SlideShare ist ein Scribd-Unternehmen logo
1 von 52
Lim Kah Huay A132816
Low Bee Chan A132764
Sonia Dilip Patel A/P Dilip Kumar A133115
Fatin Atikah Binti Kassim A132739
Jamilah Binti Ahmad A133159
Muhammad Khairil Azim bin Abdullah A133275
PRODUCTION OF BIOETHANOL FROM GLYCEROL
USING Enterobacter aerogenes TISTR1468
Group KB4
2
CONTENT
1. Introduction
2. Summary of Production
3. List of improvement work
4. Heat integration
5. PFD after heat integration
6. Piping and Instrumentation
7. P&ID after HAZOP
8. Detailed Unit & Mechanical Design
9. Waste Management
10. Process Hazard Analysis
11. Plant Layout
12. Conclusion
SUMMARY OF PRODUCTION
Specifications Description
Product Bioethanol
Microorganism used Enterobacter aerogenes TSITR
1468
Processes involved • Micro-aerobic fermentation
• Stripping
• Binary Distillation
• Extraction
• Flash Vaporization
Production basis (per hour) 3676.47 kg
Bioethanol sale price (RM / kg) 3.04
Return on investment, ROI 0.25
Payback period, PBP 3.46 years
Net present value, NPV RM 10.37 million
Discounted cash flow rate of return, DCFRR 0.19
Site location Pengerang, Johor
3
List of Improvement Work
4
CHAPTERS PROBLEM CORRECTION DONE
Chapter 3 - PFD • Size of bioreactors in series
doesn’t shows its
effectiveness in improving
productivity of fermentation
process
• Mass flow rate of medium
from distillation column to
condensers and reboilers are
too big
• Stream tables lacks of data
• Bioreactors
arrangement in parallel
• Re-calculation of mass
balance
• Edited stream table data
Chapter 5 - Heat
integration
Mistakes in inlet and outlet
temperature
Corrected pinch analysis
with heat recovery
integrated in PFD
To be continued…
5
CHAPTERS PROBLEM CORRECTION DONE
Chapter 6 – Piping and
Instrumentation
• Control loops with
electrical signal were
not drawn correctly and
some loops were not
complete
• Relief valve for after
HAZOP study was not
done
• Mistakes in P&ID
drawing
• Complete drawing of
controllers for the entire
plant
• Sizing calculated and
type of valve
determined
• Improved drawing with
second layer of safety
incorporated
Chapter 7 – Detailed
Process Design
Design calculation had
some mistake since inlet
and outlet of stream
changed
All the design calculation
had been calculated and
redesign for all unit
Chapter 8 - Mechanical
Design
The calculation for the
design and mechanical
drawing are not complete
All the calculation design
and drawing AUTOCAD
is done
…continue
List of Improvement Work
To be continued…
6
CHAPTERS PROBLEM CORRECTION DONE
Chapter 10 – Production
Hazard Analysis
HAZOP was incomplete
and did not consider P&ID
HAZOP done after
complete P&ID drawing
Chapter 11 – Site Location
and Plant Layout
Plant layout need to
reconstruct, details were
not drawn out clearly and
wrong arrangement of unit
operations in plant layout
Completed plant layout
drawing
List of Improvement Work
…continue
7
Temperature
interval start with 0KW
start with 5.915445
kW
107.5 0
105.5 0.004115 -0.004115 0.004115 5.91133
92.9 0.33933 -0.343445 0.33933 5.572
92.5 2.262 -2.605445 2.262 3.31
77.5 2.01 -4.615445 2.01 1.3
67.5 1.3 -5.915445 1.3 0
52.5 -0.4455 -5.469945 -0.4455 0.4455
29.5 0.0824 -5.552345 0.0824 0.3631E-103
PROCESS FLOW DIAGRAM after Heat integration
8
Relief System
 Spring-loaded relief valve
 Gas leaks when pressure
reaches 92-95%
 Bursting disc (rupture disc)
 ‘engineered weak spot’
 Low cost, leak tight, instantaneous
response , reliable operation
9
DESIGN OF RELIEF VALVE
Location Type Function A (mm2)
F-101 Spring-loaded To prevent the rupture of vessel due to
overpressure during process and
sterilization
20 921.57
F-102 Spring-loaded To prevent rupture of vessel due to
overpressure during process and
sterilization
18 673.24
F-103 Spring-loaded To prevent rupture of vessel due to
overpressure during process and
sterilization
21 879.60
C-101 Spring-loaded To avoid damage to C-101 due to
overpressure
17 614.22
C-102 Spring-loaded To avoid damage to C-101 due to
overpressure
16 392.17
C-103 Spring-loaded To avoid damage to C-101 due to
overpressure
15 670.20
C-104 Spring-loaded To avoid damage to C-101 due to
overpressure
17 986.11
10
11P&ID after HAZOP
DETAIL UNIT &
MECHANICAL DESIGN
i. Seed Fermenter, F-101
ii. Stripping Column, C-01
iii. Binary Distillation Column, C-102
iv. Extractive Column, C-103
v. Flash Drum, C-104
vi. Cooling Tower
vii. Heat Exchanger, E-103
12
Dimension layout of impeller design
Axial hydrofoil with 3 blades Pitched-blade impeller
Source: Lightnin 2013
Source: Hayward Gordon Ltd. 2013
Source: Geankoplis 2013
DETAILED
DESIGN
Lim Kah Huay
(A132816)
13
Fermenter layout
Source: iGEM 2010
Detailed Design Fermenters
Design Parameters F-101 F-102 & F-103
Tank diameter, Dt 1.91 m 3.50 m
Tank height, Ht 5.72 m 10.49 m
Working volume, V 16.35 m3 100.86 m3
Design of Cooling Jacket
Height of jacket 2 m 3.5 m
Spacing between jacket
and vessel wall
50 mm 50 mm
Overall heat transfer
coefficient, U
500.63 W/m.°C 201 W/m.°C
Pressure drop, ∆P 0.42 kPa 0.16 kPa
Design of Impeller
Type of impeller Axial flow 3 blades
hydrofoil
Axial flow pitched-blade
45°impeller
Impeller diameter, Da 0.98 m 1.05 m
Depth of impeller in
vessel, H
1.96 m 3.50 m
To be continued… 14
15
Design Parameters F-101 F-102 & F-103
Height of impeller above vessel floor, C 0.65 m 1.17 m
Impeller width, W 0.20 m 0.13 m
Length of impeller width, L 0.25 m 0.26 m
Diameter of impeller base, Dd 0.65 m 0.70 m
Baffle width, J 0.16 m 0.29 m
Power number, Np 0.3 1.6
Flow number, Nq 0.55 0.85
Impeller speed 0.10 rps 0.01 rps
Power, P 0.3057 W 0.0008 W
Sparger ring diameter, Ds 1.08 m 1.15 m
Sparger location above vessel floor, S 0.49 m 0.53 m
Mixing time, tT 6.67 s 2041.06 s
Circulation rate, Q 0.05 m3/s 0.29 m3/s
…Continue
Detailed Design Fermenters
16
MECHANICAL DESIGN
SEED FERMENTER, F-101
Process Description
 Microaerobic continuous fermentation with an aeration rate of 0.5
vvm, medium consistently mixed by agitator.
 Glycerol and ammonium phosphate serve as raw material of carbon
and nitrogen source respectively
 Fermentation output consists of bioethanol and carbon dioxide
Material of Construction
 Carbon Steel SA 537
17
Design Specifications Details
Operating Pressure 1 atm (15 psia)
Operating Temperature 37 C (310 K)
Corrosion Allowance 2 mm
Vessel Layout Vertical
H/D ratio 3:1
Volume
Torispherical Head (Top and Bottom Design)
Crown radius, R (m) 1.81
Knuckle radius, a (m) 0.19
Distance from the center of the torus to the center of the torus
tube, c (m)
0.76
Height from the base of the dome to the top, h (m) 0.38
Cylindrical Shell (Shell Design)
4.96
Effective Length, L (m) 5.21
18
Vessel Parts Dimensions (mm)
Torispherical Top 5.72
Cylindrical Shell 8.89
Torispherical Bottom 5.72
Overall 11
Minimum Wall Thickness
Design of Cooling Jacket
Design Parameters Details
Type Type 1 (confined entirely
to the cylindrical shell)
Closure Type (b-2)
Material of Construction Carbon Steel SA537
Jacket Space 50 mm
0.91 mm
2.91 mm
Corner radius of torus closures 5.84 mm
19
Stresses Details
4.83
9.66
0.6324
Primary stresses
6.53
4.40
5.26
157
1361.54
Combined Loading
20
Design Parameters Details
Type of support Bracket support
Type of bracket Double gusset Type 1
Type of beam Wide-flange
Number of legs 4
47 kN
Standard wide flange
beam leg type base plate
W6
21
Flanged Joint Design
Design Parameters Details
Type of flanged joint Welding neck flange
Flange faces Gasket between bolt
circle
Outside diameter of
flange (mm)
Stream 2&4 – 107.95
Stream 3&5 – 152.4
