SlideShare ist ein Scribd-Unternehmen logo
1 von 5
Downloaden Sie, um offline zu lesen
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 2545
Planning & Scheduling of Commercial Building Using Microsoft Project
& Application of Principles of Theory of Constraints for Achieving High
Efficiency in Construction Project
Manisha N. Ghotnekar1, Shashank U. Vanakudari2,
1P.G Student, Department of Civil Engineering, Jain College of Engineering, Belagavi.
2Assistant Professor, Department of Civil Engineering, Jain College of Engineering, Belagavi
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - The main goal of this paper is the representation
of comparative survey of constraint’s theory andcriticalchain
project management’s applications, which is well established
according to the critical path method for the programme
planned and scheduled in MS project software for the
construction of project with commercialessence. Thetheoryof
constraints renders the ways to achieve the control over
effective duration concept. CCPM is one of the applications of
TOC to the management of project which outlines the core
restriction as activities in the form of chain with length of
project with the usage of buffer management whose objective
is the give strict plan of construction that guards contrary to
suspicions and cut down the impending impact on changes of
construction by management of bufferseffectivelyinplanning,
scheduling, and controlling to accomplish tasks without
wasting time. Henceforth TOC, gives way for the awareness of
constraints that are faced at the time of construction in order
to reach the high performance and also helps to reduce the
time taken to construct the project undertaken by following
the five procedures of TOC with applications of CCPM and
buffer management. The impact of the above said concept has
to be well understood so that it can be appropriately adopted
in forth coming projects for better provision on time in
relation to its efficiency.
Key Words: Theory of Constraints, Critical Chain project
Management, Buffer Management and Microsoft Project.
1. INTRODUCTION
As we all know that we face many constraints in every
working environment and with the more complexity in
construction project, we need to be much sure about the
planning and scheduling in construction management. If
resources required are limited, it is very difficult for the
schedule planning and controlling in a construction project.
Sometimes we may not know that constraints exist and we
lean to ignore those constraints and concentrate more on
completion of project goal. Even if any organization is small
or big, does stand alone or multiple projects, many of the
projects are difficult to control and manage due to
uncertainty and different commitments like date or budget.
Most of the projects stop before they get completed which
wastes the money, time and effort given for the project.
Generally, the main objective of planning, scheduling and
controlling of a construction projectissuccessful completion
of every single task in the construction work. Constraint can
be defined as anything such as technical sequencing,
temporal/spatial limitations, and safety/quality concerns
which restrict or prevent the project from achieving its goal.
In its field complex construction projects such as industries,
large substructure works like underground works and
building projects like airports, campuses, hospitals etc. are
all subjected to various adverseimpactsonoverall execution
of project. Before the clearer topology constraints of
interdependencies and material connectivity between
various customs, other constraintsshouldbesatisfied before
the work progresses in the field. They exist in every working
environment even though everyprojectwill haveatleastone
constraint which represents relationship between any
process and a particular object, which prevents the project
from achieving its goal. They may cause undesirable results
or may not be contributory in the achievement of the goal.
Constraints should be managed or the impact musteither be
reduced or eliminated.
Constraints are generally classified into two main classes,
one as Internal and the other as External. Constraints that
are under the rheostat and are present inside the systemare
known as internal constraints.Thisindicateswheneverthere
is more demand in the market and the system is unable to
fulfill it, so required actions has to be taken to overcome this
constraints. External constraints are lesser under control
and are outside the system. This clearly means that the
system capacity slacks to achieve the so called external
constraints and their deeds undertaken will somewhat
decrease undesirable effects instead of constraint
elimination. Constraints with advanced impact are the root
issues and lower impactconstraintsarewithrelativelylower
impact which relates to environment factors on buildings
project performance. Theory of Constraints is applied to
critical chain method which offers advancedmethodologyto
handle the connected hazard and uncertainty. In the way to
minimize the possibilities of risk and the occurring
uncertainty buffer management used, and it also gives away
the report stating the ratio of impacts. Now a days just the
scheduling does not lead to accuracy, to defeat this problem
the latest schedules likeCCPMorbuffer managementisused.
Hence by the documentation of this method, we clearly
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 2546
understand that the heavy expense will be reduced within
the expected time.
1.1 Current Problem
As we know that usually projects fails at an alarming
frequency. Numerical evaluations show that projects more
than thirty percentage got failed in advance to completion,
by deteriorating overall money, time also strength over
them. Hence that failed projects take in more costeveryyear
which also happen in entirely kinds of projects also
humanities. Every project has an aim and satisfying and to
obtain such project aim three necessary conditions are
required as follows
1. The project scope should set a least measures to its
consequences.
2. Supreme price should be fixed by the project budget.
3. Extreme period should be fixed in the project schedule.
The above three necessary conditions are dependedon each
other. More the project consumes time, more it costs. More
the project cost, more the project consumes time. The more
projects consume time, the more opportunities occur to
change the project scope. The cost and schedule of the
project will increase if the project scope changes. One of the
main constraints of the project is the period of time in which
it should be completed, which is due to the following
reasons:
1. A delay in implementation of project in a high increase of
cost contingency.
2. A delay in implementation of project has negative
consequences about cash flow,relatedmostlytotheincrease
of general or overhead costs.
3. Change in scope of the project, change in technology of
project tasks implementation or change in the functionality
in the matter of project activities expectations may occur in
the situations of extending completion time of the project
and the expectations of stakeholders are modified.
In construction activities there will a clear correlation
between the completion time of project and its probability.
Beyond the directive project deadline has negative financial
