SlideShare ist ein Scribd-Unternehmen logo
1 von 41
Project Management
Course: MBA
Subject: Production & Operation
Management
Unit: 4.1
The Two End Points in a Project
Inspiration
Operation
A miracle occurs
Purpose of Project Management
• Ensure meeting the project objectives within the
allocated schedule & budget
– Communication
– Meetings
– Reviews
– Authorization
– Record Keeping
– Monitoring (testing)
– Interface Control
• Not for assigning blame (usually)
What is Project Management?
• Project : A group of milestones or
phases, activities or tasks that support an
effort to accomplish something
• Management : is the process of
Planning, Organizing, Controlling and
Measuring
Project
• A collection of linked activities, carried out in
an organised manner,with a clearly defined
START POINT and END POINT to achieve
some specific results desired to satisfy the
needs of the organisation at the current time
Project Management
• A dynamic process that utilises the
appropriate resources of the organisation in a
controlled and structured manner, to achieve
some clearly defined objectives identified as
needs.
• It is always conducted within a defined set of
constraints
What does Project Management
Entail?
• Planning:is the most critical and gets the
least amount of our time
Beginning with the End in mind-Stephen Covey
• Organizing: Orderly fashion
(Contingent/Prerequisites)
• Controlling: is critical if we are to use our
limited resources wisely
• Measuring: To determine if we accomplished
the goal or met the target?
Measuring…….
• Are we efficient?
• Are we productive?
• Are we doing a good job?
• What is the outcome?
• Is it what we wanted to be?
If you can’t plan it, You can’t do it
If you can’t measure it, you can’t manage it
Who uses Project Management?
 Nearly Everyone to some degree
People plan their Days, their Weeks, their
Vacations and their Budgets and keep a simple
project management form known as ‘’To Do’’
list
 Any Process or Means used to track tasks or
efforts towards accomplishing a goal could be
considered Project Management
Why is Project Management used?
• It is necessary to Track or Measure the
progress we have achieved towards a Goal we
wish to accomplish
• We use Project Management to Aid us in
Maximizing and Optimizing our resources to
accomplish our goals
How much time does Project
Management take?
• Not much. Probably more time is wasted as a
consequence of lack of Project Management
tool than is spent to Plan adequately,
Organize, Control effectively and Measure
appropriately
• How long: As long as there are things to do
Why is Project Management
Important?
• Enables us to map out a course of action or
work plan
• Helps us to think systematically and
thoroughly
• Unique Task
• Specific Objective
• Variety of Resources
• Time bound
Advantages
• In built Monitoring/ Sequencing
• Easy and Early identification of Bottlenecks
• Activity based costing
• Identification and Addition of missing and new
activities
• Preempting unnecessary activity/expenditure
• Timely Completion
• Assigning tasks
• Reporting
Road to Better Project Management
• Find a Project plan that fits your style of project
management needs
• It may be as simple as creating templates, forms and
spreadsheets to track tasks
• Formation of a Project Management committee
• Listing out all the tasks and sub-tasks to accomplish a
goal
• Jot down the time period and person responsible
against each task/sub-task
Implementation
• Regular Monitoring
• Resource Support
• Critical issues discussed and solution
• Meeting with the team on completion of
each major milestone
• Track the progress against the plan
• System to add/delete tasks in the PMT
Consequences of
not using PMT
DELAY
COST
WASTE OF RESOURCES
QUALITY
DISSATISFACTION
REPUTATION
Project Phases and the Project Life
Cycle
• A project life cycle is a collection of project
phases that defines:
– What work will be performed in each phase.
– What deliverables will be produced and when.
– Who is involved in each phase.
– How management will control and approve work
produced in each phase.
• A deliverable is a product or service produced
or provided as part of a project.
More on Project Phases
• In the early phases of a project life cycle:
– Resource needs are usually lowest.
– The level of uncertainty (risk) is highest.
– Project stakeholders have the greatest opportunity to
influence the project.
• In the middle phases of a project life cycle:
– The certainty of completing a project increases.
– More resources are needed.
• In the final phase of a project life cycle:
– The focus is on ensuring that project requirements were
met.
– The sponsor approves completion of the project.
Phases of the Traditional Project Life
Cycle
History
• Developed in 1950’s
• CPM by DuPont for chemical plants
• PERT by U.S. Navy for Polaris missile
PERT was developed by the US Navy for the planning and control of
the Polaris missile program and the emphasis was on completing the
program in the shortest possible time. In addition PERT had the
ability to cope with uncertain activity completion times (e.g. for a
particular activity the most likely completion time is 4 weeks but it
could be anywhere between 3 weeks and 8 weeks).
CPM was developed by Du Pont and the emphasis was on the
trade-off between the cost of the project and its overall
completion time (e.g. for certain activities it may be possible
to decrease their completion times by spending more money -
how does this affect the overall completion time of the
project?)
CPM - Critical Path Method
• Definition: In CPM activities are shown as a network
