Arman Mashoori
B.s Civil
Engineering
Fit out Project
Manager
1
TABLE OF CONTENTS:
Introduction Page 3
Personal Details Page 3
Summary of Experience Page 3 -5
Employers & Projects:
Fino International
Hyatt Regency Hotel & Apartments Page 6 -35
Louvre Abu Dhabi- Mock-up Building Page 36
-38
Bab Al Qasr Hotel & Serviced Apartments- Abu Dhabi Page 39
-42
Izel Restaurant & Bar at Conrad Hotel-Dubai Page 43 -
51
Sheikh Zayed Desert Learning Center (SZDLC)-Al Ain Page
52 -61
Dubai Metro (Red Line & Green Line ) Page 62 -
70
EC Harris International
Dubai Industrial City (Warehouses & Labor Cities) Page 71
-72
Parkway International Contracting
Dubai Marina Mall & Hotel Apartments Page 73 -
76
Palm Jumeirah Villas (Frond B) Page 77 -
84
References: Page 85
2
Introduction:
I am a talented, self-motivated and innovative civil engineer with more than 16
years of experience in successfully completing several prestigious projects
such as Villas, High-Rise Buildings, Hotels, Restaurants, Shopping Malls,
Museums & Industrial Complexes from conception through to hand over both
in Civil & Fit out activities.
Offer significant abilities in the areas of construction/project management,
team leadership, planning and implementing of detailed work schedule and
commissioning/handing over.
Additionally, to achieve my desired outputs such as meet the Client’s core
values and deadlines, optimize team work, provide & analyze construction
reports and improvement of construction/project skills, I am eagerly committed
to absorb as much information as possible from the relevant parties in order to
produce solutions to potential and existing issues And consequently, to
accomplish goals within the Time, Cost and Quality constraints.
Being an effective well organized Fit out Project Manager with an outgoing and
friendly nature, which allows me to interact and relate with all levels of staff ,I
am able to bridge the gap between technical and non-technical members.
Personal Details:
Qualification: B.S. Civil Engineering, 1997
Date of Birth: 22-Nov-1973
Status: Married
Nationality: Iranian
Mobile: +97155 99 31 508
Email: armanmashoori@gmail.com
Arman Mashoori
Summary of Experience:
As an active, Self-motivated Fit out Project Manager with more than 16 years
experience, I have been responsible for ,but not limited to the following duties:
3
1. Arranging and advising the precautions related to Site Mobilization.
2. Liaise with Main contractor, Consultant and the Client to meet the planned
deadlines.
3. Detailed Planning of Construction activities' sequences in relation with the
Main Baseline Program of the project.
4. Achieving the early approval of the project's Specified/Alternative material
in order to place the Purchase Orders and follow up on delivery of
Material, Tools and Equipments especially for long lead items.
5. Closely coordinate with Technical/Design team to develop relevant
drawings prior to the required approval from the Consultant.
6. Assisting the QA/QC and HSE Departments to Prepare, Submit and
Receive the early approval on Method Statements, ITPs, Risk
Assessments according to local Codes and Regulations.
7. Perform QA/QC and HSE functions of various activities, Implementation of
precautionary procedures and preventive measures in compliance with
the approved Specifications and Regulations.
8. Monitor and Supervision of Construction Tasks & Resources such as
correct Procurement and Distribution of Material, Equipment and
Manpower on daily basis.
9. Manage Direct and Indirect staff by assigning them tasks & monitoring
their daily/weekly output as well as highlighting the areas of delay which
requires action.
10. Prepare, Review and Analyze the construction activity reports.
11. Conducting Daily/Weekly Progress Meetings pertaining to various
departments (e.g. Construction, Technical, Procurement) and preparing
the related Minutes of Meetings in order to ensure that the project tasks
are being successfully accomplished.
12. Analyze and monitor the Project's Commercial and Contractual aspects
(e.g. Variation Orders, Official Site Instructions, Material Procurement) to
achieve the ultimate efficiency within the identified Project Margin.
13. Prepare and review the required documents to submit the Interim/Final
Payment Applications in accordance with the project's specified intervals.
14. Ensure Collection, Filing and archiving of the Project History in order to
achieve a proper Snagging, De-snagging and Handing Over.
Since most of my areas of expertise have been on Fit out Projects ,below are
the main items which have been conducted within the mentioned projects:
4
5
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Client: Wasl Properties
Consultant/Engineer: RMJM
Main Contractor: ABM
Interior Designer: KCA
Project Value: 54,000,000 AED
Project Description:
The Project is divided into Three Packages. Podium at 2nd Level, Presidential Suites
on the top two levels of the Hotel Tower and Six Penthouses on the top two
levels of the Apartment Tower.
At Podium level, there are six Treatment Rooms with an additional two VIP
Treatment Rooms and the related access Corridor, SPA Reception, SPA
Manager and Consultant offices. Also Male/Female Changing areas next to the
Swimming Pool, Public Toilets, Pool Deck Corridor and Lift Lobbies for Hotel
Guests and Apartment residents.
A separated GYM for Apartment residents, with a Female GYM and a Unisex GYM
along with Exercise and Yoga zone, Lounge and Kids Club for Hotel Guests.
Two Presidential Suites are in two level with different interior concepts. Each one
includes a Master Bedroom ,two Bedrooms, Maid’s room, GYM & SPA area.
Kitchen, Reception Lounge and Lift Lobby, Dinning Room, Main Lounge &
Study area, Majliis and Main Corridor.
Six Penthouses are available in different Four sizes.(One, Two, Three & Four
Bedrooms).
6
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Podium
7
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Podium
8
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Podium
9
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Podium
10
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Podium
11
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Podium
12
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Podium
13
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Podium
14
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Podium
15
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Podium
16
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Podium
17
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Podium
18
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Podium
19
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Podium
20
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Presidential Suites
21
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Presidential Suites
22
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Presidential Suites
23
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Presidential Suites
24
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Presidential Suites
25
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Presidential Suites
26
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Presidential Suites
27
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Presidential Suites
28
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Penthouse
29
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Penthouse
30
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Penthouse
31
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Penthouse
32
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Penthouse
33
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Penthouse
34
Hyatt Regency Hotel & Apartments
Designation: Project Manager Duration: February 2014 to Present
Penthouse
35
Louvre Abu Dhabi- Mock-up Building
Designation: Project Manager Duration: September 2013 to January 2014
Client: TDIC
Project Management: Turner
Consultant/Engineer: KEO Intl-Buro Happold
Main Contractor: ASO JV
Interior Designer: AJN
Project Value: 12,000,000 AED
Project Description:
The Mock up Building is intended to reflect the Abu Dhabi Louvre Museum's Main
Building design and the relevant Material which was designed by Mr. Jean
Nouvel the renowned French Architect. Therefore, it was split into Two
packages which are called “The Base Build & Museography .
The Base Build package consists of Two levels of Administrative Areas, Main
Entrance, Café, and Staircase.
The Museography package consists of the Bronze Gallery and the Main Gallery .
36
Louvre Abu Dhabi- Mock-up Building
Designation: Project Manager Duration: September 2013 to January 2014
37
Louvre Abu Dhabi- Mock-up Building
Designation: Project Manager Duration: September 2013 to January 2014
38
Bab Al Qasr Hotel and Services Apartments
Designation: Construction Manager Duration: May 2013 to January 2014
Client: EMROC
Project Management: Jacobs
Consultant/Engineer: Surbana
Main Contractor: Nurol
Interior Designer: PSI
Project Value: 150,000,000 AED
Project Description:
The Project is divided into Three Packages. Grand Lobby at Ground Floor, Hotel
Tower and Serviced Apartment Tower.
At Grand Lobby, there are unique staircases ,GRG patterned walls and Arched as
well as Wooden Cladding up to almost 51 meter high.
At Hotel Tower, there are a total of 412 Rooms categorized as detailed below:
Presidential Suite 1
Executive Suite 30
Junior Suite 54
Superior King 85
Typical King 123
Typical Queen 4
Typical Twin 115
At Serviced Apartment Tower, there are a total of 265 Rooms categorized as
detailed below:
Penthouse 1
3 Bedroom 7
2 Bedroom 50
1 Bedroom 147
Studio 60
39
Bab Al Qasr Hotel and Services Apartments
Designation: Construction Manager Duration: May 2013 to January 2014
40
Bab Al Qasr Hotel and Services Apartments
