSC based HVDC system
VSC based HVDC systemmdhsudhan
 
Pengembangan Sistem Penangkal Petir dan Pentanahan Elektroda Rod dan Plat pad...
Pengembangan Sistem Penangkal Petir dan Pentanahan Elektroda Rod dan Plat pad...Pengembangan Sistem Penangkal Petir dan Pentanahan Elektroda Rod dan Plat pad...
Pengembangan Sistem Penangkal Petir dan Pentanahan Elektroda Rod dan Plat pad...Politeknik Negeri Ujung Pandang
 
Power sytems ieee 2015 2016 projects list-vel
Power sytems ieee 2015 2016  projects list-velPower sytems ieee 2015 2016  projects list-vel
Power sytems ieee 2015 2016 projects list-velS3 Infotech IEEE Projects
 
Low voltage ride through control of modular multilevel converter based hvdc s...
Low voltage ride through control of modular multilevel converter based hvdc s...Low voltage ride through control of modular multilevel converter based hvdc s...
Low voltage ride through control of modular multilevel converter based hvdc s...Ghazal Falahi
 
Hvdc transmission seminar
Hvdc transmission seminar Hvdc transmission seminar
Hvdc transmission seminar Utkarsh Jambhule
 
Latest 2016 IEEE Electrical Projects List for BTech and MTech
Latest 2016 IEEE Electrical Projects List for BTech and MTechLatest 2016 IEEE Electrical Projects List for BTech and MTech
Latest 2016 IEEE Electrical Projects List for BTech and MTechAsoka Technologies
 
High Voltage Direct Current Transmission System Report
High Voltage Direct Current Transmission System ReportHigh Voltage Direct Current Transmission System Report
High Voltage Direct Current Transmission System ReportNadeem Khilji
 
Neil Kirby: VSC HVDC Transmission and Emerging Technologies in DC Grids
Neil Kirby: VSC HVDC Transmission and Emerging Technologies in DC GridsNeil Kirby: VSC HVDC Transmission and Emerging Technologies in DC Grids
Neil Kirby: VSC HVDC Transmission and Emerging Technologies in DC GridsEnergyTech2015
 

Andere mochten auch (20)

Simulation and analysis of HVDC on MATLAB and PSCAD
Simulation and analysis of HVDC on MATLAB and PSCADSimulation and analysis of HVDC on MATLAB and PSCAD
Simulation and analysis of HVDC on MATLAB and PSCAD
 
PSCAD Final Report
PSCAD Final ReportPSCAD Final Report
PSCAD Final Report
 
Major Project, HVDC Thesis - Saurabh Saxena
Major Project, HVDC Thesis - Saurabh SaxenaMajor Project, HVDC Thesis - Saurabh Saxena
Major Project, HVDC Thesis - Saurabh Saxena
 
S bueckert sdecmobile
S bueckert sdecmobileS bueckert sdecmobile
S bueckert sdecmobile
 
Pscad agile adoption
Pscad agile adoptionPscad agile adoption
Pscad agile adoption
 
VSC based HVDC system
VSC based HVDC systemVSC based HVDC system
VSC based HVDC system
 
main-project1
main-project1main-project1
main-project1
 
Pengembangan Sistem Penangkal Petir dan Pentanahan Elektroda Rod dan Plat pad...
Pengembangan Sistem Penangkal Petir dan Pentanahan Elektroda Rod dan Plat pad...Pengembangan Sistem Penangkal Petir dan Pentanahan Elektroda Rod dan Plat pad...
Pengembangan Sistem Penangkal Petir dan Pentanahan Elektroda Rod dan Plat pad...
 
Power sytems ieee 2015 2016 projects list-vel
Power sytems ieee 2015 2016  projects list-velPower sytems ieee 2015 2016  projects list-vel
Power sytems ieee 2015 2016 projects list-vel
 
Low voltage ride through control of modular multilevel converter based hvdc s...
Low voltage ride through control of modular multilevel converter based hvdc s...Low voltage ride through control of modular multilevel converter based hvdc s...
Low voltage ride through control of modular multilevel converter based hvdc s...
 
