SlideShare ist ein Scribd-Unternehmen logo
1 von 12
Downloaden Sie, um offline zu lesen
Taofik Adekunle Boladale & G. A. Adepoju
International Journal of Engineering(IJE), Volume (10) : Issue (2) : 2016 12
Convergence Problems Of Contingency Analysis In Electrical
Power Transmission System
Taofik Adekunle Boladale taboladale@lautech.edu.ng
Works Department,
Ladoke Akintola University of Technology.
Ogbomoso, 210214, Nigeria.
Gafari Abiola Adepoju gaadepoju@lautech.edu.ng
Facuty of Engineering/ Electronic and Electrical Department
Ladoke Akintola University of Technology.
Ogbomoso, 210214, Nigeria
Abstract
Contingency analysis is a tool used by power system engineers for planning and assessing
power system reliability. The conventional analytical method which is mathematical model based,
is not only tedious and time consuming in view of the large number of components in the network
but always left some critical components unassessed due to non-convergence of the power flow
analysis of such, hence the contingency analysis of such system could not be said to be
completed.
In this work, contingency analysis of line components of a standard IEEE-30 Bus and real 330-kV
Nigerian Transmission Company of Nigeria (TCN) network (28Bus) systems were investigated
using Radial Basis Function Neural Network (RBF-NN) which is artificial intelligence based.
The contingency analysis was carried out by solving the non-linear algebraic equations of steady
state model for the standard IEEE-30 Bus and TCN-28 Bus power networks using Newton-
Raphson (N-R) power flow method. RBF-NN method was used for the computation of Reactive
and Active performance indices (PIR and PIA ) which were ranked in order to reveal the criticality
of each line outage. Simulation was carried out using MATLAB R2013a version. The non-
converged lines in both systems were reinforced and re-analysed. The results of contingency
analyses of the reinforced systems show more robust systems with complete line ranking.
Keywords: Contingency Analysis, Analytical method, RBF-NN method, Active and Reactive
Performance Indices, Ranking .
1. INTRODUCTION
The electrical power system network comprises of Generating stations, Circuit Breakers,
Transformers, Transmission lines and the likes, all of which have different operating limits. These
limits determine to a large extent the reliability of the network. The degree however is much
worse in third world countries where poor planning, inadequate financing and lack of good
maintenance culture are the order of the day.
The challenges of ensuring the security of Power system is therefore an enormous task that must
be contended with and the effect of weather (Storms, Earthquake, Tornadoes and so on ), human
factors (sabotage, terrorism, illegal Building constructions just to mention a few ) and bad Political
structures (corruption, nepotism and favouritisms ) especially in developing countries are not
helping the already worsen situations. The major focus of power system Engineers is how to
ensure that the outages are minimised in terms of frequencies of occurrence and durations of
power outages. Since the outages cannot be completely avoided, a contingency arrangement
Taofik Adekunle Boladale & G. A. Adepoju
International Journal of Engineering(IJE), Volume (10) : Issue (2) : 2016 13
must be put in place in order to minimise the effect of shutdown resulting from the power outage
(Onohaebi, 2009).
In order to have a reliable network, continuous monitoring of the system where parameters are
continuously checked and adjusted as may be required from time to time through the use of
telemetry system or by a Supervisory Control and Data Acquisition (SCADA) equipment is
therefore required. The continuous checks and balances required in order to have a stable and
reliable system is therefore termed the contingencies control strategies. This however, involves
knowing the operating limits of each integral component of the network prior to and after the
occurrence of the contingency.
Contingency analysis is therefore time consuming and cumbersome since the operating limit of
individual components must be known. The most common approach of Contingency analysis is to
carry-out the power (load) flow analysis and compute performance indices following each
possible outage. However, in view of the cumbersomeness of the power network and the rigorous
calculations and time involve; the use of conventional approach is found to be limited and
ineffective especially on online real life systems (Shahnawaaz and Vijayalaxi, 2014). Amit (2011)
and Naik (2014) have therefore recently researched into the utilisation of the proficiency of
artificial intelligence for contingency analysis of small standard IEEE systems. This research work
therefore considers implementation of the radial basis function neural network (RBF-NN) on
medium size power transmission systems and to establish its application on real life power
system, using 330kV Nigerian transmission system as a case study.
Contingency analysis is conventionally carried out using either contingency selection (ranking) or
screening methods. Contingency ranking is achieved using Performance Indices while screening
is better achieved using fast and approximate network solution (Ejebe et. al., 1998). Contingency
screening (or selection) is therefore an important task which help to minimise the rigorous and
tasking computation, due to the complexity of the network and helps to determine the most
severe contingency as well as the degree of severity.
Generally, the Contingency analysis applies the Kirchorff Current law (Nodal Analysis) to
calculate the current injection into various buses of the power system network (Kusic, 2009);
however the most accurate methods are based on AC Power (load) flow computation which are
solved by iteration techniques (Maghrabi et al, 1998). The AC Power (load) flow are Gauss
Seidel, Newton Raphson (N-R) and Fast decoupled load flow, Gauss Seidel ought to be the most
accurate but its use is limited to small systems due its slow rate of convergence. N-R method on
the other hand has the largest convergence rate but it requires large computer memory while
Fast Decoupled method is the least accurate of the three (Adejumobi et al., 2013). The speedy
convergence advantage of N-R method irrespective of the system size prompted its choice in this
work.
Artificial neural networks in simple feed-forward topology is used in the formulation of Radial
basis function network and for Contingency analysis it is usually combined with Unsupervised
learning. The merits of both according to Boudour and Hellal (2004); are high rate of
convergence even on complex mapping problems, simple structure, fast and efficient training
process and absence of local minimal problem. It also has the capability of accommodating
newer data without any need for retraining. These reasons prompted the choice of Radial basis
function neural network (RBF-NN) for this work and its representation in simplest form is shown in
Figure1.
Taofik Adekunle Boladale & G. A. Adepoju
International Journal of Engineering(IJE), Volume (10) : Issue (2) : 2016 14
Y1
X2
X2 Y2 Y2
X3 Y3
Yn
Xn
Input Layer Weighted connections
Hidden Layer
FIGURE 1: Radial basis function (Artificial) neural network (RBF-NN)
General Structure (Andrej et. al., 2011).
2. RESEARCH METHODOLOGY
The contingency analysis was carried out by solving the non-linear algebraic equations of steady
state model for the standard IEEE-30 Bus and TCN-28 Bus power networks using Newton-
Raphson (N-R) power flow method. RBF-NN method was used for the computation of Active and
Reactive performance indices (PIA and PIR ), with the data generated from Analytical method.
Simulation was carried out using MATLAB R2013a version. The non-converged lines in both
systems were noted for reinforcement using additional lines of the same parameters, the
contingency analyses of the reinforced systems were then carried out.
2.1 Analytical Method
The conventional analytical method of carrying out contingency analysis involve; simulation of
contingency (outage), performing power (load) flow and computing the performance indices
following each contingency. Contingency Analysis of the IEEE-30 Bus Standard system and 28
Bus of Transmission Company of Nigeria (TCN) system, using Newton-Raphson (N-R) load flow
analysis and Analytical method reported by Ejebe et al., (1998) which was used to determine the
system performance indices as expressed in equations 1, 2 and 3.
2.1.1 Active Power Performance Index
Active Power performance Index (PIA) is a function of power flow limit violation of line and it is
given by equation 1 as:
r
N
i i
i
A
P
P
r
W
PI
2
1 (max)2
L














