SlideShare ist ein Scribd-Unternehmen logo
1 von 46
Downloaden Sie, um offline zu lesen
(RISK‐2196) Removing the Early‐Dates Bias 
in CPM Risk Analysis
Gui Ponce de Leon, PhD, PE, PMP
Vivek Puri, PhD, PMP
PLEASE USE MICROPHONE FOR ALL
QUESTIONS AND COMMENTS!
2
BIO of Dr. Gui Ponce de Leon
3
• Professional experience includes executive and senior roles 
as program manager, project manager, project controls 
engineer, planner/scheduler, and forensic scheduler
• A project management inventor, who holds 4 US patents on 
his groundbreaking graphical path method aka GPM
• Awarded in 1972 the first PhD from the construction 
management program at the University of Michigan
• In 1969, with Prof. Tom Schriber as co‐author, presented 
Determination of Criticality Indices in the PERT Problem at 
the Third Conference on the Application of Simulation
Founder/CEO of PMA Consultants, LLC,
a pure project management firm with a
45-year track record
BIO of Dr. Vivek Puri
• Experience in construction management research, 
simulation and risk management, and construction planning 
and execution
• PhD in Civil Engineering (2012) from Purdue University and 
M. Tech in Construction Technology and Management (2005) 
from Indian Institute of Technology Madras, India
• PhD thesis focused on combined continuous and discrete 
event simulation of project operations and its use in project 
planning
4
Senior Associate/Lead Developer
PMA Consultants, LLC
AGENDA
• Introduction
– Conventional Scheduling
– Scheduling Under Uncertainty
– Float Use Impact on Project Completion
• Graphical Path Method
• Case Study
• Bounding Completion Risk Envelope
• Safe float 
• Conclusions
5
INTRODUCTION
6
Conventional Scheduling
• In critical path method (CPM) scheduling, activity durations 
are assumed to be known with certainty
– Single‐point duration estimates
– Schedule uncertainty is dealt with through contingency, e.g., 
AACE RP 70, Principles of Schedule Contingency Management
• CPM algorithms functionality
– Using a forward pass, activities are scheduled to start on the 
earliest possible dates largely based on network logic
– Using a backward pass, late dates and total floats are 
determined by fixing the project completion date
• CPM is not used where activity durations are uncertain
7
Before CPM, Activities Had One Start Date
8
With CPM, Activities Have Early & Late Dates
9
CPM Early & Late Bounding Distribution Curves
0
200,000
400,000
600,000
800,000
1,000,000
1,200,000
1,400,000
1,600,000
9/14/2011 11/3/2011 12/23/2011 2/11/2012 4/1/2012 5/21/2012 7/10/2012 8/29/2012 10/18/2012
Early Cumulative Cost
Late Cumulative Cost
10
Scheduling Under Uncertainty
• Common sources of uncertainty
– Production rates, weather, estimating tolerance
– Internal and external risks impacting durations
• PERT introduced in 1957 for estimation of uncertainty
– Activities have three‐point duration estimates
– Duration variability follows Beta‐PERT distribution 
– Using a forward pass much as CPM does, PERT calculates the 
PERT project duration mean and variance
– Appealing to the central limit theorem, project duration is 
assumed to follow a normal distribution
11
The PERT Merge Bias
• The PERT solution is essentially a longest path algorithm that 
uses activity mean durations (as approximated by PERT) 
rather than single‐point durations as CPM does
• The PERT approach introduces a merge bias
– By calculating mean start dates based on the maximum of 
the merging paths’ mean durations, PERT underestimates 
mean start dates as the mean of the longest path is greater 
than or equal to the maximum of the merging paths’ mean 
durations
12
Schedule Simulation or Schedule Risk Analysis
• Van Slyke (1963) introduced a Monte Carlo simulation 
approach to correct for the underestimation from merge 
bias inherent in the PERT expected completion date
• Schedule simulation overcomes PERT limitations
– Uses any distribution to model activity duration uncertainty
– Rather than using mean durations to develop one early‐
schedule occurrence of the project schedule, simulation uses 
sampled activity durations to develop multiple early‐
schedule occurrences of the project schedule
– Each early‐schedule occurrence is based on the sampled 
longest path thereby removing the PERT merge bias 
– Models risks & correlations
13
Early‐Dates Bias in CPM Schedule Risk Analysis
• By scheduling activities on early starts in every iteration, 
CPM risk analysis does not account for the impact of delayed 
or late starts (impact of float use) on project completion:
– The early‐dates limitation is a deviation from the actual 
system modeled; on actual projects, activities off the critical 
are often floated and start later, making use of total float
• By not modeling floating risk in any iteration, CPM risk 
analysis merely develops the early completion risk function 
