SlideShare ist ein Scribd-Unternehmen logo
1 von 18
Project Auditing
SHOWAIB AHMED CHOWDHURY
Lecturer
Department of Building Engineering & Construction
Management
Rajshahi University of Engineering & Technology(RUET)
Introduction
Project assurance is a fundamental part of effective project
governance.
The project audit is the means to provide that assurance and enables
the sponsor to have confidence that the governance is working and that
the project is being managed as intended.
In this lesson, we will try,
to demonstrate how to plan and undertake a comprehensive audit of a
project, thereby providing that assurance.
to explain the role of an auditor, how it could be planned and
undertaken, the degrees of assurance that can be given, and how
project audits can be aligned to organizational governance.
The three main roles involved in project audits are:
Role Description
Organization board/audit committee/
sponsor/other stakeholders
Those who schedulethe projectauditand
receive the audit findings
Project team
Those whose project is being audited, with
whom the auditors interact
Project auditor(s)
Those who undertake the audit, and report its
findings and make recommendations
For any audit to be successful and provide value to all parties, these
three main roles must work together and understand each other’s
function in the process.
What is project auditing?
According to the Chartered Institute of Internal Auditors,
‘an independent, objective assurance and consulting activity designed
to add value and improve an organization's operations.
It helps an organization accomplish its objectives by bringing a
systematic, disciplined approach to evaluate and improve the
effectiveness of risk management, control, and governance processes’.
In any audit, the auditor(s) perceives and recognizes the propositions
before them for examination, collects evidence, evaluates the same,
and on this basis formulates an opinion on the adequacy of controls
within the activity being audited.
Principles of project audit
Project audit should be:
independent, and supported in this by the organization board;
accountable within a governance and reporting system;
planned and coordinated as part of the organization's
management system;
risk-based, against an independent risk evaluation;
able to allow the impact of identified weaknesses to be
reported and addressed, by follow-up and escalation.
Why do we need project audits?
• The giving of assurance to project stakeholders, including the
organization board, through providing assessment of the likelihood of
the project achieving its objectives, is a fundamental aspect of project
governance
• This assurance will cover the identification and management of risk,
evaluation of opportunities, and actions being taken to realize those
benefits on which approval of the business case was based.
• Assurance also seeks evidence of effective controls and opportunities
to increase the likelihood of success of the project
So, Throughout the phases of a project there should be provision for
independent audit to give assurance to key stakeholders including the
project sponsor and executive board, of the likelihood that the objectives
of the project will be achieved.
The audit will cover the following elements :
• Project definition and requirements management;
• Project organization and governance;
• Risks management;
• Commercial, procurement and commissioning;
• Configuration management, project change controls;
• Project planning and scheduling;
• Performance and benefits management;
• Stakeholder management and communications;
• Organizational capability and culture;
• Social responsibility and sustainability.
Project audit process
Step 1: Planning the audit
• Audit prioritization: Project audits should be planned on the basis of risks to the organization
and to the project.
• Choosing the audit team: The audit team should have access to specialist technical skills e.g.
quality assurance, and should bear in mind the organization's appetite for integrated assurance.
• Information gathering:
Background information Results
1 Project name/reference
2 Brief description of the objectives of the project
3 Project value (total)/(this year)
4 Appropriate (outline or full) business case approved/ date/value
5 Agreed project audit scope, objectives and name/ reference
6
Project governance arrangements including project sponsor,
projectmanager and projectteam
7 Project management arrangements
8 Project phase (Inception, Feasibility, Development, Delivery, Close-out)
9 Overview ofproject controls includingchange controls
10
Project Management Plan (PMP) and Project Initiation Document (PID)
approved date
11 Project audit team details
12 Organization policies andprocedures tobeusedas basis for project audit
13
Extent ofPMO support required including management, cost and
financial reports
14
Risks from corporate and project risk registers, and additional risks from
