International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1862
Project Planning, Scheduling and Preparation of Quality Assurance
Control Documents
J.SHARANYASREENIVAS1, G.GAJALAKSHMI2, K.RAVI THEJA3
1P.G Student M.Tech (Structural Engg. and construction managment) , GVIC , Madanapalle, A.P, INDIA
2Head of the Dept, Dept. of Civil Engineering GVIC, Madanapalle, A.P, INDIA
3P.G Student M.Tech (Structural Engg.)SVTM, Madanapalle, A.P, INDIA
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - The project managementtechniquesofplanning,
scheduling and controlling are used to Complete the project
within the stipulated time, scope, quality and cost. These
techniques Can be applied to all types of projects. The study
covers the process of planning and Scheduling of a Multi
Storied Building. In this project Microsoft project planner, a
powerful software tool, is used for planning and scheduling of
the various construction activities of theproject. Learningand
using such a powerful tool for the project management of an
on-going live project is considered as a major outcome of this
project. Quality assurance is theprocessofauditingthequality
requirements and the results from quality control
measurements to ensure appropriate quality standards are
incorporated. Quality assurance is an execution process that
uses data created during Perform Quality control. Quality
assurance provides direction towards control, measure and
protection against qualityproblemsthroughearlywarningsof
trouble ahead. Such early warnings play an important role in
the prevention of both internal and external problems.
Key Words: Project planning, scheduling, Quality
assurance, quality control, Microsoft project software
1. INTRODUCTION
Construction projects are time bound and all project
activities are directed towards the achievement of project
objectives with respect to time, scope and quality. In a
complex project where large number of activities are
performed at different places by different agencies and sub
organizations, with each having its own scheduled targets, a
small delay in the critical activity can affect successor
activities in schedule.
Project planning and schedulingaimsattimelyexecution
of work according to the project planned schedule and can
apply corrective measures in caseofanytimedeviations.Ina
broader sense, time control implies the control of the entire
planning system, as time is directly or in-directly related
with all project activities and project functions.
Quality assurance provides protection against quality
problems through early warnings of trouble ahead. Such
early warnings play an important role in the prevention of
both internal and external problems.
1.1 Objectives
• To study an on-going construction project with focus on
project Planning, Scheduling and preparing Quality
assurance documents.
• To identify the specific methodologies that can be adopted
in the project for Planning, Scheduling and Quality
assurance.
• To identify scheduling technique used in developing
Planning and Scheduling.
• To discuss the effectiveness of the methods and their
usefulness for construction project process.
• Use of computer software like Microsoft project software,
which is most widely and globally used.
• To identify and prepare quality assurance control
documents for the selected case study.
2.0 CONSTRUCTION PROJECT MANAGEMENT
A project is a temporary endeavour undertaken to create a
unique product, service, or result. The temporary nature of
projects indicates a definite beginning and end. The end is
reached when the project’s objectives havebeenachieved or
when the project is terminatedbecauseitsobjectiveswill not
or cannot be met, or when the need for the project no longer
exists. Temporary does not necessarily mean short in
duration. Temporary does not generally apply to the
product, service, or result created by the project; most
projects are undertaken to create a lasting outcome. Major
construction works are time bound and employ huge
resources of men, material and machines. They involve
heavy investments running to crores ofrupees.Theyrequire
a high level of technology and need an effectivemanagement
of resources.
Project management processes comprising the 5 Process
Groups.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1863
These 5 Process Groups are:
• Initiating
• Planning
• Executing
• Monitoring and Controlling, and
• Closing
2.1 Components of a project
A project is an endeavor that is undertaken to produce the
results that are expected from the requesting party.
A project consist of three components namely
• Scope
• Budget
• Schedule
Figure 2.1 Components of a Project
SCOPE: Work to be accomplished in both qualitative and
quantitative.
BUDGET: Refers to the costs measured in currency.
SCHEDULE: Logical sequencing and timing ofthework to be
performed.
2.2 Project Life Cycle
A project life cycle is a collection of generally sequential and
sometimes overlapping project phases whose name and
number are determined by the management and control
needs of the organization or organizations involved in the
project, the nature of the project itself, and its area of
application. The life cycle provides the basic framework for
managing the project, regardless of the specific work
involved. No matter how large or small, simple or complex,
all projects can be mapped to the following life cycle
structure.
• Starting the project
• Organizing and preparing
• Carrying out the project work, and
• Documenting and handover of project
This generic life cycle structure is often referred to when
communicating with upper management or other entities
less familiar with the details of the project. This high-level
view can provide a common frame of reference for
comparing projects—even if they are dissimilar in nature.
2.3 Functions of project management
Management is summarized into five basic functions:
• Planning
• Organizing
• Staffing and provisioning resources
• Directing or leading
• Controlling
Planning:
It involves deciding in advance what is to be done, how and
in what order it is to be done in order to achieve the
objectives. Planning aims at deciding upon the futurecourse
of action. In brief, Planning and scheduling involves the
following:
• Collecting and synthesising information.
•Developing alternative courses of action within specified
constraints.
•Comparing alternatives in terms of objectives feasibility
and consequences.
•Selecting and scheduling the optimum course of action.
•Establishing policies, procedures, methods, schedules,
programs, systems,standardsandbudgetsforaccomplishing
project objectives.
Organising:
It is the process of establishing a structural relationship
among functions of people, so as to streamline the
achievement of assigned objectives. Organising involves the
following main tasks:
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1864
• Dividing the work into component activities.
• Designing job structures.
• Defining performance targets and responsibilities.
• Allocating resources.
•Delegating authority commensurate with responsibility.
•Establishing structural relationship to securecoordination.
Staffing and provisioning resources:
It implies managing and keeping manned, the positions
created by the organization structure and providing them
the right quality resources at the right time. Theseresources
include people, materials, machinery and money. The
connected management tasks include the following:
• Preparing resource procurement schedules.
• Developing specifications for required resources.
• Deciding appropriate sources of procurement.
• Budgeting resources and arranging approvals and
purchases.
• Preventing wastage during resource holding at site.
