PRODUCTION
SCHEDULING
Unit-4
Overview
OUTPUT PLAN
LOADING
SEQUENCING
SCHEDULING
EXPEDITING
SCHEDULING
• Scheduling is the last of the planning functions.
• It determines when an operation is to be performed, or when
work is to be completed; the difference lies in the detail of the
scheduling procedure.
• In a centralized control situation - where all process planning,
loading, and scheduling for the plant are done in a central
office- the details of the schedule may specify the starting and
finishing time for an operation.
• On the other hand, the central schedule may simply give a
completion time for the work in a given department.
LOADING
• Once the route has been established, the work required can
be loaded against the selected machine or workstation.
• The total time required to perform the operation is computed
by multiplying the unit operation times given on the standard
process sheet by the number of parts to be processed.
• This total time is then added to the work already planned for
the workstation.
• This is the function of loading, and it results in a tabulated list
or chart showing the planned utilization of the machines or
workstations in the plant
LOADING AND SCHEDULING
PRODUCTION CONTROL
MASTER SCHEDULING
SCHEDULING -BENEFITS
• Inventory reduction,
• Process change-over reduction
• leveling
• Reduced scheduling effort
• Increased production efficiency
• Labor load leveling
• Accurate delivery date quotes
• Real time information
GANTT CHART
•A Gantt chart is a type of bar chart, developed by Henry Gantt,
that illustrates a project schedule.
• Gantt charts illustrate the start
and finish dates of the terminal elements and summary elements
of a project. Terminal elements and summary elements comprise
the work breakdown structure of the project.
•Some Gantt charts also show the dependency (i.e., precedence network)
relationships between activities.
Production Control
• Perpetual loading
– Tabulation of the time necessary to finish unfulfilled orders and
determine how long it will take to finish this work.
Perpetual loading
LINE OF BALANCE
• Find a feasible defined replacement for all undefined
(‘ANY’) ergonomic constraints on workstations, i.e. one
compatible with the ergonomic constraints and
precedence constraints defined on operations, as well as
zoning constraints and possible drifting operations
• Solve the within-workstation scheduling problem on all
workstations, for all products being assembled on the line
• Assign the operations to workstations to achieve the best
average balance, while keeping the peak times at a
manageable level.
Linear Scheduling Method
• Linear Scheduling Method (LSM) is a graphical scheduling method
focusing on continuous resource utilization in repetitive activities. It is
believed that it originally adopted the idea of Line-Of-Balance method.
• The main advantages of LSM over Critical Path Method (CPM) is its
underlying idea of keeping resources continuously at work. In other
words, it schedules activities in such a way that:
1. resource utilization is maximized;
2. interruption in on-going process is minimized, including hiring-and-
firing; and
3. the effect of the learning curve phenomenon is minimized
BATCH PRODUCTION SCHEDULING
• Batch production scheduling is the practice of planning and
scheduling of batch manufacturing processes.
• Although, scheduling may apply to traditionally continuous
processes, such as refining, it is especially important for batch
processes such as those for pharmaceutical active ingredients,
biotechnology processes and many specialty chemical
processes.
• Batch production scheduling shares some concepts and
techniques with finite capacity scheduling which has been
applied to many manufacturing problems.
• The specific issues of scheduling batch manufacturing
processes have generated considerable industrial and
academic interest
MRP
KANBAN
DISPATCHING
• Authorizing the start of an operation on the shop
floor is the function of dispatching.
• This function may be centralized or decentralized.
• The departmental dispatcher would authorize the
start of each of the machine operations – the
dispatch actions are based on the foreman’s routing
and scheduling of the work through his department.
This is decentralized dispatching.
PROGRESS REPORTING AND EXPEDITING
• The manufacturing activity of a plant is said to be “in
control” when the actual performance is within the
objectives of the planned performance.
• When jobs are started and completed on schedule,
there should be very little, if any, concern about the
meeting of commitments.
• Optimum operation of the plant, however, is attained
only if the original plan has been carefully prepared
to utilize the manufacturing facilities fully and
effectively.
Mfg. lead time
Mfg. lead time

Weitere ähnliche Inhalte

Was ist angesagt?