Designation: Construction Manager Duration: May 2013 to January 2014
41
Bab Al Qasr Hotel and Services Apartments
Designation: Construction Manager Duration: May 2013 to January 2014
42
IZEL Restaurant and Bar – Conrad Hotel
Designation: Project Manager Duration: May 2012 to April 2013
Client: Private Property
Management (PPM)
Consultant/Engineer: Atkins
Main Contractor: Arabtec/DCC JV
Interior Designer: WA International
Gross Area: 1700 m²
Project Value: 12,000,000 AED
Project Description:
According to the language of the Mayan, IZEL means “Unique”. A culture which
inspires this one-of-a-kind venue and experience, along with the “New Age”
era where Latin American culture is globally styled.
The Project is divided into three areas which are The Restaurant, The Bar and
The Terrace and is located at 7th Floor of the newly built Conrad Hotel in
Sheikh Zayed Road, Dubai.
At the Restaurant Side, the ceiling is designed with Three Domes with very
unique Chandeliers, VIP dinning room with a special lift lobby, for the guests,
The Show Kitchen and DJ Boot as well as the Band stage.
At Bar Side, the ceiling is built using three dimensional elements, The Main
Bar, The Cigar Lounge and Display units and the main Lift Lobby with a Back
lit Black & Gold Color Glass wall.
43
IZEL Restaurant and Bar – Conrad Hotel
Designation: Project Manager Duration: May 2012 to April 2013
44
IZEL Restaurant and Bar – Conrad Hotel
Designation: Project Manager Duration: May 2012 to April 2013
45
IZEL Restaurant and Bar – Conrad Hotel
Designation: Project Manager Duration: May 2012 to April 2013
46
IZEL Restaurant and Bar – Conrad Hotel
Designation: Project Manager Duration: May 2012 to April 2013
47
IZEL Restaurant and Bar – Conrad Hotel
Designation: Project Manager Duration: May 2012 to April 2013
48
IZEL Restaurant and Bar – Conrad Hotel
Designation: Project Manager Duration: May 2012 to April 2013
49
IZEL Restaurant and Bar – Conrad Hotel
Designation: Project Manager Duration: May 2012 to April 2013
50
IZEL Restaurant and Bar – Conrad Hotel
Designation: Project Manager Duration: May 2012 to April 2013
51
Sheikh Zayed Desert Learning Centre
Designation: Project Manager Duration: August 2011 to April 2012
Client: Al Ain Wildlife Park and Resort
Consultant/Engineer/Architect: Chalabi Architects & Partners
Structural Engineer: Bollinger Grohmann Schneider
Main Contractor: Ed. Züblin AG
Gross Area: 12,000 m²
Project Value: 75,000,000 AED
Project Description:
The Sheikh Zayed Desert Learning Center is a phenomenal structure not only because of
its unique design and finishes, but also for its green approaches. It is aiming to
achieve LEED Platinum and Estidama 5 Pearls which are the highest achievable
ratings for these green building systems.
LEED is a system developed in the United States whereas Estidama is a local system
(from Abu Dhabi) that focuses on green technologies and approaches related to the
Arabian Gulf , with concentration on energy and water efficiency. Sheikh Zayed
Desert Learning Center is the pilot project for Estidama v 1.0.
The Sheikh Zayed Desert Learning Center is built with unique energy efficiency and
water efficiency technologies. In addition, there is major focus on green materials for
the building. In order to achieve the high ratings, the project teams sourced and
installed regional materials, recycled content materials, low Volatile Organic
Compound (VOC) adhesives, paints, carpets, composite wood and high SRI materials
for the external cladding. The project is under very stringent waste diversion targets;
all types of wastes are segregated on site and sent for recycling rather than landfill or
incineration.
As a finishing company contracted to complete interior and exterior work, FINO is
contributing towards the achievement of the materials credits in SZDLC. Some of
these are sourcing and using chemicals that have low volatile organic compound
levels. This ensures that the indoor air quality is free of pollutants and toxic chemicals
for the occupants of the building. In addition, the doors to be used on SZDLC are
sourced from sustainable forestry. Wastes are sent back to manufacturers for
recycling rather than disposal.
The most important contributor towards the achievement of LEED and Estidama is the
close coordination between all project team members. Openly discussing issues with
our Clients, helps in meeting the requirements of these green building rating systems.
With transparent communication, the purpose of these rating systems is met, as they
encourage integrated development and holistic approach to construction.
52
Sheikh Zayed Desert Learning Centre
Designation: Project Manager Duration: August 2011 to April 2012
53
Sheikh Zayed Desert Learning Centre
Designation: Project Manager Duration: August 2011 to April 2012
54
Sheikh Zayed Desert Learning Centre
Designation: Project Manager Duration: August 2011 to April 2012
55
Sheikh Zayed Desert Learning Centre
Designation: Project Manager Duration: August 2011 to April 2012
56
Sheikh Zayed Desert Learning Centre
Designation: Project Manager Duration: August 2011 to April 2012
57
Sheikh Zayed Desert Learning Centre
Designation: Project Manager Duration: August 2011 to April 2012
58
Sheikh Zayed Desert Learning Centre
Designation: Project Manager Duration: August 2011 to April 2012
59
Sheikh Zayed Desert Learning Centre
Designation: Project Manager Duration: August 2011 to April 2012
60
Sheikh Zayed Desert Learning Centre
Designation: Project Manager Duration: August 2011 to April 2012
61
Dubai Metro (Red Line & Green Line)
Designation: Construction Manager Duration: May 2009 to July 2011
Client: Road & Transportation
Authority (RTA)
Consultant/Engineer: Atkins/ SYSTRA
Main Contractor: Dubai Rapid Link
Consortium (JTMJV)
Project Value: 210,000,000 AED
Project Description:
The Project consist of Fitout Works of Two Metro Lines in Dubai ( Red & Green).
At Metro Red Line, Our Scope was all Interior works of 28 Stations’ Entrance Pods
and Foot Bridges.
At Metro Green Line, Our Scope was Partial Interior works of 18 Stations and their
Entrance Pods.
62
Dubai Metro (Red Line & Green Line)
Designation: Construction Manager Duration: May 2009 to July 2011
63
Dubai Metro (Red Line & Green Line)
Designation: Construction Manager Duration: May 2009 to July 2011
64
Dubai Metro (Red Line & Green Line)
Designation: Construction Manager Duration: May 2009 to July 2011
65
Dubai Metro (Red Line & Green Line)
Designation: Construction Manager Duration: May 2009 to July 2011
66
Dubai Metro (Red Line & Green Line)
Designation: Construction Manager Duration: May 2009 to July 2011
67
Dubai Metro (Red Line & Green Line)
Designation: Construction Manager Duration: May 2009 to July 2011
68
Dubai Metro (Red Line & Green Line)
Designation: Construction Manager Duration: May 2009 to July 2011
69
Dubai Metro (Red Line & Green Line)
Designation: Construction Manager Duration: May 2009 to July 2011
70
Dubai Industrial City (DIC)
Designation: Project Manager Duration: September 2008 to August 2009
Client: TATWEER
Project Management: EC Harris International
Consultant/Engineer: MEECON
Main Contractor: Al Hamad Contracting
Project Description:
The Project consist of Civil works as well as Fit out Works of Five Labor Cities and
Two Warehouse complexes at Dubai Industrial City .
71
Dubai Industrial City (DIC)
Designation: Project Manager Duration: September 2008 to August 2009
72
Dubai Marina Mall & Hotel Apartments
Designation: Construction Manager Duration: October 2007 to August 2008
Client: EMAAR
Project Management: Hill International
Consultant/Engineer: DP Architects
Main Contractor: ALEC
Project Value: 46,000,000 AED
Project Description:
The Project consist of Civil works as well as Fit out Works of All Parking Levels and
Three Levels of the Shopping Mall.
73
Dubai Marina Mall & Hotel Apartments
Designation: Construction Manager Duration: October 2007 to August 2008
74
Dubai Marina Mall & Hotel Apartments
Designation: Construction Manager Duration: October 2007 to August 2008
75
Dubai Marina Mall & Hotel Apartments
Designation: Construction Manager Duration: October 2007 to August 2008
76
Palm Jumeirah Villas
Designation: Project Engineer Duration: August 2006 to September 2007
Client: Nakheel
Project Management: Hill International
Consultant/Engineer: KEO International
Main Contractor: Parkway International
Contracting
Project Value: 257,000,000 AED
Project Description:
The Project consist of Three Fronds (A,B & P) ,218 luxury villas (G+1), varying in
size, with a built up area from 350 sq.m to 700 sq.m. Our scope of works
included the complete civil works, finishing, MEP works, swimming pools and
landscaping (soft & hard).
77
Palm Jumeirah Villas
Designation: Project Engineer Duration: August 2006 to September 2007
78
Palm Jumeirah Villas
Designation: Project Engineer Duration: August 2006 to September 2007
79
Palm Jumeirah Villas
Designation: Project Engineer Duration: August 2006 to September 2007
80
Palm Jumeirah Villas
Designation: Project Engineer Duration: August 2006 to September 2007
81
Palm Jumeirah Villas
Designation: Project Engineer Duration: August 2006 to September 2007
82
Palm Jumeirah Villas
Designation: Project Engineer Duration: August 2006 to September 2007
83
Palm Jumeirah Villas
Designation: Project Engineer Duration: August 2006 to September 2007
84
References:
Company Name Name and Designation Contact
Number
Fino International Sufian Swaidan- Projects Director 050 252 5575
Fino International Douglas Gibbs- Contracts Manager 056 938 9908
EC Harris International Andrew Welsh-Senior Project
Manager
050 553 5984
EC Harris International Darek Stokowski- Construction
Manager
050 870 1323
Parkway International
Contracting
Tarek Al Zoabi-Managing Director 050 295 0116
Parkway International
Contracting
Mufid Al Zeir-General Manager 050 616 1597
85