of precedence relationships using activity-on-node
network construction
– Single estimate of activity time
– Deterministic activity times
USED IN : Production management - for the jobs of
repetitive in nature where the activity time
estimates can be predicted with considerable
certainty due to the existence of past experience.
PERT -
Project Evaluation & Review Techniques
• Definition: In PERT activities are shown as a network of
precedence relationships using activity-on-arrow network
construction
– Multiple time estimates
– Probabilistic activity times
USED IN : Project management - for non-repetitive jobs
(research and development work), where the time and
cost estimates tend to be quite uncertain. This technique
uses probabilistic time estimates.
Gantt chart
Advantages
- Gantt charts are quite commonly used.
They provide an easy graphical
representation of when activities (might)
take place.
Limitations
- Do not clearly indicate details regarding
the progress of activities
- Do not give a clear indication of
interrelation ship between the separate
activities
Originated by H.L.Gantt in
1918
CPM/PERT
These deficiencies can be eliminated to a large extent by
showing the interdependence of various activities by means
of connecting arrows called network technique.
• Overtime CPM and PERT became one technique
• ADVANTAGES:
– Precedence relationships
– large projects
– more efficient
The Project Network
• Use of nodes and arrows
Arrows  An arrow leads from tail to head directionally
– Indicate ACTIVITY, a time consuming effort that is required to perform
a part of the work.
Nodes  A node is represented by a circle
- Indicate EVENT, a point in time where one or more activities start
and/or finish.
Activity on Node & Activity on Arrow
Activity on Node
- A completion of an
activity is represented by
a node
Activity on Arrow
- An arrow represents a
task, while a node is the
completion of a task
- Arrows represent order of
events
Activity Slack
Each event has two important times associated with it :
- Earliest time , Te , which is a calendar time when a event can
occur when all the predecessor events completed at the earliest
possible times
- Latest time , TL , which is the latest time the event can occur with
out delaying the subsequent events and completion of project.
• Difference between the latest time and the earliest time of an
event is the slack time for that event
Positive slack : Slack is the amount of time an event can be delayed
without delaying the project completion
Critical Path
• Is that the sequence of activities and events
where there is no “slack” i.e.. Zero slack
• Longest path through a network
• minimum project completion time
Benefits of CPM/PERT
• Useful at many stages of project management
• Mathematically simple
• Give critical path and slack time
• Provide project documentation
• Useful in monitoring costs
Questions Answered by CPM & PERT
• Completion date?
• On Schedule?
• Within Budget?
• Critical Activities?
• How can the project be finished early at the
least cost?
Limitations to CPM/PERT
• Clearly defined, independent and stable
activities
• Specified precedence relationships
• Over emphasis on critical paths
Project Crashing
Question: Can we cut short its project
completion time?
If so, how!
Project Crashing
Solution!
Yes, the project duration can be reduced by
assigning more resources to project activities.
But, doing this would somehow increase our
project cost!
How do we strike a balance?
■ Project crashing is a method for shortening
project duration by reducing one or more
critical activities to a time less than normal
activity time.
Trade-off concept
Here, we adopt the “Trade-off” concept
• We attempt to “crash” some “critical” events
by allocating more resources to them, so that
the time of one or more critical activities is
reduced to a time that is less than the normal
activity time.
• How to do that:
• Question: What criteria should it be based
on when deciding to crashing critical times?
Example – crashing
The critical path is 1-2-3, the completion time
=11
How? Path: 1-2-3 = 5+6=11 weeks
Path: 1-3 = 5 weeks
Now, how many days can we “crash” it?
1
3
2
5 (1)
6(3)
5(0)
Normal weeks
Max weeks can be crashed
Example – crashing
1
3
2
5 (1)
6(3)
5(0)
The maximum time that can be crashed for:
Path 1-2-3 = 1 + 3 = 4
Path 1-3 = 0
Should we use up all these 4 weeks?
Example – crashing
1
3
2
5 (1)
6(3)
5(0)
If we used all 4 days, then path 1-2-3 has
(5-1) + (6-3) = 7 completion weeks
Now, we need to check if the completion time for path 1-3 has lesser than 7
weeks (why?)
Now, path 1-3 has (5-0) = 5 weeks
Since path 1-3 still shorter than 7 weeks, we used up all 4 crashed weeks
Question: What if path 1-3 has, say 8 weeks completion time?
4(0) 3(0)
Example – crashing
1
3
2
5 (1)
6(3)
8(0)
Such as
Now, we cannot use all 4 days (Why?)
Because path 1-2-3 will not be critical path anymore as
path 1-3 would now has longest hour to finish
Rule: When a path is a critical path, it will not stay as a critical path
So, we can only reduce the path 1-2-3 completion time to the same time
as path 1-3. (HOW?)
Example – crashing
1
3
2
5 (1)
6(3)
8(0)
Solution:
We can only reduce total time for path 1-2-3 = path 1-3,
that is 8 weeks
If the cost for path 1-2 and path 2-3 is the same then
We can random pick them to crash so that its completion
Time is 8 weeks
Example – crashing
1
3
2
5 (1)
6(3)
8(0)
Solution:
1
2
3
5 (1) 6(3)
8(0)
OR
4(0) 4(1)
3(0)
Now, paths 1-2-3 and 1-3 are both critical paths
References
• homes.ieu.edu.tr/stunali/courses/ch08_crashi
ng
• ww.csus.edu/indiv/b/blakeh/mgmt/

