SlideShare ist ein Scribd-Unternehmen logo
1 von 12
Downloaden Sie, um offline zu lesen
www.systra.com
BACK ANALYSIS OF HIGH TUNNEL
CONVERGENCES IN CLAYEY MARLS
SYSTRA, Paris, France: MISANO Edoardo, COUBRAY Jean-Louis,
ESPINOZA CARMONA Fabiola; Paris, France: CHIRIOTTI Elena
Figure 1. Tunnel location and typical tunnel cross section
BACK ANALYSIS OF HIGH TUNNEL
CONVERGENCES IN CLAYEY MARLS
SYSTRA, Paris, France: MISANO Edoardo, COUBRAY Jean-Louis,
ESPINOZA CARMONA Fabiola; Paris, France: CHIRIOTTI Elena
INTRODUCTION
Ganntas Tunnel is part of the modernization project of the
railway between Alger and Oran, in Algeria. In order to double
and rectify the existing line between El Affroun and Khémis
Miliana, the alignment foresees the excavation of a 7km-long
twin tunnel. The excavation works started in June 2011 with
the contractor CCECC, under the supervision of SYSTRA.
Excavation is driven in conventional method by hydraulic
hammer simultaneously on 8 different faces since excavation
was started also from a junction window towards the middle
of the tunnel. The minimum longitudinal distance to be
respected between two contiguous tunnel faces has been set
to 30m. The tunnel cross-section is a 70m² oval shaped profile,
temporary support consists of shotcrete, bolts and steel ribs.
A 30 to 50cm thick cast in situ concrete final lining is provided
as well.
When the tunnel reached a fault zone in soft clayey marls,
extreme squeezing occurred, works were stopped, and re-
profiling operations were carried out along more than 100m
tunnel length. To date, works proceed at slow rate since high
convergences are still monitored and completion of works is
not expected before December 2016.
2
4
samples; the main characteristics of the clayey
marls are summarized hereafter:
•	Passing at 80μm is about 70%
(determined on superficial detrital)
•	Plasticity index is around 20
(determined on superficial detrital)
•	CaCO3
content varies between 11%
and 32% with a mean value of 18,8%
•	Undrained cohesion varies between
30kPa and 63kPa (4 direct shear tests)
•	Friction angle varies between 15° and 20°
(4 direct shear tests)
•	Resistance to uniaxial compression varies
between 0,9MPa and 7,6MPa (3 tests)
It should be stresses that the totality of the
tests and investigations carried out is far from
being representative for a 7km tunnel and
this has led to an overestimation of resistance
parameters of soils. The geological mapping at
tunnel face assessed RMR values as low as 14
when high convergences occurred, such value
appears completely inconsistent with the set
of geotechnical parameters used to design the
tunnel supports.
HYDROLOGY
Clayey marls showed an impermeable overall
behavior, water circulation is possible in
fractures, bedding planes plans and at contact
with the sandstone layer. Water inflows are
mainly supplied by rainfalls. Experience derived
from the excavated sections confirmed that
inflows are scarce and dry conditions may be
assumes at the tunnel outward.
GEOLOGY
The project is located within the Tellian Atlas
mountain area, including in particular the Djebel
Ganntas massif in between Mitidja and Chleff
plains. Djebel Ganntas is characterized by an
extensive massif aligned in East-West direction
with smooth slopes made of soft clays that
emerge in multiple cliffs and ravines. On the top
of it, along the edge, a more recent sandstone
formation is found.
The existing data on the geology did not allow
to establish an accurate geological model at
tender stage. In-situ investigations allowed at
design stage to identify a Quaternary alluvial
cover of clays and gravel, followed by a
Miocene stratum divided in a sandy top layer
and a lower clayey layer.
From a structural point of view, geological
maps suggest a north direction dip of layers,
but the in situ surveys showed that layers
were highly folded. The lack of information
at tender stage on the structure of the
geological series should have triggered an
extensive investigation campaign at detailed
design stage which did not take place causing
serious consequences on costs and time
at construction stage.
The geological longitudinal profile was updated
four times between 1991 and 2011, the latest
being the one shown in Figure 2. Except for
a short section near the South portal, the
whole tunnel is driven through the Miocene
clayey marls. On the South side, a complicated
structure of layers was identified, in particular
a major fault zone was found at chainage
pk 180+600 where clayey marls were extremely
fractured. Nevertheless the geological risk in
this zone was underestimated and no further
investigations were established to evaluate the
mechanical parameters. It is in this zone that
the excavation encountered the major problems
and where high deformations were registered
on tunnel supporting lining.
The geological model has been established
on the basis of the information collected
through eight boreholes along the alignment
and a geophysical surface survey with the AMT
method (Audio Mangetotelluric). Laboratory
tests have been performed on extracted
5
foot before benching. High convergences caused
works to stop in order to proceed to re-profiling
operations. The contractor proposed the
E1 excavation profile (see Figure 4), the main
difference with the A1 profile consists in closing
the rib foot with a provisional invert before
benching and providing a face reinforcement by
means of 34 fiberglass bolts of 25mm diameter
and 12m length. A forepoling was added
consisting in a line of 42mm diameter tubes
at crown. After re-profiling, excavation restarted
using the new support profile. The adopted
solution showed poor results, convergences
continued to raise and a cumulative value of
HIGH CONVERGENCES
OCCURRENCE
On December 2013, around chainage pk
108+600, with about 100m overburden,
excavation was proceeding with A1 excavation
profile (see Figure 4), when high convergences
of about 20cm started to be measured at about
15m behind the tunnel face. Excavation was
driven by top heading with an advance rate of
about 1m/day. The temporary support consisted
of a 30cm shotcrete layer reinforced with HEB
180 spaced 0,6m, and 12 radial bolts of 25mm
diameter and 4m length installed at each rib
Figure 3. Clayey marls on the left, sandstones inclusions in clayey matrix on the right
Figure 2. Geological Profile of the Ganntas tunnel and detail of the faulted zone
6
to reinforce these elements by installing
2+2 micro piles beneath each rib foot and
increasing the bolts length to 6m in this zone.
During re-profiling operations convergences
did not increased, however, when the tunnel
face advancement restarted, 7cm of additional
convergence were registered again.
70cm convergence was reached when works
needed to be stopped again to proceed to new
re-profiling operations and third excavation
profile (E1R, see Figure 4) was proposed. Since
convergences were affecting mostly the rib foot
and the heave of the provisional invert was
remarked (see Figure 6), the Contractor decided
Figure 4. Excavation profile used to cope with the fault zone
7
Figure 5. Convergence registration at chainage pk 180+600
INTERVENTIONS A1 PROFILE E1 PROFILE E1R PROFILE
RADIAL BOLTS 6+6 Φ 25mm L=4m 6+6 Φ 25mm L=4m
8/9 Φ 25mm / L=4m
2+2 micro pile / L=6m
3+3 Φ25mm / L=6m
FORE-POLING - 12 tubes Φ 42mm 12 tubes Φ 42mm
STEEL RIBS HEB 180 @0,6m HEB 180 @1,0m HEB 180 @0,6m
PROVISIONAL INVERT - HEB 180 @1,0m HEB 180 @0,6m
SHOTCRETE 5+25cm 5+25cm 5+25cm
SHOTCRETE AT FACE - 4cm 7cm
FACE BOLTS - 34 Φ 25mm 34 Φ 25mm
Table 1. Excavation profile interventions around chainage pk 108+600
Figure 6. Rib foot displacement and provisional invert up-heave
8
Figure 7. Characteristic curves, Lombardi-Amberg (1974)
Table 3. Calculated rock mass parameters
according to Hoek-Brown criteria
RMR
[-]
GSI
[-]
UCS
[MPa]
mi
[-]
D
[-]
Ei
[GPa]
14 9 30 7 0,5 5,2
Tunnel face stability
High convergence phenomena are the presence
of an extended plasticized zone ahead
the tunnel face that only the back-calculated
parameter could reproduce.
The application of the stability number
(see equation (1), Panet, 1982) shows that
the stability of the tunnel face is very critical
and that an important support at tunnel face
is needed (see Table 4).
A tunnel to be driven in difficult cohesive
soils that show high convergences needs
an important stiffening of the advance
core ahead the tunnel face in order to limit
the plasticization in this zone and to allow
the installation of the temporary support before
rock failure is produced around the cavity
(Lunardi, 1999). In order to have a stability
number lower than 6,7 (to assure face stability
according to Panet 1982), the equation (2) must
be satisfied, which means that a mitigation
measure capable to increment the material
cohesion ahead the tunnel face of about 165kPa
is needed.
Using the transformation on the Mohr-Coulomb
plan (see equations (3) and (4)) and considering
a 200kPa soil-grout shear resistance at bolt
interface and standard fiber bolt dimensions,
ANALYSIS OF THE ROCK
MASS BEHAVIOUR
In parallel to the Contractor’s analyses,
the Engineer developed his own back analyses
of the observed phenomena in order to
better understand the problem and the rock
mass behavior to cross-check the proposed
excavation. The study is divided into two
parts: in the former the rock mass is analyzed
without any support in order to identify the
right set of rock mass parameters which better
describe the massif behavior; in the latter the
calculated parameters are used to analyze
the proposed excavation profile in order to
check the adequateness and the coherence
with monitoring data.
Back-analysis of
rock mass parameters
The back-analysis is carried out by using the
convergence-confinement method as proposed
by Lombardi-Amberg (1974), identifying the
set of parameters which allows to reproduce
70cm of observed convergence on the tunnel
characteristic curve at tunnel face when the half-
core resistance is reached. Available geological
data collected during construction, such as
the RMR index were used in order to best fit
the solution. Results are shown in Table 2.
Parameters were initially defined according to
the Hoek  Brown criteria, in order to use the
RMR information, and then they are converted
to Mohr-Coulomb strength parameters more
suitable to perform F.E.M. analysis.
It is to note that the difference between the
original parameters and the calculated ones
is quite relevant. The estimated stiffness
is reduced to 50% and the resistance almost
to 35%.
Table 2. Rock mass parameters according
to Mohr-Coulomb criteria
Original
Parameters
Calculated
parameters
Young Module [MPa] 200 125
Cohesion [kPa] 200 75
Friction Angle [°] 20 17
Where
9
the minimum density of needed elements is
1 bolt/m². Such density is the double of the
one foreseen in E1 and E1R excavation profiles,
which both failed in controlling convergences.
7
excavation profiles, which both failed in controlling convergences.
cm
P
N

