Lecture # 3
1. Compounding Factors
2. Effect of Inflation
1-1 Dr. A. Alim
Determination of Unknown Interest Rate
 Class of problems where the interest rate, i%,
is the unknown value
 For simple, single payment problems (i.e., P
and F only), solving for i% given the other
parameters is not difficult
 For annuity and gradient type problems,
solving for i% can be tedious
 Trial and error method
 Use EXCEL
Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012 1-2 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
The IRR and RATE Spreadsheet Functions
 Define the total cash flow as a column of
values within Excel
 Apply the IRR function:
=IRR(first_cell:last_cell, guess value)
 If the cash flow series is an A value then apply
the RATE function:
=RATE(number_years, A,P,F)
Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012 1-3 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
The IRR and RATE Spreadsheet Functions
Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012 1-4 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
Example 1
End of Year Cash Flow
0 (1,200.00)$
1 354.00$ IRR = 26.3%
2 700.00$
3 216.00$
4 953.00$
Example 2
End of Year Cash Flow
0 (1,200.00)$
1 400.00$ Rate = 12.6%
2 400.00$
3 400.00$ IRR = 12.6%
4 400.00$
Determination of Unknown Number of Years
 Class of problems where the number of time
periods (years) is the unknown
 In single payment type problems, solving for
n is straight forward
 In other types of cash flow profiles, solving
for n requires trial and error.
 In Excel, given A, P, or F, and i% values apply:
=NPER(i%,A,P,F) to return the value of n
Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012 1-5 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
Determination of Unknown Number of Years
Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012 1-6 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
Example:
P -1200
A 400
i 12.60%
Number of periods = 4
In practice – interest rates do not stay the same
over time unless by contractual obligation.
There can exist “variation” of interest rates over
time – quite normal!
If required, how do we handle that situation?
Interest rates that vary over time
Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012 1-7 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
Interest Rates that vary over time
 Best illustrated by an example.
 Assume for now that interest rate is constant 7% for the
whole 4 years period:
0 1 2 3 4
$70,000 $70,000
$35,000 $25,000
7% 7% 7% 7%
Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012 1-8 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
Interest Rates that vary over time
 Best illustrated by an example.
 Assume for now that interest rate is constant 7% for the
whole 4 years period:
0 1 2 3 4
$70,000 $70,000
$35,000 $25,000
7% 7% 7% 7%
P =
Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012 1-9 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
Interest Rates that vary over time
 Best illustrated by an example.
 Assume for now that interest rate is constant 7% for the
whole 4 years period:
0 1 2 3 4
$70,000 $70,000
$35,000 $25,000
7% 7% 7% 7%
P = 70,000(P/A,7%,2) + 35,000(P/F,7%,3) + 25,000(P/F,7%,4)
Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012 1-10 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
Interest Rates that vary over time
 Best illustrated by an example.
 Now, assume the following future profits:
0 1 2 3 4
$70,000 $70,000
$35,000 $25,000
7% 7% 9% 10%
(P/F,7%,1)
(P/F,7%,1)
(P/F,9%,1)
(P/F,10%,1)
(P/F,7%,1)
(P/F,7%,1) (P/F,7%,1)
(P/F,7%,1) (P/F,7%,1) (P/F,9%,1)
Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012 1-11 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
Varying Rates: Present Worth
To find the Present Worth:
Bring each cash flow amount back to the
appropriate point in time at the interest rate
according to:
P = F1(P/F,i1,1) + F2(P/F,i1,1)(P/F,i2,1) + …
+ Fn(P/F,i1,1)(P/F,i2,1)(P/F,i3,1)…(P/F,in,1)
This Process can get computationally involved!
Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012 1-12 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
Period-by-Period Analysis
 P0 =
$7000(P/F,7%,1) +
$7000(P/F,7%,1)(P/F,7%,1) +
$35000(P/F,9%,1)(P/F,7%,1)2 +
$25000(P/F,10%,1)(P/F,9%,1)(P/F,7%,1)2
Equals: $172,816 at t = 0…
Work backwards one period at a
time until you get to “0”.
Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012 1-13 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
Period-by-Period Analysis
 To obtain the equivalent uniform series A
over all n years, substitute the symbol A for
each Fi, then solve for A:
Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012 1-14 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
Period-by-Period Analysis
 P0 = $172,816 =
$A (P/F,7%,1) +
$A (P/F,7%,1)(P/F,7%,1) +
$A (P/F,9%,1)(P/F,7%,1)2 +
$A (P/F,10%,1)(P/F,9%,1)(P/F,7%,1)2
Solve for A = $51,777 per year
Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012 1-15 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
Varying Rates: Approximation
 An alternative approach that approximates the present value:
 Average the interest rates over the appropriate number of time
periods. In the previous example {7% + 7% + 9% + 10%} / 4 =
8.25%
 This approach is only an approximation. Students MUST NOT use
this method in solving problems in quizzes or examinations.
Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012 1-16 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
Inflation - Definition
 The increase in the amount of money
necessary to obtain the same amount of
product or service before the inflated
price was present;
 Social Phenomena where too much
money chases too few goods/services;
 Harmful impact because the purchasing
power of the currency changes downward
in value.
Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012 1-17 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
Deflation
 Where the value , i.e. the
purchasing power of the currency
increases over time.
 Less amounts of the currency can
purchase more goods and services
than before.
 Not very commonly seen……2009
was the first year with deflation (or
zero inflation) in a very long time!
Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012 1-18 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
Inflation rate - f
 The measure of the annual rate of change
in the value of a currency.
 Similar to an interest rate but should not
be viewed as an interest rate.
 f is a percentage value similar to the
interest rate.
 Let n represent the period of time
between now and a future date, then:
 Future cost = Current cost (1 +f )n
 Note: this does not involve time value of
money (compounding)
Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012 1-19 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
Example to Consider
 Assume a firm desires to purchase a
productive asset that costs $209,000 in
today’s dollars.
 Assume an inflation rate of say, 4% per
year;
 In 10 years, that same piece of equipment
would cost:
 $209,000(1.04)10 = $309,371!
 Does not include an interest rate or rate of return
consideration.
 The $309,371 are called “future dollars”.
Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012 1-20 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
Inflation can be Significant
 From the previous example we see that
even at a modest 4% rate of inflation, the
future impact on cost can be and often is
significant!
 The previous example does not consider
the time value of money.
 A proper engineering economy analysis
should consider both inflation and the
time value of money.
Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012 1-21 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
How is inflation measured*?
 Consumer Price Index (CPI) - a government measure of the
price change of a “market basket” of goods and services
(national inflation rate)
 Producer Price Indices – a government measure of price
changes for specific industries
 Chemical and Petrochemical Process Plants
 Farm Products
 Consulting Engineering Services Price Indexes
 Residential Building Construction Input Price Indexes
 Industrial product price indexes
 Raw materials price indexes
 Energy consumer price indices
* Ref. : J.C. Paradi, Centre for Management of Technology and
Entrepreneurship ( 1996-2004)
1-22Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
CPI
The CPI for a given period relates the average
price of a fixed “basket” of goods in the given
period to the average price of the same basket
of goods in a base period.
Current CPI base year is 1982 -84.
Base year index is set at 100.
The index for any other year indicates the
number of dollars needed in that year to buy the
basket of goods that cost $100 in 1982-84.
1-23Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
Historical CPI
Consumer Price Index historical summary – 1982-84 = 100%
Year CPI % Change Year CPI % Change Year CPI % Change
1972 41.8 3.2 1983 99.6 3.2 1994 148.2 2.6
1973 44.4 6.2 1984 103.9 4.3 1995 152.4 2.8
1974 49.3 11.0 1985 107.6 3.6 1996 156.9 3.0
1975 53.8 9.1 1986 109.6 1.9 1997 160.5 2.3
1976 56.9 5.8 1987 113.6 3.6 1998 163.0 1.6
1977 60.6 6.5 1988 118.3 4.1 1999 166.6 2.2
1978 65.2 7.6 1989 124.0 4.8 2000 172.2 3.4
1979 72.6 11.3 1990 130.7 5.4 2001 177.1 2.8
1980 82.4 13.5 1991 136.2 4.2 2002 179.9 1.6
1981 90.9 10.3 1992 140.3 3.0 2003 184.0 2.3
1982 96.5 6.2 1993 144.5 3.0 2004 188.9 2.7
2005 195.3 3.4
2006 201.6 3.2
2007 207.3 2.9
2008 215.3 3.8
2009 214.5 -0.4
2010 218.1 1.7
2011 224.9 3.2
2012 230.0 2.2
1-24Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
Inflation rate - f
 Defined as the percent change in CPI
from year to year.
 For example, from the previous table:
CPI in 2009 is 214.5
CPI in 2010 is 218.1
 Inflation rate in 2010 is:
100 x (218.1 – 214.4)/214.5 = approx
1.7%
Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012 1-25 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
Annual
Inflation rate
CPI
1-26Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
1-27Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012
© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
Accounting for inflation
There are two ways to make meaningful economic
calculations when the currency is changing in
value, that is when inflation is considered:
1. Convert the amounts that occur in different time
periods into constant value dollars. This is
accomplished before any time value of money
calculation is made using the real interest rate.
2. Change the interest rate used to account for
inflation plus the time value of money. This is
called the inflation-adjusted or market interest
rate.
Slide Sets to
accompany Blank &
Tarquin, Engineering
Economy, 7th Edition,
2012
28© 2012 by McGraw-Hill, New
York, N.Y All Rights Reserved
• Future Dollars = Today’s dollars(1+f)n
• Dollars at present time are termed:
– Constant-value or today’s dollars
• Dollars in time period t are termed:
– Future Dollars or,…
– Then-current Dollars.
1) Constant value dollars vs. future dollars
Slide Sets to
accompany Blank &
Tarquin, Engineering
Economy, 7th Edition,
2012
29© 2012 by McGraw-Hill, New
York, N.Y All Rights Reserved
Critical Relationships to Remember
• Constant-value Dollars (Today’s dollars)
• Future Dollars
n
future dollars
Constant-Value dollars =
(1+f)
n
Future dollars = today's dollars(1+f) .
Slide Sets to
accompany Blank &
Tarquin, Engineering
Economy, 7th Edition,
2012
30© 2012 by McGraw-Hill, New
York, N.Y All Rights Reserved
Three Important Rates
 Inflation-free interest rate.
Denoted as “i”.
 Inflation-adjusted interest rate.
Denoted as “if”
 Inflation rate.
Denoted as “f”.
2) Adjusting interest rate to include inflation
Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012 1-31 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
Real or Inflation-free Interest Rate - i
• Rate at which interest is earned.
• Effects of any inflation have been
removed.
• Represents the actual or real gain
received/charged on investments or
borrowing.
Slide Sets to
accompany Blank &
Tarquin, Engineering
Economy, 7th Edition,
2012 32© 2012 by McGraw-Hill, New
York, N.Y All Rights Reserved
Inflation-adjusted rate – if
• The interest rate that has been adjusted to
include inflation.
• Common Term –
– Market Interest Rate.
– Interest rate adjusted for inflation.
• The if rate is the combination of the real
interest rate i, and the inflation rate f.
• Also called the inflated interest rate.
Slide Sets to accompany
Blank & Tarquin, Engineering
Economy, 7th Edition, 2012
33© 2012 by McGraw-Hill, New
York, N.Y All Rights Reserved
Defining if
• if is derived from f and i as follows:
if = (i + f + if )
Or:
1
fi f
i
f