 1
where
Pi = Active (MW) power flowing on line i prior to the line outage.
Pi (max) = the maximum active power (MW) capacity of line i and it is given by DC load flow
analysis as:
 
ij
ji
i
X
VV
P

max
2
Vi = voltage at Bus i after the completion of the N-R load flow analysis
Vj = voltage at Bus j after the completion of the N-R load flow analysis and
Ω
∑
∑
∑
∑
Ω
Ω
Ω
Taofik Adekunle Boladale & G. A. Adepoju
International Journal of Engineering(IJE), Volume (10) : Issue (2) : 2016 15
Xij = the reactance of the line connecting lines i and j.
NL = is the number of transmission lines in the system under consideration
W and r are real non negative weighting factor and exponential penalty factor respectively.
W = 1 and r = 2 are said to be adequate for 14Bus system (Javan et. al, 2011).
It should be noted that according to Javan et. al, (2011); the Active power performance (PIA) has
a small value when all the line flows are within their limits and has a high value when any
line(s) is (are) overloaded for a given state of the power system.
2.1.2 Reactive Power Performance Index
The Reactive Power performance Index (PIR) is a function of Bus voltage limit violations and it
is given by:
   r
ii
avii
N
i
R
VV
VV
r
W
PI
LB
2
(min)(max)1
2
2 









 
3
where
Vi = Voltage at bus i
Vi(max) and Vi(min) are the maximum and minimum voltage limits.
2
(min)(max)
)(
ii
avi
VV
V