Ppc unit-4-production scheduling
Ppc   unit-4-production schedulingPpc   unit-4-production scheduling
Ppc unit-4-production schedulingkarthi keyan
 
Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROL
Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROLUnit 4-IE6605 & PRODUCTION PLANNING AND CONTROL
Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROLMohanumar S
 
Ppc unit-2-work study
Ppc   unit-2-work studyPpc   unit-2-work study
Ppc unit-2-work studykarthi keyan
 
PRODUCTION PLANNING AND CONTROL-Unit 5
PRODUCTION PLANNING AND CONTROL-Unit 5PRODUCTION PLANNING AND CONTROL-Unit 5
PRODUCTION PLANNING AND CONTROL-Unit 5prakash0712
 
Production Planning and Process Planning
Production Planning and Process PlanningProduction Planning and Process Planning
Production Planning and Process PlanningPraveenManickam2
 
Inventory production and Recent trends in PPC
Inventory production and Recent trends in PPCInventory production and Recent trends in PPC
Inventory production and Recent trends in PPCPraveenManickam2
 
Unit 3-IE6605 & PRODUCTION PLANNING AND CONTROL
Unit 3-IE6605 & PRODUCTION PLANNING AND CONTROLUnit 3-IE6605 & PRODUCTION PLANNING AND CONTROL
Unit 3-IE6605 & PRODUCTION PLANNING AND CONTROLMohanumar S
 
Plant layout and its types
Plant layout and its typesPlant layout and its types
Plant layout and its typesKritika Garg
 

Was ist angesagt? (15)

Ppc unit-4-production scheduling
Ppc   unit-4-production schedulingPpc   unit-4-production scheduling
Ppc unit-4-production scheduling
 
Unit 1 PPC
Unit 1 PPCUnit 1 PPC
Unit 1 PPC
 
Unit 5
Unit 5Unit 5
Unit 5
 
Unit 1
Unit 1Unit 1
Unit 1
 
Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROL
Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROLUnit 4-IE6605 & PRODUCTION PLANNING AND CONTROL
Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROL
 
production scheduling
production schedulingproduction scheduling
production scheduling
 
Ppc unit-2-work study
Ppc   unit-2-work studyPpc   unit-2-work study
Ppc unit-2-work study
 
PRODUCTION PLANNING AND CONTROL-Unit 5
PRODUCTION PLANNING AND CONTROL-Unit 5PRODUCTION PLANNING AND CONTROL-Unit 5
PRODUCTION PLANNING AND CONTROL-Unit 5
 
Production Planning and Process Planning
Production Planning and Process PlanningProduction Planning and Process Planning
Production Planning and Process Planning
 
Unit 3
Unit 3Unit 3
Unit 3
 
Work Study
Work Study Work Study
Work Study
 
Inventory production and Recent trends in PPC
Inventory production and Recent trends in PPCInventory production and Recent trends in PPC
Inventory production and Recent trends in PPC
 
Unit 3-IE6605 & PRODUCTION PLANNING AND CONTROL
Unit 3-IE6605 & PRODUCTION PLANNING AND CONTROLUnit 3-IE6605 & PRODUCTION PLANNING AND CONTROL
Unit 3-IE6605 & PRODUCTION PLANNING AND CONTROL
 
Plant layout and its types
Plant layout and its typesPlant layout and its types
Plant layout and its types
 
Unit 2
Unit 2Unit 2
Unit 2
 

Ähnlich wie PRODUCTION PLANNING AND CONTROL-Unit 4

Ähnlich wie PRODUCTION PLANNING AND CONTROL-Unit 4 (20)