Slide Sets to
accompany Blank &
Tarquin, Engineering
Economy, 7th Edition,
2012
34© 2012 by McGraw-Hill, New
York, N.Y All Rights Reserved
Example
• Assume i = 10%/ year;
• f = 4% per year;
• if is then calculated as:
if = 0.10 + 0.04 + 0.10(0.04) = 0.144 =
14.4%/year
Slide Sets to
accompany Blank &
Tarquin, Engineering
Economy, 7th Edition,
2012
35© 2012 by McGraw-Hill, New
York, N.Y All Rights Reserved
Which interest rate to use?
• Either rate is correct when the correct dollar
value is selected:
Cash flow in Interest rate to use
Today’s dollar (constant value) i
Future dollars if
Slide Sets to
accompany Blank &
Tarquin, Engineering
Economy, 7th Edition,
2012
36© 2012 by McGraw-Hill, New
York, N.Y All Rights Reserved
Example 14.1, Blank (6th ed.), page 477
Slide Sets to
accompany Blank &
Tarquin, Engineering
Economy, 7th Edition,
2012
37© 2012 by McGraw-Hill, New
York, N.Y All Rights Reserved
Slide Sets to accompany
Blank & Tarquin, Engineering
Economy, 7th Edition, 2012
38© 2012 by McGraw-Hill, New
York, N.Y All Rights Reserved
Effect of Inflation on the MARR
When inflation is expected during the life of a project, the
MARR needs to be increased to avoid accepting poor
projects.
 Inflated MARR = minimum acceptable rate of return when cash
flows are in actual dollars (future dollars).
If investors expect inflation, they require higher actual
rates of return on their investments than if inflation were
not expected.
 Inflated MARR = real MARR (without inflation) + upwards
adjustment which reflects the effect of inflation.
So, following from the definition, we have: if = (i + f + if )
MARRinflated = MARRR + f + MARRR * f
 where MARRinflated(if) is inflated MARR and MARRR (i) is real MARR
(without inflation).
Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012 1-39 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
Abbott Mining Systems wants to determine whether it should buy now or buy
later a piece of equipment used in deep mining operations. If the
company selects plan N, the equipment will be purchased now for $200,000.
However, if the company selects plan L, the purchase will be deferred for
3 years when the cost is expected to rise rapidly to $340,000. Abbott is
ambitious; it expects a real MARR of 12% per year. The inflation rate in the
country has averaged 6.75% per year. From only an economic perspective,
determine whether the company should purchase now or later (a) when inflation
is not considered and (b) when inflation is considered.
Solution
a) Inflation not considered: The real rate, or MARR, is i = 12% per year. The
cost of plan L is $340,000 three years hence. Calculate the FW value for
plan N three years from now:
FWN = -200,000(F/P,12%,3) = $-280,986
FWL = $-340,000
Hence buy now
Example 14.4, Blank (6th ed.), page 483:
Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012 1-40 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
b) Inflation considered: There is a real rate (12%), and inflation
is 6.75%. First, compute the inflation-adjusted MARR :
MARRf = 0.12 + 0.0675 + 0.12(0.0675) = 0.1956
Compute the FW value for plan N in future dollars.
FWN = -200,000(F/P,19.56%,3) = $-341,812
FWL = $-340,000
Purchasing later is selected, because it requires fewer equivalent future
dollars. The inflation rate of 6.75% per year has raised the equivalent future
worth of costs by 21.6% to $341,812.
Slide Sets to accompany Blank & Tarquin, Engineering
Economy, 7th Edition, 2012 1-41 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved

Weitere ähnliche Inhalte

Was ist angesagt?

Lecture # 9 taxes and eva
Lecture # 9 taxes and evaLecture # 9 taxes and eva
Lecture # 9 taxes and evaBich Lien Pham
 
Chapter 5 present worth analysis
Chapter 5   present worth analysisChapter 5   present worth analysis
Chapter 5 present worth analysisBich Lien Pham
 
Chapter 1 foundations of engineering economy
Chapter 1   foundations of engineering economyChapter 1   foundations of engineering economy
Chapter 1 foundations of engineering economyBich Lien Pham
 
Chapter 10 making choices & marr
Chapter 10   making choices & marrChapter 10   making choices & marr
Chapter 10 making choices & marrBich Lien Pham
 
Chapter 13 breakeven analysis
Chapter 13   breakeven analysisChapter 13   breakeven analysis
Chapter 13 breakeven analysisBich Lien Pham
 
Chapter 14 effects of inflation
Chapter 14   effects of inflationChapter 14   effects of inflation
Chapter 14 effects of inflationBich Lien Pham
 
Chapter 6 annual worth analysis
Chapter 6   annual worth analysisChapter 6   annual worth analysis
Chapter 6 annual worth analysisBich Lien Pham
 
Chapter 9 benefit & cost analysis
Chapter 9   benefit & cost analysisChapter 9   benefit & cost analysis
Chapter 9 benefit & cost analysisBich Lien Pham
 
Chapter 15 cost estimation
Chapter 15   cost estimationChapter 15   cost estimation
Chapter 15 cost estimationBich Lien Pham
 
Chapter 12 independent projects & budget limitation
Chapter 12   independent projects & budget limitationChapter 12   independent projects & budget limitation
Chapter 12 independent projects & budget limitationBich Lien Pham
 
Chapter 17 after-tax economic analysis
Chapter 17   after-tax economic analysisChapter 17   after-tax economic analysis
Chapter 17 after-tax economic analysisBich Lien Pham
 
Chapter 7 ror analysis for a single alternative
Chapter 7   ror analysis for a single alternativeChapter 7   ror analysis for a single alternative
Chapter 7 ror analysis for a single alternativeBich Lien Pham
 
Lecture # 12 measures of profitability ii
Lecture # 12 measures of profitability iiLecture # 12 measures of profitability ii
Lecture # 12 measures of profitability iiBich Lien Pham
 
Chapter 11 replacement & retention decisions
Chapter 11   replacement & retention decisionsChapter 11   replacement & retention decisions
Chapter 11 replacement & retention decisionsBich Lien Pham
 

Was ist angesagt? (15)

Engin economic slides
Engin economic slidesEngin economic slides
Engin economic slides
 
Lecture # 9 taxes and eva
Lecture # 9 taxes and evaLecture # 9 taxes and eva
Lecture # 9 taxes and eva
 
Chapter 5 present worth analysis
Chapter 5   present worth analysisChapter 5   present worth analysis
Chapter 5 present worth analysis
 
Chapter 1 foundations of engineering economy
Chapter 1   foundations of engineering economyChapter 1   foundations of engineering economy
Chapter 1 foundations of engineering economy
 
Chapter 10 making choices & marr
Chapter 10   making choices & marrChapter 10   making choices & marr
Chapter 10 making choices & marr
 
Chapter 13 breakeven analysis
Chapter 13   breakeven analysisChapter 13   breakeven analysis
Chapter 13 breakeven analysis
 
Chapter 14 effects of inflation
Chapter 14   effects of inflationChapter 14   effects of inflation
Chapter 14 effects of inflation
 
Chapter 6 annual worth analysis
Chapter 6   annual worth analysisChapter 6   annual worth analysis
Chapter 6 annual worth analysis
 
Chapter 9 benefit & cost analysis
Chapter 9   benefit & cost analysisChapter 9   benefit & cost analysis
Chapter 9 benefit & cost analysis
 
Chapter 15 cost estimation
Chapter 15   cost estimationChapter 15   cost estimation
Chapter 15 cost estimation
 
Chapter 12 independent projects & budget limitation
Chapter 12   independent projects & budget limitationChapter 12   independent projects & budget limitation
Chapter 12 independent projects & budget limitation
 