discussion with stakeholders
15 Project and organization risk management and mitigation measures
16 Integration with other assurance providers
17 Alignment of project with corporate strategy
18 Risk-based audit programmed and schedule
19 Audit reporting details including timetable
20 Significant stakeholders (including their influence and interest)
21 Communications strategy
22 Arrangements tohandovertonextphase,stageor client ofproject
• Risk assessing of a project: This should be carried out by discussion with
stakeholders on risks that they have identified but which have not been
included in the formal register; and on the auditor’s own experience and
discussion with the project team.
• The project audit programme: The audit team should identify the risks
to the project, and the controls and tests which are derived from these. The
different phases of the project life cycle should lead to audit programmed
and tests appropriate to those phases, and to the nature of the project.
2. Fieldwork : The audit team should gather information and
documentation, and talk to key stakeholders including (as appropriate)
members of the project team, the procurement function and the supply chain.
• Elements for review:
 Project definition and requirements management
 Project organization and governance
 Risks management
 Commercial, procurement and commissioning
 Project planning and scheduling
 Performance and benefits management
 Stakeholder management and communications
 Organizational capability and culture
 Social responsibility and sustainability
3. Evaluation and reporting
 Evaluation
• The basic idea is to use a grading score to rank each audited element
and indicate the extent to which the project has performed.
• One method of grading used extensively to measure performance is
the ‘traffic light’ system of three ratings: red/amber/green (RAG).
• During project audits it may be more appropriate to use four or five
ratings, with additional definitions and next steps.
• Definitions of RAG will depend on project and reporting
requirements.
 Reporting
 Individual organizations have their own reporting requirements,
including who should receive the report, who has responsibility for
responding to it, and who will be tasked with implementing its
findings and recommendations.
As some of the content of the report may be commercially or
otherwise sensitive, this should be borne in mind in circulation and
distribution of draft and final reports.
Following a close-out meeting with auditees, the preliminary report
should be prepared and internally reviewed before issue to those
auditees and other stakeholders for comment on findings and
recommendations.
The final report, which should contain the evaluation rating based on
the responses received, should be distributed in accordance with the
requirements of the agreed audit plan. The final report should also be
4. Follow-up
• Follow-up is the final element of the audit process, in which the audit
team confirms that the sponsor and project team have implemented the
agreed actions to address identified project risks and issues.
• This can be confirmed by monitoring the implementation process, or
by accepting a formal statement from the sponsor or project team that
the recommended actions have been carried out.
5. Benefits evaluation
• Where the scope of the project audit included evaluation or auditing of
outcomes on which approval of the business case was, a separate audit
process will be required.
• This will seek to compare recorded benefit outcomes against those
proposed in the business case through the use of defined benefit
measures, normally by quantitative methods.
6. Legacy and lessons learned
• The results of project audits can provide valuable reference
points for the organisation’s legacy and lessons learned
process. The audit team should be aware of the organisation’s
requirements for confidentiality if involved in the legacy and
lessons learned process.
• The organization may operate a legacy programme, to capture
the intellectual capital within a project before the project
team is disbanded.
• Prepare a mid-term audit report for a building construction project
which have a budgeted cost at TK. 1000000 with a total project
duration 8 months, Also consider at the time of mid-term 40%
construction work is completed at a cost of TK 600000.
Solution:
Auditor:
Audit-Team:
Date of Audit:
Project Audited:
Project Manager:
Introduction:
General Analysis of the project by EVM:
Budget at completion(BAC) : 1000000TK
Completion Period: 8 months
Actual cost(AC): 600000TK
Earned Value(EV)= 40% * 1000000 = 400000TK
Planned Value(PV)= 50% * 1000000 = 500000TK
Cost Variance, CV= EV-AC = -200000TK
Schedule Variance, SV= EV-PV= -100000TK
Cost Performance Index, CPI= EV/AC= 0.67<1
Schedule Performance Index, SPI= EV/PV= 0.8<1
• Current Status:
• Future Projection:
• Critical Management issues:
• Risk Analysis and Risk Management:

Weitere ähnliche Inhalte

Was ist angesagt?

Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoring
haroldtaylor1113
 

Was ist angesagt? (20)

Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoring
 
Project monitoring and control &amp; planning for monitoring
Project monitoring and control &amp; planning for monitoringProject monitoring and control &amp; planning for monitoring
Project monitoring and control &amp; planning for monitoring
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS
 
Project Execution
Project ExecutionProject Execution
Project Execution
 
PROJECT LIFE CYCLE
PROJECT LIFE CYCLEPROJECT LIFE CYCLE
PROJECT LIFE CYCLE
 
Project management life cycle
Project management life cycleProject management life cycle
Project management life cycle
 
PMP / Framework 1 2-3
PMP / Framework 1 2-3PMP / Framework 1 2-3
PMP / Framework 1 2-3
 
PROJECT PLANNING AND MANAGEMENT
PROJECT PLANNING AND MANAGEMENTPROJECT PLANNING AND MANAGEMENT
PROJECT PLANNING AND MANAGEMENT
 
Presentation on Cost Overrun ( Project Management)
Presentation on Cost Overrun ( Project Management)Presentation on Cost Overrun ( Project Management)
Presentation on Cost Overrun ( Project Management)
 
Project planning
Project planning Project planning
Project planning
 
Project cost management-slides
Project cost management-slidesProject cost management-slides
Project cost management-slides
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
 
Project Planning
Project PlanningProject Planning
Project Planning
 
project life cycle
project life cycleproject life cycle
project life cycle
 
Project management and project life cycle
Project management and project life cycleProject management and project life cycle
Project management and project life cycle
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
Ppt on project appraisal
Ppt on project appraisalPpt on project appraisal
Ppt on project appraisal
 

Ähnlich wie Project Auditing

Auditing projects in the early stages.pdf
Auditing projects in the early stages.pdfAuditing projects in the early stages.pdf
Auditing projects in the early stages.pdf
Addisu15
 
5. project activity and risk planning
5. project activity and risk planning5. project activity and risk planning
5. project activity and risk planning
Jeanette C. Patindol
 
The funkiest PRINCE2 Processes revision guide on the internet
The funkiest PRINCE2 Processes revision guide on the internetThe funkiest PRINCE2 Processes revision guide on the internet
The funkiest PRINCE2 Processes revision guide on the internet
Knowledge Train
 
PMP Training - 04 project integration management
PMP Training - 04 project integration managementPMP Training - 04 project integration management
PMP Training - 04 project integration management
ejlp12
 
BSBPMG522 Undertake project work1HousekeepingE.docx
BSBPMG522 Undertake project work1HousekeepingE.docxBSBPMG522 Undertake project work1HousekeepingE.docx
BSBPMG522 Undertake project work1HousekeepingE.docx
curwenmichaela
 
BSBPMG522 Undertake project work1Housekeeping.docx
BSBPMG522 Undertake project work1Housekeeping.docxBSBPMG522 Undertake project work1Housekeeping.docx
BSBPMG522 Undertake project work1Housekeeping.docx
jasoninnes20
 

Ähnlich wie Project Auditing (20)

a-guide-to-project-auditing.pdf
a-guide-to-project-auditing.pdfa-guide-to-project-auditing.pdf
a-guide-to-project-auditing.pdf
 
pmi project management principles.pptx
pmi project management principles.pptxpmi project management principles.pptx
pmi project management principles.pptx
 
Auditing projects in the early stages.pdf
Auditing projects in the early stages.pdfAuditing projects in the early stages.pdf
Auditing projects in the early stages.pdf
 
Topic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdfTopic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdf
 
5. project activity and risk planning
5. project activity and risk planning5. project activity and risk planning
5. project activity and risk planning
 
APM Practitioner Qualification revision cards
APM Practitioner Qualification revision cardsAPM Practitioner Qualification revision cards
APM Practitioner Qualification revision cards
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
 
GROUP-4-PRESENTATION-FINAL.pptx
GROUP-4-PRESENTATION-FINAL.pptxGROUP-4-PRESENTATION-FINAL.pptx
GROUP-4-PRESENTATION-FINAL.pptx
 
ICB Competence, Project Standards
ICB Competence, Project StandardsICB Competence, Project Standards
ICB Competence, Project Standards
 
Project Management U 1.pptx
Project Management U 1.pptxProject Management U 1.pptx
Project Management U 1.pptx
 
Pmi dec 13
Pmi dec 13Pmi dec 13
Pmi dec 13
 
The funkiest PRINCE2 Processes revision guide on the internet
The funkiest PRINCE2 Processes revision guide on the internetThe funkiest PRINCE2 Processes revision guide on the internet
The funkiest PRINCE2 Processes revision guide on the internet
 
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
 
Unit2 Project phases.pptx
Unit2 Project phases.pptxUnit2 Project phases.pptx
Unit2 Project phases.pptx
 
PMP Training - 04 project integration management
PMP Training - 04 project integration managementPMP Training - 04 project integration management
PMP Training - 04 project integration management
 
Lec-13-PM-F21 (1).pptxdoneanddustedreadytouse
Lec-13-PM-F21 (1).pptxdoneanddustedreadytouseLec-13-PM-F21 (1).pptxdoneanddustedreadytouse
Lec-13-PM-F21 (1).pptxdoneanddustedreadytouse
 
Basics in Project Management
Basics in Project ManagementBasics in Project Management
Basics in Project Management
 
BSBPMG522 Undertake project work1HousekeepingE.docx
BSBPMG522 Undertake project work1HousekeepingE.docxBSBPMG522 Undertake project work1HousekeepingE.docx
BSBPMG522 Undertake project work1HousekeepingE.docx
 
