Critical Path Method and Critical Chain Project Management

Project schedule plan is the main plan included in any Project Management Plan. Project schedule is
responsible for bringing project time, cost and quality under control. Project schedule links resources,
tasks and time line together. Once a Project Manager has list of resources, work breakdown structure
(WBS) and effort estimates, he is good to go for planning project schedule. Schedule network
analysis helps Project Manager to prevent undesirable risks involved in the project. Critical Path
Method (CPM) and Critical Chain Project Management (CCPM) are key elements of schedule network
analysis. In the following sections we will explore these elements in details to understand their
importance in keeping project on schedule to get increase in ROI.

Critical Path Method (CPM):

The Critical Path Method (CPM) is a schedule network analysis technique. CPM was developed by the
DuPont Corporation in 1957.Critical path determines the shortest time to complete the project and it
is the longest duration path through a network of tasks. Critical tasks (activities) are tasks (activities)
on the critical path.

To understand CPM further let's first understand nature of the task. According to PMBOK every
scheduled task can be defined by the following four parameters.
    • Early Start (ES): Earliest possible point in time on which a task can start.
    • Early Finish (EF): Earliest possible point in time on which a task can finish.
    • Late Start (ES): Latest possible point in time on which a task can start.
    • Late Finish (EF): Latest possible point in time on which a task can finish.

Early Start and finish dates are calculated by means of Forward Pass and Late Start and Late Finish
dates are calculated by means of Backward Pass.

Many Tasks have some amount of buffer added to them referred as Slack Time or Float. Float time is
amount of time a task can slip before it delays project schedule. There are two common types of
floats.
     • Free Float: Amount of time a single task can be delayed without delaying the early start of
        any successor task.
     • Total Float: Amount of time a single task can be delayed without delaying project completion.
Mathematically Float is defined as: Float = LS - ES or LF - EF.

Critical path has zero or negative Total Float. A project can have several critical paths.

CPM Example:
Critical Path = Task1+Task2+Task3+ Lag+ Task6 = 5+4+2+1+8 = 21 Days.

The Gantt chart representation of the same is given below.




Project Duration = Task1+Task2+Task3+ Lag+ Task6 = 5+4+2+1+8 = 21 Days.

CPM is   helpful in:
   •      Project Planning and control.
   •      Time-cost trade-offs.
   •      Cost-benefit analysis.
   •      Contingency planning.
   •      Reducing risk.

Limitations of CPM:
    • CPM assumes low uncertainty in schedule dates.
    • Does not consider resource dependencies.
    • Less efficient use of buffer time.
    • Less focus on non critical tasks that can cause risk.
    • Based on only deterministic task duration.
    • Critical Path can change during execution.

To overcome above limitations Critical Chain Project Management (CCPM) plays important role.

Critical Chain Project Management (CCPM):

According to PMBOK Critical chain method is a schedule network analysis technique that modifies the
project schedule to account for limited resources. It mixes deterministic and probabilistic approaches
to schedule network analysis. The critical chain concept was coined by Eliyahu Goldratt. Following
few sections briefly describe the concepts Critical Chain depends on and are useful to understand the
example that will follow shortly after that.

CCPM takes advantage of the best practices of:
-  PMBOK: Planning and control processes.
- TOC (Theory of Constraints): Remove bottleneck to resolve constraints.
- Lean: Eliminate waste.
- Six Sigma: Reduce Variations.

CCPM helps to overcome following phenomenon.
- Parkinson’s Law: Work expands to fill the available time.
- Student Syndrome: People start to work in full fledge only when deadline is near.
- Murphy's Law: What can go wrong will go wrong.
- Bad Multi Tasking: Bad multitasking can delay start of the successor tasks.
CCPM is based on:
- Resource constrained situations.
- Optimum use of Buffer (amount of time added to any task to prevent slippage of schedule)
       o Project Buffers (PB): Amount of buffer time at the end of the project.
       o Feeding Buffers (FB): Amount of buffer time at the end of a sequence of tasks.
       o Resource Buffers (RB): It is an alert that is used to indicate that resource is needed to
           perform a task. This alert can be set few days before a resource is actually needed.

CCPM Example:

We will consider the same example that was explained in section Critical Path Method Example.
CCPM can be applied using following three steps:

1. Remove safety time and reduce tasks durations by 50%.




Project Duration = Task1+Task2+Task3+ Task6 = 3+2+1+4 = 10 Days.

Note:
• All safety time durations are removed. For example 1 day lag after Task 2 and 4 days after Task5
   are removed.
• All tasks durations are reduced to half (50%). For example Task 1 is 3 Days instead of 6 days.

2. Create schedule on Late Finish dates and Remove resource constraints and identify critical chain.




Project Duration = Task1+Task2+Task5+ Task6 = 3+2+2+4 = 11 Days.

Note:
• Task3, Task4 and Task 5 are moved to start from Late Finish dates.
• Task2 and Task5 are to be done by resource R2 and so that aligned to remove resource
   constraints.
3. Add Project Buffer of 50% of the tasks duration and add Feeder buffer to non critical chain.




Project Duration = Task1+Task2+Task5+ Task6 + PB = 3+2+2+4+5 = 16 Days.

Note:
• Project Buffer (PB) = 50% of Project Duration (11 Days) = 5.5 Days = 5 Days (Rounded).
• Feeder Buffer (FB) for non critical tasks on chain. For example Task 4 is added 2 days FB.
• Buffer calculation is done by taking 50% of project duration for simple case and by Square root
   of the sum of the squares method (SSQ) for aggressive case.

Comparison of CPM and CCPM results:

According to the results we found above, project duration by CPM traditional approach is 21 days and
the project duration for the same amount of work by using CCPM is 16 Days.
Using CCPM:
• Project Duration can be reduced by 25-40%.
• Resources can be utilized effectively.
• Project is fully focused on both critical and non critical tasks

Implementation of CCPM:

CCPM is successfully implemented by US Navy, Lucent, NASA, US Air Force, Philips and many other
organizations.



                                                                                Umesh Dwivedi, PMP

Weitere ähnliche Inhalte

Was ist angesagt?

Project duration and staffing
Project duration and staffingProject duration and staffing
Project duration and staffing
siva R
 

Was ist angesagt? (20)

Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2
 
PM Session 5
PM Session 5PM Session 5
PM Session 5
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
 
Economics of project evaluation cpm module2
Economics of project evaluation cpm module2Economics of project evaluation cpm module2
Economics of project evaluation cpm module2
 
Project Management
Project ManagementProject Management
Project Management
 
Unit2 network optimization
Unit2 network optimizationUnit2 network optimization
Unit2 network optimization
 
Project duration and staffing
Project duration and staffingProject duration and staffing
Project duration and staffing
 
Presentation7
Presentation7Presentation7
Presentation7
 
Delay analysis of raw water reservoir and pumping Station
Delay analysis of raw water reservoir and pumping StationDelay analysis of raw water reservoir and pumping Station
Delay analysis of raw water reservoir and pumping Station
 
Pert and mbo
Pert and mboPert and mbo
Pert and mbo
 
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
 
Lecture 06 project_cost_management
Lecture 06 project_cost_managementLecture 06 project_cost_management
Lecture 06 project_cost_management
 
A New Approach for Job Scheduling Using Hybrid GA-ST Optimization-Crimson Pub...
A New Approach for Job Scheduling Using Hybrid GA-ST Optimization-Crimson Pub...A New Approach for Job Scheduling Using Hybrid GA-ST Optimization-Crimson Pub...
A New Approach for Job Scheduling Using Hybrid GA-ST Optimization-Crimson Pub...
 
Time and Projects
Time and ProjectsTime and Projects
Time and Projects
 
Chap 6 Developing A Project Plan
Chap 6 Developing A Project PlanChap 6 Developing A Project Plan
Chap 6 Developing A Project Plan
 
Program Evaluation And Review Technique
Program Evaluation And Review TechniqueProgram Evaluation And Review Technique
Program Evaluation And Review Technique
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 

Ähnlich wie Criticalchainprojectmanagement

PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docx
stilliegeorgiana
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gert
Raj J Das
 

Ähnlich wie Criticalchainprojectmanagement (20)

Software Project Scheduling Diagrams
Software Project Scheduling DiagramsSoftware Project Scheduling Diagrams
Software Project Scheduling Diagrams
 
Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...
 
PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docx
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
CPM By Junaid.pptx
CPM By Junaid.pptxCPM By Junaid.pptx
CPM By Junaid.pptx
 
Chap03
Chap03Chap03
Chap03
 
06 project time management
06  project time management06  project time management
06 project time management
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning Slides
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.ppt
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gert
 
Project time management
Project time managementProject time management
Project time management
 
Chapter 4.pptx
Chapter 4.pptxChapter 4.pptx
Chapter 4.pptx
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
Unit IV-Project Management
Unit IV-Project ManagementUnit IV-Project Management
Unit IV-Project Management
 
Traditional Management System.ppt
Traditional Management System.pptTraditional Management System.ppt
Traditional Management System.ppt
 
Chapter 5-Project Management.pptx
Chapter 5-Project Management.pptxChapter 5-Project Management.pptx
Chapter 5-Project Management.pptx
 
Chapter 07
Chapter 07Chapter 07
Chapter 07
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLS
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project Management
 
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For Beginners
 

Kürzlich hochgeladen

Call Girls Bellandur ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Call Girls Bellandur ☎ 7737669865☎ Book Your One night Stand (Bangalore)Call Girls Bellandur ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Call Girls Bellandur ☎ 7737669865☎ Book Your One night Stand (Bangalore)
amitlee9823
 
CHEAP Call Girls in Malviya Nagar, (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE
CHEAP Call Girls in  Malviya Nagar, (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICECHEAP Call Girls in  Malviya Nagar, (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE
CHEAP Call Girls in Malviya Nagar, (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Navsari Escorts Service ☎️ 6378878445 ( Sakshi Sinha ) High Profile Call Girl...
Navsari Escorts Service ☎️ 6378878445 ( Sakshi Sinha ) High Profile Call Girl...Navsari Escorts Service ☎️ 6378878445 ( Sakshi Sinha ) High Profile Call Girl...
Navsari Escorts Service ☎️ 6378878445 ( Sakshi Sinha ) High Profile Call Girl...
mriyagarg453
 

Kürzlich hochgeladen (20)

Call Girls Bellandur ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Call Girls Bellandur ☎ 7737669865☎ Book Your One night Stand (Bangalore)Call Girls Bellandur ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Call Girls Bellandur ☎ 7737669865☎ Book Your One night Stand (Bangalore)
 
Jodhpur Park ( Call Girls ) Kolkata ✔ 6297143586 ✔ Hot Model With Sexy Bhabi ...
Jodhpur Park ( Call Girls ) Kolkata ✔ 6297143586 ✔ Hot Model With Sexy Bhabi ...Jodhpur Park ( Call Girls ) Kolkata ✔ 6297143586 ✔ Hot Model With Sexy Bhabi ...
Jodhpur Park ( Call Girls ) Kolkata ✔ 6297143586 ✔ Hot Model With Sexy Bhabi ...
 
❤Personal Whatsapp Number Keylong Call Girls 8617697112 💦✅.
❤Personal Whatsapp Number Keylong Call Girls 8617697112 💦✅.❤Personal Whatsapp Number Keylong Call Girls 8617697112 💦✅.
❤Personal Whatsapp Number Keylong Call Girls 8617697112 💦✅.
 
(TOP CLASS) Call Girls In Nungambakkam Phone 7427069034 Call Girls Model With...
(TOP CLASS) Call Girls In Nungambakkam Phone 7427069034 Call Girls Model With...(TOP CLASS) Call Girls In Nungambakkam Phone 7427069034 Call Girls Model With...
(TOP CLASS) Call Girls In Nungambakkam Phone 7427069034 Call Girls Model With...
 
Hire 💕 8617697112 North Sikkim Call Girls Service Call Girls Agency
Hire 💕 8617697112 North Sikkim Call Girls Service Call Girls AgencyHire 💕 8617697112 North Sikkim Call Girls Service Call Girls Agency
Hire 💕 8617697112 North Sikkim Call Girls Service Call Girls Agency
 
CHEAP Call Girls in Malviya Nagar, (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE
CHEAP Call Girls in  Malviya Nagar, (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICECHEAP Call Girls in  Malviya Nagar, (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE
CHEAP Call Girls in Malviya Nagar, (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE
 
Ranikhet call girls 📞 8617697112 At Low Cost Cash Payment Booking
Ranikhet call girls 📞 8617697112 At Low Cost Cash Payment BookingRanikhet call girls 📞 8617697112 At Low Cost Cash Payment Booking
Ranikhet call girls 📞 8617697112 At Low Cost Cash Payment Booking
 
Model VVIP Call Girls In Porur 👉 Chennai 🍬 7427069034 Escort Service & Hotel ...
Model VVIP Call Girls In Porur 👉 Chennai 🍬 7427069034 Escort Service & Hotel ...Model VVIP Call Girls In Porur 👉 Chennai 🍬 7427069034 Escort Service & Hotel ...
Model VVIP Call Girls In Porur 👉 Chennai 🍬 7427069034 Escort Service & Hotel ...
 
Model Call Girls In Velappanchavadi WhatsApp Booking 7427069034 call girl ser...
Model Call Girls In Velappanchavadi WhatsApp Booking 7427069034 call girl ser...Model Call Girls In Velappanchavadi WhatsApp Booking 7427069034 call girl ser...
Model Call Girls In Velappanchavadi WhatsApp Booking 7427069034 call girl ser...
 
VIP Model Call Girls Vijayawada ( Pune ) Call ON 8005736733 Starting From 5K ...
VIP Model Call Girls Vijayawada ( Pune ) Call ON 8005736733 Starting From 5K ...VIP Model Call Girls Vijayawada ( Pune ) Call ON 8005736733 Starting From 5K ...
VIP Model Call Girls Vijayawada ( Pune ) Call ON 8005736733 Starting From 5K ...
 
Dum Dum ( Call Girls ) Kolkata ✔ 6297143586 ✔ Hot Model With Sexy Bhabi Ready...
Dum Dum ( Call Girls ) Kolkata ✔ 6297143586 ✔ Hot Model With Sexy Bhabi Ready...Dum Dum ( Call Girls ) Kolkata ✔ 6297143586 ✔ Hot Model With Sexy Bhabi Ready...
Dum Dum ( Call Girls ) Kolkata ✔ 6297143586 ✔ Hot Model With Sexy Bhabi Ready...
 
Navsari Escorts Service ☎️ 6378878445 ( Sakshi Sinha ) High Profile Call Girl...
Navsari Escorts Service ☎️ 6378878445 ( Sakshi Sinha ) High Profile Call Girl...Navsari Escorts Service ☎️ 6378878445 ( Sakshi Sinha ) High Profile Call Girl...
Navsari Escorts Service ☎️ 6378878445 ( Sakshi Sinha ) High Profile Call Girl...
 
Verified Trusted Call Girls Ambattur Chennai ✔✔7427069034 Independent Chenna...
Verified Trusted Call Girls Ambattur Chennai ✔✔7427069034  Independent Chenna...Verified Trusted Call Girls Ambattur Chennai ✔✔7427069034  Independent Chenna...
Verified Trusted Call Girls Ambattur Chennai ✔✔7427069034 Independent Chenna...
 
📞 Contact Number 8617697112 VIP East Sikkim Call Girls
📞 Contact Number 8617697112 VIP East Sikkim Call Girls📞 Contact Number 8617697112 VIP East Sikkim Call Girls
📞 Contact Number 8617697112 VIP East Sikkim Call Girls
 
𓀤Call On 6297143586 𓀤 Sonagachi Call Girls In All Kolkata 24/7 Provide Call W...
𓀤Call On 6297143586 𓀤 Sonagachi Call Girls In All Kolkata 24/7 Provide Call W...𓀤Call On 6297143586 𓀤 Sonagachi Call Girls In All Kolkata 24/7 Provide Call W...
𓀤Call On 6297143586 𓀤 Sonagachi Call Girls In All Kolkata 24/7 Provide Call W...
 
Model Call Girls In Ariyalur WhatsApp Booking 7427069034 call girl service 24...
Model Call Girls In Ariyalur WhatsApp Booking 7427069034 call girl service 24...Model Call Girls In Ariyalur WhatsApp Booking 7427069034 call girl service 24...
Model Call Girls In Ariyalur WhatsApp Booking 7427069034 call girl service 24...
 
WhatsApp Chat: 📞 8617697112 Hire Call Girls Raiganj For a Sensual Sex Experience
WhatsApp Chat: 📞 8617697112 Hire Call Girls Raiganj For a Sensual Sex ExperienceWhatsApp Chat: 📞 8617697112 Hire Call Girls Raiganj For a Sensual Sex Experience
WhatsApp Chat: 📞 8617697112 Hire Call Girls Raiganj For a Sensual Sex Experience
 
Thane West \ Escort Service in Mumbai - 450+ Call Girl Cash Payment 983332523...
Thane West \ Escort Service in Mumbai - 450+ Call Girl Cash Payment 983332523...Thane West \ Escort Service in Mumbai - 450+ Call Girl Cash Payment 983332523...
Thane West \ Escort Service in Mumbai - 450+ Call Girl Cash Payment 983332523...
 
Almora call girls 📞 8617697112 At Low Cost Cash Payment Booking
Almora call girls 📞 8617697112 At Low Cost Cash Payment BookingAlmora call girls 📞 8617697112 At Low Cost Cash Payment Booking
Almora call girls 📞 8617697112 At Low Cost Cash Payment Booking
 
Call Girls Bhandara Just Call 8617697112 Top Class Call Girl Service Available
Call Girls Bhandara Just Call 8617697112 Top Class Call Girl Service AvailableCall Girls Bhandara Just Call 8617697112 Top Class Call Girl Service Available
Call Girls Bhandara Just Call 8617697112 Top Class Call Girl Service Available
 

Criticalchainprojectmanagement

  • 1. Critical Path Method and Critical Chain Project Management Project schedule plan is the main plan included in any Project Management Plan. Project schedule is responsible for bringing project time, cost and quality under control. Project schedule links resources, tasks and time line together. Once a Project Manager has list of resources, work breakdown structure (WBS) and effort estimates, he is good to go for planning project schedule. Schedule network analysis helps Project Manager to prevent undesirable risks involved in the project. Critical Path Method (CPM) and Critical Chain Project Management (CCPM) are key elements of schedule network analysis. In the following sections we will explore these elements in details to understand their importance in keeping project on schedule to get increase in ROI. Critical Path Method (CPM): The Critical Path Method (CPM) is a schedule network analysis technique. CPM was developed by the DuPont Corporation in 1957.Critical path determines the shortest time to complete the project and it is the longest duration path through a network of tasks. Critical tasks (activities) are tasks (activities) on the critical path. To understand CPM further let's first understand nature of the task. According to PMBOK every scheduled task can be defined by the following four parameters. • Early Start (ES): Earliest possible point in time on which a task can start. • Early Finish (EF): Earliest possible point in time on which a task can finish. • Late Start (ES): Latest possible point in time on which a task can start. • Late Finish (EF): Latest possible point in time on which a task can finish. Early Start and finish dates are calculated by means of Forward Pass and Late Start and Late Finish dates are calculated by means of Backward Pass. Many Tasks have some amount of buffer added to them referred as Slack Time or Float. Float time is amount of time a task can slip before it delays project schedule. There are two common types of floats. • Free Float: Amount of time a single task can be delayed without delaying the early start of any successor task. • Total Float: Amount of time a single task can be delayed without delaying project completion. Mathematically Float is defined as: Float = LS - ES or LF - EF. Critical path has zero or negative Total Float. A project can have several critical paths. CPM Example:
  • 2. Critical Path = Task1+Task2+Task3+ Lag+ Task6 = 5+4+2+1+8 = 21 Days. The Gantt chart representation of the same is given below. Project Duration = Task1+Task2+Task3+ Lag+ Task6 = 5+4+2+1+8 = 21 Days. CPM is helpful in: • Project Planning and control. • Time-cost trade-offs. • Cost-benefit analysis. • Contingency planning. • Reducing risk. Limitations of CPM: • CPM assumes low uncertainty in schedule dates. • Does not consider resource dependencies. • Less efficient use of buffer time. • Less focus on non critical tasks that can cause risk. • Based on only deterministic task duration. • Critical Path can change during execution. To overcome above limitations Critical Chain Project Management (CCPM) plays important role. Critical Chain Project Management (CCPM): According to PMBOK Critical chain method is a schedule network analysis technique that modifies the project schedule to account for limited resources. It mixes deterministic and probabilistic approaches to schedule network analysis. The critical chain concept was coined by Eliyahu Goldratt. Following few sections briefly describe the concepts Critical Chain depends on and are useful to understand the example that will follow shortly after that. CCPM takes advantage of the best practices of: - PMBOK: Planning and control processes. - TOC (Theory of Constraints): Remove bottleneck to resolve constraints. - Lean: Eliminate waste. - Six Sigma: Reduce Variations. CCPM helps to overcome following phenomenon. - Parkinson’s Law: Work expands to fill the available time. - Student Syndrome: People start to work in full fledge only when deadline is near. - Murphy's Law: What can go wrong will go wrong. - Bad Multi Tasking: Bad multitasking can delay start of the successor tasks.
  • 3. CCPM is based on: - Resource constrained situations. - Optimum use of Buffer (amount of time added to any task to prevent slippage of schedule) o Project Buffers (PB): Amount of buffer time at the end of the project. o Feeding Buffers (FB): Amount of buffer time at the end of a sequence of tasks. o Resource Buffers (RB): It is an alert that is used to indicate that resource is needed to perform a task. This alert can be set few days before a resource is actually needed. CCPM Example: We will consider the same example that was explained in section Critical Path Method Example. CCPM can be applied using following three steps: 1. Remove safety time and reduce tasks durations by 50%. Project Duration = Task1+Task2+Task3+ Task6 = 3+2+1+4 = 10 Days. Note: • All safety time durations are removed. For example 1 day lag after Task 2 and 4 days after Task5 are removed. • All tasks durations are reduced to half (50%). For example Task 1 is 3 Days instead of 6 days. 2. Create schedule on Late Finish dates and Remove resource constraints and identify critical chain. Project Duration = Task1+Task2+Task5+ Task6 = 3+2+2+4 = 11 Days. Note: • Task3, Task4 and Task 5 are moved to start from Late Finish dates. • Task2 and Task5 are to be done by resource R2 and so that aligned to remove resource constraints.
  • 4. 3. Add Project Buffer of 50% of the tasks duration and add Feeder buffer to non critical chain. Project Duration = Task1+Task2+Task5+ Task6 + PB = 3+2+2+4+5 = 16 Days. Note: • Project Buffer (PB) = 50% of Project Duration (11 Days) = 5.5 Days = 5 Days (Rounded). • Feeder Buffer (FB) for non critical tasks on chain. For example Task 4 is added 2 days FB. • Buffer calculation is done by taking 50% of project duration for simple case and by Square root of the sum of the squares method (SSQ) for aggressive case. Comparison of CPM and CCPM results: According to the results we found above, project duration by CPM traditional approach is 21 days and the project duration for the same amount of work by using CCPM is 16 Days. Using CCPM: • Project Duration can be reduced by 25-40%. • Resources can be utilized effectively. • Project is fully focused on both critical and non critical tasks Implementation of CCPM: CCPM is successfully implemented by US Navy, Lucent, NASA, US Air Force, Philips and many other organizations. Umesh Dwivedi, PMP