Hvdc transmission seminar
Hvdc transmission seminar Hvdc transmission seminar
Hvdc transmission seminar
 
Latest 2016 IEEE Electrical Projects List for BTech and MTech
Latest 2016 IEEE Electrical Projects List for BTech and MTechLatest 2016 IEEE Electrical Projects List for BTech and MTech
Latest 2016 IEEE Electrical Projects List for BTech and MTech
 
High Voltage Direct Current Transmission System Report
High Voltage Direct Current Transmission System ReportHigh Voltage Direct Current Transmission System Report
High Voltage Direct Current Transmission System Report
 
Neil Kirby: VSC HVDC Transmission and Emerging Technologies in DC Grids
Neil Kirby: VSC HVDC Transmission and Emerging Technologies in DC GridsNeil Kirby: VSC HVDC Transmission and Emerging Technologies in DC Grids
Neil Kirby: VSC HVDC Transmission and Emerging Technologies in DC Grids
 
C1803061620
C1803061620C1803061620
C1803061620
 
L1303077783
L1303077783L1303077783
L1303077783
 
C010211624
C010211624C010211624
C010211624
 
ECE610 IEEE
ECE610 IEEEECE610 IEEE
ECE610 IEEE
 
A010320106
A010320106A010320106
A010320106
 
I1304026367
I1304026367I1304026367
I1304026367
 

Ähnlich wie FAULT ANALYSIS USING PSCAD/EMTDC for 150 kV SOUTH SULAWESI TRANSMISSION SYSTEM

Impact Analysis of Midpoint Connected STATCOM on Distance Relay Performance
Impact Analysis of Midpoint Connected STATCOM on Distance Relay PerformanceImpact Analysis of Midpoint Connected STATCOM on Distance Relay Performance
Impact Analysis of Midpoint Connected STATCOM on Distance Relay PerformanceRadita Apriana
 
Novel technique in charactarizing a pv module using
Novel technique in charactarizing a pv module usingNovel technique in charactarizing a pv module using
Novel technique in charactarizing a pv module usingeSAT Publishing House
 
Novel technique in charactarizing a pv module using pulse width modulator
Novel technique in charactarizing a pv module using pulse width modulatorNovel technique in charactarizing a pv module using pulse width modulator
Novel technique in charactarizing a pv module using pulse width modulatoreSAT Journals
 
Wavelet based detection and location of faults in 400kv, 50km Underground Po...
 Wavelet based detection and location of faults in 400kv, 50km Underground Po... Wavelet based detection and location of faults in 400kv, 50km Underground Po...
Wavelet based detection and location of faults in 400kv, 50km Underground Po...ijceronline
 
A detailed analysis on the performance
A detailed analysis on the performanceA detailed analysis on the performance
A detailed analysis on the performanceprj_publication
 
EXPERIMENTAL DETERMINATION AND ANALYSIS OF TRANSMISSION LINE PERFORMANCE
EXPERIMENTAL DETERMINATION AND ANALYSIS OF TRANSMISSION LINE PERFORMANCEEXPERIMENTAL DETERMINATION AND ANALYSIS OF TRANSMISSION LINE PERFORMANCE
EXPERIMENTAL DETERMINATION AND ANALYSIS OF TRANSMISSION LINE PERFORMANCEijiert bestjournal
 
overvoltage in distribution network
overvoltage in distribution networkovervoltage in distribution network
overvoltage in distribution networkmegala venkatesan
 
IRJET- Design a Fuzzy Distance Relay Including STATCOM Effects
IRJET-  	  Design a Fuzzy Distance Relay Including STATCOM EffectsIRJET-  	  Design a Fuzzy Distance Relay Including STATCOM Effects
IRJET- Design a Fuzzy Distance Relay Including STATCOM EffectsIRJET Journal
 