because decisions to use float have a likelihood of causing 
critical path delay and affect the project completion date
14
Project Completion Distribution Curve
0 %
10 %
20 %
30 %
40 %
50 %
60 %
70 %
80 %
90 %
100 %
8/26/2012 9/2/2012 9/9/2012 9/16/2012 9/23/2012 9/30/2012 10/7/2012 10/14/2012 10/21/2012
Iterations
Date
15
Float Use Impact on Project Completion
• On actual projects, it is common practice to delay non‐
critical work by using available total float
– Level resources
– Pace progress
– Other strategic reasons
• Where activities have uncertain durations, floating activities 
in a simulation itera on─even within available float─alters
the merge risk, which in turn risks a delay in completion
– High‐total‐float paths do not affect early‐dates merge bias
– When a high‐total‐float activity is floated by a sufficient 
amount of available float, the delay in start puts the activity 
closer to the merge event, and coupled with duration 
uncertainty has a likelihood of impacting completion
16
GRAPHICAL PATH METHOD 
17
Graphical Path Method (GPM)
• Planning/scheduling method that allows planners to place 
activities on GPM planned dates between early and late 
dates while retaining the algorithmic early and late dates
• GPM planned dates generate drift
– Drift is unique to GPM as drift in CPM is always zero
• GPM planned dates also generate float
– Float as a subdivision of total float is unique to GPM, as float 
in CPM is always equal to total float
18
Graphical Path Method
• In GPM, regardless of planned start date established for an 
activity, drift + float always equals total float
– In GPM, planned dates generate drift without suppressing 
total float thereby preserving total float continuity
• In CPM, date constraints that override logic do not generate 
drift, suppress total float, and cause total float discontinuity  
19
Graphical Path Method (cont’d)
• Planned dates obviate the need for SNE date constraints, 
which makes GPM invaluable for assessing schedule risk as 
date constraints can adversely impact simulation results
• AACEI Recommended Practice No. 57R‐09 recommends:
– The schedule should not rely on constraints to force activities 
to start or finish by certain dates
– It should use logic for this purpose and not artificially reduce 
or restrict total float
20
Core Tenets of GPM‐Based Schedule Simulation
• Tenet #1─Each itera on begins with the base‐case scenario 
and unfolds activity by activity according to network logic, as 
a simulated update of the base‐case scenario
– Each iteration is a simulated progression of time rather than 
a batch replacement of activity duration 
• Tenet #2─In each itera on, ac vi es may be scheduled on 
GPM planned dates, either because
– GPM planned dates are present in the base case, or
– Positive‐float activities, through sampling, are allowed to 
float by using a portion or all of then‐available float 
• Tenet #3─In each itera on, the longest path has the least 
total float; late finish date of the last activity on the longest 
path equals its early finish date or the project finish date
21
CASE STUDY
22
Case Study
• Design‐build contract to rebuild food processing facility
• Project Completion
– Required by 10/06/2012
– Early planned completion by 08/26/2012
– Total Duration: 328 calendar days
– Early completion total float: 41 days (12.5%)
• Modeled and simulated using NetPoint®/NetRisk™
• For simplicity, 
– 3‐point duration estimates follow triangular distribution
– All uncertainty in duration ranges, no other risks
23
Project Schedule─Base‐Case Scenario
24
Early‐Schedule Scenario–Completion Distribution
25
Early‐Schedule Scenario–Criticality Indices 
26
Criticality
threshold = .250 x 98%
= .245
BOUNDING COMPLETION RISK ENVELOPE
27
Float Use by Modeling Floating and Pacing
• Floating
– Delayed start of activity to consume available float
– Independent of actual progress
– Random decision
• Pacing
– Delayed start of activity to consume available float
– Delay in another path increases available float
– Decision based on threshold of current float to 
deterministic float
28
Optimism Bias in CPM‐Based Simulation
• CPM‐based simulation is unable to model floating/pacing 
– Activities are scheduled on early dates in each iteration
– Impact of delayed start of any activity not considered
– No decision‐based rules to model floating/pacing
• CPM‐based simulation yields an optimistic completion 
distribution because it is predicated on the early‐schedule 
– For instance, a P80 date without considering floating may be 
the P60 date under a postulated floating scenario
29
Modeling Bounding Completion Risk Envelope
• CPM‐based simulation provides the envelope upper bound
– Activities always scheduled to start on early dates
– The upper bound is the early‐schedule completion risk curve
• Although the maximum delay in project completion due to 