•Supplying on time required quality and quantity of
resources.
Directing or leading:
It involves influencing people so as to enable them to
contribute to organizational goals efficiently and effectively.
Direction implies the following tasks:
• Providing effective leadership.
• Motivating participant’s behaviour.
• Communicating instructions and orders.
•Providing a suitable climate forsubordinates’development.
Controlling:
It involves monitoring of the performance and applying
corrective measures in case of deviations from the plan. The
process of control can be sub-divided into the following
stages:
• Specifying the factors to be controlled.
• Stating the methods of measuring control factors.
• Evolving systems for generating performance data.
•Monitoring data received and formulating corrective
options.
• Applying corrective measures to put a plan on the
scheduling path.
• Re-planning, when necessary.
3.0 PROJECT PLANNING AND SCHEDULING
Project planning is the process of identifyingall theactivities
necessary to successfully complete a project. Proper
management and analysis of a construction project can be
achieved by proper planning, scheduling and control. The
objective of a project planning is to produce a time table of
work with each job or task allocated a start date and a finish
date, and with the assurance that the things necessary to do
each job or task will be available when required. Although
the common desired results of planning and scheduling is to
finish the project on time.
A scheduling is a work programmer, set date-wise in a
logical sequence; it is a time tableforaction.Timescheduling
is the process of developing a work programme. It implies
programming of the chosen work plan on a calendar basis
and provides the base against which time progress is
measured. A work schedule is an action plan with calendar
date targets, whereas network is a planning technique.
3.1 Principles of planning and scheduling
There must be an explicit operational plan to guide the
entire project. The plan must include and link the three
components of the project: scope, budget and schedule. Too
often, planning is focused onlyonschedulewithoutregard to
the important components ofbudgetandscope.Thisprocess
starts with WBS. Planning, scheduling and controlling begin
at the inception of the project and continue till the life of the
project until completion. The other key principles of
planning and scheduling are listed below:
• To build flexibility into the plan, include allowance for
changes and time for reviews and approvals.
• To always remember that the schedule isthe planfordoing
work and it will never be precisely correct.
• To keep the plan simple, eliminate irrelevant details that
prevent the plan from being readable.
3.2 Steps involved in Project Planning
The following are the step by step procedure for project
planning. They are:
• Make a detailed list of activities
• Prepare a network diagram
• Identify the critical path
• Allocate the resources or juggle the schedule
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1865
• Consider the trade-off of time and money
• Organize the project information
• Record the status of every activity
• Compare reported original plan
3.3 Project management process groups
Project management processes are grouped into four
categories known as Project Management
Process Groups (or Process Groups) mentioned below:
3.3.1 Planning process group
Figure 3.1 Planning process group
The Planning Process Group consists of those processes
performed to establish the total scope of the effort, define
and refine the objectives, and develop the course of action
required to attain those objectives.
The project management plan and project documents
developed as outputs from the Planning Process Group will
explore all aspects of the scope, time, costs, quality,
communication, risk, and procurements.. The Planning
Process Group (Figure 3.1)includestheprojectmanagement
processes identified below.
3.3.2 Executing Process Group
The Executing Process Group consists of those processes
performed to complete the work defined in the project
management plan to satisfy the project specifications. This
Process Group involves coordinating people and resources,
as well as integrating and performing the activities of the
project in accordance with the project management
The Executing Process Group includes the following project
management processes.
• Direct and Manage Project Execution:
Direct and Manage Project Execution is the process of
performing the work defined in the project management
plan to achieve the project’s objectives.
• Perform Quality Assurance:
Perform Quality Assurance is the process of auditing the
quality requirements and the results from quality control
measurements to ensure appropriate quality standards and
operational definitions are used.
Figure 3.2 Executing process group
• Acquire Project Team:
Acquire Project Team is the process of confirming human
resource availability and obtaining the team necessary to
complete project assignments.
• Develop Project Team:
Develop Project Team is the process of improving the
competencies, team interaction, and the overall team
environment to enhance project performance.
• Manage Project Team:
Manage Project Team is the process of tracking team
member performance, providing feedback, resolving issues,
and managing changes to optimize project performance.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1866
3.3.3 Monitoring and Controlling Process Group
Figure 3.3 Monitoring and Controlling Process Group
The Monitoring and Controlling Process Group consists of
those processes required to track, review, and regulate the
progress and performance of the project; identify any areas
in which changes to the plan are required; and initiate the
corresponding changes.
The Monitoring and ControllingProcessGroupalsoincludes:
• Controlling changes and recommending preventive action
in anticipation of possible problems.
• Monitoring the on-going project activities against the
project management plan and the project performance
baseline, and
• Influencing the factors that could circumvent integrated
change control so only approved changes are implemented
3.3.4 Closing process group
The Closing Process Group consists of those processes
performed to finalize all activities across all Project
Management Process Groups to formally complete the
project, phase, or contractual obligations. At project or
phase closure, the following may occur:
• Obtain acceptance by the customer or sponsor
• Conduct post-project or phase-end review
• Record impacts of tailoring to any process
• Document lessons learned
• Apply appropriateupdates toorganizational processassets
• Archive all relevant project documents in the Project
Management Information System (PMIS) to be used as
historical data, and
• Close out procurements
Figure 3.4closing process groups
4.0 PROJECT SCHEDULING
Scheduling is the determination of the timing of activities
and follows logically from the planning process.
4.1 Scheduling Methods
There are four basic scheduling methods that can be used:
• Bar chart
• Line of balance chart
• Network-based diagrams
Bar chart:
Bar charts were first used by Henry Gantt in the early part of
the 20TH century and accordingly are also referred to as
Gantt charts. Bar charts are perhaps the most familiar
method of scheduling
Line of balance:
The LOB is used when the activities or the work within a
project consists of a number of units that are the same. LOB
can be used for subset routines which may be a repetitious
part of a network schedule. It is often used where the same
activities are to be performed by the same team.
Network-based diagrams:
Modern planning and scheduling techniques have their
origins through two developments known as CPM (critical
path method) and PERT (program evaluation and review
technique). There are two types of basic diagrams used in
network scheduling:
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1867
• Activity-on-Arrow (AOA) and
• Activity-on-Node (AON)
Activity-on-Arrow:
AOA is the scheduling method applied when using PERT.
AOA diagrams, like logic diagrams should alwaysmovefrom
left to right, and as shown by Figure 4.1 the lines or arrows
should always consist of a sloping section and a horizontal
section. The AOA is also known as the "i-j" method; it was
referred to as the "circle and connecting line". In this type of
diagram the nodes show events; these are activities which
have no duration — that is they take no time, such as the
start or finish of an activity. The arrows connecting the
nodes represent the activities. The nodes are usually
numbered as a means of identifying the activities in the
network .In activity on arrow (AOA) diagrams, "i" is the
designation given to the start node of an activity and "j" is
the designation given to the finish node of the same activity.
Each node should have its own unique number. The same
number should not be used more than once. The best
procedure is to work out the sequence of activities first
without nodes and then number the nodes after a
satisfactory network has been drawn. Usually "j" number
node is greater than "i" number node, but this is not
mandatory. Forward numbering helps prevent loops.
Figure 4.1 Activity-on-Arrow diagrams
The numbering of nodes is very important because the
activities are normally referred to by their "i" and "j"
designators. For example, if "H" is activity 25-35 then i=25,
j=35. Both i and j represent events and points in time. Unlike
activities, events do not need time for their execution. In
AOA the nodes are represented by circles big enough to
contain an event number, it is advisable not to use
consecutive numbers.
Activity-on-Node:
The AON diagram is constructed using boxes containing
activities, these boxes are called nodes. Arrowed lines,
representing relationshipswithother activities,flowintothe
left of the node and leave on the right of the node. The
arrowed lines, as in logic diagrams, show the "flow" or
sequence of the activities. Lines in AON diagrams represent
the logical relationships among the activities. It is normal to
draw these lines in what is referred to as staff format, which
means the lines are either vertical or horizontal and all
connections being orthogonal. In AON scheduling, the
convention is that only one kind of dependency or logical
relationship between activities is allowed — that is, ''finish-
to-start'' (FS). In other words, the preceding activitymust be
complete before the succeeding activity can commence. As
FS dependencies are the most common relationshipfound in
practice between activities, then the AON network can be
accepted as a valuable method of analyzing plans.
Figure 4.2 Activity-on-Node diagrams
4.3.1 Critical Path Method (CPM)
The most widely used scheduling technique is the critical
path method (CPM) for scheduling. This method calculates
the minimum completion time for a project along with the
possible start and finish times for the project activities.
Critical path method models the activities and events of a
project as a network. Activities are shown as nodes on the
network and events that signify the beginning or ending of
activities are shown as arcs or lines between the nodes. The
figure below shows an example of a CPM network diagram:
Figure 4.3 Critical path method diagrams
4.3.2 PERT (Programme Evaluation Review
Technique)
The Programme Evaluation and Review Technique (PERT)
are employed for planning and controlling the projects
involving uncertainties.
PERT is an event-oriented technique.Itsbasisisa network of
events in which the activities are derived by connecting the
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1868
events. It lays stress on measuring the uncertaintyinactivity
times by using the three-time duration estimation method.
The figure below shows a simple example of a PERT
diagram.
Figure 4.4 Programme Evaluations and Review
Technique
5.0 QUALITY ASSURANCE
Quality assurance refers to the managerial processes which
determine the organizations design, objectives and
resources, the project team, funding agencies, performance
standards and feedback on the project’s performance,
appropriate actions to deal with deviation and all steps
necessary for promoting quality awareness at all levels and
in all parts of the project organisation.
A typical quality assurance programme addresses itself to
the following:
•Organization structure of the project team and quality
assurance department
•Responsibilities and powers of the various personnel
involved
• Identification of the coordinating personnel
• Quality and its programmes
• Quality education and awareness
• Quality circles
• Training
• Setting up of management information systems for quality
• Resolution of technical differences and disputes
• Preparation of quality assurance manuals and their
checklists
• Vendor survey procedure
• Vendor surveillance procedure
Perform quality assurance
Perform Quality Assurance is the process of auditing the
quality requirements and the results from quality control
measurements to ensure appropriate quality standards and
operational definitions are used. Perform Quality Assurance
is an execution process that uses data created during
Perform Quality Control. Continuous process improvement
reduces waste and eliminates activities that do not add
value.
Figure 5.1 Perform quality assurance: Inputs, Tools
and Techniques, and Outputs
List of some of the important BIS codes used to prepare
quality assurance manual are:
• Foundation-As per IS 2950 (part I) – 1981
• Cement-As Per IS 8112-1989 & IS 12269 – 1987
• Hollow and Solid concrete block- As per IS 2185(part I) –
2005
• Concrete Works-As Per IS 456 - 2000
• Sand-As Per IS 2116 – 1980
• Aggregates for concrete-As per IS 2386 - 1963(Part-I to
Part-V)
• Steel- As Per IS 432 (Part-I) – 1982
6.0 CONCLUSION
The construction planning and scheduling was done using
the project management software known as Microsoft
Project and was found effective in scheduling, allocation of
resources and tracking of project.
• The schedule which was prepared here involvesperiodical
as well as day to day observation in scheduling and tracking
of the project.
• Scheduling using computer software as a tool was foundto
be easy and accurate. The project schedule and projecttrack
generation was its main highlight. The schedulereporthelps
in identifying start date, finish date, also the duration of the
project as a whole.
• Quality construction assurance documents were prepared
to maintain the quality aspects in such a manner that the
standards set by BIS are maintained.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1869
REFERENCES
1. Diego Echeverry, C. Williams Ibbs, Simon Kim
(1991),’SequencingKnowledgeforConstructionScheduling’,
Journal of construction engineering and management,
Vol.117, No.1, March.
2. James L. BuratiJr, Michael F. Matthews, Satyanarayana N.
Kalidindi (1991),’Quality Management In Construction
Industry’, Journal of construction engineering and
management, Vol.117, No.2, June.
3. Alexander laufer, Aviadshapira, Dora cohenca-Zall,
Gregory A. Howell (1993), ‘Prebid and Preconstruction
Planning Process’, Journal of construction engineering and
management, Vol.119, No.3, September.
BIOGRAPHIES
J.SHARNYASREENIVAS M.tech
(civil) specialization in structural
and construction management.