Sensoring Leakage Current to Predict Pollution Levels to Improve Transmission...
Sensoring Leakage Current to Predict Pollution Levels to Improve Transmission...Sensoring Leakage Current to Predict Pollution Levels to Improve Transmission...
Sensoring Leakage Current to Predict Pollution Levels to Improve Transmission...Yayah Zakaria
 
Sensoring Leakage Current to Predict Pollution Levels to Improve Transmission...
Sensoring Leakage Current to Predict Pollution Levels to Improve Transmission...Sensoring Leakage Current to Predict Pollution Levels to Improve Transmission...
Sensoring Leakage Current to Predict Pollution Levels to Improve Transmission...IJECEIAES
 
Line Losses in the 14-Bus Power System Network using UPFC
Line Losses in the 14-Bus Power System Network using UPFCLine Losses in the 14-Bus Power System Network using UPFC
Line Losses in the 14-Bus Power System Network using UPFCIDES Editor
 
Mitigation of Voltage Fluctuations in Power System Using STATCOM
Mitigation of Voltage Fluctuations in Power System Using STATCOMMitigation of Voltage Fluctuations in Power System Using STATCOM
Mitigation of Voltage Fluctuations in Power System Using STATCOMIJERA Editor
 
Svpwm based 3 level statcom for reactive power management under line-line
Svpwm based 3 level statcom for reactive power management under line-lineSvpwm based 3 level statcom for reactive power management under line-line
Svpwm based 3 level statcom for reactive power management under line-lineIAEME Publication
 
Carrier based hybrid pwm algorithm with reduced common mode voltage
Carrier based hybrid pwm algorithm with reduced common mode voltageCarrier based hybrid pwm algorithm with reduced common mode voltage
Carrier based hybrid pwm algorithm with reduced common mode voltageIAEME Publication
 
Moshtagh new-approach-ieee-2006
Moshtagh new-approach-ieee-2006Moshtagh new-approach-ieee-2006
Moshtagh new-approach-ieee-2006imeneii
 
Optimal Reactive Power Compensation in Electric Transmission Line using STATCOM
Optimal Reactive Power Compensation in Electric Transmission Line using STATCOMOptimal Reactive Power Compensation in Electric Transmission Line using STATCOM
Optimal Reactive Power Compensation in Electric Transmission Line using STATCOMIOSR Journals
 
Design of a current Mode Sample and Hold Circuit at sampling rate of 150 MS/s
Design of a current Mode Sample and Hold Circuit at sampling rate of 150 MS/sDesign of a current Mode Sample and Hold Circuit at sampling rate of 150 MS/s
Design of a current Mode Sample and Hold Circuit at sampling rate of 150 MS/sIJERA Editor
 

Ähnlich wie FAULT ANALYSIS USING PSCAD/EMTDC for 150 kV SOUTH SULAWESI TRANSMISSION SYSTEM (20)

Power Quality Improvement in QUCEST Larkana Campus by Using Three Types of Po...
Power Quality Improvement in QUCEST Larkana Campus by Using Three Types of Po...Power Quality Improvement in QUCEST Larkana Campus by Using Three Types of Po...
Power Quality Improvement in QUCEST Larkana Campus by Using Three Types of Po...
 
Impact Analysis of Midpoint Connected STATCOM on Distance Relay Performance
Impact Analysis of Midpoint Connected STATCOM on Distance Relay PerformanceImpact Analysis of Midpoint Connected STATCOM on Distance Relay Performance
Impact Analysis of Midpoint Connected STATCOM on Distance Relay Performance
 
Novel technique in charactarizing a pv module using
Novel technique in charactarizing a pv module usingNovel technique in charactarizing a pv module using
Novel technique in charactarizing a pv module using
 
Novel technique in charactarizing a pv module using pulse width modulator
Novel technique in charactarizing a pv module using pulse width modulatorNovel technique in charactarizing a pv module using pulse width modulator
Novel technique in charactarizing a pv module using pulse width modulator
 
Wavelet based detection and location of faults in 400kv, 50km Underground Po...
 Wavelet based detection and location of faults in 400kv, 50km Underground Po... Wavelet based detection and location of faults in 400kv, 50km Underground Po...
Wavelet based detection and location of faults in 400kv, 50km Underground Po...
 
