PROGRAM MANAGEMENT 2.0
RISK MANAGEMENT
Jeanne Bradford, John Carter, Scott Elliott
April, 2018
2
22
AGENDA
1 Schedule Prediction Accuracy
Exercise in creating diagram
2 Metrics for estimating progress at the engineering task levels
Exercise in creating a Task Burn- Down Chart
3 Monitoring Progress: Earned Value – Scope, Cost and Time
Exercise in managing Partner’s delay
4 Risk & Circle Dot Charts: What happens if there is a breakdown?
Exercise
5 Management Systems
Covered in this presentation
3
33
KEY LEARNING POINTS
Monitoring Project Performance for Internal and External Partners (TCGen’s Innovate Products Faster, Greene’s Head First PMP)
1 Metrics for estimating progress (at the engineering task levels)
2 Monitoring Progress (Earned Value – Scope, Cost and Time)
3 Risk Monitoring
4 Circle Dot Charts
5 Management Systems
Participants will understand how to create and update Schedule Prediction Accuracy charts and how to demonstrate program status
by showing scope, cost and time in one chart.
They will also gain skill in creating and using:
4
44
Risk Monitoring
5
55
ESSENTIAL PROCESSES FOR MANAGING RISKS
• Assess – Learn from the past, create checklist, review prior audits, go outside, generate list of potential risks
• Plan – Perform impact and probability analysis, prioritize, and make plans
• Monitor – Keep an active watch for trouble by monitoring predictive metrics
• React – Re-mediate if and when there is trouble
Assess Plan
Monitor &
React
6
66
RISK RESPONSE OPTIONS
Risk Response Description Examples/Notes
Avoidance
Avoiding the risk.
Changing the project plan to eliminate
the risk.
Changing the project plan to protect a
project objective from the impact.
Reducing the scope remove high-risk tasks.
Adding resources or time.
Adopting a proven approach rather than new one.
Removing a “problem” resource.
Acceptance
Accepting the consequences of the risk.
The project plan is not changed to deal
with the risk.
A better response strategy cannot be
identified.
Active acceptance.
Passive acceptance.
No action.
Contingency allowance (reserves).
Communication plan around possible major cost increases if
this risk occurs.
Monitor and prepare
Accepting the risk for now.
Closely monitor the risk and develop
alternate action plans proactively if the
event occurs.
Contingency plan.
Fallback plan.
Establish criteria that will trigger the implementation of the
response plans.
Source: Project Management, Absolute Beginner’s Guide, Gregory Horine Que Publishing, Indianapolis 2013
7
77
Risk Response Description Examples/Notes
Mitigation
Taking action to reduce the likelihood that
the risk will occur.
Taking action to reduce the impact of the
risk.
Reducing the probability is always more
effective than minimizing the
consequences.
Adopting less complex approaches.
Planning on more testing.
Adding resources or time to the schedule.
Assigning a team member to visit the seller’s facilities
frequently to learn about potential delivery problems as
early as possible.
Providing a less-experienced team member with additional
training.
Deciding to prototype a high-risk solution element.
Transference
Transferring ownership of the risk factor.
Shifting the consequence of a risk and the
ownership of the response to a third party.
Outsourcing difficult work to a more experienced company.
Fixed price contract.
Contract, insurance, warranties, guarantees, and so on.
Used most often for financial risk exposure.
Does not eliminate the risk.
RISK RESPONSE OPTIONS
Source: Project Management, Absolute Beginner’s Guide, Gregory Horine Que Publishing, Indianapolis 2013
8
88
ESSENTIAL PROCESSES FOR MANAGING RISKS
Which Business Problems Does the Tool Solve?
• Innovation brings with it additional risks which can still be managed by the team on its own
• Helps improve project execution because it can help the team anticipate, prevent, and mitigate risks
Benefits:
• You can identify risks before they occur
• There is a reduction of risk impact due to early detection
• Quantitative metrics that help clarify when to act on a risk item
• Action accelerates because of the clear thresholds and the agreement to follow a process
9
99
RISK MANAGEMENT MATRIX
Status Risk Impact Likelihood Metric Threshold
Current
Value
Date Action Plan
Global team does not communicate
frequently enough. Want to keep
weekly communication high.
4 7
Meetings per
week
2 2.5 Current
Invoke team’s elevation plan,
purchase videoconferencing
systems, change incentives.
Data captured on long forms from
online interaction sessions must not be
lost if user gets error message or
returns to screen.
6 6 % Data Lost 10% 25% Q3 FY 13
Design review current forms layout,
bring in Expert Co. consulting firm,
change staff balance.
Server must respond to users rapidly
under fairly high loads – expect page to
be updated way under a second.
7 7 Ms at 1000 Users 259 1000 Q2 FY 13
Add architect and create tiger team
with system optimization
experience.
Financial partner cooperation is critical
to this household finance program, and
we need to have a sufficient number at
launch
4 6 Institutions 1000 247 Q3 FY 13
Increases business development
staff, change incentive
compensation, add external business
development firm.
Mobile operating system support must
be in place at the same time as
launching the desktop version.
5 6 On Time Q4 FY 14 Q4 FY 14 Current
Track schedule prediction accuracy.
If slip then recruit internal team
from Vietnam (permission already
granted).
10
1010
Status Risk Impact Likelihood Metric Threshold
Current
Value
Date Action Plan
Global team does not communicate
frequently enough. Want to keep
weekly communication high.
4 7
Meetings per
week
2 2.5 Current
Invoke team’s elevation plan,
purchase videoconferencing
systems, change incentives.
Data captured on long forms from
online interaction sessions must not be
lost if user gets error message or
returns to screen.
6 6 % Data Lost 10% 25% Q3 FY 13
Design review current forms layout,
bring in Expert Co. consulting firm,
change staff balance.
Server must respond to users rapidly
under fairly high loads – expect page to
be updated way under a second.
7 7 Ms at 1000 Users 259 1000 Q2 FY 13
Add architect and create tiger team
with system optimization
experience.
Financial partner cooperation is critical
to this household finance program, and
we need to have a sufficient number at
launch
4 6 Institutions 1000 247 Q3 FY 13
Increases business development
staff, change incentive
compensation, add external business
development firm.
Mobile operating system support must
be in place at the same time as
launching the desktop version.
5 6 On Time Q4 FY 14 Q4 FY 14 Current
Track schedule prediction accuracy.
If slip then recruit internal team
from Vietnam (permission already
granted).
RISK MANAGEMENT MATRIX
Impact of Risk
1 = Low,10 = High
Likelihood
1 = Low,10 = High
Metric Value
triggering action
What to do if
Threshold reached
11
1111
CONTROLLING RISKS
• Tackle high risk tasks first
• Maximize resources on high-risk tasks
• Postpone low-risk tasks
• Use iterative, phased approaches
• Frequent, smaller deliverables reduce overall risk
• Change the way you design
• Create a better balance between theory and experimentation; lean more on experimentation to get fast answers
• Get to “no” more quickly on parallel paths
• QA the planning process
• Leverage independent QA audits
12
1212
MITIGATING RISKS: ALTERNATIVES
1 Soft Skills
2 Meetings
3 Dot Voting
4 Out of Bounds
5 Communication Paths
6 Fast Tracking and Crashing
Assess Plan
Monitor
&
React
These Tools are for the “Monitor and React” phase
13
1313
SOFT SKILLS: EXECUTING
A successful Program Manager has these critical soft skills
Is the leader of communications:
sets the tone and protocols for them
When there are breakdowns, emphasizes
the outcome the team is trying to produce
not who is to blame
14
1414
MANAGING YOUR TEAM & MEETINGS
• “Smooth” program management starts by running effective meetings
• Communicating effectively outside of team meetings is where the real work gets done however
• Focusing on the outcome rather than on blaming people
• Establishing clear priorities and sticking with them
• Tracking the status of each activity (sub-project) within the project
• Using metrics to see the big picture and to drive improvement
Necessary Conditions for “Execution: Managing Teams & Meetings”
Communication
Skills
Communication
Tools
Tracking Capability Metrics
• DOCUMENTS: Communication protocols, Metrics dashboard, Priority lists (These are suggested, not in place yet at D+M)
15
1515
FAST TRACKING & CRASHING TASKS
Source: Dynamics of Project Performance: System Dynamics and Project Management , Lyneis, MIT, 2003, p 16
Worry about taking shortcuts that only cause delay because of more rework
Traditional project
Overlap phases
Compress each phase
Reduce Rework
Planned
Duration
Actual
Phase 1
Rework
Phase 2
16
1616
EXERCISE: MONITORING RISK
Possibilities:
Build a Risk Management Matrix from a
project
Have a role-playing scenario where a risk
has crossed the threshold and Partner is
not responding well
17
17
TCGen Inc.
Menlo Park
CA, 94025
jcarter@tcgen.com
(650) 733-5310

Weitere ähnliche Inhalte

Was ist angesagt?

MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project Presentation
Khem Singh
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
Serdar Temiz
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
nazi2020
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
Nithin Dev
 

Was ist angesagt? (20)

Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
 
Factors for Successful Projects
Factors for Successful ProjectsFactors for Successful Projects
Factors for Successful Projects
 
MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project Presentation
 
Chap 6 Developing A Project Plan
Chap 6 Developing A Project PlanChap 6 Developing A Project Plan
Chap 6 Developing A Project Plan
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Project management milestones-webinar
Project management milestones-webinarProject management milestones-webinar
Project management milestones-webinar
 
Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve
 
Project control. Management
Project control. ManagementProject control. Management
Project control. Management
 
Chap06 project time management
Chap06 project time managementChap06 project time management
Chap06 project time management
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Building a-project-schedule
Building a-project-scheduleBuilding a-project-schedule
Building a-project-schedule
 
Assessing Enterprise Project Risk
Assessing Enterprise Project RiskAssessing Enterprise Project Risk
Assessing Enterprise Project Risk
 
Project time management
Project time managementProject time management
Project time management
 
DCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckDCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality Check
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
Neil Varma - Stages of Project Management
Neil Varma - Stages of Project ManagementNeil Varma - Stages of Project Management
Neil Varma - Stages of Project Management
 
Using Microsoft Project 2003
Using Microsoft Project 2003Using Microsoft Project 2003
Using Microsoft Project 2003
 

Ähnlich wie Program Management 2.0: Risk Management

C. Burcham - Project Closure Report
C. Burcham - Project Closure ReportC. Burcham - Project Closure Report
C. Burcham - Project Closure Report
Cheryl Burcham
 
Agile Truths and Misconceptions
Agile Truths and MisconceptionsAgile Truths and Misconceptions
Agile Truths and Misconceptions
Richard Cheng
 
Sas Presentation
Sas PresentationSas Presentation
Sas Presentation
pats384888
 
QM-021-PDCA
QM-021-PDCAQM-021-PDCA
QM-021-PDCA
handbook
 

Ähnlich wie Program Management 2.0: Risk Management (20)

Project management (A Basic Approach)
Project management (A Basic Approach)Project management (A Basic Approach)
Project management (A Basic Approach)
 
Breaking the Project Failure Cycle
Breaking the Project Failure CycleBreaking the Project Failure Cycle
Breaking the Project Failure Cycle
 
Process Improvement Teams.pptx
Process Improvement Teams.pptxProcess Improvement Teams.pptx
Process Improvement Teams.pptx
 
Project Management How To
Project Management How ToProject Management How To
Project Management How To
 
C. Burcham - Project Closure Report
C. Burcham - Project Closure ReportC. Burcham - Project Closure Report
C. Burcham - Project Closure Report
 
Strategies for successful_engineering_management
Strategies for successful_engineering_managementStrategies for successful_engineering_management
Strategies for successful_engineering_management
 
Identifying a project in trouble and re-planning
Identifying a project in trouble and re-planningIdentifying a project in trouble and re-planning
Identifying a project in trouble and re-planning
 
significance_of_test_estimating_in_the_software_development.pdf
significance_of_test_estimating_in_the_software_development.pdfsignificance_of_test_estimating_in_the_software_development.pdf
significance_of_test_estimating_in_the_software_development.pdf
 
Project management processes ch3 (1)
Project management processes ch3 (1)Project management processes ch3 (1)
Project management processes ch3 (1)
 
significance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptxsignificance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptx
 
Agile Truths and Misconceptions
Agile Truths and MisconceptionsAgile Truths and Misconceptions
Agile Truths and Misconceptions
 
Challenging Aspects of Modern Project Management
Challenging Aspects of Modern Project ManagementChallenging Aspects of Modern Project Management
Challenging Aspects of Modern Project Management
 
Sas Presentation
Sas PresentationSas Presentation
Sas Presentation
 
Lean Six Sigma: DMAIC In-Depth
Lean Six Sigma: DMAIC In-DepthLean Six Sigma: DMAIC In-Depth
Lean Six Sigma: DMAIC In-Depth
 