Weitere ähnliche Inhalte

Was ist angesagt?

Project management and control
Project management and controlProject management and control
Project management and controlShruti Pendharkar
 
Project management.pptx
Project management.pptxProject management.pptx
Project management.pptxNimra zaman
 
Introduction to Software Project Management
Introduction to Software Project ManagementIntroduction to Software Project Management
Introduction to Software Project ManagementReetesh Gupta
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaJoshua Render
 
Project implimentation
Project implimentationProject implimentation
Project implimentationMazhar Poohlah
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-controlJatindra Malik
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupTùng Trần Thanh
 
Lecture 8 monitoring & controlling (1)
Lecture 8  monitoring & controlling (1)Lecture 8  monitoring & controlling (1)
Lecture 8 monitoring & controlling (1)Nur Azwin
 
Project Management: Integration Management Knowledge Area
Project Management: Integration Management Knowledge AreaProject Management: Integration Management Knowledge Area
Project Management: Integration Management Knowledge AreaJoshua Render
 
07. Project Integration Management
07. Project Integration Management07. Project Integration Management
07. Project Integration ManagementBhuWan Khadka
 
5. project activity and risk planning
5. project activity and risk planning5. project activity and risk planning
5. project activity and risk planningJeanette C. Patindol
 
Monitoring of project implementation
Monitoring of project implementationMonitoring of project implementation
Monitoring of project implementationDejened
 
Project Quality Management - PMBOK6
Project Quality Management - PMBOK6Project Quality Management - PMBOK6
Project Quality Management - PMBOK6Agus Suhanto
 

Was ist angesagt? (18)

PM FrameWork: Module 3
PM FrameWork: Module 3PM FrameWork: Module 3
PM FrameWork: Module 3
 
Project management and control
Project management and controlProject management and control
Project management and control
 
04 project integration management
04 project integration management04 project integration management
04 project integration management
 
Project Management Steps
Project Management StepsProject Management Steps
Project Management Steps
 
Project management.pptx
Project management.pptxProject management.pptx
Project management.pptx
 
Introduction to Software Project Management
Introduction to Software Project ManagementIntroduction to Software Project Management
Introduction to Software Project Management
 
PMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introductionPMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introduction
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge Area
 
Project implimentation
Project implimentationProject implimentation
Project implimentation
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-control
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP Workgroup
 