A detailed analysis on the performance
A detailed analysis on the performanceA detailed analysis on the performance
A detailed analysis on the performance
 
EXPERIMENTAL DETERMINATION AND ANALYSIS OF TRANSMISSION LINE PERFORMANCE
EXPERIMENTAL DETERMINATION AND ANALYSIS OF TRANSMISSION LINE PERFORMANCEEXPERIMENTAL DETERMINATION AND ANALYSIS OF TRANSMISSION LINE PERFORMANCE
EXPERIMENTAL DETERMINATION AND ANALYSIS OF TRANSMISSION LINE PERFORMANCE
 
overvoltage in distribution network
overvoltage in distribution networkovervoltage in distribution network
overvoltage in distribution network
 
Implementation on the dSPACE 1104 of VOC-SVM based anti-windup PI Controller ...
Implementation on the dSPACE 1104 of VOC-SVM based anti-windup PI Controller ...Implementation on the dSPACE 1104 of VOC-SVM based anti-windup PI Controller ...
Implementation on the dSPACE 1104 of VOC-SVM based anti-windup PI Controller ...
 
IRJET- Design a Fuzzy Distance Relay Including STATCOM Effects
IRJET-  	  Design a Fuzzy Distance Relay Including STATCOM EffectsIRJET-  	  Design a Fuzzy Distance Relay Including STATCOM Effects
IRJET- Design a Fuzzy Distance Relay Including STATCOM Effects
 
Minor project
Minor projectMinor project
Minor project
 
Sensoring Leakage Current to Predict Pollution Levels to Improve Transmission...
Sensoring Leakage Current to Predict Pollution Levels to Improve Transmission...Sensoring Leakage Current to Predict Pollution Levels to Improve Transmission...
Sensoring Leakage Current to Predict Pollution Levels to Improve Transmission...
 
Sensoring Leakage Current to Predict Pollution Levels to Improve Transmission...
Sensoring Leakage Current to Predict Pollution Levels to Improve Transmission...Sensoring Leakage Current to Predict Pollution Levels to Improve Transmission...
Sensoring Leakage Current to Predict Pollution Levels to Improve Transmission...
 
Line Losses in the 14-Bus Power System Network using UPFC
Line Losses in the 14-Bus Power System Network using UPFCLine Losses in the 14-Bus Power System Network using UPFC
Line Losses in the 14-Bus Power System Network using UPFC
 
Mitigation of Voltage Fluctuations in Power System Using STATCOM
Mitigation of Voltage Fluctuations in Power System Using STATCOMMitigation of Voltage Fluctuations in Power System Using STATCOM
Mitigation of Voltage Fluctuations in Power System Using STATCOM
 
Svpwm based 3 level statcom for reactive power management under line-line
Svpwm based 3 level statcom for reactive power management under line-lineSvpwm based 3 level statcom for reactive power management under line-line
Svpwm based 3 level statcom for reactive power management under line-line
 
Carrier based hybrid pwm algorithm with reduced common mode voltage
Carrier based hybrid pwm algorithm with reduced common mode voltageCarrier based hybrid pwm algorithm with reduced common mode voltage
Carrier based hybrid pwm algorithm with reduced common mode voltage
 
Moshtagh new-approach-ieee-2006
Moshtagh new-approach-ieee-2006Moshtagh new-approach-ieee-2006
Moshtagh new-approach-ieee-2006
 
Optimal Reactive Power Compensation in Electric Transmission Line using STATCOM
Optimal Reactive Power Compensation in Electric Transmission Line using STATCOMOptimal Reactive Power Compensation in Electric Transmission Line using STATCOM
Optimal Reactive Power Compensation in Electric Transmission Line using STATCOM
 
