Tunneling Safety
johnanewquist@gmail.com
Draft 11 8 2015
1988
• Milwaukee WI
• Methane gas was detected in a
40-foot-deep tunnel that was
under construction.
• The mining machine was
automatically shut down, and all
the employees were evacuated.
• Ten minutes later, three
employees entered the area to
determine if the atmosphere in
the tunnel was safe for reentry.
• An explosive mixture of methane
gas had developed in the air.
• Apparently, the grout pump
ignited the gas and caused an
explosion.
• The three employees were badly
burned, and they died of
asphyxiation due to overexposure
to carbon monoxide.
OSHA Specific Requirements
• Check-in/check-out.
• The employer shall maintain a
check-in/check-out procedure
that will ensure that above-
ground personnel can
determine an accurate count of
the number of persons
underground in the event of an
emergency.
• However, this procedure is not
required when the construction
of underground facilities
designed for human occupancy
has been sufficiently completed
so that the permanent
environmental controls are
effective, and when the
remaining construction activity
will not cause any
environmental hazard or
structural failure within the
facilities.
1926.800(c)
Safety Instruction
• All employees shall be
instructed in the recognition
and avoidance of hazards
associated with underground
construction activities including,
where appropriate, the
following subjects:
• Air monitoring:
• Ventilation:
• Illumination:
• Communications:
• Flood control:
• Mechanical equipment:
• Personal protective equipment:
• Explosives:
• Fire prevention and protection:
and
• Emergency procedures,
including evacuation plans and
check- in/check-out systems.
1926.800(d)
Emergency Provisions• Hoisting capability.
• When a shaft is used as a
means of egress, the
employer shall make advance
arrangements for power-
assisted hoisting capability to
be readily available in an
emergency, unless the
regular hoisting means can
continue to function in the
event of an electrical power
failure at the jobsite.
• Such hoisting means shall be
designed so that the load
hoist drum is powered in
both directions of rotation
and so that the brake is
automatically applied upon
power release or failure.
1926.800(g)(1)
Emergency Provisions• Self-rescuers.
• The employer must provide
self-rescuers approved by the
National Institute for
Occupational Safety and
Health under 42 CFR part 84.
• The respirators must be
immediately available to all
employees at work stations
in underground areas where
employees might be trapped
by smoke or gas.
• The selection, issuance, use,
and care of respirators must
be in accordance with 29 CFR
1926.103.
1926.800(g)(2)
Emergency Provisions
• Designated person.
• At least one designated
person shall be on duty
above ground whenever
any employee is working
underground.
• This designated person
shall be responsible for
securing immediate aid
and keeping an accurate
count of employees
underground in case of
emergency.
• The designated person
must not be so busy that
the counting function is
encumbered.
1926.800(g)(3)
Emergency Provisions• Emergency lighting.
• Each employee
underground shall
have an acceptable
portable hand lamp or
cap lamp in his or her
work area for
emergency use, unless
natural light or an
emergency lighting
system provides
adequate illumination
for escape.
1926.800(g)(4)
Emergency Provisions
• Rescue teams.
• On jobsites where less
than 25 employees work
underground at one
time, the employer shall
provide (or make
arrangements in
advance with locally
available rescue services
to provide) at least one
5-person rescue team to
be either on the jobsite
or within one-half hour
travel time from the
entry point.
1926.800(g)(5)(ii)
Hazardous
Classifications
• Potentially gassy operations.
• Underground construction operations
shall be classified as potentially gassy if
either:
• Air monitoring discloses 10 percent or
more of the lower explosive limit for
methane or other flammable gases
measured at 12 inches (304.8 mm) to +
or - 0.25 inch (6.35 mm) from the roof,
face, floor or walls in any underground
work area for more than a 24-hour
period: or
• The history of the geographical area or
geological formation indicates that 10
percent or more of the lower explosive
limit for methane or other flammable
gases is likely to be encountered in such
underground operations.
1926.800(h)(1)
Air Quality and
Monitoring.
• Where this paragraph requires monitoring of
airborne contaminants "as often as necessary,"
the competent person shall make a reasonable
determination as to which substances to monitor
and how frequently monitor, considering at least
the following factors:
• Location of jobsite: Proximity to fuel tanks,
sewers, gas lines, old landfills, coal deposits, and
swamps;
• Geology:
• History: Presence of air contaminants in nearby
jobsites, changes in levels of substances
monitored on the prior shift; and
• Work practices and jobsite conditions: The use of
diesel engines, use of explosives, use of fuel gas,
volume and flow of ventilation, visible
atmospheric conditions, decompression of the
atmosphere, welding, cutting and hot work, and
employees' physical reactions to working
underground.
1926.800(j)(1)(i)(B)
Air Quality and Monitoring.
• Recordkeeping.
• A record of all air quality
tests shall be maintained
above ground at the worksite
and be made available to the
Secretary of Labor upon
request.
• The record shall include the
location, date, time,
substance and amount
monitored.
• Records of exposures to toxic
substances shall be retained
in accordance with 1926.33
of this chapter.
• All other air quality test
records shall be retained
until completion of the
project.
1926.800(j)(3)
Ventilation• Fresh air shall be supplied to all
underground work areas in
sufficient quantities to prevent
dangerous or harmful
accumulation of dusts, fumes,
mists, vapors or gases.
• Mechanical ventilation shall be
provided in all underground work
areas except when the employer
can demonstrate that natural
ventilation provides the necessary
air quality through sufficient air
volume and air flow.
• A minimum of 200 cubic feet of
fresh air per minute shall be
supplied for each employee
underground.
1926.800(k)(1)
Fire Control
• Flammable or combustible
materials shall not be stored
above ground within 100 feet
(30.48m) of any access opening
to any underground operation.
• Where this is not feasible
because of space limitations at
the jobsite, such materials may
be located within the 100-foot
limit, provided that:
• They are located as far as
practicable from the opening;
and
• Either a fire-resistant barrier of
not less than one-hour rating is
placed between the stored
material and the opening, or
additional precautions are taken
which will protect the materials
from ignition sources.
1926.800(m)(7)
Oxygen and acetylene stored together
is a violation.
Fire Control
• Lighting fixtures in
storage areas, or within
25 feet (7.62 m) of
underground areas
where oil, grease, or
diesel fuel are stored,
shall be approved for
Class I, Division 2
locations, in accordance
with Subpart K of this
part.
1926.800(m)(9)
Portal Areas
• Competent persons
conducting such
inspections shall be
protected from loose
ground by location,
ground support or
equivalent means
1926.800(o)(3)
Portal Areas
• Suitable protection
shall be provided for
employees exposed to
the hazard of loose
ground while installing
ground support
systems.
1926.800(o)(3)
OSHA Citations
• Fall Protection
OSHA Citations
• Fall Protection
OSHA Citations
• Ladder
OSHA Citations
• Unapproved rigging
OSHA Citations
• Ladder
OSHA Citations
• Fall Protection
OSHA Citations
• Lighting
OSHA Citations
• Fall
OSHA Citations
• Rigging
• no capacity marked
OSHA Citations
• GHS
• Spill Control
OSHA Citations
• Fall
OSHA Citations
• Homemade drum
carrier
Structural Issues
• Rock Fall - Fall of rock blocks of major
dimensions. The different
mechanisms involved are wedge or
planar failure..
• Collapse Heading collapse - failure of
the heading / lining failure .
• Daylight Collapse Heading collapse -
lining failure of the heading that
reaches the surface creating a crater.
• Excessive Deformation - Excessive
deformations inside the tunnel or at
the surface. This can occur for
example due to deficient design,
construction defects and/or due to
particular type of terrains such as
swelling and squeezing ground,
which had not been predicted.
• Flooding - Comprises cases where the
tunnel was invaded by large
quantities of underground water.
• Rock Burst - Spalling Overstressing of
massive or intact brittle rock, i.e. the
stresses developed in the ground
exceed the local strength of the
material. It can cause spalling or in
the worst cases sudden and violent
failure of the rock mass
• Portal failure - Particular locations of
a tunnel, where there is a lower
• Shaft failure - resistance of ground
mass and/ or concentration of
stresses.
• Other - Other types of collapse that
include slope failures, etc
Structural Failures
Rock Fall
• Rock fall blocking the
TBM at the Covao
tunnel in 2006 (Madeira
Island, Portugal)
Collapse
• The large collapse occurred in front of the face and stopped the
cutter head rotation, creating a cavern more than 10 m high over
the TBM.
• This was an example of a full collapse of the face.
Collapse• Wienerwald Austria
• In this case, ground water
led to de-compaction and
bulking of the sandstone,
which caused the shear
strength to decrease.
• From this it follows that
the strength of rock was
very low and ground
pressure loaded the
temporary shotcrete
shell, which was not
designed for that kind of
high loading.
• Therefore the shotcrete
shell spalled off and the
lattice girder was
deformed.
Daylight Collapse
• These are collapses that
reach the surface
creating a crater.
• Munich Metro in 1994
• No deaths
Daylight Collapse
• Sao Paulo Brazil 2007
• 7 deaths
• Open face tunnelling is cheap.
• New Austrian Tunnelling
Method (NATM) is much less
expensive than a soft ground TBM,
but much less safe
• A combination of explosives and
mechanical excavation techniques
were being used.
• 'The top heading of the failed tunnel
was fully excavated in rock.
• There was approximately 6m of rock
above the tunnel,
• Support consisted of steel arch
girders at 800mm centres, and
350mm thick steel fibre reinforced
sprayed concrete.
• 'The vertical displacements measured
at the tunnel crown were in the
range of 3mm when the top heading
excavation was completed.
• Two to three days before the
accident, the rate of those
displacements increased, and they
reached 15mm to 20mm.
Daylight Collapse
• 2003: Shanghai's underground
Pearl Line, China
• $80 million
• The accident occurred in a cross
passage between the two parallel
tunnel tubes that had already
been driven using earth-pressure-
balance TBMs.
• Shortly before the cross passage
broke through, at a depth of
about 35 m, massive inrushes of
material and water occurred,
which the tunnel crew was not
able to bring under control and
which resulted in a large scale
subsidence at the
Daylight Collapse
• South Korean city of Taegu
on 22 January 2001
• Failure of a diaphragm wall.
• Part of a station excavation
pit caved in, burying a bus,
killing three passengers and
damaging neighboring
buildings.
• The accident was caused by
a load not considered in the
design phases and due to
unforeseen soil conditions.
• $24 million
Flooding
• It is during the construction
of underwater tunnels that
largest scale floodings have
occurred.
• The ground under rivers,
channels and bays is
normally weak and under
high water pressure and
therefore extreme safety
measures and efficient
protection against water
inflow are normally
required.
Flooding
• Seikan tunnel is a 53.85 km long
railway tunnel in Japan
• 1963-1976
• Four floods
• 23 deaths
• Leaks and soft rock
• TBM not practical due to the
various types of soils.
• Drill and pound.
• A great majority of the tunnel
crosses heavily fissured rock (9
large shear zones). The sea and
underground water penetrate
into these zones and the
maximum water pressure is
about 25 MPa
Flooding
• Lausanne, Switzerland
• A huge amount of soil
and water (1400m3)
displaced into the
tunnel and caused
extensive damage
Rockburst/Spalling
• This type of event is
caused by the
overstressing of massive
