International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1557
Factor Affecting Construction Cost and Time in road project
Pavan pal1, Dr. Mukesh Pandey2
1M.Tech. Student, Civil Engineering Department, ITM University, Gwalior,M.P, INDIA
2Professor and Head of Civil Engineering Department, ITM University, Gwalior, M.P, INDIA
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - Most construction projects in developing countries
are characterized by overruns in time and cost. This research
is conducted in an attempt to identify major factors that are
most responsible for affecting of construction cost and time. A
descriptive study was carried out and two types of data were
collected. The overrun variables were extracted from the
literature and from a thorough examination of the
questionnaire survey. The study is conductedwithreferenceto
existing theoretical literature, published and unpublished
research. The study is mainly a literaturereview/surveyon the
affect of the time and cost on the road construction project.
The primary findings emanating from the study revealed that
empirical studies have identified a number of important
factors which affected construction cost. There are fifty ( 50 )
factors are collected from the literature survey and divided
into the seven group such as consultant related, material
related, labor related, client related, equipment related,
contractor related and external related group The factors are
ranked according to the fuzzy method. 5 most significant
factors come out by the ranking through the fuzzy method
such as Late delivery of equipments , Effect of weather, High
cost of labor, Shortage of site labor, High cost of machinery
and its maintenance on site are the most affected factors
.These factors are most important to avoiding the affect of
construction cost and time.
Key Words: Analysis of the factors that affects the road
construction projects.
1.INTRODUCTION
Cost and time affecting of the construction projects is the
universal phenomenon that mostly occurs in the
construction road projects. The critical resultofthetimeand
cost affecting is time and cost overruns. Factor affecting of
the construction project have a debilitate impacts on parties
(owner, contractor, consultant) to a contract in terms of
failure of the contract and general feeling of unpleasant
towards each other. In my study, there are two types of the
data are collected first is one from literature survey and
second is one from questionnaire survey.
The questionnaire survey completed by thesis related tothe
factors of the construction time and cost affecting and
different publication journals. There are 50 common factors
are collected from the literature survey and divided into the
seven group in the guidance of guide such as group of
consultant related , group of material related, group of labor
related, group of contractor related, group of client related,
group of equipment related, and group of external related
factor affected cost and time and the questionnaire survey
have completed at the twenty two(22) number of
construction road projectsite.Thetwentytwonumberof the
questionnaire form filled up with the valuable opinionofthe
experts and according to this opinion thefuzzymethodology
provided rank to each group and each factors of the
construction time and cost affected. The fuzzy methodology
is the most important techniques to find out the top rank of
the factors. In my finding of my research, there are top three
group out of seven group are group of equipment related,
group of labor related and the group of client related. Each
group have mostly four to Accurate estimation of
construction costs is heavily dependent on theavailabilityof
quality historical cost data and the level of professional
expertise, among other things. The limited information
available at the early stages of a construction project may
mean the quantity surveyor must make assumptions about
the design details of a project, which may not eventuate as
project design, planning and construction evolve (Liu and
Zhu, 2007).
1.1 LITERATURE REVIEW
In this chapter the data is collected from the literature
survey and find out the major factor affecting construction
time and cost in the construction road project. In the
literature survey we observed that the most of the project
have cost and time affect and from these projects collected
the fifty major factors of the construction cost and time
affecting.
According to Rajakumar cost overruns are more common
in infrastructure projects especially, more common in road
construction activities. Theimpactsofcostoverrunsarevery
high in developing countries compared to developed
countries. In fact 100% of projects are suffered by cost
overruns in developing countries. (42)
According to Ibrahim Mahamid1+1, Amund Bruland2
this study is conducted to identify the cost overrun causesin
road construction projects in the West Bank in Palestine
from consultants’ view. A questionnaire survey of 40
consultants from was performed. The survey included. (51)
Suggested factors through literature review. The factors are
ranked according to the degree of importanceasassessedby
the respondents. The findings reveal that the top five
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1558
affecting factors are: materials price fluctuation, insufficient