Chapter 17 after-tax economic analysis
Chapter 17   after-tax economic analysisChapter 17   after-tax economic analysis
Chapter 17 after-tax economic analysis
 
Chapter 7 ror analysis for a single alternative
Chapter 7   ror analysis for a single alternativeChapter 7   ror analysis for a single alternative
Chapter 7 ror analysis for a single alternative
 
Lecture # 12 measures of profitability ii
Lecture # 12 measures of profitability iiLecture # 12 measures of profitability ii
Lecture # 12 measures of profitability ii
 
Chapter 11 replacement & retention decisions
Chapter 11   replacement & retention decisionsChapter 11   replacement & retention decisions
Chapter 11 replacement & retention decisions
 

Andere mochten auch

Lecture # 5 cost estimation i
Lecture # 5 cost estimation iLecture # 5 cost estimation i
Lecture # 5 cost estimation iBich Lien Pham
 
Lecture # 2 time value of money
Lecture # 2 time value of moneyLecture # 2 time value of money
Lecture # 2 time value of moneyBich Lien Pham
 
Chapter 18 sensitivity analysis
Chapter 18   sensitivity analysisChapter 18   sensitivity analysis
Chapter 18 sensitivity analysisBich Lien Pham
 
Lecture # 11 measures of profitability i
Lecture # 11 measures of profitability iLecture # 11 measures of profitability i
Lecture # 11 measures of profitability iBich Lien Pham
 
Chapter 16 depreciation methods
Chapter 16   depreciation methodsChapter 16   depreciation methods
Chapter 16 depreciation methodsBich Lien Pham
 
Chapter 19 decision-making under risk
Chapter 19   decision-making under riskChapter 19   decision-making under risk
Chapter 19 decision-making under riskBich Lien Pham
 
Lecture # 4 gradients factors and nominal and effective interest rates
Lecture # 4 gradients factors and nominal and effective interest ratesLecture # 4 gradients factors and nominal and effective interest rates
Lecture # 4 gradients factors and nominal and effective interest ratesBich Lien Pham
 
Lecture # 1 foundation
Lecture # 1 foundationLecture # 1 foundation
Lecture # 1 foundationBich Lien Pham
 
Lecture # 13 investment alternatives i
Lecture # 13 investment alternatives iLecture # 13 investment alternatives i
Lecture # 13 investment alternatives iBich Lien Pham
 
Chapter 7 capital cost estimation
Chapter 7 capital cost estimationChapter 7 capital cost estimation
Chapter 7 capital cost estimationjose2424
 
Lecture # 6 cost estimation ii
Lecture # 6 cost estimation iiLecture # 6 cost estimation ii
Lecture # 6 cost estimation iiBich Lien Pham
 
Lecture # 5 cost estimation i
Lecture # 5 cost estimation iLecture # 5 cost estimation i
Lecture # 5 cost estimation iBich Lien Pham
 
Chapter 13 breakeven analysis
Chapter 13   breakeven analysisChapter 13   breakeven analysis
Chapter 13 breakeven analysisBich Lien Pham
 
engineering economy solution manual sullivan 15th ed
engineering economy solution manual sullivan 15th edengineering economy solution manual sullivan 15th ed
engineering economy solution manual sullivan 15th edDiego Fung
 

Andere mochten auch (14)

Lecture # 5 cost estimation i
Lecture # 5 cost estimation iLecture # 5 cost estimation i
Lecture # 5 cost estimation i
 
Lecture # 2 time value of money
Lecture # 2 time value of moneyLecture # 2 time value of money
Lecture # 2 time value of money
 
Chapter 18 sensitivity analysis
Chapter 18   sensitivity analysisChapter 18   sensitivity analysis
Chapter 18 sensitivity analysis
 
Lecture # 11 measures of profitability i
Lecture # 11 measures of profitability iLecture # 11 measures of profitability i
Lecture # 11 measures of profitability i
 
Chapter 16 depreciation methods
Chapter 16   depreciation methodsChapter 16   depreciation methods
Chapter 16 depreciation methods
 
Chapter 19 decision-making under risk
Chapter 19   decision-making under riskChapter 19   decision-making under risk
Chapter 19 decision-making under risk
 
Lecture # 4 gradients factors and nominal and effective interest rates
Lecture # 4 gradients factors and nominal and effective interest ratesLecture # 4 gradients factors and nominal and effective interest rates
Lecture # 4 gradients factors and nominal and effective interest rates
 
Lecture # 1 foundation
Lecture # 1 foundationLecture # 1 foundation
Lecture # 1 foundation
 
Lecture # 13 investment alternatives i
Lecture # 13 investment alternatives iLecture # 13 investment alternatives i
Lecture # 13 investment alternatives i
 
Chapter 7 capital cost estimation
Chapter 7 capital cost estimationChapter 7 capital cost estimation
Chapter 7 capital cost estimation
 
Lecture # 6 cost estimation ii
Lecture # 6 cost estimation iiLecture # 6 cost estimation ii
Lecture # 6 cost estimation ii
 
Lecture # 5 cost estimation i
Lecture # 5 cost estimation iLecture # 5 cost estimation i
Lecture # 5 cost estimation i
 
Chapter 13 breakeven analysis
Chapter 13   breakeven analysisChapter 13   breakeven analysis
Chapter 13 breakeven analysis
 
engineering economy solution manual sullivan 15th ed
engineering economy solution manual sullivan 15th edengineering economy solution manual sullivan 15th ed
engineering economy solution manual sullivan 15th ed
 

Ähnlich wie Lecture on Engineering Economy Concepts

Chapter 2 factors, effect of time & interest on money
Chapter 2   factors, effect of time & interest on moneyChapter 2   factors, effect of time & interest on money
Chapter 2 factors, effect of time & interest on moneyBich Lien Pham
 
Chapter 2 factors, effect of time & interest on money
Chapter 2   factors, effect of time & interest on moneyChapter 2   factors, effect of time & interest on money
Chapter 2 factors, effect of time & interest on moneyBich Lien Pham
 
Leland_Tarquin_Engineering_Economy_Chapter_2_Factors_Effect_Time_Interest_Mon...
Leland_Tarquin_Engineering_Economy_Chapter_2_Factors_Effect_Time_Interest_Mon...Leland_Tarquin_Engineering_Economy_Chapter_2_Factors_Effect_Time_Interest_Mon...
Leland_Tarquin_Engineering_Economy_Chapter_2_Factors_Effect_Time_Interest_Mon...ssuser1ba731
 
chapter2-factorseffectoftimeinterestonmoney-140315184227-phpapp01.pdf
chapter2-factorseffectoftimeinterestonmoney-140315184227-phpapp01.pdfchapter2-factorseffectoftimeinterestonmoney-140315184227-phpapp01.pdf
chapter2-factorseffectoftimeinterestonmoney-140315184227-phpapp01.pdfWanizaSiddiqui
 