02

kPac
P
c
P
cm
240
cos7,6
)sin1(
7.6
2 00







3
cos2
sin1





c
  






S
N
ATLDT b
bbTaF  ;min3
Where:
 P0 = lithostatic stress
 σcm = uniaxial compression resistance
 S = excavation surface
 Nb = number of bolts at tunnel face
 Ab = bolt resistant section of bolt
 b = bolt yielding stress
 D = drilling hole diameter
 L = bolt length
 a = soil-grout shear resistance at interface
Table 4. Stability numbers for the two different parameter sets
Original parameters 7,5
Calculated parameters 21,2
7
e transformation on the Mohr-Coulomb plan (see equations (3) and (4)) and considering a
grout shear resistance at bolt interface and standard fiber bolt dimensions, the minimum
eeded elements is 1 bolt/ m². Such density is the double of the one foreseen in E1 and E1R
rofiles, which both failed in controlling convergences.
cm
P
N

02
 (1)
kPac
P
c
P
cm
240
cos7,6
)sin1(
7.6
2 00







(2)
3
cos2
sin1





c
(3)
  






S
N
ATLDT b
bbTaF  ;min3
(4)
lithostatic stress
= uniaxial compression resistance
xcavation surface
number of bolts at tunnel face
bolt resistant section of bolt
bolt yielding stress
drilling hole diameter
olt length
soil-grout shear resistance at interface
bility numbers for the two different parameter sets
Original parameters 7,5
Calculated parameters 21,2
7
ation on the Mohr-Coulomb plan (see equations (3) and (4)) and considering a
resistance at bolt interface and standard fiber bolt dimensions, the minimum
nts is 1 bolt/ m². Such density is the double of the one foreseen in E1 and E1R
h both failed in controlling convergences.
cm
P
N

02
 (1)
kPac
P
c
P
cm
240
cos7,6
)sin1(
7.6
2 00







(2)
3
cos2
sin1





c
(3)
  