consequences, such as delay in achieving proposed benefits,
postponing profit and repeatedlylossofandshareinmarket.
The consequences of delay in construction project and
investment may be significantly more than the exceeding
budget only.
2. METHODOLOGY
2.1 Theory of Constraints
The constraints theory (TOC) established by Goldratt is a
method marked in detecting and eliminating constraints in
procedures which are restricting system’s objectives. A
constraint is anything which restricts the system or entity
from moving or achieving to its goals while one of the
interesting features of Constraintstheoryisoneit essentially
arranges the activity perfection and top significance is
continually given to the present restriction. TOC offers
extremely focused methodology solution when there is
urgent need for improvement in environment. The effective
implementation of Theory of Constraints will provide the
following benefits.
1. Fast improvement in progress
2. Increased profit
3. Enhanced capacity
4. Reduction in lead time
5. Inventory reduction
The method of current development initiates with a pure
identification of a systems aim likewise the instituting of
performance measurement parameters that are directly
associated to the systems aim. The TOC delivers tool for
assessing the results of the method earlier, throughout and
also when it runs. TOC concentrates on the restrictions of
few dynamic constraints that bound the success of the
system. The time period in which a project should be
completed is considered as one of the core constraints,
which is due to the following three main reasons:
1. The delay in project implementation has negative
consequences regardingincome,relatedprimarilytotherise
in overhead cost (general cost).
2. The delay in the project implementation also results in
very high increase of price contingency.
3. The expectation of stake holders are modified and in the
condition of extending project completion times or project
selections that might occur expectations to vary the scope of
the project, and modifications in the technology of
implementing the project task or modification in the
functionality of the focus of project activities.
In command to achieve current development within the
situation of physical constraints inconstructionprojectsand
for the improvement of performance, the TOC establishes a
five step decision process as follows
Step 1. Recognize the organization restriction: In this
step a organization recognize whichpartfoundstheweakest
relation and regulates whether it is a physical restrictionsor
a policy connected matter.
Step 2. Adoptingamethod whichexploitstherestriction:
Organizations exploit “the restrictions by exploiting similar
compelling part withoutobligatingtoreal expensivechanges
and/ or advancements.
Step 3. Subordinate everything else: With a assumed tie
for exploiting the restriction, organizations modify the rest
of the organization to change thelimitationtoinformatmost
effectiveness and then assess the results to inspect if the
restriction continuous to hold back system presentation.Ifit
is, the organization lasts to step 4.If it’s not, the restriction
has been removed and therefore the organization skips fast
to step 5.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 2547
Step 4. Assessment of the restriction: If an organization
influences step4, it means that step2 and step3 where not
satisfactory in removing the restriction. At this fact, the
organization estimates restrictionsbytaking nomatterwhat
action is required to remove it. This might involve major
changes to the current system like restructuring. Capital
improvement or divestiture. Since these usually need a
considerable up-front investment, the organization should
be certain that the constraint cannot be broken in step1
through three before proceeding.
Step 5. Back to first step1: Look out for inactivity. When a
control is broken, the organization once again repeats all
steps everywhere, looking for the next object limiting the
system performance. At an corresponding time, it monitors
however changes related to succeeding restrictions which
may impact the restraints that are already broken,therefore
preventing solution of inertia.
Step 1
Step 2
Step 3
Step 4
Step 5
Fig -1 Flow chart of Five Steps Represent the TOC
Approach
There are easy ways to identify the physical constraints and
to examine them in regard to the markets real demand
which includes the following: manufacturing constraints,
raw material constraints, equipment constraints, input
restraints, staff limitations, process limitations and similar
mechanisms.
2.2 Critical Chain Project Management
CCPM is derived from the Theory of Constraints and was
developed in 1997. The method is described by “Critical
Chain” (Goldratt, 1997) and apply the Theory of Constraints
to offers an enhanced approach to manage the associated
risk and uncertainty in the project toachieveperformance in
project schedule management. The critical chain is the
longest chain and determines the lead time of the project.
Basically the method describeshowtocombatstretching out
task duration estimates,causedbyavoidingtask uncertainty.
Buffer management is introduced in CCPM in order to
control uncertainties with respect to project timing. Critical
Restraint methodology is a program grid analysis technique
that receipts into consideration of assignmentdependences,
restricted supply accessibility and buffers. As in the case of
Critical Chain Management initial step is identifying set of
activities that leads to longest track to project achievement
that are known as critical chains. It may be longer than CPM
program because it includes resources into consideration.
Next step is use efficient buffer management for limiting the
project schedule by decreasing the activity period
approximations. CCPM concentrates on eliminating the
program delays, overestimation of task period and wastage
of interior buffers correspondingly.
2.3 Buffer Management
Goldratt's critical chain methodology originated Theory of
Buffer management for planning program. Goldratt titles
that each duration approximations have safety period that
are wasted many a times in three ways which is adequate
buffer designed. He competes that the assemblies of
programs itself is additionally accountable for unwanted of
safety time. When more task cometogetheratonepointthan
delays are handed however gains don't seem to be. Instead
of permitting every task to possess some safety, this
approach recommend to drag out all the available safety in
every individual task and allocate them most likely time and
aggregates all the safety ultimately of the project that act as
complete project buffer. Similarlyit alsooffersfeederbuffers
at every point wherever non critical chainnourishesintothe
critical chain.
Buffer management eliminates the buffer from the activity
approximation, thereby making a violent activity
approximation. The setting of violent activity goals can
usually lead to a decrease in activity period. For safety in
terms of appropriateness, 3 buffers are announced to a
program: a project buffer, feeding buffer, and resource
buffer. Although it is assumed that the announced buffers
and shorter length of tasks will not lead to a modification of
the growth of the critical path. Particularly, “Activity period
uncertainty”, “path period uncertainty”, and “resource