Stream 1&6 – 228.6
DISTILLATION COLUMN (C-101)
SONIA DILIP PATEL (A133115)
C-101
D-101
H-101
BIOETHANOL
BIOMASS
WATER
55% Bioethanol
45%Water
WASTEWATER
TREATMENT/ STILLAGE
S14
S16
S18 S17
S20
S19
S21
Parameter Dimension
Column design Tray
Diameter, DT (m) 1.913
Height, H (m) 9.772
Tray spacing(m) 0.457
Number of actual stages 17
Design of plate Sieve plate
Plate spacing (m) 0.457
Downcomer area 0.2725m2
Active area 1.726m2
Holes area, 0.173m2
Number of holes 8805
22
MECHANICAL DESIGN OF C-101
SONIA DILIP PATEL (A133115)
• Material used
SS-308
• Properties
Source : MIT Department of Civil and Environment 1999
Element Content (%)
Iron, Fe 66
Chromium, Cr 20
Nickel, Ni 11
Manganese, Mn 2.0
Silicon, Si 1.0
Carbon, C 0.080
Phosphorus, P 0.045
Sulfur, S 0.030
Properties Metric
Density 8 g/cm3
Tensile strength 585 MPa
Yield strength 240 MPa
Poisson’s ratio 0.27-0.30
23
• Design parameter for C-101
Parameter Value (SI unit) Value (English unit)
Temperature, T 100 OC 212 OF
Operating pressure (gage), P0 101.325 kPa 15 psig
Height of vessel , H 9.3262 m 367.1732’’, 30.5978’
Inside diameter of vessel, Di 1.91 m 75.1969’’,6.6224’
Height of cylinder shell, Hcylinder 7.772 m 305.9843”, 25.4987’
Height of torispherical heads, Htoris 0.3688 m 14.5197”, 1.2100’
Torispherical head
24
• Combine loading
Primary Stress Value (N/mm2)
3.6226
7.2453
-0.7885
Criterion met. Design is satisfied.
25
Vessel Support
 Straight Cylindrical skirt.
Criterion satisfied, 2 mm CA added. Final skirt thickness = 12 mm
26
• Base ring and Anchor Belt Design
Nb = 4 bolts
Bolt size = nominal diameter (BS 4190: 1967)
Bolt used = M24 with root area = 353 mm2.
• Flanged Joint
Welding Neck Flange
27
28
DISTILLATION COLUMN (C-102)
LOW BEE CHAN (A132764)
Parameter Dimension
Column design Tray
Diameter, DT (m) 1.524
Height, H (m) 26.50
Tray spacing(m) 0.46
Number of actual stages 53
Design of plate Sieve
Plate spacing (m) 0.457
Downcomer area (m2) 0.146
Active area (m2) 0.925
Holes area (m2) 0.0925
Number of holes 4720
29
Mechanical Design Of Stripping Column C-102
LOW BEE CHAN A132764
Process Description:
Purify ethanol-water mixture to form azeotrope with 95.63% ethanol and
4.37% water (by weight)
Material Selection:
Austenitic Stainless Steel 304L
Design Specification:
• External pressure vessel
• Cylindrical shell
• Torispherical heads
31
Minimum wall thickness (mm)
Top and bottom heads 5.08
Cylindrical shell 15.24
Overall(standard) 18
Primary Stresses (N/mm2)
Longitudinal Stress, σL 2.1447
Circumferential Stress, σh 4.2894
Direct Stress, σw 6.65
Bending Stress, σb 46.66
Elasticity Stability (N/mm2)
CYLINDRICAL COLUMN
DESIGN
31
VESSEL SUPPORT DESIGN
Resultant Stresses (N/mm2)
<
STRAIGHT SKIRT SUPPORT
Skirt thickness (mm) 20
Skirt height (mm) 2000
Base Ring and Anchor Bolt Design
Number of bolts 12
Actual width 220mm
Minimum thickness 50mm
M56 bolts (BS 4190: 1967)
32
FLANGE DESIGN
Parameter
S26
feed
S27
top
S29
refluxed
S31
bottom
S32
reboiled
Flow rate (kg/s) 0.4233 4.314 3.356 1.054 4.314
Density (kg/m3) 846.389 1.507 770.216 796.255 1.429
Optimum diameter 34.103 614.71 97.20 54.47 625.19
Nominal pipe size 50.8 660.4 101.6 101.6 660.4
Flange class 150 150 150 150 150
Outside flange diameter,
O
152.4 831.85 228.6 228.6 831.85
Thickness of flange, Tf 17.526 63.5 22.352 22.352 63.5
Diameter of hub, X 77.724 708.152 134.874 134.874 708.152
Chamfer beginning
diameter, A
60.452 609.6 114.3 114.3 609.6
Length through Hub, Y 61.976 127 74.676 74.676 127
Bore 52.578 355.6 102.362 102.362 355.6
Number of bolts 8 8 8 8 8
• Welding Neck Flange
33
DESIGN SUMMARY
Parameter Value
Operating temperature 100
Operating pressure (atm) 1
Material of construction Austenitic stainless steel Type 304L
Vessel internal diameter (m) 1.524
Vessel height (m) 2.65
Type of head and bottom Torispherical
Type of vessel Cylindrical
Vessel wall thickness (mm) 18
Stress analysis (N/mm2) (Δσ)max S < , (7.7128 < 137.89) [Safe]
Elastic stability (N/mm2)
Type of vessel support Straight conical skirt
Type of flanged joint Welding neck flange
Flange faces Gasket between bolt circle
Flange diameter (mm) 50.8, 101.6, 660.4
34
Specifications H-101 H-103
Pitch pattern Square pitch Square pitch
Brass, kw (W/m C) 110 110
Floating head Split-ring Split-ring
Shell pass 1 1
Tube pass 4 4
Number of tubes, Nt 998 1596
Outer diameter, do(m) 0.0381 0.0381
Inner diameter, di(m) 0.0168 0.0168
Length of tubes, l (m) 5 7
Tube pitch, Pt (m) 0.0125 0.0125
Heat transfer area, A (m2) 596.96 1336.46
Shell inside diameter, Ds (m) 1.915 2.335
Baffle spacing, lB(m) 0.036 0.036
Baffle cut, (%) 45 45
Tube side coefficient, hi(W/m2∆ C) 12473.48 11138.26
Shell side coefficient, hs(W/m2∆ C) 3310.721 1053.628
Overall coefficient, Uo(W/m2 C) 991.88 603.28
Tube side pressure drop, ∆Pt(kPa) 78.83 44.67
Shell side pressure drop, ∆Ps (kPa) 1.47 14.36
CONDENSER DESIGN
35
KETTLE REBOILER DESIGN
Specifications H-102 H-104
Pitch pattern Square pitch Square pitch
Carbon steel, kw (W/m. C) 55 55
Number of U tubes 404 374
Outer diameter, do(m) 0.022 0.0381
Inner diameter, di(m) 0.01688 0.0168
Length of tubes, l (m) 5 4
Heat transfer area, A (m2) 158.78 94.09
Baffle spacing, lB (m) 0.036 0.036
Baffle cut (%) 45 45
Tube side coefficient, hi(W/m2∆ C) 736000 734000
Shell side coefficient, hnb (W/m2∆ C) 28137.52 28565.69
Overall coefficient, Uo (W/m2 C) 1444 1239.23
Tube side pressure drop, ∆Pt (kPa) 174.89 168.6
Shell side pressure drop, ∆Ps (kPa) 14.59 14.36
36
EXTRACTIVE DISTILLATION COLUMN (C-103)
JAMILAH AHMAD (A133159)
Material Carbon steel 516
Actual no of stages 27
Diameter of the column (m) 4.68
Height of the column (m) 21.19
CONDENSER H-105
Cooling water flow rate 11409.8
Area required 3.531 m2
Outside diameter 19.05 mm
Inside diameter 14.83 mm
Length 5 m
Number of tube 12
Diameter of the bundle, Db 0.11 m
Shell-side coefficient 1030.137 W/m2oC
Tube-side coefficient 8982.51 W/m2oC
Overall heat transfer cofficient, Uo 649.99 W/m2oC
Total heat load (kW) 771
6.3
Shell side coefficient
Overall heat
transfercoefficient
(W/m2oC)
496
Pressure drop (kPa) 12.1
KETTLE REBOILER H-106
37
MECHANICAL DESIGN
EXTRACTIVE COLUMN
JAMILAH AHMAD (A133159)
INTRODUCTION
• Wall thickness required for the vessel
• Pressure exerted by the outside force weather the vessel can
withstand or not.
• Type of top & bottom and shell used for the
vessel
• Type of vessel support to withstand the vessel.
38
EXTRACTIVE COLUMN
Parts Value/Description
Main Part:
•Vessel height
•Diameter
•Shell height
•Top & bottom height
•Thickness
•Type of shell
•Type of head & bottom
•Material
• 21.49 m
• 4.68 m
• 19.15 m
• 1.17 m
• 30 mm
• Cylindrical
• Torispherical
• Carbon steel 516
Support
•Type
•Material
•Height
•Thickness
• Straight skirt
• Carbon Steel
• 1.219 m
• 30 mm
Flanges
• Type of flange • Welding neck
39
Detailed Design of Flash Drum C-104
KHAIRILAZIM (A133275)
Inlet
(S41)
Vapour Outlet
(S42)
Liquid Outlet
(S43)
h=1.219m
Dv=0.366
Flash drum C-104 is used to separate
the vapour and liquid. For design
calculations it is normally assumed that
the vapour and liquid are in equilibrium
and the vessel is adiabatic
Condition Value
Temperature 100 oC
Pressure 1 atm
Density of Water 958.4 kg/m3
Vapour Density 1.422 kg/m3
From the calculation,
•The diameter must be large enough
•The high of vessel outlet above the
gas inlet should be sufficient for
liquid drops.
•Liquid level will depend on hold up
time necessary for smooth
operations and control
hv=0.283 m3
The conclusion from the calculation,
Minimum vessel diameter,
