SlideShare ist ein Scribd-Unternehmen logo
1 von 23
DESIGN OF PILE CAP
NARULA INSTITUTE OF TECHNOLOGY
DEPT. OF CIVIL ENGINEERING
GROUP MEMBERS
1. SHABAN AKHTAR (12701312085)
2. AYON BHATTACHARJEE (12701312025)
3. ANUPAM GHOSH (12701312012)
4. SOURAV GHOSH (12701312098)
5. SAMRAN BANERJEE (12701312078)
6. SANAT BANIK (12701312079)
INTRODUCTION
• Foundations provide support for structures,
transferring their load to layers of soil or rock that
have sufficient bearing capacity and suitable
settlement characteristics.
• Very broadly, foundations can be categorised as
shallow foundations or deep foundations.
• Shallow foundations are typically used where the
loads imposed by a structure are low relative to the
bearing capacity of the surface soils.
• Deep foundations are necessary where the bearing
capacity of the surface soils is insufficient to support
loads imposed and so they are transferred to deeper
layers with higher bearing capacity.
WHAT IS A PILE CAP?
• A pile cap is a thick concrete mat that rests on concrete
or timber piles that have been driven into soft or
unstable ground to provide a suitable stable foundation.
• It usually forms part of the foundation of a building,
typically a multi-story building, structure or support
base for heavy equipment.
• The cast concrete pile cap distributes the load of the
building into the piles.
• A similar structure to a pile cap is a "raft", which is a
concrete foundation floor resting directly onto soft soil
which may be liable to subsidence.
NEED FOR PILE CAP
• Pile foundation is required when the soil bearing
capacity is not sufficient for the structure to withstand.
This is due to the soil condition or the order of bottom
layers, type of loads on foundations, conditions at site
and operational conditions.
• A pile foundation consists of two components: Pile cap
and single or group of piles. Piles transfers the loads
from structures to the hard strata, rocks or soil with
high bearing capacity. These are long and slender
members whose length can be more than 15m.
DESIGN OF PILE CAP
• As per IS 2911 (Part I/ Sec 3) -2010, the pile cap
may be designed by assuming
• that the load from column is dispersed at 45° from
the top of the cap up to the mid
• depth of the pile cap from the base of the column
or pedestal. The reaction from
• piles may also be taken to be distributed at 45°
from the edge of the pile, up to the
• mid depth of the pile cap. On this basis the
maximum bending moment and shear
• forces should be worked out at critical sections.
ASSUMPTIONS INVOLVED
• (i) Pile cap is perfectly rigid.
• (ii) Pile heads are hinged to the pile cap and
hence no bending moment is
• transmitted to piles from pile caps.
• (iii) Since the piles are short and elastic columns,
the deformations and stress distribution are
planer.
DESIGN PARAMETERS
• (i) Shape of pile cap.
• (ii) Depth of pile cap.
• (iii) Amount of steel to be provided.
• (iv) Arrangement of reinforcement.
DESIGN PROCEDURE
• DETERMINE NUMBER OF PILE
• PILE CAP ARRANGEMENT AND PLANE DIMENSION
• PILE CAP PRELIMINARY DEPTH
• CHECK FORCES IN PILES
• CHECK FOR PUNCHING SHEAR
• CHECK FOR SHEAR
• DESIGN OF MOMENT
• CHECK FOR BOND
• DETAILS FOR REINFORCEMENT
Explanation of pile cap design with example:-
EXAMPLE 1 :-
Diameter of pile : 300 mm
Spacing between the piles : 3xd= 3x400 mm [ As per IS 2911
= 1200 mm (Part 1/Sec 3) :2010
Clause :
6.6.2.]
No of piles under a pile cap: 3
Size of column : 400x400 mm
Load transferred by column : 1500 kN
Load on each pile : 1500/3= 500 kN
The dimension of the pile cap, the distance between the connecting line of
the piles and the face of critical zone of punching shear are given in the
figure with details………..
Details about the pile cap of this example……………..
We
have
assume
that the
effectiv
e depth
of pile
cap
is 500
mm……
…
Unit Moment at face AB = 0.287x1000= 287 kN-m
Unit Moment at face AC = 0.287x1000= 287 kN-m
