Symbiosis Institute of
Management Studies (SIMS)
Project Management

PERT,CPM, Resource Allocation
and GERT
Manuja Goenka, E-12
Raj Jyoti Das-E-13
August 2013
Tools for Scheduling
• Two commonly used network methods for
planning and scheduling are:
1. Program Evaluation and Review Techniques
(PERT)
2. Critical path Method (CPM)
*Both PERT & CPM are termed critical path methods
History of PERT
• Project Evaluation and Review Technique (PERT)
– U S Navy (1958) for the POLARIS missile program
– Multiple task time estimates (probabilistic nature)
PERT
• PERT is based on the assumption that an activity’s
duration follows a probability distribution instead of
being a single value
• Three time estimates are required to compute the
parameters of an activity’s duration distribution:
– pessimistic time (a) - the time the activity would take
if things did not go well
– most likely time (m ) - the consensus best estimate of
the activity’s duration
– optimistic time (b) - the time the activity would take if
things did go well
a + 4m + b
Mean (expected time):te =

Variance: V =

6

b- a
6

2
Three Time Estimates of PERT
PERT uses three time estimates to address uncertainty of
project duration-

•Optimistic
•Most Likely
•Pessimistic
Mean or expected Time
It is the time where there is 50-50 chances that the activity will be
completed earlier or later than it.

For this case :
Variance
Variance is measure of variability in the activity completion
period.

The larger V, the less reliable te
The Expected Duration Of The Project
The expected duration of the project (Te) is the
sum of the expected activity times along the
critical path

Te = ∑ te
Where te are expected times of the activities on
the critical path
The Variation In The Project Duration
The variation in the project duration
distribution is computed as the sum of the
variances of the activity durations along the
critical path:
Vp = ∑ V

Where V is the variance of critical path
Near Critical Path
Path
(events)

Te = ∑ te

Vp = ∑ V

1-2-6-8

28**

6.34

1-7-8

20

17.00

1-2-5-7-8

Te=29*

Vp=6.00

1-4-5-7-8

18

3.89

1-3-4-5-78

27**

12.00
Probability of Finishing a Project
Let us assume,
Expected completion duration of a project = 29 weeks
Variance of the project duration = 6
Then what will be the probability of finishing the project by 27
weeks can be calculated by the formula:
Probability

Therefore,
Z=(27-29)/2.449
=-0.82
Prob. Of finishing the
project by 27 weeks
is app. 21%

Z
0.207
27
darla/smbs/vit

29

Time
11
History of Critical Path Method (CPM)
• E I Du Pont de Nemours & Co. (1957) for construction
of new chemical plant and maintenance shut-down
• CPM is a “Deterministic” approach
• CPM includes mathematical procedure for estimating
the trade off between project duration and project
cost
• CPM emphasis on applying additional resources to
particular key activities
Time-Cost Relationship

Normal Time, Tn: It is the time taken by an activity
under normal work conditions
Normal Cost, Cn: The cost incurred in doing an activity
in normal time.
Crashing
An activity is said to be crashed when maximum effort is
applied to finish that activity in the shortest possible
time.
Cost Slope
• The cost slope shows
by how much the cost
of job would change if
activities were speed
up or slowed down.

In this case,
Cost Slope= (18-9)/(5-8) = $3 K/week
CPM calculation
• Path
– A connected sequence of activities leading from
the starting event to the ending event

• Critical Path
– The longest path (time); determines the project
duration

• Critical Activities
– All of the activities that make up the critical path
CPM calculation
Forward Pass
• Earliest Start Time (ES)
– earliest time an activity can start
– ES = maximum EF of immediate predecessors
• Earliest finish time (EF)
– earliest time an activity can finish
– earliest start time plus activity time (EF= ES + t)

Backward Pass
Latest Start Time (LS)
Latest time an activity can start without delaying critical path time
LS= LF - t
Latest finish time (LF)
latest time an activity can be completed without delaying critical path time
LS = minimum LS of immediate predecessors
Project Crashing
• Crashing
– reducing project time by expending additional resources
• Crash time
– an amount of time an activity is reduced
• Crash cost
– cost of reducing activity time
• Goal
– reduce project duration at minimum cost
Time-Cost Relationship
 Crashing costs increase as project duration decreases
 Indirect costs increase as project duration increases
 Reduce project length as long as crashing costs are less than
indirect costs

Time-Cost Tradeoff
Total project cost
Indirect cost

Direct cost

time
Crashing Example
9
9

C
5

A

0

F
5

9
0

17

14

D

8

B

22
G

E

8

22

7

5
17

Activi
ty

17

Normal
(Wks)

Crush
(Wks)

10

Tn

Cn

A

8

Tc

Cost
Slope
(K$)

Cc

9

10 6

16 2

B

8

9

5

18 3

C

5

7

4

8

D

8

9

6

19 5

E

7

7

3

15 2

F

5

5

5

5

G

5

8

2

23 5

1

-
9
9

C
5

A
0

9
0

17

14

F
5

D
8

22

G

B

E

8

7
8

5
17

22

17

Critical Path A-D-G=22wks
10
Types of Project Constraints
• Technical or Logic Constraints
– Constraints related to the networked sequence in
which project activities must occur.

• Physical Constraints
– Activities that cannot occur in parallel or are affected
by contractual or environmental conditions.

• Resource Constraints
– The absence, shortage, or unique interrelationship
and interaction characteristics of resources that
require a particular sequencing of project activities.
The Resource Problem
• Resources and Priorities
– Project network times are not a schedule until
resources have been assigned.
• The implicit assumption is that resources will be available in
the required amounts when needed.
• Adding new projects requires making realistic judgments of
resource availability and project durations.

• Resource-Constrained Scheduling
– Resource leveling (or smoothing) involves attempting
to even out demands on resources by using slack
(delaying noncritical activities) to manage resource
utilization.
Kinds of Resource Constraints

• People
• Materials
• Equipment
• Working Capital
Classification of A Scheduling
Problem
• Time Constrained Project
– A project that must be completed by an imposed
date.
• Time is fixed, resources are flexible: additional
resources are required to ensure project meets
schedule.

• Resource Constrained Project
– A project in which the level of resources available
cannot be exceeded.
• Resources are fixed, time is flexible: inadequate
resources will delay the project.
Example :
• Without resource constraints relatively easy
• With resource constraints very complex:
when jobs share resources with limited
availability, these jobs cannot be processed
simultaneously

Jobs
p(j)
R(1,j)
R(2,j)

1
8
2
3

2
4
1
0

3
6
3
4

4
4
1
0

5
4
2
3

Resource
Available

R1
4

R2
8

1

4

2

5

3
27
S 'j  earliest possible starting time of job j
C 'j  earliest possible completion time of job j
C ''  latest possible completion time of job j
j
slack j  C ''  p j  S 'j
j

28
Resource constraints
• Suppose jobs require a resource:
Job p(j) Predecessors S' C'' R(1,j)
1 2
0 3
3
2 3
0 3
1
3 1
0 6
2
4 4
1,2
3 7
2
5 2
2,3
3 8
3
6 1
4
7 8
3

6
5

3

4
3

2

5

2
1

resource requirements

1

6
4
1

2

3

4

5

6

7

8
29
Resource constraints (cont.)
• Suppose R 1  4 :
6
5
4
3

2

2
1

1
3
1

2

5
4
3

4

5

6

7

6

8

9

10

Cmax increases by 2
30
Resource-Constrained Project
Scheduling Problem (RCPSP)
•
•
•
•
•
•

n jobs j=1,…,n
N resources i=1,…,N
Rk:availability of resource k
pj: duration of job j
Rkj:requirement of resource k for job j
Pj: (immediate) predecessors of job j

31
RCPSP
• Goal: minimize makespan: Cmax  max C
j
• Restrictions:

'
j

– no job may start before T=0
– precedence relations
– finite resource capacity

32
RCPSP
example

Job p(j) P(j) S' C'' R(1,j) R(2,j)
1
2
- 0 3
3
2
2
3
- 0 3
1
1
3
1
- 0 6
2
1
4
4 1,2 3 7
2
1
5
2 2,3 3 8
3
2
6
1
4 7 8
3
1
4

R1  4

2

2
1

0

2

2

R2  2

4

3
2

1
0

6 5

3 4

2

6

8

4
4

10

6
6

8

5
10

12

33
Loading And Leveling
• Loading- amount of a resource necessary to
conduct a project
– Depends on the requirements of individual
activities.
– Changes throughout a project

• Resource Leveling- process of scheduling
activities so that the amount of a certain
required resource is balanced throughout the
resource.
Multiproject Resource Schedules
• Multiproject Scheduling Problems
– Overall project slippage
• Delay on one project create delays for other projects

– Inefficient resource application
• The peaks and valleys of resource demands create
scheduling problems and delays for projects.

– Resource bottlenecks
• Shortages of critical resources required for multiple
projects cause delays and schedule extensions.
Multiproject Resource Schedules
• Managing Multiproject Scheduling
– Create project offices or departments to oversee
the scheduling of resources across projects.
– Use a project priority queuing system: first come,
first served for resources.
– Centralize project management: treat all projects
as a part of a “megaproject.”
– Outsource projects to reduce the number of
projects handled internally.
Limitations of PERT/CPM

• All immediate predecessor activities must be
completed before a given activity can be started.
• No activity can be repeated and no “looping
back”
• Duration time for an activity is restricted to Beta
Distribution PERT and a single estimate in CPM.
• Critical Path is always considered the longest.
• There is only one terminal event and the only
way to reach it is by completing all activities in
the project
GERT
• A network analysis technique used in project
management.
• It allows probabilistic treatment of both network logic
and activity duration estimated.
• The technique was first described in 1966 by Dr. Alan
B. Pritsker of Purdue University and WW Happ.
• Compared to other techniques, GERT is an only rarely
used scheduling technique.
Contd..
• Utilizes probabilistic and branching nodes
• It represents the node will be reached if any m
of its p immediate predecessors are
completed.
m

n

p
Contd..
• It represents a probabilistic output where any
of q outputs are possible
• Each branch has an assigned probability
• When no probability is given, the probability is
assumed to be one for each branch.
1
2

q
Example
Thank YOu

Weitere ähnliche Inhalte

Was ist angesagt?

Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTS.Vijaya Bhaskar
 
Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysisHarinadh Karimikonda
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource SmoothingDavidMcLachlan1
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure pptnazi2020
 
Project management tools and techniques
Project management tools and techniquesProject management tools and techniques
Project management tools and techniquesTata Dinyuy
 
Attributes of Project Manager
Attributes of Project ManagerAttributes of Project Manager
Attributes of Project ManagerKhurram Shakeel
 
Difference between PERT and CPM
Difference between PERT and CPMDifference between PERT and CPM
Difference between PERT and CPMMunaf Dayee
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
Pert and its applications
Pert and its applicationsPert and its applications
Pert and its applicationsAmrit Mty
 
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Zulfiquer Ahmed Amin
 

Was ist angesagt? (20)

Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysis
 
Cpm pert
Cpm pertCpm pert
Cpm pert
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Evolution of project management
Evolution of project managementEvolution of project management
Evolution of project management
 
Project management
Project managementProject management
Project management
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
 
Project Management - Critical path method
Project Management - Critical path methodProject Management - Critical path method
Project Management - Critical path method
 
Pert, cpm & gert
Pert, cpm & gertPert, cpm & gert
Pert, cpm & gert
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
 
Assignment project scheduling
Assignment project schedulingAssignment project scheduling
Assignment project scheduling
 
Project management tools and techniques
Project management tools and techniquesProject management tools and techniques
Project management tools and techniques
 
Network Techniques
Network TechniquesNetwork Techniques
Network Techniques
 
Attributes of Project Manager
Attributes of Project ManagerAttributes of Project Manager
Attributes of Project Manager
 
Difference between PERT and CPM
Difference between PERT and CPMDifference between PERT and CPM
Difference between PERT and CPM
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Pert and its applications
Pert and its applicationsPert and its applications
Pert and its applications
 
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
 

Andere mochten auch

Planning, scheduling and resource allocation
Planning, scheduling and resource allocationPlanning, scheduling and resource allocation
Planning, scheduling and resource allocationJatin Mandhyan
 
Resource planning and resource allocation
Resource planning and resource allocationResource planning and resource allocation
Resource planning and resource allocationVenu Yemul
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERTPulchowk Campus
 
Pert, cpm and other tools of project management for intrapreneurs
Pert, cpm and other tools of project management for  intrapreneurs  Pert, cpm and other tools of project management for  intrapreneurs
Pert, cpm and other tools of project management for intrapreneurs Dr. Trilok Kumar Jain
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource SchedulingNicola2903
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)Debanjan15
 
Project management cpm-pert
Project management   cpm-pertProject management   cpm-pert
Project management cpm-pertAbu Bashar
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTsalsa moyara
 
Improving Resource Utilization in Cloud using Application Placement Heuristics
Improving Resource Utilization in Cloud using Application Placement HeuristicsImproving Resource Utilization in Cloud using Application Placement Heuristics
Improving Resource Utilization in Cloud using Application Placement HeuristicsAtakanAral
 
Managing Innovation_Introduction to Innovation
Managing Innovation_Introduction to InnovationManaging Innovation_Introduction to Innovation
Managing Innovation_Introduction to InnovationOpenLearningLab
 
Cpm and pert - project management
Cpm and pert - project managementCpm and pert - project management
Cpm and pert - project managementExam Coach
 
Risk Management of a PPP programme
Risk Management of a PPP programmeRisk Management of a PPP programme
Risk Management of a PPP programmeAudrey Mwala
 
Spm unit iii-risk-resource allocation
Spm unit iii-risk-resource allocationSpm unit iii-risk-resource allocation
Spm unit iii-risk-resource allocationKanchana Devi
 

Andere mochten auch (20)

Resource allocation
Resource allocationResource allocation
Resource allocation
 
Planning, scheduling and resource allocation
Planning, scheduling and resource allocationPlanning, scheduling and resource allocation
Planning, scheduling and resource allocation
 
Resource planning and resource allocation
Resource planning and resource allocationResource planning and resource allocation
Resource planning and resource allocation
 
Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
 
Pert, cpm and other tools of project management for intrapreneurs
Pert, cpm and other tools of project management for  intrapreneurs  Pert, cpm and other tools of project management for  intrapreneurs
Pert, cpm and other tools of project management for intrapreneurs
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource Scheduling
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
Project Management101
Project Management101Project Management101
Project Management101
 
Project management cpm-pert
Project management   cpm-pertProject management   cpm-pert
Project management cpm-pert
 
PERT CPM Intro
PERT CPM IntroPERT CPM Intro
PERT CPM Intro
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
 
Pert
PertPert
Pert
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Improving Resource Utilization in Cloud using Application Placement Heuristics
Improving Resource Utilization in Cloud using Application Placement HeuristicsImproving Resource Utilization in Cloud using Application Placement Heuristics
Improving Resource Utilization in Cloud using Application Placement Heuristics
 
Managing Innovation_Introduction to Innovation
Managing Innovation_Introduction to InnovationManaging Innovation_Introduction to Innovation
Managing Innovation_Introduction to Innovation
 
Cpm and pert - project management
Cpm and pert - project managementCpm and pert - project management
Cpm and pert - project management
 
Risk Management of a PPP programme
Risk Management of a PPP programmeRisk Management of a PPP programme
Risk Management of a PPP programme
 
Spm unit iii-risk-resource allocation
Spm unit iii-risk-resource allocationSpm unit iii-risk-resource allocation
Spm unit iii-risk-resource allocation
 

Ähnlich wie Pert,cpm, resource allocation and gert

PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersIIMSE Edu
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering EconomicsDeepak Paithankar
 
Scheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.pptScheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.pptTecnicoItca
 
chapter 6.ppt
chapter 6.pptchapter 6.ppt
chapter 6.pptDejeneDay
 
13 lecture project management
13 lecture project management13 lecture project management
13 lecture project managementAhmad Basim Hamza
 
Scheduling resources and costs is a crucial aspect of project management that...
Scheduling resources and costs is a crucial aspect of project management that...Scheduling resources and costs is a crucial aspect of project management that...
Scheduling resources and costs is a crucial aspect of project management that...THULASIMANOHARAN2
 
Lecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptxLecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptxTecnicoItca
 
C03.05-Scheduling.key.pdf
C03.05-Scheduling.key.pdfC03.05-Scheduling.key.pdf
C03.05-Scheduling.key.pdfssuser8babb7
 
PM-Chapter8-1.pptx
PM-Chapter8-1.pptxPM-Chapter8-1.pptx
PM-Chapter8-1.pptxTecnicoItca
 
08. Project Time Management Upload
08. Project Time Management Upload08. Project Time Management Upload
08. Project Time Management UploadBhuWan Khadka
 
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLSiddanna Balapgol
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02kongara
 
L2_Project_Management.pdf
L2_Project_Management.pdfL2_Project_Management.pdf
L2_Project_Management.pdfJerryHung19
 
Traditional Management System.ppt
Traditional Management System.pptTraditional Management System.ppt
Traditional Management System.pptUtkarshDwivedi74
 

Ähnlich wie Pert,cpm, resource allocation and gert (20)

PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For Beginners
 
Unit IV-Project Management
Unit IV-Project ManagementUnit IV-Project Management
Unit IV-Project Management
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
 
Scheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.pptScheduling-Resources-and-Costs.ppt
Scheduling-Resources-and-Costs.ppt
 
chapter 6.ppt
chapter 6.pptchapter 6.ppt
chapter 6.ppt
 
13 lecture project management
13 lecture project management13 lecture project management
13 lecture project management
 
PM-Problems.pptx
PM-Problems.pptxPM-Problems.pptx
PM-Problems.pptx
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
 
Scheduling resources and costs is a crucial aspect of project management that...
Scheduling resources and costs is a crucial aspect of project management that...Scheduling resources and costs is a crucial aspect of project management that...
Scheduling resources and costs is a crucial aspect of project management that...
 
Lecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptxLecture-8-Scheduling-Resources-and-Cost.pptx
Lecture-8-Scheduling-Resources-and-Cost.pptx
 
C03.05-Scheduling.key.pdf
C03.05-Scheduling.key.pdfC03.05-Scheduling.key.pdf
C03.05-Scheduling.key.pdf
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
PM-Chapter8-1.pptx
PM-Chapter8-1.pptxPM-Chapter8-1.pptx
PM-Chapter8-1.pptx
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
 
08. Project Time Management Upload
08. Project Time Management Upload08. Project Time Management Upload
08. Project Time Management Upload
 
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOL
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02
 
L2_Project_Management.pdf
L2_Project_Management.pdfL2_Project_Management.pdf
L2_Project_Management.pdf
 
PERT
PERTPERT
PERT
 
Traditional Management System.ppt
Traditional Management System.pptTraditional Management System.ppt
Traditional Management System.ppt
 

Kürzlich hochgeladen

Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clashcharlottematthew16
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Enterprise Knowledge
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 3652toLead Limited
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupFlorian Wilhelm
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Mattias Andersson
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenHervé Boutemy
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024Stephanie Beckett
 
My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024The Digital Insurer
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek SchlawackFwdays
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyAlfredo García Lavilla
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfAddepto
 
The Future of Software Development - Devin AI Innovative Approach.pdf
The Future of Software Development - Devin AI Innovative Approach.pdfThe Future of Software Development - Devin AI Innovative Approach.pdf
The Future of Software Development - Devin AI Innovative Approach.pdfSeasiaInfotech2
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsRizwan Syed
 
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Wonjun Hwang
 

Kürzlich hochgeladen (20)

Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clash
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project Setup
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache Maven
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024
 
My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024
 
DMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special EditionDMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special Edition
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easy
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdf
 
The Future of Software Development - Devin AI Innovative Approach.pdf
The Future of Software Development - Devin AI Innovative Approach.pdfThe Future of Software Development - Devin AI Innovative Approach.pdf
The Future of Software Development - Devin AI Innovative Approach.pdf
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL Certs
 
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
 
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptxE-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
 

Pert,cpm, resource allocation and gert

  • 1. Symbiosis Institute of Management Studies (SIMS) Project Management PERT,CPM, Resource Allocation and GERT Manuja Goenka, E-12 Raj Jyoti Das-E-13 August 2013
  • 2. Tools for Scheduling • Two commonly used network methods for planning and scheduling are: 1. Program Evaluation and Review Techniques (PERT) 2. Critical path Method (CPM) *Both PERT & CPM are termed critical path methods
  • 3. History of PERT • Project Evaluation and Review Technique (PERT) – U S Navy (1958) for the POLARIS missile program – Multiple task time estimates (probabilistic nature)
  • 4. PERT • PERT is based on the assumption that an activity’s duration follows a probability distribution instead of being a single value • Three time estimates are required to compute the parameters of an activity’s duration distribution: – pessimistic time (a) - the time the activity would take if things did not go well – most likely time (m ) - the consensus best estimate of the activity’s duration – optimistic time (b) - the time the activity would take if things did go well a + 4m + b Mean (expected time):te = Variance: V = 6 b- a 6 2
  • 5. Three Time Estimates of PERT PERT uses three time estimates to address uncertainty of project duration- •Optimistic •Most Likely •Pessimistic
  • 6. Mean or expected Time It is the time where there is 50-50 chances that the activity will be completed earlier or later than it. For this case :
  • 7. Variance Variance is measure of variability in the activity completion period. The larger V, the less reliable te
  • 8. The Expected Duration Of The Project The expected duration of the project (Te) is the sum of the expected activity times along the critical path Te = ∑ te Where te are expected times of the activities on the critical path
  • 9. The Variation In The Project Duration The variation in the project duration distribution is computed as the sum of the variances of the activity durations along the critical path: Vp = ∑ V Where V is the variance of critical path
  • 10. Near Critical Path Path (events) Te = ∑ te Vp = ∑ V 1-2-6-8 28** 6.34 1-7-8 20 17.00 1-2-5-7-8 Te=29* Vp=6.00 1-4-5-7-8 18 3.89 1-3-4-5-78 27** 12.00
  • 11. Probability of Finishing a Project Let us assume, Expected completion duration of a project = 29 weeks Variance of the project duration = 6 Then what will be the probability of finishing the project by 27 weeks can be calculated by the formula: Probability Therefore, Z=(27-29)/2.449 =-0.82 Prob. Of finishing the project by 27 weeks is app. 21% Z 0.207 27 darla/smbs/vit 29 Time 11
  • 12. History of Critical Path Method (CPM) • E I Du Pont de Nemours & Co. (1957) for construction of new chemical plant and maintenance shut-down • CPM is a “Deterministic” approach • CPM includes mathematical procedure for estimating the trade off between project duration and project cost • CPM emphasis on applying additional resources to particular key activities
  • 13. Time-Cost Relationship Normal Time, Tn: It is the time taken by an activity under normal work conditions Normal Cost, Cn: The cost incurred in doing an activity in normal time.
  • 14. Crashing An activity is said to be crashed when maximum effort is applied to finish that activity in the shortest possible time.
  • 15. Cost Slope • The cost slope shows by how much the cost of job would change if activities were speed up or slowed down. In this case, Cost Slope= (18-9)/(5-8) = $3 K/week
  • 16. CPM calculation • Path – A connected sequence of activities leading from the starting event to the ending event • Critical Path – The longest path (time); determines the project duration • Critical Activities – All of the activities that make up the critical path
  • 17. CPM calculation Forward Pass • Earliest Start Time (ES) – earliest time an activity can start – ES = maximum EF of immediate predecessors • Earliest finish time (EF) – earliest time an activity can finish – earliest start time plus activity time (EF= ES + t) Backward Pass Latest Start Time (LS) Latest time an activity can start without delaying critical path time LS= LF - t Latest finish time (LF) latest time an activity can be completed without delaying critical path time LS = minimum LS of immediate predecessors
  • 18. Project Crashing • Crashing – reducing project time by expending additional resources • Crash time – an amount of time an activity is reduced • Crash cost – cost of reducing activity time • Goal – reduce project duration at minimum cost
  • 19. Time-Cost Relationship  Crashing costs increase as project duration decreases  Indirect costs increase as project duration increases  Reduce project length as long as crashing costs are less than indirect costs Time-Cost Tradeoff Total project cost Indirect cost Direct cost time
  • 22. Types of Project Constraints • Technical or Logic Constraints – Constraints related to the networked sequence in which project activities must occur. • Physical Constraints – Activities that cannot occur in parallel or are affected by contractual or environmental conditions. • Resource Constraints – The absence, shortage, or unique interrelationship and interaction characteristics of resources that require a particular sequencing of project activities.
  • 23. The Resource Problem • Resources and Priorities – Project network times are not a schedule until resources have been assigned. • The implicit assumption is that resources will be available in the required amounts when needed. • Adding new projects requires making realistic judgments of resource availability and project durations. • Resource-Constrained Scheduling – Resource leveling (or smoothing) involves attempting to even out demands on resources by using slack (delaying noncritical activities) to manage resource utilization.
  • 24.
  • 25. Kinds of Resource Constraints • People • Materials • Equipment • Working Capital
  • 26. Classification of A Scheduling Problem • Time Constrained Project – A project that must be completed by an imposed date. • Time is fixed, resources are flexible: additional resources are required to ensure project meets schedule. • Resource Constrained Project – A project in which the level of resources available cannot be exceeded. • Resources are fixed, time is flexible: inadequate resources will delay the project.
  • 27. Example : • Without resource constraints relatively easy • With resource constraints very complex: when jobs share resources with limited availability, these jobs cannot be processed simultaneously Jobs p(j) R(1,j) R(2,j) 1 8 2 3 2 4 1 0 3 6 3 4 4 4 1 0 5 4 2 3 Resource Available R1 4 R2 8 1 4 2 5 3 27
  • 28. S 'j  earliest possible starting time of job j C 'j  earliest possible completion time of job j C ''  latest possible completion time of job j j slack j  C ''  p j  S 'j j 28
  • 29. Resource constraints • Suppose jobs require a resource: Job p(j) Predecessors S' C'' R(1,j) 1 2 0 3 3 2 3 0 3 1 3 1 0 6 2 4 4 1,2 3 7 2 5 2 2,3 3 8 3 6 1 4 7 8 3 6 5 3 4 3 2 5 2 1 resource requirements 1 6 4 1 2 3 4 5 6 7 8 29
  • 30. Resource constraints (cont.) • Suppose R 1  4 : 6 5 4 3 2 2 1 1 3 1 2 5 4 3 4 5 6 7 6 8 9 10 Cmax increases by 2 30
  • 31. Resource-Constrained Project Scheduling Problem (RCPSP) • • • • • • n jobs j=1,…,n N resources i=1,…,N Rk:availability of resource k pj: duration of job j Rkj:requirement of resource k for job j Pj: (immediate) predecessors of job j 31
  • 32. RCPSP • Goal: minimize makespan: Cmax  max C j • Restrictions: ' j – no job may start before T=0 – precedence relations – finite resource capacity 32
  • 33. RCPSP example Job p(j) P(j) S' C'' R(1,j) R(2,j) 1 2 - 0 3 3 2 2 3 - 0 3 1 1 3 1 - 0 6 2 1 4 4 1,2 3 7 2 1 5 2 2,3 3 8 3 2 6 1 4 7 8 3 1 4 R1  4 2 2 1 0 2 2 R2  2 4 3 2 1 0 6 5 3 4 2 6 8 4 4 10 6 6 8 5 10 12 33
  • 34. Loading And Leveling • Loading- amount of a resource necessary to conduct a project – Depends on the requirements of individual activities. – Changes throughout a project • Resource Leveling- process of scheduling activities so that the amount of a certain required resource is balanced throughout the resource.
  • 35. Multiproject Resource Schedules • Multiproject Scheduling Problems – Overall project slippage • Delay on one project create delays for other projects – Inefficient resource application • The peaks and valleys of resource demands create scheduling problems and delays for projects. – Resource bottlenecks • Shortages of critical resources required for multiple projects cause delays and schedule extensions.
  • 36. Multiproject Resource Schedules • Managing Multiproject Scheduling – Create project offices or departments to oversee the scheduling of resources across projects. – Use a project priority queuing system: first come, first served for resources. – Centralize project management: treat all projects as a part of a “megaproject.” – Outsource projects to reduce the number of projects handled internally.
  • 37. Limitations of PERT/CPM • All immediate predecessor activities must be completed before a given activity can be started. • No activity can be repeated and no “looping back” • Duration time for an activity is restricted to Beta Distribution PERT and a single estimate in CPM. • Critical Path is always considered the longest. • There is only one terminal event and the only way to reach it is by completing all activities in the project
  • 38. GERT • A network analysis technique used in project management. • It allows probabilistic treatment of both network logic and activity duration estimated. • The technique was first described in 1966 by Dr. Alan B. Pritsker of Purdue University and WW Happ. • Compared to other techniques, GERT is an only rarely used scheduling technique.
  • 39. Contd.. • Utilizes probabilistic and branching nodes • It represents the node will be reached if any m of its p immediate predecessors are completed. m n p
  • 40. Contd.. • It represents a probabilistic output where any of q outputs are possible • Each branch has an assigned probability • When no probability is given, the probability is assumed to be one for each branch. 1 2 q
  • 42.