Unit 4 PPC
Unit 4 PPCUnit 4 PPC
Unit 4 PPC
 
Unit 4
Unit 4Unit 4
Unit 4
 
PRODUCTION PLANNING AND CONTROL
PRODUCTION PLANNING AND CONTROLPRODUCTION PLANNING AND CONTROL
PRODUCTION PLANNING AND CONTROL
 
unit 4.ppt
unit 4.pptunit 4.ppt
unit 4.ppt
 
UNIT 4 - PRODUCTION SCHEDULING
UNIT 4 - PRODUCTION SCHEDULINGUNIT 4 - PRODUCTION SCHEDULING
UNIT 4 - PRODUCTION SCHEDULING
 
Production planning and control
Production planning and controlProduction planning and control
Production planning and control
 
scheduling in operations Management PPT O and M
scheduling in operations Management PPT O and Mscheduling in operations Management PPT O and M
scheduling in operations Management PPT O and M
 
Operation scheduling
Operation schedulingOperation scheduling
Operation scheduling
 
Scheduling Topic of Production and Operations
Scheduling Topic of Production and OperationsScheduling Topic of Production and Operations
Scheduling Topic of Production and Operations
 
Presentation on scheduling
Presentation on schedulingPresentation on scheduling
Presentation on scheduling
 
Unit 7 production scheduling
Unit 7 production scheduling Unit 7 production scheduling
Unit 7 production scheduling
 
Operations Scheduling
Operations SchedulingOperations Scheduling
Operations Scheduling
 
Scheduling and sequencing
Scheduling and sequencingScheduling and sequencing
Scheduling and sequencing
 
MIn-218_chap 1.pptx
MIn-218_chap 1.pptxMIn-218_chap 1.pptx
MIn-218_chap 1.pptx
 
Production management
Production managementProduction management
Production management
 
Scheduling
SchedulingScheduling
Scheduling
 
Unit 3 Manufacturing system design
Unit   3 Manufacturing system designUnit   3 Manufacturing system design
Unit 3 Manufacturing system design
 
MMS PRESENTAION.pptx
MMS PRESENTAION.pptxMMS PRESENTAION.pptx
MMS PRESENTAION.pptx
 
PRODUCTION AND OPERATIONS MANAGEMENT (304) SEM3 NOV2021.pdf
PRODUCTION AND OPERATIONS MANAGEMENT (304) SEM3 NOV2021.pdfPRODUCTION AND OPERATIONS MANAGEMENT (304) SEM3 NOV2021.pdf
PRODUCTION AND OPERATIONS MANAGEMENT (304) SEM3 NOV2021.pdf
 
Operations management
Operations managementOperations management
Operations management
 

Mehr von prakash0712

UNIT-1-Steam Power Plant.pptx
UNIT-1-Steam Power Plant.pptxUNIT-1-Steam Power Plant.pptx
UNIT-1-Steam Power Plant.pptxprakash0712
 
Unit-V-Power Plant Economics and Environment.pptx
Unit-V-Power Plant Economics and Environment.pptxUnit-V-Power Plant Economics and Environment.pptx
Unit-V-Power Plant Economics and Environment.pptxprakash0712
 
Unit-IV-Renewable Energy Sources.pptx
Unit-IV-Renewable Energy Sources.pptxUnit-IV-Renewable Energy Sources.pptx
Unit-IV-Renewable Energy Sources.pptxprakash0712
 
Unit-II-Diesel Gas turbine and Combined Cycle Power Plant.pptx
Unit-II-Diesel Gas turbine and Combined Cycle Power Plant.pptxUnit-II-Diesel Gas turbine and Combined Cycle Power Plant.pptx
Unit-II-Diesel Gas turbine and Combined Cycle Power Plant.pptxprakash0712
 
Unit-III-Nuclear Power Plants.pptx
Unit-III-Nuclear Power Plants.pptxUnit-III-Nuclear Power Plants.pptx
Unit-III-Nuclear Power Plants.pptxprakash0712
 