NLB = No of load Buses in the system.
W = Weighting coefficient
r = Order of the exponent
It should be noted that the voltage range used is +10% and -10% according to Transmission
Company of Nigeria (TCN), Osogbo) as reported by Onojo et. al., (2013), hence at slack/ nominal
voltage of 1.0p.u, there will be a violation if either the Vi(max) or Vi(min) is above 1.05p.u or below
0.95p.u (1.10p.u or 0.9p.u in Transmission Company of Nigeria's case) respectively. Reactive
power performance index (PIR) is therefore an indication of the severity of the contingency
(outage) on a particular line and if it is greater than zero, the corresponding contingency is
recognised as critical or insecure otherwise it is said to be Secure.(Javan et. al., 2011).
A Matlab based code was deployed for the actualisation of this Analytical method using the flow
chart of Figure 2.
Taofik Adekunle Boladale & G. A. Adepoju
International Journal of Engineering(IJE), Volume (10) : Issue (2) : 2016 16
Carry out the reference load
flow
Are all lines
outages simulated
?
Supply
input(network
lines and buses
data)
Start
Simulate contingency
Calculate PIA using equation 1
and 2
Initial counter
Perform N-R load flow analysis
Calculate PIR at all load buses
using equation 3
Rank contingency as a function
of PIR and PIA
Print
Ranked PIR
and PIA
Stop
Figure 2: Flow Chart for Contingency
Analysis Using Analytical Method
Divide the input data to Training
and Testing
Is | RBFPIR – AMPIR | EMR and
Is |RBFPIA –AMPIA | EMA
Supply the RBF_NN inputs [x]
= [PG1 QG1...PGn, QGn, PL1,
QL1...PLn, QLn, V1...Vn]
Train RBF neural network
Compute last hidden units
output
Set values for SSE, Spread
Constant, EMR and EMA
Simulate the model Testing
Rank contingency as a function
of RBFPIR and RBFPIA
Print
Ranked
Result
Stop
Figure 3: Flow Chart for Contingency
Analysis Using RBF-NNl Method
Simulate the N-1 line contingency of the system
and compute the AMPIA and AMPIR
Is
MSE SSE
?
Start
Yes
No
No
Yes
Yes
No
Taofik Adekunle Boladale & G. A. Adepoju
International Journal of Engineering(IJE), Volume (10) : Issue (2) : 2016 17
2.2 RBF-NN Method
The contingency analysis using Analytical method in view of the large number of components in
the power system, is slow hence the use of Radial Basis Function Neural Network with the flow
chart in Figure 3 was used in this study. The procedure of RBF-NN method involves feeding the
result of load flow following each contingency into the developed RBF-NN algorithm to compute
and rank the performance indices.
Contingency Analysis of the IEEE-30 Bus Standard system and TCN-28 Bus of Nigerian system,
using Newton-Raphson (N-R) for load flow analysis and RBF-NN prediction method to determine
the performance indices were carried out. This was achieved using Matlab code based on the
flow chart in Figure 3 which was based on the general structure of RBF-NN in Figure 1 with the
determination of hidden neurons based on an algorithm called Growing and Pruning algorithm
reported by Javan et al, 2011. The statistical data used for each system is as shown in Table 1.
S/No Power
Systems
No. of
Lines
Error
Goal
Spread
Constant MSE SSE
Correlation
Coefficient
(R)
1 IEEE-30 Bus (Normal) 41 1.00E-03 15 1.001 1.0005 0.8914
2 IEEE-30 Bus (Improved) 44 1.00E-04 15 1.0331 1.0005 0.7496
3 TCN-28 Bus (Normal) 52 1.00E-03 20 0.006 0.0778 0.945
4 TCN-28 Bus (Improved) 53 1.00E-04 20 0.0081 0.0902 0.9727
TABLE 1: The statistical data of RBF-NN Method.
The Line diagram of TCN-28 system is as shown Figure 4 while that of standard IEEE-30 Bus
could be easily gotten online via www.ieee.org.
Taofik Adekunle Boladale & G. A. Adepoju
International Journal of Engineering(IJE), Volume (10) : Issue (2) : 2016 18
Okpai 27,
V27 = 1.050pu
Calabar 25,
V25 = 1.049pu
Alaoji 12,
V12 = 1.035pu
Afa G.S 11,
V11 = 1.050pu
Aladja 7,
V7 = 1.040pu
Delta G.S 2,
V2 = 1.050pu
Sapele G.S 24,
V24 = 1.050pu
Onitsha 14,
V14 = 1.050pu
New Haven 13,
V13 = 0.977pu
Papalanto G.T
28,
V28 = 1.050pu
Ikeja west 5,
V5 = 1.026pu
Egbin 1,
V1 = 1.026pu
Aja 3,
V3 = 1.045pu
Akangba 4
V4 = 1.019pu
Ayede 9,
V9 = 0.990pu
Osogbo 10,
V10 = 1.031pu
Benin 8,
V8 = 1.029pu
Ajaokuta 6,
V6 = 1.029pu
Abuja26,
V26 = 1.026pu
Jebba G.S 17,
V17 = 1.050pu
Jebba T.S 18,
V18 = 1.050pu
Shiroro G.S 23,
V23 = 1.050pu
B. Kebbi 15,
V15 = 1.065pu
Kanji G.S 21,
V21 = 1.050pu
Kaduna 20,
V20 = 1.040pu
Kano 22,
V22 = 1.010pu
Jos 19,
V19 = 1.051pu
Gombe 16,
V16 = 0.994pu
Figure 4: TCN – 28 Bus Nigerian System Pre-contingency Load Flow
(Source: TCN , 2013)
3. RESULTS AND DISCUSSION
The simulation of Contingency analysis of the two systems were carried using RBF-NN method
with normal data and improved system data and the result are presented as follows;
3.1 Standard and Improved IEEE-30 Bus Systems
Upon the implementation of the RBF-NN method for the Standard IEEE-30 Bus system, Lines 13,
16 and 34 were found not to have converged as shown in Figures 4a, these lines were ranked as
39th, 40th and 41st most critical lines respectively hence they were regarded as the least critical
lines while the three most critical lines are Lines 36, 37 and 38; based on the fact that they have
largest number of voltage violations ranging from 1.082 to 0.861pu. These results were found to
be in agreement with the reports of Mario and Carlos, 2003 and Sarika et. al., 2013. The non-
convergence of the above lines was however an indication of their criticality to the functionality of
Taofik Adekunle Boladale & G. A. Adepoju
International Journal of Engineering(IJE), Volume (10) : Issue (2) : 2016 19
the system hence outage of any of those three lines could lead to instability and eventually the
shutdown of the system. They were therefore reinforced with lines of the same parameters.
The simulation of this improved System gives the result ranked in Figures 4b., where the most
critical line is 39 (the initial line 36) and the least critical line 15 (former line14).
FIGURE 4a: Contingency Analysis Ranking of Standard IEEE-30 Bus System using Reactive performance
indices.
FIGURE 4b: Contingency Analysis Ranking of Improved IEEE-30 Bus System using Reactive performance
indices.
3.1 Standard and Improved TCN-28 Bus Systems
Also the implimentation of the method on the real Nigerian transmission TCN-28 Bus System
gives the resulting Reactive and Active performance indices shown in Figure 5a(I and II)
respectiely; which indicated that line 31 did not converge, hence was considered to be the least
Taofik Adekunle Boladale & G. A. Adepoju
International Journal of Engineering(IJE), Volume (10) : Issue (2) : 2016 20
critical line. Upon reinforcement, line 31 and the incorporated line 32 were still ranked to be the
least critical lines as far as voltage violation is concerned but this was found not to be so based
on power violation, since the most critical line was line 20 as against the initial line 31 in the
standard TCN-28 Bus system. The change in the most critical line from 31(in normal system) as
against to line 20 (in improved system) is an indication of imperfect ranking going by the
contingency analysis of the normal system. This is shown in Figure 5b (I and II). Also, the least
critical line after the reinforcement were lines 29 and 30.
FIGURE 5a(I): Contingency Analysis Ranking of Standard TCN-28 Bus System using Reactive
performance indices.
FIGURE 5a(II): Contingency Analysis Ranking of Standard TCN-28 Bus System using Active performance
indices.
Taofik Adekunle Boladale & G. A. Adepoju
International Journal of Engineering(IJE), Volume (10) : Issue (2) : 2016 21
FIGURE 5b(I): Contingency Analysis Ranking of Standard TCN-28 Bus System using Reactive
performance indices.
FIGURE 5b(II): Contingency Analysis Ranking of Standard TCN-28 Bus System using Active performance
indices.
4. CONCLUSION AND RECOMMENDATION
4.1 Conclusion
This research investigated the proficiency of artificial intelligent; radial basis function neural
network for revealing the effect of non-convergent power flow on the contingency analysis of
electrical power systems by predicting the Active and Reactive performance indices and ranking
both in ascending order to show the severity of the transmission lines outages based on power
and voltage violations respectively. The contingency analysis of lines with non-convergent power
flow which were ranked least were reinforced and their criticality as far as the stability of the
system either as a result of voltage or power flow violations is concerned were revealed.
Taofik Adekunle Boladale & G. A. Adepoju
International Journal of Engineering(IJE), Volume (10) : Issue (2) : 2016 22
Following the above findings it could be concluded that, non-covergency of some of the lines of
any power system will definitely affect the contingency analysis of such system as any outage of
the non convergent line(s) could lead to the instability and shutdown of such system since either
the voltage or power of the particular neighbouring components could be easily driven beyond the
operating limits.
Consequently in order to appropriately analysed any system with such non-convergent line(s),
reinforcing such will give the true picture of system.
Lastly, incorporation of parallel line(s) in real power systems such as TCN-28 Bus system will
improve the stability property of the system aside providing additional capability of power
transmission.
4.2 Recommendation
This research work concentrate on N-1Line contingency, multiple components contingency with
RBF-NN especially on large real systems should be considered in future work.
5. REFERENCES
[1] O. S. Onohaebi, ''Power Outages in the Nigeria transmission Grid''. Medwell Journal of
Applied Science, Vol.4, Issue1, pp.1-9, 2009.
[2] S. Shahnawaaz and L. Vijayalaxmi ''Contingency Ranking and Analysis Using Mipo
International Journal of Engineering Trends and Technology (IJETT) - India; - Vol.10,
No 8, ISSN:2231-5381, pp 417-422, 2014.
[3] K. R. Amit, ''Contingency Analysis in Power System'', M.Eng. diss., Thapar University,
Patiala, 2011.
[4] P. Naik, ''Power System Contingency Ranking using Newton Raphson Load flow
method and its prediction using Soft Computing Techniques'', M.Tech. diss., National
Institute of Technology, Rourkela -769008, 2013.
[5] G. C. Ejebe and B. F. Wollenberg, “Automatic Contingency Selection”, IEEE Transactions
on Power Apparatus and Systems, Vol. PAS-98, No. 1, January 1979, pp. 97-109, 1979.
[6] G. Kusic, ''Computer-Aided Power System Analysis'', Second Edition, Taylor & Francis
Group. LLC., 2009.
[7] H. Maghrabi, J. A. Refaee, and M. Mohandes, ''Contingency Analysis of Bulk Power System
using Neural Networks''. Proceedings of International Conference on Power System
Technology, Beijing China. POWERCON. Vol. 2:pp. 1251-1254, 1998.
[8] I. A. Adejumobi, G. A. Adepoju and K. A. Hamzat, '' Iterative Techniques for Load Flow
Study: A Comparative Study for Nigeria 330KV Grid System as a Case Study'', International
Journal of Engineering and advance Technology, ISSN:2249-8958, Vol.3, Issue-1, pp. 153-
158, 2013.
[9] M. Boudour and A. Hellal, “Combined use of unsupervised and supervised learning for
Large Scale power system Static Security Mapping”, IEEE conference on Power Systems,
pp.1321-1327, 2004.
[10] K. Andrej, B. Janez and K. Andrej, ''Introduction to the Artificial Neural Networks, Artificial
Neural Networks-Methodological and Biomedical Applications, Prof. Kenji Suzuki (Ed.),
ISBN; 978-953-307-243-2, In-Tech., pp 1-17, 2011.
Taofik Adekunle Boladale & G. A. Adepoju
International Journal of Engineering(IJE), Volume (10) : Issue (2) : 2016 23
[11] D. C. Javan, R. H. Mashhadi and M. Rouhani, '' Fast Voltage and Power Flow
Contingencies Ranking using Enhanced Radial Basis Function Neural Network'', IJEEE,
vol.7, No.4, pp 273-282, 2011.
[12] A. A. Mario, and A. C. Carlos, ''A Contingency Ranking Method for Voltage Stability in
Real Time Operation of power Systems''. IEEE Bologna Power Tech Conference, Bologna,
Italy, 0-7803-7967-5/03/, 2003.
[13] V. Sarika, S. Laxmi, P. Manjaree and S. Manisha, ''Voltage Stability Based Contingency
Ranking using Distributed Computing Environment'' International Conference on Power,
Energy and Control'' Gwaior, M.P. India, pp 208-212, 2013.
[14] O. J. Onojo, G. C. Ononiwu, and S. O. Okozi, ''Analysis of Power Flow of Nigerian 330kv
grid System(pre and post) using Matlab''. European Journal of Natural Sciences,
Vol.1(2), pp 59-66, 2013.