Unit Moment at face BC = 0.1x1000= 100 kN-m
Formula used to calculate Area of steel against
corresponding moment:
Mu= 0.87 x fy x As t x d (1 - 0.42 x Xu/d)
(AS PER IS:456 (2000) ANNEX G , CLAUSE
38.1………
Mu = Moment
fy = Characteristic strength of steel, here 415
As t = Area of steel
d= Effective depth of pile cap
Xu= Depth of neutral axis
Area of steel required parallel to AB = 1991 mm2
Area of steel required parallel to AC = 1991 mm2
Area of steel required parallel to BC = 693 mm2
We should provide 12 mm rod of 113 mm2
Spacing through AB = (113 x 1000)/1991= 60 mm
Spacing through AC = (113 x 1000)/1991= 60 mm
Spacing through BC = (113 x 1000)/693= 160 mm
OVERALL DEPTH OF THE PILE CAP =(500+(100+12+12+6)X2)= 760 mm
Explanation of pile cap design with example:-
EXAMPLE 2 :-
Diameter of pile : 300 mm
Spacing between the piles : 3xd= 3x400 mm [ As per IS 2911
= 1200 mm (Part 1/Sec
3) : 2010
Clause : 6.6.2.]
No of piles under a pile cap: 4
Size of column : 400x400 mm
Load transferred by column : 1600 kN
Load on each pile : 1600/4= 400 kN
The dimension of the pile cap, the distance between the
connecting line of the piles and the face of critical zone of
punching shear are given in the figure with details………..
Details about the pile cap of this example……………..
We have
assume
that the
overall
depth of
pile cap
is 600
mm……
…
Unit Moment at face AB = 0.23x800= 184 kN-m
Unit Moment at face BC = 0.23x800= 184 kN-m
Unit Moment at face CD = 0.23x800= 184 kN-m
Unit Moment at face DA = 0.23x800= 184 kN-m
Formula used to calculate Area of steel against
corresponding moment:
Mu= 0.87 x fy x As t x d (1 - 0.42 x Xu/d)
(AS PER IS:456 (2000) ANNEX G , CLAUSE 38.1………)
Mu = Moment
fy = Characteristic strength of steel, here 415
As t = Area of steel
d= Effective depth of pile cap
Xu= Depth of neutral axis
Area of steel required parallel to AB = 1877 mm2
Area of steel required parallel to BC = 1877 mm2
Area of steel required parallel to CD = 1877mm2
Area of steel required parallel to DA= 1877mm2
We should provide 12 mm rod of 113 mm2
Spacing through AB = (113 x 1000)/1877= 60 mm
Spacing through BC = (113 x 1000)/1877= 60 mm
Spacing through CD = (113 x 1000)/1877= 160 mm
Spacing through DA = (113 x 1000)/1877= 160 mm
EFFECTIVE DEPTH OF THE PILE CAP =(600-(100+12+12+6)X2)= 340
mm
Making of PILE CAP
In practical field…………
ACKNOWLEDGEMENT:
â–  Our project is successful due to the effort of those people
who have given their valuable time and advice. We sincerely
appreciate the inspiration, support and guidance of all those
people .
We, the student of "NARULA INSTITUTE OF TECHNOLOGY" are
extremely thankful to our teachers for giving us the
opportunity to do this project on the topic of ”Design of Pile
Cap”. At this juncture we feel deeply honour in expressing
our sincere thanks to Dr.Chandrasekhar Sen Majumdar, Prof.
Abhipriya Halder, Prof.Priyabrata Guha sir
for making the resources available at right time and
providing valuable insights leading to the successful
completion of our project.
CONCLUSION
A pile cap is a thick concrete mat that
rests on concrete or timber piles that
have been driven into soft or unstable
ground to provide a suitable stable
foundation. It usually forms part of
the foundation of a building, typically a
multi-story building, structure or support
base for heavy equipment. The
cast concrete pile cap distributes the
load of the building into the piles. A
similar structure to a pile cap is a "raft",
which is a concrete foundation floor
resting directly onto soft soil which may
be liable to subsidence.
SPECIAL THANKS to
PROF. ABHIPRIYAHALDER
We are very thankful that we have a
teacher cum leader like you. Your inspiration
really motivate us to do this project on such
a topic which play a valuable role in civil engineering.
Without your inspiration it is impossible to complete
this project. Thanks a lot sir……….for your support and
inspiration………………