BSBPMG522 Undertake project work1Housekeeping.docx
BSBPMG522 Undertake project work1Housekeeping.docxBSBPMG522 Undertake project work1Housekeeping.docx
BSBPMG522 Undertake project work1Housekeeping.docx
 
Ngo’s project management
Ngo’s project managementNgo’s project management
Ngo’s project management
 

Mehr von BECM, RUET, Bangladesh

Mehr von BECM, RUET, Bangladesh (6)

BECM 4103: Lecture 2 On site human waste management
BECM 4103: Lecture 2 On site human waste managementBECM 4103: Lecture 2 On site human waste management
BECM 4103: Lecture 2 On site human waste management
 
Introduction to environmental sanitation
Introduction to environmental sanitationIntroduction to environmental sanitation
Introduction to environmental sanitation
 
Introduction to sustainability
Introduction to sustainabilityIntroduction to sustainability
Introduction to sustainability
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Risk analysis
Risk analysisRisk analysis
Risk analysis
 
Project monitoring lecture 1
Project monitoring lecture 1Project monitoring lecture 1
Project monitoring lecture 1
 

Kürzlich hochgeladen

Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Christo Ananth
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Kürzlich hochgeladen (20)

Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICS
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICSUNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICS
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICS
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 

Project Auditing

  • 1. Project Auditing SHOWAIB AHMED CHOWDHURY Lecturer Department of Building Engineering & Construction Management Rajshahi University of Engineering & Technology(RUET)
  • 2. Introduction Project assurance is a fundamental part of effective project governance. The project audit is the means to provide that assurance and enables the sponsor to have confidence that the governance is working and that the project is being managed as intended. In this lesson, we will try, to demonstrate how to plan and undertake a comprehensive audit of a project, thereby providing that assurance. to explain the role of an auditor, how it could be planned and undertaken, the degrees of assurance that can be given, and how project audits can be aligned to organizational governance.
  • 3. The three main roles involved in project audits are: Role Description Organization board/audit committee/ sponsor/other stakeholders Those who schedulethe projectauditand receive the audit findings Project team Those whose project is being audited, with whom the auditors interact Project auditor(s) Those who undertake the audit, and report its findings and make recommendations For any audit to be successful and provide value to all parties, these three main roles must work together and understand each other’s function in the process.
  • 4. What is project auditing? According to the Chartered Institute of Internal Auditors, ‘an independent, objective assurance and consulting activity designed to add value and improve an organization's operations. It helps an organization accomplish its objectives by bringing a systematic, disciplined approach to evaluate and improve the effectiveness of risk management, control, and governance processes’. In any audit, the auditor(s) perceives and recognizes the propositions before them for examination, collects evidence, evaluates the same, and on this basis formulates an opinion on the adequacy of controls within the activity being audited.
  • 5. Principles of project audit Project audit should be: independent, and supported in this by the organization board; accountable within a governance and reporting system; planned and coordinated as part of the organization's management system; risk-based, against an independent risk evaluation; able to allow the impact of identified weaknesses to be reported and addressed, by follow-up and escalation.
  • 6. Why do we need project audits? • The giving of assurance to project stakeholders, including the organization board, through providing assessment of the likelihood of the project achieving its objectives, is a fundamental aspect of project governance • This assurance will cover the identification and management of risk, evaluation of opportunities, and actions being taken to realize those benefits on which approval of the business case was based. • Assurance also seeks evidence of effective controls and opportunities to increase the likelihood of success of the project So, Throughout the phases of a project there should be provision for independent audit to give assurance to key stakeholders including the project sponsor and executive board, of the likelihood that the objectives of the project will be achieved.
  • 7. The audit will cover the following elements : • Project definition and requirements management; • Project organization and governance; • Risks management; • Commercial, procurement and commissioning; • Configuration management, project change controls; • Project planning and scheduling; • Performance and benefits management; • Stakeholder management and communications; • Organizational capability and culture; • Social responsibility and sustainability.
  • 8. Project audit process Step 1: Planning the audit • Audit prioritization: Project audits should be planned on the basis of risks to the organization and to the project. • Choosing the audit team: The audit team should have access to specialist technical skills e.g. quality assurance, and should bear in mind the organization's appetite for integrated assurance. • Information gathering: Background information Results 1 Project name/reference 2 Brief description of the objectives of the project 3 Project value (total)/(this year) 4 Appropriate (outline or full) business case approved/ date/value 5 Agreed project audit scope, objectives and name/ reference 6 Project governance arrangements including project sponsor, projectmanager and projectteam 7 Project management arrangements