Design of a current Mode Sample and Hold Circuit at sampling rate of 150 MS/s
Design of a current Mode Sample and Hold Circuit at sampling rate of 150 MS/sDesign of a current Mode Sample and Hold Circuit at sampling rate of 150 MS/s
Design of a current Mode Sample and Hold Circuit at sampling rate of 150 MS/s
 

Mehr von Politeknik Negeri Ujung Pandang

Materi Sistem Proteksi dan Distribusi Energi Listrik SAFIRA.pptx
Materi Sistem Proteksi dan Distribusi Energi Listrik SAFIRA.pptxMateri Sistem Proteksi dan Distribusi Energi Listrik SAFIRA.pptx
Materi Sistem Proteksi dan Distribusi Energi Listrik SAFIRA.pptxPoliteknik Negeri Ujung Pandang
 
JARINGAN DISTRIBUSI SEKUNDER (JTR) SISTEM TENAGA LISTRIK
JARINGAN DISTRIBUSI SEKUNDER  (JTR)  SISTEM TENAGA LISTRIKJARINGAN DISTRIBUSI SEKUNDER  (JTR)  SISTEM TENAGA LISTRIK
JARINGAN DISTRIBUSI SEKUNDER (JTR) SISTEM TENAGA LISTRIKPoliteknik Negeri Ujung Pandang
 
JARINGAN DISTRIBUSI SEKUNDER (JTR) SISTEM TENAGA LISTRIK
JARINGAN DISTRIBUSI SEKUNDER  (JTR) SISTEM TENAGA LISTRIKJARINGAN DISTRIBUSI SEKUNDER  (JTR) SISTEM TENAGA LISTRIK
JARINGAN DISTRIBUSI SEKUNDER (JTR) SISTEM TENAGA LISTRIKPoliteknik Negeri Ujung Pandang
 

Mehr von Politeknik Negeri Ujung Pandang (20)

Materi Sistem Proteksi dan Distribusi Energi Listrik SAFIRA.pptx
Materi Sistem Proteksi dan Distribusi Energi Listrik SAFIRA.pptxMateri Sistem Proteksi dan Distribusi Energi Listrik SAFIRA.pptx
Materi Sistem Proteksi dan Distribusi Energi Listrik SAFIRA.pptx
 
SISTEM TRANSMISI ( PENYALURAN) TENAGA LISTRIK
SISTEM TRANSMISI ( PENYALURAN) TENAGA LISTRIKSISTEM TRANSMISI ( PENYALURAN) TENAGA LISTRIK
SISTEM TRANSMISI ( PENYALURAN) TENAGA LISTRIK
 
GARDU INDUK GIS SISTEM TENAGA LISTRIK 150 kV
GARDU INDUK GIS SISTEM TENAGA LISTRIK  150 kVGARDU INDUK GIS SISTEM TENAGA LISTRIK  150 kV
GARDU INDUK GIS SISTEM TENAGA LISTRIK 150 kV
 
GARDU INDUK KONVENSIONAL SISTEM TENAGA LISTRIK 150 kV
GARDU INDUK KONVENSIONAL SISTEM TENAGA LISTRIK 150 kVGARDU INDUK KONVENSIONAL SISTEM TENAGA LISTRIK 150 kV
GARDU INDUK KONVENSIONAL SISTEM TENAGA LISTRIK 150 kV
 
SISTEM OPERASI TENAGA LISTRIK (GRID CODE SULAWESI)
SISTEM OPERASI TENAGA LISTRIK (GRID CODE SULAWESI)SISTEM OPERASI TENAGA LISTRIK (GRID CODE SULAWESI)
SISTEM OPERASI TENAGA LISTRIK (GRID CODE SULAWESI)
 
SISTEM PROTEKSI (PENGAMAN) TENAGA LISTRIK
SISTEM PROTEKSI (PENGAMAN) TENAGA LISTRIKSISTEM PROTEKSI (PENGAMAN) TENAGA LISTRIK
SISTEM PROTEKSI (PENGAMAN) TENAGA LISTRIK
 