Chapter 3 combining factors
Chapter 3   combining factorsChapter 3   combining factors
Chapter 3 combining factorsBich Lien Pham
 
Chapter 3 combining factors
Chapter 3   combining factorsChapter 3   combining factors
Chapter 3 combining factorsBich Lien Pham
 
Ch 1 foundations-modified
Ch 1 foundations-modifiedCh 1 foundations-modified
Ch 1 foundations-modifiedIslaam99
 
Leland_Tarquin_Engineering_Economy_Chapter_1_Foundations_Engineering_Economy.ppt
Leland_Tarquin_Engineering_Economy_Chapter_1_Foundations_Engineering_Economy.pptLeland_Tarquin_Engineering_Economy_Chapter_1_Foundations_Engineering_Economy.ppt
Leland_Tarquin_Engineering_Economy_Chapter_1_Foundations_Engineering_Economy.pptssuser1ba731
 
Leland_Tarquin_Engineering_Economy_Chapter_1_Foundations_Engineering_Economy.pdf
Leland_Tarquin_Engineering_Economy_Chapter_1_Foundations_Engineering_Economy.pdfLeland_Tarquin_Engineering_Economy_Chapter_1_Foundations_Engineering_Economy.pdf
Leland_Tarquin_Engineering_Economy_Chapter_1_Foundations_Engineering_Economy.pdfKumailAbbas89
 
EMT320W1Lecture
EMT320W1LectureEMT320W1Lecture
EMT320W1Lectureehillier
 
Eng econslides
Eng econslidesEng econslides
Eng econslidesOmar Cesar
 
Leland_Tarquin_Engineering_Economy_Chapter_3_Combining_Factors.ppt
Leland_Tarquin_Engineering_Economy_Chapter_3_Combining_Factors.pptLeland_Tarquin_Engineering_Economy_Chapter_3_Combining_Factors.ppt
Leland_Tarquin_Engineering_Economy_Chapter_3_Combining_Factors.pptssuser1ba731
 
1031191EE 200 Engineering Economics 2Time Value o.docx
1031191EE 200 Engineering Economics 2Time Value o.docx1031191EE 200 Engineering Economics 2Time Value o.docx
1031191EE 200 Engineering Economics 2Time Value o.docxaulasnilda
 
Chapter 1 Engineering Economics.pptx
Chapter 1 Engineering Economics.pptxChapter 1 Engineering Economics.pptx
Chapter 1 Engineering Economics.pptxmatiurrehman55
 
12Insert Title HereInsert Your Name HereInsert
12Insert Title HereInsert Your Name HereInsert12Insert Title HereInsert Your Name HereInsert
12Insert Title HereInsert Your Name HereInsertChantellPantoja184
 
12Insert Title HereInsert Your Name HereInsert
12Insert Title HereInsert Your Name HereInsert12Insert Title HereInsert Your Name HereInsert
12Insert Title HereInsert Your Name HereInsertEttaBenton28
 
Cost of capital
Cost of capitalCost of capital
Cost of capitaledjolax
 
Chapter_3_Time_Value_of_Money.pdf
Chapter_3_Time_Value_of_Money.pdfChapter_3_Time_Value_of_Money.pdf
Chapter_3_Time_Value_of_Money.pdfSudipBalLama
 

Ähnlich wie Lecture on Engineering Economy Concepts (20)

Lecture2 timevalueofmoney
Lecture2 timevalueofmoneyLecture2 timevalueofmoney
Lecture2 timevalueofmoney
 
Ch 01 slides
Ch 01 slidesCh 01 slides
Ch 01 slides
 
Chapter 2 factors, effect of time & interest on money
Chapter 2   factors, effect of time & interest on moneyChapter 2   factors, effect of time & interest on money
Chapter 2 factors, effect of time & interest on money
 
Chapter 2 factors, effect of time & interest on money
Chapter 2   factors, effect of time & interest on moneyChapter 2   factors, effect of time & interest on money
Chapter 2 factors, effect of time & interest on money
 
Leland_Tarquin_Engineering_Economy_Chapter_2_Factors_Effect_Time_Interest_Mon...
Leland_Tarquin_Engineering_Economy_Chapter_2_Factors_Effect_Time_Interest_Mon...Leland_Tarquin_Engineering_Economy_Chapter_2_Factors_Effect_Time_Interest_Mon...
Leland_Tarquin_Engineering_Economy_Chapter_2_Factors_Effect_Time_Interest_Mon...
 
chapter2-factorseffectoftimeinterestonmoney-140315184227-phpapp01.pdf
chapter2-factorseffectoftimeinterestonmoney-140315184227-phpapp01.pdfchapter2-factorseffectoftimeinterestonmoney-140315184227-phpapp01.pdf
chapter2-factorseffectoftimeinterestonmoney-140315184227-phpapp01.pdf
 
Chapter 3 combining factors
Chapter 3   combining factorsChapter 3   combining factors
Chapter 3 combining factors
 
Chapter 3 combining factors
Chapter 3   combining factorsChapter 3   combining factors
Chapter 3 combining factors
 
Ch 1 foundations-modified
Ch 1 foundations-modifiedCh 1 foundations-modified
Ch 1 foundations-modified
 
Leland_Tarquin_Engineering_Economy_Chapter_1_Foundations_Engineering_Economy.ppt
Leland_Tarquin_Engineering_Economy_Chapter_1_Foundations_Engineering_Economy.pptLeland_Tarquin_Engineering_Economy_Chapter_1_Foundations_Engineering_Economy.ppt
Leland_Tarquin_Engineering_Economy_Chapter_1_Foundations_Engineering_Economy.ppt
 
Leland_Tarquin_Engineering_Economy_Chapter_1_Foundations_Engineering_Economy.pdf
Leland_Tarquin_Engineering_Economy_Chapter_1_Foundations_Engineering_Economy.pdfLeland_Tarquin_Engineering_Economy_Chapter_1_Foundations_Engineering_Economy.pdf
Leland_Tarquin_Engineering_Economy_Chapter_1_Foundations_Engineering_Economy.pdf
 
EMT320W1Lecture
EMT320W1LectureEMT320W1Lecture
EMT320W1Lecture
 
Eng econslides
Eng econslidesEng econslides
Eng econslides
 
Leland_Tarquin_Engineering_Economy_Chapter_3_Combining_Factors.ppt
Leland_Tarquin_Engineering_Economy_Chapter_3_Combining_Factors.pptLeland_Tarquin_Engineering_Economy_Chapter_3_Combining_Factors.ppt
Leland_Tarquin_Engineering_Economy_Chapter_3_Combining_Factors.ppt
 
1031191EE 200 Engineering Economics 2Time Value o.docx
1031191EE 200 Engineering Economics 2Time Value o.docx1031191EE 200 Engineering Economics 2Time Value o.docx
1031191EE 200 Engineering Economics 2Time Value o.docx
 
Chapter 1 Engineering Economics.pptx
Chapter 1 Engineering Economics.pptxChapter 1 Engineering Economics.pptx
Chapter 1 Engineering Economics.pptx
 
12Insert Title HereInsert Your Name HereInsert
12Insert Title HereInsert Your Name HereInsert12Insert Title HereInsert Your Name HereInsert
12Insert Title HereInsert Your Name HereInsert
 
12Insert Title HereInsert Your Name HereInsert
12Insert Title HereInsert Your Name HereInsert12Insert Title HereInsert Your Name HereInsert
12Insert Title HereInsert Your Name HereInsert
 
Cost of capital
Cost of capitalCost of capital
Cost of capital
 
Chapter_3_Time_Value_of_Money.pdf
Chapter_3_Time_Value_of_Money.pdfChapter_3_Time_Value_of_Money.pdf
Chapter_3_Time_Value_of_Money.pdf
 

Mehr von Bich Lien Pham

Chapter 17 after-tax economic analysis
Chapter 17   after-tax economic analysisChapter 17   after-tax economic analysis
Chapter 17 after-tax economic analysisBich Lien Pham
 
Chapter 15 cost estimation
Chapter 15   cost estimationChapter 15   cost estimation
Chapter 15 cost estimationBich Lien Pham
 
Chapter 14 effects of inflation
Chapter 14   effects of inflationChapter 14   effects of inflation
Chapter 14 effects of inflationBich Lien Pham
 
Chapter 12 independent projects & budget limitation
Chapter 12   independent projects & budget limitationChapter 12   independent projects & budget limitation
Chapter 12 independent projects & budget limitationBich Lien Pham
 
Chapter 11 replacement & retention decisions
Chapter 11   replacement & retention decisionsChapter 11   replacement & retention decisions
Chapter 11 replacement & retention decisionsBich Lien Pham
 
Chapter 10 making choices & marr
Chapter 10   making choices & marrChapter 10   making choices & marr
Chapter 10 making choices & marrBich Lien Pham
 
Chapter 9 benefit & cost analysis
Chapter 9   benefit & cost analysisChapter 9   benefit & cost analysis
Chapter 9 benefit & cost analysisBich Lien Pham
 
Chapter 8 ror analysis for multiple alternatives
Chapter 8   ror analysis for multiple alternativesChapter 8   ror analysis for multiple alternatives
Chapter 8 ror analysis for multiple alternativesBich Lien Pham
 
Chapter 7 ror analysis for a single alternative
Chapter 7   ror analysis for a single alternativeChapter 7   ror analysis for a single alternative
Chapter 7 ror analysis for a single alternativeBich Lien Pham
 
Chapter 6 annual worth analysis
Chapter 6   annual worth analysisChapter 6   annual worth analysis
Chapter 6 annual worth analysisBich Lien Pham
 
Chapter 5 present worth analysis
Chapter 5   present worth analysisChapter 5   present worth analysis
Chapter 5 present worth analysisBich Lien Pham
 
Chapter 4 nominal & effective interest rates
Chapter 4   nominal & effective interest ratesChapter 4   nominal & effective interest rates
Chapter 4 nominal & effective interest ratesBich Lien Pham
 

Mehr von Bich Lien Pham (12)

Chapter 17 after-tax economic analysis
Chapter 17   after-tax economic analysisChapter 17   after-tax economic analysis
Chapter 17 after-tax economic analysis
 
Chapter 15 cost estimation
Chapter 15   cost estimationChapter 15   cost estimation
Chapter 15 cost estimation
 
Chapter 14 effects of inflation
Chapter 14   effects of inflationChapter 14   effects of inflation
Chapter 14 effects of inflation
 
Chapter 12 independent projects & budget limitation
Chapter 12   independent projects & budget limitationChapter 12   independent projects & budget limitation
Chapter 12 independent projects & budget limitation
 
Chapter 11 replacement & retention decisions
Chapter 11   replacement & retention decisionsChapter 11   replacement & retention decisions
Chapter 11 replacement & retention decisions
 
Chapter 10 making choices & marr
Chapter 10   making choices & marrChapter 10   making choices & marr
Chapter 10 making choices & marr
 
Chapter 9 benefit & cost analysis
Chapter 9   benefit & cost analysisChapter 9   benefit & cost analysis
Chapter 9 benefit & cost analysis
 
Chapter 8 ror analysis for multiple alternatives
Chapter 8   ror analysis for multiple alternativesChapter 8   ror analysis for multiple alternatives
Chapter 8 ror analysis for multiple alternatives
 
Chapter 7 ror analysis for a single alternative
Chapter 7   ror analysis for a single alternativeChapter 7   ror analysis for a single alternative
Chapter 7 ror analysis for a single alternative
 
Chapter 6 annual worth analysis
Chapter 6   annual worth analysisChapter 6   annual worth analysis
Chapter 6 annual worth analysis
 
Chapter 5 present worth analysis
Chapter 5   present worth analysisChapter 5   present worth analysis
Chapter 5 present worth analysis
 
Chapter 4 nominal & effective interest rates
Chapter 4   nominal & effective interest ratesChapter 4   nominal & effective interest rates
Chapter 4 nominal & effective interest rates
 

Kürzlich hochgeladen

(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
India Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportIndia Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportMintel Group
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...ictsugar
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Pereraictsugar
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCRashishs7044
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxMarkAnthonyAurellano
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 

Kürzlich hochgeladen (20)

(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
India Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportIndia Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample Report
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
 
Call Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North GoaCall Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North Goa
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Perera
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 