Weitere ähnliche Inhalte

Was ist angesagt?

Building Services :Drainage, Rain Water Disposal and Harvesting
Building Services :Drainage,  Rain Water Disposal and  HarvestingBuilding Services :Drainage,  Rain Water Disposal and  Harvesting
Building Services :Drainage, Rain Water Disposal and HarvestingSumit Ranjan
 
Know about the beauty of Sultanate of Oman
Know about the beauty of Sultanate of OmanKnow about the beauty of Sultanate of Oman
Know about the beauty of Sultanate of OmanBilal Kareem
 
Traditional construction
Traditional constructionTraditional construction
Traditional constructionDr K M SONI
 
Kanshi ram eco park lucknow..Urban Design
Kanshi ram eco park lucknow..Urban DesignKanshi ram eco park lucknow..Urban Design
Kanshi ram eco park lucknow..Urban Designvinit2
 
دراسة تحليلية لمجاورات سكنية - اسكان - سنة 3 - ابراهيم الرداعي
دراسة تحليلية لمجاورات سكنية - اسكان - سنة 3 - ابراهيم الرداعيدراسة تحليلية لمجاورات سكنية - اسكان - سنة 3 - ابراهيم الرداعي
دراسة تحليلية لمجاورات سكنية - اسكان - سنة 3 - ابراهيم الرداعيIbrahem Qasim
 
Cairo American School - Sustainable Building of the School
Cairo American School - Sustainable Building of the SchoolCairo American School - Sustainable Building of the School
Cairo American School - Sustainable Building of the SchoolCAC
 
Sem 2 bs1 cold water supply 2
Sem 2 bs1 cold water supply 2Sem 2 bs1 cold water supply 2
Sem 2 bs1 cold water supply 2Est
 

Was ist angesagt? (9)

Building Services :Drainage, Rain Water Disposal and Harvesting
Building Services :Drainage,  Rain Water Disposal and  HarvestingBuilding Services :Drainage,  Rain Water Disposal and  Harvesting
Building Services :Drainage, Rain Water Disposal and Harvesting
 
Know about the beauty of Sultanate of Oman
Know about the beauty of Sultanate of OmanKnow about the beauty of Sultanate of Oman
Know about the beauty of Sultanate of Oman
 
Traditional construction
Traditional constructionTraditional construction
Traditional construction
 
Kanshi ram eco park lucknow..Urban Design
Kanshi ram eco park lucknow..Urban DesignKanshi ram eco park lucknow..Urban Design
Kanshi ram eco park lucknow..Urban Design
 
المطارات
المطاراتالمطارات
المطارات
 
دراسة تحليلية لمجاورات سكنية - اسكان - سنة 3 - ابراهيم الرداعي
دراسة تحليلية لمجاورات سكنية - اسكان - سنة 3 - ابراهيم الرداعيدراسة تحليلية لمجاورات سكنية - اسكان - سنة 3 - ابراهيم الرداعي
دراسة تحليلية لمجاورات سكنية - اسكان - سنة 3 - ابراهيم الرداعي
 
Cairo American School - Sustainable Building of the School
Cairo American School - Sustainable Building of the SchoolCairo American School - Sustainable Building of the School
Cairo American School - Sustainable Building of the School
 
Sem 2 bs1 cold water supply 2
Sem 2 bs1 cold water supply 2Sem 2 bs1 cold water supply 2
Sem 2 bs1 cold water supply 2
 
Why Consider a Green Roof?
Why Consider a Green Roof?Why Consider a Green Roof?
Why Consider a Green Roof?
 