JARINGAN DISTRIBUSI PRIMER ( JTM) STL 20 kV
JARINGAN DISTRIBUSI PRIMER ( JTM) STL 20 kVJARINGAN DISTRIBUSI PRIMER ( JTM) STL 20 kV
JARINGAN DISTRIBUSI PRIMER ( JTM) STL 20 kV
 
GARDU DISTRIBUSI SISTEM TENAGA LISTRIK 20 kv/380 V/220V
GARDU DISTRIBUSI SISTEM TENAGA LISTRIK  20 kv/380 V/220VGARDU DISTRIBUSI SISTEM TENAGA LISTRIK  20 kv/380 V/220V
GARDU DISTRIBUSI SISTEM TENAGA LISTRIK 20 kv/380 V/220V
 
JARINGAN DISTRIBUSI SEKUNDER (JTR) SISTEM TENAGA LISTRIK
JARINGAN DISTRIBUSI SEKUNDER  (JTR)  SISTEM TENAGA LISTRIKJARINGAN DISTRIBUSI SEKUNDER  (JTR)  SISTEM TENAGA LISTRIK
JARINGAN DISTRIBUSI SEKUNDER (JTR) SISTEM TENAGA LISTRIK
 
SISTEM PENYALURAN (TRANSMIS) SISTEM TENAGA LISTRIK
SISTEM PENYALURAN (TRANSMIS) SISTEM TENAGA LISTRIKSISTEM PENYALURAN (TRANSMIS) SISTEM TENAGA LISTRIK
SISTEM PENYALURAN (TRANSMIS) SISTEM TENAGA LISTRIK
 
GARDU INDUK KONVENSIONAL SISTEM TENAGA LISTRIK
GARDU INDUK KONVENSIONAL SISTEM TENAGA LISTRIKGARDU INDUK KONVENSIONAL SISTEM TENAGA LISTRIK
GARDU INDUK KONVENSIONAL SISTEM TENAGA LISTRIK
 
GAS INSULATED SUSTATION SISTEM TENAGA LISTRIK
GAS INSULATED SUSTATION SISTEM TENAGA LISTRIKGAS INSULATED SUSTATION SISTEM TENAGA LISTRIK
GAS INSULATED SUSTATION SISTEM TENAGA LISTRIK
 
OPERASI SISTEM TENAGA (GRID CODE INDONESIA)
OPERASI SISTEM TENAGA (GRID CODE INDONESIA)OPERASI SISTEM TENAGA (GRID CODE INDONESIA)
OPERASI SISTEM TENAGA (GRID CODE INDONESIA)
 
SISTEM PENGAMAN ( PROTEKSI) TENAGA LISTRIK
SISTEM PENGAMAN ( PROTEKSI) TENAGA LISTRIKSISTEM PENGAMAN ( PROTEKSI) TENAGA LISTRIK
SISTEM PENGAMAN ( PROTEKSI) TENAGA LISTRIK
 
JARINGAN DISTRIBUSI PRIMER (JTM ) SISTEM TENAGA LISTRIK
JARINGAN DISTRIBUSI PRIMER (JTM ) SISTEM TENAGA LISTRIKJARINGAN DISTRIBUSI PRIMER (JTM ) SISTEM TENAGA LISTRIK
JARINGAN DISTRIBUSI PRIMER (JTM ) SISTEM TENAGA LISTRIK
 
GARDU DISTRIBUSI SISTEM TENAGA LISTRIK 20 KV/ 380 V
GARDU DISTRIBUSI SISTEM TENAGA LISTRIK 20 KV/ 380 VGARDU DISTRIBUSI SISTEM TENAGA LISTRIK 20 KV/ 380 V
GARDU DISTRIBUSI SISTEM TENAGA LISTRIK 20 KV/ 380 V
 