time for estimate, experience in contracts, size of contract,
and incomplete drawings. (45)
According to Abdullah Alhomidan the aim of this studyis
to identify the factors causing cost overrun in road
construction projects in Saudi Arabia from contractors’
viewpoint. The risk map of 41 factors considered in a survey
indicates that the most factors affecting cost overrunin road
construction projects are: internal administrativeproblems,
payments delay, poor communication betweenconstruction
parties, and delays in decision making. (34)
1.2 METHODOLOGY
Various literatures related to the projects are reviewed.
Based on the review, the factors affecting cost and time are
identified which helps to frame a questionnaire.
Questionnaire survey is conducted among civil engineers of
various road construction site. These survey responses are
analyses using fuzzy method.
The data collected from the 22 construction site of the road
and according to the valuable opinion of the experts, the
fuzzy method is used to find out the most important factors
that affected the construction cost and time.
According to description of severity, the responses of the
respondents are collected from the construction site of the
road.
There are in total of twenty two (22) sets of survey
questionnaire was distributed to the targeted in order to
identify the most important factors of the factor affecting of
construction road projects . The questionnairessurveywere
distributed to the construction profession who are take part
in the construction road projects site and experience about
this field. The questionnaire was completed by experienced
persons who have specific experience in this area.
Group of the factors
(1) Factor of consultant related
(2) Factor of material related
(3) Factor of labor related
(4) Factor of contractor related
(5) Factor of client related
(6) Factor of equipment related
(7) Factor of external related
The following method used establishing the normalized
weight of the various factors that contribute to causes of
construction delays. There are consist of following steps to
analyzing the data.
a) Convert the opinion of the expertsintothelinguistic
numbers
N U P L A
0.0 0.1 0.5 0.6 0.8
0.0 0.2 0.6 0.7 0.9
0.1 0.3 0.7 0.8 1
Where
A=Always, L=Likely, P=Possible, U=Unlikely,N=Never
b) Find out the average of the all linguistic numbers
c) Calculate the defuzzyfied values
d) Find out the weight of the all factors
e) Provided the rank to the factor according to their
normalized weight
Triangular fuzzy no is computed as
Here
e = Defuzzyfied value
a = Average of first linguistic no of the all opinion
for a particular factor
b = Average of second linguistic no of the all opinion
for a particular factor
c = Average of third linguistic no of the all opinion
for a particular factor
2. Analysis of data
Table 1 Factor of consultant related
s
n
factors a b c D A W R
1 Frequent
design
changes
1.5
2
1.8
4
2.2
8 1.87
12.
9
0.14
4 3
2 Mistakes and
errors in
design
1.3
8
1.7
2
2.1
6
1.74
5
0.13
4 6
3 Unclear
specifications 1.4
1.7
2
2.1
6 1.75
0.13
5 5
4 Lateapproval 1.3
4
1.6
4
2.0
8
1.67
5
0.12
9 7
5 Late design
works
1.5
8
1.9
2
2.3
6
1.94
5 0.15 2
6 Late 1.7 2.1 2.5 2.16 0.16 1
Level of Severity Description
1 Never
2 Unlikely
3 Possible
4 Likely
5 Always
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1559
inspection 8 4 8 6
7 Late in
reviewing
and
approving
design
document by
consultant
1.4
4
1.7
8
2.1
8
1.79
5
0.13
8 4
Where
a=(N*0+U*0.1+P*0.5+L*0.6+A*0.8)/5
b=(N*0+U*0.2+P*0.6+L*0.7+A*0.9)/5
c=(N*0.1+U*0.3+P*0.7+L*0.8+A*1)/5
D.value=(a+2*b+c)/4
A=average of defuzzyfiedy value
Weight(w)=D.value/A.O.D
Rank=R
Figure 1 Factors of consultant related
Table 2 Overall ranking of the all factors
s.no Factors W R
1 Late delivery of equipments 0.3 1
2 Effect of weather 0.26 2
3 High cost of labor 0.252 3
4 Shortage of site labor 0.246 4
5 High cost of machinery and its
maintenance 0.246
5
6 Insufficient Numbers of
equipment 0.229
6
7 Change orders. 0.223 7
8 Equipment availability and
failure 0.223
8
9 Accident on site 0.221 9
10 Delay in progress payment by
owner 0.21
10
11 Client requirements on quality 0.209 11
12 Labor absenteeism 0.204 12
13 Labor productivity 0.197 13
14 Owner interference 0.191 14
15 Late inspection 0.166 15
16 Financial difficulties of owner 0.165 16
17 Late design works 0.15 17
18 Unforeseen ground conditions 0.148
6
18
19 Shortage of materials 0.148 19
20 Wastage of the materials 0.147 20
21 Poor technical performance 0.146 21
22 Frequent design changes 0.144 22
23 Late in reviewing and
approving design document by
consultant 0.138
23
24 Fluctuation in prices of
materials 0.137
24
25 Shortage of technical
personnel(skilled labor) 0.135
25
26 Mistakes and errors in design 0.134 26
27 Late approval 0.129 27
28 Social and cultural impacts 0.12 28
29 Unavailable construction
materials 0.109
29
30 Lack of raw materials sources 0.107 30
31 Government requirements 0.102 31
32 Late delivery of materials 0.1 32
33 Contractor's poor site
management and supervision 0.094
33
34 Thefts of materials on site 0.093 34
35 Inadequate contractor
experience 0.09
35
36 improper constructionmethod 0.087 36
37 Rework from poor material
quality 0.085
37
38 late issuing of approval
documents 0.08
38
39 Incompetent subcontractors 0.078 39
40 Incorrect material take off
from drawings and design
document 0.075
40
41 Delay in materials
procurement 0.074
41
42 Slow in making decisions 0.072 42
43 Incorrect planning and
scheduling by contractors 0.068
43
44 late submission of nominated
materials 0.066
44
45 undefined scope of working 0.063 45
46 Postponement of project 0.06 46
47 changes in management ways 0.055 47
48 Cash flow and financial
difficulties faced by
contractors 0.053
48
49 poor communication between
construction parties 0.052
49
50 Shortage of technical
personnel(skilled labor) 0.135
50
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1560
Table 3 Ranking of group of the factors that affect time
and cost
s.n Group of the factors AVERAGE
R
1 factor of consultant related 0.1422 5
2 factor of material related 0.1111 6
3 factor of labor related 0.2068 2
4 factor of contractor related 0.0709 7
5 factor of client related 0.1996 3
6 factor of equipment related 0.2495 1
7 Factor of external related 0.1662 4
Figure 2 Ranking of group that affect time and cost
3. CONCLUSIONS
In the present time, the construction industries is biggest
industries in India and it supporttodevelopingandattaining
object of the society.
The main objective of this study which have been find out at
the beginning of study was identifying the critical factor of
the cost and time affecting in the construction road projects.
These objectives were performed by the questionnaire
survey that was designed with regard to the knowledge of
Indian construction industries and their respond had a
significant influence on this study. Also the during the
process of filling questionnaire andoral interviewshelpedin
realizing the good answer to the main factor of the
construction time and cost affecting. During questionnaire
survey, they gave their opinion related to construction time
and cost affecting and according to these valuable opinions
of the experts, find out the top most factors of The
construction time and cost affecting using the fuzzy
methodology. The fuzzy methodology isbasedonthehuman
judgment or opinion. The result of the fuzzy methodology.
According to weight that came out from the calculation
provided the rank and this rank indicated the power of the
factor. Those factors are the most important in construction
industries to avoiding the construction time and cost
affecting that factor have the highest weight. In my study,
find out the top forth group of the factors out of seven group
of the factors that most important to avoid or minimize the
construction time and cost affecting in theroadconstruction
projects. The factor groups of equipment related have first
rank, labor related have secondrank andthirdrank havethe
client related .have forth rank external related. The fuzzy
method is applied data provided by different expertsthetop
forth rank is came out in each group. The construction time
and cost affecting may avoided by considering these factors.
These factors have played very important role for occurring
the construction time cost affecting in the construction
industries because the most of the experts gave our opinion
regarding these factors and he accepted that construction
time and cost affecting can be avoided by considering these
factors.
When consider the all fifty factor in a group and find out the
rank according their normalizedweightthen topfourfactors
are came out that have 1st, 2nd and 3rd 4th rank. The top
most four factors are Late delivery of equipments, Effect of
weather, High cost of labor, Shortageofsitelabor. Thesefour
factors belongs to group of the factor of equipment related,
group of the labor related and group of the client related,
means during the construction the management of the
money, equipment and material are most important. Now a
days, all the construction work is depend on the money,
machinery and material so availability of money, machines
and material are most important in the construction
industries. To avoiding the construction cost and time,these
factors should be consider in mind during the construction
work. The contractor should be proper management inboth
labors and construction equipments to timely completionof
the projects under the cost.
REFERENCES
1. Endut, I.R., Shehu, Z., Akintoye, A., and Jaafar, A., 2009,
“Cost and Time of Construction Projects in Malaysia,” in
Fifth International Conference on Construction in the
21st Century (CITC-V) “Collaboration and Integrationin
Engineering, Management and Technology” May 20-22,
2009, Istanbul, Turkey.
2. Liu, L. and Zhu, K. (2007). Improving cost estimates of
construction projects using phased cost factors. Journal
of Construction Engineering and Management, 133(1):
91–95.
3. Memon, A. H., I.A. Rahman, Abdullah, M.R., & Azis, A.A.A.
(2011). Time Overrun in Construction Projectsfromthe
Perspective of Project ManagementConsultant(PMC).
Journal of Surveying, Construction and Property, 2(1),
54-66
4. Rajakumar A C 04 | Apr-2016. Analysis of Cost Overrun
in Road Construction Activities – A Critical Review M.E.
final year in Construction EngineeringandManagement
Meenakshi Sundararajan Engineering College, Chennai
24 – India
5. Ibrahim Mahamid1+1, Amund Bruland2 2011 Cost
Overrun Causes in Road Construction Projects:
‘’ConsultantsPerspective1PhD,NorwegianUniversityof
Science and Technology (NTNU), Civil Eng. Dept.,
Trondheim, Norway. 2Professor, Norwegian University
of Science and Technology (NTNU), Civil Eng. Dept.,
Trondheim, Norway.