Lecture on Engineering Economy Concepts

  • 1. Lecture # 3 1. Compounding Factors 2. Effect of Inflation 1-1 Dr. A. Alim
  • 2. Determination of Unknown Interest Rate  Class of problems where the interest rate, i%, is the unknown value  For simple, single payment problems (i.e., P and F only), solving for i% given the other parameters is not difficult  For annuity and gradient type problems, solving for i% can be tedious  Trial and error method  Use EXCEL Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 1-2 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 3. The IRR and RATE Spreadsheet Functions  Define the total cash flow as a column of values within Excel  Apply the IRR function: =IRR(first_cell:last_cell, guess value)  If the cash flow series is an A value then apply the RATE function: =RATE(number_years, A,P,F) Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 1-3 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 4. The IRR and RATE Spreadsheet Functions Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 1-4 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved Example 1 End of Year Cash Flow 0 (1,200.00)$ 1 354.00$ IRR = 26.3% 2 700.00$ 3 216.00$ 4 953.00$ Example 2 End of Year Cash Flow 0 (1,200.00)$ 1 400.00$ Rate = 12.6% 2 400.00$ 3 400.00$ IRR = 12.6% 4 400.00$
  • 5. Determination of Unknown Number of Years  Class of problems where the number of time periods (years) is the unknown  In single payment type problems, solving for n is straight forward  In other types of cash flow profiles, solving for n requires trial and error.  In Excel, given A, P, or F, and i% values apply: =NPER(i%,A,P,F) to return the value of n Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 1-5 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 6. Determination of Unknown Number of Years Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 1-6 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved Example: P -1200 A 400 i 12.60% Number of periods = 4
  • 7. In practice – interest rates do not stay the same over time unless by contractual obligation. There can exist “variation” of interest rates over time – quite normal! If required, how do we handle that situation? Interest rates that vary over time Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 1-7 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 8. Interest Rates that vary over time  Best illustrated by an example.  Assume for now that interest rate is constant 7% for the whole 4 years period: 0 1 2 3 4 $70,000 $70,000 $35,000 $25,000 7% 7% 7% 7% Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 1-8 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 9. Interest Rates that vary over time  Best illustrated by an example.  Assume for now that interest rate is constant 7% for the whole 4 years period: 0 1 2 3 4 $70,000 $70,000 $35,000 $25,000 7% 7% 7% 7% P = Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 1-9 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 10. Interest Rates that vary over time  Best illustrated by an example.  Assume for now that interest rate is constant 7% for the whole 4 years period: 0 1 2 3 4 $70,000 $70,000 $35,000 $25,000 7% 7% 7% 7% P = 70,000(P/A,7%,2) + 35,000(P/F,7%,3) + 25,000(P/F,7%,4) Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 1-10 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 11. Interest Rates that vary over time  Best illustrated by an example.  Now, assume the following future profits: 0 1 2 3 4 $70,000 $70,000 $35,000 $25,000 7% 7% 9% 10% (P/F,7%,1) (P/F,7%,1) (P/F,9%,1) (P/F,10%,1) (P/F,7%,1) (P/F,7%,1) (P/F,7%,1) (P/F,7%,1) (P/F,7%,1) (P/F,9%,1) Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 1-11 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 12. Varying Rates: Present Worth To find the Present Worth: Bring each cash flow amount back to the appropriate point in time at the interest rate according to: P = F1(P/F,i1,1) + F2(P/F,i1,1)(P/F,i2,1) + … + Fn(P/F,i1,1)(P/F,i2,1)(P/F,i3,1)…(P/F,in,1) This Process can get computationally involved! Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 1-12 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 13. Period-by-Period Analysis  P0 = $7000(P/F,7%,1) + $7000(P/F,7%,1)(P/F,7%,1) + $35000(P/F,9%,1)(P/F,7%,1)2 + $25000(P/F,10%,1)(P/F,9%,1)(P/F,7%,1)2 Equals: $172,816 at t = 0… Work backwards one period at a time until you get to “0”. Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 1-13 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 14. Period-by-Period Analysis  To obtain the equivalent uniform series A over all n years, substitute the symbol A for each Fi, then solve for A: Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 1-14 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 15. Period-by-Period Analysis  P0 = $172,816 = $A (P/F,7%,1) + $A (P/F,7%,1)(P/F,7%,1) + $A (P/F,9%,1)(P/F,7%,1)2 + $A (P/F,10%,1)(P/F,9%,1)(P/F,7%,1)2 Solve for A = $51,777 per year Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 1-15 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 16. Varying Rates: Approximation  An alternative approach that approximates the present value:  Average the interest rates over the appropriate number of time periods. In the previous example {7% + 7% + 9% + 10%} / 4 = 8.25%  This approach is only an approximation. Students MUST NOT use this method in solving problems in quizzes or examinations. Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 1-16 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 17. Inflation - Definition  The increase in the amount of money necessary to obtain the same amount of product or service before the inflated price was present;  Social Phenomena where too much money chases too few goods/services;  Harmful impact because the purchasing power of the currency changes downward in value. Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 1-17 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 18. Deflation  Where the value , i.e. the purchasing power of the currency increases over time.  Less amounts of the currency can purchase more goods and services than before.  Not very commonly seen……2009 was the first year with deflation (or zero inflation) in a very long time! Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 1-18 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 19. Inflation rate - f  The measure of the annual rate of change in the value of a currency.  Similar to an interest rate but should not be viewed as an interest rate.  f is a percentage value similar to the interest rate.  Let n represent the period of time between now and a future date, then:  Future cost = Current cost (1 +f )n  Note: this does not involve time value of money (compounding) Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 1-19 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 20. Example to Consider  Assume a firm desires to purchase a productive asset that costs $209,000 in today’s dollars.  Assume an inflation rate of say, 4% per year;  In 10 years, that same piece of equipment would cost:  $209,000(1.04)10 = $309,371!  Does not include an interest rate or rate of return consideration.  The $309,371 are called “future dollars”. Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 1-20 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 21. Inflation can be Significant  From the previous example we see that even at a modest 4% rate of inflation, the future impact on cost can be and often is significant!  The previous example does not consider the time value of money.  A proper engineering economy analysis should consider both inflation and the time value of money. Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 1-21 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 22. How is inflation measured*?  