SlideShare ist ein Scribd-Unternehmen logo
1 von 13
Downloaden Sie, um offline zu lesen
Amy Chen, Director of MWD Program
Imported Water Committee
March 26, 2015
 Cost of the Delta conveyance facility is within range
of urban and agricultural users capacity to pay
 On average, supply costs for the BDCP are
competitive to alternative supplies
2
 CVP contractors will need to develop
financing mechanism to fund their
share of BDCP, including creation of
take-or-pay contracts or rate
stabilization fund
3
“a number of important financing issues…will need to be resolved
before bonds could be issued to support construction of the BDCP
conveyance facility…”
Issuance of bonds:
“may not be representative of the many
smaller SWP and CVP contactors, most
notably CVP agricultural water users.”
Modeled four agencies:
“ability to pay for the BDCP-related costs depends
primarily upon their agricultural customers’ capacity to
absorb these higher water costs…”
Agricultural contractors:
“much higher for permanent crops and
vegetable crops and much lower for row crops.”
Capacity to Pay:
4
“Because so much
uncertainty remains as
to how costs will
actually be allocated
among water
contractors and their
customers, however,
all of the results
presented here
should be considered
preliminary and
illustrative.”
 Total estimated BDCP costs: $25 billion
 Water contractors’ share: $17 billion
 Cost allocation between SWP and CVP
 Two scenarios: 50/50, 60/40
 Three cases evaluated
 Base
 Costs and construction schedule, same as BDCP; 40-year
bond
 Best
 Capital costs 10% less than base; interest rates 1% lower
 Worst
 Capital costs 30% higher; interest rates 2% more
5
6
Base Case Best Case Worst Case
Total Peak Cost
Peak Contractor Cost ($2015) $909M $604M $1,359M
SWP Share
50/50 Split for SWP/CVP ($2015) $455M $302M $680M
60/40 Split for SWP/CVP ($2015) $546M $362M $816M
MWD Share (Table A)*
50/50 Split for SWP/CVP ($2015) $211M $140M $315M
60/40 Split for SWP/CVP ($2015) $253M $168M $378M
]
1. Source: MWD presentation from January 27, 2015
* MWD performed its own analysis in 2013, when that analysis is brought forward to 2015$, it
shows MWD share would be $250M under a 50/50 split or $299M under a 60/40 split
7
MWD Incremental BDCP Benefits (Based on Table A%) = 199,337AF1
Cost
Split
Base Case Best Case Worst
Case
MWD
Estimate2
MWD Share Peak
Annual Cost3
(2015$)
SWP:
60%
CVP:
40%
$253 M $168 M $378 M $299 M
MWD Cost/
BDCP Incremental
Benefit
$1,269/AF $843/AF $1,896/AF $1,500/AF
1. Based on data provided in MWD’s September 23, 2014 presentation, MWD’s calculated incremental BDCP
benefit is about 200,000 AF/Y on average, based on its Table A allocation
2. MWD's 2013 estimate (presented in 2014) displayed in 2015 $s
3. Costs shown differ from State Treasurer's Report: Nominal $ shown in State Treasurer's Report; 2015$ shown
in MWD PPT and here. Data shown can be found in MWD’s January 27, 2015 presentation
8
“Even if the CVP
contractors develop a new
credit with take-or-pay
obligations and similar
credit features to the DWR
bonds, it is not clear at this
point whether $10.25
billion of bonds (assuming
a 50/50 split) in the base
case could reasonably be
issued without a large rate
stabilization fund or other
credit enhancement or
subsidy from the federal
government, state
government or SWP
contractors.”
9
“..there are a number of
important risks…
Construction cost
overruns and
delays…Regulatory
uncertainty…if.. State
and federal funding for
habitat conservation is
not …forthcoming, the
ability to operate the
tunnels could be
jeopardized.. Climate
change…presents a
financing risk…”
10
 Important financing issues must be resolved
before bonds could be issued
 Certainty of revenue stream critical
 Debt service requirements for SWP contractors
 Need for CVP contractors to develop new credit to
finance their share
 State Treasurer’s Report is illustrative
11
12
13

Weitere ähnliche Inhalte

Andere mochten auch

BWT_Seawater_desalination_web
BWT_Seawater_desalination_webBWT_Seawater_desalination_web
BWT_Seawater_desalination_web
Thomas Larsen
 
{Ed1b3845 4477-45f9-80bd-807c64b69168} 201509-dw_ps_global_wr_wa_advanced_ro_...
{Ed1b3845 4477-45f9-80bd-807c64b69168} 201509-dw_ps_global_wr_wa_advanced_ro_...{Ed1b3845 4477-45f9-80bd-807c64b69168} 201509-dw_ps_global_wr_wa_advanced_ro_...
{Ed1b3845 4477-45f9-80bd-807c64b69168} 201509-dw_ps_global_wr_wa_advanced_ro_...
MODI20077
 

Andere mochten auch (12)

Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...
Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...
Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...
 