or intact brittle rock, i.e.
the stresses developed in
the ground exceed the
local strength of the
material.
• It can cause spalling or in
the worst cases sudden
and violent failure of the
rock mass
Excessive Deformation
• These are cases where
excessive deformations
occur inside the tunnel or at
the surface but an actual
total collapse does not
happen.
• This can occur for example
due to deficient design,
construction defects and/or
due to particular type of
terrains such as swelling
and squeezing ground,
which had not been
predicted.
Excessive Deformation
• Rotarelle to San Vittore
tunnel, Italy 1991
• After 650m of excavation,
enormous ground pressures
caused cracking of the
shotcrete, buckling of the
steel arches after a few
hours, and deformations of
200 mm in 24h and 400 mm
after 12 days
• The deformations were
caused by swelling clay
filling of the rock.
Excessive Deformation
• Squeezing is
characterized large
time-dependent
convergence during
tunnel excavation.
• Failure of the support
system.
• Inadequate support for
such ground conditions.
1999: Bolu Tunnel, Turkey
An earthquake caused the collapse of a
section of the Bolu tunnel, part of the
Anatolian highway, even though the
tunnel had been designed to withstand
earthquakes. $115 million loss
1908-1913
• Lotschberg tunnel
• Switzerland
• Use of timber supports
after collapse killed 25
in 1908
Hawks Nest WV
• 1930s
• A simple diversion tunnel for
the New River in West Virginia
• After workers discovered silica
in the rock they were told to
mine it as a by-product of
tunnel construction, however,
they were never given any
masks or protective gear.
• Hundreds of workers
developed silicosis due to the
long-term exposure of silica
dust in their lungs.
New York City Third Water Tunnel
• The largest
infrastructure project in
New York state history
is currently tunneling
below New Yorker's feet
to provide a third
connection to the
upstate water supply
St. Gotthard Road Tunnel, 1969-1980
• At the time it was
completed, this 10-mile
tunnel in Switzerland was
the longest road tunnel in
the world.
• Tragically, 19 people died
working on the tunnel—
which was created to
connect central Switzerland
with Milan, Italy through
the Alps, providing a faster
and safer year-round
alternative to the winding
Gotthard Pass.
Big Dig Ceiling
Collapse
• July 10, 2006
• Concrete ceiling panel and debris
weighing 26 tons fell in Boston's
Fort Point Channel Tunnel
• The panel fell on a car killing a
passenger and injuring the driver.
• The collapse of the ceiling
structure began with the
simultaneous creep-type failure
of several anchors embedded in
epoxy in the tunnel's roof slab.
• Each of the panel's intersecting
connection points consists of
several individual bolts anchored
into the roof slab concrete.
• The failure of a group of anchors
set off a chain reaction which
caused other adjacent connection
groups to creep then fail
Big Dig Ceiling
Collapse
• Not only were the bolts too short,
but the epoxy used to glue the
bolts into the concrete was not
up to standard.
Big Dig Ceiling
Collapse
• Major cause of the collapse to
"epoxy creep“
• On August 8, 2007, a Suffolk
County Grand Jury indicted epoxy
company Powers Fasteners, Inc.,
on one charge of involuntary
manslaughter, with the maximum
penalty in Massachusetts being a
fine of one thousand dollars.[10]
• The epoxy used in the D Street
portal that failed cost $1287.60.
The cost to redesign, inspect, and
repair all of the tunnels after the
collapse was $54 million.[1
2004: Circle Line, Singapore
• Collapse of a construction
pit resulted in the death
of four workers plus the
collapse of an adjoining
highway.
• It eventually was found
that the most apparent
cause of the collapse was
that the retaining wall
could not handle the
stress of holding up the
tunnel, forcing it to give
way.
1994: Heathrow Express Link
• London
• Three tunnels forming part of the
Heathrow Express Link,
connecting central London and
Heathrow Airport, caved in and
took several buildings with them.
• $141 million
• According to the HSE, a chain of
events led directly to the
collapse.
• This included a failure to check
substandard construction over a
period of some three months,
pressure grouting that damaged
the tunnel plus inadequately
executed repairs some two
months before the collapse.
1994/95: Metro
• Taipei, Taiwan
• When the Metro was being built
in Taiwan in the 1990s, several
serious tunnel collapses occurred,
causing major property damage
to adjacent buildings as well as
serious liability losses.
• $41 million
• Difficult geology, with fractured
rock and massive inflows of
water, countless cave-ins, mud
and rock slides caused by massive
inflows of groundwater.
• Eleven people were killed in the
accidents.
1999: Tunnel in Hull
• England
• During one of the tunnel
drives for a 6.5 mile
underground sewer in Hull,
England, a deformation in the
floor of the tunnel shell led to
flooding of the tunnel and
subsidence at the surface,
resulting in substantial
damage to buildings, roads
and utility lines.
• Machines and the tunnel were
abandoned.
• $55 million
XIAN Subway
• 2013 China
• At least two are dead after an
accident at a subway
construction site in Xi’an,
Shaanxi province this morning.
• At around 2:40 am, a tunnel
caved in as nine workers were
in the midst of building Line 3.
• Four have been rescued, but
of the five that were buried,
two have been found dead
while the other three are still
missing
Dec 2014
• Vietnam
• Rescuers have created a
16 cm-wide access hole
to the location where
12 workers have been
trapped inside a
collapsed tunnel section
at a hydropower plant
in the Central Highlands
province of Lam Dong
They may have assumed that the dry
season had come and it was safe to
dig, but this year the rainy season
lasted too long.
With heavy rains making the
foundation weak, sinkages occurred
in the tunnel.
And given the Central Highlands’
geological formations, digging up a
big rock may lead to the whole
tunnel’s collapse.
2000
• Dulles Airport
• One dead
• At the time of the accident, about
700 ft of the approximately 40 ft
wide by 16 ft tall tunnel had been
excavated.
• Employee #1 was using a
shotcrete hose to spray the side
walls at the tunnel's earthen face
when the top and side of the
tunnel collapsed.
• In the week before the tunnel
gave way, there were three
partial collapses, each increasing
in severity
July 2015
• A construction worker
who was killed when a
winch he was operating
broke loose from its
anchor at a tunneling
site in the High Desert
has been identified as
David Padilla, 38, of
Pahrump, Nevada.
February 2015
• Seattle WA
• WSDOT now says five
workers were installing
rebar for a concrete
wall at the tunnel’s
north portal work zone.
• The wall of rebar gave
way, injuring four of the
five workers.
2013
• Sunol CA
• On August 22, 2013, Employee
#1, was working on a pipeline
project.
• A piece of cement grout
approximately 1.5 feet by 1.5
feet by 6 feet long fell out of
the tunnel face approximately
3 feet above the invert.
• The cement pinned Employee
#1's leg against a roadheader.
• Employee #1 sustained
bruising/contusions/abrasions.
2013
• On June 17, 2013, an employee was working as a heavy equipment
mechanic for a bridge, tunnel, and highway construction firm.
• He was on a segment build deck, assembling a tunnel boring machine.
• He fell off the deck, falling a distance of 10 feet.
He sustained a strain or sprain in his left ankle
TBM Closed Mode
2011
• Webster NY
• Employee #1, a locomotive
operator, was moving muck
buckets and equipment to the
head section of a tunnel.
• When the operator reached
the end of the tunnel, the
locomotive failed to stop and
Employee #1 was crushed
between the locomotive and
the conveyor on the tunnel
boring machine.
• Employee #1 was killed.
2011
• Woodland CA
• Employee #2, a laborer, noticed a
hole in a material chute in the No.
196 tunnel conveyor system.
• Employee #1 was joined by Employee
#2 in the reclaim tunnel to schedule
and plan a repair operation.
• As the two Employees exited the
tunnel and walked away from the
overhead No. 196 Conveyor, a 10
pound rock fell off the conveyor
striking Employee #1 in the head and
Employee #2 in the back, knocking
both employees to the ground.
• Employee #1 was knocked
unconscious and landed on top of
Employee #2.
2009
• Kermit, WV
• Employee #1 was engaged in the
preparations for raising the
height of a tunnel liner.
• Employee #1 bored several holes
for taking core samples and
pictures were taken.
• Employee #1 entered the tunnel
through the west portal entrance,
with his excavator equipped with
a hoe ram.
• After reaching the necessary
work station, Employee #1 began
hammering out the center part of
the tunnel's liner to remove it.
• About 30 minutes following the
start of work, a section of the
roof fell, crushing and killing
Employee #1.
2009
• Alexandria VA
• Employee #1 was working in a
subway tunnel for the
Washington Metropolitan Area
Transit Authority.
• A train passed by the location
where Employee #1 was standing.
• Coworkers reported that they
heard a noise and then the train
stopped.
• When the coworkers found
Employee #1, it was apparent
that he had been struck by the
train and suffered trauma to his
head and one leg.
2009
• Cartersville GA
• Employee #1 was packing
straw around the east end of
the tunnel plate.
• The top, unprotected end of
the tunnel collapsed and
buried Employee #1's head
and neck in mud on top of the
tunnel plate.
• Coworkers attempted to
rescue Employee #1; however,
they were unsuccessful and he
was pronounced dead at the
site.
2008• Employees #1 though #5, were
repairing the floor of the south
bypass conduit water tunnel
located under Lake Las Vegas in
Henderson, Nevada.
• The tunnel was two miles long
and seven feet in diameter.
• They were preparing to pour
concrete on the tunnel floor.
• Two workers activated the
ventilation fan from outside.
• Concrete was carried in eight
buggy carts pulled by bobcat.
• Behind them, the mechanic and
Project Superintendent followed
on a propane-operated golf cart.
• Around 10:00 a.m., these
employees arrived at the work
location and found that the
mechanical ventilation fan had
been shut down.
• Several unsuccessful attempts
were made to start the fan.
• The Project Superintendent and
foreman decided that work would
continue, after measuring the natural
air flow using a handheld Mini
Thermo-Anemometer by Extech
Instrument.
• At 11:15 a.m., the foreman radioed
from inside tunnel that employees
were experiencing difficulty
breathing, chest pains, and fatigue.
• The project superintendent sent golf
carts and removed all employees
from the tunnel about 12:16 p.m.
• Employees #1 through #5 were
treated for asphyxia and carbon
monoxide poisoning at University
Medical Center (UMC) in Las Vegas
and St. Rose De Lima in Henderson
2007
• Houston TX
• Employee and five coworkers were
working attempting to install a 60-in.
by 10-ft by 0.5-in. steel pipe casing
for the 42-in. regional main water
line.
• The site was comprised of a 60-ft by
40-ft shaft which led down to a
tunnel, which had already pushed
the 60-in. steel pipe approximately
120-130-ft laterally under the
Cypress Creek.
• The employee was cleaning the
excess dirt from the 60-in. pipe as the
pipe was hydraulically pushed inside.
• A breach occurred, immediately
filling the tunnel and the shaft with
water.
• All of the coworkers were able to
escape except the employee.
2005
• Minneapolis MN
• At approximately 7:00 a.m. on
September 6, 2005, Employee
#1 entered the work area on
the fifth floor of the project.
• Employee #1 was walking
through tunnel forms to
prepare the forms for a
concrete pour.
• As Employee #1 walked
toward the end of the form
inspecting his work, he
stepped through a floor hole
and fell approximately 45 ft to
his death.
2000
• Chanilly VA
• The 27 ft deep passenger
walkway tunnel was being
constructed from one terminal to
another.
• At the time of the accident, about
700 ft of the approximately 40 ft
wide by 16 ft tall tunnel had been
excavated.
• Employee #1 was using a
shotcrete hose to spray the side
walls at the tunnel's earthen face
when the top and side of the
tunnel collapsed.
• Fire and emergency services were
called but they were unable to
rescue Employee #1.

Weitere ähnliche Inhalte

Was ist angesagt?

OSHA demolition
OSHA demolitionOSHA demolition
OSHA demolitionHni Amiera
 
NGI-Excavation Hazards
NGI-Excavation HazardsNGI-Excavation Hazards
NGI-Excavation Hazardslifecombo
 
Risk assessment for testing & commissioning of cranes
Risk assessment for  testing & commissioning of cranesRisk assessment for  testing & commissioning of cranes
Risk assessment for testing & commissioning of cranesAzmeel Contracting Company
 
Demolition of building and its precautionary measures as per IS code
Demolition of building and its precautionary measures as per IS codeDemolition of building and its precautionary measures as per IS code
Demolition of building and its precautionary measures as per IS codejaimin1702
 
Method statement for structure excavation
Method statement for structure excavationMethod statement for structure excavation
Method statement for structure excavationAl-Amin Ahmed Nabin
 
15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templates23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templatesDwarika Bhushan Sharma
 
risk assessment - pile cap.pdf
risk assessment - pile cap.pdfrisk assessment - pile cap.pdf
risk assessment - pile cap.pdfmydl2
 
1926 concrete safety 2017
1926 concrete safety 20171926 concrete safety 2017
1926 concrete safety 2017John Newquist
 
10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templatesDwarika Bhushan Sharma
 
Method statement for expansion joint
Method statement for expansion jointMethod statement for expansion joint
Method statement for expansion jointakash yadav
 

Was ist angesagt? (20)

OSHA demolition
OSHA demolitionOSHA demolition
OSHA demolition
 
NGI-Excavation Hazards
NGI-Excavation HazardsNGI-Excavation Hazards
NGI-Excavation Hazards
 
Risk assessment for testing & commissioning of cranes
Risk assessment for  testing & commissioning of cranesRisk assessment for  testing & commissioning of cranes
Risk assessment for testing & commissioning of cranes
 
Demolition of building and its precautionary measures as per IS code
Demolition of building and its precautionary measures as per IS codeDemolition of building and its precautionary measures as per IS code
Demolition of building and its precautionary measures as per IS code
 
Method statement for structure excavation
Method statement for structure excavationMethod statement for structure excavation
Method statement for structure excavation
 
Scaffolds Training by Pennsylvania L&I
Scaffolds Training by Pennsylvania L&IScaffolds Training by Pennsylvania L&I
Scaffolds Training by Pennsylvania L&I
 
Scaffold and Aerial Lift Safety by KTA
Scaffold and Aerial Lift Safety by KTAScaffold and Aerial Lift Safety by KTA
Scaffold and Aerial Lift Safety by KTA
 
15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates
 
23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templates23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templates
 
Excavation and trenching
Excavation and trenchingExcavation and trenching
Excavation and trenching
 
OSHA Trenching and Excavation Requirements
OSHA Trenching and Excavation Requirements OSHA Trenching and Excavation Requirements
OSHA Trenching and Excavation Requirements
 
Excavations ppt
Excavations pptExcavations ppt
Excavations ppt
 
Report on excavation
Report on excavationReport on excavation
Report on excavation
 
Excavation safety
Excavation safetyExcavation safety
Excavation safety
 
risk assessment - pile cap.pdf
risk assessment - pile cap.pdfrisk assessment - pile cap.pdf
risk assessment - pile cap.pdf
 
CRANE SAFETY HANDBOOK
CRANE SAFETY HANDBOOK CRANE SAFETY HANDBOOK
CRANE SAFETY HANDBOOK
 
1926 concrete safety 2017
1926 concrete safety 20171926 concrete safety 2017
1926 concrete safety 2017
 
Casting yard
Casting yardCasting yard
Casting yard
 
10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates
 
Method statement for expansion joint
Method statement for expansion jointMethod statement for expansion joint
Method statement for expansion joint
 

Andere mochten auch

TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014Hitesh Khanna
 
Sustainability and Safety in Tunnels
Sustainability and Safety in TunnelsSustainability and Safety in Tunnels
Sustainability and Safety in TunnelsFathi Tarada
 
Advanced tunnel borring machine.ppt
Advanced tunnel borring machine.pptAdvanced tunnel borring machine.ppt
Advanced tunnel borring machine.pptabhishek kulkarni
 
Tunnel Safety Technologies
Tunnel Safety Technologies Tunnel Safety Technologies
Tunnel Safety Technologies Luigi Carrarini
 
Fire Protection and Safety in Tunnels
Fire Protection and Safety in TunnelsFire Protection and Safety in Tunnels
Fire Protection and Safety in TunnelsArena International
 
Top 10-violations-fy-16
Top 10-violations-fy-16Top 10-violations-fy-16
Top 10-violations-fy-16John Newquist
 
Immersed Tunnels Recent developments
Immersed Tunnels Recent developmentsImmersed Tunnels Recent developments
Immersed Tunnels Recent developmentsStatybos Akademija
 
Bandar masa depan
Bandar masa depanBandar masa depan
Bandar masa depanAL- AMIN
 
Seminar for Tunneling & Compressed Air Workers Delhi Metro 2014
Seminar for Tunneling & Compressed  Air Workers  Delhi Metro 2014Seminar for Tunneling & Compressed  Air Workers  Delhi Metro 2014
Seminar for Tunneling & Compressed Air Workers Delhi Metro 2014apollohyperbaric
 
Kompetensi 1 lengkap
Kompetensi 1 lengkapKompetensi 1 lengkap
Kompetensi 1 lengkapZul Hilmi
 
A Part 6 Lifting Operations
A  Part 6 Lifting OperationsA  Part 6 Lifting Operations
A Part 6 Lifting OperationsJames McCann
 
Tunnel ventilation ppt tunnel asia 2013
Tunnel ventilation ppt tunnel asia 2013Tunnel ventilation ppt tunnel asia 2013
Tunnel ventilation ppt tunnel asia 2013Hitesh Khanna
 
tunnel boring machine
tunnel boring machinetunnel boring machine
tunnel boring machineNaquiakhter
 
Keselamatan dan Kesehatan Kerja Pelabuhan
Keselamatan dan Kesehatan Kerja Pelabuhan Keselamatan dan Kesehatan Kerja Pelabuhan
Keselamatan dan Kesehatan Kerja Pelabuhan Bondan Winarno
 
Langkah keselamatan mengangkat barang
Langkah keselamatan mengangkat barangLangkah keselamatan mengangkat barang
Langkah keselamatan mengangkat barangSalwa Zakaria
 

Andere mochten auch (20)

TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
 
Tunnel engineering
  Tunnel engineering  Tunnel engineering
Tunnel engineering
 
Sustainability and Safety in Tunnels
Sustainability and Safety in TunnelsSustainability and Safety in Tunnels
Sustainability and Safety in Tunnels
 
Advanced tunnel borring machine.ppt
Advanced tunnel borring machine.pptAdvanced tunnel borring machine.ppt
Advanced tunnel borring machine.ppt
 
Tunnel Safety Technologies
Tunnel Safety Technologies Tunnel Safety Technologies
Tunnel Safety Technologies
 
Fire Protection and Safety in Tunnels
Fire Protection and Safety in TunnelsFire Protection and Safety in Tunnels
Fire Protection and Safety in Tunnels
 
Top 10-violations-fy-16
Top 10-violations-fy-16Top 10-violations-fy-16
Top 10-violations-fy-16
 
My Presentation
My PresentationMy Presentation
My Presentation
 
Bab 1
Bab 1Bab 1
Bab 1
 
Immersed Tunnels Recent developments
Immersed Tunnels Recent developmentsImmersed Tunnels Recent developments
Immersed Tunnels Recent developments
 
Bandar masa depan
Bandar masa depanBandar masa depan
Bandar masa depan
 
Seminar for Tunneling & Compressed Air Workers Delhi Metro 2014
Seminar for Tunneling & Compressed  Air Workers  Delhi Metro 2014Seminar for Tunneling & Compressed  Air Workers  Delhi Metro 2014
Seminar for Tunneling & Compressed Air Workers Delhi Metro 2014
 
Kompetensi 1 lengkap
Kompetensi 1 lengkapKompetensi 1 lengkap
Kompetensi 1 lengkap
 
A Part 6 Lifting Operations
A  Part 6 Lifting OperationsA  Part 6 Lifting Operations
A Part 6 Lifting Operations
 
Tunneling
TunnelingTunneling
Tunneling
 
Tunnel ventilation ppt tunnel asia 2013
Tunnel ventilation ppt tunnel asia 2013Tunnel ventilation ppt tunnel asia 2013
Tunnel ventilation ppt tunnel asia 2013
 
tunnel boring machine
tunnel boring machinetunnel boring machine
tunnel boring machine
 
lifting operation
lifting operationlifting operation
lifting operation
 
Keselamatan dan Kesehatan Kerja Pelabuhan
Keselamatan dan Kesehatan Kerja Pelabuhan Keselamatan dan Kesehatan Kerja Pelabuhan
Keselamatan dan Kesehatan Kerja Pelabuhan
 
Langkah keselamatan mengangkat barang
Langkah keselamatan mengangkat barangLangkah keselamatan mengangkat barang
Langkah keselamatan mengangkat barang
 

Ähnlich wie 510 tunneling safety 2016

Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers referencessuser2c065e
 
Extraction of developed pillars - a case study
Extraction of developed pillars - a case studyExtraction of developed pillars - a case study
Extraction of developed pillars - a case studyTIKESHWAR MAHTO
 
NIOSH - Preventing Worker Deaths from Trench Cave-ins
NIOSH - Preventing Worker Deaths from Trench Cave-ins NIOSH - Preventing Worker Deaths from Trench Cave-ins
NIOSH - Preventing Worker Deaths from Trench Cave-ins Robson Peixoto
 
ACFrOgBSniHxrc2va_BWHYAGsaBYrgpXXwbEWS4TZx_EJijqAUWYUgZyjAhF_DF8qD4kKiyCs_A69...
ACFrOgBSniHxrc2va_BWHYAGsaBYrgpXXwbEWS4TZx_EJijqAUWYUgZyjAhF_DF8qD4kKiyCs_A69...ACFrOgBSniHxrc2va_BWHYAGsaBYrgpXXwbEWS4TZx_EJijqAUWYUgZyjAhF_DF8qD4kKiyCs_A69...
ACFrOgBSniHxrc2va_BWHYAGsaBYrgpXXwbEWS4TZx_EJijqAUWYUgZyjAhF_DF8qD4kKiyCs_A69...R K DHIMAN
 
Excavation Awareness Training.pptx
Excavation Awareness Training.pptxExcavation Awareness Training.pptx
Excavation Awareness Training.pptxAdeniranIdris
 
Rev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationRev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationSiddhartha Bhamidipati
 
Demolition Safety 2015
Demolition Safety 2015Demolition Safety 2015
Demolition Safety 2015John Newquist
 
Dust monitoring and control in metal Mines
Dust monitoring and control in metal MinesDust monitoring and control in metal Mines
Dust monitoring and control in metal MinesAdil Mathew
 
Gi2011hotworks abridged
Gi2011hotworks abridgedGi2011hotworks abridged
Gi2011hotworks abridgedvtsiri
 
Gi2011hotworks abridged
Gi2011hotworks abridgedGi2011hotworks abridged
Gi2011hotworks abridgedBryan Haywood
 

Ähnlich wie 510 tunneling safety 2016 (20)

Es3
Es3Es3
Es3
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers reference
 
Metropolitan colliery gas (Dave Gordon)
Metropolitan colliery gas (Dave Gordon)Metropolitan colliery gas (Dave Gordon)
Metropolitan colliery gas (Dave Gordon)
 
Extraction of developed pillars by opencast mine: acase study
Extraction of developed pillars by opencast mine:   acase studyExtraction of developed pillars by opencast mine:   acase study
Extraction of developed pillars by opencast mine: acase study
 
Extraction of developed pillars - a case study
Extraction of developed pillars - a case studyExtraction of developed pillars - a case study
Extraction of developed pillars - a case study
 
NIOSH - Preventing Worker Deaths from Trench Cave-ins
NIOSH - Preventing Worker Deaths from Trench Cave-ins NIOSH - Preventing Worker Deaths from Trench Cave-ins
NIOSH - Preventing Worker Deaths from Trench Cave-ins
 
ACFrOgBSniHxrc2va_BWHYAGsaBYrgpXXwbEWS4TZx_EJijqAUWYUgZyjAhF_DF8qD4kKiyCs_A69...
ACFrOgBSniHxrc2va_BWHYAGsaBYrgpXXwbEWS4TZx_EJijqAUWYUgZyjAhF_DF8qD4kKiyCs_A69...ACFrOgBSniHxrc2va_BWHYAGsaBYrgpXXwbEWS4TZx_EJijqAUWYUgZyjAhF_DF8qD4kKiyCs_A69...
ACFrOgBSniHxrc2va_BWHYAGsaBYrgpXXwbEWS4TZx_EJijqAUWYUgZyjAhF_DF8qD4kKiyCs_A69...
 
IOC jaipur
IOC jaipurIOC jaipur
IOC jaipur
 
Excavation Awareness Training.pptx
Excavation Awareness Training.pptxExcavation Awareness Training.pptx
Excavation Awareness Training.pptx
 
UG TO OCP rough.pptx
UG TO OCP rough.pptxUG TO OCP rough.pptx
UG TO OCP rough.pptx
 
EXCAVATION SLIDE.pptx
EXCAVATION SLIDE.pptxEXCAVATION SLIDE.pptx
EXCAVATION SLIDE.pptx
 
Rev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationRev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigation
 
2.3a bhopal case_study
2.3a bhopal case_study2.3a bhopal case_study
2.3a bhopal case_study
 
NDL FUEL STATION OPERATION
NDL FUEL STATION OPERATIONNDL FUEL STATION OPERATION
NDL FUEL STATION OPERATION
 
Gas disaster in steel industries
Gas disaster in steel industriesGas disaster in steel industries
Gas disaster in steel industries
 
343312365 mt-ppt
343312365 mt-ppt343312365 mt-ppt
343312365 mt-ppt
 
Demolition Safety 2015
Demolition Safety 2015Demolition Safety 2015
Demolition Safety 2015
 
Dust monitoring and control in metal Mines
Dust monitoring and control in metal MinesDust monitoring and control in metal Mines
Dust monitoring and control in metal Mines
 
Gi2011hotworks abridged
Gi2011hotworks abridgedGi2011hotworks abridged
Gi2011hotworks abridged
 
Gi2011hotworks abridged
Gi2011hotworks abridgedGi2011hotworks abridged
Gi2011hotworks abridged
 

Mehr von John Newquist

1926 motor vechicles and struck by 2021
1926 motor vechicles and struck by 20211926 motor vechicles and struck by 2021
1926 motor vechicles and struck by 2021John Newquist
 
Circular saw safety 2021
Circular saw safety 2021Circular saw safety 2021
Circular saw safety 2021John Newquist
 
Fy20 Most Frequently Cited OSHA Standards in Construction
Fy20 Most Frequently Cited OSHA Standards in ConstructionFy20 Most Frequently Cited OSHA Standards in Construction
Fy20 Most Frequently Cited OSHA Standards in ConstructionJohn Newquist
 
Fy20 most frequently cited manufacturing OSHA
Fy20 most frequently cited manufacturing OSHA Fy20 most frequently cited manufacturing OSHA
Fy20 most frequently cited manufacturing OSHA John Newquist
 
Cy19 gi most freq cited general industry
Cy19 gi most freq cited general industryCy19 gi most freq cited general industry
Cy19 gi most freq cited general industryJohn Newquist
 
Gi 2018 subpart h hazardous materials
Gi 2018 subpart h hazardous materialsGi 2018 subpart h hazardous materials
Gi 2018 subpart h hazardous materialsJohn Newquist
 
Silica 2018 construction
Silica 2018 constructionSilica 2018 construction
Silica 2018 constructionJohn Newquist
 
Gi 2017 loto seven hour
Gi 2017 loto seven hourGi 2017 loto seven hour
Gi 2017 loto seven hourJohn Newquist
 
Combustible Dust Safety 2017
Combustible Dust Safety 2017Combustible Dust Safety 2017
Combustible Dust Safety 2017John Newquist
 
Safety Training Techniques 2017
Safety Training Techniques 2017Safety Training Techniques 2017
Safety Training Techniques 2017John Newquist
 
Outreach Training Requirements 2017 new
Outreach Training Requirements 2017 newOutreach Training Requirements 2017 new
Outreach Training Requirements 2017 newJohn Newquist
 
Safety and Health Training
Safety and Health Training Safety and Health Training
Safety and Health Training John Newquist
 
Swimming Pool Safety 2017
Swimming Pool Safety 2017 Swimming Pool Safety 2017
Swimming Pool Safety 2017 John Newquist
 
Lockout Minor Servicing Exceptions
Lockout Minor Servicing ExceptionsLockout Minor Servicing Exceptions
Lockout Minor Servicing ExceptionsJohn Newquist
 
Osha Update 2017 July 2017
Osha Update 2017 July 2017Osha Update 2017 July 2017
Osha Update 2017 July 2017John Newquist
 
Extreme Weather 2017
Extreme Weather 2017Extreme Weather 2017
Extreme Weather 2017John Newquist
 

Mehr von John Newquist (20)

1926 motor vechicles and struck by 2021
1926 motor vechicles and struck by 20211926 motor vechicles and struck by 2021
1926 motor vechicles and struck by 2021
 
Circular saw safety 2021
Circular saw safety 2021Circular saw safety 2021
Circular saw safety 2021
 
Fy20 Most Frequently Cited OSHA Standards in Construction
Fy20 Most Frequently Cited OSHA Standards in ConstructionFy20 Most Frequently Cited OSHA Standards in Construction
Fy20 Most Frequently Cited OSHA Standards in Construction
 
Fy20 most frequently cited manufacturing OSHA
Fy20 most frequently cited manufacturing OSHA Fy20 most frequently cited manufacturing OSHA
Fy20 most frequently cited manufacturing OSHA
 
Cy19 gi most freq cited general industry
Cy19 gi most freq cited general industryCy19 gi most freq cited general industry
Cy19 gi most freq cited general industry
 
Gi 2018 subpart h hazardous materials
Gi 2018 subpart h hazardous materialsGi 2018 subpart h hazardous materials
Gi 2018 subpart h hazardous materials
 
Respirators 2018
Respirators 2018Respirators 2018
Respirators 2018
 
Silica 2018 construction
Silica 2018 constructionSilica 2018 construction
Silica 2018 construction
 
Gi 2017 loto seven hour
Gi 2017 loto seven hourGi 2017 loto seven hour
Gi 2017 loto seven hour
 
Combustible Dust Safety 2017
Combustible Dust Safety 2017Combustible Dust Safety 2017
Combustible Dust Safety 2017
 
Hepatitis c
Hepatitis cHepatitis c
Hepatitis c
 
Gi 2017 lockout 503
Gi 2017 lockout 503Gi 2017 lockout 503
Gi 2017 lockout 503
 
Safety Training Techniques 2017
Safety Training Techniques 2017Safety Training Techniques 2017
Safety Training Techniques 2017
 
Outreach Training Requirements 2017 new
Outreach Training Requirements 2017 newOutreach Training Requirements 2017 new
Outreach Training Requirements 2017 new
 
Safety and Health Training
Safety and Health Training Safety and Health Training
Safety and Health Training
 
Swimming Pool Safety 2017
Swimming Pool Safety 2017 Swimming Pool Safety 2017
Swimming Pool Safety 2017
 
Pesticide safety
Pesticide safetyPesticide safety
Pesticide safety
 
Lockout Minor Servicing Exceptions
Lockout Minor Servicing ExceptionsLockout Minor Servicing Exceptions
Lockout Minor Servicing Exceptions
 
Osha Update 2017 July 2017
Osha Update 2017 July 2017Osha Update 2017 July 2017
Osha Update 2017 July 2017
 
Extreme Weather 2017
Extreme Weather 2017Extreme Weather 2017
Extreme Weather 2017
 

Kürzlich hochgeladen

VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...Suhani Kapoor
 
Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024ARCResearch
 
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
WIPO magazine issue -1 - 2024 World Intellectual Property organization.
WIPO magazine issue -1 - 2024 World Intellectual Property organization.WIPO magazine issue -1 - 2024 World Intellectual Property organization.
WIPO magazine issue -1 - 2024 World Intellectual Property organization.Christina Parmionova
 
2024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 282024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 28JSchaus & Associates
 
(DIVYA) Call Girls Wakad ( 7001035870 ) HI-Fi Pune Escorts Service
(DIVYA) Call Girls Wakad ( 7001035870 ) HI-Fi Pune Escorts Service(DIVYA) Call Girls Wakad ( 7001035870 ) HI-Fi Pune Escorts Service
(DIVYA) Call Girls Wakad ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up NumberMs Riya
 
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxPeter Miles
 
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130 Available With Room
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130  Available With RoomVIP Kolkata Call Girl Jatin Das Park 👉 8250192130  Available With Room
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130 Available With Roomishabajaj13
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfahcitycouncil
 
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile ServiceCunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile ServiceHigh Profile Call Girls
 
2024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 272024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 27JSchaus & Associates
 
CBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCongressional Budget Office
 
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...Suhani Kapoor
 
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...Suhani Kapoor
 

Kürzlich hochgeladen (20)

Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
 
Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024
 
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wadki ( 7001035870 ) HI-Fi Pune Escorts Service
 
WIPO magazine issue -1 - 2024 World Intellectual Property organization.
WIPO magazine issue -1 - 2024 World Intellectual Property organization.WIPO magazine issue -1 - 2024 World Intellectual Property organization.
WIPO magazine issue -1 - 2024 World Intellectual Property organization.
 
2024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 282024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 28
 
(DIVYA) Call Girls Wakad ( 7001035870 ) HI-Fi Pune Escorts Service
(DIVYA) Call Girls Wakad ( 7001035870 ) HI-Fi Pune Escorts Service(DIVYA) Call Girls Wakad ( 7001035870 ) HI-Fi Pune Escorts Service
(DIVYA) Call Girls Wakad ( 7001035870 ) HI-Fi Pune Escorts Service
 
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up Number
 
Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...
Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...
Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...
 
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
 
How to Save a Place: 12 Tips To Research & Know the Threat
How to Save a Place: 12 Tips To Research & Know the ThreatHow to Save a Place: 12 Tips To Research & Know the Threat
How to Save a Place: 12 Tips To Research & Know the Threat
 
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130 Available With Room
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130  Available With RoomVIP Kolkata Call Girl Jatin Das Park 👉 8250192130  Available With Room
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130 Available With Room
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdf
 
Rohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile ServiceCunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
Cunningham Road Call Girls Bangalore WhatsApp 8250192130 High Profile Service
 
2024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 272024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 27
 
CBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related Topics
 
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
VIP Call Girls Service Bikaner Aishwarya 8250192130 Independent Escort Servic...
 
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
 
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
 

510 tunneling safety 2016

  • 2. 1988 • Milwaukee WI • Methane gas was detected in a 40-foot-deep tunnel that was under construction. • The mining machine was automatically shut down, and all the employees were evacuated. • Ten minutes later, three employees entered the area to determine if the atmosphere in the tunnel was safe for reentry. • An explosive mixture of methane gas had developed in the air. • Apparently, the grout pump ignited the gas and caused an explosion. • The three employees were badly burned, and they died of asphyxiation due to overexposure to carbon monoxide.
  • 3. OSHA Specific Requirements • Check-in/check-out. • The employer shall maintain a check-in/check-out procedure that will ensure that above- ground personnel can determine an accurate count of the number of persons underground in the event of an emergency. • However, this procedure is not required when the construction of underground facilities designed for human occupancy has been sufficiently completed so that the permanent environmental controls are effective, and when the remaining construction activity will not cause any environmental hazard or structural failure within the facilities. 1926.800(c)
  • 4. Safety Instruction • All employees shall be instructed in the recognition and avoidance of hazards associated with underground construction activities including, where appropriate, the following subjects: • Air monitoring: • Ventilation: • Illumination: • Communications: • Flood control: • Mechanical equipment: • Personal protective equipment: • Explosives: • Fire prevention and protection: and • Emergency procedures, including evacuation plans and check- in/check-out systems. 1926.800(d)
  • 5. Emergency Provisions• Hoisting capability. • When a shaft is used as a means of egress, the employer shall make advance arrangements for power- assisted hoisting capability to be readily available in an emergency, unless the regular hoisting means can continue to function in the event of an electrical power failure at the jobsite. • Such hoisting means shall be designed so that the load hoist drum is powered in both directions of rotation and so that the brake is automatically applied upon power release or failure. 1926.800(g)(1)
  • 6. Emergency Provisions• Self-rescuers. • The employer must provide self-rescuers approved by the National Institute for Occupational Safety and Health under 42 CFR part 84. • The respirators must be immediately available to all employees at work stations in underground areas where employees might be trapped by smoke or gas. • The selection, issuance, use, and care of respirators must be in accordance with 29 CFR 1926.103. 1926.800(g)(2)
  • 7. Emergency Provisions • Designated person. • At least one designated person shall be on duty above ground whenever any employee is working underground. • This designated person shall be responsible for securing immediate aid and keeping an accurate count of employees underground in case of emergency. • The designated person must not be so busy that the counting function is encumbered. 1926.800(g)(3)
  • 8. Emergency Provisions• Emergency lighting. • Each employee underground shall have an acceptable portable hand lamp or cap lamp in his or her work area for emergency use, unless natural light or an emergency lighting system provides adequate illumination for escape. 1926.800(g)(4)
  • 9. Emergency Provisions • Rescue teams. • On jobsites where less than 25 employees work underground at one time, the employer shall provide (or make arrangements in advance with locally available rescue services to provide) at least one 5-person rescue team to be either on the jobsite or within one-half hour travel time from the entry point. 1926.800(g)(5)(ii)
  • 10. Hazardous Classifications • Potentially gassy operations. • Underground construction operations shall be classified as potentially gassy if either: • Air monitoring discloses 10 percent or more of the lower explosive limit for methane or other flammable gases measured at 12 inches (304.8 mm) to + or - 0.25 inch (6.35 mm) from the roof, face, floor or walls in any underground work area for more than a 24-hour period: or • The history of the geographical area or geological formation indicates that 10 percent or more of the lower explosive limit for methane or other flammable gases is likely to be encountered in such underground operations. 1926.800(h)(1)
  • 11. Air Quality and Monitoring. • Where this paragraph requires monitoring of airborne contaminants "as often as necessary," the competent person shall make a reasonable determination as to which substances to monitor and how frequently monitor, considering at least the following factors: • Location of jobsite: Proximity to fuel tanks, sewers, gas lines, old landfills, coal deposits, and swamps; • Geology: • History: Presence of air contaminants in nearby jobsites, changes in levels of substances monitored on the prior shift; and • Work practices and jobsite conditions: The use of diesel engines, use of explosives, use of fuel gas, volume and flow of ventilation, visible atmospheric conditions, decompression of the atmosphere, welding, cutting and hot work, and employees' physical reactions to working underground. 1926.800(j)(1)(i)(B)
  • 12. Air Quality and Monitoring. • Recordkeeping. • A record of all air quality tests shall be maintained above ground at the worksite and be made available to the Secretary of Labor upon request. • The record shall include the location, date, time, substance and amount monitored. • Records of exposures to toxic substances shall be retained in accordance with 1926.33 of this chapter. • All other air quality test records shall be retained until completion of the project. 1926.800(j)(3)
  • 13. Ventilation• Fresh air shall be supplied to all underground work areas in sufficient quantities to prevent dangerous or harmful accumulation of dusts, fumes, mists, vapors or gases. • Mechanical ventilation shall be provided in all underground work areas except when the employer can demonstrate that natural ventilation provides the necessary air quality through sufficient air volume and air flow. • A minimum of 200 cubic feet of fresh air per minute shall be supplied for each employee underground. 1926.800(k)(1)
  • 14. Fire Control • Flammable or combustible materials shall not be stored above ground within 100 feet (30.48m) of any access opening to any underground operation. • Where this is not feasible because of space limitations at the jobsite, such materials may be located within the 100-foot limit, provided that: • They are located as far as practicable from the opening; and • Either a fire-resistant barrier of not less than one-hour rating is placed between the stored material and the opening, or additional precautions are taken which will protect the materials from ignition sources. 1926.800(m)(7) Oxygen and acetylene stored together is a violation.
  • 15. Fire Control • Lighting fixtures in storage areas, or within 25 feet (7.62 m) of underground areas where oil, grease, or diesel fuel are stored, shall be approved for Class I, Division 2 locations, in accordance with Subpart K of this part. 1926.800(m)(9)
  • 16. Portal Areas • Competent persons conducting such inspections shall be protected from loose ground by location, ground support or equivalent means 1926.800(o)(3)
  • 17. Portal Areas • Suitable protection shall be provided for employees exposed to the hazard of loose ground while installing ground support systems. 1926.800(o)(3)
  • 26. OSHA Citations • Rigging • no capacity marked
  • 27. OSHA Citations • GHS • Spill Control
  • 30. Structural Issues • Rock Fall - Fall of rock blocks of major dimensions. The different mechanisms involved are wedge or planar failure.. • Collapse Heading collapse - failure of the heading / lining failure . • Daylight Collapse Heading collapse - lining failure of the heading that reaches the surface creating a crater. • Excessive Deformation - Excessive deformations inside the tunnel or at the surface. This can occur for example due to deficient design, construction defects and/or due to particular type of terrains such as swelling and squeezing ground, which had not been predicted. • Flooding - Comprises cases where the tunnel was invaded by large quantities of underground water. • Rock Burst - Spalling Overstressing of massive or intact brittle rock, i.e. the stresses developed in the ground exceed the local strength of the material. It can cause spalling or in the worst cases sudden and violent failure of the rock mass • Portal failure - Particular locations of a tunnel, where there is a lower • Shaft failure - resistance of ground mass and/ or concentration of stresses. • Other - Other types of collapse that include slope failures, etc
  • 32. Rock Fall • Rock fall blocking the TBM at the Covao tunnel in 2006 (Madeira Island, Portugal)
  • 33. Collapse • The large collapse occurred in front of the face and stopped the cutter head rotation, creating a cavern more than 10 m high over the TBM. • This was an example of a full collapse of the face.
  • 34. Collapse• Wienerwald Austria • In this case, ground water led to de-compaction and bulking of the sandstone, which caused the shear strength to decrease. • From this it follows that the strength of rock was very low and ground pressure loaded the temporary shotcrete shell, which was not designed for that kind of high loading. • Therefore the shotcrete shell spalled off and the lattice girder was deformed.
  • 35. Daylight Collapse • These are collapses that reach the surface creating a crater. • Munich Metro in 1994 • No deaths
  • 36. Daylight Collapse • Sao Paulo Brazil 2007 • 7 deaths • Open face tunnelling is cheap. • New Austrian Tunnelling Method (NATM) is much less expensive than a soft ground TBM, but much less safe • A combination of explosives and mechanical excavation techniques were being used. • 'The top heading of the failed tunnel was fully excavated in rock. • There was approximately 6m of rock above the tunnel, • Support consisted of steel arch girders at 800mm centres, and 350mm thick steel fibre reinforced sprayed concrete. • 'The vertical displacements measured at the tunnel crown were in the range of 3mm when the top heading excavation was completed. • Two to three days before the accident, the rate of those displacements increased, and they reached 15mm to 20mm.
  • 37. Daylight Collapse • 2003: Shanghai's underground Pearl Line, China • $80 million • The accident occurred in a cross passage between the two parallel tunnel tubes that had already been driven using earth-pressure- balance TBMs. • Shortly before the cross passage broke through, at a depth of about 35 m, massive inrushes of material and water occurred, which the tunnel crew was not able to bring under control and which resulted in a large scale subsidence at the
  • 38. Daylight Collapse • South Korean city of Taegu on 22 January 2001 • Failure of a diaphragm wall. • Part of a station excavation pit caved in, burying a bus, killing three passengers and damaging neighboring buildings. • The accident was caused by a load not considered in the design phases and due to unforeseen soil conditions. • $24 million
  • 39. Flooding • It is during the construction of underwater tunnels that largest scale floodings have occurred. • The ground under rivers, channels and bays is normally weak and under high water pressure and therefore extreme safety measures and efficient protection against water inflow are normally required.
  • 40. Flooding • Seikan tunnel is a 53.85 km long railway tunnel in Japan • 1963-1976 • Four floods • 23 deaths • Leaks and soft rock • TBM not practical due to the various types of soils. • Drill and pound. • A great majority of the tunnel crosses heavily fissured rock (9 large shear zones). The sea and underground water penetrate into these zones and the maximum water pressure is about 25 MPa
  • 41. Flooding • Lausanne, Switzerland • A huge amount of soil and water (1400m3) displaced into the tunnel and caused extensive damage
  • 42. Rockburst/Spalling • This type of event is caused by the overstressing of massive or intact brittle rock, i.e. the stresses developed in the ground exceed the local strength of the material. • It can cause spalling or in the worst cases sudden and violent failure of the rock mass
  • 43. Excessive Deformation • These are cases where excessive deformations occur inside the tunnel or at the surface but an actual total collapse does not happen. • This can occur for example due to deficient design, construction defects and/or due to particular type of terrains such as swelling and squeezing ground, which had not been predicted.
  • 44. Excessive Deformation • Rotarelle to San Vittore tunnel, Italy 1991 • After 650m of excavation, enormous ground pressures caused cracking of the shotcrete, buckling of the steel arches after a few hours, and deformations of 200 mm in 24h and 400 mm after 12 days • The deformations were caused by swelling clay filling of the rock.
  • 45. Excessive Deformation • Squeezing is characterized large time-dependent convergence during tunnel excavation. • Failure of the support system. • Inadequate support for such ground conditions. 1999: Bolu Tunnel, Turkey An earthquake caused the collapse of a section of the Bolu tunnel, part of the Anatolian highway, even though the tunnel had been designed to withstand earthquakes. $115 million loss
  • 46. 1908-1913 • Lotschberg tunnel • Switzerland • Use of timber supports after collapse killed 25 in 1908
  • 47. Hawks Nest WV • 1930s • A simple diversion tunnel for the New River in West Virginia • After workers discovered silica in the rock they were told to mine it as a by-product of tunnel construction, however, they were never given any masks or protective gear. • Hundreds of workers developed silicosis due to the long-term exposure of silica dust in their lungs.
  • 48. New York City Third Water Tunnel • The largest infrastructure project in New York state history is currently tunneling below New Yorker's feet to provide a third connection to the upstate water supply
  • 49. St. Gotthard Road Tunnel, 1969-1980 • At the time it was completed, this 10-mile tunnel in Switzerland was the longest road tunnel in the world. • Tragically, 19 people died working on the tunnel— which was created to connect central Switzerland with Milan, Italy through the Alps, providing a faster and safer year-round alternative to the winding Gotthard Pass.
  • 50. Big Dig Ceiling Collapse • July 10, 2006 • Concrete ceiling panel and debris weighing 26 tons fell in Boston's Fort Point Channel Tunnel • The panel fell on a car killing a passenger and injuring the driver. • The collapse of the ceiling structure began with the simultaneous creep-type failure of several anchors embedded in epoxy in the tunnel's roof slab. • Each of the panel's intersecting connection points consists of several individual bolts anchored into the roof slab concrete. • The failure of a group of anchors set off a chain reaction which caused other adjacent connection groups to creep then fail
  • 51. Big Dig Ceiling Collapse • Not only were the bolts too short, but the epoxy used to glue the bolts into the concrete was not up to standard.
  • 52. Big Dig Ceiling Collapse • Major cause of the collapse to "epoxy creep“ • On August 8, 2007, a Suffolk County Grand Jury indicted epoxy company Powers Fasteners, Inc., on one charge of involuntary manslaughter, with the maximum penalty in Massachusetts being a fine of one thousand dollars.[10] • The epoxy used in the D Street portal that failed cost $1287.60. The cost to redesign, inspect, and repair all of the tunnels after the collapse was $54 million.[1
  • 53. 2004: Circle Line, Singapore • Collapse of a construction pit resulted in the death of four workers plus the collapse of an adjoining highway. • It eventually was found that the most apparent cause of the collapse was that the retaining wall could not handle the stress of holding up the tunnel, forcing it to give way.
  • 54. 1994: Heathrow Express Link • London • Three tunnels forming part of the Heathrow Express Link, connecting central London and Heathrow Airport, caved in and took several buildings with them. • $141 million • According to the HSE, a chain of events led directly to the collapse. • This included a failure to check substandard construction over a period of some three months, pressure grouting that damaged the tunnel plus inadequately executed repairs some two months before the collapse.
  • 55. 1994/95: Metro • Taipei, Taiwan • When the Metro was being built in Taiwan in the 1990s, several serious tunnel collapses occurred, causing major property damage to adjacent buildings as well as serious liability losses. • $41 million • Difficult geology, with fractured rock and massive inflows of water, countless cave-ins, mud and rock slides caused by massive inflows of groundwater. • Eleven people were killed in the accidents.
  • 56. 1999: Tunnel in Hull • England • During one of the tunnel drives for a 6.5 mile underground sewer in Hull, England, a deformation in the floor of the tunnel shell led to flooding of the tunnel and subsidence at the surface, resulting in substantial damage to buildings, roads and utility lines. • Machines and the tunnel were abandoned. • $55 million
  • 57. XIAN Subway • 2013 China • At least two are dead after an accident at a subway construction site in Xi’an, Shaanxi province this morning. • At around 2:40 am, a tunnel caved in as nine workers were in the midst of building Line 3. • Four have been rescued, but of the five that were buried, two have been found dead while the other three are still missing
  • 58. Dec 2014 • Vietnam • Rescuers have created a 16 cm-wide access hole to the location where 12 workers have been trapped inside a collapsed tunnel section at a hydropower plant in the Central Highlands province of Lam Dong They may have assumed that the dry season had come and it was safe to dig, but this year the rainy season lasted too long. With heavy rains making the foundation weak, sinkages occurred in the tunnel. And given the Central Highlands’ geological formations, digging up a big rock may lead to the whole tunnel’s collapse.
  • 59. 2000 • Dulles Airport • One dead • At the time of the accident, about 700 ft of the approximately 40 ft wide by 16 ft tall tunnel had been excavated. • Employee #1 was using a shotcrete hose to spray the side walls at the tunnel's earthen face when the top and side of the tunnel collapsed. • In the week before the tunnel gave way, there were three partial collapses, each increasing in severity
  • 60. July 2015 • A construction worker who was killed when a winch he was operating broke loose from its anchor at a tunneling site in the High Desert has been identified as David Padilla, 38, of Pahrump, Nevada.
  • 61. February 2015 • Seattle WA • WSDOT now says five workers were installing rebar for a concrete wall at the tunnel’s north portal work zone. • The wall of rebar gave way, injuring four of the five workers.
  • 62. 2013 • Sunol CA • On August 22, 2013, Employee #1, was working on a pipeline project. • A piece of cement grout approximately 1.5 feet by 1.5 feet by 6 feet long fell out of the tunnel face approximately 3 feet above the invert. • The cement pinned Employee #1's leg against a roadheader. • Employee #1 sustained bruising/contusions/abrasions.
  • 63. 2013 • On June 17, 2013, an employee was working as a heavy equipment mechanic for a bridge, tunnel, and highway construction firm. • He was on a segment build deck, assembling a tunnel boring machine. • He fell off the deck, falling a distance of 10 feet. He sustained a strain or sprain in his left ankle
  • 65. 2011 • Webster NY • Employee #1, a locomotive operator, was moving muck buckets and equipment to the head section of a tunnel. • When the operator reached the end of the tunnel, the locomotive failed to stop and Employee #1 was crushed between the locomotive and the conveyor on the tunnel boring machine. • Employee #1 was killed.
  • 66. 2011 • Woodland CA • Employee #2, a laborer, noticed a hole in a material chute in the No. 196 tunnel conveyor system. • Employee #1 was joined by Employee #2 in the reclaim tunnel to schedule and plan a repair operation. • As the two Employees exited the tunnel and walked away from the overhead No. 196 Conveyor, a 10 pound rock fell off the conveyor striking Employee #1 in the head and Employee #2 in the back, knocking both employees to the ground. • Employee #1 was knocked unconscious and landed on top of Employee #2.
  • 67. 2009 • Kermit, WV • Employee #1 was engaged in the preparations for raising the height of a tunnel liner. • Employee #1 bored several holes for taking core samples and pictures were taken. • Employee #1 entered the tunnel through the west portal entrance, with his excavator equipped with a hoe ram. • After reaching the necessary work station, Employee #1 began hammering out the center part of the tunnel's liner to remove it. • About 30 minutes following the start of work, a section of the roof fell, crushing and killing Employee #1.
  • 68. 2009 • Alexandria VA • Employee #1 was working in a subway tunnel for the Washington Metropolitan Area Transit Authority. • A train passed by the location where Employee #1 was standing. • Coworkers reported that they heard a noise and then the train stopped. • When the coworkers found Employee #1, it was apparent that he had been struck by the train and suffered trauma to his head and one leg.
  • 69. 2009 • Cartersville GA • Employee #1 was packing straw around the east end of the tunnel plate. • The top, unprotected end of the tunnel collapsed and buried Employee #1's head and neck in mud on top of the tunnel plate. • Coworkers attempted to rescue Employee #1; however, they were unsuccessful and he was pronounced dead at the site.
  • 70. 2008• Employees #1 though #5, were repairing the floor of the south bypass conduit water tunnel located under Lake Las Vegas in Henderson, Nevada. • The tunnel was two miles long and seven feet in diameter. • They were preparing to pour concrete on the tunnel floor. • Two workers activated the ventilation fan from outside. • Concrete was carried in eight buggy carts pulled by bobcat. • Behind them, the mechanic and Project Superintendent followed on a propane-operated golf cart. • Around 10:00 a.m., these employees arrived at the work location and found that the mechanical ventilation fan had been shut down. • Several unsuccessful attempts were made to start the fan. • The Project Superintendent and foreman decided that work would continue, after measuring the natural air flow using a handheld Mini Thermo-Anemometer by Extech Instrument. • At 11:15 a.m., the foreman radioed from inside tunnel that employees were experiencing difficulty breathing, chest pains, and fatigue. • The project superintendent sent golf carts and removed all employees from the tunnel about 12:16 p.m. • Employees #1 through #5 were treated for asphyxia and carbon monoxide poisoning at University Medical Center (UMC) in Las Vegas and St. Rose De Lima in Henderson
  • 71. 2007 • Houston TX • Employee and five coworkers were working attempting to install a 60-in. by 10-ft by 0.5-in. steel pipe casing for the 42-in. regional main water line. • The site was comprised of a 60-ft by 40-ft shaft which led down to a tunnel, which had already pushed the 60-in. steel pipe approximately 120-130-ft laterally under the Cypress Creek. • The employee was cleaning the excess dirt from the 60-in. pipe as the pipe was hydraulically pushed inside. • A breach occurred, immediately filling the tunnel and the shaft with water. • All of the coworkers were able to escape except the employee.
  • 72. 2005 • Minneapolis MN • At approximately 7:00 a.m. on September 6, 2005, Employee #1 entered the work area on the fifth floor of the project. • Employee #1 was walking through tunnel forms to prepare the forms for a concrete pour. • As Employee #1 walked toward the end of the form inspecting his work, he stepped through a floor hole and fell approximately 45 ft to his death.
  • 73. 2000 • Chanilly VA • The 27 ft deep passenger walkway tunnel was being constructed from one terminal to another. • At the time of the accident, about 700 ft of the approximately 40 ft wide by 16 ft tall tunnel had been excavated. • Employee #1 was using a shotcrete hose to spray the side walls at the tunnel's earthen face when the top and side of the tunnel collapsed. • Fire and emergency services were called but they were unable to rescue Employee #1.