Dv = 0.366 m
Liquid depth required,
hv = 0.238 m3
Height of the tank,
H = 1.219 m
Mechanical Design of Flash Drum C-104
KHAIRILAZIM (A133275)
Parts Value/Description
Main Part:
•Height
•Diameter
•Thickness
•MAWPvessel
1.219 m
0.366 m
3.5 mm
1.714 kPa
Support
•Type
•Material
•Height
•Thickness
Conical skirt
Plain Carbon Steel
0.25 m
3.5 mm
Flanges
•Feed
•Liquid
•Vapour
Welding neck
Welding neck
Welding neck
Design Summary of C-104
41
Properties Value
Cooling water flow rate (kg/h) 105458
Water inlet temperature (°C) 37
Water outlet temperature (°C) 28
Ambient wet bulb temperature
(°C)
23.9
Tower characteristic, KaL/V 1.5
Minimum tower area (m2) 17
Height of cooling tower (m) 10.4Source : HarrisonCooling
Tower 2002
FATIN ATIKAH (A132739)
42
Number of tube 43
Length tube 4 m
Shell-Side Pressure Drop 78.94 kPa
Tube-Side Pressure Drop 1.84 kPa
Shell-side coefficient 63.94 W/m2oC
Tube-side coefficient 661 W/m2oC
Overall heat transfer
cofficient, Uo
549.47 W/m2oC
Shell and Tube Exchanger
FATIN ATIKAH (A132739)
43
Parts Value/Description
Main Part:
•Vessel length
•Height vessel
•Inner diameter
•Outer diameter
4.0 m
0.267 m
0.016 m
0.02 m
Support
•Type
•Material
•Height
•Thickness
Saddle support
Carbon Steel
0.8 m
0.15 m
Flanges Welding neck
Shell and Tube Exchanger
Saddle support Welding neck flanges
FATIN ATIKAH (A132739)
44
T-102 Primary Clarifier A-101 Air Blower T-105 Sludge Storage Tank
Check Pond
Wastewater
from production
plant
Air
Flocculants and
Coagulant
T-101
T-102
T-103
A-101
T-104
T-105
1
2
3
4
5
7
8
9
10
6
WASTEWATER MANAGEMENT
ACTIVATED SLUDGE WASTEWATER TREATMENT PLANT
PROCESS FLOW DIAGRAM
Stream 1
Flowrate(m3/day) 892.99
S,BOD (mg/L) 362422.7
X, SS (mg/L) 16792.5
Stream 8
Flowrate (m3/day) 0.47
S,BOD (mg/L) -
X, SS (mg/L) 5850.5
Stream 7
Flowrate (m3/day) 4.25
S,BOD (mg/L) -
X, SS (mg/L) 5850.5
Stream 6
Flowrate(m3/day) 4.72
S,BOD (mg/L) -
X, SS (mg/L) 5850.5
Stream 5
Flowrate (m3/day) 884.29
S,BOD (mg/L) 362422.7
X, SS (mg/L) 5940.5
Stream 4
Flowrate(m3/day) 9.45
S,BOD (mg/L) -
X, SS (mg/L) 11775.7
Stream 3
Flowrate(m3/day) 883.54
S,BOD (mg/L) 362422.7
X, SS (mg/L) 5016.8
Stream 2
Flowrate (m3/day) 892.99
S,BOD (mg/L) 362422.7
X, SS (mg/L) 16792.5
Stream 10
Flowrate (m3/day) 879.57
S,BOD (mg/L) 45
X, SS (mg/L) 90
Stream 9
Flowrate(m3/day) 9.92
S,BOD (mg/L) -
X, SS (mg/L) 12290.9
Flocculation
tank
Sludge
storage tank
Aeration
tank
Secondary
clarifier
Primary
clarifier
46.51 m3
60 min
93.02 m3
SL: 40m3/m2.day
188. 06 m3
Length: 8.17 m
Width: 3.8 m
Height: 3m
93.02 m3
Length: 9.3 m
Width: 5 m
Height: 2 m
45
46
PLANT LAYOUT
Process Hazard Analysis
Components Hazardous
Properties
Glycerol • Flammable
• Explosion
• Toxic
Ammonium phosphate • Toxic
Oxygen • Flammable
• Toxic
Ethanol • Fire
• Explosion
• Toxic
Carbon dioxide • Explosion
• Toxic
Nitrogen • Toxic
Hazard Identification
Legal Acts Requirement
1. Environmental Quality Act
(EQA) 1974
2. Occupational Safety and Health
Act (OSHA) 1994
3. Factory and Machinery Act
(FMA) 1967
Methods for PHA:
1. HAZOP analysis
2. FMEA
Set of organized and systematic assessments of the potential hazards associated with an
industrial process. A PHA provides information intended to assist managers and employees
in making decisions for improving safety and reducing the consequences of unwanted or
unplanned releases of hazardous chemicals.
47
FMEA method
- Systematic process to identify potential failures to fulfill the intended function,
to identify possible failure and locate the failure impacts
- Example of the method is shown in Seed Fermenter F-101
Component Failure mode Failure effects Symptom Safeguard Action
Level control
valve
Valve fails open
Valve fails
closed
Fluid will
exceed the level
of storage tank
causing
overflow and
rupture the tank
Liquid overflow None Schedule
inspection and
maintenance
required
Pure glycerol
valve
Valve fails open No glycerol in
the tank. Product
produce does
not meet the
specification.
The reaction is
not complete
None Daily check
Temperature
control valve
Valve fails open High
temperature in
the tank. It will
effect product
reaction
No cooling
water is supply
to the tank
Low level alarm Daily check
Process Hazard Analysis
48
Component Failure mode Failure effects Symptom Safeguard Action
Heat exchanger Tube failure High pressure and
could cause a cause
a major fire
Odors at the
cooling tower
None Daily check and
schedule
maintenance
Centrifugal pump Pump stop Loss of power
which cause
mechanical failure
Risk of upstream
process pump
damage due to
overpressure
None Preventive
maintenance
Temperature
control valve
Heater failure Electric device
failure. Loss of
electric power
May cause over
temperature which
will rupture the
wall
None Schedule
inspection and
maintenance
Condenser(Cooler) Power failure Unable to cool the
outlet stream
Very high
temperature is
flowing out
None Back-up power
supply generator
Level control valve Valve fails open
Valve fails closed
Fluid will exceed
the level of storage
tank causing
overflow and
Liquid overflow None Schedule
inspection and
maintenance
required
- FMEA analysis for Distillation Column C-101
49
PROCESS HAZARD ANALYSIS
HAZOP Analysis
• HAZOP Analysis is to identify how a process deviation can be prevented
or mitigate to minimize the potential hazard. Example of the analysis is
in the distillation column.
Project name : Process Plant Design
Process : Bio ethanol production
Part : Distillation Column
Study node Process parameter
Deviations
(guide words)
Possible causes Possible consequence Action required
Stream 28 Flow NO Pipe broken or plugging Loss of feed into column/not achieve into
desired output.
Level decrease in distillation column.
Off specification product.
1. Schedule inspection
and maintene.an
LOW 1. Pipe partial plugged or leakage. 1. Level decrease in distillation
column.
2. Off specification product.
3. Back flow of material.
Install check valve.
HIGH 1. High pressure from source 1. Flooding in distillation column. 1. Install bypass line with
manual valve.
Distillation column Level HIGH 1. Output pipe blockage. Overpressure of reflux drum.
Condensed liquid flow back to
distillation.
1. Install high level alarm
2. Scheduling inspection
LOW Pipe partial clogged & leakage. Level decrease in the vessel
The valve closed.
Back flow of material.
1. Scheduling inspection
2. Install valve.
Temperature HIGH 1. Low incoming flow from H-101
cause overheating.
Off specification product. Install temperature sensor.
LOW 1. H-101 malfunction.
2. High incoming flow through H-
101.
Low level inside reboiler.
Off specification product.
1. Scheduling inspection
2. Install temperature sensor.
50
51
 A high yield and potential for ethanol as fuel from Enterobacter
aerogenes. Pengerang has been the best location judging from the
coming development as Asia’s largest storage terminal.
 Production rate of 3276 kg/hr and high demand in 2018 (projection) will
leave a very stable economic growth for ethanol.
 65% saving of energy through pinch and heat exchanger installation will
further bloom the net profit.
 Mechanical calculations and drawings for main utilities provide a clearer
insight of the sizing and supports.
 Safety has been of top consideration through FMEA and HAZOP
performed. Layers of control aspect will further enhance the safety and
continuous operation of ethanol plant.
 Waste management has been of top priority and calculations from waste
treatment plant designed is able to lower down pollutants to allowable
limits.
FYDP Sem 2