uncertainties” are 3 types of uncertainties in project design
and planning. In demand to decrease those uncertainties,
these buffers are utilized and used within the CCPM with
Recognize the organization
restriction
Adopting a method which exploit the
restriction
Subordinate everything else to the
above choice
Does a new
restriction
boundary output
Do not allow to break organization
restriction
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 2548
added times to protect what's necessary to the achievement
of that project.
2.4 Buffer Management in Construction
Buffer management is used to create valuation of feeding
and buffers replacementconcerningtothetasksandprojects
in order to deal with indeterminate case in construction
projects. It will deliver a vibrant vision of increasing in
impact of danger for performing of project. Compared with
CPM method, critical chain involves the concern of resource
constraints and it concentrates on effect of vagueness
organization. This management throws light on the practice
of buffer managing without deteriorating crucial period in
constructionproject routine. Moreover,thesurveyconcludes
the scenario applying critical chain management in
construction. The following diagram clearly elaborates the
CCPM applications in construction. As mentioned in the
above context, three different estimated buffers are
incorporated in stream of CPM method, and the related
techniques are convoluted in the below displayed figure.
Fig-2 The Application of Buffer in Critical Chain
At the last critical chain activity at the projects finishing line
allocation of the project buffer is done to defend schedule
against clog. Feeding buffer comes into its form to defend
critical chain compared to clog among critical chain and
noncritical chain depending ontheirchainsoffeeding.Buffer
of resources comes into frame to certify that they are
assessable in fact required for the safe guard of the schedule
and it also help to protect resource availability without
adding extra time to the chain.
If the project gets finished before the planned program
which means the buffer is increasing. On the other hand it
indicates that the project is likely to be delayed if buffer gets
decreased. The main procedures below explain the
applications of buffers in construction projects:
Step 1: By the means of CPM method constructionschedule
is planned.
Step 2: The protective estimate for every activity is
identified and defined.
Step 3: The sensible estimate for every activity is identified
and defined.
Step 4: Based on steps 2 and 3 eliminatethesafetyduration
from each activity.
Step 5: Identify the longest chain of reliedtasks,asa critical
chain for the predictable schedule that gets recognized in
step 4.
Step 6: At the final stage of the critical chain, insert the
project buffer.
Step 7: During noncritical chain integrating with critical
chain feeding buffers are inserted.
Step 8: To certify the activity to availability of resource
buffers are inserted.
3. CONCLUSIONS
To have a noble understanding of the recognizedconstraints
at the development stages, and proposal for the certification
of constraints in significant project planning program and
schedule as well as during operation stage, the organization
should be conscious of the constraints that meet by tracing
of the growth. The Theory of Constraints facilitates the
examination of norms primary outdated developed rules,
policies, and measures and focuses on the few serious
constraints that restrict the achievementoftheorganization.
The status of the projects in terms of data, valuesandvisuals
has been obtained by using MS project software and the
corrective measures on the constraints occurred in the
project schedule are solved by application of TOC, Critical
Chain Management and management of buffer to ensure the
success of projects. The procedure of buffer in TOC and
Critical Chain highlights laid on finishing activities lacking
wasting time. It allows monitoring and having a fine grip
over project schedule and can be utilized in order to reduce
total project duration without any extra resource. The
planning and scheduling of project using MSP, which
portrays total duration of 989 days for completion
considered. After applying principles of Theory of
Constraints (TOC) the project duration reduced to 888 days.
Hence TOC provides the concept for achieving effective
duration control by managing the buffers in scheduling
planning and control to achieve significant improvement
resulting in higher efficiency.
Chart -1: Comparison of constraints and theory of
constraints
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 2549
According to the study, The Theory of Constraints had been
successfully used and is an vital tool to help in the provision
of a successful project. Moreover shorter duration of the
project can be accomplished by use of Critical Chain and
management of buffering can be well applied in
construction projects without dense up costs and also the
use of buffers management in project planning will recover
the effectiveness precisely in the planning phase of
construction.
REFERENCES
[1] Bikram Nepal (2014) Time Management in Projects:
Tools, Techniques and Methods.
[2] Ch. Lakshmi Tulasi, A. Ramakrishna Rao (2012) Review
on Theory of Constraints.
[3] Chotchai Charoenngam, Planning And Scheduling
Consideration and Constraints In Automated Construction
Environment.
[4] Ellen lau, janet jiahui kong,Identificationofconstraintsin
construction projects to improve performance.
[5] Gary P. Moynihan (2014) Application of the Theory of
Constraints for Capacity Requirements Analysis.
[6] Goldratt, E. M. & Cox, J. (1989) Chapter4:The importance
of a system’s constraints. The Theory of Constraints Journal,
Avraham Y. Goldratt Institute, New haven.
[7] H. Steyn (2001) Project Management Applications of
Theory of Constraints beyond Critical chain scheduling.
[8] Jan, Shu-Hui, Ho, S. Ping (2006), Construction Project
Buffer Management in scheduling planning and control.
[9] Krystyna Araszkiewicz Application of Critical Chain
Management in Construction Projects Schedules in a Multi-
Project Environment.
[10] Lawrence P. Leach (2000) Critical Chain Project
Management.
[11] McMullen, T.B. (1998). Introduction to the Theory of
Constraints (TOC) Management System.
[12] Maryam Mirzaei, Victoria J. Mabin. Exploring
Constraints in Projects.
[13] Malvika.Rajeevan, R.Nagavinothini (2015) Time
Optimization for Resource-Constrained Project Scheduling
Using Meta-Heuristic Approach.
[14] Nanfang Cui (1997), The calculation of buffer size
considering activity schedule risk.
[15] Ron Winter, PSP, F. Burak Evrenosoglu,(2011) MS
Project For Construction Schedulers.
[16] Siddesh Pai & S.Giridharan, Application of Theory Of
Constraints And Critical Chain Method For Project
Management In Ultra Mega Power Projects.
[17] Steven J. Balderstone and Victoria J. Mabin (1990). A
Review of Goldratt’s Theory of Constraints (TOC) – lessons
from the international Literature.
[18] T. Subramani1, D. S. Stephan Jabasingh, J. Jayalakshmi
Analysis of Cost Controlling In Construction Industries by
Earned Value Method Using Primavera.
[19] Ted Blackmon, Rehul Saxena, and Lingguang. A
Conceptual Framework .For Total ConstraintInConstruction
[20] Victoria Mabin, Goldratt's "Theory of Constraints"
Thinking Processes: A Systems Methodology linking Soft
with Hard.

Weitere ähnliche Inhalte

Was ist angesagt?

Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingSHAZEBALIKHAN1
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Schedulingakashpadole
 
Construction project management
Construction project managementConstruction project management
Construction project managementSenthil Kannan
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project ManagementAravind Samala
 
Quantity Surveying & Cost Planning
Quantity Surveying & Cost PlanningQuantity Surveying & Cost Planning
Quantity Surveying & Cost PlanningGalala University
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & managementManit Agarwal
 
Report on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridgeReport on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridgeKundan Sanap
 
Construction project management
Construction project managementConstruction project management
Construction project managementsaif hasan
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedMichael Pink
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyorLY97
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Managementsrinivas2036
 
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...Shrikant Kate
 
Role of Project Management Consultancy in Construction Project
Role of Project Management Consultancy in Construction ProjectRole of Project Management Consultancy in Construction Project
Role of Project Management Consultancy in Construction ProjectIOSR Journals
 
CONSTRUCTION TECHNOLOGY
CONSTRUCTION TECHNOLOGY CONSTRUCTION TECHNOLOGY
CONSTRUCTION TECHNOLOGY VISHNU VIJAYAN
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction managementXubitech
 
Primavara
PrimavaraPrimavara
Primavaradanabl
 
Construction management
Construction managementConstruction management
Construction managementUsama Khalid
 
Mechanization in construction_Advanced Construction Technology (Semester-6), ...
Mechanization in construction_Advanced Construction Technology (Semester-6), ...Mechanization in construction_Advanced Construction Technology (Semester-6), ...
Mechanization in construction_Advanced Construction Technology (Semester-6), ...A Makwana
 
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...IRJET Journal
 
Construction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdfConstruction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdfMeleseMengistu
 

Was ist angesagt? (20)

Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential Building
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Quantity Surveying & Cost Planning
Quantity Surveying & Cost PlanningQuantity Surveying & Cost Planning
Quantity Surveying & Cost Planning
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
 
Report on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridgeReport on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridge
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
 
Role of Project Management Consultancy in Construction Project
Role of Project Management Consultancy in Construction ProjectRole of Project Management Consultancy in Construction Project
Role of Project Management Consultancy in Construction Project
 
CONSTRUCTION TECHNOLOGY
CONSTRUCTION TECHNOLOGY CONSTRUCTION TECHNOLOGY
CONSTRUCTION TECHNOLOGY
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
 
Primavara
PrimavaraPrimavara
Primavara
 
Construction management
Construction managementConstruction management
Construction management
 
Mechanization in construction_Advanced Construction Technology (Semester-6), ...
Mechanization in construction_Advanced Construction Technology (Semester-6), ...Mechanization in construction_Advanced Construction Technology (Semester-6), ...
Mechanization in construction_Advanced Construction Technology (Semester-6), ...
 