floating is theoretically unbounded, an envelope lower 
bound can be determined by assuming floating is limited by 
then‐available float
– Modeled by floating activities off the critical path with 100% 
probability and using 100% of then‐available float (meaning, 
float available at that point in an iteration)
– Represents the late completion risk curve (different than 
starting activities on late dates)
30
Bounding Completion Risk Envelope
CPM Base/All Early Scenario
Selective Floating Scenario
Selective Floating & Pacing Scenario
All Late/100% Floating Scenario
31
SAFE FLOAT
32
Safe Float
• Safe float: within modeled uncertainty, extent an activity 
may be delayed from its base‐case early start date without 
delaying the targeted (P value) project completion date
• Activity Elec Equipment Installation (early‐dates simulation)
– Stochastic earliest Start: 05/10/2012
– Stochastic latest Start: 07/15/2012
33
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0
20
40
60
80
100
120
5/10/2012 5/17/2012 5/24/2012 5/31/2012 6/7/2012 6/14/2012 6/21/2012 6/28/2012 7/5/2012 7/12/2012
Cumulative Probability
Iterations
Start Date
Num. of Iterations
Cumulative Probability
0.00%
1.00%
2.00%
3.00%
4.00%
5.00%
0.00%
0.50%
1.00%
1.50%
2.00%
2.50%
3.00%
3.50%
6/20/2012
6/21/2012
6/22/2012
6/23/2012
6/24/2012
6/25/2012
6/26/2012
6/27/2012
6/28/2012
6/29/2012
6/30/2012
7/1/2012
7/2/2012
7/3/2012
7/4/2012
7/5/2012
7/6/2012
7/7/2012
7/8/2012
7/9/2012
7/10/2012
7/11/2012
7/12/2012
7/13/2012
7/14/2012
7/15/2012
Cumulative Probability for Delay
Probability
Start Date for Electrical Equipment Installation
No Delay
Delay
Cumulative Percent
Safe‐Float Use–Stochastic Approach
34
Each iteration is analyzed to determine where both the
activity is critical and the schedule completion date
extends beyond the targeted (P80) completion date
Latest start date where activity is on
the longest path and completion does
not extend beyond 10/01/2012, so
safe float = 06/26 – 05/19 = 38 days
Safe‐Float Use–Analyzing Results
• 3000 iterations
• Targeted (P80 date) project completion by 10/01/2012
– Latest start without delay 06/26/2012
– 98 days to targeted project completion
• Remaining path length > 98 days
– Assuming the path to be always driving
– Probability ≤ 0.012, practically insignificant
• Safe float = safe float start date ‐ base‐case early start date
35
Unsafe‐Float Activities: No Safe Float Start Dates
36
Categorizing Activities Using Safe Float Range
• Unsafe‐float activities: under high duration variability, there 
may be two types of activities without safe float whatsoever
– Type 1: no possible start date later than the stochastic 
optimistic early start without delaying targeted completion 
– Type 2: no possible start date later than the base‐case early 
start date without delaying targeted (P value)completion 
• Low safe‐float activities: have safe float below a threshold, 
for example, safe float < 20 days
• Mid safe‐float activities: Have safe float above a threshold, 
for example safe float ≥ 20 days 
• High safe‐float activities: have unbounded safe float within 
modeled uncertainty
37
Type 2 Unsafe‐Float Activities
38
Low Safe‐Float Activities
39
Mid Safe‐Float Activities  
40
High Safe‐Float Activities
41
Safe‐Float Values (Low & Mid)
Activity Description Criticality
Base‐Case 
Start Date
Safe‐Float 
Start Date
Total 
Float
Safe‐
float
Elec Equipment Fab/Delivery 0.249 2/14/2012 2/16/2012 56 2
Steel, Joists, Decking 0.537 2/20/2012 3/9/2012 36 18
SOG, Pour & Seal Decks 0.537 3/19/2012 4/7/2012 36 19
Power/Lighting/Low Voltage 0.441 4/23/2012 5/14/2012 36 21
Piping/HVAC/FS Rough‐In 0.131 4/23/2012 5/16/2012 43 23
MEP Process Equip 0.768 7/2/2012 7/27/2012 36 25
Install/Connect Process Equipment 1.000 7/16/2012 8/13/2012 36 28
Elec Equipment Installation 0.249 5/19/2012 6/26/2012 56 38
42
Safe‐float & Criticality Overlay
43
CONCLUSIONS
44
Conclusions
1. While correcting for the PERT merge bias, CPM risk analysis 
determines only the early‐schedule completion risk curve
2. When merge bias from randomly selected delayed starts is 
considered, multiple completion risk curves are revealed
3. The 100%‐float‐use scenario yields the stochastic 
equivalent of the late schedule impact on completion risk
4. With GPM, risk analysis catches up with the notion of 
bounding early/late distributions; targeted completion 
dates have a reliable P value that considers floating risk
5. A method is introduced to determine safe float, regardless 
of scenario, without impacting target completion (P date)
6. The method allows determination of unsafe‐float activities
7. Activities are categorized as low and mid safe float based 
on selected safe‐float thresholds and high safe float where 
safe float is unbounded by modeled uncertainty
45
QUESTIONS/COMMENTS?
(PLEASE USE MICROPHONE)
46