Weitere ähnliche Inhalte

Was ist angesagt?

Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectIRJET Journal
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...iosrjce
 
Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...IJLT EMAS
 
IRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET Journal
 
The Bateman Approach towards achieving economic and financial requirements fo...
The Bateman Approach towards achieving economic and financial requirements fo...The Bateman Approach towards achieving economic and financial requirements fo...
The Bateman Approach towards achieving economic and financial requirements fo...Steve Burks
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET Journal
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Sankalp Swarnkar
 
causes and implication of delay in construction
causes and implication of delay in constructioncauses and implication of delay in construction
causes and implication of delay in constructionsudinak
 
Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...ijtsrd
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...IJERA Editor
 
Diagnose the causes of cost deviation in highway construction
Diagnose the causes of cost deviation in highway constructionDiagnose the causes of cost deviation in highway construction
Diagnose the causes of cost deviation in highway constructionFaiq M. S. Al-Zwainy
 
A Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction RisksA Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction RisksIRJET Journal
 
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...IRJET Journal
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsTwana Ahmad
 
“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”IOSR Journals
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentIJERD Editor
 
Ijirt100070 paper
Ijirt100070 paperIjirt100070 paper
Ijirt100070 paperMolay Reja
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overruneSAT Journals
 
The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Co...
The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Co...The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Co...
The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Co...ijtsrd
 

Was ist angesagt? (20)

Time overruns
Time overrunsTime overruns
Time overruns
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road project
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...
 
IRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction Projects
 
The Bateman Approach towards achieving economic and financial requirements fo...
The Bateman Approach towards achieving economic and financial requirements fo...The Bateman Approach towards achieving economic and financial requirements fo...
The Bateman Approach towards achieving economic and financial requirements fo...
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
 
causes and implication of delay in construction
causes and implication of delay in constructioncauses and implication of delay in construction
causes and implication of delay in construction
 
Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...
 