Energy Use and Pricing for Carlsbad Seawater Desalination
Energy Use and Pricing for Carlsbad Seawater DesalinationEnergy Use and Pricing for Carlsbad Seawater Desalination
Energy Use and Pricing for Carlsbad Seawater Desalination
 
Carlsbad Seawater Desalination Project Update
Carlsbad Seawater Desalination Project UpdateCarlsbad Seawater Desalination Project Update
Carlsbad Seawater Desalination Project Update
 
BWT_Seawater_desalination_web
BWT_Seawater_desalination_webBWT_Seawater_desalination_web
BWT_Seawater_desalination_web
 
Bay Delta Conservation Plan/California WaterFix
Bay Delta Conservation Plan/California WaterFixBay Delta Conservation Plan/California WaterFix
Bay Delta Conservation Plan/California WaterFix
 
Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...
Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...
Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...
 
Bay Delta Conservation Plan/California WaterFix
Bay Delta Conservation Plan/California WaterFixBay Delta Conservation Plan/California WaterFix
Bay Delta Conservation Plan/California WaterFix
 
2015-2016 Bay-Delta Workplan - February 26, 2015
2015-2016 Bay-Delta Workplan - February 26, 20152015-2016 Bay-Delta Workplan - February 26, 2015
2015-2016 Bay-Delta Workplan - February 26, 2015
 
Update on Supply Conditions and Drought Response Activities - September 24, 2015
Update on Supply Conditions and Drought Response Activities - September 24, 2015Update on Supply Conditions and Drought Response Activities - September 24, 2015
Update on Supply Conditions and Drought Response Activities - September 24, 2015
 
Update on Supply Conditions and Drought Response Activities
Update on Supply Conditions and Drought Response ActivitiesUpdate on Supply Conditions and Drought Response Activities
Update on Supply Conditions and Drought Response Activities
 
ASCE Seawater Desalination Project at Huntington Beach - Poseidon Water
ASCE Seawater Desalination Project at Huntington Beach - Poseidon WaterASCE Seawater Desalination Project at Huntington Beach - Poseidon Water
ASCE Seawater Desalination Project at Huntington Beach - Poseidon Water
 
{Ed1b3845 4477-45f9-80bd-807c64b69168} 201509-dw_ps_global_wr_wa_advanced_ro_...
{Ed1b3845 4477-45f9-80bd-807c64b69168} 201509-dw_ps_global_wr_wa_advanced_ro_...{Ed1b3845 4477-45f9-80bd-807c64b69168} 201509-dw_ps_global_wr_wa_advanced_ro_...
{Ed1b3845 4477-45f9-80bd-807c64b69168} 201509-dw_ps_global_wr_wa_advanced_ro_...
 

Ähnlich wie State Treasurer's Assessment of the Affordability and Financing Considerations of the Bay Delta Conveyance Facility - March 26, 2015

Ch9-Lecture 2018 (2).ppt
Ch9-Lecture 2018 (2).pptCh9-Lecture 2018 (2).ppt
Ch9-Lecture 2018 (2).ppt
4723bilal
 
ET April 2023 Investor Presentation_Final.pdf
ET April 2023 Investor Presentation_Final.pdfET April 2023 Investor Presentation_Final.pdf
ET April 2023 Investor Presentation_Final.pdf
ssuser6f254f1
 
Q3 2014 Growth Initiatives Update
Q3 2014 Growth Initiatives UpdateQ3 2014 Growth Initiatives Update
Q3 2014 Growth Initiatives Update
EnLinkMidstreamLLC
 

Ähnlich wie State Treasurer's Assessment of the Affordability and Financing Considerations of the Bay Delta Conveyance Facility - March 26, 2015 (20)

Bay-Delta Conservation Plan: Preliminary Assessment of Financing Risk Paramet...
Bay-Delta Conservation Plan: Preliminary Assessment of Financing Risk Paramet...Bay-Delta Conservation Plan: Preliminary Assessment of Financing Risk Paramet...
Bay-Delta Conservation Plan: Preliminary Assessment of Financing Risk Paramet...
 
Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...
Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...
Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...
 