JARINGAN DISTRIBUSI SEKUNDER (JTR) SISTEM TENAGA LISTRIK
JARINGAN DISTRIBUSI SEKUNDER  (JTR) SISTEM TENAGA LISTRIKJARINGAN DISTRIBUSI SEKUNDER  (JTR) SISTEM TENAGA LISTRIK
JARINGAN DISTRIBUSI SEKUNDER (JTR) SISTEM TENAGA LISTRIK
 
GARDU INDUK KONVENSIONAL SISTEM TENAGA LISTRIK
GARDU INDUK KONVENSIONAL SISTEM TENAGA LISTRIKGARDU INDUK KONVENSIONAL SISTEM TENAGA LISTRIK
GARDU INDUK KONVENSIONAL SISTEM TENAGA LISTRIK
 
SISTEM TRANSMISI TENAGA LISTRIK INDONESIA
SISTEM TRANSMISI TENAGA LISTRIK INDONESIASISTEM TRANSMISI TENAGA LISTRIK INDONESIA
SISTEM TRANSMISI TENAGA LISTRIK INDONESIA
 
GAS INSULATED SUSTATION SISTEM TENAGA LISTRIK
GAS INSULATED SUSTATION SISTEM TENAGA LISTRIKGAS INSULATED SUSTATION SISTEM TENAGA LISTRIK
GAS INSULATED SUSTATION SISTEM TENAGA LISTRIK
 

Kürzlich hochgeladen

Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxMuhammadAsimMuhammad6
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Servicemeghakumariji156
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEselvakumar948
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiessarkmank1
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxNadaHaitham1
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 

Kürzlich hochgeladen (20)

Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptx
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 