Weitere ähnliche Inhalte

Ähnlich wie Risk 2196 Removing the Early-Dates Bias in CPM Risk Analysis

B tech mechanical engineering syllabus - MITAOE
B tech mechanical engineering syllabus - MITAOEB tech mechanical engineering syllabus - MITAOE
B tech mechanical engineering syllabus - MITAOEMITAcademy1
 
6th Modular & Precast Construction_pro
6th  Modular & Precast Construction_pro6th  Modular & Precast Construction_pro
6th Modular & Precast Construction_proGeri Purisima
 
Declarations of Software Engineering Project Managers Managing Remotely: Prov...
Declarations of Software Engineering Project Managers Managing Remotely: Prov...Declarations of Software Engineering Project Managers Managing Remotely: Prov...
Declarations of Software Engineering Project Managers Managing Remotely: Prov...Dr. Mustafa Değerli
 
Teaching Learning Process.pptx
Teaching Learning Process.pptxTeaching Learning Process.pptx
Teaching Learning Process.pptxETC2019ABIT
 
It project risk management
It project risk managementIt project risk management
It project risk managementssuserab06ad1
 
01 02&03 introduction to pmp-mao
01 02&03 introduction to pmp-mao01 02&03 introduction to pmp-mao
01 02&03 introduction to pmp-maomao-osman73
 
Overview of Project Management: NIMechE NSF Presentation
Overview of Project Management: NIMechE NSF PresentationOverview of Project Management: NIMechE NSF Presentation
Overview of Project Management: NIMechE NSF PresentationJonahIbiamagabara
 
Chemical engineering syllabus - mitaoe
Chemical engineering syllabus - mitaoeChemical engineering syllabus - mitaoe
Chemical engineering syllabus - mitaoeMITAcademy1
 
Lecture 1
Lecture 1Lecture 1
Lecture 19anm12
 
Building Information Modelling at GCU, Development of a BIM Centre of Expertise
Building Information Modelling at GCU, Development of a BIM Centre of ExpertiseBuilding Information Modelling at GCU, Development of a BIM Centre of Expertise
Building Information Modelling at GCU, Development of a BIM Centre of ExpertiseRuggero Lancia
 