Weitere ähnliche Inhalte

Was ist angesagt?

Int 327 ch01
Int 327 ch01Int 327 ch01
Int 327 ch01
Lisa Vick
 
Quality Metrics
Quality Metrics Quality Metrics
Quality Metrics
Haroon Abbu
 
Quality Program Overview
Quality Program OverviewQuality Program Overview
Quality Program Overview
jscover
 

Was ist angesagt? (20)

June 21 2012 Process Performance Metrics Presentation
June 21 2012 Process Performance Metrics PresentationJune 21 2012 Process Performance Metrics Presentation
June 21 2012 Process Performance Metrics Presentation
 
quality engineering(ME522) part 1
quality engineering(ME522) part 1quality engineering(ME522) part 1
quality engineering(ME522) part 1
 
Int 327 ch01
Int 327 ch01Int 327 ch01
Int 327 ch01
 
C12 quality
C12 qualityC12 quality
C12 quality
 
Quality Metrics
Quality Metrics Quality Metrics
Quality Metrics
 
Managing Operations, Quality and Productivity by nabeel
Managing Operations, Quality and Productivity by nabeelManaging Operations, Quality and Productivity by nabeel
Managing Operations, Quality and Productivity by nabeel
 
Tqm ch 10
Tqm ch 10Tqm ch 10
Tqm ch 10
 
Quality Management
Quality ManagementQuality Management
Quality Management
 
Quality Program Overview
Quality Program OverviewQuality Program Overview
Quality Program Overview
 
Quality Assurance in Japanese Construction (Henry Loo)
Quality Assurance in Japanese Construction (Henry Loo)Quality Assurance in Japanese Construction (Henry Loo)
Quality Assurance in Japanese Construction (Henry Loo)
 
HP case study sloution
HP case study sloutionHP case study sloution
HP case study sloution
 
Quality and performance excellence chapter 5
Quality and performance excellence chapter 5Quality and performance excellence chapter 5
Quality and performance excellence chapter 5
 
Lean project management
Lean project management Lean project management
Lean project management
 
5 Minutes to Process Improvement Success
5 Minutes to Process Improvement Success5 Minutes to Process Improvement Success
5 Minutes to Process Improvement Success
 
Total Quality Management - Chapter 6 Management of Process Quality
Total Quality Management - Chapter 6 Management of Process QualityTotal Quality Management - Chapter 6 Management of Process Quality
Total Quality Management - Chapter 6 Management of Process Quality
 
Bpr Case Study
Bpr Case StudyBpr Case Study
Bpr Case Study
 
Quality manegment
Quality manegmentQuality manegment
Quality manegment
 
Quality Management Philosophies & Quotations by Operational Excellence Consul...
Quality Management Philosophies & Quotations by Operational Excellence Consul...Quality Management Philosophies & Quotations by Operational Excellence Consul...
Quality Management Philosophies & Quotations by Operational Excellence Consul...
 
Business Process Reengineering PowerPoint Presentation Slides
Business Process Reengineering PowerPoint Presentation SlidesBusiness Process Reengineering PowerPoint Presentation Slides
Business Process Reengineering PowerPoint Presentation Slides
 
Total quality management tools and techniques
Total quality management tools and techniquesTotal quality management tools and techniques
Total quality management tools and techniques
 

Andere mochten auch

How To Do An Mba Project
How To Do An Mba ProjectHow To Do An Mba Project
How To Do An Mba Project
sunil sharma
 
A STUDY ON TOTAL QUALITY MANAGEMENT
A STUDY ON TOTAL QUALITY MANAGEMENTA STUDY ON TOTAL QUALITY MANAGEMENT
A STUDY ON TOTAL QUALITY MANAGEMENT
surendra tripathi
 
A study on consumer satisfaction in ford motors
A study on consumer satisfaction in ford motorsA study on consumer satisfaction in ford motors
A study on consumer satisfaction in ford motors
rajukann
 

Andere mochten auch (11)

How To Do An Mba Project
How To Do An Mba ProjectHow To Do An Mba Project
How To Do An Mba Project
 
A STUDY ON TOTAL QUALITY MANAGEMENT
A STUDY ON TOTAL QUALITY MANAGEMENTA STUDY ON TOTAL QUALITY MANAGEMENT
A STUDY ON TOTAL QUALITY MANAGEMENT
 
A project report on TQM by Abhinandan Kumar
A project report on TQM by Abhinandan KumarA project report on TQM by Abhinandan Kumar
A project report on TQM by Abhinandan Kumar
 
A project report on TQM
A project report on TQMA project report on TQM
A project report on TQM
 
Hr policy in maruthi
Hr policy in maruthi Hr policy in maruthi
Hr policy in maruthi
 
Awareness of commodity market a project report on mba finance
Awareness of commodity market a project report on mba financeAwareness of commodity market a project report on mba finance
Awareness of commodity market a project report on mba finance
 
A study on consumer satisfaction in ford motors
A study on consumer satisfaction in ford motorsA study on consumer satisfaction in ford motors
A study on consumer satisfaction in ford motors
 
A study of customer satisfaction on after sales and service conducted at arpi...
A study of customer satisfaction on after sales and service conducted at arpi...A study of customer satisfaction on after sales and service conducted at arpi...
A study of customer satisfaction on after sales and service conducted at arpi...
 