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
 
Construction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdfConstruction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdf
 

Ähnlich wie Planning & Scheduling of Commercial Building using Microsoft Project & Application of Principles of Theory of Constraints for Achieving High Efficiency in Construction Project

Calculation of the construction time systematic management of project uncert...
Calculation of the construction time  systematic management of project uncert...Calculation of the construction time  systematic management of project uncert...
Calculation of the construction time systematic management of project uncert...eSAT Journals
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...IRJET Journal
 
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET Journal
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET Journal
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTIRJET Journal
 
Analysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsAnalysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsIRJET Journal
 
The Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project SuccessThe Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project SuccessIRJET Journal
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsIRJET Journal
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project managementIRJET Journal
 
76 s201905
76 s20190576 s201905
76 s201905IJRAT
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET Journal
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewIRJET Journal
 
Assessment of Project Monitoring and Control Techniques in Ondo State Agency ...
Assessment of Project Monitoring and Control Techniques in Ondo State Agency ...Assessment of Project Monitoring and Control Techniques in Ondo State Agency ...
Assessment of Project Monitoring and Control Techniques in Ondo State Agency ...Dr. Amarjeet Singh
 
Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...IRJET Journal
 
Activity schedule and affective control of component based project
Activity schedule and affective control of component based projectActivity schedule and affective control of component based project
Activity schedule and affective control of component based projecteSAT Journals
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET Journal
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET Journal
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET Journal
 
Delay Analysis for an On-Going Residential Project
Delay Analysis for an On-Going Residential ProjectDelay Analysis for an On-Going Residential Project
Delay Analysis for an On-Going Residential ProjectIRJET Journal
 

Ähnlich wie Planning & Scheduling of Commercial Building using Microsoft Project & Application of Principles of Theory of Constraints for Achieving High Efficiency in Construction Project (20)

Calculation of the construction time systematic management of project uncert...
Calculation of the construction time  systematic management of project uncert...Calculation of the construction time  systematic management of project uncert...
Calculation of the construction time systematic management of project uncert...
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...
 
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
 
Analysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsAnalysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction Projects
 
The Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project SuccessThe Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project Success
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction Projects
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project management
 
PERT
PERTPERT
PERT
 
76 s201905
76 s20190576 s201905
76 s201905
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
 
Assessment of Project Monitoring and Control Techniques in Ondo State Agency ...
Assessment of Project Monitoring and Control Techniques in Ondo State Agency ...Assessment of Project Monitoring and Control Techniques in Ondo State Agency ...
Assessment of Project Monitoring and Control Techniques in Ondo State Agency ...
 
Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...
 
Activity schedule and affective control of component based project
Activity schedule and affective control of component based projectActivity schedule and affective control of component based project
Activity schedule and affective control of component based project
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
 
Delay Analysis for an On-Going Residential Project
Delay Analysis for an On-Going Residential ProjectDelay Analysis for an On-Going Residential Project
Delay Analysis for an On-Going Residential Project
 

Mehr von IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

Mehr von IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Kürzlich hochgeladen

Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Christo Ananth
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 

Kürzlich hochgeladen (20)

Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 

Planning & Scheduling of Commercial Building using Microsoft Project & Application of Principles of Theory of Constraints for Achieving High Efficiency in Construction Project

