SlideShare ist ein Scribd-Unternehmen logo
1 von 25
Contract Costing
CONTRACT
COSTING
 Contract costing also known as terminal
costing, is a variant of job costing. In this
method of job costing , each contract is a
cost unit and a account is opened for each
contract in the book of contractor to ascertain
profit/loss thereon.
 Contract costing is used in: Building
construction, Road construction, Bridge
construction, other civil engineering works,
ship building etc.
Contract costing and job
costing -Distinction
 Main points of distinction as follows:
1- The no. of jobs undertaken at a time are
usually large as compared to no. of
contracts because contracts are
generally much bigger in size.
2- In contract costing , most of the costs
are chargeable direct to contract
account. Under job costing direct
allocation to such an extent is not
possible.
Con..
3- Allocation and apportionment of overhead
costs is simpler in contract costing as
compared to job costing .
4- contract is generally big while job is a small.
It is well said , “ a job is small contract and
contract is big job”
5- jobs are usually carried in factory premises
while contract work is done at site.
Features of contract costing
1- contracts are generally takes more than one
year to complete .
2- contracts are generally of large size and
therefore, a contractor usually carries out small
number of contracts in the course of one year.
3- work on contracts is carried out at the site of
contracts and not in factory premises .
4-Each contract under taken is treated as a cost
unit.
5-A separate contract account is prepared for each
contract in the books of the contractor to
ascertain profit and loss on each contract.
Recording Cost Contract or Costing Procedure
In contract costing, costs are allocated, collected and accumulated
according to the contract works.
Each contract is treated as a separate entity in which each contract
account may be maintained separately
or in general ledger itself for the purpose of costing and cost control. The
following are the costing
procedure for different costs relating to the important expenses :
(1) Materials:
(A) Contract Account is debited with the following transactions relating to
materials :
(I) Bulk of materials are purchased for a specific contract from suppliers.
(2) Materials obtained from contractor's central stores through the
requisition slips.
(3) Materials transferred from one contract to another contract.
(4) Value of materials remaining unutilized on site during the accounting
year.
.
(B) Contract Account is credited with the
following transactions relating to materials:
(1) Materials returned under Materials Return
Note.
(2) Sale of materials at site on account of some
extraneous reasons.
(3) Materials transferred to other contracts.
(4) Materials stolen or destroyed by fire.
(5) On completion, if a part of materials received
from the stores are returned
(C) Any profit or loss on materials account is transferred to the
Profu and Loss Account:
(I) Sale price is different from the cost price.
(2) Resulting from the sale of materials at site.
(3) Resulting from the materials stolen or destroyed by fire.
(2) Labour: In the case of contract costing, all labours engaged
at site and the salaries and wages paid to the labour and
workers are treated as direct labour cost is debited to Contract
Account.
(3) Direct Expenses: Most of the expenses like electricity,
insurance telephone, postage, sub-contracts, Architect's fees
etc. can also be treated as direct cost is debited to Contract
Account.
(4) Overhead Cost: In the case of contract costing overheads
incurred only an insignificant part of the total cost of contract
account. The nature office and administrative expenses of a
particular contract may be apportioned on suitable basis.
(5) Plant and Machinery: For use of plant and machinery in a
particular contract, the treatment of plant costs in any of the two
ways:
(a) Where a plant has been specially purchased for a particular
contract and will be exhausted at site Contract Account
should be debited with the cost of the plant. On completion
of the contract the residual or written down value as shown
by the Plant Ledger will be credited "to the Contract Account.
(b) When the plant and machinery are required to the contract
site only for a shorter period, the contract account should be
debited with the notional amount of depreciation based on some
estimates be charged to Contract Account.
Sub-Contracts: Sub-Contracts refer to some portions of the
specified work connected with the main contract, to be done by
the sub-contractor. For example, the work of painting, special
flooring, steel work etc. may be given to the sub-contractors.
Usually sub-contract has been undertaken on cost-plus basis
and the cost of such sub-contract should be treated as a direct
charge and is debited to Contract Account.
(7) Work Certified: In the case of the small contracts which are
completed within the shorter period, the contractor pays the
contract price on the completion of the contract. In the case of
contracts of long duration. the contract agreement provides
interim payment to the contractor. It is done on the basis of
certificates issued
by the contractee's Surveyor, Architect or Engineer. At the same
time Contractee usually does not pay to the full value of the
work certified. A portion of amount say 20% or 30% thereof shall
be retained by the Contractee.
The money so retained is called as "Retention Money." This
retention money is intented to ensure that the contractor to
complete the work as scheduled and according to
specifications. Money retained could also be used for imposing
penalties for faulty or delayed work. This amount will be settled
on completion of the contract.
(8) Work Uncertified : If the progress of a work is
unsatisfactory or the work has not reached the stipulated
stage, though certain work is completed, such work does
not qualify for a certificate by the Contractee's Architect
or Surveyor is termed as "Work Uncertified." It is valued
at cost and credited to Contract
Account and debited to Work in Progress Account.
(9) Work in Progress: Work in progress includes the
amount of work .certified and the amount of work
uncertified. The work in progress account will appear on
the asset side of the balance sheet. The amount of cash
received from the contractee and reserve for
contingencies will be deducted out of this amount.
Treatment of Profits or Loss on Contracts Alc.
The accounting treatment of profits or loss of
contracts in the following stages :
(A) Profit or Loss on incomplete contracts
(B) Profits or Loss on completed contracts
(A) Profit or Loss on Incomplete Contracts
To determine the profits to be taken to Profit and Loss
Account. in the case of incomplete contracts,
the following situations may arise :
(i) Completion of Contract is Less than 25% : In this case no
profit should be taken to Profit and Loss Account.
(ii) Completion of Contract is upto 25% or more but Less than
50% : In this case one-third of the notional profit, reduced in
the ratio of cash received to work certified, should be
transferred to Profit and Loss Account. It can be expressed as:
1/3 x Notional Profitx Cash Received/ Work Certified
(iii) Completion of Contract is upto 50% or more but Less
than 90% : In this case two-third of the notional profit
reduced by proportion of cash received to work certified
is transferred to Profit and Loss Account. The equation is
2/3xNotionalProfitxCashReceived/Work Certified
(iv) Completion of Contract is upto 90% or more than 90%, i.e., it is
nearing completion: In this case the profit to be taken to Profit and
Loss Account is determined by determining the estimated profit and
using anyone of the following formula :
(a)Estimated Profit x Work Certified/ Contract Price
(b) Estimated Profit x Cash Received / Contract Price
(c) Estimated Profit x Cost of Work to Date/ Estimated total cost
(d) Estimated Profit X Cost of Work to Date/ Estimated
Total Cost x Cash Received / Work Certified
(e) Notional Profit X Work Certified /Contract Price
Escalation Clause: This clause is often provided in contracts
as safeguard against any likely changes in price or utilization
of material and labour. Such a clause in a contract would
provide that in the event of a specified contingency
happening, the contract price would be suitably enhanced by
an agreed formula or factor.
This clause is particularly necessary where the prices of a
certain raw material are likely to rise. where labour rates are
anticipated to increase, or where the quantity of material and
labour hours cannot be assessed properly or estimated
unless the job has progressed sufficiently.
Cost-Plus Contract: These contracts provide for
the payment by the contractee of the actual cost of
manufacturing plus a stipulated profit. The profit to
be added to the cost may be a fixed amount or it
may be a stipulated percentage of cost. These
contracts are generally entered into when at the time
of undertaking of a work, it is not possible to
estimate it's cost with reasonable accuracy due to
unstable condition of material. labour etc. or when
the work is spread over a long period of time and
prices of materials. rates of labour etc. are liable to
fluctuate.
(B) Profits or Loss on Completed Contracts :
When a contract is completed, the overall profit or loss on the
contract is transferred to the Profit and Loss Account.
The following are the expenses on a contract which commences
on 1st Jan. 2003
Materials purchased 1.00.000
Materials on hand 5.000
Direct wages 1.50.000
Plant issued 50.000
Direct expenses 80000
The contract price was Rs. 15.00.000 and the same was duly
received when the contract was completed in
August 2003. Charge indirect expenses at 15% on wages.
provide Rs. 10.000 for depreciation on plant and prepare the
contract account and the contractee's account.
CONTRACT ACCOUNT
PARTICULARS Rs.
PARTICULARS Rs
To Materials Purchased 1.00.000 By Materials on hand
5.000
To Direct Wages 1.50.000 By Plant on hand
To Direct Expenses 80.000 (Rs.50.000 -
10.000) 40.000
To Indirect Expenses } By Contractor's Alc
(15% on wages) 22.500 (Contract Price)
15.00.000
To Depreciation on Plant 10.000
To Profit & Loss Alc 11.82.500
15,45,000
15,45,000
Contractee's Account
Particulars Rs. Particulars
Rs.
To contract a/c 1500000 By Bank a/c
1500000
1500000
1500000
References/Sources
 Accounting for Managers by Dr. Sakshi Vasudeva Galgotia
Publishing Company Chapter 25 Contract Costing page no. 867
 Cost Accounting by S.P jain K.L Naran Part 4 Chapter 1 Job Batch
and Contract costing page no. 1.5
Thank U