Weitere ähnliche Inhalte

Was ist angesagt?

Reinforced slab
Reinforced slabReinforced slab
Reinforced slab
Nik M Farid
 

Was ist angesagt? (20)

Combined footings
Combined footingsCombined footings
Combined footings
 
Singly reinforced beam ast - over reinforced
Singly reinforced beam   ast - over reinforcedSingly reinforced beam   ast - over reinforced
Singly reinforced beam ast - over reinforced
 
Numerical problem on bearing capacity is code terzaghi water table (usefulsea...
Numerical problem on bearing capacity is code terzaghi water table (usefulsea...Numerical problem on bearing capacity is code terzaghi water table (usefulsea...
Numerical problem on bearing capacity is code terzaghi water table (usefulsea...
 
Design of Reinforced Concrete Structure (IS 456:2000)
Design of Reinforced Concrete Structure (IS 456:2000)Design of Reinforced Concrete Structure (IS 456:2000)
Design of Reinforced Concrete Structure (IS 456:2000)
 
Rcc member design steps
Rcc member design stepsRcc member design steps
Rcc member design steps
 
Problems on bearing capacity of soil
Problems on bearing capacity of soilProblems on bearing capacity of soil
Problems on bearing capacity of soil
 
Ch 7 design of rcc footing
Ch 7 design of rcc footingCh 7 design of rcc footing
Ch 7 design of rcc footing
 
Numerical problem bearing capacity terzaghi , group pile capacity (usefulsear...
Numerical problem bearing capacity terzaghi , group pile capacity (usefulsear...Numerical problem bearing capacity terzaghi , group pile capacity (usefulsear...
Numerical problem bearing capacity terzaghi , group pile capacity (usefulsear...
 
Lecture 8 raft foundation
Lecture 8 raft foundationLecture 8 raft foundation
Lecture 8 raft foundation
 
Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma
 
Chapter 1
Chapter 1Chapter 1
Chapter 1
 
Column design.ppt
Column design.pptColumn design.ppt
Column design.ppt
 
ANALYSIS AND DESIGN OF HIGH RISE BUILDING BY USING ETABS
ANALYSIS AND DESIGN OF HIGH RISE BUILDING BY USING ETABSANALYSIS AND DESIGN OF HIGH RISE BUILDING BY USING ETABS
ANALYSIS AND DESIGN OF HIGH RISE BUILDING BY USING ETABS
 
Pile cap design structural guide
Pile cap design   structural guidePile cap design   structural guide
Pile cap design structural guide
 
Geotechnical Engineering-II [Lec #23: Rankine Earth Pressure Theory]
Geotechnical Engineering-II [Lec #23: Rankine Earth Pressure Theory]Geotechnical Engineering-II [Lec #23: Rankine Earth Pressure Theory]
Geotechnical Engineering-II [Lec #23: Rankine Earth Pressure Theory]
 
Reinforced slab
Reinforced slabReinforced slab
Reinforced slab
 
One way slab load calculation
One way slab load calculation One way slab load calculation
One way slab load calculation
 
Lecture 3 foundation settlement
Lecture 3 foundation settlementLecture 3 foundation settlement
Lecture 3 foundation settlement
 
Footing design
Footing designFooting design
Footing design
 
Flexural design of beam...PRC-I
Flexural design of beam...PRC-IFlexural design of beam...PRC-I
Flexural design of beam...PRC-I
 

Andere mochten auch

Pile foundation
Pile foundationPile foundation
Pile foundation
Shivam Gandhi
 
PILE-CAP & Batching plant
PILE-CAP & Batching plantPILE-CAP & Batching plant
PILE-CAP & Batching plant
Sagnik Datta
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
Wilden How
 
Room Acoustics
Room AcousticsRoom Acoustics
Room Acoustics
Drew
 
PILE FOUNDATION-INDIA
PILE FOUNDATION-INDIAPILE FOUNDATION-INDIA
PILE FOUNDATION-INDIA
aditya singh
 

Andere mochten auch (20)

Pile design guide (Collected)
Pile design guide (Collected)Pile design guide (Collected)
Pile design guide (Collected)
 
Sachpazis: 4 rc piles cap design with eccentricity example (bs8110 part1-1997)
Sachpazis: 4 rc piles cap design with eccentricity example (bs8110 part1-1997)Sachpazis: 4 rc piles cap design with eccentricity example (bs8110 part1-1997)
Sachpazis: 4 rc piles cap design with eccentricity example (bs8110 part1-1997)
 