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 2545 Planning & Scheduling of Commercial Building Using Microsoft Project & Application of Principles of Theory of Constraints for Achieving High Efficiency in Construction Project Manisha N. Ghotnekar1, Shashank U. Vanakudari2, 1P.G Student, Department of Civil Engineering, Jain College of Engineering, Belagavi. 2Assistant Professor, Department of Civil Engineering, Jain College of Engineering, Belagavi ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - The main goal of this paper is the representation of comparative survey of constraint’s theory andcriticalchain project management’s applications, which is well established according to the critical path method for the programme planned and scheduled in MS project software for the construction of project with commercialessence. Thetheoryof constraints renders the ways to achieve the control over effective duration concept. CCPM is one of the applications of TOC to the management of project which outlines the core restriction as activities in the form of chain with length of project with the usage of buffer management whose objective is the give strict plan of construction that guards contrary to suspicions and cut down the impending impact on changes of construction by management of bufferseffectivelyinplanning, scheduling, and controlling to accomplish tasks without wasting time. Henceforth TOC, gives way for the awareness of constraints that are faced at the time of construction in order to reach the high performance and also helps to reduce the time taken to construct the project undertaken by following the five procedures of TOC with applications of CCPM and buffer management. The impact of the above said concept has to be well understood so that it can be appropriately adopted in forth coming projects for better provision on time in relation to its efficiency. Key Words: Theory of Constraints, Critical Chain project Management, Buffer Management and Microsoft Project. 1. INTRODUCTION As we all know that we face many constraints in every working environment and with the more complexity in construction project, we need to be much sure about the planning and scheduling in construction management. If resources required are limited, it is very difficult for the schedule planning and controlling in a construction project. Sometimes we may not know that constraints exist and we lean to ignore those constraints and concentrate more on completion of project goal. Even if any organization is small or big, does stand alone or multiple projects, many of the projects are difficult to control and manage due to uncertainty and different commitments like date or budget. Most of the projects stop before they get completed which wastes the money, time and effort given for the project. Generally, the main objective of planning, scheduling and controlling of a construction projectissuccessful completion of every single task in the construction work. Constraint can be defined as anything such as technical sequencing, temporal/spatial limitations, and safety/quality concerns which restrict or prevent the project from achieving its goal. In its field complex construction projects such as industries, large substructure works like underground works and building projects like airports, campuses, hospitals etc. are all subjected to various adverseimpactsonoverall execution of project. Before the clearer topology constraints of interdependencies and material connectivity between various customs, other constraintsshouldbesatisfied before the work progresses in the field. They exist in every working environment even though everyprojectwill haveatleastone constraint which represents relationship between any process and a particular object, which prevents the project from achieving its goal. They may cause undesirable results or may not be contributory in the achievement of the goal. Constraints should be managed or the impact musteither be reduced or eliminated. Constraints are generally classified into two main classes, one as Internal and the other as External. Constraints that are under the rheostat and are present inside the systemare known as internal constraints.Thisindicateswheneverthere is more demand in the market and the system is unable to fulfill it, so required actions has to be taken to overcome this constraints. External constraints are lesser under control and are outside the system. This clearly means that the system capacity slacks to achieve the so called external constraints and their deeds undertaken will somewhat decrease undesirable effects instead of constraint elimination. Constraints with advanced impact are the root issues and lower impactconstraintsarewithrelativelylower impact which relates to environment factors on buildings project performance. Theory of Constraints is applied to critical chain method which offers advancedmethodologyto handle the connected hazard and uncertainty. In the way to minimize the possibilities of risk and the occurring uncertainty buffer management used, and it also gives away the report stating the ratio of impacts. Now a days just the scheduling does not lead to accuracy, to defeat this problem the latest schedules likeCCPMorbuffer managementisused. Hence by the documentation of this method, we clearly
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 2546 understand that the heavy expense will be reduced within the expected time. 1.1 Current Problem As we know that usually projects fails at an alarming frequency. Numerical evaluations show that projects more than thirty percentage got failed in advance to completion, by deteriorating overall money, time also strength over them. Hence that failed projects take in more costeveryyear which also happen in entirely kinds of projects also humanities. Every project has an aim and satisfying and to obtain such project aim three necessary conditions are required as follows 1. The project scope should set a least measures to its consequences. 2. Supreme price should be fixed by the project budget. 3. Extreme period should be fixed in the project schedule. The above three necessary conditions are dependedon each other. More the project consumes time, more it costs. More the project cost, more the project consumes time. The more projects consume time, the more opportunities occur to change the project scope. The cost and schedule of the project will increase if the project scope changes. One of the main constraints of the project is the period of time in which it should be completed, which is due to the following reasons: 1. A delay in implementation of project in a high increase of cost contingency. 2. A delay in implementation of project has negative consequences about cash flow,relatedmostlytotheincrease of general or overhead costs. 