Weitere ähnliche Inhalte

Was ist angesagt?

Was ist angesagt? (20)

Methods and techniques of Costing
Methods and techniques of CostingMethods and techniques of Costing
Methods and techniques of Costing
 
Contract costing
Contract costingContract costing
Contract costing
 
Batch costing
Batch costingBatch costing
Batch costing
 
Method of costing
Method of costingMethod of costing
Method of costing
 
A presentation on process costing
A presentation on process costingA presentation on process costing
A presentation on process costing
 
Contract and Job costing
Contract and Job costing Contract and Job costing
Contract and Job costing
 
Contract account
Contract accountContract account
Contract account
 
Absorption Costing and Marginal Costing ppt
Absorption Costing and Marginal Costing pptAbsorption Costing and Marginal Costing ppt
Absorption Costing and Marginal Costing ppt
 
Job and batch costing
Job and batch costingJob and batch costing
Job and batch costing
 
Job costing
Job costingJob costing
Job costing
 
Cost Accounting
 Cost Accounting  Cost Accounting
Cost Accounting
 
Elements of cost
Elements of costElements of cost
Elements of cost
 
Unit or output costing i
Unit or output costing iUnit or output costing i
Unit or output costing i
 
Overheads
OverheadsOverheads
Overheads
 
Overhead cost
Overhead costOverhead cost
Overhead cost
 
Contract costing
Contract costingContract costing
Contract costing
 
Cost Accountancy Assignment
Cost Accountancy AssignmentCost Accountancy Assignment
Cost Accountancy Assignment
 
Cost accounting
Cost accountingCost accounting
Cost accounting
 
Cost accounting
Cost accountingCost accounting
Cost accounting
 
Chapter 06 Costing Methods
Chapter 06   Costing MethodsChapter 06   Costing Methods
Chapter 06 Costing Methods
 

Andere mochten auch

Construction contract
Construction contractConstruction contract
Construction contractAqsa Shafique
 
Workshop on tally- Cost Centre
Workshop on tally- Cost CentreWorkshop on tally- Cost Centre
Workshop on tally- Cost CentreAnchit Agrawal
 
Standard Costing with CA Megha Shah
Standard Costing with CA Megha ShahStandard Costing with CA Megha Shah
Standard Costing with CA Megha ShahMegha Shah
 
People Soft Standard Costing Dmug
People Soft Standard Costing DmugPeople Soft Standard Costing Dmug
People Soft Standard Costing Dmugrcaldwell002
 
hybrid Costing process costing contract costing h
hybrid Costing process costing contract costing hhybrid Costing process costing contract costing h
hybrid Costing process costing contract costing hMitikaAnjel
 
Cost accounting bba fri
Cost accounting bba friCost accounting bba fri
Cost accounting bba friArslan Mehmood
 
Standard Costing - Uses & Limitations
Standard Costing - Uses & LimitationsStandard Costing - Uses & Limitations
Standard Costing - Uses & LimitationsM Ravish Malgi
 
Process costing
Process costingProcess costing
Process costinggrvthakkar
 
ICT Initiatives in Higher Education Department, GOK
ICT Initiatives in  Higher Education Department, GOKICT Initiatives in  Higher Education Department, GOK
ICT Initiatives in Higher Education Department, GOKeGov Magazine
 

Andere mochten auch (20)

Cost accounting bba 3rd
Cost accounting bba 3rdCost accounting bba 3rd
Cost accounting bba 3rd
 