Diagnose the causes of cost deviation in highway construction
Diagnose the causes of cost deviation in highway constructionDiagnose the causes of cost deviation in highway construction
Diagnose the causes of cost deviation in highway construction
 
A Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction RisksA Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction Risks
 
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
 
“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
Ijirt100070 paper
Ijirt100070 paperIjirt100070 paper
Ijirt100070 paper
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Co...
The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Co...The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Co...
The Rank of Risk Factors Affecting Time Delay and Cost Overrun of Building Co...
 

Ähnlich wie Factor Affecting Construction Cost and Time in road project

INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTIRJET Journal
 
Causes of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectsCauses of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectseSAT Journals
 
Causes of delay in indian transportation
Causes of delay in indian transportationCauses of delay in indian transportation
Causes of delay in indian transportationeSAT Publishing House
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsIRJET Journal
 
Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...
Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...
Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...IRJET Journal
 
Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis IOSR Journals
 
Time delay and cost escalation in construction works
Time delay and cost escalation in construction worksTime delay and cost escalation in construction works
Time delay and cost escalation in construction worksvivatechijri
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET Journal
 
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET Journal
 
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionRisk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionIRJET Journal
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Managementijsrd.com
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET Journal
 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET Journal
 
An empirical study on key determinants of construction Delay
An empirical study on key determinants of construction DelayAn empirical study on key determinants of construction Delay
An empirical study on key determinants of construction DelayIRJET Journal
 
journalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfjournalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfKarthikeyanP288430
 
Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...
Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...
Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...ijtsrd
 

Ähnlich wie Factor Affecting Construction Cost and Time in road project (20)

INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
 
Causes of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectsCauses of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projects
 
Causes of delay in indian transportation
Causes of delay in indian transportationCauses of delay in indian transportation
Causes of delay in indian transportation
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
 
Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...
Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...
Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...
 
Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis
 
Time delay and cost escalation in construction works
Time delay and cost escalation in construction worksTime delay and cost escalation in construction works
Time delay and cost escalation in construction works
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
 
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction Project
 
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionRisk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Management
 
D012261521
D012261521D012261521
D012261521
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
 
I012646171
I012646171I012646171
I012646171
 
I012646171
I012646171I012646171
I012646171
 
An empirical study on key determinants of construction Delay
An empirical study on key determinants of construction DelayAn empirical study on key determinants of construction Delay
An empirical study on key determinants of construction Delay
 
journalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfjournalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdf
 
Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...
Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...
Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...
 

Mehr von IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

Mehr von IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Kürzlich hochgeladen

Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...soginsider
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projectssmsksolar
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf203318pmpc
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086anil_gaur
 

Kürzlich hochgeladen (20)

Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 

Factor Affecting Construction Cost and Time in road project

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1557 Factor Affecting Construction Cost and Time in road project Pavan pal1, Dr. Mukesh Pandey2 1M.Tech. Student, Civil Engineering Department, ITM University, Gwalior,M.P, INDIA 2Professor and Head of Civil Engineering Department, ITM University, Gwalior, M.P, INDIA ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - Most construction projects in developing countries are characterized by overruns in time and cost. This research is conducted in an attempt to identify major factors that are most responsible for affecting of construction cost and time. A descriptive study was carried out and two types of data were collected. The overrun variables were extracted from the literature and from a thorough examination of the questionnaire survey. The study is conductedwithreferenceto existing theoretical literature, published and unpublished research. The study is mainly a literaturereview/surveyon the affect of the time and cost on the road construction project. The primary findings emanating from the study revealed that empirical studies have identified a number of important factors which affected construction cost. There are fifty ( 50 ) factors are collected from the literature survey and divided into the seven group such as consultant related, material related, labor related, client related, equipment related, contractor related and external related group The factors are ranked according to the fuzzy method. 5 most significant factors come out by the ranking through the fuzzy method such as Late delivery of equipments , Effect of weather, High cost of labor, Shortage of site labor, High cost of machinery and its maintenance on site are the most affected factors .These factors are most important to avoiding the affect of construction cost and time. Key Words: Analysis of the factors that affects the road construction projects. 1.INTRODUCTION Cost and time affecting of the construction projects is the universal phenomenon that mostly occurs in the construction road projects. The critical resultofthetimeand cost affecting is time and cost overruns. Factor affecting of the construction project have a debilitate impacts on parties (owner, contractor, consultant) to a contract in terms of failure of the contract and general feeling of unpleasant towards each other. In my study, there are two types of the data are collected first is one from literature survey and second is one from questionnaire survey. The questionnaire survey completed by thesis related tothe factors of the construction time and cost affecting and different publication journals. There are 50 common factors are collected from the literature survey and divided into the seven group in the guidance of guide such as group of consultant related , group of material related, group of labor related, group of contractor related, group of client related, group of equipment related, and group of external related factor affected cost and time and the questionnaire survey have completed at the twenty two(22) number of construction road projectsite.Thetwentytwonumberof the questionnaire form filled up with the valuable opinionofthe experts and according to this opinion thefuzzymethodology provided rank to each group and each factors of the construction time and cost affected. The fuzzy methodology is the most important techniques to find out the top rank of the factors. In my finding of my research, there are top three group out of seven group are group of equipment related, group of labor related and the group of client related. Each group have mostly four to Accurate estimation of construction costs is heavily dependent on theavailabilityof quality historical cost data and the level of professional expertise, among other things. The limited information available at the early stages of a construction project may mean the quantity surveyor must make assumptions about the design details of a project, which may not eventuate as project design, planning and construction evolve (Liu and Zhu, 2007). 1.1 LITERATURE REVIEW In this chapter the data is collected from the literature survey and find out the major factor affecting construction time and cost in the construction road project. In the literature survey we observed that the most of the project have cost and time affect and from these projects collected the fifty major factors of the construction cost and time affecting. According to Rajakumar cost overruns are more common in infrastructure projects especially, more common in road construction activities. Theimpactsofcostoverrunsarevery high in developing countries compared to developed countries. In fact 100% of projects are suffered by cost overruns in developing countries. (42) According to Ibrahim Mahamid1+1, Amund Bruland2 this study is conducted to identify the cost overrun causesin road construction projects in the West Bank in Palestine from consultants’ view. A questionnaire survey of 40 consultants from was performed. The survey included. (51) Suggested factors through literature review. The factors are ranked according to the degree of importanceasassessedby the respondents. The findings reveal that the top five