Weitere ähnliche Inhalte

Was ist angesagt?

International Journal of Engineering (IJE) Volume (3) Issue (1)
International Journal of Engineering (IJE) Volume (3)  Issue (1)International Journal of Engineering (IJE) Volume (3)  Issue (1)
International Journal of Engineering (IJE) Volume (3) Issue (1)
CSCJournals
 
INTELLIGENT ELECTRICAL MULTI OUTLETS CONTROLLED AND ACTIVATED BY A DATA MININ...
INTELLIGENT ELECTRICAL MULTI OUTLETS CONTROLLED AND ACTIVATED BY A DATA MININ...INTELLIGENT ELECTRICAL MULTI OUTLETS CONTROLLED AND ACTIVATED BY A DATA MININ...
INTELLIGENT ELECTRICAL MULTI OUTLETS CONTROLLED AND ACTIVATED BY A DATA MININ...
ijscai
 
Modern Tools for the Small-Signal Stability Analysis and Design of FACTS Assi...
Modern Tools for the Small-Signal Stability Analysis and Design of FACTS Assi...Modern Tools for the Small-Signal Stability Analysis and Design of FACTS Assi...
Modern Tools for the Small-Signal Stability Analysis and Design of FACTS Assi...
Power System Operation
 
Efficient decentralized iterative learning tracker for unknown sampled data i...
Efficient decentralized iterative learning tracker for unknown sampled data i...Efficient decentralized iterative learning tracker for unknown sampled data i...
Efficient decentralized iterative learning tracker for unknown sampled data i...
ISA Interchange
 
TCSC Placement Problem Solving Using Hybridization of ABC and DE Algorithm
TCSC Placement Problem Solving Using Hybridization of ABC and DE AlgorithmTCSC Placement Problem Solving Using Hybridization of ABC and DE Algorithm
TCSC Placement Problem Solving Using Hybridization of ABC and DE Algorithm
paperpublications3
 
Fault diagnosis of a high voltage transmission line using waveform matching a...
Fault diagnosis of a high voltage transmission line using waveform matching a...Fault diagnosis of a high voltage transmission line using waveform matching a...
Fault diagnosis of a high voltage transmission line using waveform matching a...
ijsc
 

Was ist angesagt? (16)

International Journal of Engineering (IJE) Volume (3) Issue (1)
International Journal of Engineering (IJE) Volume (3)  Issue (1)International Journal of Engineering (IJE) Volume (3)  Issue (1)
International Journal of Engineering (IJE) Volume (3) Issue (1)
 
Cluster Computing Environment for On - line Static Security Assessment of lar...
Cluster Computing Environment for On - line Static Security Assessment of lar...Cluster Computing Environment for On - line Static Security Assessment of lar...
Cluster Computing Environment for On - line Static Security Assessment of lar...
 
On-line Power System Static Security Assessment in a Distributed Computing Fr...
On-line Power System Static Security Assessment in a Distributed Computing Fr...On-line Power System Static Security Assessment in a Distributed Computing Fr...
On-line Power System Static Security Assessment in a Distributed Computing Fr...
 
Reliability Prediction of Port Harcourt Electricity Distribution Network Usin...
Reliability Prediction of Port Harcourt Electricity Distribution Network Usin...Reliability Prediction of Port Harcourt Electricity Distribution Network Usin...
Reliability Prediction of Port Harcourt Electricity Distribution Network Usin...
 
Power System Problems in Teaching Control Theory on Simulink
Power System Problems in Teaching Control Theory on SimulinkPower System Problems in Teaching Control Theory on Simulink
Power System Problems in Teaching Control Theory on Simulink
 
Probabilistic Performance Index based Contingency Screening for Composite Pow...
Probabilistic Performance Index based Contingency Screening for Composite Pow...Probabilistic Performance Index based Contingency Screening for Composite Pow...
Probabilistic Performance Index based Contingency Screening for Composite Pow...
 
INTELLIGENT ELECTRICAL MULTI OUTLETS CONTROLLED AND ACTIVATED BY A DATA MININ...
INTELLIGENT ELECTRICAL MULTI OUTLETS CONTROLLED AND ACTIVATED BY A DATA MININ...INTELLIGENT ELECTRICAL MULTI OUTLETS CONTROLLED AND ACTIVATED BY A DATA MININ...
INTELLIGENT ELECTRICAL MULTI OUTLETS CONTROLLED AND ACTIVATED BY A DATA MININ...
 
Comparative Study on the Performance of A Coherency-based Simple Dynamic Equi...
Comparative Study on the Performance of A Coherency-based Simple Dynamic Equi...Comparative Study on the Performance of A Coherency-based Simple Dynamic Equi...
Comparative Study on the Performance of A Coherency-based Simple Dynamic Equi...
 
Modern Tools for the Small-Signal Stability Analysis and Design of FACTS Assi...
Modern Tools for the Small-Signal Stability Analysis and Design of FACTS Assi...Modern Tools for the Small-Signal Stability Analysis and Design of FACTS Assi...
Modern Tools for the Small-Signal Stability Analysis and Design of FACTS Assi...
 
IRJET- A Review on SVM based Induction Motor
IRJET- A Review on SVM based Induction MotorIRJET- A Review on SVM based Induction Motor
IRJET- A Review on SVM based Induction Motor
 
Efficient decentralized iterative learning tracker for unknown sampled data i...
Efficient decentralized iterative learning tracker for unknown sampled data i...Efficient decentralized iterative learning tracker for unknown sampled data i...
Efficient decentralized iterative learning tracker for unknown sampled data i...
 
TCSC Placement Problem Solving Using Hybridization of ABC and DE Algorithm
TCSC Placement Problem Solving Using Hybridization of ABC and DE AlgorithmTCSC Placement Problem Solving Using Hybridization of ABC and DE Algorithm
TCSC Placement Problem Solving Using Hybridization of ABC and DE Algorithm
 
Fault diagnosis of a high voltage transmission line using waveform matching a...
Fault diagnosis of a high voltage transmission line using waveform matching a...Fault diagnosis of a high voltage transmission line using waveform matching a...
Fault diagnosis of a high voltage transmission line using waveform matching a...
 