Project Management
Project ManagementProject Management
Project Management
 
Agile Methodology
Agile MethodologyAgile Methodology
Agile Methodology
 
Project Management Control
Project Management ControlProject Management Control
Project Management Control
 
significance_of_test_estimating_in_the_software_development.pdf
significance_of_test_estimating_in_the_software_development.pdfsignificance_of_test_estimating_in_the_software_development.pdf
significance_of_test_estimating_in_the_software_development.pdf
 
A3 Management (Part 2 of 2)
A3 Management (Part 2 of 2)A3 Management (Part 2 of 2)
A3 Management (Part 2 of 2)
 
QM-021-PDCA
QM-021-PDCAQM-021-PDCA
QM-021-PDCA
 

Mehr von John Carter

Mehr von John Carter (17)

Product Roadmaps Done Right
Product Roadmaps Done RightProduct Roadmaps Done Right
Product Roadmaps Done Right
 
Product Development Metrics: More Harm Than Good?
Product Development Metrics: More Harm Than Good?Product Development Metrics: More Harm Than Good?
Product Development Metrics: More Harm Than Good?
 
Innovation Sprint Readiness Scorecard
Innovation Sprint Readiness ScorecardInnovation Sprint Readiness Scorecard
Innovation Sprint Readiness Scorecard
 
Never The Twain Shall Meet: Can Agile Work with a Waterfall Process?
Never The Twain Shall Meet: Can Agile Work with a Waterfall Process?Never The Twain Shall Meet: Can Agile Work with a Waterfall Process?
Never The Twain Shall Meet: Can Agile Work with a Waterfall Process?
 
Agile Project Management in a Waterfall World: Managing Sprints with Predicti...
Agile Project Management in a Waterfall World: Managing Sprints with Predicti...Agile Project Management in a Waterfall World: Managing Sprints with Predicti...
Agile Project Management in a Waterfall World: Managing Sprints with Predicti...
 
Learning from the Trenches: Scrum for Hardware
Learning from the Trenches: Scrum for HardwareLearning from the Trenches: Scrum for Hardware
Learning from the Trenches: Scrum for Hardware
 
Leadership and Product Strategy
Leadership and Product StrategyLeadership and Product Strategy
Leadership and Product Strategy
 
Customer Collaboration & Product Innovation Using Social Networks
Customer Collaboration & Product Innovation Using Social NetworksCustomer Collaboration & Product Innovation Using Social Networks
Customer Collaboration & Product Innovation Using Social Networks
 
Strategy Leadership and Product Portfolio Management
Strategy Leadership and Product Portfolio ManagementStrategy Leadership and Product Portfolio Management
Strategy Leadership and Product Portfolio Management
 
Agile: Not Just for Sofware
Agile: Not Just for SofwareAgile: Not Just for Sofware
Agile: Not Just for Sofware
 
Agile Methods to Develop Tangible Products Quickly
Agile Methods to Develop Tangible Products QuicklyAgile Methods to Develop Tangible Products Quickly
Agile Methods to Develop Tangible Products Quickly
 
Can Agile Work With a Waterfall Process?
Can Agile Work With a Waterfall Process?Can Agile Work With a Waterfall Process?
Can Agile Work With a Waterfall Process?
 
Program and Change Management
Program and Change ManagementProgram and Change Management
Program and Change Management
 
Software Quality Dashboard Benchmarking Study
Software Quality Dashboard Benchmarking StudySoftware Quality Dashboard Benchmarking Study
Software Quality Dashboard Benchmarking Study
 
Smart Agile: An Elegant Recipe for Product Developers
Smart Agile: An Elegant Recipe for Product DevelopersSmart Agile: An Elegant Recipe for Product Developers
Smart Agile: An Elegant Recipe for Product Developers
 
Boundary Conditions - Who Needs Agile?
Boundary Conditions - Who Needs Agile?Boundary Conditions - Who Needs Agile?
Boundary Conditions - Who Needs Agile?
 
Software QA Metrics Dashboard Benchmarking
Software QA Metrics Dashboard BenchmarkingSoftware QA Metrics Dashboard Benchmarking
Software QA Metrics Dashboard Benchmarking
 

Kürzlich hochgeladen

Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
alinstan901
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Riyadh +966572737505 get cytotec
 

Kürzlich hochgeladen (20)

Discover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdfDiscover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdf
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
 
LoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner CircleLoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner Circle
 
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdfImagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
 
Continuous Improvement Posters for Learning
Continuous Improvement Posters for LearningContinuous Improvement Posters for Learning
Continuous Improvement Posters for Learning
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
 
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdfImagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
 
situational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Ssituational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima S
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
Intro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptxIntro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptx
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 
Empowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdfEmpowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdf
 
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg PartnershipUnlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
 
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 
Peak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian DugmorePeak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian Dugmore
 

Program Management 2.0: Risk Management

  • 1. 1 1 PROGRAM MANAGEMENT 2.0 RISK MANAGEMENT Jeanne Bradford, John Carter, Scott Elliott April, 2018
  • 2. 2 22 AGENDA 1 Schedule Prediction Accuracy Exercise in creating diagram 2 Metrics for estimating progress at the engineering task levels Exercise in creating a Task Burn- Down Chart 3 Monitoring Progress: Earned Value – Scope, Cost and Time Exercise in managing Partner’s delay 4 Risk & Circle Dot Charts: What happens if there is a breakdown? Exercise 5 Management Systems Covered in this presentation
  • 3. 3 33 KEY LEARNING POINTS Monitoring Project Performance for Internal and External Partners (TCGen’s Innovate Products Faster, Greene’s Head First PMP) 1 Metrics for estimating progress (at the engineering task levels) 2 Monitoring Progress (Earned Value – Scope, Cost and Time) 3 Risk Monitoring 4 Circle Dot Charts 5 Management Systems Participants will understand how to create and update Schedule Prediction Accuracy charts and how to demonstrate program status by showing scope, cost and time in one chart. They will also gain skill in creating and using:
  • 5. 5 55 ESSENTIAL PROCESSES FOR MANAGING RISKS • Assess – Learn from the past, create checklist, review prior audits, go outside, generate list of potential risks • Plan – Perform impact and probability analysis, prioritize, and make plans • Monitor – Keep an active watch for trouble by monitoring predictive metrics • React – Re-mediate if and when there is trouble Assess Plan Monitor & React
  • 6. 6 66 RISK RESPONSE OPTIONS Risk Response Description Examples/Notes Avoidance Avoiding the risk. Changing the project plan to eliminate the risk. Changing the project plan to protect a project objective from the impact. Reducing the scope remove high-risk tasks. Adding resources or time. Adopting a proven approach rather than new one. Removing a “problem” resource. Acceptance Accepting the consequences of the risk. The project plan is not changed to deal with the risk. A better response strategy cannot be identified. Active acceptance. Passive acceptance. No action. Contingency allowance (reserves). Communication plan around possible major cost increases if this risk occurs. Monitor and prepare Accepting the risk for now. Closely monitor the risk and develop alternate action plans proactively if the event occurs. Contingency plan. Fallback plan. Establish criteria that will trigger the implementation of the response plans. Source: Project Management, Absolute Beginner’s Guide, Gregory Horine Que Publishing, Indianapolis 2013
  • 7. 7 77 Risk Response Description Examples/Notes Mitigation Taking action to reduce the likelihood that the risk will occur. Taking action to reduce the impact of the risk. Reducing the probability is always more effective than minimizing the consequences. Adopting less complex approaches. Planning on more testing. Adding resources or time to the schedule. Assigning a team member to visit the seller’s facilities frequently to learn about potential delivery problems as early as possible. Providing a less-experienced team member with additional training. Deciding to prototype a high-risk solution element. Transference Transferring ownership of the risk factor. Shifting the consequence of a risk and the ownership of the response to a third party. Outsourcing difficult work to a more experienced company. Fixed price contract. Contract, insurance, warranties, guarantees, and so on. Used most often for financial risk exposure. Does not eliminate the risk. RISK RESPONSE OPTIONS Source: Project Management, Absolute Beginner’s Guide, Gregory Horine Que Publishing, Indianapolis 2013
  • 8. 8 88 ESSENTIAL PROCESSES FOR MANAGING RISKS Which Business Problems Does the Tool Solve? • Innovation brings with it additional risks which can still be managed by the team on its own • Helps improve project execution because it can help the team anticipate, prevent, and mitigate risks Benefits: • You can identify risks before they occur • There is a reduction of risk impact due to early detection • Quantitative metrics that help clarify when to act on a risk item • Action accelerates because of the clear thresholds and the agreement to follow a process