S
N
ATLDT b
bbTaF  ;min3
(4)
ress
mpression resistance
rface
bolts at tunnel face
nt section of bolt
stress
diameter
ear resistance at interface
rs for the two different parameter sets
parameters 7,5
d parameters 21,2
Phase number Description Distance from tunnel face Deconfinement ratio
1 Geostatic conditions - 0% P0
2 Half top section excavation 0 m 80% P0
3 Steel ribs and shotcrete installation 1 m 90% P0
4 1 day shotcrete curing 2 m 93% P0
5 3 day shotcrete curing 3 m 95% P0
6 9 day shotcrete curing 4 m 98% P0
7 28 day shotcrete curing 5 m 100% P0
8 Invert excavation 0 m* 80% P1**
9 Steel ribs and shotcrete installation on invert 1 m* 95% P1**
10 1 day shotcrete curing of invert lining 2 m* 96% P1**
11 28 day shotcrete curing of invert lining ∞ 100% P1**
Cross-check of the proposed
supporting sections
Calculated rock mass parameters are then used
to check the proposed supporting system
and to verify the consistency of the results
found in the previous analysis. The excavation
profiles E1 and E1R are studied with the
help of F.E.M. using the calculation program
PHASE² (Rocscience). The rock mass is taken
into account as an equivalent continuum, soil
behavior is modeled as an elastic perfectly
plastic material, and the resistance law follows
the Mohr-Coulomb criteria. Staged construction
is taken into account (see Table 5) in different
calculation phases in order to consider the
non-linear behavior of materials, deconfinement
ratios are estimated on the results of an
axisymmetric problem, as intersection of
the convergence curve along the tunnel and
the characteristic curve as evaluated previously.
Forepoling has been taken into account in the
model by stiffening a portion of soil at crown.
The principal outcomes of the analysis are
the following:
•	Results in term of displacement are consistent
with monitoring data (see Figure 8),
•	The extension of the plastic zone points
out that radial bolts are not an effective
intervention to limit convergences since
they are placed within the plasticized zone,
•	The stress analysis of first lining shows
clearly that the foreseen intervention could
not afford the pressures induced by the failing
rock mass.
Table 4. Stability numbers for
the two different parameter sets
Original parameters 7,5
Calculated parameters 21,2
7
e transformation on the Mohr-Coulomb plan (see equations (3) and (4)) and considering a
grout shear resistance at bolt interface and standard fiber bolt dimensions, the minimum
eeded elements is 1 bolt/ m². Such density is the double of the one foreseen in E1 and E1R
rofiles, which both failed in controlling convergences.
cm
P
N

02
 (1)
kPac
P
c
P
cm
240
cos7,6
)sin1(
7.6
2 00







(2)
3
cos2
sin1





c
(3)
  






S
N
ATLDT b
bbTaF  ;min3
(4)
lithostatic stress
= uniaxial compression resistance
xcavation surface
number of bolts at tunnel face
bolt resistant section of bolt
bolt yielding stress
drilling hole diameter
olt length
soil-grout shear resistance at interface
bility numbers for the two different parameter sets
Original parameters 7,5
Calculated parameters 21,2
7
ation on the Mohr-Coulomb plan (see equations (3) and (4)) and considering a
resistance at bolt interface and standard fiber bolt dimensions, the minimum
nts is 1 bolt/ m². Such density is the double of the one foreseen in E1 and E1R
h both failed in controlling convergences.
cm
P
N

02
 (1)
kPac
P
c
P
cm
240
cos7,6
)sin1(
7.6
2 00







(2)
3
cos2
sin1





c
(3)
  






S
N
ATLDT b
bbTaF  ;min3
(4)
ress
mpression resistance
rface
bolts at tunnel face
nt section of bolt
stress
diameter
ear resistance at interface
rs for the two different parameter sets
parameters 7,5
d parameters 21,2
7
e transformation on the Mohr-Coulomb plan (see equations (3) and (4)) and considering a
grout shear resistance at bolt interface and standard fiber bolt dimensions, the minimum
eeded elements is 1 bolt/ m². Such density is the double of the one foreseen in E1 and E1R
rofiles, which both failed in controlling convergences.
cm
P
N

02
 (1)
kPac
P
c
P
cm
240
cos7,6
)sin1(
7.6
2 00







(2)
3
cos2
sin1





c
(3)
  






S
N
ATLDT b
bbTaF  ;min3
(4)
lithostatic stress
= uniaxial compression resistance
xcavation surface
number of bolts at tunnel face
bolt resistant section of bolt
bolt yielding stress
drilling hole diameter
olt length
soil-grout shear resistance at interface
bility numbers for the two different parameter sets
Original parameters 7,5
Calculated parameters 21,2
7
ation on the Mohr-Coulomb plan (see equations (3) and (4)) and considering a
resistance at bolt interface and standard fiber bolt dimensions, the minimum
nts is 1 bolt/ m². Such density is the double of the one foreseen in E1 and E1R
h both failed in controlling convergences.
cm
P
N

02
 (1)
kPac
P
c
P
cm
240
cos7,6
)sin1(
7.6
2 00







(2)
3
cos2
sin1





c
(3)
  






S
N
ATLDT b
bbTaF  ;min3
(4)
ress
mpression resistance
rface
bolts at tunnel face
nt section of bolt
stress
diameter
ear resistance at interface
rs for the two different parameter sets
parameters 7,5
d parameters 21,2
7
e transformation on the Mohr-Coulomb plan (see equations (3) and (4)) and considering a
grout shear resistance at bolt interface and standard fiber bolt dimensions, the minimum
eeded elements is 1 bolt/ m². Such density is the double of the one foreseen in E1 and E1R
rofiles, which both failed in controlling convergences.
cm
P
N

02
 (1)
kPac
P
c
P
cm
240
cos7,6
)sin1(
7.6
2 00







(2)
3
cos2
sin1





c
(3)
  






S
N
ATLDT b
bbTaF  ;min3
(4)
lithostatic stress
= uniaxial compression resistance
xcavation surface
number of bolts at tunnel face
bolt resistant section of bolt
bolt yielding stress
drilling hole diameter
olt length
soil-grout shear resistance at interface
bility numbers for the two different parameter sets
Original parameters 7,5
Calculated parameters 21,2
7
ation on the Mohr-Coulomb plan (see equations (3) and (4)) and considering a
resistance at bolt interface and standard fiber bolt dimensions, the minimum
nts is 1 bolt/ m². Such density is the double of the one foreseen in E1 and E1R
h both failed in controlling convergences.
cm
P
N

02
 (1)
kPac
P
c
P
cm
240
cos7,6
)sin1(
7.6
2 00







(2)
3
cos2
sin1





c
(3)
  






