International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1892
Risk Analysis and Strategic Evaluation of Procurement Process in
Construction
Sharayu P. Pawar1, Dr. M.N.Bajad2, Prof. Mr. R.D. Shinde3
1PG Student (Construction Management), RMD Sinhgad College of Engineering, Warje, Pune, Maharashtra, India.
2Associate Professor, Department of civil engineering, Sinhgad College of Engineering, Vadgaon, Pune- 411041,
Maharashtra, India.
3Head of the Department of Civil Engineering, RMD Sinhgad College of Engineering, Warje, Pune- 411052,
Maharashtra, India.
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - Procurement process is one of the components
that bring construction projects into existence. Each project
possesses a number of different variables that will determine
the choice of procurement providing the most advantageous
route. The selection of the procurement route may have
repercussions on the operation of the building throughout its
life. Therefore it is necessary to correctly decide the
procurement, which is based on issues surrounding the main
priorities of the clients such as completion of building on time,
in budget and to the given quality. In order to ensure that the
project can be completed successfully, the client must select
the most appropriate contractor. It is important to adopt an
approach that will include all the criteria that are important
in selecting a contractor. But while doing procurement in
construction industry variousrisksmayoccursuchasfinancial
risks, legal risks, risks during transportation etc. At present
study a decision making treeisdevelopedtoselectappropriate
method to analyse procurement risk. At present, the risk
analysis has become the important part of procurement. The
present study gives the different aspects of procurement in
construction industry by using the comparison of the methods
namely RII and IMPI. The study also shows the reasons behind
the delay and risks in procurement.
Key Words: (Risk factors in procurement, Relative
Importance Index, Importance Index, Decision MakingTree,
Degree of severity, Comparison of RII and IMPI, Delay and
risk factors.
1. INTRODUCTION:
Procurement process is one of the components that bring
construction projects into existence.Procurementisdefined
as the process which creates, manages and fulfils
construction contracts. The keys for a successful project
outcome are the findings of a procurement strategy which
helps to identify and set up key project objectives. These
strategies reflects aspects of risk, and helps to find out that
how the process will be managed. For the constructions to
be unique and exclusive clientshavetofacethevarioustypes
of the risks during constructions. These risks include the
completion of the project on the time i.e., delivering the
project on given time, delay due to transportation or delay
due to any litigation these factors costs more than the
client’s budget. All these risks affectsontheclient’s business.
Therefore, a procurement strategy shouldbedevelopedthat
balances risk against the project objectives that are to be
found out at an early stage. Risk management is a key
component of project management because unmanaged or
unmitigated risks are one of the primary causes of project
failure. Risk management is an important concept that
mainly aims at identifying, quantifying, mitigating and
reviewing of events that may have an adverse impact on the
organization. There is a strong connection between the
amount of risk managed during the project and the level of
success of the project as more successful projects use more
risk management. Also the earlierthatrisk management was
used in a project, the more successful it was. Risks identified
here will not only help the production of the necessary
project products, but will increase the chance of overall
project success. A significant risk that is not identified and
mitigated will become a real problem at some point during
the project life cycle. Proper risk management will reduce
not only the probability of an event occurring, but also the
degree of its impact.
2. LITERATURE REVIEW:
Anup Wilfred et al (2015)1 have studied that the major
causes of delay in Indian Construction Industry.Acasestudy
is also conducted in the Karnataka region of India to further
research the major causes of delay in this region. This study
is quite useful to the stakeholders take measures to reduce
the occurrence of these delays.
Desai Megha et.al (2013) 2 have studied the causes of delay
in residential construction projects in India. The paper
focuses on delays that are caused in the residential
constructions and are analysed using the two methods viz.
Relative Index and Importance Index.
Hardik Lokhandwala, et.al (2015)3 have studied the causes
of delay in constructions. The paper focuses on delays that
are caused in the residential constructions and are analysed
using the two methods i.e., Relative Index and Importance
Index.
Marzouk et.al (2012)4 have distributed 33 questionnaires
which contains 43 delay causes and they categorized it in 7
groups and submitted it to owners, consultants and
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1893
contractors organization in Egypt.FrequencyIndex, Severity
Index and Importance Index were calculated by using the
information collected from this survey and the top 10 delay
causes were determined. Statistical analysis was done using
analysis of variance ANOVA method to test delay causes.
Meet Patel et.al (2016)5 have studied about the factors that
affects the residential constructions. Various factors are
finalised and reviews of various contractors are taken and
are analysed on basis of relative index technique and
importance index technique.
Tarun Patel, et.al (2016)6 have studied about the factors that
affectsconstruction projectsduring handling of the material.
So the study is based on how to reduce the overall project
cost. The outcomeof this papermayprovideaplatformforall
construction industry stakeholders to appreciate the most
critical factors in material procurement management in
construction industry.
3. RESEARCH METHODOLOGY:
In traditional approach clients were used to select the
supplier with the lowest bid. This led to taking the increased
risk in procurement in most of the cases. The involvementof
the contractor and supplier plays an important role in
successful completion of any project. Hence the present
work addresses calculating the reasons behind the delays
and risks in construction procurement. A basic concept of
risk was taken for calculating the risk. A questionnaire was