Corporate presentation 1 q 15 s.a vf
Corporate presentation 1 q 15 s.a vfCorporate presentation 1 q 15 s.a vf
Corporate presentation 1 q 15 s.a vf
 
Ch9-Lecture 2018 (2).ppt
Ch9-Lecture 2018 (2).pptCh9-Lecture 2018 (2).ppt
Ch9-Lecture 2018 (2).ppt
 
RBC Capital Markets MLP Conference
RBC Capital Markets MLP ConferenceRBC Capital Markets MLP Conference
RBC Capital Markets MLP Conference
 
WELLS FARGO SECURITIES RESEARCH, ECONOMICS AND STRATEGY 2014 ENERGY SYMPOSIUM
WELLS FARGO SECURITIES RESEARCH, ECONOMICS AND STRATEGY 2014 ENERGY SYMPOSIUMWELLS FARGO SECURITIES RESEARCH, ECONOMICS AND STRATEGY 2014 ENERGY SYMPOSIUM
WELLS FARGO SECURITIES RESEARCH, ECONOMICS AND STRATEGY 2014 ENERGY SYMPOSIUM
 
Electric Vehicles Cost/Benefit Analysis by Dick Wanderscheid
Electric Vehicles Cost/Benefit Analysis by Dick WanderscheidElectric Vehicles Cost/Benefit Analysis by Dick Wanderscheid
Electric Vehicles Cost/Benefit Analysis by Dick Wanderscheid
 
The Financial Condition of the Pension Benefit Guaranty Corporation’s Multiem...
The Financial Condition of the Pension Benefit Guaranty Corporation’s Multiem...The Financial Condition of the Pension Benefit Guaranty Corporation’s Multiem...
The Financial Condition of the Pension Benefit Guaranty Corporation’s Multiem...
 
ET April 2023 Investor Presentation_Final.pdf
ET April 2023 Investor Presentation_Final.pdfET April 2023 Investor Presentation_Final.pdf
ET April 2023 Investor Presentation_Final.pdf
 
Open Door Forum: Next Generation ACO Model - Financial Methodology and Relate...
Open Door Forum: Next Generation ACO Model - Financial Methodology and Relate...Open Door Forum: Next Generation ACO Model - Financial Methodology and Relate...
Open Door Forum: Next Generation ACO Model - Financial Methodology and Relate...
 
Anatomy of a Cost Estimate for Legislation Funding Transportation Programs
Anatomy of a Cost Estimate for Legislation Funding Transportation ProgramsAnatomy of a Cost Estimate for Legislation Funding Transportation Programs
Anatomy of a Cost Estimate for Legislation Funding Transportation Programs
 
Corporate presentation 4 q 14 sa
Corporate presentation 4 q 14 saCorporate presentation 4 q 14 sa
Corporate presentation 4 q 14 sa
 
Citi MLP / Midstream Infrastructure Conference
Citi MLP / Midstream Infrastructure ConferenceCiti MLP / Midstream Infrastructure Conference
Citi MLP / Midstream Infrastructure Conference
 
Goldman Sachs Power, Utilities, MLP & Pipeline Conference
Goldman Sachs Power, Utilities, MLP & Pipeline ConferenceGoldman Sachs Power, Utilities, MLP & Pipeline Conference
Goldman Sachs Power, Utilities, MLP & Pipeline Conference
 
Citi conference presentation final - 8.20.14
Citi conference presentation   final - 8.20.14Citi conference presentation   final - 8.20.14
Citi conference presentation final - 8.20.14
 
Am website presentation september 2015
Am website presentation   september 2015Am website presentation   september 2015
Am website presentation september 2015
 
RBC Capital Markets MLP Conference 2015
RBC Capital Markets MLP Conference 2015RBC Capital Markets MLP Conference 2015
RBC Capital Markets MLP Conference 2015
 
2015 Jefferies Energy Conference
2015 Jefferies Energy Conference2015 Jefferies Energy Conference
2015 Jefferies Energy Conference
 
Recommended Changes to Downers Grove Stormwater Utility
Recommended Changes to Downers Grove Stormwater UtilityRecommended Changes to Downers Grove Stormwater Utility
Recommended Changes to Downers Grove Stormwater Utility
 
Q3 2014 Growth Initiatives Update
Q3 2014 Growth Initiatives UpdateQ3 2014 Growth Initiatives Update
Q3 2014 Growth Initiatives Update
 

Mehr von San Diego County Water Authority

Mehr von San Diego County Water Authority (14)

Session 2 presentation
Session 2 presentationSession 2 presentation
Session 2 presentation
 