Project management using Primavera 6.x by Karim Ragab
Project management using Primavera 6.x by Karim RagabProject management using Primavera 6.x by Karim Ragab
Project management using Primavera 6.x by Karim RagabKarim Ragab
 
2016 Design Innovation Project
2016 Design Innovation Project2016 Design Innovation Project
2016 Design Innovation Projecterikbohemia
 
Project Management Workshop
Project Management WorkshopProject Management Workshop
Project Management WorkshopO' Neil Lim
 
Project Management - 2015-06-12
Project Management - 2015-06-12Project Management - 2015-06-12
Project Management - 2015-06-12Yves Francis
 

Ähnlich wie Risk 2196 Removing the Early-Dates Bias in CPM Risk Analysis (20)

Mega Project Support
Mega Project SupportMega Project Support
Mega Project Support
 
Mega Project Support
Mega Project SupportMega Project Support
Mega Project Support
 
project dev't cycle
project dev't cycleproject dev't cycle
project dev't cycle
 
B tech mechanical engineering syllabus - MITAOE
B tech mechanical engineering syllabus - MITAOEB tech mechanical engineering syllabus - MITAOE
B tech mechanical engineering syllabus - MITAOE
 
6th Modular & Precast Construction_pro
6th  Modular & Precast Construction_pro6th  Modular & Precast Construction_pro
6th Modular & Precast Construction_pro
 
Declarations of Software Engineering Project Managers Managing Remotely: Prov...
Declarations of Software Engineering Project Managers Managing Remotely: Prov...Declarations of Software Engineering Project Managers Managing Remotely: Prov...
Declarations of Software Engineering Project Managers Managing Remotely: Prov...
 
Teaching Learning Process.pptx
Teaching Learning Process.pptxTeaching Learning Process.pptx
Teaching Learning Process.pptx
 
It project risk management
It project risk managementIt project risk management
It project risk management
 
01 02&03 introduction to pmp-mao
01 02&03 introduction to pmp-mao01 02&03 introduction to pmp-mao
01 02&03 introduction to pmp-mao
 
2.4 id model
2.4 id model2.4 id model
2.4 id model
 
Overview of Project Management: NIMechE NSF Presentation
Overview of Project Management: NIMechE NSF PresentationOverview of Project Management: NIMechE NSF Presentation
Overview of Project Management: NIMechE NSF Presentation
 
Chemical engineering syllabus - mitaoe
Chemical engineering syllabus - mitaoeChemical engineering syllabus - mitaoe
Chemical engineering syllabus - mitaoe
 
Lecture 1
Lecture 1Lecture 1
Lecture 1
 
Project Management Methodologies
Project Management MethodologiesProject Management Methodologies
Project Management Methodologies
 
Building Information Modelling at GCU, Development of a BIM Centre of Expertise
Building Information Modelling at GCU, Development of a BIM Centre of ExpertiseBuilding Information Modelling at GCU, Development of a BIM Centre of Expertise
Building Information Modelling at GCU, Development of a BIM Centre of Expertise
 
Lunga CV 2016
Lunga CV 2016Lunga CV 2016
Lunga CV 2016
 
Project management using Primavera 6.x by Karim Ragab
Project management using Primavera 6.x by Karim RagabProject management using Primavera 6.x by Karim Ragab
Project management using Primavera 6.x by Karim Ragab
 
2016 Design Innovation Project
2016 Design Innovation Project2016 Design Innovation Project
2016 Design Innovation Project
 
Project Management Workshop
Project Management WorkshopProject Management Workshop
Project Management Workshop
 
Project Management - 2015-06-12
Project Management - 2015-06-12Project Management - 2015-06-12
Project Management - 2015-06-12
 

Mehr von PMA Consultants

Practical Application of Value Engineering in Capital Projects
Practical Application of Value Engineering in Capital ProjectsPractical Application of Value Engineering in Capital Projects
Practical Application of Value Engineering in Capital ProjectsPMA Consultants
 
Project Cost & Schedule Integration Lessons Learnt
Project Cost & Schedule Integration Lessons LearntProject Cost & Schedule Integration Lessons Learnt
Project Cost & Schedule Integration Lessons LearntPMA Consultants
 