design and developed and the opinion of the experts were
taken as the basis for development of the data which can
provide the chances of occurrence of events i.e., factors and
there reasons behind the risk occurrence. The two standard
methods named Relative Importance Index (RII) and
Importance Index Technique (IMPI) were used for
determination of risk and delays in projects.
4. DATA COLLECTION:
A preliminary questionnaires survey was employed to get a
general overview of the characteristics of procurement
strategy implemented. A Criteria is defined that a personnel
take into consideration whileselectingprocurementmethod
and understand the process in selecting supplier. The exact
risk mitigation procedure is to be found out from the
comparison of two methods namely, RII and IMPI.Following
steps were involved to find out procurement risk:
1. Literature search from various journals, previous
research and relevant data available on supplier
contract selection.
2. Study of events occurring at constructionsitedueto
poor procurement process.
3. Factors affecting the supplier selection process.
4. Preparation of questionnaire using the factors
affecting procurement process.
5. Conduct the questionnaire survey.
6. Analysis of questionnaire using RII and IMPI
methods.
7. Calculation of different scenario withlowestimpact
to highest impact.
8. Evaluate risk ranks by RII and IMPI methods.
9. Conclusion from the comparison.
4.1 Finalization of Factors:
Study of different events and their consequences i.e.,
probable factors affecting the construction project are
determined. For this various type of factors are responsible.
The different type of factors were finalized for procurement
risk which are as follow:
1. Communication between supplier and contractor.
2. Deviation in the scope of the project.
3. Political and social factor.
4. Project funding.
5. Assess available to project site.
6. Technical capability of contractor.
7. Technical capability of supplier.
8. Financial capability of supplier.
9. Involvement of contractor in actual procurement
process.
10. Strike in market.
11. Influence of availability of material, equipment in
market.
12. Transport facility available.
13. Recession period in project duration.
14. Inflation in cost of resources.
15. Methods of litigation used for project
5. DATA ANALYSIS:
5.1 Decision Making Tree:
There are various methods of making a decisionmakingtool
such as decision making tree, risk rating matrix, Pareto
analysis etc. here we have used the decision makingtreeasa
soft tool to give the appropriate method for identification
and analysis of procurement risks. The developed model
helps to choose the right method to analyze the risk and to
choose proper supplier. The methodology has been adopted
from approaches mentioned in the literature review. The
following steps could be applied in order to choose themore
appropriate method for risk analysis. The following figure
shows the decision making tree which is used to find the
method used to minimize the risks in procurement.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1894
Fig. 1- Decision making tree which supports risk analysis
Hence, by using the above tool we can compare the two
methods namely, RelativeImportanceIndexandImportance
Index Technique.
5.2 Relative Importance Index Technique (RII):
This technique is used to determine the relative importance
of the various causes and effects of delays. The method is
adopted in this study within various groups (i.e. project
engineers, proprietor and site supervisor, designers,
surveyors). The four-point scale ranged from 1 (very little
degree affect) to 5 (very high degree affect) is adopted and
transformed to relative importance indices (RII) for each
factor as follows:
RII = ΣW / (A*N)
Where,
 W = Weighting to each factor (from 1 to 4)
 A = Highest weight (i.e. 5 here)
 N = Total number of respondents.
Higher the value of RII, more important was the reason of
delays. [Tarun Patel, Hiren Rathod et.al 2016]
5.3 Importance Index Technique (IMPI):
In this technique, two factors are important based on which
the importance index is to be identified andthosefactorsare
Frequency of occurrence and degree of severity. Frequency
of occurrence and degree of severity were both divided on a
four-point scale. Frequency of occurrence is classified as
follows: always, often, sometimes and rarely (on 4 to 1 point
scale). Similarly, degree of severity was classified asfollows:
extreme, great, moderate and little (on 4 to 1 point scale)
[Tarun Patel, Hiren Rathod et.al 2016].
1) Frequency index: This formula is used to rank causes of
delay based on frequency of occurrence as identified by the
participants.
(F.I.) (%) = Σ a (n/N) * 100/4
Where,
 a = Constant signifying weighting for each response
(from 1 to 4 )
 n = Frequency of the responses
 N = Total number of responses.
2) Severity index: This formula is used to rank causes of
delay based on severity as indicated by the participants.
S.I. (%) = Σ a (n/N) * 100/4
Where,
 a = Constant signifying weighting for each response
(from 1 to 4 )
 n = Frequency of the responses
 N = Total number of responses.
3) Importance index: The importance index of each cause is
calculated as follows:
IMPI (%) = [F.I. * S.I.] /100
6. RESULTS AND DISCUSSIONS:
The results are found on the basis of comparision of two
methods for procurement risk analysis. With the help of the
decision making tree the two methods namely RII and IMPI
methods are selected to find out the procurement risk
analysis in construction Industry.
The following table shows findings of various ranksbyusing
RII method:
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1895
Table I: Ranks of risks in procurement process using RII
method
Sr.
No Risk Factor ∑W RII Rank
A
Communication
between supplier and
contractor
procurement process.
125 0.5 7
B
The deviation in the
scope of the project in
procurement process.
123 0.492 9
C
The political or social
factors influence the
procurement process.
107 0.428 12
D
Project funding
influence the
procurement process.
147 0.588 5
E
Assess to the project
site influence the
procurement process.
134 0.536 6
F
The technical capability
of supplier in the
procurement process.
170 0.68 4
G
The Technical
capability of contractor
in procurement
214 0.856 1
H
The financial capability
of contractor in the
procurement.
209 0.836 2
I
The involvement of
contractor in
procurement process
influences the
procurement.
186 0.744 3
J Litigation process in
the procurement.
124 0.496 8
K
Strike in market in the
procurement process 113 0.452 11