Artificial Neural Network Based Load Forecasting
Artificial Neural Network Based Load ForecastingArtificial Neural Network Based Load Forecasting
Artificial Neural Network Based Load Forecasting
 
DYNAMIC VOLTAGE SCALING FOR POWER CONSUMPTION REDUCTION IN REAL-TIME MIXED TA...
DYNAMIC VOLTAGE SCALING FOR POWER CONSUMPTION REDUCTION IN REAL-TIME MIXED TA...DYNAMIC VOLTAGE SCALING FOR POWER CONSUMPTION REDUCTION IN REAL-TIME MIXED TA...
DYNAMIC VOLTAGE SCALING FOR POWER CONSUMPTION REDUCTION IN REAL-TIME MIXED TA...
 
[IJET V2I5P13] Authors: Pawan Kumar Kaushal, Mrs. Minal Tomar
[IJET V2I5P13] Authors: Pawan Kumar Kaushal, Mrs. Minal Tomar[IJET V2I5P13] Authors: Pawan Kumar Kaushal, Mrs. Minal Tomar
[IJET V2I5P13] Authors: Pawan Kumar Kaushal, Mrs. Minal Tomar
 

Ähnlich wie Convergence Problems Of Contingency Analysis In Electrical Power Transmission System

Predicting Post Outage Transmission Line Flows using Linear Distribution Factors
Predicting Post Outage Transmission Line Flows using Linear Distribution FactorsPredicting Post Outage Transmission Line Flows using Linear Distribution Factors
Predicting Post Outage Transmission Line Flows using Linear Distribution Factors
Dr. Amarjeet Singh
 

Ähnlich wie Convergence Problems Of Contingency Analysis In Electrical Power Transmission System (20)

Power Flow Analysis of Island Business District 33KV Distribution Grid System...
Power Flow Analysis of Island Business District 33KV Distribution Grid System...Power Flow Analysis of Island Business District 33KV Distribution Grid System...
Power Flow Analysis of Island Business District 33KV Distribution Grid System...
 
Q01052136142
Q01052136142Q01052136142
Q01052136142
 
LATEST TRENDS IN CONTINGENCY ANALYSIS OF POWER SYSTEM
LATEST TRENDS IN CONTINGENCY ANALYSIS OF POWER SYSTEMLATEST TRENDS IN CONTINGENCY ANALYSIS OF POWER SYSTEM
LATEST TRENDS IN CONTINGENCY ANALYSIS OF POWER SYSTEM
 
Predicting Post Outage Transmission Line Flows using Linear Distribution Factors
Predicting Post Outage Transmission Line Flows using Linear Distribution FactorsPredicting Post Outage Transmission Line Flows using Linear Distribution Factors
Predicting Post Outage Transmission Line Flows using Linear Distribution Factors
 
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...
IRJET- Voltage Stability, Loadability and Contingency Analysis with Optimal I...
 
Power System Contingency Ranking Using Fast Decoupled Load Flow Method
Power System Contingency Ranking Using Fast Decoupled Load Flow MethodPower System Contingency Ranking Using Fast Decoupled Load Flow Method
Power System Contingency Ranking Using Fast Decoupled Load Flow Method
 
IRJET- A Simple Approach to Identify Power System Transmission Line Faults us...
IRJET- A Simple Approach to Identify Power System Transmission Line Faults us...IRJET- A Simple Approach to Identify Power System Transmission Line Faults us...
IRJET- A Simple Approach to Identify Power System Transmission Line Faults us...
 
IRJET- Feed-Forward Neural Network Based Transient Stability Assessment o...
IRJET-  	  Feed-Forward Neural Network Based Transient Stability Assessment o...IRJET-  	  Feed-Forward Neural Network Based Transient Stability Assessment o...
IRJET- Feed-Forward Neural Network Based Transient Stability Assessment o...
 
Influencing Factors on Power Losses in Electric Distribution Network
Influencing Factors on Power Losses in Electric Distribution NetworkInfluencing Factors on Power Losses in Electric Distribution Network
Influencing Factors on Power Losses in Electric Distribution Network
 
Filter Implementation Using Output Transformer of UPS for Power Quality Impro...
Filter Implementation Using Output Transformer of UPS for Power Quality Impro...Filter Implementation Using Output Transformer of UPS for Power Quality Impro...
Filter Implementation Using Output Transformer of UPS for Power Quality Impro...
 
Impact of Electric Vehicle Integration on Grid
Impact of Electric Vehicle Integration on GridImpact of Electric Vehicle Integration on Grid
Impact of Electric Vehicle Integration on Grid
 
40520130101002
4052013010100240520130101002
40520130101002
 
IRJET - Fault Detection and Classification in Transmission Line by using KNN ...
IRJET - Fault Detection and Classification in Transmission Line by using KNN ...IRJET - Fault Detection and Classification in Transmission Line by using KNN ...
IRJET - Fault Detection and Classification in Transmission Line by using KNN ...
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
International Journal of Computational Engineering Research(IJCER)
 International Journal of Computational Engineering Research(IJCER)  International Journal of Computational Engineering Research(IJCER)
International Journal of Computational Engineering Research(IJCER)
 
Short Term Load Forecasting: One Week (With & Without Weekend) Using Artifici...
Short Term Load Forecasting: One Week (With & Without Weekend) Using Artifici...Short Term Load Forecasting: One Week (With & Without Weekend) Using Artifici...
Short Term Load Forecasting: One Week (With & Without Weekend) Using Artifici...
 
Work Portfolio
Work PortfolioWork Portfolio
Work Portfolio
 
A hybrid approach of artificial neural network-particle swarm optimization a...
A hybrid approach of artificial neural network-particle swarm  optimization a...A hybrid approach of artificial neural network-particle swarm  optimization a...
A hybrid approach of artificial neural network-particle swarm optimization a...
 
ENHANCEMENT OF POWER SYSTEM SECURITY USING PSO-NR OPTIMIZATION TECHNIQUE
ENHANCEMENT OF POWER SYSTEM SECURITY USING PSO-NR OPTIMIZATION TECHNIQUEENHANCEMENT OF POWER SYSTEM SECURITY USING PSO-NR OPTIMIZATION TECHNIQUE
ENHANCEMENT OF POWER SYSTEM SECURITY USING PSO-NR OPTIMIZATION TECHNIQUE
 
A Novel Study on Bipolar High Voltage Direct Current Transmission Lines Prote...
A Novel Study on Bipolar High Voltage Direct Current Transmission Lines Prote...A Novel Study on Bipolar High Voltage Direct Current Transmission Lines Prote...
A Novel Study on Bipolar High Voltage Direct Current Transmission Lines Prote...
 