Lecture 8 monitoring & controlling (1)
Lecture 8  monitoring & controlling (1)Lecture 8  monitoring & controlling (1)
Lecture 8 monitoring & controlling (1)
 
Project Management: Integration Management Knowledge Area
Project Management: Integration Management Knowledge AreaProject Management: Integration Management Knowledge Area
Project Management: Integration Management Knowledge Area
 
07. Project Integration Management
07. Project Integration Management07. Project Integration Management
07. Project Integration Management
 
PM FrameWork: Module 2
PM FrameWork: Module 2PM FrameWork: Module 2
PM FrameWork: Module 2
 
5. project activity and risk planning
5. project activity and risk planning5. project activity and risk planning
5. project activity and risk planning
 
Monitoring of project implementation
Monitoring of project implementationMonitoring of project implementation
Monitoring of project implementation
 
Project Quality Management - PMBOK6
Project Quality Management - PMBOK6Project Quality Management - PMBOK6
Project Quality Management - PMBOK6
 

Ähnlich wie Project Planning, Scheduling and Preparation of Quality Assurance Control Documents

DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project ManagementRasan Samarasinghe
 
Lecture PLAN MONITORING and EVALUATING.
Lecture PLAN  MONITORING and EVALUATING.Lecture PLAN  MONITORING and EVALUATING.
Lecture PLAN MONITORING and EVALUATING.Jo Balucanag - Bitonio
 
Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptxHarsimratDeo1
 
Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptxHarsimratDeo1
 
Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...write31
 
Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...write4
 
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGSOPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGSIAEME Publication
 
Project Management Ch 14.ppt
Project Management Ch 14.pptProject Management Ch 14.ppt
Project Management Ch 14.pptUjalaBatool7
 
Project typed
Project typedProject typed
Project typedRahul
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project managementIRJET Journal
 
Software Project Management - Staffing
Software Project Management - StaffingSoftware Project Management - Staffing
Software Project Management - StaffingTanishqRongta1
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800PRIYANSHU KUMAR
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01samansari22
 

Ähnlich wie Project Planning, Scheduling and Preparation of Quality Assurance Control Documents (20)

DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
Lecture PLAN MONITORING and EVALUATING.
Lecture PLAN  MONITORING and EVALUATING.Lecture PLAN  MONITORING and EVALUATING.
Lecture PLAN MONITORING and EVALUATING.
 
Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptx
 
Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptx
 
sample456.pptx
sample456.pptxsample456.pptx
sample456.pptx
 
Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...
 
Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...
 
PART- 2: Engineering Project Management
PART- 2: Engineering Project Management PART- 2: Engineering Project Management
PART- 2: Engineering Project Management
 
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGSOPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
 
Project Management Ch 14.ppt
Project Management Ch 14.pptProject Management Ch 14.ppt
Project Management Ch 14.ppt
 
Project typed
Project typedProject typed
Project typed
 
Project Management U 1.pptx
Project Management U 1.pptxProject Management U 1.pptx
Project Management U 1.pptx
 
Software Project Management by Dr. B. J. Mohite
Software Project Management by Dr. B. J. MohiteSoftware Project Management by Dr. B. J. Mohite
Software Project Management by Dr. B. J. Mohite
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project management
 
Software Project Management - Staffing
Software Project Management - StaffingSoftware Project Management - Staffing
Software Project Management - Staffing
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
H1303024956
H1303024956H1303024956
H1303024956
 

Mehr von IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

Mehr von IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Kürzlich hochgeladen

VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086anil_gaur
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfRagavanV2
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...soginsider
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projectssmsksolar
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 

Kürzlich hochgeladen (20)

VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 

Project Planning, Scheduling and Preparation of Quality Assurance Control Documents