  • 9. 9 99 RISK MANAGEMENT MATRIX Status Risk Impact Likelihood Metric Threshold Current Value Date Action Plan Global team does not communicate frequently enough. Want to keep weekly communication high. 4 7 Meetings per week 2 2.5 Current Invoke team’s elevation plan, purchase videoconferencing systems, change incentives. Data captured on long forms from online interaction sessions must not be lost if user gets error message or returns to screen. 6 6 % Data Lost 10% 25% Q3 FY 13 Design review current forms layout, bring in Expert Co. consulting firm, change staff balance. Server must respond to users rapidly under fairly high loads – expect page to be updated way under a second. 7 7 Ms at 1000 Users 259 1000 Q2 FY 13 Add architect and create tiger team with system optimization experience. Financial partner cooperation is critical to this household finance program, and we need to have a sufficient number at launch 4 6 Institutions 1000 247 Q3 FY 13 Increases business development staff, change incentive compensation, add external business development firm. Mobile operating system support must be in place at the same time as launching the desktop version. 5 6 On Time Q4 FY 14 Q4 FY 14 Current Track schedule prediction accuracy. If slip then recruit internal team from Vietnam (permission already granted).
  • 10. 10 1010 Status Risk Impact Likelihood Metric Threshold Current Value Date Action Plan Global team does not communicate frequently enough. Want to keep weekly communication high. 4 7 Meetings per week 2 2.5 Current Invoke team’s elevation plan, purchase videoconferencing systems, change incentives. Data captured on long forms from online interaction sessions must not be lost if user gets error message or returns to screen. 6 6 % Data Lost 10% 25% Q3 FY 13 Design review current forms layout, bring in Expert Co. consulting firm, change staff balance. Server must respond to users rapidly under fairly high loads – expect page to be updated way under a second. 7 7 Ms at 1000 Users 259 1000 Q2 FY 13 Add architect and create tiger team with system optimization experience. Financial partner cooperation is critical to this household finance program, and we need to have a sufficient number at launch 4 6 Institutions 1000 247 Q3 FY 13 Increases business development staff, change incentive compensation, add external business development firm. Mobile operating system support must be in place at the same time as launching the desktop version. 5 6 On Time Q4 FY 14 Q4 FY 14 Current Track schedule prediction accuracy. If slip then recruit internal team from Vietnam (permission already granted). RISK MANAGEMENT MATRIX Impact of Risk 1 = Low,10 = High Likelihood 1 = Low,10 = High Metric Value triggering action What to do if Threshold reached
  • 11. 11 1111 CONTROLLING RISKS • Tackle high risk tasks first • Maximize resources on high-risk tasks • Postpone low-risk tasks • Use iterative, phased approaches • Frequent, smaller deliverables reduce overall risk • Change the way you design • Create a better balance between theory and experimentation; lean more on experimentation to get fast answers • Get to “no” more quickly on parallel paths • QA the planning process • Leverage independent QA audits
  • 12. 12 1212 MITIGATING RISKS: ALTERNATIVES 1 Soft Skills 2 Meetings 3 Dot Voting 4 Out of Bounds 5 Communication Paths 6 Fast Tracking and Crashing Assess Plan Monitor & React These Tools are for the “Monitor and React” phase
  • 13. 13 1313 SOFT SKILLS: EXECUTING A successful Program Manager has these critical soft skills Is the leader of communications: sets the tone and protocols for them When there are breakdowns, emphasizes the outcome the team is trying to produce not who is to blame
  • 14. 14 1414 MANAGING YOUR TEAM & MEETINGS • “Smooth” program management starts by running effective meetings • Communicating effectively outside of team meetings is where the real work gets done however • Focusing on the outcome rather than on blaming people • Establishing clear priorities and sticking with them • Tracking the status of each activity (sub-project) within the project • Using metrics to see the big picture and to drive improvement Necessary Conditions for “Execution: Managing Teams & Meetings” Communication Skills Communication Tools Tracking Capability Metrics • DOCUMENTS: Communication protocols, Metrics dashboard, Priority lists (These are suggested, not in place yet at D+M)
  • 15. 15 1515 FAST TRACKING & CRASHING TASKS Source: Dynamics of Project Performance: System Dynamics and Project Management , Lyneis, MIT, 2003, p 16 Worry about taking shortcuts that only cause delay because of more rework Traditional project Overlap phases Compress each phase Reduce Rework Planned Duration Actual Phase 1 Rework Phase 2
  • 16. 16 1616 EXERCISE: MONITORING RISK Possibilities: Build a Risk Management Matrix from a project Have a role-playing scenario where a risk has crossed the threshold and Partner is not responding well
  • 17. 17 17 TCGen Inc. Menlo Park CA, 94025 jcarter@tcgen.com (650) 733-5310