S
N
ATLDT b
bbTaF  ;min3
(4)
ress
mpression resistance
rface
bolts at tunnel face
nt section of bolt
stress
diameter
ear resistance at interface
rs for the two different parameter sets
parameters 7,5
d parameters 21,2
Table 5. Calculation phases | * distance is calculated from bench, ** P1 is the residual stress in bench
10
Figure 8. Calculated displacements (in meters) for E1 (on the left) and plastic zone extension around E1R (on the right)
Figure 9. First lining verification of E1 excavation profile
11
Experience in tunneling showed that when
face stability is not assured in plastic soils,
the support system is not able to control
the development of the plastic zone around
the excavation and pre-confining measures,
such as extended face nailing or grouting,
are necessary in order to ensure a safe
excavation and a cost effective work progress.
The presented case history reminds finally of
the importance of the following main aspects:
•	Performing a sufficient quantity of ground
investigations before tender stage may highly
reduce costs and time of the entire project.
•	Construction methods and engineering
analyses should be integrated in a
homogeneous design process in order
to find the most suitable solution.
•	When the lack of geological and geotechnical
information do not allow to define safe
and reliable rock mass characteristics, it is
important to analyze the rock-mass behavior
during construction. In case of deviation
from the foreseen behavior, such information
will allow then to perform back-analysis
to adapt the construction to the encountered
conditions.
During the excavation of the Ganntas Tunnel,
in the Algerian Atlas mountain area, high
convergences occurred slightly after temporary
support installation, and re-profiling operation
were carried out along more than 100m
of tunnel. The failure occurred when the
tunnel face reached a faulted zone in clayey
marls with an overburden of about 100m.
The geological investigations proved to be
insufficient at design stage since the presence
of such material along the tunnel alignment
was unknown until the construction stage.
This occurrence caused delays and costs
increase since the appropriate solution was not
found in short term. The Engineer performed
a series of independent analyses to back-
calculate the design parameters of the rock
mass and to calibrate a model able to reproduce
the monitoring data in terms of displacement
of the supporting lining.
The accordance between the analysis results
and the in-situ observations proves that the
original set of parameter was not able to
properly describe the soil-structure interaction
problem and therefore to design an effective
supporting system.
REFERENCES
Hoek, E., Carranza-Torres, C. 2002. Hoek-Brown failure criterion – 2002 edition.
Proc. NARMS-TAC Conference, Toronto
ITA Working Group Research. Strategy for Site Investigation of Tunneling Projects.
ITA Report n.15/May 2015
Lombardi, G., Amberg, W. A. 1974. Une méthode de calcul élasto-plastique de l’état de tension
et de déformation autour d’une cavité souterraine. International Congres ISRM, Denver.
Lunardi, P. 1999. The Tartaguille tunnel, or use of the ADECO-RS approach in the construction
of an “impossible” tunnel. Gallerie e grandi opera sotterranee, No 58.
Panet, M., Guenot A. 1982. Analysis of convergence behind the face of a tunnel.
Tunnelling, Brighton.
CONCLUSIONS
© SYSTRA2016,© M.Kadri/CAPAPictures
72 rue Henry Farman
CS 41594
75513 Paris Cedex 15
+ 33 1 40 16 61 00

Weitere ähnliche Inhalte

Was ist angesagt?

Lect 6 pavement design
Lect 6 pavement designLect 6 pavement design
Lect 6 pavement design
M Firdaus
 
Pavement skid resistance
Pavement skid resistancePavement skid resistance
Pavement skid resistance
Hai Vo
 
Experimental behaviour and analysis of stress in rigid pavement
Experimental behaviour and analysis of stress in rigid pavementExperimental behaviour and analysis of stress in rigid pavement
Experimental behaviour and analysis of stress in rigid pavement
Vivek Loyola
 
Pavement materials and design in western australia by geoffrey cocks
Pavement materials and design in western australia by geoffrey cocksPavement materials and design in western australia by geoffrey cocks
Pavement materials and design in western australia by geoffrey cocks
Engineers Australia
 
Design of multi-anchored_walls_for_deep (1)
Design of multi-anchored_walls_for_deep (1)Design of multi-anchored_walls_for_deep (1)
Design of multi-anchored_walls_for_deep (1)
Bulent U
 

Was ist angesagt? (20)

GeoEng12334
GeoEng12334GeoEng12334
GeoEng12334
 
Evaluation and strengthening of reconstructed roads excavated for utilities u...
Evaluation and strengthening of reconstructed roads excavated for utilities u...Evaluation and strengthening of reconstructed roads excavated for utilities u...
Evaluation and strengthening of reconstructed roads excavated for utilities u...
 
Lect 6 pavement design
Lect 6 pavement designLect 6 pavement design
Lect 6 pavement design
 
Final year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement DesignFinal year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement Design
 
Lyapichev. Analysis, design & behavior of CFRDs
Lyapichev. Analysis, design & behavior of CFRDsLyapichev. Analysis, design & behavior of CFRDs
Lyapichev. Analysis, design & behavior of CFRDs
 
Study of design of the flexible pavements
Study of design of the flexible pavementsStudy of design of the flexible pavements
Study of design of the flexible pavements
 
Lyapichev. New RCC dams (Inter. Conf. on RCC, 2003)
Lyapichev. New RCC dams (Inter. Conf. on RCC, 2003)Lyapichev. New RCC dams (Inter. Conf. on RCC, 2003)
Lyapichev. New RCC dams (Inter. Conf. on RCC, 2003)
 
Mechanical Response Analysis of Asphalt Pavement Structure
Mechanical Response Analysis of Asphalt Pavement StructureMechanical Response Analysis of Asphalt Pavement Structure
Mechanical Response Analysis of Asphalt Pavement Structure
 
Lyapichev Yury - Innovation structures of very lean RCC dams (Journal of Stru...
Lyapichev Yury - Innovation structures of very lean RCC dams (Journal of Stru...Lyapichev Yury - Innovation structures of very lean RCC dams (Journal of Stru...
Lyapichev Yury - Innovation structures of very lean RCC dams (Journal of Stru...
 
