Points and Crossings
srinivas
Outline
• Turnout
• Types
– Left hand
– Right Hand
• Components
• Points and Switches
• Crossings
Turnout
• In case of roads – vehicles move in any
direction
• Trains - not possible at will to change the
direction
• Change is made possible with the provision of
turnouts
• Consists of points and crossings.
• Information sent to loco pilot using signals.
Turnout - Definition
• Simple arrangement of points and crossings by
the manipulation of which the train from one
track may be diverted to the another track or
branch line or to siding is known as turnout.
• 2 tracks either merge or diverge, or 2 tracks
parallel to each other but are still connected
to each other- This connection helps in
changing the direction of trains.
• for this points and crossings are used.
Turnouts
• The combination of lead rails with curved rails
(and fastenings) helps in diverting rolling stock
from one track to another track.
• Rails depending on curvature
– Lead rails are straight
– Curved rails have curvature
• Turnouts are also provided in yards and
sidings
Turnouts and Problems
• Some problems exist
• Weakest points on the track due to joints and
fastenings. Safety becomes main concern in
design
• Retards the movement of the trains
Types of Turnouts
• Depending on direction of movement of trains
from main tracks
– Left hand turnout
– Right hand turnout
Constituents of turnout
Component Parts of a Turnout
1. A pair of tongue rails
2. A pair of stock rails
3. Two check rails
4. Four lead rails
5. A Vee crossing
6. Slide chairs
7. Stretcher bar
8. A pair of heel blocks
9. Switch tie plate or gauge
10. Parts for operating points-
Rods, cranks, levers etc
11. Locking system which
includes locking box, lock
bar, plunger bar etc
• Facing direction:
– Standing at switch and looking towards crossing
• Trailing direction:
– Standing at crossing and looking towards switches
• Points:
– A pair of tongue rails with stock rails
– Train diverting from the main track will negotiate
these points first.
• Tongue Rail:
– It is a tapered movable rail, made of high-carbon
or -manganese steel to withstand wear.
– At its thicker end, it is attached to a running rail.
– A tongue rail is also called a switch rail.
• Stock Rail:
– It is the running rail against which a tongue rail
operates.
• Switch angle:
– angle between the gauge face of the stock rail and
tongue rail at the theoretical toe of switch.
• Throw of switch:
– Distance by which the tongue rail moves laterally
at the toe of switch
• Crossing:
– A crossing is a device introduced at the junction
where two rails cross each other to permit the
wheel flange of a railway vehicle to pass from one
track to another.
Switches - Components
• A set of points or switches consists of the
following main constituents
– A pair of stock rails
– A pair of tongue rails
• also known as switch rails, made of medium-
manganese steel to withstand wear. The tongue rails
are machined to a very thin section to obtain a snug fit
with the stock rail. The tapered end of the tongue rail is
called the toe and the thicker end is called the heel.
Switches
– A pair of heel blocks which hold the heel of the
tongue rails is held at the standard clearance or
distance from the stock rails.
– A number of slide chairs to support the tongue rail
and enable its movement towards or away from the
stock rail.
– Two or more stretcher bars connecting both the
tongue rails close to the toe, for the purpose of
holding them at a fixed distance from each other
– A gauge tie plate to fix gauges and ensure correct
gauge at the points.
Types of Switches
• Two types
– Stud switch
• no separate tongue rail is provided and some portion of
the track is moved from one side to the other side
– Split switch
• These consist of a pair of stock rails and a pair of
tongue rails
• These are 2 types
– loose heel type
– Fixed heel type
• Loose heel type:
– In this type of split switch, the switch or tongue
rail finishes at the heel of the switch to enable
movement of the free end of the tongue rail.
– The fish plates holding the tongue rail may be
straight or slightly bent.
– The tongue rail is fastened to the stock rail with
the help of a fishing fit block and four bolts.
– The fish bolts in the lead rail are tightened while
those in the tongue rail are kept loose or snug to
allow free movement of the tongue
– As the discontinuity of the track at the heel is a
weakness in the structure, the use of these
switches is not preferred.
• Fixed heel type:
– In this type of split switch, the tongue rail does
not end at the heel of the switch but extends
further and is rigidly connected.