Weitere ähnliche Inhalte

Was ist angesagt?

Design of pressure vessel
Design of pressure vesselDesign of pressure vessel
Design of pressure vesselKJ Savaliya
 
PSV Sizing - API Based
PSV Sizing - API BasedPSV Sizing - API Based
PSV Sizing - API BasedVijay Sarathy
 
Production of 66000 ton/year of Formaldehyde from Methanol using Silver catal...
Production of 66000 ton/year of Formaldehyde from Methanol using Silver catal...Production of 66000 ton/year of Formaldehyde from Methanol using Silver catal...
Production of 66000 ton/year of Formaldehyde from Methanol using Silver catal...Engr Muhammad Zeeshan
 
Selection of Reboilers for Distillation Columns
Selection of Reboilers for Distillation ColumnsSelection of Reboilers for Distillation Columns
Selection of Reboilers for Distillation ColumnsGerard B. Hawkins
 
Types and design of the towers trays
Types and design of the towers traysTypes and design of the towers trays
Types and design of the towers traysFertiglobe
 
Aspen HYSYS - Petroleum Assays and Oil Characterization (Slideshare)
Aspen HYSYS - Petroleum Assays and Oil Characterization (Slideshare)Aspen HYSYS - Petroleum Assays and Oil Characterization (Slideshare)
Aspen HYSYS - Petroleum Assays and Oil Characterization (Slideshare)Chemical Engineering Guy
 
Project: Formaldehyde from methanol and air
Project: Formaldehyde from methanol and airProject: Formaldehyde from methanol and air
Project: Formaldehyde from methanol and airMehmoodIqbal7
 
Piping and Vessels Flushing and Cleaning Procedure
Piping and Vessels Flushing and Cleaning ProcedurePiping and Vessels Flushing and Cleaning Procedure
Piping and Vessels Flushing and Cleaning ProcedureGerard B. Hawkins
 
Chapter 7 capital cost estimation
Chapter 7 capital cost estimationChapter 7 capital cost estimation
Chapter 7 capital cost estimationjose2424
 
Material & Energy Balance for Distillation
Material & Energy Balance for DistillationMaterial & Energy Balance for Distillation
Material & Energy Balance for DistillationPankaj Khandelwal
 
column packing in mass transfer
column packing in mass transfercolumn packing in mass transfer
column packing in mass transferdnyaneshwar bande
 
Shell and tube heat exchanger design
Shell and tube heat exchanger designShell and tube heat exchanger design
Shell and tube heat exchanger designhossie
 
Psv scenario-and-calculation
Psv scenario-and-calculationPsv scenario-and-calculation
Psv scenario-and-calculationChingLuh Nike
 
Storage vessel design
Storage vessel designStorage vessel design
Storage vessel designMASUKUMARA1
 
hazop 2nd half edited.docx
hazop 2nd half edited.docxhazop 2nd half edited.docx
hazop 2nd half edited.docxssuser74a443
 

Was ist angesagt? (20)

Design of pressure vessel
Design of pressure vesselDesign of pressure vessel
Design of pressure vessel
 
PSV Sizing - API Based
PSV Sizing - API BasedPSV Sizing - API Based
PSV Sizing - API Based
 
Design of pressure vessel
Design of pressure vesselDesign of pressure vessel
Design of pressure vessel
 
API STD 521
API STD 521API STD 521
API STD 521
 
Production of 66000 ton/year of Formaldehyde from Methanol using Silver catal...
Production of 66000 ton/year of Formaldehyde from Methanol using Silver catal...Production of 66000 ton/year of Formaldehyde from Methanol using Silver catal...
Production of 66000 ton/year of Formaldehyde from Methanol using Silver catal...
 
Selection of Reboilers for Distillation Columns
Selection of Reboilers for Distillation ColumnsSelection of Reboilers for Distillation Columns
Selection of Reboilers for Distillation Columns
 
Hazop Sample.pdf
Hazop Sample.pdfHazop Sample.pdf
Hazop Sample.pdf
 
Types and design of the towers trays
Types and design of the towers traysTypes and design of the towers trays
Types and design of the towers trays
 
Aspen HYSYS - Petroleum Assays and Oil Characterization (Slideshare)
Aspen HYSYS - Petroleum Assays and Oil Characterization (Slideshare)Aspen HYSYS - Petroleum Assays and Oil Characterization (Slideshare)
Aspen HYSYS - Petroleum Assays and Oil Characterization (Slideshare)
 
Project: Formaldehyde from methanol and air
Project: Formaldehyde from methanol and airProject: Formaldehyde from methanol and air
Project: Formaldehyde from methanol and air
 
Piping and Vessels Flushing and Cleaning Procedure
Piping and Vessels Flushing and Cleaning ProcedurePiping and Vessels Flushing and Cleaning Procedure
Piping and Vessels Flushing and Cleaning Procedure
 
AMMONIA storage
AMMONIA storageAMMONIA storage
AMMONIA storage
 
Chapter 7 capital cost estimation
Chapter 7 capital cost estimationChapter 7 capital cost estimation
Chapter 7 capital cost estimation
 
Material & Energy Balance for Distillation
Material & Energy Balance for DistillationMaterial & Energy Balance for Distillation
Material & Energy Balance for Distillation
 
column packing in mass transfer
column packing in mass transfercolumn packing in mass transfer
column packing in mass transfer
 