Andere mochten auch

teatro chino
teatro chinoteatro chino
teatro chinomariellin
 
Kevin Slade - CV
Kevin Slade - CVKevin Slade - CV
Kevin Slade - CVKevin Slade
 
Flyer MusikSommerKurs 2019
Flyer MusikSommerKurs 2019Flyer MusikSommerKurs 2019
Flyer MusikSommerKurs 2019arturopiano
 
Opening ceremony AISF Pisa
Opening ceremony AISF PisaOpening ceremony AISF Pisa
Opening ceremony AISF PisaJose Gonzalez
 
Wie soziale Medien den Lerntransfer unterstützen (können)
Wie soziale Medien den Lerntransfer unterstützen (können)Wie soziale Medien den Lerntransfer unterstützen (können)
Wie soziale Medien den Lerntransfer unterstützen (können)Sandra Schön (aka Schoen)
 
Consejos para una compra online segura
Consejos para una compra online seguraConsejos para una compra online segura
Consejos para una compra online segurayaysi
 
Boletín Help/Falck abril
Boletín Help/Falck abrilBoletín Help/Falck abril
Boletín Help/Falck abrilgrupoemi
 
Generando evidencias 26 may15
Generando evidencias 26 may15Generando evidencias 26 may15
Generando evidencias 26 may15dboyco
 
TYPO3 responsive bootstrap basepackage T3ee presentation 2013 romania
TYPO3 responsive bootstrap basepackage T3ee presentation 2013 romaniaTYPO3 responsive bootstrap basepackage T3ee presentation 2013 romania
TYPO3 responsive bootstrap basepackage T3ee presentation 2013 romaniaRobert Lindh
 
Green Global Software Company
Green Global Software CompanyGreen Global Software Company
Green Global Software CompanyHai Le
 
personajes del hip hop
personajes del hip hoppersonajes del hip hop
personajes del hip hopccforero
 
Mixed Vegetable Gardening - PermacultureUk
Mixed Vegetable Gardening - PermacultureUkMixed Vegetable Gardening - PermacultureUk
Mixed Vegetable Gardening - PermacultureUkFaiga64c
 

Andere mochten auch (20)

IBM Client Center Madrid
IBM Client Center MadridIBM Client Center Madrid
IBM Client Center Madrid
 
teatro chino
teatro chinoteatro chino
teatro chino
 
Kevin Slade - CV
Kevin Slade - CVKevin Slade - CV
Kevin Slade - CV
 
Flyer MusikSommerKurs 2019
Flyer MusikSommerKurs 2019Flyer MusikSommerKurs 2019
Flyer MusikSommerKurs 2019
 
Opening ceremony AISF Pisa
Opening ceremony AISF PisaOpening ceremony AISF Pisa
Opening ceremony AISF Pisa
 
Wie soziale Medien den Lerntransfer unterstützen (können)
Wie soziale Medien den Lerntransfer unterstützen (können)Wie soziale Medien den Lerntransfer unterstützen (können)
Wie soziale Medien den Lerntransfer unterstützen (können)
 
Consejos para una compra online segura
Consejos para una compra online seguraConsejos para una compra online segura
Consejos para una compra online segura
 
CaseStudyAboutHappyAcademy
CaseStudyAboutHappyAcademyCaseStudyAboutHappyAcademy
CaseStudyAboutHappyAcademy
 
Boletín XXVII julio 2016
Boletín XXVII julio 2016Boletín XXVII julio 2016
Boletín XXVII julio 2016
 
Estudio metrico poema1
Estudio metrico poema1Estudio metrico poema1
Estudio metrico poema1
 
Boletín Help/Falck abril
Boletín Help/Falck abrilBoletín Help/Falck abril
Boletín Help/Falck abril
 
Cosinus768x384w2015
Cosinus768x384w2015Cosinus768x384w2015
Cosinus768x384w2015
 
Generando evidencias 26 may15
Generando evidencias 26 may15Generando evidencias 26 may15
Generando evidencias 26 may15
 
Rauno Pella
Rauno PellaRauno Pella
Rauno Pella
 
TYPO3 responsive bootstrap basepackage T3ee presentation 2013 romania
TYPO3 responsive bootstrap basepackage T3ee presentation 2013 romaniaTYPO3 responsive bootstrap basepackage T3ee presentation 2013 romania
TYPO3 responsive bootstrap basepackage T3ee presentation 2013 romania
 
Green Global Software Company
Green Global Software CompanyGreen Global Software Company
Green Global Software Company
 
personajes del hip hop
personajes del hip hoppersonajes del hip hop
personajes del hip hop
 
Mixed Vegetable Gardening - PermacultureUk
Mixed Vegetable Gardening - PermacultureUkMixed Vegetable Gardening - PermacultureUk
Mixed Vegetable Gardening - PermacultureUk
 
Proyecto de-politica-planificacion-familiar
Proyecto de-politica-planificacion-familiarProyecto de-politica-planificacion-familiar
Proyecto de-politica-planificacion-familiar
 
Presentación enfermedad pick
Presentación enfermedad pickPresentación enfermedad pick
Presentación enfermedad pick
 

Ähnlich wie Arman mashoori - Fit out Project Manager (20)

Architect Technical
Architect TechnicalArchitect Technical
Architect Technical
 
MT_CV
MT_CVMT_CV
MT_CV
 
Yehia CV+Portfolio 2017 Final
Yehia CV+Portfolio 2017 FinalYehia CV+Portfolio 2017 Final
Yehia CV+Portfolio 2017 Final
 
Dy Head CV
Dy Head CVDy Head CV
Dy Head CV
 
cv porto2
cv porto2cv porto2
cv porto2
 
Resume - Moustapha Omar
Resume - Moustapha OmarResume - Moustapha Omar
Resume - Moustapha Omar
 
avinash chandrashekar-CV
avinash chandrashekar-CVavinash chandrashekar-CV
avinash chandrashekar-CV
 
biju DGM
biju DGMbiju DGM
biju DGM
 
Prajeesh K. CV - Sep 2016
Prajeesh K. CV - Sep 2016Prajeesh K. CV - Sep 2016
Prajeesh K. CV - Sep 2016
 
Architect mohamed el-tarabily
Architect mohamed el-tarabilyArchitect mohamed el-tarabily
Architect mohamed el-tarabily
 
Nizar Mukahal CV 2015
Nizar Mukahal CV 2015Nizar Mukahal CV 2015
Nizar Mukahal CV 2015
 
Lina Mohamed CV
Lina Mohamed CVLina Mohamed CV
Lina Mohamed CV
 
CV-2016
CV-2016CV-2016
CV-2016
 
Wesam Maannee CV- Aug16
Wesam Maannee CV- Aug16Wesam Maannee CV- Aug16
Wesam Maannee CV- Aug16
 
Adnan.S_CV
Adnan.S_CVAdnan.S_CV
Adnan.S_CV
 
CV2
CV2CV2
CV2
 
Mohammed imad ahmed
Mohammed imad ahmedMohammed imad ahmed
Mohammed imad ahmed
 
Shaker Mohammed Sr. Draftsman Arch
Shaker Mohammed Sr. Draftsman ArchShaker Mohammed Sr. Draftsman Arch
Shaker Mohammed Sr. Draftsman Arch
 
CV 2015
CV   2015CV   2015
CV 2015
 
HANI ISMAIL HARZALLAH - Latest
HANI ISMAIL HARZALLAH - LatestHANI ISMAIL HARZALLAH - Latest
HANI ISMAIL HARZALLAH - Latest
 

Kürzlich hochgeladen

Personal Brand Exploration - Fernando Negron
Personal Brand Exploration - Fernando NegronPersonal Brand Exploration - Fernando Negron
Personal Brand Exploration - Fernando Negronnegronf24
 
UIowa Application Instructions - 2024 Update
UIowa Application Instructions - 2024 UpdateUIowa Application Instructions - 2024 Update
UIowa Application Instructions - 2024 UpdateUniversity of Iowa
 
Top profile Call Girls In Varanasi [ 7014168258 ] Call Me For Genuine Models ...
Top profile Call Girls In Varanasi [ 7014168258 ] Call Me For Genuine Models ...Top profile Call Girls In Varanasi [ 7014168258 ] Call Me For Genuine Models ...
Top profile Call Girls In Varanasi [ 7014168258 ] Call Me For Genuine Models ...gajnagarg
 