– The movement at the toe of the switch is made
possible on account of the flexibility of the tongue
rail.
Based on Toe of Switches
• Undercut switch
– The foot of the stock rail is planed to accommodate the
tongue rail
• Straight cut switch
– Tongue rail is cut straight along the stock rail to increase
thickness at toe.
• Over riding switch
– Stock rail occupies the full section and the tongue rail is
planed to a 6mm thick edge which overrides the foot of
stock rail
– Switch rail is kept 6mm higher than the stock rail from the
heel to the point towards the toe where planning starts
– Eliminates the possibility of splitting which might be caused
by the movement of false flange in the trailing direction
– Stock rail is uncut, hence more stronger
– manufacturing work is confined only to tongue
rail, which is very economical
– Tongue rail supported by stock rail, hence
combined strength of rails between sleepers is
greater than that of tongue rail alone in the case
of undercut switch.
– These overriding switches are standardized and
used in IR.
Crossings
• A crossing or frog is a device introduced at the
point where two gauge faces cross each other
to permit the flanges of a railway vehicle to
pass from one track to another.
• A gap is provided from throw to the nose of
crossing
• Check rails assures the correct movement and
guides the wheels properly.
Crossing - Components
• 2 Rails – Point rail, Splice rail are joined
• These are machined to form a nose.
• The point rail has its fine end slightly cut off to form a
blunt nose, with a thickness of 6 mm (1/4").
• The toe of the blunt nose is called the actual nose of
crossing (ANC) and the theoretical point where gauge
faces from both sides intersect is called the
theoretical nose of crossing (TNC).
• The ‘V’ rail is planed to a depth of 6 mm (1/4") at the nose
and runs out in 89 mm to stop a wheel running in the
facing direction from hitting the nose.
Crossings - Components
• Two wing rails consisting of a right-hand and a
left-hand wing rail that converge to form a
throat and diverge again on either side of the
nose.
• Wing rails are flared at the ends to facilitate
the entry and exit of the flanged wheel in the
gap.
• A pair of check rails are used to guide the
wheels
Crossing - Types
• Based on the angle of crossing
– Acute angle crossing: (or V crossing)
• 2 rail gauge faces cross at acute angle
– Obtuse angle or Diamond crossing
• 2 gauge faces meet at obtuse angle
– Square crossing
• Two tracks cross at right angles
Crossings - Types
• For manufacturing purposes
– Built up crossing:
• 2 wing rails, a V section consisting of point and splice
rails are assembled together by means of bolts and
distance blocks to form a crossing.
• Low cost
• Easy to place and repair.
• Bolts require frequent checking.
• If wear is more than 10mm renewal required.
Crossings - Types
– Cast steel crossing:
• One piece crossing with no bolts and require little
maintenance.
• More rigid as it is one single piece.
• High initial cost
• High maintenance cost
• Replaced by Cast Manganese Steel crossings these days
– Combined rail and cast crossing
• Combination of built up and cast steel crossing
• Consists of a cast steel nose finished to ordinary rail
faces
Crossing - Types
• CMS Crossings
– Due to heavy loads and traffic, normal manganese
rails are quickly wearing out
– CMS crossings possess high strength, high resistance
to wear, longer life.
– Avg life of CMS crossing is 4 times that of built up
crossing
– CMS crossings are free from bolts and other
components which normally get loose as a result of
traffic.
– High initial cost, but less maintenance
– Standardized in Indian Railways
Crossing- Types
• According to Diversion:
– In a spring crossing, one wing rail is movable and
is held against the V of the crossing with a strong
helical spring while the other wing rail is fixed.
Crossings:
Crossover Crossing
Function of this crossing is to
connect two parallel
or diverging tracks.
According to Diversion
Crossings:
Crossover
Crossing
Crossings:
Scissors Crossing(Double cross):
This type of crossing consists
4 pair of switch
6 Acute crossings
2 Obtuse crossings
check rails
And this type is use at goods yard.
According to Diversion
Crossings:
Double cross
Crossings:
Diamond Crossing
When two tracks crosses each
other at less than 90 angle then
it forms diamond shape so it
is called Diamond Crossing
According to Diversion
Crossings:
Diamond Crossing
Crossings:
Diamond Crossing
Crossings:
Gathering Lines:
When there is more than
two track divert from one
line then it is called
Gathering lines.
According to Diversion