METHODS & TECHNIQUES OF COSTING
METHODS & TECHNIQUES OF COSTINGMETHODS & TECHNIQUES OF COSTING
METHODS & TECHNIQUES OF COSTING
 
Tally. erp9
Tally. erp9Tally. erp9
Tally. erp9
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Workshop on tally- Cost Centre
Workshop on tally- Cost CentreWorkshop on tally- Cost Centre
Workshop on tally- Cost Centre
 
Standard Costing with CA Megha Shah
Standard Costing with CA Megha ShahStandard Costing with CA Megha Shah
Standard Costing with CA Megha Shah
 
Standard Costing
Standard CostingStandard Costing
Standard Costing
 
Fma10
Fma10Fma10
Fma10
 
People Soft Standard Costing Dmug
People Soft Standard Costing DmugPeople Soft Standard Costing Dmug
People Soft Standard Costing Dmug
 
hybrid Costing process costing contract costing h
hybrid Costing process costing contract costing hhybrid Costing process costing contract costing h
hybrid Costing process costing contract costing h
 
Cost accounting bba fri
Cost accounting bba friCost accounting bba fri
Cost accounting bba fri
 
IAS 11 Construction Contracts
IAS 11 Construction ContractsIAS 11 Construction Contracts
IAS 11 Construction Contracts
 
Standard costing
Standard costingStandard costing
Standard costing
 
Standard Costing - Uses & Limitations
Standard Costing - Uses & LimitationsStandard Costing - Uses & Limitations
Standard Costing - Uses & Limitations
 
Process costing
Process costingProcess costing
Process costing
 
Standard Costing Day2
Standard Costing Day2Standard Costing Day2
Standard Costing Day2
 
ICT Initiatives in Higher Education Department, GOK
ICT Initiatives in  Higher Education Department, GOKICT Initiatives in  Higher Education Department, GOK
ICT Initiatives in Higher Education Department, GOK
 
Standard Costing
Standard Costing Standard Costing
Standard Costing
 
Standard costing
Standard costingStandard costing
Standard costing
 
Standard Costing
Standard CostingStandard Costing
Standard Costing
 

Ähnlich wie Bba ii cost and management accounting u 3.3 contract costing

Contract costing, BCOM (HONS)
Contract costing, BCOM (HONS)Contract costing, BCOM (HONS)
Contract costing, BCOM (HONS)AmarnathRana1
 
AS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party TransactionsAS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party TransactionsPrakhar Jain
 
Job,batch and contract costing
Job,batch and contract costingJob,batch and contract costing
Job,batch and contract costingCollen Mahambo
 
Contract Costing NOtes.docx
Contract Costing NOtes.docxContract Costing NOtes.docx
Contract Costing NOtes.docxSreedeviPMenon
 
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr  ias 11 construction contract presentation by MOHSIN MUMTAZCfr  ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZmianmohsinmumtazshb
 
Types of contracts
Types of contracts   Types of contracts
Types of contracts MANNU KUMAR
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfChelDems
 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdfSaqib Imran
 
Chapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptxChapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptxsulevrunda
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-ContractsNikhil Kumar
 
Vietnam Accounting Standards - VAS 15 Construction contracts
Vietnam Accounting Standards - VAS 15 Construction contractsVietnam Accounting Standards - VAS 15 Construction contracts
Vietnam Accounting Standards - VAS 15 Construction contractsAC&C Consulting Co., Ltd.
 
contracts-unit 3.ppt
contracts-unit 3.pptcontracts-unit 3.ppt
contracts-unit 3.pptmayuray
 
Reasonableness of Construction Completion Costs
Reasonableness of Construction Completion CostsReasonableness of Construction Completion Costs
Reasonableness of Construction Completion CostsThe Vertex Companies, LLC
 
Final types of contracts- different types of contracts
Final types of contracts- different types of contractsFinal types of contracts- different types of contracts
Final types of contracts- different types of contractsMohammedAlfayad2
 

Ähnlich wie Bba ii cost and management accounting u 3.3 contract costing (20)

Contract costing, BCOM (HONS)
Contract costing, BCOM (HONS)Contract costing, BCOM (HONS)
Contract costing, BCOM (HONS)
 