Pile cap two pile laod 50 t desigh and drawing
Pile cap  two pile laod 50 t  desigh and drawingPile cap  two pile laod 50 t  desigh and drawing
Pile cap two pile laod 50 t desigh and drawing
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Pile Foundations
Pile FoundationsPile Foundations
Pile Foundations
 
PILE-CAP & Batching plant
PILE-CAP & Batching plantPILE-CAP & Batching plant
PILE-CAP & Batching plant
 
Pile foundation ppt
Pile foundation pptPile foundation ppt
Pile foundation ppt
 
Pile foundation
Pile  foundation Pile  foundation
Pile foundation
 
types of Foundations with animated sketches
types of Foundations with animated sketchestypes of Foundations with animated sketches
types of Foundations with animated sketches
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
 
Building Construction - Foundation
Building Construction - FoundationBuilding Construction - Foundation
Building Construction - Foundation
 
Room Acoustics
Room AcousticsRoom Acoustics
Room Acoustics
 
Specifications of excavation and foundation
Specifications of excavation and foundationSpecifications of excavation and foundation
Specifications of excavation and foundation
 
Illumination
IlluminationIllumination
Illumination
 
Electric power grid
Electric power gridElectric power grid
Electric power grid
 
Shallow Foundations ( Combined, Strap, Raft foundation)
Shallow Foundations ( Combined, Strap, Raft foundation)Shallow Foundations ( Combined, Strap, Raft foundation)
Shallow Foundations ( Combined, Strap, Raft foundation)
 
ALL ABOUT DEEP FOUNDATIONS
ALL ABOUT DEEP FOUNDATIONSALL ABOUT DEEP FOUNDATIONS
ALL ABOUT DEEP FOUNDATIONS
 
Pile Foundation presentation
Pile Foundation presentationPile Foundation presentation
Pile Foundation presentation
 
PILE FOUNDATION-INDIA
PILE FOUNDATION-INDIAPILE FOUNDATION-INDIA
PILE FOUNDATION-INDIA
 
Elevators & Escalators
Elevators & EscalatorsElevators & Escalators
Elevators & Escalators
 

Ă„hnlich wie Design of pile cap

Deep Foundation (Pile)
Deep Foundation (Pile)Deep Foundation (Pile)
Deep Foundation (Pile)
GeraldDaniel9
 

Ă„hnlich wie Design of pile cap (20)

Two Pile Group.pdf
Two Pile Group.pdfTwo Pile Group.pdf
Two Pile Group.pdf
 
Two pile group
Two pile groupTwo pile group
Two pile group
 
pile group
pile grouppile group
pile group
 
Two Pile Group.pdf
Two Pile Group.pdfTwo Pile Group.pdf
Two Pile Group.pdf
 
Design of Steel Grillage Foundation for an Auditorium
Design of Steel Grillage Foundation for an AuditoriumDesign of Steel Grillage Foundation for an Auditorium
Design of Steel Grillage Foundation for an Auditorium
 
design-of-combined-footings-by-is-456-ppt.pdf
design-of-combined-footings-by-is-456-ppt.pdfdesign-of-combined-footings-by-is-456-ppt.pdf
design-of-combined-footings-by-is-456-ppt.pdf
 
BATCH 4 PPT.pptx
BATCH 4 PPT.pptxBATCH 4 PPT.pptx
BATCH 4 PPT.pptx
 
design of steel flyover
design of steel flyoverdesign of steel flyover
design of steel flyover
 
Deep Foundation (Pile)
Deep Foundation (Pile)Deep Foundation (Pile)
Deep Foundation (Pile)
 
Presentationt design and analysis of multistorey building
Presentationt design and analysis of multistorey buildingPresentationt design and analysis of multistorey building
Presentationt design and analysis of multistorey building
 
onw way slab design
onw way slab designonw way slab design
onw way slab design
 
Memorial Hall- Design Project
Memorial Hall- Design ProjectMemorial Hall- Design Project
Memorial Hall- Design Project
 
Isolated footing design
Isolated footing designIsolated footing design
Isolated footing design
 
Design of RCC Column footing
Design of RCC Column footingDesign of RCC Column footing
Design of RCC Column footing
 
0 ne way slab
0 ne way slab0 ne way slab
0 ne way slab
 
Analysis & design of T-Beam bridge
Analysis & design of T-Beam bridgeAnalysis & design of T-Beam bridge
Analysis & design of T-Beam bridge
 