Weitere ähnliche Inhalte

Was ist angesagt?

Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )
mohit kumar panchal
 

Was ist angesagt? (20)

Railway Planning - Unit 1
Railway Planning - Unit 1Railway Planning - Unit 1
Railway Planning - Unit 1
 
Stations and Yards of Railway
Stations and Yards of RailwayStations and Yards of Railway
Stations and Yards of Railway
 
11.track junctions and layouts
11.track junctions and layouts11.track junctions and layouts
11.track junctions and layouts
 
Chapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway trackChapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway track
 
Railway engg geometric design
Railway engg geometric designRailway engg geometric design
Railway engg geometric design
 
Railway Track Maintenance
Railway Track  MaintenanceRailway Track  Maintenance
Railway Track Maintenance
 
Cross Section of Permanent Way.pdf
Cross Section of Permanent Way.pdfCross Section of Permanent Way.pdf
Cross Section of Permanent Way.pdf
 
5.track or permanent way and track stresses
5.track or permanent way and track stresses5.track or permanent way and track stresses
5.track or permanent way and track stresses
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
 
Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )
 
PERMANANT WAY
PERMANANT WAYPERMANANT WAY
PERMANANT WAY
 
modern methods of railway track maintanence
modern methods of railway track maintanencemodern methods of railway track maintanence
modern methods of railway track maintanence
 
Signalling and Interlocking
Signalling and InterlockingSignalling and Interlocking
Signalling and Interlocking
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
Coning of Wheels in Railways & Rail Creep
Coning of Wheels in Railways & Rail CreepConing of Wheels in Railways & Rail Creep
Coning of Wheels in Railways & Rail Creep
 
Railway track construction, drainage & maintenence
Railway track  construction, drainage & maintenenceRailway track  construction, drainage & maintenence
Railway track construction, drainage & maintenence
 
Fittings and Fastenings of Rails.pdf
Fittings and Fastenings of Rails.pdfFittings and Fastenings of Rails.pdf
Fittings and Fastenings of Rails.pdf
 
Geometric design of the track
Geometric design of the trackGeometric design of the track
Geometric design of the track
 
Rail fastenings and joints
Rail fastenings and jointsRail fastenings and joints
Rail fastenings and joints
 
Railway station and YARD
Railway station and YARD Railway station and YARD
Railway station and YARD
 

Andere mochten auch

Railway transportation 2.1
Railway transportation 2.1Railway transportation 2.1
Railway transportation 2.1
Hasan Gunes
 
Topic%20 compression
Topic%20 compressionTopic%20 compression
Topic%20 compression
Saleem Malik
 

Andere mochten auch (20)

Points and crossing
Points and crossingPoints and crossing
Points and crossing
 
Railway Engineering-Curves and superelevation
Railway Engineering-Curves and superelevationRailway Engineering-Curves and superelevation
Railway Engineering-Curves and superelevation
 
Rail Deflection
Rail DeflectionRail Deflection
Rail Deflection
 
Railway Engineering - Geometric design of track
Railway Engineering - Geometric design of trackRailway Engineering - Geometric design of track
Railway Engineering - Geometric design of track
 
Points and crossings ( special assigments )
Points and crossings ( special assigments )Points and crossings ( special assigments )
Points and crossings ( special assigments )
 
Surface runoff
Surface runoffSurface runoff
Surface runoff
 
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
 
Introduction to ground water hydrology
Introduction to ground water hydrologyIntroduction to ground water hydrology
Introduction to ground water hydrology
 
Geometric desing of railway track
Geometric desing of railway trackGeometric desing of railway track
Geometric desing of railway track
 
Water cycle and water budget
Water cycle and water budgetWater cycle and water budget
Water cycle and water budget
 
Stream flow measurement
Stream flow measurementStream flow measurement
Stream flow measurement
 
Precipitation and its estimation
Precipitation and its estimationPrecipitation and its estimation
Precipitation and its estimation
 
Station yards
Station yardsStation yards
Station yards
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
2 handouts-lecture-7
2  handouts-lecture-72  handouts-lecture-7
2 handouts-lecture-7
 
Floods
FloodsFloods
Floods
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
Railway transportation 2.1
Railway transportation 2.1Railway transportation 2.1
Railway transportation 2.1
 
Railway track:An Introduction
Railway track:An IntroductionRailway track:An Introduction
Railway track:An Introduction
 
Topic%20 compression
Topic%20 compressionTopic%20 compression
Topic%20 compression
 

Ähnlich wie Points and crossings

Points, Crossings and Turnouts of Railways.pptx
Points, Crossings and Turnouts of Railways.pptxPoints, Crossings and Turnouts of Railways.pptx
Points, Crossings and Turnouts of Railways.pptx
dshah162002
 