Kürzlich hochgeladen

The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
heathfieldcps1
 
Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
AnaAcapella
 

Kürzlich hochgeladen (20)

Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptx
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 

Convergence Problems Of Contingency Analysis In Electrical Power Transmission System

  • 1. Taofik Adekunle Boladale & G. A. Adepoju International Journal of Engineering(IJE), Volume (10) : Issue (2) : 2016 12 Convergence Problems Of Contingency Analysis In Electrical Power Transmission System Taofik Adekunle Boladale taboladale@lautech.edu.ng Works Department, Ladoke Akintola University of Technology. Ogbomoso, 210214, Nigeria. Gafari Abiola Adepoju gaadepoju@lautech.edu.ng Facuty of Engineering/ Electronic and Electrical Department Ladoke Akintola University of Technology. Ogbomoso, 210214, Nigeria Abstract Contingency analysis is a tool used by power system engineers for planning and assessing power system reliability. The conventional analytical method which is mathematical model based, is not only tedious and time consuming in view of the large number of components in the network but always left some critical components unassessed due to non-convergence of the power flow analysis of such, hence the contingency analysis of such system could not be said to be completed. In this work, contingency analysis of line components of a standard IEEE-30 Bus and real 330-kV Nigerian Transmission Company of Nigeria (TCN) network (28Bus) systems were investigated using Radial Basis Function Neural Network (RBF-NN) which is artificial intelligence based. The contingency analysis was carried out by solving the non-linear algebraic equations of steady state model for the standard IEEE-30 Bus and TCN-28 Bus power networks using Newton- Raphson (N-R) power flow method. RBF-NN method was used for the computation of Reactive and Active performance indices (PIR and PIA ) which were ranked in order to reveal the criticality of each line outage. Simulation was carried out using MATLAB R2013a version. The non- converged lines in both systems were reinforced and re-analysed. The results of contingency analyses of the reinforced systems show more robust systems with complete line ranking. Keywords: Contingency Analysis, Analytical method, RBF-NN method, Active and Reactive Performance Indices, Ranking . 1. INTRODUCTION The electrical power system network comprises of Generating stations, Circuit Breakers, Transformers, Transmission lines and the likes, all of which have different operating limits. These limits determine to a large extent the reliability of the network. The degree however is much worse in third world countries where poor planning, inadequate financing and lack of good maintenance culture are the order of the day. The challenges of ensuring the security of Power system is therefore an enormous task that must be contended with and the effect of weather (Storms, Earthquake, Tornadoes and so on ), human factors (sabotage, terrorism, illegal Building constructions just to mention a few ) and bad Political structures (corruption, nepotism and favouritisms ) especially in developing countries are not helping the already worsen situations. The major focus of power system Engineers is how to ensure that the outages are minimised in terms of frequencies of occurrence and durations of power outages. Since the outages cannot be completely avoided, a contingency arrangement
  • 2. Taofik Adekunle Boladale & G. A. Adepoju International Journal of Engineering(IJE), Volume (10) : Issue (2) : 2016 13 must be put in place in order to minimise the effect of shutdown resulting from the power outage (Onohaebi, 2009). In order to have a reliable network, continuous monitoring of the system where parameters are continuously checked and adjusted as may be required from time to time through the use of telemetry system or by a Supervisory Control and Data Acquisition (SCADA) equipment is therefore required. The continuous checks and balances required in order to have a stable and reliable system is therefore termed the contingencies control strategies. This however, involves knowing the operating limits of each integral component of the network prior to and after the occurrence of the contingency. Contingency analysis is therefore time consuming and cumbersome since the operating limit of individual components must be known. The most common approach of Contingency analysis is to carry-out the power (load) flow analysis and compute performance indices following each possible outage. However, in view of the cumbersomeness of the power network and the rigorous calculations and time involve; the use of conventional approach is found to be limited and ineffective especially on online real life systems (Shahnawaaz and Vijayalaxi, 2014). Amit (2011) and Naik (2014) have therefore recently researched into the utilisation of the proficiency of artificial intelligence for contingency analysis of small standard IEEE systems. This research work therefore considers implementation of the radial basis function neural network (RBF-NN) on medium size power transmission systems and to establish its application on real life power system, using 330kV Nigerian transmission system as a case study. Contingency analysis is conventionally carried out using either contingency selection (ranking) or screening methods. Contingency ranking is achieved using Performance Indices while screening is better achieved using fast and approximate network solution (Ejebe et. al., 1998). Contingency screening (or selection) is therefore an important task which help to minimise the rigorous and tasking computation, due to the complexity of the network and helps to determine the most severe contingency as well as the degree of severity. Generally, the Contingency analysis applies the Kirchorff Current law (Nodal Analysis) to calculate the current injection into various buses of the power system network (Kusic, 2009); however the most accurate methods are based on AC Power (load) flow computation which are solved by iteration techniques (Maghrabi et al, 1998). The AC Power (load) flow are Gauss Seidel, Newton Raphson (N-R) and Fast decoupled load flow, Gauss Seidel ought to be the most accurate but its use is limited to small systems due its slow rate of convergence. N-R method on the other hand has the largest convergence rate but it requires large computer memory while Fast Decoupled method is the least accurate of the three (Adejumobi et al., 2013). The speedy convergence advantage of N-R method irrespective of the system size prompted its choice in this work. Artificial neural networks in simple feed-forward topology is used in the formulation of Radial basis function network and for Contingency analysis it is usually combined with Unsupervised learning. The merits of both according to Boudour and Hellal (2004); are high rate of convergence even on complex mapping problems, simple structure, fast and efficient training process and absence of local minimal problem. It also has the capability of accommodating newer data without any need for retraining. These reasons prompted the choice of Radial basis function neural network (RBF-NN) for this work and its representation in simplest form is shown in Figure1.