Update on Supply Conditions and Drought Response Activities - June 25, 2015
Update on Supply Conditions and Drought Response Activities - June 25, 2015 Update on Supply Conditions and Drought Response Activities - June 25, 2015
Update on Supply Conditions and Drought Response Activities - June 25, 2015
 
Update on Supply Conditions and Drought Response Activities - October 22, 2015
Update on Supply Conditions and Drought Response Activities - October 22, 2015Update on Supply Conditions and Drought Response Activities - October 22, 2015
Update on Supply Conditions and Drought Response Activities - October 22, 2015
 
Update on Supply Conditions and Drought Response Activities - December 10, 2015
Update on Supply Conditions and Drought Response Activities - December 10, 2015Update on Supply Conditions and Drought Response Activities - December 10, 2015
Update on Supply Conditions and Drought Response Activities - December 10, 2015
 
Update on Supply Conditions and Drought Response Activities - August 27, 2015
Update on Supply Conditions and Drought Response Activities - August 27, 2015Update on Supply Conditions and Drought Response Activities - August 27, 2015
Update on Supply Conditions and Drought Response Activities - August 27, 2015
 
Water Supply and Drought Management Update - Feb. 26, 2015
Water Supply and Drought Management Update - Feb. 26, 2015Water Supply and Drought Management Update - Feb. 26, 2015
Water Supply and Drought Management Update - Feb. 26, 2015
 
Update on Water Supply Conditions and Drought Response Activities - March 26,...
Update on Water Supply Conditions and Drought Response Activities - March 26,...Update on Water Supply Conditions and Drought Response Activities - March 26,...
Update on Water Supply Conditions and Drought Response Activities - March 26,...
 
Water Supply and Drought Management Update - Nov. 20, 2014
Water Supply and Drought Management Update - Nov. 20, 2014Water Supply and Drought Management Update - Nov. 20, 2014
Water Supply and Drought Management Update - Nov. 20, 2014
 
Water Supply and Drought Managment Update - Oct. 23, 2014
Water Supply and Drought Managment Update - Oct. 23, 2014Water Supply and Drought Managment Update - Oct. 23, 2014
Water Supply and Drought Managment Update - Oct. 23, 2014
 
Water Supply and Drought Management Update - Jan. 22, 2015
Water Supply and Drought Management Update - Jan. 22, 2015Water Supply and Drought Management Update - Jan. 22, 2015
Water Supply and Drought Management Update - Jan. 22, 2015
 
Water Supply and Drought Managment Update - Sept. 25, 2014
Water Supply and Drought Managment Update - Sept. 25, 2014Water Supply and Drought Managment Update - Sept. 25, 2014
Water Supply and Drought Managment Update - Sept. 25, 2014
 
Water Supply and Drought Managment Update - Aug. 28, 2014
Water Supply and Drought Managment Update - Aug. 28, 2014Water Supply and Drought Managment Update - Aug. 28, 2014
Water Supply and Drought Managment Update - Aug. 28, 2014
 
Water Reuse Coalition
Water Reuse CoalitionWater Reuse Coalition
Water Reuse Coalition
 
Pure Water San Diego
Pure Water San DiegoPure Water San Diego
Pure Water San Diego
 

Kürzlich hochgeladen

Call Girls In datia Escorts ☎️7427069034 🔝 💃 Enjoy 24/7 Escort Service Enjoy...
Call Girls In datia Escorts ☎️7427069034  🔝 💃 Enjoy 24/7 Escort Service Enjoy...Call Girls In datia Escorts ☎️7427069034  🔝 💃 Enjoy 24/7 Escort Service Enjoy...
Call Girls In datia Escorts ☎️7427069034 🔝 💃 Enjoy 24/7 Escort Service Enjoy...
nehasharma67844
 
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Chandigarh Call girls 9053900678 Call girls in Chandigarh
 

Kürzlich hochgeladen (20)

PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORSPPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
 
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
 
A PPT on digital India initiative by Government of India
A PPT on digital India initiative by Government of IndiaA PPT on digital India initiative by Government of India
A PPT on digital India initiative by Government of India
 
1935 CONSTITUTION REPORT IN RIPH FINALLS
1935 CONSTITUTION REPORT IN RIPH FINALLS1935 CONSTITUTION REPORT IN RIPH FINALLS
1935 CONSTITUTION REPORT IN RIPH FINALLS
 
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
 
Call Girls In datia Escorts ☎️7427069034 🔝 💃 Enjoy 24/7 Escort Service Enjoy...
Call Girls In datia Escorts ☎️7427069034  🔝 💃 Enjoy 24/7 Escort Service Enjoy...Call Girls In datia Escorts ☎️7427069034  🔝 💃 Enjoy 24/7 Escort Service Enjoy...
Call Girls In datia Escorts ☎️7427069034 🔝 💃 Enjoy 24/7 Escort Service Enjoy...
 