AS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party TransactionsAS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party Transactions
 
Job,batch and contract costing
Job,batch and contract costingJob,batch and contract costing
Job,batch and contract costing
 
Contract Costing NOtes.docx
Contract Costing NOtes.docxContract Costing NOtes.docx
Contract Costing NOtes.docx
 
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr  ias 11 construction contract presentation by MOHSIN MUMTAZCfr  ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
 
Types of contracts
Types of contracts   Types of contracts
Types of contracts
 
Ias 11
Ias 11Ias 11
Ias 11
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdf
 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdf
 
MODULE 5.pptx
MODULE 5.pptxMODULE 5.pptx
MODULE 5.pptx
 
Chapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptxChapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptx
 
ICDS : Construction Contracts
ICDS : Construction ContractsICDS : Construction Contracts
ICDS : Construction Contracts
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
 
Types of contracts
Types of contractsTypes of contracts
Types of contracts
 
Vietnam Accounting Standards - VAS 15 Construction contracts
Vietnam Accounting Standards - VAS 15 Construction contractsVietnam Accounting Standards - VAS 15 Construction contracts
Vietnam Accounting Standards - VAS 15 Construction contracts
 
contracts-unit 3.ppt
contracts-unit 3.pptcontracts-unit 3.ppt
contracts-unit 3.ppt
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Reasonableness of Construction Completion Costs
Reasonableness of Construction Completion CostsReasonableness of Construction Completion Costs
Reasonableness of Construction Completion Costs
 
Final types of contracts- different types of contracts
Final types of contracts- different types of contractsFinal types of contracts- different types of contracts
Final types of contracts- different types of contracts
 

Mehr von Rai University

Brochure Rai University
Brochure Rai University Brochure Rai University
Brochure Rai University Rai University
 
Bdft ii, tmt, unit-iii, dyeing & types of dyeing,
Bdft ii, tmt, unit-iii,  dyeing & types of dyeing,Bdft ii, tmt, unit-iii,  dyeing & types of dyeing,
Bdft ii, tmt, unit-iii, dyeing & types of dyeing,Rai University
 
Bsc agri 2 pae u-4.4 publicrevenue-presentation-130208082149-phpapp02
Bsc agri  2 pae  u-4.4 publicrevenue-presentation-130208082149-phpapp02Bsc agri  2 pae  u-4.4 publicrevenue-presentation-130208082149-phpapp02
Bsc agri 2 pae u-4.4 publicrevenue-presentation-130208082149-phpapp02Rai University
 
Bsc agri 2 pae u-4.3 public expenditure
Bsc agri  2 pae  u-4.3 public expenditureBsc agri  2 pae  u-4.3 public expenditure
Bsc agri 2 pae u-4.3 public expenditureRai University
 
Bsc agri 2 pae u-4.2 public finance
Bsc agri  2 pae  u-4.2 public financeBsc agri  2 pae  u-4.2 public finance
Bsc agri 2 pae u-4.2 public financeRai University
 
Bsc agri 2 pae u-4.1 introduction
Bsc agri  2 pae  u-4.1 introductionBsc agri  2 pae  u-4.1 introduction
Bsc agri 2 pae u-4.1 introductionRai University
 
Bsc agri 2 pae u-3.3 inflation
Bsc agri  2 pae  u-3.3  inflationBsc agri  2 pae  u-3.3  inflation
Bsc agri 2 pae u-3.3 inflationRai University
 
Bsc agri 2 pae u-3.2 introduction to macro economics
Bsc agri  2 pae  u-3.2 introduction to macro economicsBsc agri  2 pae  u-3.2 introduction to macro economics
Bsc agri 2 pae u-3.2 introduction to macro economicsRai University
 
Bsc agri 2 pae u-3.1 marketstructure
Bsc agri  2 pae  u-3.1 marketstructureBsc agri  2 pae  u-3.1 marketstructure
Bsc agri 2 pae u-3.1 marketstructureRai University
 
Bsc agri 2 pae u-3 perfect-competition
Bsc agri  2 pae  u-3 perfect-competitionBsc agri  2 pae  u-3 perfect-competition
Bsc agri 2 pae u-3 perfect-competitionRai University
 

Mehr von Rai University (20)