Kannada Call Girls Mira Bhayandar WhatsApp +91-9930687706, Best Service
Kannada Call Girls Mira Bhayandar WhatsApp +91-9930687706, Best ServiceKannada Call Girls Mira Bhayandar WhatsApp +91-9930687706, Best Service
Kannada Call Girls Mira Bhayandar WhatsApp +91-9930687706, Best Servicemeghakumariji156
 
Brand Analysis for reggaeton artist Jahzel.
Brand Analysis for reggaeton artist Jahzel.Brand Analysis for reggaeton artist Jahzel.
Brand Analysis for reggaeton artist Jahzel.GabrielaMiletti
 
Miletti Gabriela_Vision Plan for artist Jahzel.pdf
Miletti Gabriela_Vision Plan for artist Jahzel.pdfMiletti Gabriela_Vision Plan for artist Jahzel.pdf
Miletti Gabriela_Vision Plan for artist Jahzel.pdfGabrielaMiletti
 
K Venkat Naveen Kumar | GCP Data Engineer | CV
K Venkat Naveen Kumar | GCP Data Engineer | CVK Venkat Naveen Kumar | GCP Data Engineer | CV
K Venkat Naveen Kumar | GCP Data Engineer | CVK VENKAT NAVEEN KUMAR
 
207095666-Book-Review-on-Ignited-Minds-Final.pptx
207095666-Book-Review-on-Ignited-Minds-Final.pptx207095666-Book-Review-on-Ignited-Minds-Final.pptx
207095666-Book-Review-on-Ignited-Minds-Final.pptxpawangadkhe786
 
Dating Call Girls inTiruvallur { 9332606886 } VVIP NISHA Call Girls Near 5 St...
Dating Call Girls inTiruvallur { 9332606886 } VVIP NISHA Call Girls Near 5 St...Dating Call Girls inTiruvallur { 9332606886 } VVIP NISHA Call Girls Near 5 St...
Dating Call Girls inTiruvallur { 9332606886 } VVIP NISHA Call Girls Near 5 St...ruksarkahn825
 
Joshua Minker Brand Exploration Sports Broadcaster .pptx
Joshua Minker Brand Exploration Sports Broadcaster .pptxJoshua Minker Brand Exploration Sports Broadcaster .pptx
Joshua Minker Brand Exploration Sports Broadcaster .pptxsportsworldproductio
 
Guide to a Winning Interview May 2024 for MCWN
Guide to a Winning Interview May 2024 for MCWNGuide to a Winning Interview May 2024 for MCWN
Guide to a Winning Interview May 2024 for MCWNBruce Bennett
 
Simple, 3-Step Strategy to Improve Your Executive Presence (Even if You Don't...
Simple, 3-Step Strategy to Improve Your Executive Presence (Even if You Don't...Simple, 3-Step Strategy to Improve Your Executive Presence (Even if You Don't...
Simple, 3-Step Strategy to Improve Your Executive Presence (Even if You Don't...Angela Justice, PhD
 
怎样办理哥伦比亚大学毕业证(Columbia毕业证书)成绩单学校原版复制
怎样办理哥伦比亚大学毕业证(Columbia毕业证书)成绩单学校原版复制怎样办理哥伦比亚大学毕业证(Columbia毕业证书)成绩单学校原版复制
怎样办理哥伦比亚大学毕业证(Columbia毕业证书)成绩单学校原版复制yynod
 
Top profile Call Girls In Agartala [ 7014168258 ] Call Me For Genuine Models ...
Top profile Call Girls In Agartala [ 7014168258 ] Call Me For Genuine Models ...Top profile Call Girls In Agartala [ 7014168258 ] Call Me For Genuine Models ...
Top profile Call Girls In Agartala [ 7014168258 ] Call Me For Genuine Models ...gajnagarg
 
Low Cost Coimbatore Call Girls Service 👉📞 6378878445 👉📞 Just📲 Call Ruhi Call ...
Low Cost Coimbatore Call Girls Service 👉📞 6378878445 👉📞 Just📲 Call Ruhi Call ...Low Cost Coimbatore Call Girls Service 👉📞 6378878445 👉📞 Just📲 Call Ruhi Call ...
Low Cost Coimbatore Call Girls Service 👉📞 6378878445 👉📞 Just📲 Call Ruhi Call ...vershagrag
 
drug book file on obs. and gynae clinical pstings
drug book file on obs. and gynae clinical pstingsdrug book file on obs. and gynae clinical pstings
drug book file on obs. and gynae clinical pstingsKarishma7720
 
B.tech Civil Engineering Major Project by Deepak Kumar ppt.pdf
B.tech Civil Engineering Major Project by Deepak Kumar ppt.pdfB.tech Civil Engineering Major Project by Deepak Kumar ppt.pdf
B.tech Civil Engineering Major Project by Deepak Kumar ppt.pdfDeepak15CivilEngg
 
Top profile Call Girls In Rampur [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Rampur [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Rampur [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Rampur [ 7014168258 ] Call Me For Genuine Models We...nirzagarg
 
<DUBAI>Abortion pills IN UAE {{+971561686603*^Mifepristone & Misoprostol in D...
<DUBAI>Abortion pills IN UAE {{+971561686603*^Mifepristone & Misoprostol in D...<DUBAI>Abortion pills IN UAE {{+971561686603*^Mifepristone & Misoprostol in D...
<DUBAI>Abortion pills IN UAE {{+971561686603*^Mifepristone & Misoprostol in D...gynedubai
 

Kürzlich hochgeladen (20)

Cara Gugurkan Kandungan Awal Kehamilan 1 bulan (087776558899)
Cara Gugurkan Kandungan Awal Kehamilan 1 bulan (087776558899)Cara Gugurkan Kandungan Awal Kehamilan 1 bulan (087776558899)
Cara Gugurkan Kandungan Awal Kehamilan 1 bulan (087776558899)
 
Personal Brand Exploration - Fernando Negron
Personal Brand Exploration - Fernando NegronPersonal Brand Exploration - Fernando Negron
Personal Brand Exploration - Fernando Negron
 
UIowa Application Instructions - 2024 Update
UIowa Application Instructions - 2024 UpdateUIowa Application Instructions - 2024 Update
UIowa Application Instructions - 2024 Update
 
Top profile Call Girls In Varanasi [ 7014168258 ] Call Me For Genuine Models ...
Top profile Call Girls In Varanasi [ 7014168258 ] Call Me For Genuine Models ...Top profile Call Girls In Varanasi [ 7014168258 ] Call Me For Genuine Models ...
Top profile Call Girls In Varanasi [ 7014168258 ] Call Me For Genuine Models ...
 
Kannada Call Girls Mira Bhayandar WhatsApp +91-9930687706, Best Service
Kannada Call Girls Mira Bhayandar WhatsApp +91-9930687706, Best ServiceKannada Call Girls Mira Bhayandar WhatsApp +91-9930687706, Best Service
Kannada Call Girls Mira Bhayandar WhatsApp +91-9930687706, Best Service
 
Brand Analysis for reggaeton artist Jahzel.
Brand Analysis for reggaeton artist Jahzel.Brand Analysis for reggaeton artist Jahzel.
Brand Analysis for reggaeton artist Jahzel.
 