FAULT ANALYSIS USING PSCAD/EMTDC for 150 kV SOUTH SULAWESI TRANSMISSION SYSTEM

  • 1. UTMUNIVERSITI TEKNOLOGI MALAYSIA Fault Analysis Using PSCAD/EMTDC for 150 kV South Sulawesi Transmission System M. Saini, A.A. Mohd Zin, M.W. Mustafa, A.R. Sultan. Faculty of Electrical Engineering, Universiti Teknologi Malaysia, 81310 UTM Johor Bahru, Johor.
  • 2. TABLE OF CONTENT 1. INTRODUCTION 2. Overview Short Circuit Fault Analysis 3. RESEARCH METHOD 4. ANALYSIS OF THE SIMULATION RESULTS 5. RESULTS 6.CONCLUSION
  • 3. Introduction In analyzing the problems in South Sulawesi transmission system, simulations of PSCAD / EMTDC [5-6] and PWS (Power World Simulator) [7] software were used to simulate changes in electrical current and voltage during a disturbance. -Single phase to Ground, -Line to Fault Line, -Double Line to Ground -Three phase Short Circuit
  • 4. Introduction Since 2002, the transmission system of South Sulawesi has introduced Intelligent Electronic Devices (IEDs) such as Digital Protective Relays (DPRs) and the Digital Fault Recorders (DFRs) on all feeder transmission [8]. In the simulations of this total Power Plant 591.3 MW and the total Load of 568.9 MW.
  • 5. Overview Short Circuit Fault Analysis Short circuit interruption is one of the disorders of electric power system transient characteristics that must be addressed by the safety equipment. The occurrence of short circuit current spikes results in a higher magnitude than the normal state and the voltage at the site to be very low can result -Damage to the insulation -Mechanical damage to the conductor -Electrical sparks -The worst is the failure of the overall system operation [9].
  • 6. RESEARCH METHOD A. PSCAD/EMTDC This research analysis using PSCAD (Power System CAD) is to simulate fault conditions of the transmission system in South Sulawesi were presented by using the transmission- line model line Bergeron of PSCAD / EMTDC [11] . PSCAD enables users to build a circuit schematic, running simulations, analyzing results, manage data in a fully integrated graphical environment, control and meter so that users can change system parameters during the simulation run and can obtain immediate results [11].
  • 7. RESEARCH METHOD PSCAD comes with a library of models that have been programmed and tested, ranging from simple passive elements, control functions and more complex models such as electric machines, FACTS devise, transmission lines, transformers and cables. EMTDC (Electromagnetic Transient, Including DC) proposes and solves differential equations in time domain.
  • 8. RESEARCH METHOD B. PWS ( Power Worlds Simulator) PSW is a power system simulation package consists of a number of integrated products. This simulator allows the user to visualize the system through the use of color charts online, complete with animated zooming capabilities and planning. System models can be modified and quickly built from scratch using a full-featured graphics editor special simulator. Transmission lines can be switched in or out of service, the new transmission line can be added and created. .
  • 9. RESEARCH METHOD This simulation package capable of solving the power system consists of up to 100,000 buses covering of Integrated Economic Dispatch, Power transfer distribution factor Computation, Short Circuit Analysis, and contingency analysis. PWS had the ability to import data from all sources of data, Moreover, in order to power flow model of PWS, a text file interface to exchange data and execute command scripts BATCH .
  • 10. ANALYSIS OF THE SIMULATION RESULTS Simulation System Simulation system is performed during a short circuit on the 150 kV transmission system south Sulawesi as shown in Figure 3. Transmission line simulation between bus PPKEP and bus PPARE fault lines to ground (LG), three-phase (LLL), double fault line (LL) and double fault line to ground (LLG) by fault impedance 0 ohm and 45 km from Pangkep to Pare-Pare. During the simulation, load flow data is the total power plan 591.3 MW, the total load, 568,9 MW and the power loss 22.4 MW with a base of 150 kV and 100 MVA.
  • 11. Single Line Diagram of 150 kV Transmission South Sulawesi
  • 12. Pre-Fault Voltage and Current Waveform between Bus PPKEP and Bus PPARE
  • 13. Voltage and current waveform of Line to Ground Fault (LG) between Bus PPKE and Bus PPARE
  • 14. Voltage and current waveform of Line-Line to Ground Fault (LLG) Between Bus PPKE and Bus PPARE
  • 15. Voltage and current waveform of Line-Line Fault (LL) Between Bus PPKE and Bus PPARE
  • 16. Voltage and current waveform of Line-Line-Line Fault (LLL) Between Bus PPKE and Bus PPARE
  • 17. RESULTS From the simulation results it can be analyzed from the characteristics of electric current and voltage at Bus PKEP, that bus signal waveform of PPARE has a peak value of electric current equal to 509 Amperes when a fault line to ground (LG), three-phase fault (LLL), double line fault (LL) and double line to ground faults (LLG),
  • 18. Table 1. Short circuit Current Without Fault Impedance Z= 0
  • 19. Table 2. Short circuit Current With Fault Impedance Z= 10 Ohm
  • 20. Table 3. Short circuit Current With Fault Impedance Z= 15 Ohm
  • 21. Table 4. Fault Voltage With Fault Impedance Z= 0 Ohm
  • 22. Table 5. Fault Voltage With Fault Impedance Z= 10 Ohm
  • 23. Table 6. Fault Voltage With Fault Impedance Z= 15 Ohm
  • 24. CONCLUSION For short circuit fault with impedance Z = 0, the fault tends to electrical current higher than the short circuit fault using impedance Z = 10 ohm and Z =15 ohm, this is due to the absence of resistance to the flow of electric short circuit fault. The interference voltage at Z = 15 Ohm tends to be greater than the voltage at Z = 0 ohm impedance and Z = 10 Ohm, this is due to large resistance causes a very small electric current flows so that the voltage is higher
  • 25. CONCLUSION For a distance fault of 22.5 km obtained by the fault current from the biggest bus PKEP, while at a distance of 66.5 km, it is acquired by the fault current of the largest from the bus PPARE, four types of errors are analyzed in which the Z = 0 ohm is the largest short circuit interruption occurs in three phase fault (LLL). While at Z = 10 ohm = 15 ohm Z, the biggest mistakes of the line short-circuit line is ground faults (LLG).
  • 26. 26