PANDEMIC RESILIENTSCHOOLS
PANDEMIC RESILIENTSCHOOLSPANDEMIC RESILIENTSCHOOLS
PANDEMIC RESILIENTSCHOOLSPMA Consultants
 
BioPharma Projects: Essentials in Project Controls
BioPharma Projects: Essentials in Project ControlsBioPharma Projects: Essentials in Project Controls
BioPharma Projects: Essentials in Project ControlsPMA Consultants
 
How to Implement a Project Management Information System
How to Implement a Project Management Information SystemHow to Implement a Project Management Information System
How to Implement a Project Management Information SystemPMA Consultants
 
Top Five Metrics for Measuring Schedule Reliability
Top Five Metrics for Measuring Schedule ReliabilityTop Five Metrics for Measuring Schedule Reliability
Top Five Metrics for Measuring Schedule ReliabilityPMA Consultants
 
What are the disadvantages of Gantt charts?
What are the disadvantages of Gantt charts?What are the disadvantages of Gantt charts?
What are the disadvantages of Gantt charts?PMA Consultants
 
BIM and VDC for Megaproject Construction Projects
BIM and VDC for Megaproject Construction ProjectsBIM and VDC for Megaproject Construction Projects
BIM and VDC for Megaproject Construction ProjectsPMA Consultants
 
Setting up Filters & Layouts in P6
Setting up Filters & Layouts in P6Setting up Filters & Layouts in P6
Setting up Filters & Layouts in P6PMA Consultants
 
How to Choose a Project Delivery Method
How to Choose a Project Delivery MethodHow to Choose a Project Delivery Method
How to Choose a Project Delivery MethodPMA Consultants
 
Risk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacRisk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacPMA Consultants
 
Project Controls Processes
Project Controls ProcessesProject Controls Processes
Project Controls ProcessesPMA Consultants
 
Work Breakdown Structure Planning in NetPoint
Work Breakdown Structure Planning in NetPointWork Breakdown Structure Planning in NetPoint
Work Breakdown Structure Planning in NetPointPMA Consultants
 
How to Import/Export a Schedule between NetPoint and Microsft Excel
How to Import/Export a Schedule between NetPoint and Microsft ExcelHow to Import/Export a Schedule between NetPoint and Microsft Excel
How to Import/Export a Schedule between NetPoint and Microsft ExcelPMA Consultants
 
Smarter Planning with Microsoft Excel
Smarter Planning with Microsoft ExcelSmarter Planning with Microsoft Excel
Smarter Planning with Microsoft ExcelPMA Consultants
 
In Pursuit of Reliable Schedules
In Pursuit of Reliable SchedulesIn Pursuit of Reliable Schedules
In Pursuit of Reliable SchedulesPMA Consultants
 
Leveraging NetPoint & Excel for Template-Based Project Planning
Leveraging NetPoint & Excel for Template-Based Project PlanningLeveraging NetPoint & Excel for Template-Based Project Planning
Leveraging NetPoint & Excel for Template-Based Project PlanningPMA Consultants
 
The Value of Project Risk Management
The Value of Project Risk ManagementThe Value of Project Risk Management
The Value of Project Risk ManagementPMA Consultants
 
Risk Modeling and Analysis (Mitigating the Planning Fallacy)
Risk Modeling and Analysis (Mitigating the Planning Fallacy)Risk Modeling and Analysis (Mitigating the Planning Fallacy)
Risk Modeling and Analysis (Mitigating the Planning Fallacy)PMA Consultants
 

Mehr von PMA Consultants (20)

Practical Application of Value Engineering in Capital Projects
Practical Application of Value Engineering in Capital ProjectsPractical Application of Value Engineering in Capital Projects
Practical Application of Value Engineering in Capital Projects
 
Project Cost & Schedule Integration Lessons Learnt
Project Cost & Schedule Integration Lessons LearntProject Cost & Schedule Integration Lessons Learnt
Project Cost & Schedule Integration Lessons Learnt
 