  • 3. Taofik Adekunle Boladale & G. A. Adepoju International Journal of Engineering(IJE), Volume (10) : Issue (2) : 2016 14 Y1 X2 X2 Y2 Y2 X3 Y3 Yn Xn Input Layer Weighted connections Hidden Layer FIGURE 1: Radial basis function (Artificial) neural network (RBF-NN) General Structure (Andrej et. al., 2011). 2. RESEARCH METHODOLOGY The contingency analysis was carried out by solving the non-linear algebraic equations of steady state model for the standard IEEE-30 Bus and TCN-28 Bus power networks using Newton- Raphson (N-R) power flow method. RBF-NN method was used for the computation of Active and Reactive performance indices (PIA and PIR ), with the data generated from Analytical method. Simulation was carried out using MATLAB R2013a version. The non-converged lines in both systems were noted for reinforcement using additional lines of the same parameters, the contingency analyses of the reinforced systems were then carried out. 2.1 Analytical Method The conventional analytical method of carrying out contingency analysis involve; simulation of contingency (outage), performing power (load) flow and computing the performance indices following each contingency. Contingency Analysis of the IEEE-30 Bus Standard system and 28 Bus of Transmission Company of Nigeria (TCN) system, using Newton-Raphson (N-R) load flow analysis and Analytical method reported by Ejebe et al., (1998) which was used to determine the system performance indices as expressed in equations 1, 2 and 3. 2.1.1 Active Power Performance Index Active Power performance Index (PIA) is a function of power flow limit violation of line and it is given by equation 1 as: r N i i i A P P r W PI 2 1 (max)2 L                1 where Pi = Active (MW) power flowing on line i prior to the line outage. Pi (max) = the maximum active power (MW) capacity of line i and it is given by DC load flow analysis as:   ij ji i X VV P  max 2 Vi = voltage at Bus i after the completion of the N-R load flow analysis Vj = voltage at Bus j after the completion of the N-R load flow analysis and Ω ∑ ∑ ∑ ∑ Ω Ω Ω
  • 4. Taofik Adekunle Boladale & G. A. Adepoju International Journal of Engineering(IJE), Volume (10) : Issue (2) : 2016 15 Xij = the reactance of the line connecting lines i and j. NL = is the number of transmission lines in the system under consideration W and r are real non negative weighting factor and exponential penalty factor respectively. W = 1 and r = 2 are said to be adequate for 14Bus system (Javan et. al, 2011). It should be noted that according to Javan et. al, (2011); the Active power performance (PIA) has a small value when all the line flows are within their limits and has a high value when any line(s) is (are) overloaded for a given state of the power system. 2.1.2 Reactive Power Performance Index The Reactive Power performance Index (PIR) is a function of Bus voltage limit violations and it is given by:    r ii avii N i R VV VV r W PI LB 2 (min)(max)1 2 2             3 where Vi = Voltage at bus i Vi(max) and Vi(min) are the maximum and minimum voltage limits. 2 (min)(max) )( ii avi VV V   NLB = No of load Buses in the system. W = Weighting coefficient r = Order of the exponent It should be noted that the voltage range used is +10% and -10% according to Transmission Company of Nigeria (TCN), Osogbo) as reported by Onojo et. al., (2013), hence at slack/ nominal voltage of 1.0p.u, there will be a violation if either the Vi(max) or Vi(min) is above 1.05p.u or below 0.95p.u (1.10p.u or 0.9p.u in Transmission Company of Nigeria's case) respectively. Reactive power performance index (PIR) is therefore an indication of the severity of the contingency (outage) on a particular line and if it is greater than zero, the corresponding contingency is recognised as critical or insecure otherwise it is said to be Secure.(Javan et. al., 2011). A Matlab based code was deployed for the actualisation of this Analytical method using the flow chart of Figure 2.
  • 5. Taofik Adekunle Boladale & G. A. Adepoju International Journal of Engineering(IJE), Volume (10) : Issue (2) : 2016 16 Carry out the reference load flow Are all lines outages simulated ? Supply input(network lines and buses data) Start Simulate contingency Calculate PIA using equation 1 and 2 Initial counter Perform N-R load flow analysis Calculate PIR at all load buses using equation 3 Rank contingency as a function of PIR and PIA Print Ranked PIR and PIA Stop Figure 2: Flow Chart for Contingency Analysis Using Analytical Method Divide the input data to Training and Testing Is | RBFPIR – AMPIR | EMR and Is |RBFPIA –AMPIA | EMA Supply the RBF_NN inputs [x] = [PG1 QG1...PGn, QGn, PL1, QL1...PLn, QLn, V1...Vn] Train RBF neural network Compute last hidden units output Set values for SSE, Spread Constant, EMR and EMA Simulate the model Testing Rank contingency as a function of RBFPIR and RBFPIA Print Ranked Result Stop Figure 3: Flow Chart for Contingency Analysis Using RBF-NNl Method Simulate the N-1 line contingency of the system and compute the AMPIA and AMPIR Is MSE SSE ? Start Yes No No Yes Yes No
  • 6. Taofik Adekunle Boladale & G. A. Adepoju International Journal of Engineering(IJE), Volume (10) : Issue (2) : 2016 17 2.2 RBF-NN Method The contingency analysis using Analytical method in view of the large number of components in the power system, is slow hence the use of Radial Basis Function Neural Network with the flow chart in Figure 3 was used in this study. The procedure of RBF-NN method involves feeding the result of load flow following each contingency into the developed RBF-NN algorithm to compute and rank the performance indices. Contingency Analysis of the IEEE-30 Bus Standard system and TCN-28 Bus of Nigerian system, using Newton-Raphson (N-R) for load flow analysis and RBF-NN prediction method to determine the performance indices were carried out. This was achieved using Matlab code based on the flow chart in Figure 3 which was based on the general structure of RBF-NN in Figure 1 with the determination of hidden neurons based on an algorithm called Growing and Pruning algorithm reported by Javan et al, 2011. The statistical data used for each system is as shown in Table 1. S/No Power Systems No. of Lines Error Goal Spread Constant MSE SSE Correlation Coefficient (R) 1 IEEE-30 Bus (Normal) 41 1.00E-03 15 1.001 1.0005 0.8914 2 IEEE-30 Bus (Improved) 44 1.00E-04 15 1.0331 1.0005 0.7496 3 TCN-28 Bus (Normal) 52 1.00E-03 20 0.006 0.0778 0.945 4 TCN-28 Bus (Improved) 53 1.00E-04 20 0.0081 0.0902 0.9727 TABLE 1: The statistical data of RBF-NN Method. The Line diagram of TCN-28 system is as shown Figure 4 while that of standard IEEE-30 Bus could be easily gotten online via www.ieee.org.
  • 7. Taofik Adekunle Boladale & G. A. Adepoju International Journal of Engineering(IJE), Volume (10) : Issue (2) : 2016 18 Okpai 27, V27 = 1.050pu Calabar 25, V25 = 1.049pu Alaoji 12, V12 = 1.035pu Afa G.S 11, V11 = 1.050pu Aladja 7, V7 = 1.040pu Delta G.S 2, V2 = 1.050pu Sapele G.S 24, V24 = 1.050pu Onitsha 14, V14 = 1.050pu New Haven 13, V13 = 0.977pu Papalanto G.T 28, V28 = 1.050pu Ikeja west 5, V5 = 1.026pu Egbin 1, V1 = 1.026pu Aja 3, V3 = 1.045pu Akangba 4 V4 = 1.019pu Ayede 9, V9 = 0.990pu Osogbo 10, V10 = 1.031pu Benin 8, V8 = 1.029pu Ajaokuta 6, V6 = 1.029pu Abuja26, V26 = 1.026pu Jebba G.S 17, V17 = 1.050pu Jebba T.S 18, V18 = 1.050pu Shiroro G.S 23, V23 = 1.050pu B. Kebbi 15, V15 = 1.065pu Kanji G.S 21, V21 = 1.050pu Kaduna 20, V20 = 1.040pu Kano 22, V22 = 1.010pu Jos 19, V19 = 1.051pu Gombe 16, V16 = 0.994pu Figure 4: TCN – 28 Bus Nigerian System Pre-contingency Load Flow (Source: TCN , 2013) 3. RESULTS AND DISCUSSION The simulation of Contingency analysis of the two systems were carried using RBF-NN method with normal data and improved system data and the result are presented as follows; 3.1 Standard and Improved IEEE-30 Bus Systems Upon the implementation of the RBF-NN method for the Standard IEEE-30 Bus system, Lines 13, 16 and 34 were found not to have converged as shown in Figures 4a, these lines were ranked as 39th, 40th and 41st most critical lines respectively hence they were regarded as the least critical lines while the three most critical lines are Lines 36, 37 and 38; based on the fact that they have largest number of voltage violations ranging from 1.082 to 0.861pu. These results were found to be in agreement with the reports of Mario and Carlos, 2003 and Sarika et. al., 2013. The non- convergence of the above lines was however an indication of their criticality to the functionality of