Shell and tube heat exchanger design
Shell and tube heat exchanger designShell and tube heat exchanger design
Shell and tube heat exchanger design
 
Psv scenario-and-calculation
Psv scenario-and-calculationPsv scenario-and-calculation
Psv scenario-and-calculation
 
Ced_ppt
Ced_pptCed_ppt
Ced_ppt
 
Storage vessel design
Storage vessel designStorage vessel design
Storage vessel design
 
hazop 2nd half edited.docx
hazop 2nd half edited.docxhazop 2nd half edited.docx
hazop 2nd half edited.docx
 

Ähnlich wie FYDP Sem 2

Directional solidification in GDC dies through cooling and heating Design in ...
Directional solidification in GDC dies through cooling and heating Design in ...Directional solidification in GDC dies through cooling and heating Design in ...
Directional solidification in GDC dies through cooling and heating Design in ...AnirudhKumarprajapat
 
Cryogenic air separation plant design
Cryogenic air separation plant designCryogenic air separation plant design
Cryogenic air separation plant designRahul Ghalme
 
L pac presentation
L pac presentationL pac presentation
L pac presentationSonia Patel
 
Styrene Production by Catalytic Dehydrogenation of Ethylbenzene
Styrene Production by Catalytic Dehydrogenation of Ethylbenzene Styrene Production by Catalytic Dehydrogenation of Ethylbenzene
Styrene Production by Catalytic Dehydrogenation of Ethylbenzene Michelle Otutu
 
Dimethyl Ether Production
Dimethyl Ether ProductionDimethyl Ether Production
Dimethyl Ether ProductionAziz Albattah
 
IRJET-Enhancing the Performance of Hybrid Microgrid using non Isolated Single...
IRJET-Enhancing the Performance of Hybrid Microgrid using non Isolated Single...IRJET-Enhancing the Performance of Hybrid Microgrid using non Isolated Single...
IRJET-Enhancing the Performance of Hybrid Microgrid using non Isolated Single...IRJET Journal
 
SARNATH-PROFILE-CAE
SARNATH-PROFILE-CAESARNATH-PROFILE-CAE
SARNATH-PROFILE-CAESarnath R
 
Prefeseability study of petroleum field
Prefeseability study of petroleum fieldPrefeseability study of petroleum field
Prefeseability study of petroleum fieldSafwen Sakhraoui
 
AETEG Presentation.pptx
AETEG Presentation.pptxAETEG Presentation.pptx
AETEG Presentation.pptxTamarana Kumar
 

Ähnlich wie FYDP Sem 2 (20)

project ppt
project pptproject ppt
project ppt
 
presentation
presentationpresentation
presentation
 
SLIDE FYDP2
SLIDE FYDP2SLIDE FYDP2
SLIDE FYDP2
 
Directional solidification in GDC dies through cooling and heating Design in ...
Directional solidification in GDC dies through cooling and heating Design in ...Directional solidification in GDC dies through cooling and heating Design in ...
Directional solidification in GDC dies through cooling and heating Design in ...
 
Cryogenic air separation plant design
Cryogenic air separation plant designCryogenic air separation plant design
Cryogenic air separation plant design
 
L pac presentation
L pac presentationL pac presentation
L pac presentation
 
I1303044552
I1303044552I1303044552
I1303044552
 
Project ppt
Project pptProject ppt
Project ppt
 
Styrene Production by Catalytic Dehydrogenation of Ethylbenzene
Styrene Production by Catalytic Dehydrogenation of Ethylbenzene Styrene Production by Catalytic Dehydrogenation of Ethylbenzene
Styrene Production by Catalytic Dehydrogenation of Ethylbenzene
 
Dimethyl Ether Production
Dimethyl Ether ProductionDimethyl Ether Production
Dimethyl Ether Production
 
EFYP2 Presentation
EFYP2 PresentationEFYP2 Presentation
EFYP2 Presentation
 
IRJET-Enhancing the Performance of Hybrid Microgrid using non Isolated Single...
IRJET-Enhancing the Performance of Hybrid Microgrid using non Isolated Single...IRJET-Enhancing the Performance of Hybrid Microgrid using non Isolated Single...
IRJET-Enhancing the Performance of Hybrid Microgrid using non Isolated Single...
 
Tg section eqpt details
Tg section eqpt detailsTg section eqpt details
Tg section eqpt details
 
Alpha 500e
Alpha 500eAlpha 500e
Alpha 500e
 
SARNATH-PROFILE-CAE
SARNATH-PROFILE-CAESARNATH-PROFILE-CAE
SARNATH-PROFILE-CAE
 
2nd Presentation NAME 338
2nd Presentation NAME 3382nd Presentation NAME 338
2nd Presentation NAME 338
 
Prefeseability study of petroleum field
Prefeseability study of petroleum fieldPrefeseability study of petroleum field
Prefeseability study of petroleum field
 
AETEG Presentation.pptx
AETEG Presentation.pptxAETEG Presentation.pptx
AETEG Presentation.pptx
 
NAME 338 , Presentation 1
NAME 338 , Presentation 1NAME 338 , Presentation 1
NAME 338 , Presentation 1
 
project
projectproject
project
 

Mehr von Sonia Patel

ethanol production from crude glycerol
ethanol production from crude glycerol ethanol production from crude glycerol
ethanol production from crude glycerol Sonia Patel
 
Water Case Study
Water Case Study Water Case Study
Water Case Study Sonia Patel
 
production of citric acid.
production of citric acid.production of citric acid.
production of citric acid.Sonia Patel
 
Production of PHB
Production of PHBProduction of PHB
Production of PHBSonia Patel
 

Mehr von Sonia Patel (6)

ethanol production from crude glycerol
ethanol production from crude glycerol ethanol production from crude glycerol
ethanol production from crude glycerol
 
Water Case Study
Water Case Study Water Case Study
Water Case Study
 
random
randomrandom
random
 
production of citric acid.
production of citric acid.production of citric acid.
production of citric acid.
 
Production of PHB
Production of PHBProduction of PHB
Production of PHB
 
wind turbine
wind turbinewind turbine
wind turbine
 

Kürzlich hochgeladen

KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Kürzlich hochgeladen (20)

DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 

FYDP Sem 2

  • 1. Lim Kah Huay A132816 Low Bee Chan A132764 Sonia Dilip Patel A/P Dilip Kumar A133115 Fatin Atikah Binti Kassim A132739 Jamilah Binti Ahmad A133159 Muhammad Khairil Azim bin Abdullah A133275 PRODUCTION OF BIOETHANOL FROM GLYCEROL USING Enterobacter aerogenes TISTR1468 Group KB4
  • 2. 2 CONTENT 1. Introduction 2. Summary of Production 3. List of improvement work 4. Heat integration 5. PFD after heat integration 6. Piping and Instrumentation 7. P&ID after HAZOP 8. Detailed Unit & Mechanical Design 9. Waste Management 10. Process Hazard Analysis 11. Plant Layout 12. Conclusion
  • 3. SUMMARY OF PRODUCTION Specifications Description Product Bioethanol Microorganism used Enterobacter aerogenes TSITR 1468 Processes involved • Micro-aerobic fermentation • Stripping • Binary Distillation • Extraction • Flash Vaporization Production basis (per hour) 3676.47 kg Bioethanol sale price (RM / kg) 3.04 Return on investment, ROI 0.25 Payback period, PBP 3.46 years Net present value, NPV RM 10.37 million Discounted cash flow rate of return, DCFRR 0.19 Site location Pengerang, Johor 3
  • 4. List of Improvement Work 4 CHAPTERS PROBLEM CORRECTION DONE Chapter 3 - PFD • Size of bioreactors in series doesn’t shows its effectiveness in improving productivity of fermentation process • Mass flow rate of medium from distillation column to condensers and reboilers are too big • Stream tables lacks of data • Bioreactors arrangement in parallel • Re-calculation of mass balance • Edited stream table data Chapter 5 - Heat integration Mistakes in inlet and outlet temperature Corrected pinch analysis with heat recovery integrated in PFD To be continued…
  • 5. 5 CHAPTERS PROBLEM CORRECTION DONE Chapter 6 – Piping and Instrumentation • Control loops with electrical signal were not drawn correctly and some loops were not complete • Relief valve for after HAZOP study was not done • Mistakes in P&ID drawing • Complete drawing of controllers for the entire plant • Sizing calculated and type of valve determined • Improved drawing with second layer of safety incorporated Chapter 7 – Detailed Process Design Design calculation had some mistake since inlet and outlet of stream changed All the design calculation had been calculated and redesign for all unit Chapter 8 - Mechanical Design The calculation for the design and mechanical drawing are not complete All the calculation design and drawing AUTOCAD is done …continue List of Improvement Work To be continued…
  • 6. 6 CHAPTERS PROBLEM CORRECTION DONE Chapter 10 – Production Hazard Analysis HAZOP was incomplete and did not consider P&ID HAZOP done after complete P&ID drawing Chapter 11 – Site Location and Plant Layout Plant layout need to reconstruct, details were not drawn out clearly and wrong arrangement of unit operations in plant layout Completed plant layout drawing List of Improvement Work …continue
  • 7. 7 Temperature interval start with 0KW start with 5.915445 kW 107.5 0 105.5 0.004115 -0.004115 0.004115 5.91133 92.9 0.33933 -0.343445 0.33933 5.572 92.5 2.262 -2.605445 2.262 3.31 77.5 2.01 -4.615445 2.01 1.3 67.5 1.3 -5.915445 1.3 0 52.5 -0.4455 -5.469945 -0.4455 0.4455 29.5 0.0824 -5.552345 0.0824 0.3631E-103
  • 8. PROCESS FLOW DIAGRAM after Heat integration 8
  • 9. Relief System  Spring-loaded relief valve  Gas leaks when pressure reaches 92-95%  Bursting disc (rupture disc)  ‘engineered weak spot’  Low cost, leak tight, instantaneous response , reliable operation 9
  • 10. DESIGN OF RELIEF VALVE Location Type Function A (mm2) F-101 Spring-loaded To prevent the rupture of vessel due to overpressure during process and sterilization 20 921.57 F-102 Spring-loaded To prevent rupture of vessel due to overpressure during process and sterilization 18 673.24 F-103 Spring-loaded To prevent rupture of vessel due to overpressure during process and sterilization 21 879.60 C-101 Spring-loaded To avoid damage to C-101 due to overpressure 17 614.22 C-102 Spring-loaded To avoid damage to C-101 due to overpressure 16 392.17 C-103 Spring-loaded To avoid damage to C-101 due to overpressure 15 670.20 C-104 Spring-loaded To avoid damage to C-101 due to overpressure 17 986.11 10
  • 12. DETAIL UNIT & MECHANICAL DESIGN i. Seed Fermenter, F-101 ii. Stripping Column, C-01 iii. Binary Distillation Column, C-102 iv. Extractive Column, C-103 v. Flash Drum, C-104 vi. Cooling Tower vii. Heat Exchanger, E-103 12
  • 13. Dimension layout of impeller design Axial hydrofoil with 3 blades Pitched-blade impeller Source: Lightnin 2013 Source: Hayward Gordon Ltd. 2013 Source: Geankoplis 2013 DETAILED DESIGN Lim Kah Huay (A132816) 13 Fermenter layout Source: iGEM 2010
  • 14. Detailed Design Fermenters Design Parameters F-101 F-102 & F-103 Tank diameter, Dt 1.91 m 3.50 m Tank height, Ht 5.72 m 10.49 m Working volume, V 16.35 m3 100.86 m3 Design of Cooling Jacket Height of jacket 2 m 3.5 m Spacing between jacket and vessel wall 50 mm 50 mm Overall heat transfer coefficient, U 500.63 W/m.°C 201 W/m.°C Pressure drop, ∆P 0.42 kPa 0.16 kPa Design of Impeller Type of impeller Axial flow 3 blades hydrofoil Axial flow pitched-blade 45°impeller Impeller diameter, Da 0.98 m 1.05 m Depth of impeller in vessel, H 1.96 m 3.50 m To be continued… 14
  • 15. 15 Design Parameters F-101 F-102 & F-103 Height of impeller above vessel floor, C 0.65 m 1.17 m Impeller width, W 0.20 m 0.13 m Length of impeller width, L 0.25 m 0.26 m Diameter of impeller base, Dd 0.65 m 0.70 m Baffle width, J 0.16 m 0.29 m Power number, Np 0.3 1.6 Flow number, Nq 0.55 0.85 Impeller speed 0.10 rps 0.01 rps Power, P 0.3057 W 0.0008 W Sparger ring diameter, Ds 1.08 m 1.15 m Sparger location above vessel floor, S 0.49 m 0.53 m Mixing time, tT 6.67 s 2041.06 s Circulation rate, Q 0.05 m3/s 0.29 m3/s …Continue Detailed Design Fermenters
  • 16. 16 MECHANICAL DESIGN SEED FERMENTER, F-101 Process Description  Microaerobic continuous fermentation with an aeration rate of 0.5 vvm, medium consistently mixed by agitator.  Glycerol and ammonium phosphate serve as raw material of carbon and nitrogen source respectively  Fermentation output consists of bioethanol and carbon dioxide Material of Construction  Carbon Steel SA 537
  • 17. 17 Design Specifications Details Operating Pressure 1 atm (15 psia) Operating Temperature 37 C (310 K) Corrosion Allowance 2 mm Vessel Layout Vertical H/D ratio 3:1 Volume Torispherical Head (Top and Bottom Design) Crown radius, R (m) 1.81 Knuckle radius, a (m) 0.19 Distance from the center of the torus to the center of the torus tube, c (m) 0.76 Height from the base of the dome to the top, h (m) 0.38 Cylindrical Shell (Shell Design) 4.96 Effective Length, L (m) 5.21
  • 18. 18 Vessel Parts Dimensions (mm) Torispherical Top 5.72 Cylindrical Shell 8.89 Torispherical Bottom 5.72 Overall 11 Minimum Wall Thickness Design of Cooling Jacket Design Parameters Details Type Type 1 (confined entirely to the cylindrical shell) Closure Type (b-2) Material of Construction Carbon Steel SA537 Jacket Space 50 mm 0.91 mm 2.91 mm Corner radius of torus closures 5.84 mm
  • 20. 20 Design Parameters Details Type of support Bracket support Type of bracket Double gusset Type 1 Type of beam Wide-flange Number of legs 4 47 kN Standard wide flange beam leg type base plate W6
  • 21. 21 Flanged Joint Design Design Parameters Details Type of flanged joint Welding neck flange Flange faces Gasket between bolt circle Outside diameter of flange (mm) Stream 2&4 – 107.95 Stream 3&5 – 152.4 Stream 1&6 – 228.6