Literature Review
Literature ReviewLiterature Review
Literature Review
 
State of the Word 2011
State of the Word 2011State of the Word 2011
State of the Word 2011
 
Slideshare ppt
Slideshare pptSlideshare ppt
Slideshare ppt
 

Ähnlich wie Mba ii pmom_unit-4.1 project management a

Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_siesOm lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
videoaakash15
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system project
a23ccb
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system project
alpha1unity
 
Presintation on Project constraint
Presintation on Project constraint Presintation on Project constraint
Presintation on Project constraint
university(kust)
 

Ähnlich wie Mba ii pmom_unit-4.1 project management a (20)

Project Management
Project ManagementProject Management
Project Management
 
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_siesOm lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
 
pm--basic.pptx
pm--basic.pptxpm--basic.pptx
pm--basic.pptx
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
Project management master class karin rheeder
Project management master class   karin rheederProject management master class   karin rheeder
Project management master class karin rheeder
 
Time management pressent
Time management pressentTime management pressent
Time management pressent
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
 
Project management and project life cycle
Project management and project life cycleProject management and project life cycle
Project management and project life cycle
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx
 
Project planning and control
Project planning and controlProject planning and control
Project planning and control
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
 
Project-Time-Line.pdf
Project-Time-Line.pdfProject-Time-Line.pdf
Project-Time-Line.pdf
 
Project management essentials 3 day training program
Project management essentials   3 day training programProject management essentials   3 day training program
Project management essentials 3 day training program
 
MandC.pdf
MandC.pdfMandC.pdf
MandC.pdf
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system project
 
SPM Unit 1.pptx
SPM Unit 1.pptxSPM Unit 1.pptx
SPM Unit 1.pptx
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system project
 
Presintation on Project constraint
Presintation on Project constraint Presintation on Project constraint
Presintation on Project constraint
 

Mehr von Rai University

Bsc agri 2 pae u-4.4 publicrevenue-presentation-130208082149-phpapp02
Bsc agri  2 pae  u-4.4 publicrevenue-presentation-130208082149-phpapp02Bsc agri  2 pae  u-4.4 publicrevenue-presentation-130208082149-phpapp02
Bsc agri 2 pae u-4.4 publicrevenue-presentation-130208082149-phpapp02
Rai University
 

Mehr von Rai University (20)

Brochure Rai University
Brochure Rai University Brochure Rai University
Brochure Rai University
 
Mm unit 4point2
Mm unit 4point2Mm unit 4point2
Mm unit 4point2
 
Mm unit 4point1
Mm unit 4point1Mm unit 4point1
Mm unit 4point1
 
Mm unit 4point3
Mm unit 4point3Mm unit 4point3
Mm unit 4point3
 
Mm unit 3point2
Mm unit 3point2Mm unit 3point2
Mm unit 3point2
 
Mm unit 3point1
Mm unit 3point1Mm unit 3point1
Mm unit 3point1
 
Mm unit 2point2
Mm unit 2point2Mm unit 2point2
Mm unit 2point2
 
Mm unit 2 point 1
Mm unit 2 point 1Mm unit 2 point 1
Mm unit 2 point 1
 
Mm unit 1point3
Mm unit 1point3Mm unit 1point3
Mm unit 1point3
 
Mm unit 1point2
Mm unit 1point2Mm unit 1point2
Mm unit 1point2
 
Mm unit 1point1
Mm unit 1point1Mm unit 1point1
Mm unit 1point1
 
Bdft ii, tmt, unit-iii, dyeing & types of dyeing,
Bdft ii, tmt, unit-iii,  dyeing & types of dyeing,Bdft ii, tmt, unit-iii,  dyeing & types of dyeing,
Bdft ii, tmt, unit-iii, dyeing & types of dyeing,
 
Bsc agri 2 pae u-4.4 publicrevenue-presentation-130208082149-phpapp02
Bsc agri  2 pae  u-4.4 publicrevenue-presentation-130208082149-phpapp02Bsc agri  2 pae  u-4.4 publicrevenue-presentation-130208082149-phpapp02
Bsc agri 2 pae u-4.4 publicrevenue-presentation-130208082149-phpapp02
 
Bsc agri 2 pae u-4.3 public expenditure
Bsc agri  2 pae  u-4.3 public expenditureBsc agri  2 pae  u-4.3 public expenditure
Bsc agri 2 pae u-4.3 public expenditure
 
Bsc agri 2 pae u-4.2 public finance
Bsc agri  2 pae  u-4.2 public financeBsc agri  2 pae  u-4.2 public finance
Bsc agri 2 pae u-4.2 public finance
 