PANDEMIC RESILIENTSCHOOLS
PANDEMIC RESILIENTSCHOOLSPANDEMIC RESILIENTSCHOOLS
PANDEMIC RESILIENTSCHOOLS
 
BioPharma Projects: Essentials in Project Controls
BioPharma Projects: Essentials in Project ControlsBioPharma Projects: Essentials in Project Controls
BioPharma Projects: Essentials in Project Controls
 
How to Implement a Project Management Information System
How to Implement a Project Management Information SystemHow to Implement a Project Management Information System
How to Implement a Project Management Information System
 
Top Five Metrics for Measuring Schedule Reliability
Top Five Metrics for Measuring Schedule ReliabilityTop Five Metrics for Measuring Schedule Reliability
Top Five Metrics for Measuring Schedule Reliability
 
What are the disadvantages of Gantt charts?
What are the disadvantages of Gantt charts?What are the disadvantages of Gantt charts?
What are the disadvantages of Gantt charts?
 
BIM and VDC for Megaproject Construction Projects
BIM and VDC for Megaproject Construction ProjectsBIM and VDC for Megaproject Construction Projects
BIM and VDC for Megaproject Construction Projects
 
Setting up Filters & Layouts in P6
Setting up Filters & Layouts in P6Setting up Filters & Layouts in P6
Setting up Filters & Layouts in P6
 
How to Choose a Project Delivery Method
How to Choose a Project Delivery MethodHow to Choose a Project Delivery Method
How to Choose a Project Delivery Method
 
Risk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacRisk Management Processes from Jerry Klanac
Risk Management Processes from Jerry Klanac
 
Project Controls Processes
Project Controls ProcessesProject Controls Processes
Project Controls Processes
 
Work Breakdown Structure Planning in NetPoint
Work Breakdown Structure Planning in NetPointWork Breakdown Structure Planning in NetPoint
Work Breakdown Structure Planning in NetPoint
 
How to Import/Export a Schedule between NetPoint and Microsft Excel
How to Import/Export a Schedule between NetPoint and Microsft ExcelHow to Import/Export a Schedule between NetPoint and Microsft Excel
How to Import/Export a Schedule between NetPoint and Microsft Excel
 
Smarter Planning with Microsoft Excel
Smarter Planning with Microsoft ExcelSmarter Planning with Microsoft Excel
Smarter Planning with Microsoft Excel
 
In Pursuit of Reliable Schedules
In Pursuit of Reliable SchedulesIn Pursuit of Reliable Schedules
In Pursuit of Reliable Schedules
 
Leveraging NetPoint & Excel for Template-Based Project Planning
Leveraging NetPoint & Excel for Template-Based Project PlanningLeveraging NetPoint & Excel for Template-Based Project Planning
Leveraging NetPoint & Excel for Template-Based Project Planning
 
The Value of Project Risk Management
The Value of Project Risk ManagementThe Value of Project Risk Management
The Value of Project Risk Management
 
Risk Modeling and Analysis (Mitigating the Planning Fallacy)
Risk Modeling and Analysis (Mitigating the Planning Fallacy)Risk Modeling and Analysis (Mitigating the Planning Fallacy)
Risk Modeling and Analysis (Mitigating the Planning Fallacy)
 
P6 tips tricks-client
P6 tips tricks-clientP6 tips tricks-client
P6 tips tricks-client
 

Kürzlich hochgeladen

Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoffsammart93
 
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot ModelMcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot ModelDeepika Singh
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century educationjfdjdjcjdnsjd
 
Vector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptxVector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptxRemote DBA Services
 
Six Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal OntologySix Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal Ontologyjohnbeverley2021
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDropbox
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodJuan lago vázquez
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businesspanagenda
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FMESafe Software
 
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...apidays
 
Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)Zilliz
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesrafiqahmad00786416
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingEdi Saputra
 
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...apidays
 
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfRising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfOrbitshub
 
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...Zilliz
 
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Orbitshub
 
FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024The Digital Insurer
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2
 

Kürzlich hochgeladen (20)

Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot ModelMcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
Vector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptxVector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptx
 
Six Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal OntologySix Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal Ontology
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
 
Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challenges
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
 
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfRising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
 
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
 
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
 
FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering Developers
 

Risk 2196 Removing the Early-Dates Bias in CPM Risk Analysis