Pavement skid resistance
Pavement skid resistancePavement skid resistance
Pavement skid resistance
 
Introduction to Pavement Design Concepts
Introduction to Pavement Design ConceptsIntroduction to Pavement Design Concepts
Introduction to Pavement Design Concepts
 
Design of a rigid pavement (jpcp & crcp)
Design of a rigid pavement (jpcp & crcp)Design of a rigid pavement (jpcp & crcp)
Design of a rigid pavement (jpcp & crcp)
 
Reservoir characterization technique based on geostatistical inversion method
Reservoir characterization technique based on geostatistical inversion methodReservoir characterization technique based on geostatistical inversion method
Reservoir characterization technique based on geostatistical inversion method
 
Experimental behaviour and analysis of stress in rigid pavement
Experimental behaviour and analysis of stress in rigid pavementExperimental behaviour and analysis of stress in rigid pavement
Experimental behaviour and analysis of stress in rigid pavement
 
Pavement materials and design in western australia by geoffrey cocks
Pavement materials and design in western australia by geoffrey cocksPavement materials and design in western australia by geoffrey cocks
Pavement materials and design in western australia by geoffrey cocks
 
Unit 5
Unit 5Unit 5
Unit 5
 
Flexible Pavement Design
Flexible Pavement DesignFlexible Pavement Design
Flexible Pavement Design
 
Design of multi-anchored_walls_for_deep (1)
Design of multi-anchored_walls_for_deep (1)Design of multi-anchored_walls_for_deep (1)
Design of multi-anchored_walls_for_deep (1)
 
Pavement design
Pavement designPavement design
Pavement design
 
Introduction, alignment & surveys
Introduction, alignment & surveysIntroduction, alignment & surveys
Introduction, alignment & surveys
 

Ähnlich wie Back analysis of high tunnel convergences in clayey marls

Mokpo symposium pecker 2006
Mokpo symposium pecker 2006Mokpo symposium pecker 2006
Mokpo symposium pecker 2006
gefyra-rion
 
Athens pecker 2005
Athens pecker 2005Athens pecker 2005
Athens pecker 2005
gefyra-rion
 
Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015
Abner Silva
 
Design and dynamic testing of precast piles oscar varde
Design and dynamic testing of precast piles   oscar vardeDesign and dynamic testing of precast piles   oscar varde
Design and dynamic testing of precast piles oscar varde
cfpbolivia
 
03 azamat the experience of industrial processing of an uranium deposit of ak...
03 azamat the experience of industrial processing of an uranium deposit of ak...03 azamat the experience of industrial processing of an uranium deposit of ak...
03 azamat the experience of industrial processing of an uranium deposit of ak...
Monatom Mgl
 
Geo trans2004 pecker
Geo trans2004 peckerGeo trans2004 pecker
Geo trans2004 pecker
gefyra-rion
 

Ähnlich wie Back analysis of high tunnel convergences in clayey marls (20)

PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxPPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
 
Effect Of Water On Slope Stability And Investigation Of ΝΝw Drainage Techniqu...
Effect Of Water On Slope Stability And Investigation Of ΝΝw Drainage Techniqu...Effect Of Water On Slope Stability And Investigation Of ΝΝw Drainage Techniqu...
Effect Of Water On Slope Stability And Investigation Of ΝΝw Drainage Techniqu...
 
Assessing the interaction between the excavation of a large cavern and existi...
Assessing the interaction between the excavation of a large cavern and existi...Assessing the interaction between the excavation of a large cavern and existi...
Assessing the interaction between the excavation of a large cavern and existi...
 
SPE-178786-MS
SPE-178786-MSSPE-178786-MS
SPE-178786-MS
 
S7
S7S7
S7
 
Paper on intrepid approachs in highway tunnel in bhutan
Paper on intrepid approachs in highway tunnel in bhutanPaper on intrepid approachs in highway tunnel in bhutan
Paper on intrepid approachs in highway tunnel in bhutan
 
Mokpo symposium pecker 2006
Mokpo symposium pecker 2006Mokpo symposium pecker 2006
Mokpo symposium pecker 2006
 
Metro Torino Extension - Design and construction problems
Metro Torino Extension - Design and construction problemsMetro Torino Extension - Design and construction problems
Metro Torino Extension - Design and construction problems
 
Athens pecker 2005
Athens pecker 2005Athens pecker 2005
Athens pecker 2005
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
Dfi2005 pecker
Dfi2005 peckerDfi2005 pecker
Dfi2005 pecker
 
Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015
 
Design and dynamic testing of precast piles oscar varde
Design and dynamic testing of precast piles   oscar vardeDesign and dynamic testing of precast piles   oscar varde
Design and dynamic testing of precast piles oscar varde
 
03 azamat the experience of industrial processing of an uranium deposit of ak...
03 azamat the experience of industrial processing of an uranium deposit of ak...03 azamat the experience of industrial processing of an uranium deposit of ak...
03 azamat the experience of industrial processing of an uranium deposit of ak...
 
Geo trans2004 pecker
Geo trans2004 peckerGeo trans2004 pecker
Geo trans2004 pecker
 
Design of Auger highwall mining
Design of Auger highwall miningDesign of Auger highwall mining
Design of Auger highwall mining
 
Pecker aci2003
Pecker aci2003Pecker aci2003
Pecker aci2003
 
Implementation of a Finite Element Model to Generate Synthetic data for Open ...
Implementation of a Finite Element Model to Generate Synthetic data for Open ...Implementation of a Finite Element Model to Generate Synthetic data for Open ...
Implementation of a Finite Element Model to Generate Synthetic data for Open ...
 
ISEE Journal
ISEE JournalISEE Journal
ISEE Journal
 

Kürzlich hochgeladen

Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
MayuraD1
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 

Kürzlich hochgeladen (20)

DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech Civil
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptx
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 