UNIT-IV-STEERING, BRAKES AND SUSPENSION SYSTEMS.pptx
UNIT-IV-STEERING, BRAKES AND SUSPENSION SYSTEMS.pptxUNIT-IV-STEERING, BRAKES AND SUSPENSION SYSTEMS.pptx
UNIT-IV-STEERING, BRAKES AND SUSPENSION SYSTEMS.pptxprakash0712
 
UNIT-II-ENGINE AUXILIARY SYSTEMS.pptx
UNIT-II-ENGINE AUXILIARY SYSTEMS.pptxUNIT-II-ENGINE AUXILIARY SYSTEMS.pptx
UNIT-II-ENGINE AUXILIARY SYSTEMS.pptxprakash0712
 
UNIT-V-ELECTRIC AND HYBRID VEHICLES.pptx
UNIT-V-ELECTRIC AND HYBRID VEHICLES.pptxUNIT-V-ELECTRIC AND HYBRID VEHICLES.pptx
UNIT-V-ELECTRIC AND HYBRID VEHICLES.pptxprakash0712
 
UNIT-1-VEHICLE STRUCTURE AND ENGINES.ppt
UNIT-1-VEHICLE STRUCTURE AND ENGINES.pptUNIT-1-VEHICLE STRUCTURE AND ENGINES.ppt
UNIT-1-VEHICLE STRUCTURE AND ENGINES.pptprakash0712
 
UNIT-III-TRANSMISSION SYSTEMS.pptx
UNIT-III-TRANSMISSION SYSTEMS.pptxUNIT-III-TRANSMISSION SYSTEMS.pptx
UNIT-III-TRANSMISSION SYSTEMS.pptxprakash0712
 
PRODUCTION PLANNING AND CONTROL-Unit 1
PRODUCTION PLANNING AND CONTROL-Unit 1PRODUCTION PLANNING AND CONTROL-Unit 1
PRODUCTION PLANNING AND CONTROL-Unit 1prakash0712
 
PRODUCTION PLANNING AND CONTROL-Unit 2
PRODUCTION PLANNING AND CONTROL-Unit 2PRODUCTION PLANNING AND CONTROL-Unit 2
PRODUCTION PLANNING AND CONTROL-Unit 2prakash0712
 
ENGINEERING THERMODYNAMICS-Unit 2
ENGINEERING THERMODYNAMICS-Unit 2ENGINEERING THERMODYNAMICS-Unit 2
ENGINEERING THERMODYNAMICS-Unit 2prakash0712
 
ENGINEERING THERMODYNAMICS- unit 2
ENGINEERING THERMODYNAMICS- unit 2ENGINEERING THERMODYNAMICS- unit 2
ENGINEERING THERMODYNAMICS- unit 2prakash0712
 
ENGINEERING THERMODYNAMICS- unit-3
ENGINEERING THERMODYNAMICS- unit-3ENGINEERING THERMODYNAMICS- unit-3
ENGINEERING THERMODYNAMICS- unit-3prakash0712
 

Mehr von prakash0712 (20)

UNIT-1-Steam Power Plant.pptx
UNIT-1-Steam Power Plant.pptxUNIT-1-Steam Power Plant.pptx
UNIT-1-Steam Power Plant.pptx
 
Unit-V-Power Plant Economics and Environment.pptx
Unit-V-Power Plant Economics and Environment.pptxUnit-V-Power Plant Economics and Environment.pptx
Unit-V-Power Plant Economics and Environment.pptx
 
Unit-IV-Renewable Energy Sources.pptx
Unit-IV-Renewable Energy Sources.pptxUnit-IV-Renewable Energy Sources.pptx
Unit-IV-Renewable Energy Sources.pptx
 