Miletti Gabriela_Vision Plan for artist Jahzel.pdf
Miletti Gabriela_Vision Plan for artist Jahzel.pdfMiletti Gabriela_Vision Plan for artist Jahzel.pdf
Miletti Gabriela_Vision Plan for artist Jahzel.pdf
 
K Venkat Naveen Kumar | GCP Data Engineer | CV
K Venkat Naveen Kumar | GCP Data Engineer | CVK Venkat Naveen Kumar | GCP Data Engineer | CV
K Venkat Naveen Kumar | GCP Data Engineer | CV
 
207095666-Book-Review-on-Ignited-Minds-Final.pptx
207095666-Book-Review-on-Ignited-Minds-Final.pptx207095666-Book-Review-on-Ignited-Minds-Final.pptx
207095666-Book-Review-on-Ignited-Minds-Final.pptx
 
Dating Call Girls inTiruvallur { 9332606886 } VVIP NISHA Call Girls Near 5 St...
Dating Call Girls inTiruvallur { 9332606886 } VVIP NISHA Call Girls Near 5 St...Dating Call Girls inTiruvallur { 9332606886 } VVIP NISHA Call Girls Near 5 St...
Dating Call Girls inTiruvallur { 9332606886 } VVIP NISHA Call Girls Near 5 St...
 
Joshua Minker Brand Exploration Sports Broadcaster .pptx
Joshua Minker Brand Exploration Sports Broadcaster .pptxJoshua Minker Brand Exploration Sports Broadcaster .pptx
Joshua Minker Brand Exploration Sports Broadcaster .pptx
 
Guide to a Winning Interview May 2024 for MCWN
Guide to a Winning Interview May 2024 for MCWNGuide to a Winning Interview May 2024 for MCWN
Guide to a Winning Interview May 2024 for MCWN
 
Simple, 3-Step Strategy to Improve Your Executive Presence (Even if You Don't...
Simple, 3-Step Strategy to Improve Your Executive Presence (Even if You Don't...Simple, 3-Step Strategy to Improve Your Executive Presence (Even if You Don't...
Simple, 3-Step Strategy to Improve Your Executive Presence (Even if You Don't...
 
怎样办理哥伦比亚大学毕业证(Columbia毕业证书)成绩单学校原版复制
怎样办理哥伦比亚大学毕业证(Columbia毕业证书)成绩单学校原版复制怎样办理哥伦比亚大学毕业证(Columbia毕业证书)成绩单学校原版复制
怎样办理哥伦比亚大学毕业证(Columbia毕业证书)成绩单学校原版复制
 
Top profile Call Girls In Agartala [ 7014168258 ] Call Me For Genuine Models ...
Top profile Call Girls In Agartala [ 7014168258 ] Call Me For Genuine Models ...Top profile Call Girls In Agartala [ 7014168258 ] Call Me For Genuine Models ...
Top profile Call Girls In Agartala [ 7014168258 ] Call Me For Genuine Models ...
 
Low Cost Coimbatore Call Girls Service 👉📞 6378878445 👉📞 Just📲 Call Ruhi Call ...
Low Cost Coimbatore Call Girls Service 👉📞 6378878445 👉📞 Just📲 Call Ruhi Call ...Low Cost Coimbatore Call Girls Service 👉📞 6378878445 👉📞 Just📲 Call Ruhi Call ...
Low Cost Coimbatore Call Girls Service 👉📞 6378878445 👉📞 Just📲 Call Ruhi Call ...
 
drug book file on obs. and gynae clinical pstings
drug book file on obs. and gynae clinical pstingsdrug book file on obs. and gynae clinical pstings
drug book file on obs. and gynae clinical pstings
 
B.tech Civil Engineering Major Project by Deepak Kumar ppt.pdf
B.tech Civil Engineering Major Project by Deepak Kumar ppt.pdfB.tech Civil Engineering Major Project by Deepak Kumar ppt.pdf
B.tech Civil Engineering Major Project by Deepak Kumar ppt.pdf
 
Top profile Call Girls In Rampur [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Rampur [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Rampur [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Rampur [ 7014168258 ] Call Me For Genuine Models We...
 
<DUBAI>Abortion pills IN UAE {{+971561686603*^Mifepristone & Misoprostol in D...
<DUBAI>Abortion pills IN UAE {{+971561686603*^Mifepristone & Misoprostol in D...<DUBAI>Abortion pills IN UAE {{+971561686603*^Mifepristone & Misoprostol in D...
<DUBAI>Abortion pills IN UAE {{+971561686603*^Mifepristone & Misoprostol in D...
 