Back analysis of high tunnel convergences in clayey marls

  • 1. www.systra.com BACK ANALYSIS OF HIGH TUNNEL CONVERGENCES IN CLAYEY MARLS SYSTRA, Paris, France: MISANO Edoardo, COUBRAY Jean-Louis, ESPINOZA CARMONA Fabiola; Paris, France: CHIRIOTTI Elena
  • 2. Figure 1. Tunnel location and typical tunnel cross section
  • 3. BACK ANALYSIS OF HIGH TUNNEL CONVERGENCES IN CLAYEY MARLS SYSTRA, Paris, France: MISANO Edoardo, COUBRAY Jean-Louis, ESPINOZA CARMONA Fabiola; Paris, France: CHIRIOTTI Elena INTRODUCTION Ganntas Tunnel is part of the modernization project of the railway between Alger and Oran, in Algeria. In order to double and rectify the existing line between El Affroun and Khémis Miliana, the alignment foresees the excavation of a 7km-long twin tunnel. The excavation works started in June 2011 with the contractor CCECC, under the supervision of SYSTRA. Excavation is driven in conventional method by hydraulic hammer simultaneously on 8 different faces since excavation was started also from a junction window towards the middle of the tunnel. The minimum longitudinal distance to be respected between two contiguous tunnel faces has been set to 30m. The tunnel cross-section is a 70m² oval shaped profile, temporary support consists of shotcrete, bolts and steel ribs. A 30 to 50cm thick cast in situ concrete final lining is provided as well. When the tunnel reached a fault zone in soft clayey marls, extreme squeezing occurred, works were stopped, and re- profiling operations were carried out along more than 100m tunnel length. To date, works proceed at slow rate since high convergences are still monitored and completion of works is not expected before December 2016. 2
  • 4. 4 samples; the main characteristics of the clayey marls are summarized hereafter: • Passing at 80μm is about 70% (determined on superficial detrital) • Plasticity index is around 20 (determined on superficial detrital) • CaCO3 content varies between 11% and 32% with a mean value of 18,8% • Undrained cohesion varies between 30kPa and 63kPa (4 direct shear tests) • Friction angle varies between 15° and 20° (4 direct shear tests) • Resistance to uniaxial compression varies between 0,9MPa and 7,6MPa (3 tests) It should be stresses that the totality of the tests and investigations carried out is far from being representative for a 7km tunnel and this has led to an overestimation of resistance parameters of soils. The geological mapping at tunnel face assessed RMR values as low as 14 when high convergences occurred, such value appears completely inconsistent with the set of geotechnical parameters used to design the tunnel supports. HYDROLOGY Clayey marls showed an impermeable overall behavior, water circulation is possible in fractures, bedding planes plans and at contact with the sandstone layer. Water inflows are mainly supplied by rainfalls. Experience derived from the excavated sections confirmed that inflows are scarce and dry conditions may be assumes at the tunnel outward. GEOLOGY The project is located within the Tellian Atlas mountain area, including in particular the Djebel Ganntas massif in between Mitidja and Chleff plains. Djebel Ganntas is characterized by an extensive massif aligned in East-West direction with smooth slopes made of soft clays that emerge in multiple cliffs and ravines. On the top of it, along the edge, a more recent sandstone formation is found. The existing data on the geology did not allow to establish an accurate geological model at tender stage. In-situ investigations allowed at design stage to identify a Quaternary alluvial cover of clays and gravel, followed by a Miocene stratum divided in a sandy top layer and a lower clayey layer. From a structural point of view, geological maps suggest a north direction dip of layers, but the in situ surveys showed that layers were highly folded. The lack of information at tender stage on the structure of the geological series should have triggered an extensive investigation campaign at detailed design stage which did not take place causing serious consequences on costs and time at construction stage. The geological longitudinal profile was updated four times between 1991 and 2011, the latest being the one shown in Figure 2. Except for a short section near the South portal, the whole tunnel is driven through the Miocene clayey marls. On the South side, a complicated structure of layers was identified, in particular a major fault zone was found at chainage pk 180+600 where clayey marls were extremely fractured. Nevertheless the geological risk in this zone was underestimated and no further investigations were established to evaluate the mechanical parameters. It is in this zone that the excavation encountered the major problems and where high deformations were registered on tunnel supporting lining. The geological model has been established on the basis of the information collected through eight boreholes along the alignment and a geophysical surface survey with the AMT method (Audio Mangetotelluric). Laboratory tests have been performed on extracted
  • 5. 5 foot before benching. High convergences caused works to stop in order to proceed to re-profiling operations. The contractor proposed the E1 excavation profile (see Figure 4), the main difference with the A1 profile consists in closing the rib foot with a provisional invert before benching and providing a face reinforcement by means of 34 fiberglass bolts of 25mm diameter and 12m length. A forepoling was added consisting in a line of 42mm diameter tubes at crown. After re-profiling, excavation restarted using the new support profile. The adopted solution showed poor results, convergences continued to raise and a cumulative value of HIGH CONVERGENCES OCCURRENCE On December 2013, around chainage pk 108+600, with about 100m overburden, excavation was proceeding with A1 excavation profile (see Figure 4), when high convergences of about 20cm started to be measured at about 15m behind the tunnel face. Excavation was driven by top heading with an advance rate of about 1m/day. The temporary support consisted of a 30cm shotcrete layer reinforced with HEB 180 spaced 0,6m, and 12 radial bolts of 25mm diameter and 4m length installed at each rib Figure 3. Clayey marls on the left, sandstones inclusions in clayey matrix on the right Figure 2. Geological Profile of the Ganntas tunnel and detail of the faulted zone
  • 6. 6 to reinforce these elements by installing 2+2 micro piles beneath each rib foot and increasing the bolts length to 6m in this zone. During re-profiling operations convergences did not increased, however, when the tunnel face advancement restarted, 7cm of additional convergence were registered again. 70cm convergence was reached when works needed to be stopped again to proceed to new re-profiling operations and third excavation profile (E1R, see Figure 4) was proposed. Since convergences were affecting mostly the rib foot and the heave of the provisional invert was remarked (see Figure 6), the Contractor decided Figure 4. Excavation profile used to cope with the fault zone
  • 7. 7 Figure 5. Convergence registration at chainage pk 180+600 INTERVENTIONS A1 PROFILE E1 PROFILE E1R PROFILE RADIAL BOLTS 6+6 Φ 25mm L=4m 6+6 Φ 25mm L=4m 8/9 Φ 25mm / L=4m 2+2 micro pile / L=6m 3+3 Φ25mm / L=6m FORE-POLING - 12 tubes Φ 42mm 12 tubes Φ 42mm STEEL RIBS HEB 180 @0,6m HEB 180 @1,0m HEB 180 @0,6m PROVISIONAL INVERT - HEB 180 @1,0m HEB 180 @0,6m SHOTCRETE 5+25cm 5+25cm 5+25cm SHOTCRETE AT FACE - 4cm 7cm FACE BOLTS - 34 Φ 25mm 34 Φ 25mm Table 1. Excavation profile interventions around chainage pk 108+600 Figure 6. Rib foot displacement and provisional invert up-heave