  • 8. Taofik Adekunle Boladale & G. A. Adepoju International Journal of Engineering(IJE), Volume (10) : Issue (2) : 2016 19 the system hence outage of any of those three lines could lead to instability and eventually the shutdown of the system. They were therefore reinforced with lines of the same parameters. The simulation of this improved System gives the result ranked in Figures 4b., where the most critical line is 39 (the initial line 36) and the least critical line 15 (former line14). FIGURE 4a: Contingency Analysis Ranking of Standard IEEE-30 Bus System using Reactive performance indices. FIGURE 4b: Contingency Analysis Ranking of Improved IEEE-30 Bus System using Reactive performance indices. 3.1 Standard and Improved TCN-28 Bus Systems Also the implimentation of the method on the real Nigerian transmission TCN-28 Bus System gives the resulting Reactive and Active performance indices shown in Figure 5a(I and II) respectiely; which indicated that line 31 did not converge, hence was considered to be the least
  • 9. Taofik Adekunle Boladale & G. A. Adepoju International Journal of Engineering(IJE), Volume (10) : Issue (2) : 2016 20 critical line. Upon reinforcement, line 31 and the incorporated line 32 were still ranked to be the least critical lines as far as voltage violation is concerned but this was found not to be so based on power violation, since the most critical line was line 20 as against the initial line 31 in the standard TCN-28 Bus system. The change in the most critical line from 31(in normal system) as against to line 20 (in improved system) is an indication of imperfect ranking going by the contingency analysis of the normal system. This is shown in Figure 5b (I and II). Also, the least critical line after the reinforcement were lines 29 and 30. FIGURE 5a(I): Contingency Analysis Ranking of Standard TCN-28 Bus System using Reactive performance indices. FIGURE 5a(II): Contingency Analysis Ranking of Standard TCN-28 Bus System using Active performance indices.
  • 10. Taofik Adekunle Boladale & G. A. Adepoju International Journal of Engineering(IJE), Volume (10) : Issue (2) : 2016 21 FIGURE 5b(I): Contingency Analysis Ranking of Standard TCN-28 Bus System using Reactive performance indices. FIGURE 5b(II): Contingency Analysis Ranking of Standard TCN-28 Bus System using Active performance indices. 4. CONCLUSION AND RECOMMENDATION 4.1 Conclusion This research investigated the proficiency of artificial intelligent; radial basis function neural network for revealing the effect of non-convergent power flow on the contingency analysis of electrical power systems by predicting the Active and Reactive performance indices and ranking both in ascending order to show the severity of the transmission lines outages based on power and voltage violations respectively. The contingency analysis of lines with non-convergent power flow which were ranked least were reinforced and their criticality as far as the stability of the system either as a result of voltage or power flow violations is concerned were revealed.
  • 11. Taofik Adekunle Boladale & G. A. Adepoju International Journal of Engineering(IJE), Volume (10) : Issue (2) : 2016 22 Following the above findings it could be concluded that, non-covergency of some of the lines of any power system will definitely affect the contingency analysis of such system as any outage of the non convergent line(s) could lead to the instability and shutdown of such system since either the voltage or power of the particular neighbouring components could be easily driven beyond the operating limits. Consequently in order to appropriately analysed any system with such non-convergent line(s), reinforcing such will give the true picture of system. Lastly, incorporation of parallel line(s) in real power systems such as TCN-28 Bus system will improve the stability property of the system aside providing additional capability of power transmission. 4.2 Recommendation This research work concentrate on N-1Line contingency, multiple components contingency with RBF-NN especially on large real systems should be considered in future work. 5. REFERENCES [1] O. S. Onohaebi, ''Power Outages in the Nigeria transmission Grid''. Medwell Journal of Applied Science, Vol.4, Issue1, pp.1-9, 2009. [2] S. Shahnawaaz and L. Vijayalaxmi ''Contingency Ranking and Analysis Using Mipo International Journal of Engineering Trends and Technology (IJETT) - India; - Vol.10, No 8, ISSN:2231-5381, pp 417-422, 2014. [3] K. R. Amit, ''Contingency Analysis in Power System'', M.Eng. diss., Thapar University, Patiala, 2011. [4] P. Naik, ''Power System Contingency Ranking using Newton Raphson Load flow method and its prediction using Soft Computing Techniques'', M.Tech. diss., National Institute of Technology, Rourkela -769008, 2013. [5] G. C. Ejebe and B. F. Wollenberg, “Automatic Contingency Selection”, IEEE Transactions on Power Apparatus and Systems, Vol. PAS-98, No. 1, January 1979, pp. 97-109, 1979. [6] G. Kusic, ''Computer-Aided Power System Analysis'', Second Edition, Taylor & Francis Group. LLC., 2009. [7] H. Maghrabi, J. A. Refaee, and M. Mohandes, ''Contingency Analysis of Bulk Power System using Neural Networks''. Proceedings of International Conference on Power System Technology, Beijing China. POWERCON. Vol. 2:pp. 1251-1254, 1998. [8] I. A. Adejumobi, G. A. Adepoju and K. A. Hamzat, '' Iterative Techniques for Load Flow Study: A Comparative Study for Nigeria 330KV Grid System as a Case Study'', International Journal of Engineering and advance Technology, ISSN:2249-8958, Vol.3, Issue-1, pp. 153- 158, 2013. [9] M. Boudour and A. Hellal, “Combined use of unsupervised and supervised learning for Large Scale power system Static Security Mapping”, IEEE conference on Power Systems, pp.1321-1327, 2004. [10] K. Andrej, B. Janez and K. Andrej, ''Introduction to the Artificial Neural Networks, Artificial Neural Networks-Methodological and Biomedical Applications, Prof. Kenji Suzuki (Ed.), ISBN; 978-953-307-243-2, In-Tech., pp 1-17, 2011.
  • 12. Taofik Adekunle Boladale & G. A. Adepoju International Journal of Engineering(IJE), Volume (10) : Issue (2) : 2016 23 [11] D. C. Javan, R. H. Mashhadi and M. Rouhani, '' Fast Voltage and Power Flow Contingencies Ranking using Enhanced Radial Basis Function Neural Network'', IJEEE, vol.7, No.4, pp 273-282, 2011. [12] A. A. Mario, and A. C. Carlos, ''A Contingency Ranking Method for Voltage Stability in Real Time Operation of power Systems''. IEEE Bologna Power Tech Conference, Bologna, Italy, 0-7803-7967-5/03/, 2003. [13] V. Sarika, S. Laxmi, P. Manjaree and S. Manisha, ''Voltage Stability Based Contingency Ranking using Distributed Computing Environment'' International Conference on Power, Energy and Control'' Gwaior, M.P. India, pp 208-212, 2013. [14] O. J. Onojo, G. C. Ononiwu, and S. O. Okozi, ''Analysis of Power Flow of Nigerian 330kv grid System(pre and post) using Matlab''. European Journal of Natural Sciences, Vol.1(2), pp 59-66, 2013.