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1862 Project Planning, Scheduling and Preparation of Quality Assurance Control Documents J.SHARANYASREENIVAS1, G.GAJALAKSHMI2, K.RAVI THEJA3 1P.G Student M.Tech (Structural Engg. and construction managment) , GVIC , Madanapalle, A.P, INDIA 2Head of the Dept, Dept. of Civil Engineering GVIC, Madanapalle, A.P, INDIA 3P.G Student M.Tech (Structural Engg.)SVTM, Madanapalle, A.P, INDIA ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - The project managementtechniquesofplanning, scheduling and controlling are used to Complete the project within the stipulated time, scope, quality and cost. These techniques Can be applied to all types of projects. The study covers the process of planning and Scheduling of a Multi Storied Building. In this project Microsoft project planner, a powerful software tool, is used for planning and scheduling of the various construction activities of theproject. Learningand using such a powerful tool for the project management of an on-going live project is considered as a major outcome of this project. Quality assurance is theprocessofauditingthequality requirements and the results from quality control measurements to ensure appropriate quality standards are incorporated. Quality assurance is an execution process that uses data created during Perform Quality control. Quality assurance provides direction towards control, measure and protection against qualityproblemsthroughearlywarningsof trouble ahead. Such early warnings play an important role in the prevention of both internal and external problems. Key Words: Project planning, scheduling, Quality assurance, quality control, Microsoft project software 1. INTRODUCTION Construction projects are time bound and all project activities are directed towards the achievement of project objectives with respect to time, scope and quality. In a complex project where large number of activities are performed at different places by different agencies and sub organizations, with each having its own scheduled targets, a small delay in the critical activity can affect successor activities in schedule. Project planning and schedulingaimsattimelyexecution of work according to the project planned schedule and can apply corrective measures in caseofanytimedeviations.Ina broader sense, time control implies the control of the entire planning system, as time is directly or in-directly related with all project activities and project functions. Quality assurance provides protection against quality problems through early warnings of trouble ahead. Such early warnings play an important role in the prevention of both internal and external problems. 1.1 Objectives • To study an on-going construction project with focus on project Planning, Scheduling and preparing Quality assurance documents. • To identify the specific methodologies that can be adopted in the project for Planning, Scheduling and Quality assurance. • To identify scheduling technique used in developing Planning and Scheduling. • To discuss the effectiveness of the methods and their usefulness for construction project process. • Use of computer software like Microsoft project software, which is most widely and globally used. • To identify and prepare quality assurance control documents for the selected case study. 2.0 CONSTRUCTION PROJECT MANAGEMENT A project is a temporary endeavour undertaken to create a unique product, service, or result. The temporary nature of projects indicates a definite beginning and end. The end is reached when the project’s objectives havebeenachieved or when the project is terminatedbecauseitsobjectiveswill not or cannot be met, or when the need for the project no longer exists. Temporary does not necessarily mean short in duration. Temporary does not generally apply to the product, service, or result created by the project; most projects are undertaken to create a lasting outcome. Major construction works are time bound and employ huge resources of men, material and machines. They involve heavy investments running to crores ofrupees.Theyrequire a high level of technology and need an effectivemanagement of resources. Project management processes comprising the 5 Process Groups.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1863 These 5 Process Groups are: • Initiating • Planning • Executing • Monitoring and Controlling, and • Closing 2.1 Components of a project A project is an endeavor that is undertaken to produce the results that are expected from the requesting party. A project consist of three components namely • Scope • Budget • Schedule Figure 2.1 Components of a Project SCOPE: Work to be accomplished in both qualitative and quantitative. BUDGET: Refers to the costs measured in currency. SCHEDULE: Logical sequencing and timing ofthework to be performed. 2.2 Project Life Cycle A project life cycle is a collection of generally sequential and sometimes overlapping project phases whose name and number are determined by the management and control needs of the organization or organizations involved in the project, the nature of the project itself, and its area of application. The life cycle provides the basic framework for managing the project, regardless of the specific work involved. No matter how large or small, simple or complex, all projects can be mapped to the following life cycle structure. • Starting the project • Organizing and preparing • Carrying out the project work, and • Documenting and handover of project This generic life cycle structure is often referred to when communicating with upper management or other entities less familiar with the details of the project. This high-level view can provide a common frame of reference for comparing projects—even if they are dissimilar in nature. 2.3 Functions of project management Management is summarized into five basic functions: • Planning • Organizing • Staffing and provisioning resources • Directing or leading • Controlling Planning: It involves deciding in advance what is to be done, how and in what order it is to be done in order to achieve the objectives. Planning aims at deciding upon the futurecourse of action. In brief, Planning and scheduling involves the following: • Collecting and synthesising information. •Developing alternative courses of action within specified constraints. •Comparing alternatives in terms of objectives feasibility and consequences. •Selecting and scheduling the optimum course of action. •Establishing policies, procedures, methods, schedules, programs, systems,standardsandbudgetsforaccomplishing project objectives. Organising: It is the process of establishing a structural relationship among functions of people, so as to streamline the achievement of assigned objectives. Organising involves the following main tasks:
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1864 • Dividing the work into component activities. • Designing job structures. • Defining performance targets and responsibilities. • Allocating resources. •Delegating authority commensurate with responsibility. •Establishing structural relationship to securecoordination. Staffing and provisioning resources: It implies managing and keeping manned, the positions created by the organization structure and providing them the right quality resources at the right time. Theseresources include people, materials, machinery and money. The connected management tasks include the following: • Preparing resource procurement schedules. • Developing specifications for required resources. • Deciding appropriate sources of procurement. • Budgeting resources and arranging approvals and purchases. • Preventing wastage during resource holding at site. •Supplying on time required quality and quantity of resources. Directing or leading: It involves influencing people so as to enable them to contribute to organizational goals efficiently and effectively. Direction implies the following tasks: • Providing effective leadership. • Motivating participant’s behaviour. • Communicating instructions and orders. •Providing a suitable climate forsubordinates’development. Controlling: It involves monitoring of the performance and applying corrective measures in case of deviations from the plan. The process of control can be sub-divided into the following stages: • Specifying the factors to be controlled. • Stating the methods of measuring control factors. • Evolving systems for generating performance data. •Monitoring data received and formulating corrective options. • Applying corrective measures to put a plan on the scheduling path. • Re-planning, when necessary. 3.0 PROJECT PLANNING AND SCHEDULING Project planning is the process of identifyingall theactivities necessary to successfully complete a project. Proper management and analysis of a construction project can be achieved by proper planning, scheduling and control. The objective of a project planning is to produce a time table of work with each job or task allocated a start date and a finish date, and with the assurance that the things necessary to do each job or task will be available when required. Although the common desired results of planning and scheduling is to finish the project on time. A scheduling is a work programmer, set date-wise in a logical sequence; it is a time tableforaction.Timescheduling is the process of developing a work programme. It implies programming of the chosen work plan on a calendar basis and provides the base against which time progress is measured. A work schedule is an action plan with calendar date targets, whereas network is a planning technique. 3.1 Principles of planning and scheduling There must be an explicit operational plan to guide the entire project. The plan must include and link the three components of the project: scope, budget and schedule. Too often, planning is focused onlyonschedulewithoutregard to the important components ofbudgetandscope.Thisprocess starts with WBS. Planning, scheduling and controlling begin at the inception of the project and continue till the life of the project until completion. The other key principles of planning and scheduling are listed below: • To build flexibility into the plan, include allowance for changes and time for reviews and approvals. • To always remember that the schedule isthe planfordoing work and it will never be precisely correct. • To keep the plan simple, eliminate irrelevant details that prevent the plan from being readable. 3.2 Steps involved in Project Planning The following are the step by step procedure for project planning. They are: • Make a detailed list of activities • Prepare a network diagram • Identify the critical path • Allocate the resources or juggle the schedule
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1865 • Consider the trade-off of time and money • Organize the project information • Record the status of every activity • Compare reported original plan 3.3 Project management process groups Project management processes are grouped into four categories known as Project Management Process Groups (or Process Groups) mentioned below: 3.3.1 Planning process group Figure 3.1 Planning process group The Planning Process Group consists of those processes performed to establish the total scope of the effort, define and refine the objectives, and develop the course of action required to attain those objectives. The project management plan and project documents developed as outputs from the Planning Process Group will explore all aspects of the scope, time, costs, quality, communication, risk, and procurements.. The Planning Process Group (Figure 3.1)includestheprojectmanagement processes identified below. 3.3.2 Executing Process Group The Executing Process Group consists of those processes performed to complete the work defined in the project management plan to satisfy the project specifications. This Process Group involves coordinating people and resources, as well as integrating and performing the activities of the project in accordance with the project management The Executing Process Group includes the following project management processes. • Direct and Manage Project Execution: Direct and Manage Project Execution is the process of performing the work defined in the project management plan to achieve the project’s objectives. • Perform Quality Assurance: Perform Quality Assurance is the process of auditing the quality requirements and the results from quality control measurements to ensure appropriate quality standards and operational definitions are used. Figure 3.2 Executing process group • Acquire Project Team: Acquire Project Team is the process of confirming human resource availability and obtaining the team necessary to complete project assignments. • Develop Project Team: Develop Project Team is the process of improving the competencies, team interaction, and the overall team environment to enhance project performance. • Manage Project Team: Manage Project Team is the process of tracking team member performance, providing feedback, resolving issues, and managing changes to optimize project performance.
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1866 3.3.3 Monitoring and Controlling Process Group Figure 3.3 Monitoring and Controlling Process Group The Monitoring and Controlling Process Group consists of those processes required to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes. The Monitoring and ControllingProcessGroupalsoincludes: • Controlling changes and recommending preventive action in anticipation of possible problems. • Monitoring the on-going project activities against the project management plan and the project performance baseline, and • Influencing the factors that could circumvent integrated change control so only approved changes are implemented 3.3.4 Closing process group The Closing Process Group consists of those processes performed to finalize all activities across all Project Management Process Groups to formally complete the project, phase, or contractual obligations. At project or phase closure, the following may occur: • Obtain acceptance by the customer or sponsor • Conduct post-project or phase-end review • Record impacts of tailoring to any process • Document lessons learned • Apply appropriateupdates toorganizational processassets • Archive all relevant project documents in the Project Management Information System (PMIS) to be used as historical data, and • Close out procurements Figure 3.4closing process groups 4.0 PROJECT SCHEDULING Scheduling is the determination of the timing of activities and follows logically from the planning process. 4.1 Scheduling Methods There are four basic scheduling methods that can be used: • Bar chart • Line of balance chart • Network-based diagrams Bar chart: Bar charts were first used by Henry Gantt in the early part of the 20TH century and accordingly are also referred to as Gantt charts. Bar charts are perhaps the most familiar method of scheduling Line of balance: The LOB is used when the activities or the work within a project consists of a number of units that are the same. LOB can be used for subset routines which may be a repetitious part of a network schedule. It is often used where the same activities are to be performed by the same team. Network-based diagrams: Modern planning and scheduling techniques have their origins through two developments known as CPM (critical path method) and PERT (program evaluation and review technique). There are two types of basic diagrams used in network scheduling:
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1867 • Activity-on-Arrow (AOA) and • Activity-on-Node (AON) Activity-on-Arrow: AOA is the scheduling method applied when using PERT. AOA diagrams, like logic diagrams should alwaysmovefrom left to right, and as shown by Figure 4.1 the lines or arrows should always consist of a sloping section and a horizontal section. The AOA is also known as the "i-j" method; it was referred to as the "circle and connecting line". In this type of diagram the nodes show events; these are activities which have no duration — that is they take no time, such as the start or finish of an activity. The arrows connecting the nodes represent the activities. The nodes are usually numbered as a means of identifying the activities in the network .In activity on arrow (AOA) diagrams, "i" is the designation given to the start node of an activity and "j" is the designation given to the finish node of the same activity. Each node should have its own unique number. The same number should not be used more than once. The best procedure is to work out the sequence of activities first without nodes and then number the nodes after a satisfactory network has been drawn. Usually "j" number node is greater than "i" number node, but this is not mandatory. Forward numbering helps prevent loops. Figure 4.1 Activity-on-Arrow diagrams The numbering of nodes is very important because the activities are normally referred to by their "i" and "j" designators. For example, if "H" is activity 25-35 then i=25, j=35. Both i and j represent events and points in time. Unlike activities, events do not need time for their execution. In AOA the nodes are represented by circles big enough to contain an event number, it is advisable not to use consecutive numbers. Activity-on-Node: The AON diagram is constructed using boxes containing activities, these boxes are called nodes. Arrowed lines, representing relationshipswithother activities,flowintothe left of the node and leave on the right of the node. The arrowed lines, as in logic diagrams, show the "flow" or sequence of the activities. Lines in AON diagrams represent the logical relationships among the activities. It is normal to draw these lines in what is referred to as staff format, which means the lines are either vertical or horizontal and all connections being orthogonal. In AON scheduling, the convention is that only one kind of dependency or logical relationship between activities is allowed — that is, ''finish- to-start'' (FS). In other words, the preceding activitymust be complete before the succeeding activity can commence. As FS dependencies are the most common relationshipfound in practice between activities, then the AON network can be accepted as a valuable method of analyzing plans. Figure 4.2 Activity-on-Node diagrams 4.3.1 Critical Path Method (CPM) The most widely used scheduling technique is the critical path method (CPM) for scheduling. This method calculates the minimum completion time for a project along with the possible start and finish times for the project activities. Critical path method models the activities and events of a project as a network. Activities are shown as nodes on the network and events that signify the beginning or ending of activities are shown as arcs or lines between the nodes. The figure below shows an example of a CPM network diagram: Figure 4.3 Critical path method diagrams 4.3.2 PERT (Programme Evaluation Review Technique) The Programme Evaluation and Review Technique (PERT) are employed for planning and controlling the projects involving uncertainties. PERT is an event-oriented technique.Itsbasisisa network of events in which the activities are derived by connecting the
  • 7. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1868 events. It lays stress on measuring the uncertaintyinactivity times by using the three-time duration estimation method. The figure below shows a simple example of a PERT diagram. Figure 4.4 Programme Evaluations and Review Technique 5.0 QUALITY ASSURANCE Quality assurance refers to the managerial processes which determine the organizations design, objectives and resources, the project team, funding agencies, performance standards and feedback on the project’s performance, appropriate actions to deal with deviation and all steps necessary for promoting quality awareness at all levels and in all parts of the project organisation. A typical quality assurance programme addresses itself to the following: •Organization structure of the project team and quality assurance department •Responsibilities and powers of the various personnel involved • Identification of the coordinating personnel • Quality and its programmes • Quality education and awareness • Quality circles • Training • Setting up of management information systems for quality • Resolution of technical differences and disputes • Preparation of quality assurance manuals and their checklists • Vendor survey procedure • Vendor surveillance procedure Perform quality assurance Perform Quality Assurance is the process of auditing the quality requirements and the results from quality control measurements to ensure appropriate quality standards and operational definitions are used. Perform Quality Assurance is an execution process that uses data created during Perform Quality Control. Continuous process improvement reduces waste and eliminates activities that do not add value. Figure 5.1 Perform quality assurance: Inputs, Tools and Techniques, and Outputs List of some of the important BIS codes used to prepare quality assurance manual are: • Foundation-As per IS 2950 (part I) – 1981 • Cement-As Per IS 8112-1989 & IS 12269 – 1987 • Hollow and Solid concrete block- As per IS 2185(part I) – 2005 • Concrete Works-As Per IS 456 - 2000 • Sand-As Per IS 2116 – 1980 • Aggregates for concrete-As per IS 2386 - 1963(Part-I to Part-V) • Steel- As Per IS 432 (Part-I) – 1982 6.0 CONCLUSION The construction planning and scheduling was done using the project management software known as Microsoft Project and was found effective in scheduling, allocation of resources and tracking of project. • The schedule which was prepared here involvesperiodical as well as day to day observation in scheduling and tracking of the project. • Scheduling using computer software as a tool was foundto be easy and accurate. The project schedule and projecttrack generation was its main highlight. The schedulereporthelps in identifying start date, finish date, also the duration of the project as a whole. • Quality construction assurance documents were prepared to maintain the quality aspects in such a manner that the standards set by BIS are maintained.
  • 8. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1869 REFERENCES 1. Diego Echeverry, C. Williams Ibbs, Simon Kim (1991),’SequencingKnowledgeforConstructionScheduling’, Journal of construction engineering and management, Vol.117, No.1, March. 2. James L. BuratiJr, Michael F. Matthews, Satyanarayana N. Kalidindi (1991),’Quality Management In Construction Industry’, Journal of construction engineering and management, Vol.117, No.2, June. 3. Alexander laufer, Aviadshapira, Dora cohenca-Zall, Gregory A. Howell (1993), ‘Prebid and Preconstruction Planning Process’, Journal of construction engineering and management, Vol.119, No.3, September. BIOGRAPHIES J.SHARNYASREENIVAS M.tech (civil) specialization in structural and construction management.