Brochure Rai University
Brochure Rai University Brochure Rai University
Brochure Rai University
 
Mm unit 4point2
Mm unit 4point2Mm unit 4point2
Mm unit 4point2
 
Mm unit 4point1
Mm unit 4point1Mm unit 4point1
Mm unit 4point1
 
Mm unit 4point3
Mm unit 4point3Mm unit 4point3
Mm unit 4point3
 
Mm unit 3point2
Mm unit 3point2Mm unit 3point2
Mm unit 3point2
 
Mm unit 3point1
Mm unit 3point1Mm unit 3point1
Mm unit 3point1
 
Mm unit 2point2
Mm unit 2point2Mm unit 2point2
Mm unit 2point2
 
Mm unit 2 point 1
Mm unit 2 point 1Mm unit 2 point 1
Mm unit 2 point 1
 
Mm unit 1point3
Mm unit 1point3Mm unit 1point3
Mm unit 1point3
 
Mm unit 1point2
Mm unit 1point2Mm unit 1point2
Mm unit 1point2
 
Mm unit 1point1
Mm unit 1point1Mm unit 1point1
Mm unit 1point1
 
Bdft ii, tmt, unit-iii, dyeing & types of dyeing,
Bdft ii, tmt, unit-iii,  dyeing & types of dyeing,Bdft ii, tmt, unit-iii,  dyeing & types of dyeing,
Bdft ii, tmt, unit-iii, dyeing & types of dyeing,
 
Bsc agri 2 pae u-4.4 publicrevenue-presentation-130208082149-phpapp02
Bsc agri  2 pae  u-4.4 publicrevenue-presentation-130208082149-phpapp02Bsc agri  2 pae  u-4.4 publicrevenue-presentation-130208082149-phpapp02
Bsc agri 2 pae u-4.4 publicrevenue-presentation-130208082149-phpapp02
 
Bsc agri 2 pae u-4.3 public expenditure
Bsc agri  2 pae  u-4.3 public expenditureBsc agri  2 pae  u-4.3 public expenditure
Bsc agri 2 pae u-4.3 public expenditure
 
Bsc agri 2 pae u-4.2 public finance
Bsc agri  2 pae  u-4.2 public financeBsc agri  2 pae  u-4.2 public finance
Bsc agri 2 pae u-4.2 public finance
 
Bsc agri 2 pae u-4.1 introduction
Bsc agri  2 pae  u-4.1 introductionBsc agri  2 pae  u-4.1 introduction
Bsc agri 2 pae u-4.1 introduction
 
Bsc agri 2 pae u-3.3 inflation
Bsc agri  2 pae  u-3.3  inflationBsc agri  2 pae  u-3.3  inflation
Bsc agri 2 pae u-3.3 inflation
 
Bsc agri 2 pae u-3.2 introduction to macro economics
Bsc agri  2 pae  u-3.2 introduction to macro economicsBsc agri  2 pae  u-3.2 introduction to macro economics
Bsc agri 2 pae u-3.2 introduction to macro economics
 
Bsc agri 2 pae u-3.1 marketstructure
Bsc agri  2 pae  u-3.1 marketstructureBsc agri  2 pae  u-3.1 marketstructure
Bsc agri 2 pae u-3.1 marketstructure
 
Bsc agri 2 pae u-3 perfect-competition
Bsc agri  2 pae  u-3 perfect-competitionBsc agri  2 pae  u-3 perfect-competition
Bsc agri 2 pae u-3 perfect-competition
 

Kürzlich hochgeladen

APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Disha Kariya
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...Sapna Thakur
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 

Kürzlich hochgeladen (20)

APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 

Bba ii cost and management accounting u 3.3 contract costing

  • 2. CONTRACT COSTING  Contract costing also known as terminal costing, is a variant of job costing. In this method of job costing , each contract is a cost unit and a account is opened for each contract in the book of contractor to ascertain profit/loss thereon.  Contract costing is used in: Building construction, Road construction, Bridge construction, other civil engineering works, ship building etc.
  • 3. Contract costing and job costing -Distinction  Main points of distinction as follows: 1- The no. of jobs undertaken at a time are usually large as compared to no. of contracts because contracts are generally much bigger in size. 2- In contract costing , most of the costs are chargeable direct to contract account. Under job costing direct allocation to such an extent is not possible.
  • 4. Con.. 3- Allocation and apportionment of overhead costs is simpler in contract costing as compared to job costing . 4- contract is generally big while job is a small. It is well said , “ a job is small contract and contract is big job” 5- jobs are usually carried in factory premises while contract work is done at site.
  • 5. Features of contract costing 1- contracts are generally takes more than one year to complete . 2- contracts are generally of large size and therefore, a contractor usually carries out small number of contracts in the course of one year. 3- work on contracts is carried out at the site of contracts and not in factory premises . 4-Each contract under taken is treated as a cost unit. 5-A separate contract account is prepared for each contract in the books of the contractor to ascertain profit and loss on each contract.
  • 6. Recording Cost Contract or Costing Procedure In contract costing, costs are allocated, collected and accumulated according to the contract works. Each contract is treated as a separate entity in which each contract account may be maintained separately or in general ledger itself for the purpose of costing and cost control. The following are the costing procedure for different costs relating to the important expenses : (1) Materials: (A) Contract Account is debited with the following transactions relating to materials : (I) Bulk of materials are purchased for a specific contract from suppliers. (2) Materials obtained from contractor's central stores through the requisition slips. (3) Materials transferred from one contract to another contract. (4) Value of materials remaining unutilized on site during the accounting year. .
  • 7. (B) Contract Account is credited with the following transactions relating to materials: (1) Materials returned under Materials Return Note. (2) Sale of materials at site on account of some extraneous reasons. (3) Materials transferred to other contracts. (4) Materials stolen or destroyed by fire. (5) On completion, if a part of materials received from the stores are returned
  • 8. (C) Any profit or loss on materials account is transferred to the Profu and Loss Account: (I) Sale price is different from the cost price. (2) Resulting from the sale of materials at site. (3) Resulting from the materials stolen or destroyed by fire. (2) Labour: In the case of contract costing, all labours engaged at site and the salaries and wages paid to the labour and workers are treated as direct labour cost is debited to Contract Account. (3) Direct Expenses: Most of the expenses like electricity, insurance telephone, postage, sub-contracts, Architect's fees etc. can also be treated as direct cost is debited to Contract Account. (4) Overhead Cost: In the case of contract costing overheads incurred only an insignificant part of the total cost of contract account. The nature office and administrative expenses of a particular contract may be apportioned on suitable basis.
  • 9. (5) Plant and Machinery: For use of plant and machinery in a particular contract, the treatment of plant costs in any of the two ways: (a) Where a plant has been specially purchased for a particular contract and will be exhausted at site Contract Account should be debited with the cost of the plant. On completion of the contract the residual or written down value as shown by the Plant Ledger will be credited "to the Contract Account. (b) When the plant and machinery are required to the contract site only for a shorter period, the contract account should be debited with the notional amount of depreciation based on some estimates be charged to Contract Account.
  • 10. Sub-Contracts: Sub-Contracts refer to some portions of the specified work connected with the main contract, to be done by the sub-contractor. For example, the work of painting, special flooring, steel work etc. may be given to the sub-contractors. Usually sub-contract has been undertaken on cost-plus basis and the cost of such sub-contract should be treated as a direct charge and is debited to Contract Account.