  • 22. DISTILLATION COLUMN (C-101) SONIA DILIP PATEL (A133115) C-101 D-101 H-101 BIOETHANOL BIOMASS WATER 55% Bioethanol 45%Water WASTEWATER TREATMENT/ STILLAGE S14 S16 S18 S17 S20 S19 S21 Parameter Dimension Column design Tray Diameter, DT (m) 1.913 Height, H (m) 9.772 Tray spacing(m) 0.457 Number of actual stages 17 Design of plate Sieve plate Plate spacing (m) 0.457 Downcomer area 0.2725m2 Active area 1.726m2 Holes area, 0.173m2 Number of holes 8805 22
  • 23. MECHANICAL DESIGN OF C-101 SONIA DILIP PATEL (A133115) • Material used SS-308 • Properties Source : MIT Department of Civil and Environment 1999 Element Content (%) Iron, Fe 66 Chromium, Cr 20 Nickel, Ni 11 Manganese, Mn 2.0 Silicon, Si 1.0 Carbon, C 0.080 Phosphorus, P 0.045 Sulfur, S 0.030 Properties Metric Density 8 g/cm3 Tensile strength 585 MPa Yield strength 240 MPa Poisson’s ratio 0.27-0.30 23
  • 24. • Design parameter for C-101 Parameter Value (SI unit) Value (English unit) Temperature, T 100 OC 212 OF Operating pressure (gage), P0 101.325 kPa 15 psig Height of vessel , H 9.3262 m 367.1732’’, 30.5978’ Inside diameter of vessel, Di 1.91 m 75.1969’’,6.6224’ Height of cylinder shell, Hcylinder 7.772 m 305.9843”, 25.4987’ Height of torispherical heads, Htoris 0.3688 m 14.5197”, 1.2100’ Torispherical head 24
  • 25. • Combine loading Primary Stress Value (N/mm2) 3.6226 7.2453 -0.7885 Criterion met. Design is satisfied. 25
  • 26. Vessel Support  Straight Cylindrical skirt. Criterion satisfied, 2 mm CA added. Final skirt thickness = 12 mm 26
  • 27. • Base ring and Anchor Belt Design Nb = 4 bolts Bolt size = nominal diameter (BS 4190: 1967) Bolt used = M24 with root area = 353 mm2. • Flanged Joint Welding Neck Flange 27
  • 28. 28
  • 29. DISTILLATION COLUMN (C-102) LOW BEE CHAN (A132764) Parameter Dimension Column design Tray Diameter, DT (m) 1.524 Height, H (m) 26.50 Tray spacing(m) 0.46 Number of actual stages 53 Design of plate Sieve Plate spacing (m) 0.457 Downcomer area (m2) 0.146 Active area (m2) 0.925 Holes area (m2) 0.0925 Number of holes 4720 29
  • 30. Mechanical Design Of Stripping Column C-102 LOW BEE CHAN A132764 Process Description: Purify ethanol-water mixture to form azeotrope with 95.63% ethanol and 4.37% water (by weight) Material Selection: Austenitic Stainless Steel 304L Design Specification: • External pressure vessel • Cylindrical shell • Torispherical heads 31
  • 31. Minimum wall thickness (mm) Top and bottom heads 5.08 Cylindrical shell 15.24 Overall(standard) 18 Primary Stresses (N/mm2) Longitudinal Stress, σL 2.1447 Circumferential Stress, σh 4.2894 Direct Stress, σw 6.65 Bending Stress, σb 46.66 Elasticity Stability (N/mm2) CYLINDRICAL COLUMN DESIGN 31
  • 32. VESSEL SUPPORT DESIGN Resultant Stresses (N/mm2) < STRAIGHT SKIRT SUPPORT Skirt thickness (mm) 20 Skirt height (mm) 2000 Base Ring and Anchor Bolt Design Number of bolts 12 Actual width 220mm Minimum thickness 50mm M56 bolts (BS 4190: 1967) 32
  • 33. FLANGE DESIGN Parameter S26 feed S27 top S29 refluxed S31 bottom S32 reboiled Flow rate (kg/s) 0.4233 4.314 3.356 1.054 4.314 Density (kg/m3) 846.389 1.507 770.216 796.255 1.429 Optimum diameter 34.103 614.71 97.20 54.47 625.19 Nominal pipe size 50.8 660.4 101.6 101.6 660.4 Flange class 150 150 150 150 150 Outside flange diameter, O 152.4 831.85 228.6 228.6 831.85 Thickness of flange, Tf 17.526 63.5 22.352 22.352 63.5 Diameter of hub, X 77.724 708.152 134.874 134.874 708.152 Chamfer beginning diameter, A 60.452 609.6 114.3 114.3 609.6 Length through Hub, Y 61.976 127 74.676 74.676 127 Bore 52.578 355.6 102.362 102.362 355.6 Number of bolts 8 8 8 8 8 • Welding Neck Flange 33
  • 34. DESIGN SUMMARY Parameter Value Operating temperature 100 Operating pressure (atm) 1 Material of construction Austenitic stainless steel Type 304L Vessel internal diameter (m) 1.524 Vessel height (m) 2.65 Type of head and bottom Torispherical Type of vessel Cylindrical Vessel wall thickness (mm) 18 Stress analysis (N/mm2) (Δσ)max S < , (7.7128 < 137.89) [Safe] Elastic stability (N/mm2) Type of vessel support Straight conical skirt Type of flanged joint Welding neck flange Flange faces Gasket between bolt circle Flange diameter (mm) 50.8, 101.6, 660.4 34
  • 35. Specifications H-101 H-103 Pitch pattern Square pitch Square pitch Brass, kw (W/m C) 110 110 Floating head Split-ring Split-ring Shell pass 1 1 Tube pass 4 4 Number of tubes, Nt 998 1596 Outer diameter, do(m) 0.0381 0.0381 Inner diameter, di(m) 0.0168 0.0168 Length of tubes, l (m) 5 7 Tube pitch, Pt (m) 0.0125 0.0125 Heat transfer area, A (m2) 596.96 1336.46 Shell inside diameter, Ds (m) 1.915 2.335 Baffle spacing, lB(m) 0.036 0.036 Baffle cut, (%) 45 45 Tube side coefficient, hi(W/m2∆ C) 12473.48 11138.26 Shell side coefficient, hs(W/m2∆ C) 3310.721 1053.628 Overall coefficient, Uo(W/m2 C) 991.88 603.28 Tube side pressure drop, ∆Pt(kPa) 78.83 44.67 Shell side pressure drop, ∆Ps (kPa) 1.47 14.36 CONDENSER DESIGN 35
  • 36. KETTLE REBOILER DESIGN Specifications H-102 H-104 Pitch pattern Square pitch Square pitch Carbon steel, kw (W/m. C) 55 55 Number of U tubes 404 374 Outer diameter, do(m) 0.022 0.0381 Inner diameter, di(m) 0.01688 0.0168 Length of tubes, l (m) 5 4 Heat transfer area, A (m2) 158.78 94.09 Baffle spacing, lB (m) 0.036 0.036 Baffle cut (%) 45 45 Tube side coefficient, hi(W/m2∆ C) 736000 734000 Shell side coefficient, hnb (W/m2∆ C) 28137.52 28565.69 Overall coefficient, Uo (W/m2 C) 1444 1239.23 Tube side pressure drop, ∆Pt (kPa) 174.89 168.6 Shell side pressure drop, ∆Ps (kPa) 14.59 14.36 36
  • 37. EXTRACTIVE DISTILLATION COLUMN (C-103) JAMILAH AHMAD (A133159) Material Carbon steel 516 Actual no of stages 27 Diameter of the column (m) 4.68 Height of the column (m) 21.19 CONDENSER H-105 Cooling water flow rate 11409.8 Area required 3.531 m2 Outside diameter 19.05 mm Inside diameter 14.83 mm Length 5 m Number of tube 12 Diameter of the bundle, Db 0.11 m Shell-side coefficient 1030.137 W/m2oC Tube-side coefficient 8982.51 W/m2oC Overall heat transfer cofficient, Uo 649.99 W/m2oC Total heat load (kW) 771 6.3 Shell side coefficient Overall heat transfercoefficient (W/m2oC) 496 Pressure drop (kPa) 12.1 KETTLE REBOILER H-106 37
  • 38. MECHANICAL DESIGN EXTRACTIVE COLUMN JAMILAH AHMAD (A133159) INTRODUCTION • Wall thickness required for the vessel • Pressure exerted by the outside force weather the vessel can withstand or not. • Type of top & bottom and shell used for the vessel • Type of vessel support to withstand the vessel. 38
  • 39. EXTRACTIVE COLUMN Parts Value/Description Main Part: •Vessel height •Diameter •Shell height •Top & bottom height •Thickness •Type of shell •Type of head & bottom •Material • 21.49 m • 4.68 m • 19.15 m • 1.17 m • 30 mm • Cylindrical • Torispherical • Carbon steel 516 Support •Type •Material •Height •Thickness • Straight skirt • Carbon Steel • 1.219 m • 30 mm Flanges • Type of flange • Welding neck 39
  • 40. Detailed Design of Flash Drum C-104 KHAIRILAZIM (A133275) Inlet (S41) Vapour Outlet (S42) Liquid Outlet (S43) h=1.219m Dv=0.366 Flash drum C-104 is used to separate the vapour and liquid. For design calculations it is normally assumed that the vapour and liquid are in equilibrium and the vessel is adiabatic Condition Value Temperature 100 oC Pressure 1 atm Density of Water 958.4 kg/m3 Vapour Density 1.422 kg/m3 From the calculation, •The diameter must be large enough •The high of vessel outlet above the gas inlet should be sufficient for liquid drops. •Liquid level will depend on hold up time necessary for smooth operations and control hv=0.283 m3 The conclusion from the calculation, Minimum vessel diameter, Dv = 0.366 m Liquid depth required, hv = 0.238 m3 Height of the tank, H = 1.219 m