POINTS AND CROSSINGS (1) FINAL.pptx
POINTS AND CROSSINGS (1) FINAL.pptxPOINTS AND CROSSINGS (1) FINAL.pptx
POINTS AND CROSSINGS (1) FINAL.pptx
ShruthiBS13
 
Railway and Airport Engineering
Railway and Airport EngineeringRailway and Airport Engineering
Railway and Airport Engineering
Emaan Sharma
 

Ähnlich wie Points and crossings (20)

Points and crossings.ppt
Points and crossings.pptPoints and crossings.ppt
Points and crossings.ppt
 
Railway engineering part3
Railway engineering part3Railway engineering part3
Railway engineering part3
 
Points, Crossings and Turnouts of Railways.pptx
Points, Crossings and Turnouts of Railways.pptxPoints, Crossings and Turnouts of Railways.pptx
Points, Crossings and Turnouts of Railways.pptx
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
1Point & crossing.pdf
1Point & crossing.pdf1Point & crossing.pdf
1Point & crossing.pdf
 
Railway Engineering: Turnouts
Railway Engineering: TurnoutsRailway Engineering: Turnouts
Railway Engineering: Turnouts
 
POINTS AND CROSSINGS (1) FINAL.pptx
POINTS AND CROSSINGS (1) FINAL.pptxPOINTS AND CROSSINGS (1) FINAL.pptx
POINTS AND CROSSINGS (1) FINAL.pptx
 
Railway and Airport Engineering
Railway and Airport EngineeringRailway and Airport Engineering
Railway and Airport Engineering
 
Points and Crossings
Points and Crossings Points and Crossings
Points and Crossings
 
Design of Transmission Systems
Design of Transmission SystemsDesign of Transmission Systems
Design of Transmission Systems
 
1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptx1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptx
 
MODULE-II INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-II INFRASTRUCTURE ENGINEERING BTCVC702MODULE-II INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-II INFRASTRUCTURE ENGINEERING BTCVC702
 
Unit 1 gauge creep
Unit 1 gauge creepUnit 1 gauge creep
Unit 1 gauge creep
 
Chapter 1 introductution to railway and permanent way
Chapter 1 introductution to railway and permanent wayChapter 1 introductution to railway and permanent way
Chapter 1 introductution to railway and permanent way
 
Railway points, crossings and components
Railway points, crossings and componentsRailway points, crossings and components
Railway points, crossings and components
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
Chapter 6 Points,crossings and yards
Chapter 6 Points,crossings and yardsChapter 6 Points,crossings and yards
Chapter 6 Points,crossings and yards
 
Armoured face conveyor
Armoured face conveyorArmoured face conveyor
Armoured face conveyor
 
railway failure and its type
railway failure and its typerailway failure and its type
railway failure and its type
 
A PRESENTATION ON MECHANICAL POWER TRANSMISSION DRIVES.pptx
A PRESENTATION  ON MECHANICAL POWER TRANSMISSION DRIVES.pptxA PRESENTATION  ON MECHANICAL POWER TRANSMISSION DRIVES.pptx
A PRESENTATION ON MECHANICAL POWER TRANSMISSION DRIVES.pptx
 

Mehr von srinivas2036

Mehr von srinivas2036 (20)

Fundamental operations
Fundamental operationsFundamental operations
Fundamental operations
 
Data collection and input overview
Data collection and input overviewData collection and input overview
Data collection and input overview
 
Theoretical framework for gis
Theoretical framework for gisTheoretical framework for gis
Theoretical framework for gis
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 
Mechanized construction
Mechanized constructionMechanized construction
Mechanized construction
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Fire protection in construction
Fire protection in constructionFire protection in construction
Fire protection in construction
 
Environment at site – construction management
Environment at site – construction managementEnvironment at site – construction management
Environment at site – construction management
 
Electrical safety in construction
Electrical safety in constructionElectrical safety in construction
Electrical safety in construction
 
Personal safety in construction
Personal safety in constructionPersonal safety in construction
Personal safety in construction
 
Startup india action plan – who are eligible
Startup india action plan – who are eligibleStartup india action plan – who are eligible
Startup india action plan – who are eligible
 
Introduction to aerial photography and photogrammetry.ppt
Introduction to aerial photography and photogrammetry.pptIntroduction to aerial photography and photogrammetry.ppt
Introduction to aerial photography and photogrammetry.ppt
 
Topic stereoscopy, Parallax, Relief displacement
Topic  stereoscopy, Parallax, Relief displacementTopic  stereoscopy, Parallax, Relief displacement
Topic stereoscopy, Parallax, Relief displacement
 