L
Availability of material
in the market in the
procurement process
88 0.352 15
M
The transport facility to
project site in the
procurement.
99 0.396 13
N The recession in the
market in the
procurement process.
98 0.392 14
O The inflation in
material rate in the
procurement process.
114 0.456 10
The following graph shows the risk values or ranks by
using the above analysis of RII method:
Chart 1 Risk values using RII method
The following table shows findings of various ranksbyusing
IMPI method:
Table II: Ranks of risks in procurement process using
IMPI method
Sr.
No Risk Factor F.I. S.I. IMPI
(%)
Rank
A
Communicatio
n between
supplier and
contractor
procurement
process
54.5 52.5 28.61 7
B
The deviation
in the scope of
the project in
procurement
process.
49.5 49 24.26 8
C
The political
or social
factors
influence the
procurement
process.
42.5 42 7.85 14
D
Project
funding
influence the
procurement
process.
63 71 44.73 5
E
Assess to the
project site
influence the
procurement
process.
55 55 30.25 6
F
The technical
capability of
supplier in the
procurement
process.
75 77 57.75 4
The Technical
capability of 82.5 81 66.83 1
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1896
G contractor in
procurement
H
The financial
capability of
contractor in
the
procurement.
81.5 81.5 66.42 2
I
The
involvement
of contractor
in
procurement
process
influences the
procurement.
78.5 76.5 60.05 3
J
Litigation
process in the
procurement
40.5 45 18.23 13
K
Strike in
market in the
procurement
process
53 40 21.20 10
L
Availability of
material in the
market in the
procurement
process
43.5 43.5 18.92 12
M
The transport
facility to
project site in
the
procurement.
47 43.5 20.45 11
N
The recession
in the market
in the
procurement
process.
45.5 49.5 22.52 9
O
The inflation
in material
rate in the
procurement
process.
42.5 40 17 15
Thus, the above table I shows the various ranks of risks in
procurement process using IMPI method.
The following chart II shows the risk values or ranks by
using the above analysis of IMPI method:
Chart II- Risk values using IMPI method
The following table shows findings of various ranks by
comparing RII and IMPI method:
Table III: Comparison of RII and IMPI method
Sr.
No
Risk Factor RII Rank IMPI Rank
A
Communicatio
n between
supplier and
contractor
procurement
process
0.5 7 28.61 7
B
The deviation
in the scope of
the project in
procurement
process.
0.492 9 24.26 8
C
The political
or social
factors
influence the
procurement
process.
0.428 12 17.85 14
D
Project
funding
influence the
procurement
process.
0.588 5 44.73 5
E
Assess to the
project site
influence the
procurement
process.
0.536 6 30.25 6
F
The technical
capability of
supplier in the
procurement
process.
0.68 4 57.75 4
The Technical
capability of
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1897
G contractor in
procurement
0.856 1 66.83 1
H
The financial
capability of
contractor in
the
procurement
0.836 2 66.42 2
I
The
involvement
of contractor
in
procurement
process
influences the
procurement
0.744 3 60.05 3
J
Litigation
process in the
procurement
0.496 8 18.23 13
K
Strike in
market in the
procurement
process
0.452 11 21.20 10
L
Availability of
material in
the market in
the
procurement
process
0.352 15 18.92 12
M
The transport
facility to
project site in
the
procurement
0.788 13 20.45 11
N
The recession
in the market
in the
procurement
process.
0.396 14 22.52 9
O
The inflation
in material
rate in the
procurement
process.
0.456 10 17 15
Thus, the above table III shows the comparison of various
ranks of risks in procurement process using RII and IMPI
method.
The following graph shows the risk values or ranks by
using comparison of RII and IMPI method:
0
5
10
15
20
A B C D E F G H I J K L M N O
Comparison of RII & IMPI
RII IMPI
Chart-III Comparison of ranks of RII and IMPI method
7. CONCLUSION:
The ranking by both the methods is not getting differ very
much, so we can consider preference of risk by any of these
method. So from the above analysis we canconcludethatthe
major reasons behind the delays and risks in procurement
are project funding for procurement, technical capability of
contractor, technical capability of supplier, financial
capability of supplier, involvement of contractor in actual
procurement process. So, we have to take precautions to
avoid these types of risks during procurement. So while
doing any project the selectionofcontractorandsupplier are
the important factors. Theproperselectionofcontractorand
supplier may reduce the other risks like project funding,
deviation in the scope of project,etc.Sotakingprecautionsof
these risks will reduce the delays in project also.
8. ACKNOWLEDGEMENT:
We attribute the success ofprojectstageoneprimarilyto our
guide Prof.Rahul Shinde for the efforts taken by himtoguide
throughout completion of project and for encouraging us
through the tough as well as easier phase in an expert
manner with full attention. Wealsoacknowledgethesupport
given by Prof. Rahul Shinde, Head of Civil Engineering
Department and Dr.C.B.Bangal Principal of providing the
necessary facilities and infrastructure for the seminar.
We would like to take this opportunity to express our
gratitude to all those who have in various ways helped in
successfully developing the seminar report from its initial
stage to its completion stage.
Last but not the least we also acknowledge the efforts made
by all staff members of Civil Engineering Department and
our friend for their kind co-operation in all phase of the
project.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1898
9. REFERENCES:
1) Anup Wilfred, “a methodology to identifythedelays
and rank its causative factors inIndianconstruction
industry”, International Research Journal of
Engineering and Technology (IRJET), Volume: 02
Issue: 03 | June-2015.
2) Desai Megha, Rajiv Bhatt,“Critical CausesofDelayin
Residential Construction Projects: Case Study of
Central Gujarat Region of India “(Volume-4 Issue-4,
Year of Publication: 2013
3) Hardik Lokhandwala et.al, “RankingoftheCausesof
Delay for Private Sector Industrial Construction
Projects in Indian Context”, Volume 2,Issue 5, May -
2015
4) M. Marzouk and T. El-Rasas,‘Analyzingdelaycauses
in Egyptian construction projects’, Journal of
Advanced Research, vol. 5, no. 1, pp. 49-55, 2014.
5) Meet Patel “ Factors affecting on contractor’s
bidding strategy in large scale residential
construction” Volume 3,Issue 5,May -2016
6) Tarun Patel et.al, “Comparison analysis of
parameters affecting material Procurement in
construction industry by RII and IMPI methods”
IJSDR Volume 1, Issue 5 , May 2016

Weitere ähnliche Inhalte

Was ist angesagt?

Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libre
UTHM
 
IDENTIFICATION AND MITIGATION OF FACTORS AFFECTING HUMAN RESOURCE PRODUCTIVIT...
IDENTIFICATION AND MITIGATION OF FACTORS AFFECTING HUMAN RESOURCE PRODUCTIVIT...IDENTIFICATION AND MITIGATION OF FACTORS AFFECTING HUMAN RESOURCE PRODUCTIVIT...
IDENTIFICATION AND MITIGATION OF FACTORS AFFECTING HUMAN RESOURCE PRODUCTIVIT...
IAEME Publication
 
Towards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and ControlTowards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and Control
civej
 

Was ist angesagt? (20)

Ijciet 08 04_220
Ijciet 08 04_220Ijciet 08 04_220
Ijciet 08 04_220
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libre
 
IRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction ProjectIRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction Project
 
IDENTIFICATION AND MITIGATION OF FACTORS AFFECTING HUMAN RESOURCE PRODUCTIVIT...
IDENTIFICATION AND MITIGATION OF FACTORS AFFECTING HUMAN RESOURCE PRODUCTIVIT...IDENTIFICATION AND MITIGATION OF FACTORS AFFECTING HUMAN RESOURCE PRODUCTIVIT...
IDENTIFICATION AND MITIGATION OF FACTORS AFFECTING HUMAN RESOURCE PRODUCTIVIT...
 
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
 
Risk Management in Medium Sized Commercial Buildings
Risk Management in Medium Sized Commercial BuildingsRisk Management in Medium Sized Commercial Buildings
Risk Management in Medium Sized Commercial Buildings
 
33 article text-127-1-10-20181005
33 article text-127-1-10-2018100533 article text-127-1-10-20181005
33 article text-127-1-10-20181005
 
20320140503023
2032014050302320320140503023
20320140503023
 
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction Project
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
 
Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...
 
Towards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and ControlTowards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and Control
 
7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan
 
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
 
Study and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsStudy and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction Projects
 
“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”
 

Ähnlich wie Risk Analysis and Strategic Evaluation of Procurement Process in Construction

Risk Management in High Rise Construction Projects: A Review
Risk Management in High Rise Construction Projects: A ReviewRisk Management in High Rise Construction Projects: A Review
Risk Management in High Rise Construction Projects: A Review
A Makwana
 

Ähnlich wie Risk Analysis and Strategic Evaluation of Procurement Process in Construction (20)

Attributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a reviewAttributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a review
 
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
I012646171
I012646171I012646171
I012646171
 
I012646171
I012646171I012646171
I012646171
 
IRJET- Most Efficient Critical Success Factor for Construction
IRJET-  	  Most Efficient Critical Success Factor for ConstructionIRJET-  	  Most Efficient Critical Success Factor for Construction
IRJET- Most Efficient Critical Success Factor for Construction
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
Risk Management in High Rise Construction Projects: A Review
Risk Management in High Rise Construction Projects: A ReviewRisk Management in High Rise Construction Projects: A Review
Risk Management in High Rise Construction Projects: A Review
 
Time delay and cost escalation in construction works
Time delay and cost escalation in construction worksTime delay and cost escalation in construction works
Time delay and cost escalation in construction works
 
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...  A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
A STUDY OF VARIOUS FACTORS AFFECTING CONTRACTOR’S PERFORMANCE IN LOWEST BID...
 
Ijciet 08 02_005
Ijciet 08 02_005Ijciet 08 02_005
Ijciet 08 02_005
 
Risk Management In High Rise Construction Projects
Risk Management In High Rise Construction ProjectsRisk Management In High Rise Construction Projects
Risk Management In High Rise Construction Projects
 
Documentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewDocumentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- Review
 
IRJET- Identification of Crucial Factor Affecting to Sustainable Construc...
IRJET-  	  Identification of Crucial Factor Affecting to Sustainable Construc...IRJET-  	  Identification of Crucial Factor Affecting to Sustainable Construc...
IRJET- Identification of Crucial Factor Affecting to Sustainable Construc...
 
D012261521
D012261521D012261521
D012261521
 
Construction Equipment Monitoring By using Relative Important Indices RII Ana...
Construction Equipment Monitoring By using Relative Important Indices RII Ana...Construction Equipment Monitoring By using Relative Important Indices RII Ana...
Construction Equipment Monitoring By using Relative Important Indices RII Ana...
 
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
 
IRJET- Risk Management in the Construction Project: Review
IRJET-  	  Risk Management in the Construction Project: ReviewIRJET-  	  Risk Management in the Construction Project: Review
IRJET- Risk Management in the Construction Project: Review
 
A Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction RisksA Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction Risks
 
IRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction ProjectsIRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction Projects
 

Mehr von IRJET Journal

Mehr von IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Kürzlich hochgeladen

Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Christo Ananth
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
Tonystark477637
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Kürzlich hochgeladen (20)

The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spain
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 

Risk Analysis and Strategic Evaluation of Procurement Process in Construction

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1892 Risk Analysis and Strategic Evaluation of Procurement Process in Construction Sharayu P. Pawar1, Dr. M.N.Bajad2, Prof. Mr. R.D. Shinde3 1PG Student (Construction Management), RMD Sinhgad College of Engineering, Warje, Pune, Maharashtra, India. 2Associate Professor, Department of civil engineering, Sinhgad College of Engineering, Vadgaon, Pune- 411041, Maharashtra, India. 3Head of the Department of Civil Engineering, RMD Sinhgad College of Engineering, Warje, Pune- 411052, Maharashtra, India. ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - Procurement process is one of the components that bring construction projects into existence. Each project possesses a number of different variables that will determine the choice of procurement providing the most advantageous route. The selection of the procurement route may have repercussions on the operation of the building throughout its life. Therefore it is necessary to correctly decide the procurement, which is based on issues surrounding the main priorities of the clients such as completion of building on time, in budget and to the given quality. In order to ensure that the project can be completed successfully, the client must select the most appropriate contractor. It is important to adopt an approach that will include all the criteria that are important in selecting a contractor. But while doing procurement in construction industry variousrisksmayoccursuchasfinancial risks, legal risks, risks during transportation etc. At present study a decision making treeisdevelopedtoselectappropriate method to analyse procurement risk. At present, the risk analysis has become the important part of procurement. The present study gives the different aspects of procurement in construction industry by using the comparison of the methods namely RII and IMPI. The study also shows the reasons behind the delay and risks in procurement. Key Words: (Risk factors in procurement, Relative Importance Index, Importance Index, Decision MakingTree, Degree of severity, Comparison of RII and IMPI, Delay and risk factors. 1. INTRODUCTION: Procurement process is one of the components that bring construction projects into existence.Procurementisdefined as the process which creates, manages and fulfils construction contracts. The keys for a successful project outcome are the findings of a procurement strategy which helps to identify and set up key project objectives. These strategies reflects aspects of risk, and helps to find out that how the process will be managed. For the constructions to be unique and exclusive clientshavetofacethevarioustypes of the risks during constructions. These risks include the completion of the project on the time i.e., delivering the project on given time, delay due to transportation or delay due to any litigation these factors costs more than the client’s budget. All these risks affectsontheclient’s business. Therefore, a procurement strategy shouldbedevelopedthat balances risk against the project objectives that are to be found out at an early stage. Risk management is a key component of project management because unmanaged or unmitigated risks are one of the primary causes of project failure. Risk management is an important concept that mainly aims at identifying, quantifying, mitigating and reviewing of events that may have an adverse impact on the organization. There is a strong connection between the amount of risk managed during the project and the level of success of the project as more successful projects use more risk management. Also the earlierthatrisk management was used in a project, the more successful it was. Risks identified here will not only help the production of the necessary project products, but will increase the chance of overall project success. A significant risk that is not identified and mitigated will become a real problem at some point during the project life cycle. Proper risk management will reduce not only the probability of an event occurring, but also the degree of its impact. 2. LITERATURE REVIEW: Anup Wilfred et al (2015)1 have studied that the major causes of delay in Indian Construction Industry.Acasestudy is also conducted in the Karnataka region of India to further research the major causes of delay in this region. This study is quite useful to the stakeholders take measures to reduce the occurrence of these delays. Desai Megha et.al (2013) 2 have studied the causes of delay in residential construction projects in India. The paper focuses on delays that are caused in the residential constructions and are analysed using the two methods viz. Relative Index and Importance Index. Hardik Lokhandwala, et.al (2015)3 have studied the causes of delay in constructions. The paper focuses on delays that are caused in the residential constructions and are analysed using the two methods i.e., Relative Index and Importance Index. Marzouk et.al (2012)4 have distributed 33 questionnaires which contains 43 delay causes and they categorized it in 7 groups and submitted it to owners, consultants and
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1893 contractors organization in Egypt.FrequencyIndex, Severity Index and Importance Index were calculated by using the information collected from this survey and the top 10 delay causes were determined. Statistical analysis was done using analysis of variance ANOVA method to test delay causes. Meet Patel et.al (2016)5 have studied about the factors that affects the residential constructions. Various factors are finalised and reviews of various contractors are taken and are analysed on basis of relative index technique and importance index technique. Tarun Patel, et.al (2016)6 have studied about the factors that affectsconstruction projectsduring handling of the material. So the study is based on how to reduce the overall project cost. The outcomeof this papermayprovideaplatformforall construction industry stakeholders to appreciate the most critical factors in material procurement management in construction industry. 3. RESEARCH METHODOLOGY: In traditional approach clients were used to select the supplier with the lowest bid. This led to taking the increased risk in procurement in most of the cases. The involvementof the contractor and supplier plays an important role in successful completion of any project. Hence the present work addresses calculating the reasons behind the delays and risks in construction procurement. A basic concept of risk was taken for calculating the risk. A questionnaire was design and developed and the opinion of the experts were taken as the basis for development of the data which can provide the chances of occurrence of events i.e., factors and there reasons behind the risk occurrence. The two standard methods named Relative Importance Index (RII) and Importance Index Technique (IMPI) were used for determination of risk and delays in projects. 