From Taylor to Tailoring - In Pursuit of the Organizational Fit
1. Second International Scientific Conference on
Project Management in the Baltic Countries
FROM TAYLOR TO TAILORING
IN PURSUIT OF THE ORGANIZATIONAL FIT
Marisa Silva, PMP PRINCE2
Carlos Jerónimo, Eng. ITIL PMP
2. AGENDA
Literature Review
The Fit Challenge
From Taylor to Tailoring
The Diamond Approach
Research Methodology
Data Analysis and Discussion
As-Is State
Proposed Method
Key Findings
Conclusions
QA
Marisa Silva, PMP PRINCE2
2
3. The Fit Challenge
Marisa Silva, PMP PRINCE2
Particular practices, structures and
approaches that are most appropriate – that fit
– to a particular organization, in a particular
environment, trying to reach a particular
strategy
Measure that states to what extent did the implementation met
the needs of the organization or enables its success in
delivering projects
3
4. From Taylor to Tailoring
Marisa Silva, PMP PRINCE2
You can have any colour as long as it's black. One size doesn’t fit all
The ability to adapt or tailor the Project Management
processes to the characteristics of the project and its
context and ensure that projects are managed with the
proper amount of documentation and control and
related to the project environment and product design
4
5. From Taylor to Tailoring
Marisa Silva, PMP PRINCE2
A project
is a project
is a project
syndrome
(Shenhar and Dvir)
5
6. From Taylor to Tailoring
Marisa Silva, PMP PRINCE2
6
HEROIC
PROJECT
MANAGER
Doesn’t follow any methodology
Few documentation and control
Agile and flexible
Management by exception
Thinks outside-the-box
Project Management as an art
Accidental Project Manager
ROBOTIC
PROJECT
MANAGER
Follows the methodology blindly
Excess of documentation and control
Slow and inflexible
Management by the book
Stuck in-the-box
Project Management as a science
Professional Project Manager
8. Research Methodology
Marisa Silva, PMP PRINCE2
Should it be the ORGANIZATION to adapt to the project or
should it be the PROJECT to adapt to the organization?
IT Business Unit of one of the largest retail companies in Portugal
>150 people and a portfolio of 110 simultaneous projects
sample of 44 projects
2 days a week at the company, during 6 months
observations, interviews, and studies of written material
8
9. As-Is State
Marisa Silva, PMP PRINCE2
I don’t have time for
paperwork! I have a
project to manage!
The methodology has
no use for my project
so I’ve made some
changes!
I’m managing a
simple project and
it is over-burdened
Is there a Project
Management
methodology?
Well, we followed some
of the processes for
this project…
32 interviews
Same Project Management artifacts
regardless of project size or complexity
20% of project total duration was project
management work
Projects were prioritized based only on its
duration and budget
My project is taking longer just
because the PMO wants me to
comply with the methodology!
9
10. Proposed Method
Marisa Silva, PMP PRINCE2
1. Analyse the project’s portfolio and set a set of dimensions and
criteria
2. Define the configurations for each criteria and project types
3. Characterize projects for each criteria to obtain the project type
4. Define which processes and deliverables from the PM methodology
are applicable to different project types
10
14. Proposed Method
Marisa Silva, PMP PRINCE2
14
Light Medium Advanced
Initiation Project Charter Project Charter
Business Case
Project Charter
Planning
Product Breakdown Structure
Project Plan
Kick-off Meeting
Stakeholders Management Matrix
Product Breakdown Structure
Risk Register
Project Plan
Kick-off Meeting
Stakeholders Management Matrix
Risk Register
RACI Matrix
Product Breakdown Structure
Communication Management Plan
Procurement Management Plan
Project Plan
Kick-off Meeting
Capacity Planning
Execution Change Request
Change Request
Intermediate Deliverables
Acceptance
Change Request
Intermediate Deliverables Acceptance
Team Performance Appraisal
Monitoring and Control
Status Report
Change Request
Status Report
Change Request
Status Report
Change Request
Steering Committee
Closing
Final Acceptance
Internal Report
Lessons Learned Report
Final Acceptance
Internal Report
Lessons Learned Report
Final Acceptance Report and Meetingc
Satisfaction Survey
Internal Report
Lessons Learned Report
Project Lifecycle
Project Type
PM Methodology Tailoring Proposal
15. Key Findings
Marisa Silva, PMP PRINCE2
Technical Work
PM Work
100%
80%20%
-5%
-10%
-20%
Technical Work
PM Work
95%
90%5%
Light
Technical Work
PM Work
90%
80%10%
Medium
80%
Technical Work
PM Work
60%20%
Advanced
Pre-Tailoring Post-Tailoring
15
16. Key Findings
Marisa Silva, PMP PRINCE2
Decrease in projects duration (positive variance of 11 days)
Improvement of quality of information present in Project Management documentation
Reduced variability in how the processes are performed across the organization
Defined process for tailoring project management methodology
Distinguished and clarified priorities based in project classification
Increased stakeholder’s satisfaction rate
16
17. Conclusions
Marisa Silva, PMP PRINCE2
On the other hand…
the project too should adapt to the organization in the way that,
despite the different levels of project management work intensity
related to project type, all projects must follow a pre-defined and
standardized methodology
17
On one hand…
the organization should adapt itself to the project by not forcing a
project management methodology but instead define it in concordance
with the project portfolio characteristics