  • 8. 8 Figure 7. Characteristic curves, Lombardi-Amberg (1974) Table 3. Calculated rock mass parameters according to Hoek-Brown criteria RMR [-] GSI [-] UCS [MPa] mi [-] D [-] Ei [GPa] 14 9 30 7 0,5 5,2 Tunnel face stability High convergence phenomena are the presence of an extended plasticized zone ahead the tunnel face that only the back-calculated parameter could reproduce. The application of the stability number (see equation (1), Panet, 1982) shows that the stability of the tunnel face is very critical and that an important support at tunnel face is needed (see Table 4). A tunnel to be driven in difficult cohesive soils that show high convergences needs an important stiffening of the advance core ahead the tunnel face in order to limit the plasticization in this zone and to allow the installation of the temporary support before rock failure is produced around the cavity (Lunardi, 1999). In order to have a stability number lower than 6,7 (to assure face stability according to Panet 1982), the equation (2) must be satisfied, which means that a mitigation measure capable to increment the material cohesion ahead the tunnel face of about 165kPa is needed. Using the transformation on the Mohr-Coulomb plan (see equations (3) and (4)) and considering a 200kPa soil-grout shear resistance at bolt interface and standard fiber bolt dimensions, ANALYSIS OF THE ROCK MASS BEHAVIOUR In parallel to the Contractor’s analyses, the Engineer developed his own back analyses of the observed phenomena in order to better understand the problem and the rock mass behavior to cross-check the proposed excavation. The study is divided into two parts: in the former the rock mass is analyzed without any support in order to identify the right set of rock mass parameters which better describe the massif behavior; in the latter the calculated parameters are used to analyze the proposed excavation profile in order to check the adequateness and the coherence with monitoring data. Back-analysis of rock mass parameters The back-analysis is carried out by using the convergence-confinement method as proposed by Lombardi-Amberg (1974), identifying the set of parameters which allows to reproduce 70cm of observed convergence on the tunnel characteristic curve at tunnel face when the half- core resistance is reached. Available geological data collected during construction, such as the RMR index were used in order to best fit the solution. Results are shown in Table 2. Parameters were initially defined according to the Hoek Brown criteria, in order to use the RMR information, and then they are converted to Mohr-Coulomb strength parameters more suitable to perform F.E.M. analysis. It is to note that the difference between the original parameters and the calculated ones is quite relevant. The estimated stiffness is reduced to 50% and the resistance almost to 35%. Table 2. Rock mass parameters according to Mohr-Coulomb criteria Original Parameters Calculated parameters Young Module [MPa] 200 125 Cohesion [kPa] 200 75 Friction Angle [°] 20 17
  • 9. Where 9 the minimum density of needed elements is 1 bolt/m². Such density is the double of the one foreseen in E1 and E1R excavation profiles, which both failed in controlling convergences. 7 excavation profiles, which both failed in controlling convergences. cm P N  02  kPac P c P cm 240 cos7,6 )sin1( 7.6 2 00        3 cos2 sin1      c          S N ATLDT b bbTaF  ;min3 Where:  P0 = lithostatic stress  σcm = uniaxial compression resistance  S = excavation surface  Nb = number of bolts at tunnel face  Ab = bolt resistant section of bolt  b = bolt yielding stress  D = drilling hole diameter  L = bolt length  a = soil-grout shear resistance at interface Table 4. Stability numbers for the two different parameter sets Original parameters 7,5 Calculated parameters 21,2 7 e transformation on the Mohr-Coulomb plan (see equations (3) and (4)) and considering a grout shear resistance at bolt interface and standard fiber bolt dimensions, the minimum eeded elements is 1 bolt/ m². Such density is the double of the one foreseen in E1 and E1R rofiles, which both failed in controlling convergences. cm P N  02  (1) kPac P c P cm 240 cos7,6 )sin1( 7.6 2 00        (2) 3 cos2 sin1      c (3)          S N ATLDT b bbTaF  ;min3 (4) lithostatic stress = uniaxial compression resistance xcavation surface number of bolts at tunnel face bolt resistant section of bolt bolt yielding stress drilling hole diameter olt length soil-grout shear resistance at interface bility numbers for the two different parameter sets Original parameters 7,5 Calculated parameters 21,2 7 ation on the Mohr-Coulomb plan (see equations (3) and (4)) and considering a resistance at bolt interface and standard fiber bolt dimensions, the minimum nts is 1 bolt/ m². Such density is the double of the one foreseen in E1 and E1R h both failed in controlling convergences. cm P N  02  (1) kPac P c P cm 240 cos7,6 )sin1( 7.6 2 00        (2) 3 cos2 sin1      c (3)          S N ATLDT b bbTaF  ;min3 (4) ress mpression resistance rface bolts at tunnel face nt section of bolt stress diameter ear resistance at interface rs for the two different parameter sets parameters 7,5 d parameters 21,2 Phase number Description Distance from tunnel face Deconfinement ratio 1 Geostatic conditions - 0% P0 2 Half top section excavation 0 m 80% P0 3 Steel ribs and shotcrete installation 1 m 90% P0 4 1 day shotcrete curing 2 m 93% P0 5 3 day shotcrete curing 3 m 95% P0 6 9 day shotcrete curing 4 m 98% P0 7 28 day shotcrete curing 5 m 100% P0 8 Invert excavation 0 m* 80% P1** 9 Steel ribs and shotcrete installation on invert 1 m* 95% P1** 10 1 day shotcrete curing of invert lining 2 m* 96% P1** 11 28 day shotcrete curing of invert lining ∞ 100% P1** Cross-check of the proposed supporting sections Calculated rock mass parameters are then used to check the proposed supporting system and to verify the consistency of the results found in the previous analysis. The excavation profiles E1 and E1R are studied with the help of F.E.M. using the calculation program PHASE² (Rocscience). The rock mass is taken into account as an equivalent continuum, soil behavior is modeled as an elastic perfectly plastic material, and the resistance law follows the Mohr-Coulomb criteria. Staged construction is taken into account (see Table 5) in different calculation phases in order to consider the non-linear behavior of materials, deconfinement ratios are estimated on the results of an axisymmetric problem, as intersection of the convergence curve along the tunnel and the characteristic curve as evaluated previously. Forepoling has been taken into account in the model by stiffening a portion of soil at crown. The principal outcomes of the analysis are the following: • Results in term of displacement are consistent with monitoring data (see Figure 8), • The extension of the plastic zone points out that radial bolts are not an effective intervention to limit convergences since they are placed within the plasticized zone, • The stress analysis of first lining shows clearly that the foreseen intervention could not afford the pressures induced by the failing rock mass. Table 4. Stability numbers for the two different parameter sets Original parameters 7,5 