3. Change in scope of the project, change in technology of project tasks implementation or change in the functionality in the matter of project activities expectations may occur in the situations of extending completion time of the project and the expectations of stakeholders are modified. In construction activities there will a clear correlation between the completion time of project and its probability. Beyond the directive project deadline has negative financial consequences, such as delay in achieving proposed benefits, postponing profit and repeatedlylossofandshareinmarket. The consequences of delay in construction project and investment may be significantly more than the exceeding budget only. 2. METHODOLOGY 2.1 Theory of Constraints The constraints theory (TOC) established by Goldratt is a method marked in detecting and eliminating constraints in procedures which are restricting system’s objectives. A constraint is anything which restricts the system or entity from moving or achieving to its goals while one of the interesting features of Constraintstheoryisoneit essentially arranges the activity perfection and top significance is continually given to the present restriction. TOC offers extremely focused methodology solution when there is urgent need for improvement in environment. The effective implementation of Theory of Constraints will provide the following benefits. 1. Fast improvement in progress 2. Increased profit 3. Enhanced capacity 4. Reduction in lead time 5. Inventory reduction The method of current development initiates with a pure identification of a systems aim likewise the instituting of performance measurement parameters that are directly associated to the systems aim. The TOC delivers tool for assessing the results of the method earlier, throughout and also when it runs. TOC concentrates on the restrictions of few dynamic constraints that bound the success of the system. The time period in which a project should be completed is considered as one of the core constraints, which is due to the following three main reasons: 1. The delay in project implementation has negative consequences regardingincome,relatedprimarilytotherise in overhead cost (general cost). 2. The delay in the project implementation also results in very high increase of price contingency. 3. The expectation of stake holders are modified and in the condition of extending project completion times or project selections that might occur expectations to vary the scope of the project, and modifications in the technology of implementing the project task or modification in the functionality of the focus of project activities. In command to achieve current development within the situation of physical constraints inconstructionprojectsand for the improvement of performance, the TOC establishes a five step decision process as follows Step 1. Recognize the organization restriction: In this step a organization recognize whichpartfoundstheweakest relation and regulates whether it is a physical restrictionsor a policy connected matter. Step 2. Adoptingamethod whichexploitstherestriction: Organizations exploit “the restrictions by exploiting similar compelling part withoutobligatingtoreal expensivechanges and/ or advancements. Step 3. Subordinate everything else: With a assumed tie for exploiting the restriction, organizations modify the rest of the organization to change thelimitationtoinformatmost effectiveness and then assess the results to inspect if the restriction continuous to hold back system presentation.Ifit is, the organization lasts to step 4.If it’s not, the restriction has been removed and therefore the organization skips fast to step 5.
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 2547 Step 4. Assessment of the restriction: If an organization influences step4, it means that step2 and step3 where not satisfactory in removing the restriction. At this fact, the organization estimates restrictionsbytaking nomatterwhat action is required to remove it. This might involve major changes to the current system like restructuring. Capital improvement or divestiture. Since these usually need a considerable up-front investment, the organization should be certain that the constraint cannot be broken in step1 through three before proceeding. Step 5. Back to first step1: Look out for inactivity. When a control is broken, the organization once again repeats all steps everywhere, looking for the next object limiting the system performance. At an corresponding time, it monitors however changes related to succeeding restrictions which may impact the restraints that are already broken,therefore preventing solution of inertia. Step 1 Step 2 Step 3 Step 4 Step 5 Fig -1 Flow chart of Five Steps Represent the TOC Approach There are easy ways to identify the physical constraints and to examine them in regard to the markets real demand which includes the following: manufacturing constraints, raw material constraints, equipment constraints, input restraints, staff limitations, process limitations and similar mechanisms. 2.2 Critical Chain Project Management CCPM is derived from the Theory of Constraints and was developed in 1997. The method is described by “Critical Chain” (Goldratt, 1997) and apply the Theory of Constraints to offers an enhanced approach to manage the associated risk and uncertainty in the project toachieveperformance in project schedule management. The critical chain is the longest chain and determines the lead time of the project. Basically the method describeshowtocombatstretching out task duration estimates,causedbyavoidingtask uncertainty. Buffer management is introduced in CCPM in order to control uncertainties with respect to project timing. Critical Restraint methodology is a program grid analysis technique that receipts into consideration of assignmentdependences, restricted supply accessibility and buffers. As in the case of Critical Chain Management initial step is identifying set of activities that leads to longest track to project achievement that are known as critical chains. It may be longer than CPM program because it includes resources into consideration. Next step is use efficient buffer management for limiting the project schedule by decreasing the activity period approximations. CCPM concentrates on eliminating the program delays, overestimation of task period and wastage of interior buffers correspondingly. 2.3 Buffer Management Goldratt's critical chain methodology originated Theory of Buffer management for planning program. Goldratt titles that each duration approximations have safety period that are wasted many a times in three ways which is adequate buffer designed. He competes that the assemblies of programs itself is additionally accountable for unwanted of safety time. When more task cometogetheratonepointthan delays are handed however gains don't seem to be. Instead of permitting every task to possess some safety, this approach recommend to drag out all the available safety in every individual task and allocate them most likely time and aggregates all the safety ultimately of the project that act as complete project buffer. Similarlyit alsooffersfeederbuffers at every point wherever non critical chainnourishesintothe critical chain. Buffer management eliminates the buffer from the activity approximation, thereby making a violent activity approximation. The setting of violent activity goals can usually lead to a decrease in activity period. For safety in terms of appropriateness, 3 buffers are announced to a program: a project buffer, feeding buffer, and resource buffer. Although it is assumed that the announced buffers and shorter length of tasks will not lead to a modification of the growth of the critical path. Particularly, “Activity period uncertainty”, “path period uncertainty”, and “resource uncertainties” are 3 types of uncertainties in project design and planning. In demand to decrease those uncertainties, these buffers are utilized and used within the CCPM with Recognize the organization restriction Adopting a method which exploit the restriction Subordinate everything else to the above choice Does a new restriction boundary output Do not allow to break organization restriction