Bsc agri 2 pae u-4.1 introduction
Bsc agri  2 pae  u-4.1 introductionBsc agri  2 pae  u-4.1 introduction
Bsc agri 2 pae u-4.1 introduction
 
Bsc agri 2 pae u-3.3 inflation
Bsc agri  2 pae  u-3.3  inflationBsc agri  2 pae  u-3.3  inflation
Bsc agri 2 pae u-3.3 inflation
 
Bsc agri 2 pae u-3.2 introduction to macro economics
Bsc agri  2 pae  u-3.2 introduction to macro economicsBsc agri  2 pae  u-3.2 introduction to macro economics
Bsc agri 2 pae u-3.2 introduction to macro economics
 
Bsc agri 2 pae u-3.1 marketstructure
Bsc agri  2 pae  u-3.1 marketstructureBsc agri  2 pae  u-3.1 marketstructure
Bsc agri 2 pae u-3.1 marketstructure
 
Bsc agri 2 pae u-3 perfect-competition
Bsc agri  2 pae  u-3 perfect-competitionBsc agri  2 pae  u-3 perfect-competition
Bsc agri 2 pae u-3 perfect-competition
 

Kürzlich hochgeladen

The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
heathfieldcps1
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
PECB
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
Chris Hunter
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
ciinovamais
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
QucHHunhnh
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
negromaestrong
 

Kürzlich hochgeladen (20)

Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Asian American Pacific Islander Month DDSD 2024.pptx
Asian American Pacific Islander Month DDSD 2024.pptxAsian American Pacific Islander Month DDSD 2024.pptx
Asian American Pacific Islander Month DDSD 2024.pptx
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-IIFood Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
Food Chain and Food Web (Ecosystem) EVS, B. Pharmacy 1st Year, Sem-II
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
Role Of Transgenic Animal In Target Validation-1.pptx
Role Of Transgenic Animal In Target Validation-1.pptxRole Of Transgenic Animal In Target Validation-1.pptx
Role Of Transgenic Animal In Target Validation-1.pptx
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 