Arman mashoori - Fit out Project Manager

  • 2. TABLE OF CONTENTS: Introduction Page 3 Personal Details Page 3 Summary of Experience Page 3 -5 Employers & Projects: Fino International Hyatt Regency Hotel & Apartments Page 6 -35 Louvre Abu Dhabi- Mock-up Building Page 36 -38 Bab Al Qasr Hotel & Serviced Apartments- Abu Dhabi Page 39 -42 Izel Restaurant & Bar at Conrad Hotel-Dubai Page 43 - 51 Sheikh Zayed Desert Learning Center (SZDLC)-Al Ain Page 52 -61 Dubai Metro (Red Line & Green Line ) Page 62 - 70 EC Harris International Dubai Industrial City (Warehouses & Labor Cities) Page 71 -72 Parkway International Contracting Dubai Marina Mall & Hotel Apartments Page 73 - 76 Palm Jumeirah Villas (Frond B) Page 77 - 84 References: Page 85 2
  • 3. Introduction: I am a talented, self-motivated and innovative civil engineer with more than 16 years of experience in successfully completing several prestigious projects such as Villas, High-Rise Buildings, Hotels, Restaurants, Shopping Malls, Museums & Industrial Complexes from conception through to hand over both in Civil & Fit out activities. Offer significant abilities in the areas of construction/project management, team leadership, planning and implementing of detailed work schedule and commissioning/handing over. Additionally, to achieve my desired outputs such as meet the Client’s core values and deadlines, optimize team work, provide & analyze construction reports and improvement of construction/project skills, I am eagerly committed to absorb as much information as possible from the relevant parties in order to produce solutions to potential and existing issues And consequently, to accomplish goals within the Time, Cost and Quality constraints. Being an effective well organized Fit out Project Manager with an outgoing and friendly nature, which allows me to interact and relate with all levels of staff ,I am able to bridge the gap between technical and non-technical members. Personal Details: Qualification: B.S. Civil Engineering, 1997 Date of Birth: 22-Nov-1973 Status: Married Nationality: Iranian Mobile: +97155 99 31 508 Email: armanmashoori@gmail.com Arman Mashoori Summary of Experience: As an active, Self-motivated Fit out Project Manager with more than 16 years experience, I have been responsible for ,but not limited to the following duties: 3
  • 4. 1. Arranging and advising the precautions related to Site Mobilization. 2. Liaise with Main contractor, Consultant and the Client to meet the planned deadlines. 3. Detailed Planning of Construction activities' sequences in relation with the Main Baseline Program of the project. 4. Achieving the early approval of the project's Specified/Alternative material in order to place the Purchase Orders and follow up on delivery of Material, Tools and Equipments especially for long lead items. 5. Closely coordinate with Technical/Design team to develop relevant drawings prior to the required approval from the Consultant. 6. Assisting the QA/QC and HSE Departments to Prepare, Submit and Receive the early approval on Method Statements, ITPs, Risk Assessments according to local Codes and Regulations. 7. Perform QA/QC and HSE functions of various activities, Implementation of precautionary procedures and preventive measures in compliance with the approved Specifications and Regulations. 8. Monitor and Supervision of Construction Tasks & Resources such as correct Procurement and Distribution of Material, Equipment and Manpower on daily basis. 9. Manage Direct and Indirect staff by assigning them tasks & monitoring their daily/weekly output as well as highlighting the areas of delay which requires action. 10. Prepare, Review and Analyze the construction activity reports. 11. Conducting Daily/Weekly Progress Meetings pertaining to various departments (e.g. Construction, Technical, Procurement) and preparing the related Minutes of Meetings in order to ensure that the project tasks are being successfully accomplished. 12. Analyze and monitor the Project's Commercial and Contractual aspects (e.g. Variation Orders, Official Site Instructions, Material Procurement) to achieve the ultimate efficiency within the identified Project Margin. 13. Prepare and review the required documents to submit the Interim/Final Payment Applications in accordance with the project's specified intervals. 14. Ensure Collection, Filing and archiving of the Project History in order to achieve a proper Snagging, De-snagging and Handing Over. Since most of my areas of expertise have been on Fit out Projects ,below are the main items which have been conducted within the mentioned projects: 4
  • 5. 5
  • 6. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Client: Wasl Properties Consultant/Engineer: RMJM Main Contractor: ABM Interior Designer: KCA Project Value: 54,000,000 AED Project Description: The Project is divided into Three Packages. Podium at 2nd Level, Presidential Suites on the top two levels of the Hotel Tower and Six Penthouses on the top two levels of the Apartment Tower. At Podium level, there are six Treatment Rooms with an additional two VIP Treatment Rooms and the related access Corridor, SPA Reception, SPA Manager and Consultant offices. Also Male/Female Changing areas next to the Swimming Pool, Public Toilets, Pool Deck Corridor and Lift Lobbies for Hotel Guests and Apartment residents. A separated GYM for Apartment residents, with a Female GYM and a Unisex GYM along with Exercise and Yoga zone, Lounge and Kids Club for Hotel Guests. Two Presidential Suites are in two level with different interior concepts. Each one includes a Master Bedroom ,two Bedrooms, Maid’s room, GYM & SPA area. Kitchen, Reception Lounge and Lift Lobby, Dinning Room, Main Lounge & Study area, Majliis and Main Corridor. Six Penthouses are available in different Four sizes.(One, Two, Three & Four Bedrooms). 6
  • 7. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Podium 7
  • 8. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Podium 8
  • 9. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Podium 9
  • 10. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Podium 10
  • 11. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Podium 11
  • 12. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Podium 12
  • 13. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Podium 13
  • 14. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Podium 14
  • 15. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Podium 15
  • 16. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Podium 16
  • 17. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Podium 17
  • 18. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Podium 18
  • 19. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Podium 19
  • 20. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Podium 20
  • 21. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Presidential Suites 21
  • 22. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Presidential Suites 22
  • 23. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Presidential Suites 23
  • 24. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Presidential Suites 24
  • 25. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Presidential Suites 25
  • 26. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Presidential Suites 26
  • 27. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Presidential Suites 27
  • 28. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Presidential Suites 28
  • 29. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Penthouse 29
  • 30. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Penthouse 30
  • 31. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Penthouse 31
  • 32. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Penthouse 32
  • 33. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Penthouse 33
  • 34. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Penthouse 34
  • 35. Hyatt Regency Hotel & Apartments Designation: Project Manager Duration: February 2014 to Present Penthouse 35
  • 36. Louvre Abu Dhabi- Mock-up Building Designation: Project Manager Duration: September 2013 to January 2014 Client: TDIC Project Management: Turner Consultant/Engineer: KEO Intl-Buro Happold Main Contractor: ASO JV Interior Designer: AJN Project Value: 12,000,000 AED Project Description: The Mock up Building is intended to reflect the Abu Dhabi Louvre Museum's Main Building design and the relevant Material which was designed by Mr. Jean Nouvel the renowned French Architect. Therefore, it was split into Two packages which are called “The Base Build & Museography . The Base Build package consists of Two levels of Administrative Areas, Main Entrance, Café, and Staircase. The Museography package consists of the Bronze Gallery and the Main Gallery . 36
  • 37. Louvre Abu Dhabi- Mock-up Building Designation: Project Manager Duration: September 2013 to January 2014 37
  • 38. Louvre Abu Dhabi- Mock-up Building Designation: Project Manager Duration: September 2013 to January 2014 38
  • 39. Bab Al Qasr Hotel and Services Apartments Designation: Construction Manager Duration: May 2013 to January 2014 Client: EMROC Project Management: Jacobs Consultant/Engineer: Surbana Main Contractor: Nurol Interior Designer: PSI Project Value: 150,000,000 AED Project Description: The Project is divided into Three Packages. Grand Lobby at Ground Floor, Hotel Tower and Serviced Apartment Tower. At Grand Lobby, there are unique staircases ,GRG patterned walls and Arched as well as Wooden Cladding up to almost 51 meter high. At Hotel Tower, there are a total of 412 Rooms categorized as detailed below: Presidential Suite 1 Executive Suite 30 Junior Suite 54 Superior King 85 Typical King 123 Typical Queen 4 Typical Twin 115 At Serviced Apartment Tower, there are a total of 265 Rooms categorized as detailed below: Penthouse 1 3 Bedroom 7 2 Bedroom 50 1 Bedroom 147 Studio 60 39
  • 40. Bab Al Qasr Hotel and Services Apartments Designation: Construction Manager Duration: May 2013 to January 2014 40
  • 41. Bab Al Qasr Hotel and Services Apartments Designation: Construction Manager Duration: May 2013 to January 2014 41