Consumer Price Index (CPI) - a government measure of the price change of a “market basket” of goods and services (national inflation rate)  Producer Price Indices – a government measure of price changes for specific industries  Chemical and Petrochemical Process Plants  Farm Products  Consulting Engineering Services Price Indexes  Residential Building Construction Input Price Indexes  Industrial product price indexes  Raw materials price indexes  Energy consumer price indices * Ref. : J.C. Paradi, Centre for Management of Technology and Entrepreneurship ( 1996-2004) 1-22Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 23. CPI The CPI for a given period relates the average price of a fixed “basket” of goods in the given period to the average price of the same basket of goods in a base period. Current CPI base year is 1982 -84. Base year index is set at 100. The index for any other year indicates the number of dollars needed in that year to buy the basket of goods that cost $100 in 1982-84. 1-23Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 24. Historical CPI Consumer Price Index historical summary – 1982-84 = 100% Year CPI % Change Year CPI % Change Year CPI % Change 1972 41.8 3.2 1983 99.6 3.2 1994 148.2 2.6 1973 44.4 6.2 1984 103.9 4.3 1995 152.4 2.8 1974 49.3 11.0 1985 107.6 3.6 1996 156.9 3.0 1975 53.8 9.1 1986 109.6 1.9 1997 160.5 2.3 1976 56.9 5.8 1987 113.6 3.6 1998 163.0 1.6 1977 60.6 6.5 1988 118.3 4.1 1999 166.6 2.2 1978 65.2 7.6 1989 124.0 4.8 2000 172.2 3.4 1979 72.6 11.3 1990 130.7 5.4 2001 177.1 2.8 1980 82.4 13.5 1991 136.2 4.2 2002 179.9 1.6 1981 90.9 10.3 1992 140.3 3.0 2003 184.0 2.3 1982 96.5 6.2 1993 144.5 3.0 2004 188.9 2.7 2005 195.3 3.4 2006 201.6 3.2 2007 207.3 2.9 2008 215.3 3.8 2009 214.5 -0.4 2010 218.1 1.7 2011 224.9 3.2 2012 230.0 2.2 1-24Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 25. Inflation rate - f  Defined as the percent change in CPI from year to year.  For example, from the previous table: CPI in 2009 is 214.5 CPI in 2010 is 218.1  Inflation rate in 2010 is: 100 x (218.1 – 214.4)/214.5 = approx 1.7% Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 1-25 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 26. Annual Inflation rate CPI 1-26Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 27. 1-27Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 28. Accounting for inflation There are two ways to make meaningful economic calculations when the currency is changing in value, that is when inflation is considered: 1. Convert the amounts that occur in different time periods into constant value dollars. This is accomplished before any time value of money calculation is made using the real interest rate. 2. Change the interest rate used to account for inflation plus the time value of money. This is called the inflation-adjusted or market interest rate. Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 28© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 29. • Future Dollars = Today’s dollars(1+f)n • Dollars at present time are termed: – Constant-value or today’s dollars • Dollars in time period t are termed: – Future Dollars or,… – Then-current Dollars. 1) Constant value dollars vs. future dollars Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 29© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 30. Critical Relationships to Remember • Constant-value Dollars (Today’s dollars) • Future Dollars n future dollars Constant-Value dollars = (1+f) n Future dollars = today's dollars(1+f) . Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 30© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 31. Three Important Rates  Inflation-free interest rate. Denoted as “i”.  Inflation-adjusted interest rate. Denoted as “if”  Inflation rate. Denoted as “f”. 2) Adjusting interest rate to include inflation Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 1-31 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 32. Real or Inflation-free Interest Rate - i • Rate at which interest is earned. • Effects of any inflation have been removed. • Represents the actual or real gain received/charged on investments or borrowing. Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 32© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 33. Inflation-adjusted rate – if • The interest rate that has been adjusted to include inflation. • Common Term – – Market Interest Rate. – Interest rate adjusted for inflation. • The if rate is the combination of the real interest rate i, and the inflation rate f. • Also called the inflated interest rate. Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 33© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 34. Defining if • if is derived from f and i as follows: if = (i + f + if ) Or: 1 fi f i f   Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 34© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 35. Example • Assume i = 10%/ year; • f = 4% per year; • if is then calculated as: if = 0.10 + 0.04 + 0.10(0.04) = 0.144 = 14.4%/year Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 35© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 36. Which interest rate to use? • Either rate is correct when the correct dollar value is selected: Cash flow in Interest rate to use Today’s dollar (constant value) i Future dollars if Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 36© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 37. Example 14.1, Blank (6th ed.), page 477 Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 37© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 38. Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 38© 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 39. Effect of Inflation on the MARR When inflation is expected during the life of a project, the MARR needs to be increased to avoid accepting poor projects.  Inflated MARR = minimum acceptable rate of return when cash flows are in actual dollars (future dollars). If investors expect inflation, they require higher actual rates of return on their investments than if inflation were not expected.  Inflated MARR = real MARR (without inflation) + upwards adjustment which reflects the effect of inflation. So, following from the definition, we have: if = (i + f + if ) MARRinflated = MARRR + f + MARRR * f  where MARRinflated(if) is inflated MARR and MARRR (i) is real MARR (without inflation). Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 1-39 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 40. Abbott Mining Systems wants to determine whether it should buy now or buy later a piece of equipment used in deep mining operations. If the company selects plan N, the equipment will be purchased now for $200,000. However, if the company selects plan L, the purchase will be deferred for 3 years when the cost is expected to rise rapidly to $340,000. Abbott is ambitious; it expects a real MARR of 12% per year. The inflation rate in the country has averaged 6.75% per year. From only an economic perspective, determine whether the company should purchase now or later (a) when inflation is not considered and (b) when inflation is considered. Solution a) Inflation not considered: The real rate, or MARR, is i = 12% per year. The cost of plan L is $340,000 three years hence. Calculate the FW value for plan N three years from now: FWN = -200,000(F/P,12%,3) = $-280,986 FWL = $-340,000 Hence buy now Example 14.4, Blank (6th ed.), page 483: Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 1-40 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 41. b) Inflation considered: There is a real rate (12%), and inflation is 6.75%. First, compute the inflation-adjusted MARR : MARRf = 0.12 + 0.0675 + 0.12(0.0675) = 0.1956 Compute the FW value for plan N in future dollars. FWN = -200,000(F/P,19.56%,3) = $-341,812 FWL = $-340,000 Purchasing later is selected, because it requires fewer equivalent future dollars. The inflation rate of 6.75% per year has raised the equivalent future worth of costs by 21.6% to $341,812. Slide Sets to accompany Blank & Tarquin, Engineering Economy, 7th Edition, 2012 1-41 © 2012 by McGraw-Hill, New York, N.Y All Rights Reserved