8. Multitasking Is Killing Productivity Task A Task B Process Time A Process Time B Elapsed Time A Elapsed Time B A/4 A/4 A/4 A/4 B/4 B/4 B/4 B/4
9. Additional Damage Task A Task B Process Time A Process Time B Elapsed Time A Elapsed Time B Mental setup penalty A/4 A/4 A/4 A/4 B/4 B/4 B/4 B/4
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24. Variation And The Parallel WBS Component Start Project Start Component Start 70 For seven tasks only For four tasks only For four tasks only Task 8 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10
32. Buffer Management (TOC) Project Buffer 1.0 .5 Project Schedule 0.0 Project Start Date Project End Date “ SHIFT happens!!!” Protection Ratio = Remaining Buffer/Required Buffer PR
33.
34. Portfolio View From cc-Pulse 30 13 7 7 7 7 7 93 135 168 210 252 301 6 61 52 70 76 86 100 25.5 PR=114% PR=14% PR=136% PR=78% PR=89% PR=90% PR=100% 9-Sep-03 23-Sep-03 7-Oct-03 21-Oct-03 4-Nov-03 18-Nov-03 2-Dec-03 16-Dec-03 30-Dec-03 13-Jan-04 27-Jan-04 10-Feb-04 24-Feb-04 9-Mar-04 23-Mar-04 6-Apr-04 20-Apr-04 4-May-04 18-May-04 1-Jun-04 15-Jun-04 29-Jun-04 13-Jul-04 27-Jul-04 10-Aug-04 24-Aug-04 7-Sep-04 21-Sep-04 5-Oct-04 19-Oct-04 2-Nov-04 16-Nov-04 30-Nov-04 Test 2 PB protecting z Youth Center PB protecting End Of Project 5 Buffers.mpp PB protecting System I&T 5 Buffers.mpp PB protecting System I&T 5 Buffers.mpp PB protecting System I&T 5 Buffers.mpp PB protecting System I&T 5 Buffers.mpp PB protecting System I&T Completed Duration Remaining Duration Buffer Remaining Portfolio Name: Master Schedule 10/14/2003 Report Date List of deliverable names, hyperlinked to corresponding time histories of remaining duration. Time of this report. Elapsed time for this deliverable. Duration remaining for this deliverable. Expected completion for this deliverable, as of the date of this report. Protection Ration, as of the date of this report.