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 2548 added times to protect what's necessary to the achievement of that project. 2.4 Buffer Management in Construction Buffer management is used to create valuation of feeding and buffers replacementconcerningtothetasksandprojects in order to deal with indeterminate case in construction projects. It will deliver a vibrant vision of increasing in impact of danger for performing of project. Compared with CPM method, critical chain involves the concern of resource constraints and it concentrates on effect of vagueness organization. This management throws light on the practice of buffer managing without deteriorating crucial period in constructionproject routine. Moreover,thesurveyconcludes the scenario applying critical chain management in construction. The following diagram clearly elaborates the CCPM applications in construction. As mentioned in the above context, three different estimated buffers are incorporated in stream of CPM method, and the related techniques are convoluted in the below displayed figure. Fig-2 The Application of Buffer in Critical Chain At the last critical chain activity at the projects finishing line allocation of the project buffer is done to defend schedule against clog. Feeding buffer comes into its form to defend critical chain compared to clog among critical chain and noncritical chain depending ontheirchainsoffeeding.Buffer of resources comes into frame to certify that they are assessable in fact required for the safe guard of the schedule and it also help to protect resource availability without adding extra time to the chain. If the project gets finished before the planned program which means the buffer is increasing. On the other hand it indicates that the project is likely to be delayed if buffer gets decreased. The main procedures below explain the applications of buffers in construction projects: Step 1: By the means of CPM method constructionschedule is planned. Step 2: The protective estimate for every activity is identified and defined. Step 3: The sensible estimate for every activity is identified and defined. Step 4: Based on steps 2 and 3 eliminatethesafetyduration from each activity. Step 5: Identify the longest chain of reliedtasks,asa critical chain for the predictable schedule that gets recognized in step 4. Step 6: At the final stage of the critical chain, insert the project buffer. Step 7: During noncritical chain integrating with critical chain feeding buffers are inserted. Step 8: To certify the activity to availability of resource buffers are inserted. 3. CONCLUSIONS To have a noble understanding of the recognizedconstraints at the development stages, and proposal for the certification of constraints in significant project planning program and schedule as well as during operation stage, the organization should be conscious of the constraints that meet by tracing of the growth. The Theory of Constraints facilitates the examination of norms primary outdated developed rules, policies, and measures and focuses on the few serious constraints that restrict the achievementoftheorganization. The status of the projects in terms of data, valuesandvisuals has been obtained by using MS project software and the corrective measures on the constraints occurred in the project schedule are solved by application of TOC, Critical Chain Management and management of buffer to ensure the success of projects. The procedure of buffer in TOC and Critical Chain highlights laid on finishing activities lacking wasting time. It allows monitoring and having a fine grip over project schedule and can be utilized in order to reduce total project duration without any extra resource. The planning and scheduling of project using MSP, which portrays total duration of 989 days for completion considered. After applying principles of Theory of Constraints (TOC) the project duration reduced to 888 days. Hence TOC provides the concept for achieving effective duration control by managing the buffers in scheduling planning and control to achieve significant improvement resulting in higher efficiency. Chart -1: Comparison of constraints and theory of constraints
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 2549 According to the study, The Theory of Constraints had been successfully used and is an vital tool to help in the provision of a successful project. Moreover shorter duration of the project can be accomplished by use of Critical Chain and management of buffering can be well applied in construction projects without dense up costs and also the use of buffers management in project planning will recover the effectiveness precisely in the planning phase of construction. REFERENCES [1] Bikram Nepal (2014) Time Management in Projects: Tools, Techniques and Methods. [2] Ch. Lakshmi Tulasi, A. Ramakrishna Rao (2012) Review on Theory of Constraints. [3] Chotchai Charoenngam, Planning And Scheduling Consideration and Constraints In Automated Construction Environment. [4] Ellen lau, janet jiahui kong,Identificationofconstraintsin construction projects to improve performance. [5] Gary P. Moynihan (2014) Application of the Theory of Constraints for Capacity Requirements Analysis. [6] Goldratt, E. M. & Cox, J. (1989) Chapter4:The importance of a system’s constraints. The Theory of Constraints Journal, Avraham Y. Goldratt Institute, New haven. [7] H. Steyn (2001) Project Management Applications of Theory of Constraints beyond Critical chain scheduling. [8] Jan, Shu-Hui, Ho, S. Ping (2006), Construction Project Buffer Management in scheduling planning and control. [9] Krystyna Araszkiewicz Application of Critical Chain Management in Construction Projects Schedules in a Multi- Project Environment. [10] Lawrence P. Leach (2000) Critical Chain Project Management. [11] McMullen, T.B. (1998). Introduction to the Theory of Constraints (TOC) Management System. [12] Maryam Mirzaei, Victoria J. Mabin. Exploring Constraints in Projects. [13] Malvika.Rajeevan, R.Nagavinothini (2015) Time Optimization for Resource-Constrained Project Scheduling Using Meta-Heuristic Approach. [14] Nanfang Cui (1997), The calculation of buffer size considering activity schedule risk. [15] Ron Winter, PSP, F. Burak Evrenosoglu,(2011) MS Project For Construction Schedulers. [16] Siddesh Pai & S.Giridharan, Application of Theory Of Constraints And Critical Chain Method For Project Management In Ultra Mega Power Projects. [17] Steven J. Balderstone and Victoria J. Mabin (1990). A Review of Goldratt’s Theory of Constraints (TOC) – lessons from the international Literature. [18] T. Subramani1, D. S. Stephan Jabasingh, J. Jayalakshmi Analysis of Cost Controlling In Construction Industries by Earned Value Method Using Primavera. [19] Ted Blackmon, Rehul Saxena, and Lingguang. A Conceptual Framework .For Total ConstraintInConstruction [20] Victoria Mabin, Goldratt's "Theory of Constraints" Thinking Processes: A Systems Methodology linking Soft with Hard.