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1558 affecting factors are: materials price fluctuation, insufficient time for estimate, experience in contracts, size of contract, and incomplete drawings. (45) According to Abdullah Alhomidan the aim of this studyis to identify the factors causing cost overrun in road construction projects in Saudi Arabia from contractors’ viewpoint. The risk map of 41 factors considered in a survey indicates that the most factors affecting cost overrunin road construction projects are: internal administrativeproblems, payments delay, poor communication betweenconstruction parties, and delays in decision making. (34) 1.2 METHODOLOGY Various literatures related to the projects are reviewed. Based on the review, the factors affecting cost and time are identified which helps to frame a questionnaire. Questionnaire survey is conducted among civil engineers of various road construction site. These survey responses are analyses using fuzzy method. The data collected from the 22 construction site of the road and according to the valuable opinion of the experts, the fuzzy method is used to find out the most important factors that affected the construction cost and time. According to description of severity, the responses of the respondents are collected from the construction site of the road. There are in total of twenty two (22) sets of survey questionnaire was distributed to the targeted in order to identify the most important factors of the factor affecting of construction road projects . The questionnairessurveywere distributed to the construction profession who are take part in the construction road projects site and experience about this field. The questionnaire was completed by experienced persons who have specific experience in this area. Group of the factors (1) Factor of consultant related (2) Factor of material related (3) Factor of labor related (4) Factor of contractor related (5) Factor of client related (6) Factor of equipment related (7) Factor of external related The following method used establishing the normalized weight of the various factors that contribute to causes of construction delays. There are consist of following steps to analyzing the data. a) Convert the opinion of the expertsintothelinguistic numbers N U P L A 0.0 0.1 0.5 0.6 0.8 0.0 0.2 0.6 0.7 0.9 0.1 0.3 0.7 0.8 1 Where A=Always, L=Likely, P=Possible, U=Unlikely,N=Never b) Find out the average of the all linguistic numbers c) Calculate the defuzzyfied values d) Find out the weight of the all factors e) Provided the rank to the factor according to their normalized weight Triangular fuzzy no is computed as Here e = Defuzzyfied value a = Average of first linguistic no of the all opinion for a particular factor b = Average of second linguistic no of the all opinion for a particular factor c = Average of third linguistic no of the all opinion for a particular factor 2. Analysis of data Table 1 Factor of consultant related s n factors a b c D A W R 1 Frequent design changes 1.5 2 1.8 4 2.2 8 1.87 12. 9 0.14 4 3 2 Mistakes and errors in design 1.3 8 1.7 2 2.1 6 1.74 5 0.13 4 6 3 Unclear specifications 1.4 1.7 2 2.1 6 1.75 0.13 5 5 4 Lateapproval 1.3 4 1.6 4 2.0 8 1.67 5 0.12 9 7 5 Late design works 1.5 8 1.9 2 2.3 6 1.94 5 0.15 2 6 Late 1.7 2.1 2.5 2.16 0.16 1 Level of Severity Description 1 Never 2 Unlikely 3 Possible 4 Likely 5 Always
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1559 inspection 8 4 8 6 7 Late in reviewing and approving design document by consultant 1.4 4 1.7 8 2.1 8 1.79 5 0.13 8 4 Where a=(N*0+U*0.1+P*0.5+L*0.6+A*0.8)/5 b=(N*0+U*0.2+P*0.6+L*0.7+A*0.9)/5 c=(N*0.1+U*0.3+P*0.7+L*0.8+A*1)/5 D.value=(a+2*b+c)/4 A=average of defuzzyfiedy value Weight(w)=D.value/A.O.D Rank=R Figure 1 Factors of consultant related Table 2 Overall ranking of the all factors s.no Factors W R 1 Late delivery of equipments 0.3 1 2 Effect of weather 0.26 2 3 High cost of labor 0.252 3 4 Shortage of site labor 0.246 4 5 High cost of machinery and its maintenance 0.246 5 6 Insufficient Numbers of equipment 0.229 6 7 Change orders. 0.223 7 8 Equipment availability and failure 0.223 8 9 Accident on site 0.221 9 10 Delay in progress payment by owner 0.21 10 11 Client requirements on quality 0.209 11 12 Labor absenteeism 0.204 12 13 Labor productivity 0.197 13 14 Owner interference 0.191 14 15 Late inspection 0.166 15 16 Financial difficulties of owner 0.165 16 17 Late design works 0.15 17 18 Unforeseen ground conditions 0.148 6 18 19 Shortage of materials 0.148 19 20 Wastage of the materials 0.147 20 21 Poor technical performance 0.146 21 22 Frequent design changes 0.144 22 23 Late in reviewing and approving design document by consultant 0.138 23 24 Fluctuation in prices of materials 0.137 24 25 Shortage of technical personnel(skilled labor) 0.135 25 26 Mistakes and errors in design 0.134 26 27 Late approval 0.129 27 28 Social and cultural impacts 0.12 28 29 Unavailable construction materials 0.109 29 30 Lack of raw materials sources 0.107 30 31 Government requirements 0.102 31 32 Late delivery of materials 0.1 32 33 Contractor's poor site management and supervision 0.094 33 34 Thefts of materials on site 0.093 34 35 Inadequate contractor experience 0.09 35 36 improper constructionmethod 0.087 36 37 Rework from poor material quality 0.085 37 38 late issuing of approval documents 0.08 38 39 Incompetent subcontractors 0.078 39 40 Incorrect material take off from drawings and design document 0.075 40 41 Delay in materials procurement 0.074 41 42 Slow in making decisions 0.072 42 43 Incorrect planning and scheduling by contractors 0.068 43 44 late submission of nominated materials 0.066 44 45 undefined scope of working 0.063 45 46 Postponement of project 0.06 46 47 changes in management ways 0.055 47 48 Cash flow and financial difficulties faced by contractors 0.053 48 49 poor communication between construction parties 0.052 49 50 Shortage of technical personnel(skilled labor) 0.135 50