Calculated parameters 21,2 7 e transformation on the Mohr-Coulomb plan (see equations (3) and (4)) and considering a grout shear resistance at bolt interface and standard fiber bolt dimensions, the minimum eeded elements is 1 bolt/ m². Such density is the double of the one foreseen in E1 and E1R rofiles, which both failed in controlling convergences. cm P N  02  (1) kPac P c P cm 240 cos7,6 )sin1( 7.6 2 00        (2) 3 cos2 sin1      c (3)          S N ATLDT b bbTaF  ;min3 (4) lithostatic stress = uniaxial compression resistance xcavation surface number of bolts at tunnel face bolt resistant section of bolt bolt yielding stress drilling hole diameter olt length soil-grout shear resistance at interface bility numbers for the two different parameter sets Original parameters 7,5 Calculated parameters 21,2 7 ation on the Mohr-Coulomb plan (see equations (3) and (4)) and considering a resistance at bolt interface and standard fiber bolt dimensions, the minimum nts is 1 bolt/ m². Such density is the double of the one foreseen in E1 and E1R h both failed in controlling convergences. cm P N  02  (1) kPac P c P cm 240 cos7,6 )sin1( 7.6 2 00        (2) 3 cos2 sin1      c (3)          S N ATLDT b bbTaF  ;min3 (4) ress mpression resistance rface bolts at tunnel face nt section of bolt stress diameter ear resistance at interface rs for the two different parameter sets parameters 7,5 d parameters 21,2 7 e transformation on the Mohr-Coulomb plan (see equations (3) and (4)) and considering a grout shear resistance at bolt interface and standard fiber bolt dimensions, the minimum eeded elements is 1 bolt/ m². Such density is the double of the one foreseen in E1 and E1R rofiles, which both failed in controlling convergences. cm P N  02  (1) kPac P c P cm 240 cos7,6 )sin1( 7.6 2 00        (2) 3 cos2 sin1      c (3)          S N ATLDT b bbTaF  ;min3 (4) lithostatic stress = uniaxial compression resistance xcavation surface number of bolts at tunnel face bolt resistant section of bolt bolt yielding stress drilling hole diameter olt length soil-grout shear resistance at interface bility numbers for the two different parameter sets Original parameters 7,5 Calculated parameters 21,2 7 ation on the Mohr-Coulomb plan (see equations (3) and (4)) and considering a resistance at bolt interface and standard fiber bolt dimensions, the minimum nts is 1 bolt/ m². Such density is the double of the one foreseen in E1 and E1R h both failed in controlling convergences. cm P N  02  (1) kPac P c P cm 240 cos7,6 )sin1( 7.6 2 00        (2) 3 cos2 sin1      c (3)          S N ATLDT b bbTaF  ;min3 (4) ress mpression resistance rface bolts at tunnel face nt section of bolt stress diameter ear resistance at interface rs for the two different parameter sets parameters 7,5 d parameters 21,2 7 e transformation on the Mohr-Coulomb plan (see equations (3) and (4)) and considering a grout shear resistance at bolt interface and standard fiber bolt dimensions, the minimum eeded elements is 1 bolt/ m². Such density is the double of the one foreseen in E1 and E1R rofiles, which both failed in controlling convergences. cm P N  02  (1) kPac P c P cm 240 cos7,6 )sin1( 7.6 2 00        (2) 3 cos2 sin1      c (3)          S N ATLDT b bbTaF  ;min3 (4) lithostatic stress = uniaxial compression resistance xcavation surface number of bolts at tunnel face bolt resistant section of bolt bolt yielding stress drilling hole diameter olt length soil-grout shear resistance at interface bility numbers for the two different parameter sets Original parameters 7,5 Calculated parameters 21,2 7 ation on the Mohr-Coulomb plan (see equations (3) and (4)) and considering a resistance at bolt interface and standard fiber bolt dimensions, the minimum nts is 1 bolt/ m². Such density is the double of the one foreseen in E1 and E1R h both failed in controlling convergences. cm P N  02  (1) kPac P c P cm 240 cos7,6 )sin1( 7.6 2 00        (2) 3 cos2 sin1      c (3)          S N ATLDT b bbTaF  ;min3 (4) ress mpression resistance rface bolts at tunnel face nt section of bolt stress diameter ear resistance at interface rs for the two different parameter sets parameters 7,5 d parameters 21,2 Table 5. Calculation phases | * distance is calculated from bench, ** P1 is the residual stress in bench
  • 10. 10 Figure 8. Calculated displacements (in meters) for E1 (on the left) and plastic zone extension around E1R (on the right) Figure 9. First lining verification of E1 excavation profile
  • 11. 11 Experience in tunneling showed that when face stability is not assured in plastic soils, the support system is not able to control the development of the plastic zone around the excavation and pre-confining measures, such as extended face nailing or grouting, are necessary in order to ensure a safe excavation and a cost effective work progress. The presented case history reminds finally of the importance of the following main aspects: • Performing a sufficient quantity of ground investigations before tender stage may highly reduce costs and time of the entire project. • Construction methods and engineering analyses should be integrated in a homogeneous design process in order to find the most suitable solution. • When the lack of geological and geotechnical information do not allow to define safe and reliable rock mass characteristics, it is important to analyze the rock-mass behavior during construction. In case of deviation from the foreseen behavior, such information will allow then to perform back-analysis to adapt the construction to the encountered conditions. During the excavation of the Ganntas Tunnel, in the Algerian Atlas mountain area, high convergences occurred slightly after temporary support installation, and re-profiling operation were carried out along more than 100m of tunnel. The failure occurred when the tunnel face reached a faulted zone in clayey marls with an overburden of about 100m. The geological investigations proved to be insufficient at design stage since the presence of such material along the tunnel alignment was unknown until the construction stage. This occurrence caused delays and costs increase since the appropriate solution was not found in short term. The Engineer performed a series of independent analyses to back- calculate the design parameters of the rock mass and to calibrate a model able to reproduce the monitoring data in terms of displacement of the supporting lining. The accordance between the analysis results and the in-situ observations proves that the original set of parameter was not able to properly describe the soil-structure interaction problem and therefore to design an effective supporting system. REFERENCES Hoek, E., Carranza-Torres, C. 2002. Hoek-Brown failure criterion – 2002 edition. Proc. NARMS-TAC Conference, Toronto ITA Working Group Research. Strategy for Site Investigation of Tunneling Projects. ITA Report n.15/May 2015 Lombardi, G., Amberg, W. A. 1974. Une méthode de calcul élasto-plastique de l’état de tension et de déformation autour d’une cavité souterraine. International Congres ISRM, Denver. Lunardi, P. 1999. The Tartaguille tunnel, or use of the ADECO-RS approach in the construction of an “impossible” tunnel. Gallerie e grandi opera sotterranee, No 58. Panet, M., Guenot A. 1982. Analysis of convergence behind the face of a tunnel. Tunnelling, Brighton. CONCLUSIONS
  • 12. © SYSTRA2016,© M.Kadri/CAPAPictures 72 rue Henry Farman CS 41594 75513 Paris Cedex 15 + 33 1 40 16 61 00