BCON PROJ 1
BCON PROJ 1BCON PROJ 1
BCON PROJ 1
 
Rectangular tank
Rectangular tankRectangular tank
Rectangular tank
 
Hospital Building(PPT).pptx
Hospital Building(PPT).pptxHospital Building(PPT).pptx
Hospital Building(PPT).pptx
 
footing design
footing designfooting design
footing design
 

KĂĽrzlich hochgeladen

"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 

KĂĽrzlich hochgeladen (20)

Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptx
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 

Design of pile cap

  • 1. DESIGN OF PILE CAP NARULA INSTITUTE OF TECHNOLOGY DEPT. OF CIVIL ENGINEERING
  • 2. GROUP MEMBERS 1. SHABAN AKHTAR (12701312085) 2. AYON BHATTACHARJEE (12701312025) 3. ANUPAM GHOSH (12701312012) 4. SOURAV GHOSH (12701312098) 5. SAMRAN BANERJEE (12701312078) 6. SANAT BANIK (12701312079)
  • 3. INTRODUCTION • Foundations provide support for structures, transferring their load to layers of soil or rock that have sufficient bearing capacity and suitable settlement characteristics. • Very broadly, foundations can be categorised as shallow foundations or deep foundations. • Shallow foundations are typically used where the loads imposed by a structure are low relative to the bearing capacity of the surface soils. • Deep foundations are necessary where the bearing capacity of the surface soils is insufficient to support loads imposed and so they are transferred to deeper layers with higher bearing capacity.
  • 4. WHAT IS A PILE CAP? • A pile cap is a thick concrete mat that rests on concrete or timber piles that have been driven into soft or unstable ground to provide a suitable stable foundation. • It usually forms part of the foundation of a building, typically a multi-story building, structure or support base for heavy equipment. • The cast concrete pile cap distributes the load of the building into the piles. • A similar structure to a pile cap is a "raft", which is a concrete foundation floor resting directly onto soft soil which may be liable to subsidence.
  • 5. NEED FOR PILE CAP • Pile foundation is required when the soil bearing capacity is not sufficient for the structure to withstand. This is due to the soil condition or the order of bottom layers, type of loads on foundations, conditions at site and operational conditions. • A pile foundation consists of two components: Pile cap and single or group of piles. Piles transfers the loads from structures to the hard strata, rocks or soil with high bearing capacity. These are long and slender members whose length can be more than 15m.
  • 6. DESIGN OF PILE CAP • As per IS 2911 (Part I/ Sec 3) -2010, the pile cap may be designed by assuming • that the load from column is dispersed at 45° from the top of the cap up to the mid • depth of the pile cap from the base of the column or pedestal. The reaction from • piles may also be taken to be distributed at 45° from the edge of the pile, up to the • mid depth of the pile cap. On this basis the maximum bending moment and shear • forces should be worked out at critical sections.
  • 7. ASSUMPTIONS INVOLVED • (i) Pile cap is perfectly rigid. • (ii) Pile heads are hinged to the pile cap and hence no bending moment is • transmitted to piles from pile caps. • (iii) Since the piles are short and elastic columns, the deformations and stress distribution are planer.
  • 8. DESIGN PARAMETERS • (i) Shape of pile cap. • (ii) Depth of pile cap. • (iii) Amount of steel to be provided. • (iv) Arrangement of reinforcement.
  • 9. DESIGN PROCEDURE • DETERMINE NUMBER OF PILE • PILE CAP ARRANGEMENT AND PLANE DIMENSION • PILE CAP PRELIMINARY DEPTH • CHECK FORCES IN PILES • CHECK FOR PUNCHING SHEAR • CHECK FOR SHEAR • DESIGN OF MOMENT • CHECK FOR BOND • DETAILS FOR REINFORCEMENT
  • 10. Explanation of pile cap design with example:- EXAMPLE 1 :- Diameter of pile : 300 mm Spacing between the piles : 3xd= 3x400 mm [ As per IS 2911 = 1200 mm (Part 1/Sec 3) :2010 Clause : 6.6.2.] No of piles under a pile cap: 3 Size of column : 400x400 mm Load transferred by column : 1500 kN Load on each pile : 1500/3= 500 kN The dimension of the pile cap, the distance between the connecting line of the piles and the face of critical zone of punching shear are given in the figure with details………..