Mba ii pmom_unit-4.1 project management a

  • 1. Project Management Course: MBA Subject: Production & Operation Management Unit: 4.1
  • 2. The Two End Points in a Project Inspiration Operation A miracle occurs
  • 3. Purpose of Project Management • Ensure meeting the project objectives within the allocated schedule & budget – Communication – Meetings – Reviews – Authorization – Record Keeping – Monitoring (testing) – Interface Control • Not for assigning blame (usually)
  • 4. What is Project Management? • Project : A group of milestones or phases, activities or tasks that support an effort to accomplish something • Management : is the process of Planning, Organizing, Controlling and Measuring
  • 5. Project • A collection of linked activities, carried out in an organised manner,with a clearly defined START POINT and END POINT to achieve some specific results desired to satisfy the needs of the organisation at the current time
  • 6. Project Management • A dynamic process that utilises the appropriate resources of the organisation in a controlled and structured manner, to achieve some clearly defined objectives identified as needs. • It is always conducted within a defined set of constraints
  • 7. What does Project Management Entail? • Planning:is the most critical and gets the least amount of our time Beginning with the End in mind-Stephen Covey • Organizing: Orderly fashion (Contingent/Prerequisites) • Controlling: is critical if we are to use our limited resources wisely • Measuring: To determine if we accomplished the goal or met the target?
  • 8. Measuring……. • Are we efficient? • Are we productive? • Are we doing a good job? • What is the outcome? • Is it what we wanted to be? If you can’t plan it, You can’t do it If you can’t measure it, you can’t manage it
  • 9. Who uses Project Management?  Nearly Everyone to some degree People plan their Days, their Weeks, their Vacations and their Budgets and keep a simple project management form known as ‘’To Do’’ list  Any Process or Means used to track tasks or efforts towards accomplishing a goal could be considered Project Management
  • 10. Why is Project Management used? • It is necessary to Track or Measure the progress we have achieved towards a Goal we wish to accomplish • We use Project Management to Aid us in Maximizing and Optimizing our resources to accomplish our goals
  • 11. How much time does Project Management take? • Not much. Probably more time is wasted as a consequence of lack of Project Management tool than is spent to Plan adequately, Organize, Control effectively and Measure appropriately • How long: As long as there are things to do
  • 12. Why is Project Management Important? • Enables us to map out a course of action or work plan • Helps us to think systematically and thoroughly • Unique Task • Specific Objective • Variety of Resources • Time bound
  • 13. Advantages • In built Monitoring/ Sequencing • Easy and Early identification of Bottlenecks • Activity based costing • Identification and Addition of missing and new activities • Preempting unnecessary activity/expenditure • Timely Completion • Assigning tasks • Reporting
  • 14. Road to Better Project Management • Find a Project plan that fits your style of project management needs • It may be as simple as creating templates, forms and spreadsheets to track tasks • Formation of a Project Management committee • Listing out all the tasks and sub-tasks to accomplish a goal • Jot down the time period and person responsible against each task/sub-task
  • 15. Implementation • Regular Monitoring • Resource Support • Critical issues discussed and solution • Meeting with the team on completion of each major milestone • Track the progress against the plan • System to add/delete tasks in the PMT
  • 16. Consequences of not using PMT DELAY COST WASTE OF RESOURCES QUALITY DISSATISFACTION REPUTATION
  • 17. Project Phases and the Project Life Cycle • A project life cycle is a collection of project phases that defines: – What work will be performed in each phase. – What deliverables will be produced and when. – Who is involved in each phase. – How management will control and approve work produced in each phase. • A deliverable is a product or service produced or provided as part of a project.
  • 18. More on Project Phases • In the early phases of a project life cycle: – Resource needs are usually lowest. – The level of uncertainty (risk) is highest. – Project stakeholders have the greatest opportunity to influence the project. • In the middle phases of a project life cycle: – The certainty of completing a project increases. – More resources are needed. • In the final phase of a project life cycle: – The focus is on ensuring that project requirements were met. – The sponsor approves completion of the project.
  • 19. Phases of the Traditional Project Life Cycle
  • 20. History • Developed in 1950’s • CPM by DuPont for chemical plants • PERT by U.S. Navy for Polaris missile PERT was developed by the US Navy for the planning and control of the Polaris missile program and the emphasis was on completing the program in the shortest possible time. In addition PERT had the ability to cope with uncertain activity completion times (e.g. for a particular activity the most likely completion time is 4 weeks but it could be anywhere between 3 weeks and 8 weeks). CPM was developed by Du Pont and the emphasis was on the trade-off between the cost of the project and its overall completion time (e.g. for certain activities it may be possible to decrease their completion times by spending more money - how does this affect the overall completion time of the project?)