  • 11. (7) Work Certified: In the case of the small contracts which are completed within the shorter period, the contractor pays the contract price on the completion of the contract. In the case of contracts of long duration. the contract agreement provides interim payment to the contractor. It is done on the basis of certificates issued by the contractee's Surveyor, Architect or Engineer. At the same time Contractee usually does not pay to the full value of the work certified. A portion of amount say 20% or 30% thereof shall be retained by the Contractee. The money so retained is called as "Retention Money." This retention money is intented to ensure that the contractor to complete the work as scheduled and according to specifications. Money retained could also be used for imposing penalties for faulty or delayed work. This amount will be settled on completion of the contract.
  • 12. (8) Work Uncertified : If the progress of a work is unsatisfactory or the work has not reached the stipulated stage, though certain work is completed, such work does not qualify for a certificate by the Contractee's Architect or Surveyor is termed as "Work Uncertified." It is valued at cost and credited to Contract Account and debited to Work in Progress Account. (9) Work in Progress: Work in progress includes the amount of work .certified and the amount of work uncertified. The work in progress account will appear on the asset side of the balance sheet. The amount of cash received from the contractee and reserve for contingencies will be deducted out of this amount.
  • 13. Treatment of Profits or Loss on Contracts Alc. The accounting treatment of profits or loss of contracts in the following stages : (A) Profit or Loss on incomplete contracts (B) Profits or Loss on completed contracts
  • 14. (A) Profit or Loss on Incomplete Contracts To determine the profits to be taken to Profit and Loss Account. in the case of incomplete contracts, the following situations may arise : (i) Completion of Contract is Less than 25% : In this case no profit should be taken to Profit and Loss Account. (ii) Completion of Contract is upto 25% or more but Less than 50% : In this case one-third of the notional profit, reduced in the ratio of cash received to work certified, should be transferred to Profit and Loss Account. It can be expressed as: 1/3 x Notional Profitx Cash Received/ Work Certified
  • 15. (iii) Completion of Contract is upto 50% or more but Less than 90% : In this case two-third of the notional profit reduced by proportion of cash received to work certified is transferred to Profit and Loss Account. The equation is 2/3xNotionalProfitxCashReceived/Work Certified
  • 16. (iv) Completion of Contract is upto 90% or more than 90%, i.e., it is nearing completion: In this case the profit to be taken to Profit and Loss Account is determined by determining the estimated profit and using anyone of the following formula : (a)Estimated Profit x Work Certified/ Contract Price (b) Estimated Profit x Cash Received / Contract Price (c) Estimated Profit x Cost of Work to Date/ Estimated total cost
  • 17. (d) Estimated Profit X Cost of Work to Date/ Estimated Total Cost x Cash Received / Work Certified (e) Notional Profit X Work Certified /Contract Price
  • 18. Escalation Clause: This clause is often provided in contracts as safeguard against any likely changes in price or utilization of material and labour. Such a clause in a contract would provide that in the event of a specified contingency happening, the contract price would be suitably enhanced by an agreed formula or factor. This clause is particularly necessary where the prices of a certain raw material are likely to rise. where labour rates are anticipated to increase, or where the quantity of material and labour hours cannot be assessed properly or estimated unless the job has progressed sufficiently.
  • 19. Cost-Plus Contract: These contracts provide for the payment by the contractee of the actual cost of manufacturing plus a stipulated profit. The profit to be added to the cost may be a fixed amount or it may be a stipulated percentage of cost. These contracts are generally entered into when at the time of undertaking of a work, it is not possible to estimate it's cost with reasonable accuracy due to unstable condition of material. labour etc. or when the work is spread over a long period of time and prices of materials. rates of labour etc. are liable to fluctuate.
  • 20. (B) Profits or Loss on Completed Contracts : When a contract is completed, the overall profit or loss on the contract is transferred to the Profit and Loss Account.
  • 21. The following are the expenses on a contract which commences on 1st Jan. 2003 Materials purchased 1.00.000 Materials on hand 5.000 Direct wages 1.50.000 Plant issued 50.000 Direct expenses 80000 The contract price was Rs. 15.00.000 and the same was duly received when the contract was completed in August 2003. Charge indirect expenses at 15% on wages. provide Rs. 10.000 for depreciation on plant and prepare the contract account and the contractee's account.
  • 22. CONTRACT ACCOUNT PARTICULARS Rs. PARTICULARS Rs To Materials Purchased 1.00.000 By Materials on hand 5.000 To Direct Wages 1.50.000 By Plant on hand To Direct Expenses 80.000 (Rs.50.000 - 10.000) 40.000 To Indirect Expenses } By Contractor's Alc (15% on wages) 22.500 (Contract Price) 15.00.000 To Depreciation on Plant 10.000 To Profit & Loss Alc 11.82.500 15,45,000 15,45,000
  • 23. Contractee's Account Particulars Rs. Particulars Rs. To contract a/c 1500000 By Bank a/c 1500000 1500000 1500000
  • 24. References/Sources  Accounting for Managers by Dr. Sakshi Vasudeva Galgotia Publishing Company Chapter 25 Contract Costing page no. 867  Cost Accounting by S.P jain K.L Naran Part 4 Chapter 1 Job Batch and Contract costing page no. 1.5