  • 41. Mechanical Design of Flash Drum C-104 KHAIRILAZIM (A133275) Parts Value/Description Main Part: •Height •Diameter •Thickness •MAWPvessel 1.219 m 0.366 m 3.5 mm 1.714 kPa Support •Type •Material •Height •Thickness Conical skirt Plain Carbon Steel 0.25 m 3.5 mm Flanges •Feed •Liquid •Vapour Welding neck Welding neck Welding neck Design Summary of C-104 41
  • 42. Properties Value Cooling water flow rate (kg/h) 105458 Water inlet temperature (°C) 37 Water outlet temperature (°C) 28 Ambient wet bulb temperature (°C) 23.9 Tower characteristic, KaL/V 1.5 Minimum tower area (m2) 17 Height of cooling tower (m) 10.4Source : HarrisonCooling Tower 2002 FATIN ATIKAH (A132739) 42
  • 43. Number of tube 43 Length tube 4 m Shell-Side Pressure Drop 78.94 kPa Tube-Side Pressure Drop 1.84 kPa Shell-side coefficient 63.94 W/m2oC Tube-side coefficient 661 W/m2oC Overall heat transfer cofficient, Uo 549.47 W/m2oC Shell and Tube Exchanger FATIN ATIKAH (A132739) 43
  • 44. Parts Value/Description Main Part: •Vessel length •Height vessel •Inner diameter •Outer diameter 4.0 m 0.267 m 0.016 m 0.02 m Support •Type •Material •Height •Thickness Saddle support Carbon Steel 0.8 m 0.15 m Flanges Welding neck Shell and Tube Exchanger Saddle support Welding neck flanges FATIN ATIKAH (A132739) 44
  • 45. T-102 Primary Clarifier A-101 Air Blower T-105 Sludge Storage Tank Check Pond Wastewater from production plant Air Flocculants and Coagulant T-101 T-102 T-103 A-101 T-104 T-105 1 2 3 4 5 7 8 9 10 6 WASTEWATER MANAGEMENT ACTIVATED SLUDGE WASTEWATER TREATMENT PLANT PROCESS FLOW DIAGRAM Stream 1 Flowrate(m3/day) 892.99 S,BOD (mg/L) 362422.7 X, SS (mg/L) 16792.5 Stream 8 Flowrate (m3/day) 0.47 S,BOD (mg/L) - X, SS (mg/L) 5850.5 Stream 7 Flowrate (m3/day) 4.25 S,BOD (mg/L) - X, SS (mg/L) 5850.5 Stream 6 Flowrate(m3/day) 4.72 S,BOD (mg/L) - X, SS (mg/L) 5850.5 Stream 5 Flowrate (m3/day) 884.29 S,BOD (mg/L) 362422.7 X, SS (mg/L) 5940.5 Stream 4 Flowrate(m3/day) 9.45 S,BOD (mg/L) - X, SS (mg/L) 11775.7 Stream 3 Flowrate(m3/day) 883.54 S,BOD (mg/L) 362422.7 X, SS (mg/L) 5016.8 Stream 2 Flowrate (m3/day) 892.99 S,BOD (mg/L) 362422.7 X, SS (mg/L) 16792.5 Stream 10 Flowrate (m3/day) 879.57 S,BOD (mg/L) 45 X, SS (mg/L) 90 Stream 9 Flowrate(m3/day) 9.92 S,BOD (mg/L) - X, SS (mg/L) 12290.9 Flocculation tank Sludge storage tank Aeration tank Secondary clarifier Primary clarifier 46.51 m3 60 min 93.02 m3 SL: 40m3/m2.day 188. 06 m3 Length: 8.17 m Width: 3.8 m Height: 3m 93.02 m3 Length: 9.3 m Width: 5 m Height: 2 m 45
  • 47. Process Hazard Analysis Components Hazardous Properties Glycerol • Flammable • Explosion • Toxic Ammonium phosphate • Toxic Oxygen • Flammable • Toxic Ethanol • Fire • Explosion • Toxic Carbon dioxide • Explosion • Toxic Nitrogen • Toxic Hazard Identification Legal Acts Requirement 1. Environmental Quality Act (EQA) 1974 2. Occupational Safety and Health Act (OSHA) 1994 3. Factory and Machinery Act (FMA) 1967 Methods for PHA: 1. HAZOP analysis 2. FMEA Set of organized and systematic assessments of the potential hazards associated with an industrial process. A PHA provides information intended to assist managers and employees in making decisions for improving safety and reducing the consequences of unwanted or unplanned releases of hazardous chemicals. 47
  • 48. FMEA method - Systematic process to identify potential failures to fulfill the intended function, to identify possible failure and locate the failure impacts - Example of the method is shown in Seed Fermenter F-101 Component Failure mode Failure effects Symptom Safeguard Action Level control valve Valve fails open Valve fails closed Fluid will exceed the level of storage tank causing overflow and rupture the tank Liquid overflow None Schedule inspection and maintenance required Pure glycerol valve Valve fails open No glycerol in the tank. Product produce does not meet the specification. The reaction is not complete None Daily check Temperature control valve Valve fails open High temperature in the tank. It will effect product reaction No cooling water is supply to the tank Low level alarm Daily check Process Hazard Analysis 48
  • 49. Component Failure mode Failure effects Symptom Safeguard Action Heat exchanger Tube failure High pressure and could cause a cause a major fire Odors at the cooling tower None Daily check and schedule maintenance Centrifugal pump Pump stop Loss of power which cause mechanical failure Risk of upstream process pump damage due to overpressure None Preventive maintenance Temperature control valve Heater failure Electric device failure. Loss of electric power May cause over temperature which will rupture the wall None Schedule inspection and maintenance Condenser(Cooler) Power failure Unable to cool the outlet stream Very high temperature is flowing out None Back-up power supply generator Level control valve Valve fails open Valve fails closed Fluid will exceed the level of storage tank causing overflow and Liquid overflow None Schedule inspection and maintenance required - FMEA analysis for Distillation Column C-101 49
  • 50. PROCESS HAZARD ANALYSIS HAZOP Analysis • HAZOP Analysis is to identify how a process deviation can be prevented or mitigate to minimize the potential hazard. Example of the analysis is in the distillation column. Project name : Process Plant Design Process : Bio ethanol production Part : Distillation Column Study node Process parameter Deviations (guide words) Possible causes Possible consequence Action required Stream 28 Flow NO Pipe broken or plugging Loss of feed into column/not achieve into desired output. Level decrease in distillation column. Off specification product. 1. Schedule inspection and maintene.an LOW 1. Pipe partial plugged or leakage. 1. Level decrease in distillation column. 2. Off specification product. 3. Back flow of material. Install check valve. HIGH 1. High pressure from source 1. Flooding in distillation column. 1. Install bypass line with manual valve. Distillation column Level HIGH 1. Output pipe blockage. Overpressure of reflux drum. Condensed liquid flow back to distillation. 1. Install high level alarm 2. Scheduling inspection LOW Pipe partial clogged & leakage. Level decrease in the vessel The valve closed. Back flow of material. 1. Scheduling inspection 2. Install valve. Temperature HIGH 1. Low incoming flow from H-101 cause overheating. Off specification product. Install temperature sensor. LOW 1. H-101 malfunction. 2. High incoming flow through H- 101. Low level inside reboiler. Off specification product. 1. Scheduling inspection 2. Install temperature sensor. 50
  • 51. 51  A high yield and potential for ethanol as fuel from Enterobacter aerogenes. Pengerang has been the best location judging from the coming development as Asia’s largest storage terminal.  Production rate of 3276 kg/hr and high demand in 2018 (projection) will leave a very stable economic growth for ethanol.  65% saving of energy through pinch and heat exchanger installation will further bloom the net profit.  Mechanical calculations and drawings for main utilities provide a clearer insight of the sizing and supports.  Safety has been of top consideration through FMEA and HAZOP performed. Layers of control aspect will further enhance the safety and continuous operation of ethanol plant.  Waste management has been of top priority and calculations from waste treatment plant designed is able to lower down pollutants to allowable limits.