  • 11. Details about the pile cap of this example……………..
  • 12. We have assume that the effectiv e depth of pile cap is 500 mm…… …
  • 13. Unit Moment at face AB = 0.287x1000= 287 kN-m Unit Moment at face AC = 0.287x1000= 287 kN-m Unit Moment at face BC = 0.1x1000= 100 kN-m Formula used to calculate Area of steel against corresponding moment: Mu= 0.87 x fy x As t x d (1 - 0.42 x Xu/d) (AS PER IS:456 (2000) ANNEX G , CLAUSE 38.1……… Mu = Moment fy = Characteristic strength of steel, here 415 As t = Area of steel d= Effective depth of pile cap Xu= Depth of neutral axis
  • 14. Area of steel required parallel to AB = 1991 mm2 Area of steel required parallel to AC = 1991 mm2 Area of steel required parallel to BC = 693 mm2 We should provide 12 mm rod of 113 mm2 Spacing through AB = (113 x 1000)/1991= 60 mm Spacing through AC = (113 x 1000)/1991= 60 mm Spacing through BC = (113 x 1000)/693= 160 mm OVERALL DEPTH OF THE PILE CAP =(500+(100+12+12+6)X2)= 760 mm
  • 15. Explanation of pile cap design with example:- EXAMPLE 2 :- Diameter of pile : 300 mm Spacing between the piles : 3xd= 3x400 mm [ As per IS 2911 = 1200 mm (Part 1/Sec 3) : 2010 Clause : 6.6.2.] No of piles under a pile cap: 4 Size of column : 400x400 mm Load transferred by column : 1600 kN Load on each pile : 1600/4= 400 kN The dimension of the pile cap, the distance between the connecting line of the piles and the face of critical zone of punching shear are given in the figure with details………..
  • 16. Details about the pile cap of this example……………..
  • 17. We have assume that the overall depth of pile cap is 600 mm…… …
  • 18. Unit Moment at face AB = 0.23x800= 184 kN-m Unit Moment at face BC = 0.23x800= 184 kN-m Unit Moment at face CD = 0.23x800= 184 kN-m Unit Moment at face DA = 0.23x800= 184 kN-m Formula used to calculate Area of steel against corresponding moment: Mu= 0.87 x fy x As t x d (1 - 0.42 x Xu/d) (AS PER IS:456 (2000) ANNEX G , CLAUSE 38.1………) Mu = Moment fy = Characteristic strength of steel, here 415 As t = Area of steel d= Effective depth of pile cap Xu= Depth of neutral axis
  • 19. Area of steel required parallel to AB = 1877 mm2 Area of steel required parallel to BC = 1877 mm2 Area of steel required parallel to CD = 1877mm2 Area of steel required parallel to DA= 1877mm2 We should provide 12 mm rod of 113 mm2 Spacing through AB = (113 x 1000)/1877= 60 mm Spacing through BC = (113 x 1000)/1877= 60 mm Spacing through CD = (113 x 1000)/1877= 160 mm Spacing through DA = (113 x 1000)/1877= 160 mm EFFECTIVE DEPTH OF THE PILE CAP =(600-(100+12+12+6)X2)= 340 mm
  • 20. Making of PILE CAP In practical field…………
  • 21. ACKNOWLEDGEMENT: â–  Our project is successful due to the effort of those people who have given their valuable time and advice. We sincerely appreciate the inspiration, support and guidance of all those people . We, the student of "NARULA INSTITUTE OF TECHNOLOGY" are extremely thankful to our teachers for giving us the opportunity to do this project on the topic of ”Design of Pile Cap”. At this juncture we feel deeply honour in expressing our sincere thanks to Dr.Chandrasekhar Sen Majumdar, Prof. Abhipriya Halder, Prof.Priyabrata Guha sir for making the resources available at right time and providing valuable insights leading to the successful completion of our project.
  • 22. CONCLUSION A pile cap is a thick concrete mat that rests on concrete or timber piles that have been driven into soft or unstable ground to provide a suitable stable foundation. It usually forms part of the foundation of a building, typically a multi-story building, structure or support base for heavy equipment. The cast concrete pile cap distributes the load of the building into the piles. A similar structure to a pile cap is a "raft", which is a concrete foundation floor resting directly onto soft soil which may be liable to subsidence.
  • 23. SPECIAL THANKS to PROF. ABHIPRIYAHALDER We are very thankful that we have a teacher cum leader like you. Your inspiration really motivate us to do this project on such a topic which play a valuable role in civil engineering. Without your inspiration it is impossible to complete this project. Thanks a lot sir……….for your support and inspiration………………