Principle of aerial photography and types.ppt
Principle of aerial photography and types.pptPrinciple of aerial photography and types.ppt
Principle of aerial photography and types.ppt
 
GATE Syllabus Civil engineering
GATE Syllabus Civil engineeringGATE Syllabus Civil engineering
GATE Syllabus Civil engineering
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
Valuation
ValuationValuation
Valuation
 
Airport lighting
Airport lightingAirport lighting
Airport lighting
 
Airport marking
Airport markingAirport marking
Airport marking
 
Airport apron and holding bays
Airport apron and holding baysAirport apron and holding bays
Airport apron and holding bays
 

Kürzlich hochgeladen

AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Dr.Costas Sachpazis
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 

Kürzlich hochgeladen (20)

Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 

Points and crossings

  • 2. Outline • Turnout • Types – Left hand – Right Hand • Components • Points and Switches • Crossings
  • 3. Turnout • In case of roads – vehicles move in any direction • Trains - not possible at will to change the direction • Change is made possible with the provision of turnouts • Consists of points and crossings. • Information sent to loco pilot using signals.
  • 4. Turnout - Definition • Simple arrangement of points and crossings by the manipulation of which the train from one track may be diverted to the another track or branch line or to siding is known as turnout. • 2 tracks either merge or diverge, or 2 tracks parallel to each other but are still connected to each other- This connection helps in changing the direction of trains. • for this points and crossings are used.
  • 5. Turnouts • The combination of lead rails with curved rails (and fastenings) helps in diverting rolling stock from one track to another track. • Rails depending on curvature – Lead rails are straight – Curved rails have curvature • Turnouts are also provided in yards and sidings
  • 6.
  • 7. Turnouts and Problems • Some problems exist • Weakest points on the track due to joints and fastenings. Safety becomes main concern in design • Retards the movement of the trains
  • 8. Types of Turnouts • Depending on direction of movement of trains from main tracks – Left hand turnout – Right hand turnout
  • 10. Component Parts of a Turnout 1. A pair of tongue rails 2. A pair of stock rails 3. Two check rails 4. Four lead rails 5. A Vee crossing 6. Slide chairs 7. Stretcher bar 8. A pair of heel blocks 9. Switch tie plate or gauge 10. Parts for operating points- Rods, cranks, levers etc 11. Locking system which includes locking box, lock bar, plunger bar etc
  • 11. • Facing direction: – Standing at switch and looking towards crossing • Trailing direction: – Standing at crossing and looking towards switches • Points: – A pair of tongue rails with stock rails – Train diverting from the main track will negotiate these points first.
  • 12. • Tongue Rail: – It is a tapered movable rail, made of high-carbon or -manganese steel to withstand wear. – At its thicker end, it is attached to a running rail. – A tongue rail is also called a switch rail. • Stock Rail: – It is the running rail against which a tongue rail operates.
  • 13. • Switch angle: – angle between the gauge face of the stock rail and tongue rail at the theoretical toe of switch. • Throw of switch: – Distance by which the tongue rail moves laterally at the toe of switch
  • 14. • Crossing: – A crossing is a device introduced at the junction where two rails cross each other to permit the wheel flange of a railway vehicle to pass from one track to another.
  • 15.
  • 16. Switches - Components • A set of points or switches consists of the following main constituents – A pair of stock rails – A pair of tongue rails • also known as switch rails, made of medium- manganese steel to withstand wear. The tongue rails are machined to a very thin section to obtain a snug fit with the stock rail. The tapered end of the tongue rail is called the toe and the thicker end is called the heel.
  • 17. Switches – A pair of heel blocks which hold the heel of the tongue rails is held at the standard clearance or distance from the stock rails. – A number of slide chairs to support the tongue rail and enable its movement towards or away from the stock rail. – Two or more stretcher bars connecting both the tongue rails close to the toe, for the purpose of holding them at a fixed distance from each other – A gauge tie plate to fix gauges and ensure correct gauge at the points.
  • 18. Types of Switches • Two types – Stud switch • no separate tongue rail is provided and some portion of the track is moved from one side to the other side – Split switch • These consist of a pair of stock rails and a pair of tongue rails • These are 2 types – loose heel type – Fixed heel type
  • 19. • Loose heel type: – In this type of split switch, the switch or tongue rail finishes at the heel of the switch to enable movement of the free end of the tongue rail. – The fish plates holding the tongue rail may be straight or slightly bent. – The tongue rail is fastened to the stock rail with the help of a fishing fit block and four bolts.
  • 20. – The fish bolts in the lead rail are tightened while those in the tongue rail are kept loose or snug to allow free movement of the tongue – As the discontinuity of the track at the heel is a weakness in the structure, the use of these switches is not preferred.
  • 21. • Fixed heel type: – In this type of split switch, the tongue rail does not end at the heel of the switch but extends further and is rigidly connected. – The movement at the toe of the switch is made possible on account of the flexibility of the tongue rail.
  • 22. Based on Toe of Switches • Undercut switch – The foot of the stock rail is planed to accommodate the tongue rail • Straight cut switch – Tongue rail is cut straight along the stock rail to increase thickness at toe. • Over riding switch – Stock rail occupies the full section and the tongue rail is planed to a 6mm thick edge which overrides the foot of stock rail – Switch rail is kept 6mm higher than the stock rail from the heel to the point towards the toe where planning starts – Eliminates the possibility of splitting which might be caused by the movement of false flange in the trailing direction
  • 23. – Stock rail is uncut, hence more stronger – manufacturing work is confined only to tongue rail, which is very economical – Tongue rail supported by stock rail, hence combined strength of rails between sleepers is greater than that of tongue rail alone in the case of undercut switch. – These overriding switches are standardized and used in IR.
  • 24. Crossings • A crossing or frog is a device introduced at the point where two gauge faces cross each other to permit the flanges of a railway vehicle to pass from one track to another. • A gap is provided from throw to the nose of crossing • Check rails assures the correct movement and guides the wheels properly.
  • 25. Crossing - Components • 2 Rails – Point rail, Splice rail are joined • These are machined to form a nose. • The point rail has its fine end slightly cut off to form a blunt nose, with a thickness of 6 mm (1/4"). • The toe of the blunt nose is called the actual nose of crossing (ANC) and the theoretical point where gauge faces from both sides intersect is called the theoretical nose of crossing (TNC). • The ‘V’ rail is planed to a depth of 6 mm (1/4") at the nose and runs out in 89 mm to stop a wheel running in the facing direction from hitting the nose.
  • 26.
  • 27. Crossings - Components • Two wing rails consisting of a right-hand and a left-hand wing rail that converge to form a throat and diverge again on either side of the nose. • Wing rails are flared at the ends to facilitate the entry and exit of the flanged wheel in the gap. • A pair of check rails are used to guide the wheels
  • 28. Crossing - Types • Based on the angle of crossing – Acute angle crossing: (or V crossing) • 2 rail gauge faces cross at acute angle – Obtuse angle or Diamond crossing • 2 gauge faces meet at obtuse angle – Square crossing • Two tracks cross at right angles
  • 29. Crossings - Types • For manufacturing purposes – Built up crossing: • 2 wing rails, a V section consisting of point and splice rails are assembled together by means of bolts and distance blocks to form a crossing. • Low cost • Easy to place and repair. • Bolts require frequent checking. • If wear is more than 10mm renewal required.
  • 30. Crossings - Types – Cast steel crossing: • One piece crossing with no bolts and require little maintenance. • More rigid as it is one single piece. • High initial cost • High maintenance cost • Replaced by Cast Manganese Steel crossings these days – Combined rail and cast crossing • Combination of built up and cast steel crossing • Consists of a cast steel nose finished to ordinary rail faces
  • 31. Crossing - Types • CMS Crossings – Due to heavy loads and traffic, normal manganese rails are quickly wearing out – CMS crossings possess high strength, high resistance to wear, longer life. – Avg life of CMS crossing is 4 times that of built up crossing – CMS crossings are free from bolts and other components which normally get loose as a result of traffic. – High initial cost, but less maintenance – Standardized in Indian Railways
  • 32. Crossing- Types • According to Diversion: – In a spring crossing, one wing rail is movable and is held against the V of the crossing with a strong helical spring while the other wing rail is fixed.
  • 33. Crossings: Crossover Crossing Function of this crossing is to connect two parallel or diverging tracks. According to Diversion
  • 35. Crossings: Scissors Crossing(Double cross): This type of crossing consists 4 pair of switch 6 Acute crossings 2 Obtuse crossings check rails And this type is use at goods yard. According to Diversion
  • 37. Crossings: Diamond Crossing When two tracks crosses each other at less than 90 angle then it forms diamond shape so it is called Diamond Crossing According to Diversion