  • 9. 8 Project phase (Inception, Feasibility, Development, Delivery, Close-out) 9 Overview ofproject controls includingchange controls 10 Project Management Plan (PMP) and Project Initiation Document (PID) approved date 11 Project audit team details 12 Organization policies andprocedures tobeusedas basis for project audit 13 Extent ofPMO support required including management, cost and financial reports 14 Risks from corporate and project risk registers, and additional risks from discussion with stakeholders 15 Project and organization risk management and mitigation measures 16 Integration with other assurance providers 17 Alignment of project with corporate strategy 18 Risk-based audit programmed and schedule 19 Audit reporting details including timetable 20 Significant stakeholders (including their influence and interest) 21 Communications strategy 22 Arrangements tohandovertonextphase,stageor client ofproject
  • 10. • Risk assessing of a project: This should be carried out by discussion with stakeholders on risks that they have identified but which have not been included in the formal register; and on the auditor’s own experience and discussion with the project team. • The project audit programme: The audit team should identify the risks to the project, and the controls and tests which are derived from these. The different phases of the project life cycle should lead to audit programmed and tests appropriate to those phases, and to the nature of the project.
  • 11. 2. Fieldwork : The audit team should gather information and documentation, and talk to key stakeholders including (as appropriate) members of the project team, the procurement function and the supply chain. • Elements for review:  Project definition and requirements management  Project organization and governance  Risks management  Commercial, procurement and commissioning  Project planning and scheduling  Performance and benefits management  Stakeholder management and communications  Organizational capability and culture  Social responsibility and sustainability
  • 12. 3. Evaluation and reporting  Evaluation • The basic idea is to use a grading score to rank each audited element and indicate the extent to which the project has performed. • One method of grading used extensively to measure performance is the ‘traffic light’ system of three ratings: red/amber/green (RAG). • During project audits it may be more appropriate to use four or five ratings, with additional definitions and next steps. • Definitions of RAG will depend on project and reporting requirements.
  • 13.  Reporting  Individual organizations have their own reporting requirements, including who should receive the report, who has responsibility for responding to it, and who will be tasked with implementing its findings and recommendations. As some of the content of the report may be commercially or otherwise sensitive, this should be borne in mind in circulation and distribution of draft and final reports. Following a close-out meeting with auditees, the preliminary report should be prepared and internally reviewed before issue to those auditees and other stakeholders for comment on findings and recommendations. The final report, which should contain the evaluation rating based on the responses received, should be distributed in accordance with the requirements of the agreed audit plan. The final report should also be
  • 14. 4. Follow-up • Follow-up is the final element of the audit process, in which the audit team confirms that the sponsor and project team have implemented the agreed actions to address identified project risks and issues. • This can be confirmed by monitoring the implementation process, or by accepting a formal statement from the sponsor or project team that the recommended actions have been carried out. 5. Benefits evaluation • Where the scope of the project audit included evaluation or auditing of outcomes on which approval of the business case was, a separate audit process will be required. • This will seek to compare recorded benefit outcomes against those proposed in the business case through the use of defined benefit measures, normally by quantitative methods.
  • 15. 6. Legacy and lessons learned • The results of project audits can provide valuable reference points for the organisation’s legacy and lessons learned process. The audit team should be aware of the organisation’s requirements for confidentiality if involved in the legacy and lessons learned process. • The organization may operate a legacy programme, to capture the intellectual capital within a project before the project team is disbanded.
  • 16. • Prepare a mid-term audit report for a building construction project which have a budgeted cost at TK. 1000000 with a total project duration 8 months, Also consider at the time of mid-term 40% construction work is completed at a cost of TK 600000. Solution: Auditor: Audit-Team: Date of Audit: Project Audited: Project Manager: Introduction:
  • 17. General Analysis of the project by EVM: Budget at completion(BAC) : 1000000TK Completion Period: 8 months Actual cost(AC): 600000TK Earned Value(EV)= 40% * 1000000 = 400000TK Planned Value(PV)= 50% * 1000000 = 500000TK Cost Variance, CV= EV-AC = -200000TK Schedule Variance, SV= EV-PV= -100000TK Cost Performance Index, CPI= EV/AC= 0.67<1 Schedule Performance Index, SPI= EV/PV= 0.8<1
  • 18. • Current Status: • Future Projection: • Critical Management issues: • Risk Analysis and Risk Management: