Kalyani Kadam
SITE REPORT
Page 0 of 21
SITE REPORT
PEBBLES II
ABSTRACT
This report highlights the construction
practices and different methods of
managing the construction site of a
residential building as observed in this
visit.
Kalyani Kadam
CPM
Kalyani Kadam
SITE REPORT
Page 1 of 21
Name of project: Pebbles II
Name of the construction firm: Abhinav Group and Rainbow Housing Developers
Vice-president: Mr Santosh Runwall
Location: Bavdhan Budruk, Pune
Date of Visit: 22nd September 2014
Date of commencement: 22nd September 2012
Date of completion: June 2015
Type of project: Multi-storey residential buildings
INTRODUCTION
Pebbles II residential project is started after the enormous success of Pebbles I,
by the same developer in 2012. These ultra-luxurious flats are designed and
constructed keeping quality and finesse in mind. This project by the Abhinav Group and
Rainbow Housing Developers, in Joint Venture, is constructed with the aim of making it
an eco-friendly project. The developers are accredited with the Adarsh Griha
certificate for environment-friendly construction.
The project estimation is around 600 crore INR.
The construction cost is 2500 INR/ sq.ft – 3000 INR/ sq.ft.
The selling price is currently 6200 INR/ sq. ft.
Kalyani Kadam
SITE REPORT
Page 2 of 21
Fig. 1: Layout of project.
Kalyani Kadam
SITE REPORT
Page 3 of 21
Fig. 2: Location of site
SITE LAYOUT
The plot is spread over an area of 6 lac sq.ft in Bavdhan Budruk, which falls under the
town planning zone of Pune. The actual constructed area covers 3 lac sq.ft with 816
flats of type 2bhk and 3bhk.
The site is located near the NH4 highway (Mumbai-Bangalore) providing easy
accessibility.
A sample layout of the site is shown below with markings showing the components at
the site.
Kalyani Kadam
SITE REPORT
Page 4 of 21
Fig. 3: Site layout.
SALIENT FEATURES
1. TOPOGRAPHY:
 The location of the site was close to a moderately hilly region having high
ground water table.
 The land surface is undulated with expansive black soil dominant in this
region.
 Site is in close proximity to pre-existing buildings and National Highway 4.
2. EXCAVATION:
 Excavation was carried out with the help of excavators.
 We observed an area excavated for construction of club house.
 1m offset was marked around the excavated zone to facilitate easy
movement of the machinery around the periphery.
 The excavated soil was carried by dumpers for dumping and de-watering of
the excavated part was undertaken with the help of pumps.
Kalyani Kadam
SITE REPORT
Page 5 of 21
3. LABOUR CAMP:
 Labour camp was provided close to the site compound wall for easy access to
site.
 There were in all 700 labours in the camped area whereas 150 labours were
in function on the site.
 The labours carried out work as per the regional speciality, viz:
Concreting: Malda labours (West Bengal)
Tiling: Rajasthani labours
Reinforcing: Maharashtrian labours
Shuttering: Uttar Pradesh and West Bengal
Levelling: Andhra Pradesh
 The labour camp was divided in 3 prominent sections, i.e. hutments,
provisional stores and sanitation facility.
 The site also provided school and crèche facility to the children and toddlers,
with 3 teachers to take care of the necessary educational requirement of
the 60 children.
 A storage tank is provided for potable water around the periphery of the
camp.
4. STORES:
 Stores were located in the building vicinity to enable easy transport of
materials.
 The store kept a book record of the quantities provided for construction and
procured additional materials required.
 It also housed a Compression testing machine to test the Concrete Block
Strength on site apart from the third party testing which is carried out by
Durecrite.
 It stored Cement blocks, Tiles, Sanitary fixtures, Pump parts, Granite slabs,
pipes, plumbing accessories, lighting fixtures etc.
Kalyani Kadam
SITE REPORT
Page 6 of 21
Fig. 4: Labelling concrete blocks for Testing.
5. BAR BENDING YARDS:
 Bar bending yard was located near the entrance to the buildings, facilitating
prompt delivery of reinforcement on site.
 Bar bending was carried out manually by labours.
 The bars after cutting were laid separately as per their shape, thus
increasing efficiency.
Fig. 5: Bar bending yard.
Kalyani Kadam
SITE REPORT
Page 7 of 21
6. PLANT AND MACHINERY:
 Plant and machinery were involved on a large scale in the construction of this
project, making the project as of whole cost-effective.
 Detachable Tower Cranes were employed for building construction.
 Excavators, dumpers and dozers were also employed.
 Maintenance of the machinery was taken care of by the Maintenance
Engineer.
7. BATCHING PLANT:
A batching plant is an equipment used to mix the different components of concrete to
produce a desired grade of concrete.
 A batching plant with 2 silos for cement and fly ash was located on site.
 The coarse and fine aggregate was laid around the mixer for easy filling.
 Water was directly pumped in the mixer by a pump and hose.
Fig. 6: Cement & Fly ash silo in Batching Plant.
 The automated plant was operated by a Mechanical Operator, by feeding the
inputs as per the given combination to achieve a uniform mix.
 The capacity of the mixer was 0.35m3.
 The discharge rate of plant is 12 m3 per hour.
Kalyani Kadam
SITE REPORT
Page 8 of 21
Fig. 7: Concrete mixer in Batching Plant.
 The freshly produced concrete was then pumped at the desired spot.
 Cement slurry is passed through the pipe prior to concreting to wet the inner
section of pipe to, thus avoiding obstruction.
 The concreting pipe was cleaned with the help of high speed water jets and
passing a ball to clear the residual concrete in the pipe.
8. WATER AND POWER SUPPLY:
 Taking advantage of the high water table and undulated hilly area, an
artificial reservoir is constructed close to the site.
 This work was undertaken to fulfil two objectives, namely:
a. Raising the ground water table
b. Providing water for construction activities
 Water from the artificial reservoir is pumped onsite, helping to reduce the
load on local water supply.
 Power is obtained from MSEB (Maharashtra State Electricity Board),
through transformers installed on site, for operating machines.
 An additional diesel generator backup is provided for emergency power
generation.
 The construction activities are so planned to avoid wastage of water and
power.
Kalyani Kadam
SITE REPORT
Page 9 of 21
9. FOUNDATION:
 Hard strata was found at a shallow depth ranging from 2m to 4m.
 Owing to this shallow depth, box footing is provided to the structure instead
of raft footing.
 Since the depth of the hard strata varied between 2m to 4m, depth of footing
was changed accordingly.
 Concrete of grade M30 was used for construction of footing.
10.SCAFFOLDING AND SHUTTERING:
 Bamboo scaffolds were primarily used for scaffolding and tied with binding
wires.
 Wooden ply boards, horizontal and vertical planks and metal props were
used for shuttering.
 The extendable vertical props can be extended up to a height of 4m.
 Horizontal distance between two successive props was 2ft centre-to-centre.
 To reduce the number of vertical props, GI span sections were laid
horizontally at beam sections.
 For columns, the shuttering was provided with inclined extendable metal
struts, anchored to the ground with a bolted base plate.
 To hold the shuttering in place and retain the shape C-clamps were also used.
Fig. 8: Bamboo scaffolding and shuttering.
Kalyani Kadam
SITE REPORT
Page 10 of 21
11.CONCRETING:
Concreting is the process of producing concrete by preparing a uniform homogenous
mixture of cement, crushed sand, aggregates, water and admixture.
 Concrete of grade M20 and M30 were produced for suitable sections.
 Slabs and beams were cast monolithically using M20 grade of concrete.
 For columns, M30 grade of concrete was produced.
 For basement, parking, podium and slab sections concrete pumping was
employed.
 For column sections, concreting was done manually.
 Vibrators were used for proper consolidation of concrete and to avoid
segregation and bleeding.
Fig. 9: Representative picture displaying Pump Concreting.
 Concrete blocks were cast and tested periodically for strength parameters.
 For walls and partitions AAC blocks (Autoclaved Aerated Concrete) were
used due to the following advantages:
a. Light weight
b. Less consumptions of power during production
c. Reduced amount of water for curing
d. Heat refractor
e. High strength
f. Less amount of sealant used to fill the joints, hence economical
g. Easy to place and skilled labour not required
 Size of AAC block was 300mm*225mm*150mm and
600mm*225mm*150mm.
Kalyani Kadam
SITE REPORT
Page 11 of 21
Fig. 10: AAC block wall.
12.DRAINAGE AND UTILITY LINE:
 Trenches were excavated with the help of backhoe to lay the drainage and
electricity lines.
 These trenches were rectangular in section and laid with asbestos pipes to
carry sewage.
 These pipelines connected the sewage pipes to the city sewage system.
 Power lines, encased in PVC pipes, were also laid underground along with
water supply lines.
Kalyani Kadam
SITE REPORT
Page 12 of 21
Fig. 11: Representative picture showing Trench Digging.
13.PARKING AND BASEMENT:
 2 storey parking facility is provided, which included basement parking and
podium parking.
 The pavement for the basement parking was 200mm thick tremix concrete
with underlying wire mesh to provide additional support.
 This pavement layer after laying was lined with a wire brush to avoid
skidding of vehicles.
 A 3m high retaining wall is constructed in the basement parking, prior to
construction of super structure, to counteract the horizontal earth
pressure.
Kalyani Kadam
SITE REPORT
Page 13 of 21
Fig. 12: Podium & basement parking.
 Lighting facility in the basement parking section is an innovative example to
reduce power consumption.
 Hollow vertical ducts up to 1m height were erected on the podium and
covered with light refracting material on the under-side.
 This mechanism allowed ample lighting during day, while only using artificial
lights at night.
Kalyani Kadam
SITE REPORT
Page 14 of 21
Fig. 13: Hollow vertical ducts.
Fig. 14: Solar refracting Lights.
14.FINISHING:
 Wall finishing in the building was done using Gypsum plaster instead of
Plaster due to its heat resistant property and it gives a gloss finish.
 A 15mm thick Gypsum layer is applied after which 2 coats of paint is applied
on the wall.
 Master bedroom was provided with Wooden flooring with interlocking
segments.
 Kitchen was furnished with Hafele gas burners and chimney.
 Large windows and balcony were provided for better ventilation and
lighting.
 The flights up to 1st floor were provided with Saddar Ali Granite.
 Provision was made on the stair edge similar to skirting to avoid water
spillage during cleaning.
 External finishing consisted of 15 mm thick 1st coat of Gypsum followed by
5mm thick Gypsum plaster.
 Later a coat of paint is applied on the prepared surface.
Kalyani Kadam
SITE REPORT
Page 15 of 21
Fig. 15: Sample flat with finishing work completed.
15.ELECTRICAL AND PLUMBING FIXTURES:
 Electrical and plumbing fixtures were carried out in 4 stages:
a. Provision for conduits prior to concreting
b. Outlet is provided to fix electric points
c. After the completion of construction wires are passed through
conduits
d. Fixing of switches and distribution board and meter boards
 Switches were provided at standard heights of 2ft and 4ft.
 Legrand switches were used.
 Provision for foot lamps was also made.
 The entire plumbing system was concealed and fixtures were provided at 2ft
and 4ft height.
Kalyani Kadam
SITE REPORT
Page 16 of 21
16.FIRE FIGHTING SYSTEMS:
 Each floor was equipped with fire fighting equipment such as water hose
connected to water tank and fire extinguisher.
 Parking in the basement was covered with a web of Main and Intermediary
pipes carrying water and connected to a sprinkler mechanism.
 Fire exit doors were provided in the buildings to enable safe exit of residents.
 Smoke detectors were provided throughout the building structure, to detect
smoke and take preventive action.
 The sprinklers would be activated, when a smoke detector sounds an alarm.
17.GARBAGE DUMPING:
 Outlet chutes were provided in the corridor of every floor.
 These chutes pass the garbage to the movable collection bin, which transfers
it to the local garbage collection bodies.
18. ELEVATORS:
 2 elevators were provided in each building.
 One was reserved for general use.
 The other elevator is for maids, maintenance and carrying heavy
equipment.
19.WATER STORAGE AND SEWAGE TREATMENT PLANT (STP):
 The water storage tank is constructed below the basement parking.
 Covers an area of 32m*22m and depth of 3.5m.
 Its storage capacity is 25 million litres.
 The water is supplied to the storage tank from an auxiliary tank, by force of
gravity.
 Sewage treatment plant (STP) is provided under the basement to treat
sewage from household activities, and recycle the water.
 The capacity of STP tank to process, is 665 m3 per day.
 This treated water is used for cleaning vehicles, gardening and flushing in
toilets.
Kalyani Kadam
SITE REPORT
Page 17 of 21
Fig. 16: Sewage Treatment Plant (STP).
20.QUALITY:
 Quality of work during construction was stringently maintained by periodic
tests.
 The finishing of the flats was done as per required specifications.
 Some of the specifications are:
a. 800 mm x 800 mm vitrified tiles in entire flat.
b. Toto bathroom and sanitary fixtures.
c. Powder coated windows.
d. Designer 7 feet high entrance door.
e. Laminated internal doors.
f. Security system.
g. Glass partition in master bedroom
h. S. S railing and toughened glass in terrace.
Kalyani Kadam
SITE REPORT
Page 18 of 21
Fig. 17: Kitchen with Hafele fitting.
Fig. 18: S. S railing & Toughened glass.
Kalyani Kadam
SITE REPORT
Page 19 of 21
21.SAFETY:
 Workers were using helmets and harnesses while working at heights.
 Safety nets were provided at the under-constructed floor to restrict the
debris from falling.
 Labours involved in concreting used gumboots and gloves.
 Lift well were provided with barricade.
 Fire extinguishers were present on site to counter any outbreak of fire.
Fig. 19: Safety net provision.
22.AMENITIES:
 A club house with fully equipped gymnasium and swimming pool is
provided around the building.
 Landscaped gardens, lawns and rock garden covered the open spaces with
provision for rest areas.
 Multi-purpose court, jogging track and net practice cricket pitch is to be
constructed for healthy living.
 An amphitheatre and banquet hall is provided for entertainment purpose.
 An old age home facility will also be provided for elderly.
Kalyani Kadam
SITE REPORT
Page 20 of 21
Fig. 20: Swimming pool for kids & adults.
Fig. 21: Open garden & elevated walkways.
Fig. 22: Fully equipped Gym.
Kalyani Kadam
SITE REPORT
Page 21 of 21
23.PURCHASING:
 Material requirement is calculated on the basis of tender document that is
item specifications tender drawings and the purchase requisition is prepared.
 The sample of each material is approved from authorised architect and
client. After the approval of sample the quotations are called from approved
list of suppliers or vendors.
 After receiving quotations from vendors, the final negotiations from the
contractors are called along with checking their capability of in-time supply
and credit limit.
 Finally, a comparative statement is prepared to select lowest quotation with
mode of payment.
 The material is ordered by issuing purchase order including all
requirements, specifications, rate and taxation if any.
 It includes mode of transportation, loading and unloading charges, octroi
charges in municipal corporation area, VAT and other applicable government
taxes.
24.CREDITS:
 Architect: Abhikalpan Architects and Planners
 RCC: Hansal Parikh and Associate Structural Consultants
 Landscape: Designterra Landscape Consultants
 Liaison Architect: Gohad Architects
 Interior: Pranali Shende
CONCLUSION:
The visit enabled us to experience construction practices adopted on site,
all the while maintaining quality and standards. The use of innovative techniques
and installation of STP, makes the project economical and environmentally
beneficial. Efficient use of machinery, saved cost and aids in maintaining the
progress of construction activities.

Weitere ähnliche Inhalte

Was ist angesagt?

industrial training report
industrial training reportindustrial training report
industrial training reportdavid minja
 
Glass Fibre Reinforced Gypsum Panels By Raijul Islam
Glass Fibre Reinforced Gypsum Panels By Raijul IslamGlass Fibre Reinforced Gypsum Panels By Raijul Islam
Glass Fibre Reinforced Gypsum Panels By Raijul IslamMd Raijul Islam
 
Summer Training Report On Bituminous (Asphalt) Road
Summer Training Report On Bituminous (Asphalt) RoadSummer Training Report On Bituminous (Asphalt) Road
Summer Training Report On Bituminous (Asphalt) Roadshashanksingh593
 
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESHPRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESHImrul Quesh
 
Anshul pwd training report
Anshul pwd training reportAnshul pwd training report
Anshul pwd training reportAnshul Shakya
 
Sachin gupta summer training in pwd
Sachin gupta summer training in pwdSachin gupta summer training in pwd
Sachin gupta summer training in pwdSachin gupta
 
MANUFACTURE OF INTERLOCKING CONCRETE PAVING BLOCKS WITH FLY ASH AND GLASS POWDER
MANUFACTURE OF INTERLOCKING CONCRETE PAVING BLOCKS WITH FLY ASH AND GLASS POWDERMANUFACTURE OF INTERLOCKING CONCRETE PAVING BLOCKS WITH FLY ASH AND GLASS POWDER
MANUFACTURE OF INTERLOCKING CONCRETE PAVING BLOCKS WITH FLY ASH AND GLASS POWDERIAEME Publication
 
Design of rigit pavement
Design of rigit pavementDesign of rigit pavement
Design of rigit pavementTAHIR HUSEN
 
Rmc plant
Rmc plantRmc plant
Rmc plantKp Ahm
 
Current Methods in Road and Highway Construction
Current Methods in Road and Highway ConstructionCurrent Methods in Road and Highway Construction
Current Methods in Road and Highway ConstructionKathleenOrr67
 
widening of flexible pavement AND construction of drainage system
widening of flexible pavement AND construction of drainage systemwidening of flexible pavement AND construction of drainage system
widening of flexible pavement AND construction of drainage systemeakram akhtar
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concreteMylene Delmoro
 
ROAD REPAIR CIVIL ENGINEERING
ROAD REPAIR CIVIL ENGINEERINGROAD REPAIR CIVIL ENGINEERING
ROAD REPAIR CIVIL ENGINEERINGRanBir ShaRma
 
Georesources Journal 3-2018 - Maccaferri Article
Georesources Journal 3-2018 - Maccaferri ArticleGeoresources Journal 3-2018 - Maccaferri Article
Georesources Journal 3-2018 - Maccaferri ArticleMaccaferri World
 

Was ist angesagt? (20)

FINAL REPORT
FINAL REPORTFINAL REPORT
FINAL REPORT
 
Bituminous Road
 Bituminous Road Bituminous Road
Bituminous Road
 
industrial training report
industrial training reportindustrial training report
industrial training report
 
Glass Fibre Reinforced Gypsum Panels By Raijul Islam
Glass Fibre Reinforced Gypsum Panels By Raijul IslamGlass Fibre Reinforced Gypsum Panels By Raijul Islam
Glass Fibre Reinforced Gypsum Panels By Raijul Islam
 
Summer Training Report On Bituminous (Asphalt) Road
Summer Training Report On Bituminous (Asphalt) RoadSummer Training Report On Bituminous (Asphalt) Road
Summer Training Report On Bituminous (Asphalt) Road
 
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESHPRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
 
Anshul pwd training report
Anshul pwd training reportAnshul pwd training report
Anshul pwd training report
 
Sachin gupta summer training in pwd
Sachin gupta summer training in pwdSachin gupta summer training in pwd
Sachin gupta summer training in pwd
 
MANUFACTURE OF INTERLOCKING CONCRETE PAVING BLOCKS WITH FLY ASH AND GLASS POWDER
MANUFACTURE OF INTERLOCKING CONCRETE PAVING BLOCKS WITH FLY ASH AND GLASS POWDERMANUFACTURE OF INTERLOCKING CONCRETE PAVING BLOCKS WITH FLY ASH AND GLASS POWDER
MANUFACTURE OF INTERLOCKING CONCRETE PAVING BLOCKS WITH FLY ASH AND GLASS POWDER
 
Design of rigit pavement
Design of rigit pavementDesign of rigit pavement
Design of rigit pavement
 
Rmc plant
Rmc plantRmc plant
Rmc plant
 
Current Methods in Road and Highway Construction
Current Methods in Road and Highway ConstructionCurrent Methods in Road and Highway Construction
Current Methods in Road and Highway Construction
 
Unit 2
Unit 2Unit 2
Unit 2
 
Road construction
Road constructionRoad construction
Road construction
 
Unit 3
Unit 3Unit 3
Unit 3
 
widening of flexible pavement AND construction of drainage system
widening of flexible pavement AND construction of drainage systemwidening of flexible pavement AND construction of drainage system
widening of flexible pavement AND construction of drainage system
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concrete
 
Flexible pavement
Flexible pavementFlexible pavement
Flexible pavement
 
ROAD REPAIR CIVIL ENGINEERING
ROAD REPAIR CIVIL ENGINEERINGROAD REPAIR CIVIL ENGINEERING
ROAD REPAIR CIVIL ENGINEERING
 
Georesources Journal 3-2018 - Maccaferri Article
Georesources Journal 3-2018 - Maccaferri ArticleGeoresources Journal 3-2018 - Maccaferri Article
Georesources Journal 3-2018 - Maccaferri Article
 

Andere mochten auch (16)

1ST
1ST1ST
1ST
 
MY CERT
MY CERTMY CERT
MY CERT
 
Lưu dưới dạng file tự chạy.gif
Lưu dưới dạng file tự chạy.gifLưu dưới dạng file tự chạy.gif
Lưu dưới dạng file tự chạy.gif
 
mohammad arslan cv
mohammad arslan cvmohammad arslan cv
mohammad arslan cv
 
Beretta presentazione2
Beretta presentazione2Beretta presentazione2
Beretta presentazione2
 
Nassouri- bio
Nassouri- bioNassouri- bio
Nassouri- bio
 
Ppt chf maju fix
Ppt chf maju fixPpt chf maju fix
Ppt chf maju fix
 
3.3.33
3.3.333.3.33
3.3.33
 
Organizational communication & information technology
Organizational communication & information technologyOrganizational communication & information technology
Organizational communication & information technology
 
BACE1 inhibitor
BACE1 inhibitorBACE1 inhibitor
BACE1 inhibitor
 
Amerika, 6.r
Amerika, 6.rAmerika, 6.r
Amerika, 6.r
 
Motor coach
Motor coachMotor coach
Motor coach
 
Horus Technology
Horus TechnologyHorus Technology
Horus Technology
 
Deforestation
DeforestationDeforestation
Deforestation
 
Mesopotamia
MesopotamiaMesopotamia
Mesopotamia
 
understanding vegetables&Salad
 understanding vegetables&Salad understanding vegetables&Salad
understanding vegetables&Salad
 

Ähnlich wie Pebbles II site report

civil enginnering industrial training report
civil enginnering industrial training report civil enginnering industrial training report
civil enginnering industrial training report KRISHNA MURARI
 
civil enginnering industrial training report
civil enginnering industrial training report civil enginnering industrial training report
civil enginnering industrial training report KRISHNA MURARI
 
Chhabra Thermal Power plant ppt by Cm lodha
Chhabra Thermal Power plant ppt by Cm lodhaChhabra Thermal Power plant ppt by Cm lodha
Chhabra Thermal Power plant ppt by Cm lodhaChandra Mohan Lodha
 
internship ppt.pptx civil engineering institute
internship ppt.pptx civil engineering instituteinternship ppt.pptx civil engineering institute
internship ppt.pptx civil engineering instituteSrikanthReddy345872
 
31_SHRUTIGARG_BC_GROUPREPORT.pdf
31_SHRUTIGARG_BC_GROUPREPORT.pdf31_SHRUTIGARG_BC_GROUPREPORT.pdf
31_SHRUTIGARG_BC_GROUPREPORT.pdfShrutiGarg261479
 
Slope Stability Measure For Basement Excavation, A Case Study on Office Build...
Slope Stability Measure For Basement Excavation, A Case Study on Office Build...Slope Stability Measure For Basement Excavation, A Case Study on Office Build...
Slope Stability Measure For Basement Excavation, A Case Study on Office Build...Andy Sugianto
 
Construction site
Construction siteConstruction site
Construction siteTimun Loh
 
Dda training presentation
Dda training presentationDda training presentation
Dda training presentationAKASHGARG131
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxPraveendubey82
 
Bridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara SetuBridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara SetuVishweshwar Rao Narla
 
Construction of gravity dam by M.R.S
Construction of gravity dam by M.R.SConstruction of gravity dam by M.R.S
Construction of gravity dam by M.R.SMD RAHEL SK
 
The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)Adib Ramli
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sectionsjuwes
 
IRJET- Roughness Coefficient of Alkali Activated Mineral based Concrete C...
IRJET-  	  Roughness Coefficient of Alkali Activated Mineral based Concrete C...IRJET-  	  Roughness Coefficient of Alkali Activated Mineral based Concrete C...
IRJET- Roughness Coefficient of Alkali Activated Mineral based Concrete C...IRJET Journal
 

Ähnlich wie Pebbles II site report (20)

Grouting
Grouting Grouting
Grouting
 
JEEVA.pptx
JEEVA.pptxJEEVA.pptx
JEEVA.pptx
 
civil enginnering industrial training report
civil enginnering industrial training report civil enginnering industrial training report
civil enginnering industrial training report
 
civil enginnering industrial training report
civil enginnering industrial training report civil enginnering industrial training report
civil enginnering industrial training report
 
Chhabra Thermal Power plant ppt by Cm lodha
Chhabra Thermal Power plant ppt by Cm lodhaChhabra Thermal Power plant ppt by Cm lodha
Chhabra Thermal Power plant ppt by Cm lodha
 
internship ppt.pptx civil engineering institute
internship ppt.pptx civil engineering instituteinternship ppt.pptx civil engineering institute
internship ppt.pptx civil engineering institute
 
31_SHRUTIGARG_BC_GROUPREPORT.pdf
31_SHRUTIGARG_BC_GROUPREPORT.pdf31_SHRUTIGARG_BC_GROUPREPORT.pdf
31_SHRUTIGARG_BC_GROUPREPORT.pdf
 
Slope Stability Measure For Basement Excavation, A Case Study on Office Build...
Slope Stability Measure For Basement Excavation, A Case Study on Office Build...Slope Stability Measure For Basement Excavation, A Case Study on Office Build...
Slope Stability Measure For Basement Excavation, A Case Study on Office Build...
 
Construction site
Construction siteConstruction site
Construction site
 
Dda training presentation
Dda training presentationDda training presentation
Dda training presentation
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptx
 
training report LMRC
training report LMRCtraining report LMRC
training report LMRC
 
Bridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara SetuBridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara Setu
 
Ppt of design of dams
Ppt of design of damsPpt of design of dams
Ppt of design of dams
 
Construction of gravity dam by M.R.S
Construction of gravity dam by M.R.SConstruction of gravity dam by M.R.S
Construction of gravity dam by M.R.S
 
training1 (1).pptx
training1 (1).pptxtraining1 (1).pptx
training1 (1).pptx
 
Flyover construction
Flyover constructionFlyover construction
Flyover construction
 
The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sections
 
IRJET- Roughness Coefficient of Alkali Activated Mineral based Concrete C...
IRJET-  	  Roughness Coefficient of Alkali Activated Mineral based Concrete C...IRJET-  	  Roughness Coefficient of Alkali Activated Mineral based Concrete C...
IRJET- Roughness Coefficient of Alkali Activated Mineral based Concrete C...
 

Pebbles II site report

  • 1. Kalyani Kadam SITE REPORT Page 0 of 21 SITE REPORT PEBBLES II ABSTRACT This report highlights the construction practices and different methods of managing the construction site of a residential building as observed in this visit. Kalyani Kadam CPM
  • 2. Kalyani Kadam SITE REPORT Page 1 of 21 Name of project: Pebbles II Name of the construction firm: Abhinav Group and Rainbow Housing Developers Vice-president: Mr Santosh Runwall Location: Bavdhan Budruk, Pune Date of Visit: 22nd September 2014 Date of commencement: 22nd September 2012 Date of completion: June 2015 Type of project: Multi-storey residential buildings INTRODUCTION Pebbles II residential project is started after the enormous success of Pebbles I, by the same developer in 2012. These ultra-luxurious flats are designed and constructed keeping quality and finesse in mind. This project by the Abhinav Group and Rainbow Housing Developers, in Joint Venture, is constructed with the aim of making it an eco-friendly project. The developers are accredited with the Adarsh Griha certificate for environment-friendly construction. The project estimation is around 600 crore INR. The construction cost is 2500 INR/ sq.ft – 3000 INR/ sq.ft. The selling price is currently 6200 INR/ sq. ft.
  • 3. Kalyani Kadam SITE REPORT Page 2 of 21 Fig. 1: Layout of project.
  • 4. Kalyani Kadam SITE REPORT Page 3 of 21 Fig. 2: Location of site SITE LAYOUT The plot is spread over an area of 6 lac sq.ft in Bavdhan Budruk, which falls under the town planning zone of Pune. The actual constructed area covers 3 lac sq.ft with 816 flats of type 2bhk and 3bhk. The site is located near the NH4 highway (Mumbai-Bangalore) providing easy accessibility. A sample layout of the site is shown below with markings showing the components at the site.
  • 5. Kalyani Kadam SITE REPORT Page 4 of 21 Fig. 3: Site layout. SALIENT FEATURES 1. TOPOGRAPHY:  The location of the site was close to a moderately hilly region having high ground water table.  The land surface is undulated with expansive black soil dominant in this region.  Site is in close proximity to pre-existing buildings and National Highway 4. 2. EXCAVATION:  Excavation was carried out with the help of excavators.  We observed an area excavated for construction of club house.  1m offset was marked around the excavated zone to facilitate easy movement of the machinery around the periphery.  The excavated soil was carried by dumpers for dumping and de-watering of the excavated part was undertaken with the help of pumps.
  • 6. Kalyani Kadam SITE REPORT Page 5 of 21 3. LABOUR CAMP:  Labour camp was provided close to the site compound wall for easy access to site.  There were in all 700 labours in the camped area whereas 150 labours were in function on the site.  The labours carried out work as per the regional speciality, viz: Concreting: Malda labours (West Bengal) Tiling: Rajasthani labours Reinforcing: Maharashtrian labours Shuttering: Uttar Pradesh and West Bengal Levelling: Andhra Pradesh  The labour camp was divided in 3 prominent sections, i.e. hutments, provisional stores and sanitation facility.  The site also provided school and crèche facility to the children and toddlers, with 3 teachers to take care of the necessary educational requirement of the 60 children.  A storage tank is provided for potable water around the periphery of the camp. 4. STORES:  Stores were located in the building vicinity to enable easy transport of materials.  The store kept a book record of the quantities provided for construction and procured additional materials required.  It also housed a Compression testing machine to test the Concrete Block Strength on site apart from the third party testing which is carried out by Durecrite.  It stored Cement blocks, Tiles, Sanitary fixtures, Pump parts, Granite slabs, pipes, plumbing accessories, lighting fixtures etc.
  • 7. Kalyani Kadam SITE REPORT Page 6 of 21 Fig. 4: Labelling concrete blocks for Testing. 5. BAR BENDING YARDS:  Bar bending yard was located near the entrance to the buildings, facilitating prompt delivery of reinforcement on site.  Bar bending was carried out manually by labours.  The bars after cutting were laid separately as per their shape, thus increasing efficiency. Fig. 5: Bar bending yard.
  • 8. Kalyani Kadam SITE REPORT Page 7 of 21 6. PLANT AND MACHINERY:  Plant and machinery were involved on a large scale in the construction of this project, making the project as of whole cost-effective.  Detachable Tower Cranes were employed for building construction.  Excavators, dumpers and dozers were also employed.  Maintenance of the machinery was taken care of by the Maintenance Engineer. 7. BATCHING PLANT: A batching plant is an equipment used to mix the different components of concrete to produce a desired grade of concrete.  A batching plant with 2 silos for cement and fly ash was located on site.  The coarse and fine aggregate was laid around the mixer for easy filling.  Water was directly pumped in the mixer by a pump and hose. Fig. 6: Cement & Fly ash silo in Batching Plant.  The automated plant was operated by a Mechanical Operator, by feeding the inputs as per the given combination to achieve a uniform mix.  The capacity of the mixer was 0.35m3.  The discharge rate of plant is 12 m3 per hour.
  • 9. Kalyani Kadam SITE REPORT Page 8 of 21 Fig. 7: Concrete mixer in Batching Plant.  The freshly produced concrete was then pumped at the desired spot.  Cement slurry is passed through the pipe prior to concreting to wet the inner section of pipe to, thus avoiding obstruction.  The concreting pipe was cleaned with the help of high speed water jets and passing a ball to clear the residual concrete in the pipe. 8. WATER AND POWER SUPPLY:  Taking advantage of the high water table and undulated hilly area, an artificial reservoir is constructed close to the site.  This work was undertaken to fulfil two objectives, namely: a. Raising the ground water table b. Providing water for construction activities  Water from the artificial reservoir is pumped onsite, helping to reduce the load on local water supply.  Power is obtained from MSEB (Maharashtra State Electricity Board), through transformers installed on site, for operating machines.  An additional diesel generator backup is provided for emergency power generation.  The construction activities are so planned to avoid wastage of water and power.
  • 10. Kalyani Kadam SITE REPORT Page 9 of 21 9. FOUNDATION:  Hard strata was found at a shallow depth ranging from 2m to 4m.  Owing to this shallow depth, box footing is provided to the structure instead of raft footing.  Since the depth of the hard strata varied between 2m to 4m, depth of footing was changed accordingly.  Concrete of grade M30 was used for construction of footing. 10.SCAFFOLDING AND SHUTTERING:  Bamboo scaffolds were primarily used for scaffolding and tied with binding wires.  Wooden ply boards, horizontal and vertical planks and metal props were used for shuttering.  The extendable vertical props can be extended up to a height of 4m.  Horizontal distance between two successive props was 2ft centre-to-centre.  To reduce the number of vertical props, GI span sections were laid horizontally at beam sections.  For columns, the shuttering was provided with inclined extendable metal struts, anchored to the ground with a bolted base plate.  To hold the shuttering in place and retain the shape C-clamps were also used. Fig. 8: Bamboo scaffolding and shuttering.
  • 11. Kalyani Kadam SITE REPORT Page 10 of 21 11.CONCRETING: Concreting is the process of producing concrete by preparing a uniform homogenous mixture of cement, crushed sand, aggregates, water and admixture.  Concrete of grade M20 and M30 were produced for suitable sections.  Slabs and beams were cast monolithically using M20 grade of concrete.  For columns, M30 grade of concrete was produced.  For basement, parking, podium and slab sections concrete pumping was employed.  For column sections, concreting was done manually.  Vibrators were used for proper consolidation of concrete and to avoid segregation and bleeding. Fig. 9: Representative picture displaying Pump Concreting.  Concrete blocks were cast and tested periodically for strength parameters.  For walls and partitions AAC blocks (Autoclaved Aerated Concrete) were used due to the following advantages: a. Light weight b. Less consumptions of power during production c. Reduced amount of water for curing d. Heat refractor e. High strength f. Less amount of sealant used to fill the joints, hence economical g. Easy to place and skilled labour not required  Size of AAC block was 300mm*225mm*150mm and 600mm*225mm*150mm.
  • 12. Kalyani Kadam SITE REPORT Page 11 of 21 Fig. 10: AAC block wall. 12.DRAINAGE AND UTILITY LINE:  Trenches were excavated with the help of backhoe to lay the drainage and electricity lines.  These trenches were rectangular in section and laid with asbestos pipes to carry sewage.  These pipelines connected the sewage pipes to the city sewage system.  Power lines, encased in PVC pipes, were also laid underground along with water supply lines.
  • 13. Kalyani Kadam SITE REPORT Page 12 of 21 Fig. 11: Representative picture showing Trench Digging. 13.PARKING AND BASEMENT:  2 storey parking facility is provided, which included basement parking and podium parking.  The pavement for the basement parking was 200mm thick tremix concrete with underlying wire mesh to provide additional support.  This pavement layer after laying was lined with a wire brush to avoid skidding of vehicles.  A 3m high retaining wall is constructed in the basement parking, prior to construction of super structure, to counteract the horizontal earth pressure.
  • 14. Kalyani Kadam SITE REPORT Page 13 of 21 Fig. 12: Podium & basement parking.  Lighting facility in the basement parking section is an innovative example to reduce power consumption.  Hollow vertical ducts up to 1m height were erected on the podium and covered with light refracting material on the under-side.  This mechanism allowed ample lighting during day, while only using artificial lights at night.
  • 15. Kalyani Kadam SITE REPORT Page 14 of 21 Fig. 13: Hollow vertical ducts. Fig. 14: Solar refracting Lights. 14.FINISHING:  Wall finishing in the building was done using Gypsum plaster instead of Plaster due to its heat resistant property and it gives a gloss finish.  A 15mm thick Gypsum layer is applied after which 2 coats of paint is applied on the wall.  Master bedroom was provided with Wooden flooring with interlocking segments.  Kitchen was furnished with Hafele gas burners and chimney.  Large windows and balcony were provided for better ventilation and lighting.  The flights up to 1st floor were provided with Saddar Ali Granite.  Provision was made on the stair edge similar to skirting to avoid water spillage during cleaning.  External finishing consisted of 15 mm thick 1st coat of Gypsum followed by 5mm thick Gypsum plaster.  Later a coat of paint is applied on the prepared surface.
  • 16. Kalyani Kadam SITE REPORT Page 15 of 21 Fig. 15: Sample flat with finishing work completed. 15.ELECTRICAL AND PLUMBING FIXTURES:  Electrical and plumbing fixtures were carried out in 4 stages: a. Provision for conduits prior to concreting b. Outlet is provided to fix electric points c. After the completion of construction wires are passed through conduits d. Fixing of switches and distribution board and meter boards  Switches were provided at standard heights of 2ft and 4ft.  Legrand switches were used.  Provision for foot lamps was also made.  The entire plumbing system was concealed and fixtures were provided at 2ft and 4ft height.
  • 17. Kalyani Kadam SITE REPORT Page 16 of 21 16.FIRE FIGHTING SYSTEMS:  Each floor was equipped with fire fighting equipment such as water hose connected to water tank and fire extinguisher.  Parking in the basement was covered with a web of Main and Intermediary pipes carrying water and connected to a sprinkler mechanism.  Fire exit doors were provided in the buildings to enable safe exit of residents.  Smoke detectors were provided throughout the building structure, to detect smoke and take preventive action.  The sprinklers would be activated, when a smoke detector sounds an alarm. 17.GARBAGE DUMPING:  Outlet chutes were provided in the corridor of every floor.  These chutes pass the garbage to the movable collection bin, which transfers it to the local garbage collection bodies. 18. ELEVATORS:  2 elevators were provided in each building.  One was reserved for general use.  The other elevator is for maids, maintenance and carrying heavy equipment. 19.WATER STORAGE AND SEWAGE TREATMENT PLANT (STP):  The water storage tank is constructed below the basement parking.  Covers an area of 32m*22m and depth of 3.5m.  Its storage capacity is 25 million litres.  The water is supplied to the storage tank from an auxiliary tank, by force of gravity.  Sewage treatment plant (STP) is provided under the basement to treat sewage from household activities, and recycle the water.  The capacity of STP tank to process, is 665 m3 per day.  This treated water is used for cleaning vehicles, gardening and flushing in toilets.
  • 18. Kalyani Kadam SITE REPORT Page 17 of 21 Fig. 16: Sewage Treatment Plant (STP). 20.QUALITY:  Quality of work during construction was stringently maintained by periodic tests.  The finishing of the flats was done as per required specifications.  Some of the specifications are: a. 800 mm x 800 mm vitrified tiles in entire flat. b. Toto bathroom and sanitary fixtures. c. Powder coated windows. d. Designer 7 feet high entrance door. e. Laminated internal doors. f. Security system. g. Glass partition in master bedroom h. S. S railing and toughened glass in terrace.
  • 19. Kalyani Kadam SITE REPORT Page 18 of 21 Fig. 17: Kitchen with Hafele fitting. Fig. 18: S. S railing & Toughened glass.
  • 20. Kalyani Kadam SITE REPORT Page 19 of 21 21.SAFETY:  Workers were using helmets and harnesses while working at heights.  Safety nets were provided at the under-constructed floor to restrict the debris from falling.  Labours involved in concreting used gumboots and gloves.  Lift well were provided with barricade.  Fire extinguishers were present on site to counter any outbreak of fire. Fig. 19: Safety net provision. 22.AMENITIES:  A club house with fully equipped gymnasium and swimming pool is provided around the building.  Landscaped gardens, lawns and rock garden covered the open spaces with provision for rest areas.  Multi-purpose court, jogging track and net practice cricket pitch is to be constructed for healthy living.  An amphitheatre and banquet hall is provided for entertainment purpose.  An old age home facility will also be provided for elderly.
  • 21. Kalyani Kadam SITE REPORT Page 20 of 21 Fig. 20: Swimming pool for kids & adults. Fig. 21: Open garden & elevated walkways. Fig. 22: Fully equipped Gym.
  • 22. Kalyani Kadam SITE REPORT Page 21 of 21 23.PURCHASING:  Material requirement is calculated on the basis of tender document that is item specifications tender drawings and the purchase requisition is prepared.  The sample of each material is approved from authorised architect and client. After the approval of sample the quotations are called from approved list of suppliers or vendors.  After receiving quotations from vendors, the final negotiations from the contractors are called along with checking their capability of in-time supply and credit limit.  Finally, a comparative statement is prepared to select lowest quotation with mode of payment.  The material is ordered by issuing purchase order including all requirements, specifications, rate and taxation if any.  It includes mode of transportation, loading and unloading charges, octroi charges in municipal corporation area, VAT and other applicable government taxes. 24.CREDITS:  Architect: Abhikalpan Architects and Planners  RCC: Hansal Parikh and Associate Structural Consultants  Landscape: Designterra Landscape Consultants  Liaison Architect: Gohad Architects  Interior: Pranali Shende CONCLUSION: The visit enabled us to experience construction practices adopted on site, all the while maintaining quality and standards. The use of innovative techniques and installation of STP, makes the project economical and environmentally beneficial. Efficient use of machinery, saved cost and aids in maintaining the progress of construction activities.