  • 21. CPM - Critical Path Method • Definition: In CPM activities are shown as a network of precedence relationships using activity-on-node network construction – Single estimate of activity time – Deterministic activity times USED IN : Production management - for the jobs of repetitive in nature where the activity time estimates can be predicted with considerable certainty due to the existence of past experience.
  • 22. PERT - Project Evaluation & Review Techniques • Definition: In PERT activities are shown as a network of precedence relationships using activity-on-arrow network construction – Multiple time estimates – Probabilistic activity times USED IN : Project management - for non-repetitive jobs (research and development work), where the time and cost estimates tend to be quite uncertain. This technique uses probabilistic time estimates.
  • 23. Gantt chart Advantages - Gantt charts are quite commonly used. They provide an easy graphical representation of when activities (might) take place. Limitations - Do not clearly indicate details regarding the progress of activities - Do not give a clear indication of interrelation ship between the separate activities Originated by H.L.Gantt in 1918
  • 24. CPM/PERT These deficiencies can be eliminated to a large extent by showing the interdependence of various activities by means of connecting arrows called network technique. • Overtime CPM and PERT became one technique • ADVANTAGES: – Precedence relationships – large projects – more efficient
  • 25. The Project Network • Use of nodes and arrows Arrows  An arrow leads from tail to head directionally – Indicate ACTIVITY, a time consuming effort that is required to perform a part of the work. Nodes  A node is represented by a circle - Indicate EVENT, a point in time where one or more activities start and/or finish.
  • 26. Activity on Node & Activity on Arrow Activity on Node - A completion of an activity is represented by a node Activity on Arrow - An arrow represents a task, while a node is the completion of a task - Arrows represent order of events
  • 27. Activity Slack Each event has two important times associated with it : - Earliest time , Te , which is a calendar time when a event can occur when all the predecessor events completed at the earliest possible times - Latest time , TL , which is the latest time the event can occur with out delaying the subsequent events and completion of project. • Difference between the latest time and the earliest time of an event is the slack time for that event Positive slack : Slack is the amount of time an event can be delayed without delaying the project completion
  • 28. Critical Path • Is that the sequence of activities and events where there is no “slack” i.e.. Zero slack • Longest path through a network • minimum project completion time
  • 29. Benefits of CPM/PERT • Useful at many stages of project management • Mathematically simple • Give critical path and slack time • Provide project documentation • Useful in monitoring costs
  • 30. Questions Answered by CPM & PERT • Completion date? • On Schedule? • Within Budget? • Critical Activities? • How can the project be finished early at the least cost?
  • 31. Limitations to CPM/PERT • Clearly defined, independent and stable activities • Specified precedence relationships • Over emphasis on critical paths
  • 32. Project Crashing Question: Can we cut short its project completion time? If so, how!
  • 33. Project Crashing Solution! Yes, the project duration can be reduced by assigning more resources to project activities. But, doing this would somehow increase our project cost! How do we strike a balance? ■ Project crashing is a method for shortening project duration by reducing one or more critical activities to a time less than normal activity time.
  • 34. Trade-off concept Here, we adopt the “Trade-off” concept • We attempt to “crash” some “critical” events by allocating more resources to them, so that the time of one or more critical activities is reduced to a time that is less than the normal activity time. • How to do that: • Question: What criteria should it be based on when deciding to crashing critical times?
  • 35. Example – crashing The critical path is 1-2-3, the completion time =11 How? Path: 1-2-3 = 5+6=11 weeks Path: 1-3 = 5 weeks Now, how many days can we “crash” it? 1 3 2 5 (1) 6(3) 5(0) Normal weeks Max weeks can be crashed
  • 36. Example – crashing 1 3 2 5 (1) 6(3) 5(0) The maximum time that can be crashed for: Path 1-2-3 = 1 + 3 = 4 Path 1-3 = 0 Should we use up all these 4 weeks?
  • 37. Example – crashing 1 3 2 5 (1) 6(3) 5(0) If we used all 4 days, then path 1-2-3 has (5-1) + (6-3) = 7 completion weeks Now, we need to check if the completion time for path 1-3 has lesser than 7 weeks (why?) Now, path 1-3 has (5-0) = 5 weeks Since path 1-3 still shorter than 7 weeks, we used up all 4 crashed weeks Question: What if path 1-3 has, say 8 weeks completion time? 4(0) 3(0)
  • 38. Example – crashing 1 3 2 5 (1) 6(3) 8(0) Such as Now, we cannot use all 4 days (Why?) Because path 1-2-3 will not be critical path anymore as path 1-3 would now has longest hour to finish Rule: When a path is a critical path, it will not stay as a critical path So, we can only reduce the path 1-2-3 completion time to the same time as path 1-3. (HOW?)
  • 39. Example – crashing 1 3 2 5 (1) 6(3) 8(0) Solution: We can only reduce total time for path 1-2-3 = path 1-3, that is 8 weeks If the cost for path 1-2 and path 2-3 is the same then We can random pick them to crash so that its completion Time is 8 weeks
  • 40. Example – crashing 1 3 2 5 (1) 6(3) 8(0) Solution: 1 2 3 5 (1) 6(3) 8(0) OR 4(0) 4(1) 3(0) Now, paths 1-2-3 and 1-3 are both critical paths