Unit-II-Diesel Gas turbine and Combined Cycle Power Plant.pptx
Unit-II-Diesel Gas turbine and Combined Cycle Power Plant.pptxUnit-II-Diesel Gas turbine and Combined Cycle Power Plant.pptx
Unit-II-Diesel Gas turbine and Combined Cycle Power Plant.pptx
 
Unit-III-Nuclear Power Plants.pptx
Unit-III-Nuclear Power Plants.pptxUnit-III-Nuclear Power Plants.pptx
Unit-III-Nuclear Power Plants.pptx
 
UNIT-IV-STEERING, BRAKES AND SUSPENSION SYSTEMS.pptx
UNIT-IV-STEERING, BRAKES AND SUSPENSION SYSTEMS.pptxUNIT-IV-STEERING, BRAKES AND SUSPENSION SYSTEMS.pptx
UNIT-IV-STEERING, BRAKES AND SUSPENSION SYSTEMS.pptx
 
UNIT-II-ENGINE AUXILIARY SYSTEMS.pptx
UNIT-II-ENGINE AUXILIARY SYSTEMS.pptxUNIT-II-ENGINE AUXILIARY SYSTEMS.pptx
UNIT-II-ENGINE AUXILIARY SYSTEMS.pptx
 
UNIT-V-ELECTRIC AND HYBRID VEHICLES.pptx
UNIT-V-ELECTRIC AND HYBRID VEHICLES.pptxUNIT-V-ELECTRIC AND HYBRID VEHICLES.pptx
UNIT-V-ELECTRIC AND HYBRID VEHICLES.pptx
 
UNIT-1-VEHICLE STRUCTURE AND ENGINES.ppt
UNIT-1-VEHICLE STRUCTURE AND ENGINES.pptUNIT-1-VEHICLE STRUCTURE AND ENGINES.ppt
UNIT-1-VEHICLE STRUCTURE AND ENGINES.ppt
 
UNIT-III-TRANSMISSION SYSTEMS.pptx
UNIT-III-TRANSMISSION SYSTEMS.pptxUNIT-III-TRANSMISSION SYSTEMS.pptx
UNIT-III-TRANSMISSION SYSTEMS.pptx
 
AICE-Unit 3
AICE-Unit   3AICE-Unit   3
AICE-Unit 3
 
AICE-Unit 2
AICE-Unit   2AICE-Unit   2
AICE-Unit 2
 
AICE-Unit 5
AICE-Unit   5AICE-Unit   5
AICE-Unit 5
 
AICE-Unit 4
AICE-Unit   4AICE-Unit   4
AICE-Unit 4
 
AICE-Unit 1
AICE-Unit   1AICE-Unit   1
AICE-Unit 1
 
PRODUCTION PLANNING AND CONTROL-Unit 1
PRODUCTION PLANNING AND CONTROL-Unit 1PRODUCTION PLANNING AND CONTROL-Unit 1
PRODUCTION PLANNING AND CONTROL-Unit 1
 
PRODUCTION PLANNING AND CONTROL-Unit 2
PRODUCTION PLANNING AND CONTROL-Unit 2PRODUCTION PLANNING AND CONTROL-Unit 2
PRODUCTION PLANNING AND CONTROL-Unit 2
 
ENGINEERING THERMODYNAMICS-Unit 2
ENGINEERING THERMODYNAMICS-Unit 2ENGINEERING THERMODYNAMICS-Unit 2
ENGINEERING THERMODYNAMICS-Unit 2
 
ENGINEERING THERMODYNAMICS- unit 2
ENGINEERING THERMODYNAMICS- unit 2ENGINEERING THERMODYNAMICS- unit 2
ENGINEERING THERMODYNAMICS- unit 2
 
ENGINEERING THERMODYNAMICS- unit-3
ENGINEERING THERMODYNAMICS- unit-3ENGINEERING THERMODYNAMICS- unit-3
ENGINEERING THERMODYNAMICS- unit-3
 