4. DATA COLLECTION: A preliminary questionnaires survey was employed to get a general overview of the characteristics of procurement strategy implemented. A Criteria is defined that a personnel take into consideration whileselectingprocurementmethod and understand the process in selecting supplier. The exact risk mitigation procedure is to be found out from the comparison of two methods namely, RII and IMPI.Following steps were involved to find out procurement risk: 1. Literature search from various journals, previous research and relevant data available on supplier contract selection. 2. Study of events occurring at constructionsitedueto poor procurement process. 3. Factors affecting the supplier selection process. 4. Preparation of questionnaire using the factors affecting procurement process. 5. Conduct the questionnaire survey. 6. Analysis of questionnaire using RII and IMPI methods. 7. Calculation of different scenario withlowestimpact to highest impact. 8. Evaluate risk ranks by RII and IMPI methods. 9. Conclusion from the comparison. 4.1 Finalization of Factors: Study of different events and their consequences i.e., probable factors affecting the construction project are determined. For this various type of factors are responsible. The different type of factors were finalized for procurement risk which are as follow: 1. Communication between supplier and contractor. 2. Deviation in the scope of the project. 3. Political and social factor. 4. Project funding. 5. Assess available to project site. 6. Technical capability of contractor. 7. Technical capability of supplier. 8. Financial capability of supplier. 9. Involvement of contractor in actual procurement process. 10. Strike in market. 11. Influence of availability of material, equipment in market. 12. Transport facility available. 13. Recession period in project duration. 14. Inflation in cost of resources. 15. Methods of litigation used for project 5. DATA ANALYSIS: 5.1 Decision Making Tree: There are various methods of making a decisionmakingtool such as decision making tree, risk rating matrix, Pareto analysis etc. here we have used the decision makingtreeasa soft tool to give the appropriate method for identification and analysis of procurement risks. The developed model helps to choose the right method to analyze the risk and to choose proper supplier. The methodology has been adopted from approaches mentioned in the literature review. The following steps could be applied in order to choose themore appropriate method for risk analysis. The following figure shows the decision making tree which is used to find the method used to minimize the risks in procurement.
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1894 Fig. 1- Decision making tree which supports risk analysis Hence, by using the above tool we can compare the two methods namely, RelativeImportanceIndexandImportance Index Technique. 5.2 Relative Importance Index Technique (RII): This technique is used to determine the relative importance of the various causes and effects of delays. The method is adopted in this study within various groups (i.e. project engineers, proprietor and site supervisor, designers, surveyors). The four-point scale ranged from 1 (very little degree affect) to 5 (very high degree affect) is adopted and transformed to relative importance indices (RII) for each factor as follows: RII = ΣW / (A*N) Where,  W = Weighting to each factor (from 1 to 4)  A = Highest weight (i.e. 5 here)  N = Total number of respondents. Higher the value of RII, more important was the reason of delays. [Tarun Patel, Hiren Rathod et.al 2016] 5.3 Importance Index Technique (IMPI): In this technique, two factors are important based on which the importance index is to be identified andthosefactorsare Frequency of occurrence and degree of severity. Frequency of occurrence and degree of severity were both divided on a four-point scale. Frequency of occurrence is classified as follows: always, often, sometimes and rarely (on 4 to 1 point scale). Similarly, degree of severity was classified asfollows: extreme, great, moderate and little (on 4 to 1 point scale) [Tarun Patel, Hiren Rathod et.al 2016]. 1) Frequency index: This formula is used to rank causes of delay based on frequency of occurrence as identified by the participants. (F.I.) (%) = Σ a (n/N) * 100/4 Where,  a = Constant signifying weighting for each response (from 1 to 4 )  n = Frequency of the responses  N = Total number of responses. 2) Severity index: This formula is used to rank causes of delay based on severity as indicated by the participants. S.I. (%) = Σ a (n/N) * 100/4 Where,  a = Constant signifying weighting for each response (from 1 to 4 )  n = Frequency of the responses  N = Total number of responses. 3) Importance index: The importance index of each cause is calculated as follows: IMPI (%) = [F.I. * S.I.] /100 6. RESULTS AND DISCUSSIONS: The results are found on the basis of comparision of two methods for procurement risk analysis. With the help of the decision making tree the two methods namely RII and IMPI methods are selected to find out the procurement risk analysis in construction Industry. The following table shows findings of various ranksbyusing RII method:
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1895 Table I: Ranks of risks in procurement process using RII method Sr. No Risk Factor ∑W RII Rank A Communication between supplier and contractor procurement process. 125 0.5 7 B The deviation in the scope of the project in procurement process. 123 0.492 9 C The political or social factors influence the procurement process. 107 0.428 12 D Project funding influence the procurement process. 147 0.588 5 E Assess to the project site influence the procurement process. 134 0.536 6 F The technical capability of supplier in the procurement process. 170 0.68 4 G The Technical capability of contractor in procurement 214 0.856 1 H The financial capability of contractor in the procurement. 209 0.836 2 I The involvement of contractor in procurement process influences the procurement. 186 0.744 3 J Litigation process in the procurement. 124 0.496 8 K Strike in market in the procurement process 113 0.452 11 L Availability of material in the market in the procurement process 88 0.352 15 M The transport facility to project site in the procurement. 99 0.396 13 N The recession in the market in the procurement process. 98 0.392 14 O The inflation in material rate in the procurement process. 114 0.456 10 The following graph shows the risk values or ranks by using the above analysis of RII method: Chart 1 Risk values using RII method The following table shows findings of various ranksbyusing IMPI method: Table II: Ranks of risks in procurement process using IMPI method Sr. No Risk Factor F.I. S.I. IMPI (%) Rank A Communicatio n between supplier and contractor procurement process 54.5 52.5 28.61 7 B The deviation in the scope of the project in procurement process. 49.5 49 24.26 8 C The political or social factors influence the procurement process. 42.5 42 7.85 14 D Project funding influence the procurement process. 63 71 44.73 5 E Assess to the project site influence the procurement process. 55 55 30.25 6 F The technical capability of supplier in the procurement process. 75 77 57.75 4 The Technical capability of 82.5 81 66.83 1
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1896 G contractor in procurement H The financial capability of contractor in the procurement. 81.5 81.5 66.42 2 I The involvement of contractor in procurement process influences the procurement. 78.5 76.5 60.05 3 J Litigation process in the procurement 40.5 45 18.23 13 K Strike in market in the procurement process 53 40 21.20 10 L Availability of material in the market in the procurement process 43.5 43.5 18.92 12 M The transport facility to project site in the procurement. 47 43.5 20.45 11 N The recession in the market in the procurement process. 45.5 49.5 22.52 9 O The inflation in material rate in the procurement process. 42.5 40 17 15 Thus, the above table I shows the various ranks of risks in procurement process using IMPI method. The following chart II shows the risk values or ranks by using the above analysis of IMPI method: Chart II- Risk values using IMPI method The following table shows findings of various ranks by comparing RII and IMPI method: Table III: Comparison of RII and IMPI method Sr. No Risk Factor RII Rank IMPI Rank A Communicatio n between supplier and contractor procurement process 0.5 7 28.61 7 B The deviation in the scope of the project in procurement process. 0.492 9 24.26 8 C The political or social factors influence the procurement process. 0.428 12 17.85 14 D Project funding influence the procurement process. 0.588 5 44.73 5 E Assess to the project site influence the procurement process. 0.536 6 30.25 6 F The technical capability of supplier in the procurement process. 0.68 4 57.75 4 The Technical capability of
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1897 G contractor in procurement 0.856 1 66.83 1 H The financial capability of contractor in the procurement 0.836 2 66.42 2 I The involvement of contractor in procurement process influences the procurement 0.744 3 60.05 3 J Litigation process in the procurement 0.496 8 18.23 13 K Strike in market in the procurement process 0.452 11 21.20 10 L Availability of material in the market in the procurement process 0.352 15 18.92 12 M The transport facility to project site in the procurement 0.788 13 20.45 11 N The recession in the market in the procurement process. 0.396 14 22.52 9 O The inflation in material rate in the procurement process. 0.456 10 17 15 Thus, the above table III shows the comparison of various ranks of risks in procurement process using RII and IMPI method. The following graph shows the risk values or ranks by using comparison of RII and IMPI method: 0 5 10 15 20 A B C D E F G H I J K L M N O Comparison of RII & IMPI RII IMPI Chart-III Comparison of ranks of RII and IMPI method 7. CONCLUSION: The ranking by both the methods is not getting differ very much, so we can consider preference of risk by any of these method. So from the above analysis we canconcludethatthe major reasons behind the delays and risks in procurement are project funding for procurement, technical capability of contractor, technical capability of supplier, financial capability of supplier, involvement of contractor in actual procurement process. So, we have to take precautions to avoid these types of risks during procurement. So while doing any project the selectionofcontractorandsupplier are the important factors. Theproperselectionofcontractorand supplier may reduce the other risks like project funding, deviation in the scope of project,etc.Sotakingprecautionsof these risks will reduce the delays in project also. 8. ACKNOWLEDGEMENT: We attribute the success ofprojectstageoneprimarilyto our guide Prof.Rahul Shinde for the efforts taken by himtoguide throughout completion of project and for encouraging us through the tough as well as easier phase in an expert manner with full attention. Wealsoacknowledgethesupport given by Prof. Rahul Shinde, Head of Civil Engineering Department and Dr.C.B.Bangal Principal of providing the necessary facilities and infrastructure for the seminar. We would like to take this opportunity to express our gratitude to all those who have in various ways helped in successfully developing the seminar report from its initial stage to its completion stage. Last but not the least we also acknowledge the efforts made by all staff members of Civil Engineering Department and our friend for their kind co-operation in all phase of the project.
  • 7. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 06 | June -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1898 9. REFERENCES: 1) Anup Wilfred, “a methodology to identifythedelays and rank its causative factors inIndianconstruction industry”, International Research Journal of Engineering and Technology (IRJET), Volume: 02 Issue: 03 | June-2015. 2) Desai Megha, Rajiv Bhatt,“Critical CausesofDelayin Residential Construction Projects: Case Study of Central Gujarat Region of India “(Volume-4 Issue-4, Year of Publication: 2013 3) Hardik Lokhandwala et.al, “RankingoftheCausesof Delay for Private Sector Industrial Construction Projects in Indian Context”, Volume 2,Issue 5, May - 2015 4) M. Marzouk and T. El-Rasas,‘Analyzingdelaycauses in Egyptian construction projects’, Journal of Advanced Research, vol. 5, no. 1, pp. 49-55, 2014. 5) Meet Patel “ Factors affecting on contractor’s bidding strategy in large scale residential construction” Volume 3,Issue 5,May -2016 6) Tarun Patel et.al, “Comparison analysis of parameters affecting material Procurement in construction industry by RII and IMPI methods” IJSDR Volume 1, Issue 5 , May 2016