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 08 | Aug -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 1560 Table 3 Ranking of group of the factors that affect time and cost s.n Group of the factors AVERAGE R 1 factor of consultant related 0.1422 5 2 factor of material related 0.1111 6 3 factor of labor related 0.2068 2 4 factor of contractor related 0.0709 7 5 factor of client related 0.1996 3 6 factor of equipment related 0.2495 1 7 Factor of external related 0.1662 4 Figure 2 Ranking of group that affect time and cost 3. CONCLUSIONS In the present time, the construction industries is biggest industries in India and it supporttodevelopingandattaining object of the society. The main objective of this study which have been find out at the beginning of study was identifying the critical factor of the cost and time affecting in the construction road projects. These objectives were performed by the questionnaire survey that was designed with regard to the knowledge of Indian construction industries and their respond had a significant influence on this study. Also the during the process of filling questionnaire andoral interviewshelpedin realizing the good answer to the main factor of the construction time and cost affecting. During questionnaire survey, they gave their opinion related to construction time and cost affecting and according to these valuable opinions of the experts, find out the top most factors of The construction time and cost affecting using the fuzzy methodology. The fuzzy methodology isbasedonthehuman judgment or opinion. The result of the fuzzy methodology. According to weight that came out from the calculation provided the rank and this rank indicated the power of the factor. Those factors are the most important in construction industries to avoiding the construction time and cost affecting that factor have the highest weight. In my study, find out the top forth group of the factors out of seven group of the factors that most important to avoid or minimize the construction time and cost affecting in theroadconstruction projects. The factor groups of equipment related have first rank, labor related have secondrank andthirdrank havethe client related .have forth rank external related. The fuzzy method is applied data provided by different expertsthetop forth rank is came out in each group. The construction time and cost affecting may avoided by considering these factors. These factors have played very important role for occurring the construction time cost affecting in the construction industries because the most of the experts gave our opinion regarding these factors and he accepted that construction time and cost affecting can be avoided by considering these factors. When consider the all fifty factor in a group and find out the rank according their normalizedweightthen topfourfactors are came out that have 1st, 2nd and 3rd 4th rank. The top most four factors are Late delivery of equipments, Effect of weather, High cost of labor, Shortageofsitelabor. Thesefour factors belongs to group of the factor of equipment related, group of the labor related and group of the client related, means during the construction the management of the money, equipment and material are most important. Now a days, all the construction work is depend on the money, machinery and material so availability of money, machines and material are most important in the construction industries. To avoiding the construction cost and time,these factors should be consider in mind during the construction work. The contractor should be proper management inboth labors and construction equipments to timely completionof the projects under the cost. REFERENCES 1. Endut, I.R., Shehu, Z., Akintoye, A., and Jaafar, A., 2009, “Cost and Time of Construction Projects in Malaysia,” in Fifth International Conference on Construction in the 21st Century (CITC-V) “Collaboration and Integrationin Engineering, Management and Technology” May 20-22, 2009, Istanbul, Turkey. 2. Liu, L. and Zhu, K. (2007). Improving cost estimates of construction projects using phased cost factors. Journal of Construction Engineering and Management, 133(1): 91–95. 3. Memon, A. H., I.A. Rahman, Abdullah, M.R., & Azis, A.A.A. (2011). Time Overrun in Construction Projectsfromthe Perspective of Project ManagementConsultant(PMC). Journal of Surveying, Construction and Property, 2(1), 54-66 4. Rajakumar A C 04 | Apr-2016. Analysis of Cost Overrun in Road Construction Activities – A Critical Review M.E. final year in Construction EngineeringandManagement Meenakshi Sundararajan Engineering College, Chennai 24 – India 5. Ibrahim Mahamid1+1, Amund Bruland2 2011 Cost Overrun Causes in Road Construction Projects: ‘’ConsultantsPerspective1PhD,NorwegianUniversityof Science and Technology (NTNU), Civil Eng. Dept., Trondheim, Norway. 2Professor, Norwegian University of Science and Technology (NTNU), Civil Eng. Dept., Trondheim, Norway.