Kürzlich hochgeladen

Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdfSuman Jyoti
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...tanu pandey
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 

Kürzlich hochgeladen (20)

(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 

PRODUCTION PLANNING AND CONTROL-Unit 4

  • 3. SCHEDULING • Scheduling is the last of the planning functions. • It determines when an operation is to be performed, or when work is to be completed; the difference lies in the detail of the scheduling procedure. • In a centralized control situation - where all process planning, loading, and scheduling for the plant are done in a central office- the details of the schedule may specify the starting and finishing time for an operation. • On the other hand, the central schedule may simply give a completion time for the work in a given department.
  • 4. LOADING • Once the route has been established, the work required can be loaded against the selected machine or workstation. • The total time required to perform the operation is computed by multiplying the unit operation times given on the standard process sheet by the number of parts to be processed. • This total time is then added to the work already planned for the workstation. • This is the function of loading, and it results in a tabulated list or chart showing the planned utilization of the machines or workstations in the plant
  • 8. SCHEDULING -BENEFITS • Inventory reduction, • Process change-over reduction • leveling • Reduced scheduling effort • Increased production efficiency • Labor load leveling • Accurate delivery date quotes • Real time information
  • 9. GANTT CHART •A Gantt chart is a type of bar chart, developed by Henry Gantt, that illustrates a project schedule. • Gantt charts illustrate the start and finish dates of the terminal elements and summary elements of a project. Terminal elements and summary elements comprise the work breakdown structure of the project. •Some Gantt charts also show the dependency (i.e., precedence network) relationships between activities.
  • 10. Production Control • Perpetual loading – Tabulation of the time necessary to finish unfulfilled orders and determine how long it will take to finish this work. Perpetual loading
  • 11. LINE OF BALANCE • Find a feasible defined replacement for all undefined (‘ANY’) ergonomic constraints on workstations, i.e. one compatible with the ergonomic constraints and precedence constraints defined on operations, as well as zoning constraints and possible drifting operations • Solve the within-workstation scheduling problem on all workstations, for all products being assembled on the line • Assign the operations to workstations to achieve the best average balance, while keeping the peak times at a manageable level.
  • 12. Linear Scheduling Method • Linear Scheduling Method (LSM) is a graphical scheduling method focusing on continuous resource utilization in repetitive activities. It is believed that it originally adopted the idea of Line-Of-Balance method. • The main advantages of LSM over Critical Path Method (CPM) is its underlying idea of keeping resources continuously at work. In other words, it schedules activities in such a way that: 1. resource utilization is maximized; 2. interruption in on-going process is minimized, including hiring-and- firing; and 3. the effect of the learning curve phenomenon is minimized
  • 13. BATCH PRODUCTION SCHEDULING • Batch production scheduling is the practice of planning and scheduling of batch manufacturing processes. • Although, scheduling may apply to traditionally continuous processes, such as refining, it is especially important for batch processes such as those for pharmaceutical active ingredients, biotechnology processes and many specialty chemical processes. • Batch production scheduling shares some concepts and techniques with finite capacity scheduling which has been applied to many manufacturing problems. • The specific issues of scheduling batch manufacturing processes have generated considerable industrial and academic interest
  • 14. MRP
  • 16. DISPATCHING • Authorizing the start of an operation on the shop floor is the function of dispatching. • This function may be centralized or decentralized. • The departmental dispatcher would authorize the start of each of the machine operations – the dispatch actions are based on the foreman’s routing and scheduling of the work through his department. This is decentralized dispatching.
  • 17. PROGRESS REPORTING AND EXPEDITING • The manufacturing activity of a plant is said to be “in control” when the actual performance is within the objectives of the planned performance. • When jobs are started and completed on schedule, there should be very little, if any, concern about the meeting of commitments. • Optimum operation of the plant, however, is attained only if the original plan has been carefully prepared to utilize the manufacturing facilities fully and effectively.