  • 42. Bab Al Qasr Hotel and Services Apartments Designation: Construction Manager Duration: May 2013 to January 2014 42
  • 43. IZEL Restaurant and Bar – Conrad Hotel Designation: Project Manager Duration: May 2012 to April 2013 Client: Private Property Management (PPM) Consultant/Engineer: Atkins Main Contractor: Arabtec/DCC JV Interior Designer: WA International Gross Area: 1700 m² Project Value: 12,000,000 AED Project Description: According to the language of the Mayan, IZEL means “Unique”. A culture which inspires this one-of-a-kind venue and experience, along with the “New Age” era where Latin American culture is globally styled. The Project is divided into three areas which are The Restaurant, The Bar and The Terrace and is located at 7th Floor of the newly built Conrad Hotel in Sheikh Zayed Road, Dubai. At the Restaurant Side, the ceiling is designed with Three Domes with very unique Chandeliers, VIP dinning room with a special lift lobby, for the guests, The Show Kitchen and DJ Boot as well as the Band stage. At Bar Side, the ceiling is built using three dimensional elements, The Main Bar, The Cigar Lounge and Display units and the main Lift Lobby with a Back lit Black & Gold Color Glass wall. 43
  • 44. IZEL Restaurant and Bar – Conrad Hotel Designation: Project Manager Duration: May 2012 to April 2013 44
  • 45. IZEL Restaurant and Bar – Conrad Hotel Designation: Project Manager Duration: May 2012 to April 2013 45
  • 46. IZEL Restaurant and Bar – Conrad Hotel Designation: Project Manager Duration: May 2012 to April 2013 46
  • 47. IZEL Restaurant and Bar – Conrad Hotel Designation: Project Manager Duration: May 2012 to April 2013 47
  • 48. IZEL Restaurant and Bar – Conrad Hotel Designation: Project Manager Duration: May 2012 to April 2013 48
  • 49. IZEL Restaurant and Bar – Conrad Hotel Designation: Project Manager Duration: May 2012 to April 2013 49
  • 50. IZEL Restaurant and Bar – Conrad Hotel Designation: Project Manager Duration: May 2012 to April 2013 50
  • 51. IZEL Restaurant and Bar – Conrad Hotel Designation: Project Manager Duration: May 2012 to April 2013 51
  • 52. Sheikh Zayed Desert Learning Centre Designation: Project Manager Duration: August 2011 to April 2012 Client: Al Ain Wildlife Park and Resort Consultant/Engineer/Architect: Chalabi Architects & Partners Structural Engineer: Bollinger Grohmann Schneider Main Contractor: Ed. Züblin AG Gross Area: 12,000 m² Project Value: 75,000,000 AED Project Description: The Sheikh Zayed Desert Learning Center is a phenomenal structure not only because of its unique design and finishes, but also for its green approaches. It is aiming to achieve LEED Platinum and Estidama 5 Pearls which are the highest achievable ratings for these green building systems. LEED is a system developed in the United States whereas Estidama is a local system (from Abu Dhabi) that focuses on green technologies and approaches related to the Arabian Gulf , with concentration on energy and water efficiency. Sheikh Zayed Desert Learning Center is the pilot project for Estidama v 1.0. The Sheikh Zayed Desert Learning Center is built with unique energy efficiency and water efficiency technologies. In addition, there is major focus on green materials for the building. In order to achieve the high ratings, the project teams sourced and installed regional materials, recycled content materials, low Volatile Organic Compound (VOC) adhesives, paints, carpets, composite wood and high SRI materials for the external cladding. The project is under very stringent waste diversion targets; all types of wastes are segregated on site and sent for recycling rather than landfill or incineration. As a finishing company contracted to complete interior and exterior work, FINO is contributing towards the achievement of the materials credits in SZDLC. Some of these are sourcing and using chemicals that have low volatile organic compound levels. This ensures that the indoor air quality is free of pollutants and toxic chemicals for the occupants of the building. In addition, the doors to be used on SZDLC are sourced from sustainable forestry. Wastes are sent back to manufacturers for recycling rather than disposal. The most important contributor towards the achievement of LEED and Estidama is the close coordination between all project team members. Openly discussing issues with our Clients, helps in meeting the requirements of these green building rating systems. With transparent communication, the purpose of these rating systems is met, as they encourage integrated development and holistic approach to construction. 52
  • 53. Sheikh Zayed Desert Learning Centre Designation: Project Manager Duration: August 2011 to April 2012 53
  • 54. Sheikh Zayed Desert Learning Centre Designation: Project Manager Duration: August 2011 to April 2012 54
  • 55. Sheikh Zayed Desert Learning Centre Designation: Project Manager Duration: August 2011 to April 2012 55
  • 56. Sheikh Zayed Desert Learning Centre Designation: Project Manager Duration: August 2011 to April 2012 56
  • 57. Sheikh Zayed Desert Learning Centre Designation: Project Manager Duration: August 2011 to April 2012 57
  • 58. Sheikh Zayed Desert Learning Centre Designation: Project Manager Duration: August 2011 to April 2012 58
  • 59. Sheikh Zayed Desert Learning Centre Designation: Project Manager Duration: August 2011 to April 2012 59
  • 60. Sheikh Zayed Desert Learning Centre Designation: Project Manager Duration: August 2011 to April 2012 60
  • 61. Sheikh Zayed Desert Learning Centre Designation: Project Manager Duration: August 2011 to April 2012 61
  • 62. Dubai Metro (Red Line & Green Line) Designation: Construction Manager Duration: May 2009 to July 2011 Client: Road & Transportation Authority (RTA) Consultant/Engineer: Atkins/ SYSTRA Main Contractor: Dubai Rapid Link Consortium (JTMJV) Project Value: 210,000,000 AED Project Description: The Project consist of Fitout Works of Two Metro Lines in Dubai ( Red & Green). At Metro Red Line, Our Scope was all Interior works of 28 Stations’ Entrance Pods and Foot Bridges. At Metro Green Line, Our Scope was Partial Interior works of 18 Stations and their Entrance Pods. 62
  • 63. Dubai Metro (Red Line & Green Line) Designation: Construction Manager Duration: May 2009 to July 2011 63
  • 64. Dubai Metro (Red Line & Green Line) Designation: Construction Manager Duration: May 2009 to July 2011 64
  • 65. Dubai Metro (Red Line & Green Line) Designation: Construction Manager Duration: May 2009 to July 2011 65
  • 66. Dubai Metro (Red Line & Green Line) Designation: Construction Manager Duration: May 2009 to July 2011 66
  • 67. Dubai Metro (Red Line & Green Line) Designation: Construction Manager Duration: May 2009 to July 2011 67
  • 68. Dubai Metro (Red Line & Green Line) Designation: Construction Manager Duration: May 2009 to July 2011 68
  • 69. Dubai Metro (Red Line & Green Line) Designation: Construction Manager Duration: May 2009 to July 2011 69
  • 70. Dubai Metro (Red Line & Green Line) Designation: Construction Manager Duration: May 2009 to July 2011 70
  • 71. Dubai Industrial City (DIC) Designation: Project Manager Duration: September 2008 to August 2009 Client: TATWEER Project Management: EC Harris International Consultant/Engineer: MEECON Main Contractor: Al Hamad Contracting Project Description: The Project consist of Civil works as well as Fit out Works of Five Labor Cities and Two Warehouse complexes at Dubai Industrial City . 71
  • 72. Dubai Industrial City (DIC) Designation: Project Manager Duration: September 2008 to August 2009 72
  • 73. Dubai Marina Mall & Hotel Apartments Designation: Construction Manager Duration: October 2007 to August 2008 Client: EMAAR Project Management: Hill International Consultant/Engineer: DP Architects Main Contractor: ALEC Project Value: 46,000,000 AED Project Description: The Project consist of Civil works as well as Fit out Works of All Parking Levels and Three Levels of the Shopping Mall. 73
  • 74. Dubai Marina Mall & Hotel Apartments Designation: Construction Manager Duration: October 2007 to August 2008 74
  • 75. Dubai Marina Mall & Hotel Apartments Designation: Construction Manager Duration: October 2007 to August 2008 75
  • 76. Dubai Marina Mall & Hotel Apartments Designation: Construction Manager Duration: October 2007 to August 2008 76
  • 77. Palm Jumeirah Villas Designation: Project Engineer Duration: August 2006 to September 2007 Client: Nakheel Project Management: Hill International Consultant/Engineer: KEO International Main Contractor: Parkway International Contracting Project Value: 257,000,000 AED Project Description: The Project consist of Three Fronds (A,B & P) ,218 luxury villas (G+1), varying in size, with a built up area from 350 sq.m to 700 sq.m. Our scope of works included the complete civil works, finishing, MEP works, swimming pools and landscaping (soft & hard). 77
  • 78. Palm Jumeirah Villas Designation: Project Engineer Duration: August 2006 to September 2007 78
  • 79. Palm Jumeirah Villas Designation: Project Engineer Duration: August 2006 to September 2007 79
  • 80. Palm Jumeirah Villas Designation: Project Engineer Duration: August 2006 to September 2007 80
  • 81. Palm Jumeirah Villas Designation: Project Engineer Duration: August 2006 to September 2007 81
  • 82. Palm Jumeirah Villas Designation: Project Engineer Duration: August 2006 to September 2007 82
  • 83. Palm Jumeirah Villas Designation: Project Engineer Duration: August 2006 to September 2007 83
  • 84. Palm Jumeirah Villas Designation: Project Engineer Duration: August 2006 to September 2007 84
  • 85. References: Company Name Name and Designation Contact Number Fino International Sufian Swaidan- Projects Director 050 252 5575 Fino International Douglas Gibbs- Contracts Manager 056 938 9908 EC Harris International Andrew Welsh-Senior Project Manager 050 553 5984 EC Harris International Darek Stokowski- Construction Manager 050 870 1323 Parkway International Contracting Tarek Al Zoabi-Managing Director 050 295 0116 Parkway International Contracting Mufid Al Zeir-General Manager 050 616 1597 85