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdf
 
Scaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP processScaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP process
 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'
 
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
 
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)
 
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
 
Finance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCCFinance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCC
 
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
 
Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...
Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...
Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...
 
The NAP process & South-South peer learning
The NAP process & South-South peer learningThe NAP process & South-South peer learning
The NAP process & South-South peer learning
 
TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...
TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...
TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...
 

State Treasurer's Assessment of the Affordability and Financing Considerations of the Bay Delta Conveyance Facility - March 26, 2015

  • 1. Amy Chen, Director of MWD Program Imported Water Committee March 26, 2015
  • 2.  Cost of the Delta conveyance facility is within range of urban and agricultural users capacity to pay  On average, supply costs for the BDCP are competitive to alternative supplies 2  CVP contractors will need to develop financing mechanism to fund their share of BDCP, including creation of take-or-pay contracts or rate stabilization fund
  • 3. 3 “a number of important financing issues…will need to be resolved before bonds could be issued to support construction of the BDCP conveyance facility…” Issuance of bonds: “may not be representative of the many smaller SWP and CVP contactors, most notably CVP agricultural water users.” Modeled four agencies: “ability to pay for the BDCP-related costs depends primarily upon their agricultural customers’ capacity to absorb these higher water costs…” Agricultural contractors: “much higher for permanent crops and vegetable crops and much lower for row crops.” Capacity to Pay:
  • 4. 4 “Because so much uncertainty remains as to how costs will actually be allocated among water contractors and their customers, however, all of the results presented here should be considered preliminary and illustrative.”
  • 5.  Total estimated BDCP costs: $25 billion  Water contractors’ share: $17 billion  Cost allocation between SWP and CVP  Two scenarios: 50/50, 60/40  Three cases evaluated  Base  Costs and construction schedule, same as BDCP; 40-year bond  Best  Capital costs 10% less than base; interest rates 1% lower  Worst  Capital costs 30% higher; interest rates 2% more 5
  • 6. 6 Base Case Best Case Worst Case Total Peak Cost Peak Contractor Cost ($2015) $909M $604M $1,359M SWP Share 50/50 Split for SWP/CVP ($2015) $455M $302M $680M 60/40 Split for SWP/CVP ($2015) $546M $362M $816M MWD Share (Table A)* 50/50 Split for SWP/CVP ($2015) $211M $140M $315M 60/40 Split for SWP/CVP ($2015) $253M $168M $378M ] 1. Source: MWD presentation from January 27, 2015 * MWD performed its own analysis in 2013, when that analysis is brought forward to 2015$, it shows MWD share would be $250M under a 50/50 split or $299M under a 60/40 split
  • 7. 7 MWD Incremental BDCP Benefits (Based on Table A%) = 199,337AF1 Cost Split Base Case Best Case Worst Case MWD Estimate2 MWD Share Peak Annual Cost3 (2015$) SWP: 60% CVP: 40% $253 M $168 M $378 M $299 M MWD Cost/ BDCP Incremental Benefit $1,269/AF $843/AF $1,896/AF $1,500/AF 1. Based on data provided in MWD’s September 23, 2014 presentation, MWD’s calculated incremental BDCP benefit is about 200,000 AF/Y on average, based on its Table A allocation 2. MWD's 2013 estimate (presented in 2014) displayed in 2015 $s 3. Costs shown differ from State Treasurer's Report: Nominal $ shown in State Treasurer's Report; 2015$ shown in MWD PPT and here. Data shown can be found in MWD’s January 27, 2015 presentation
  • 8. 8 “Even if the CVP contractors develop a new credit with take-or-pay obligations and similar credit features to the DWR bonds, it is not clear at this point whether $10.25 billion of bonds (assuming a 50/50 split) in the base case could reasonably be issued without a large rate stabilization fund or other credit enhancement or subsidy from the federal government, state government or SWP contractors.”
  • 9. 9 “..there are a number of important risks… Construction cost overruns and delays…Regulatory uncertainty…if.. State and federal funding for habitat conservation is not …forthcoming, the ability to operate the tunnels could be jeopardized.. Climate change…presents a financing risk…”
  • 10. 10
  • 11.  Important financing issues must be resolved before bonds could be issued  Certainty of revenue stream critical  Debt service requirements for SWP contractors  Need for CVP contractors to develop new credit to finance their share  State Treasurer’s Report is illustrative 11
  • 12. 12
  • 13. 13