International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 8
A study on the analysis and evaluation of delays in private construction
Projects in Kerala
Jidesh K1, Shrinath Rao K2
1 Student, M. Tech (Construction Management), Dept. of Civil Engineering,
Srinivas University Institute of Engineering & Technology, Mukka, Mangalore
2 Associate Professor, Dept. of Civil Engineering,
Srinivas University of Engineering & Technology, Mukka, Mangalore
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - Construction industry is one of the very
prominent industries in India due to its huge contribution to
the economic development of the country. Due to the
geographical, political, social and financial situations, many
of the construction projects in the country are prone to
delays. These delay factors can only be avoided by
identifying factors and their sources.
The main objectives of this research are to find out the main
causes of delays in the construction projects in the State of
Kerala. The research design was quantitative where data
was collected from owners, designers, and contractors. The
questionnaire was prepared using Google form, included a
list of reasons for delays factors, each of which respondents
were asked to rank on a 5-point scale. Acquired data were
analyzed using SPSS, the statistical program for social
scientists. Questionnaire survey was conducted in order to
find the top 15 delays occurred in the private projects in
Kerala. Finally, recommendations are made to void delays in
construction projects.
Key Words: construction management, construction
delays, construction industry, effects of delays, India,
Kerala
1. INTRODUCTION
Construction sector is one of the most important economic
sectors that play an important role in economic
development of a country. However, many projects had
significant delays that exceeded original time and cost
estimates. Construction delays are applied in terms of
time, cost, quality and safety as project success. If the
project duration (the actual duration of the work) is either
above the final end date specified in the contract
document or above the date the project owner and
contractors agreed to transfer the project and exceeds the
expected time, it is identified as a time delay. This is when
project work is out of date and requires higher
construction costs and additional labor time than what is
agreed to be planned on the contract document. For
project holders, the delay can be defined by the loss of
income in the absence of construction services and
rentable premises or dependence on side services. For
contractors or developers of projects, the delay is a big
financial loss due to the fact that the work takes a long
time to progress, higher price of construction material due
to inflation, increase in labor costs. Usually delays in the
construction industry many factors related to time, quality
and cost. A construction project is generally accepted as
successful when it is completed on time, within budget,
according to specifications and to the satisfaction of the
parties involved. Delay increases work slippage and late
project completion, client and contractor disagreement.
This can cause project progress disruptions and loss of
services, also increases time-bound costs and ultimately
can result in the termination of project construction work
and its contract.
1.1 Type of delays
The type of delay may also impact activities that require a
more detailed analysis to determine whether or not an
additional extension is warranted. There are four basic
ways to categorize delay types:
1.11 Critical or non-critical
1.12 Excusable or non-excusable
• Excusable delay with compensation
• Excusable delay without compensation
• Non-excusable delay
1.13 Compensable or non-compensable
1.14 Concurrent or non-concurrent
1.11 Critical or non-critical
Delays that affect the completion of the project or, in some
cases, the milestone date are considered critical delays,
and delays that do not affect the completion of the project
or the milestone date are non-critical delays
1.12 Excusable or non-excusable
An excusable delay is a delay that is caused by an
unforeseeable event beyond the control of the contractor
or subcontractor. For example, general strikes, fires and
acts of God. Inexcusable delays are events that are within
the supplier's control or that are foreseeable.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 9
1.13 Compensable or non-compensable
A compensable delay is a delay in which the contractor is
entitled to an extension of the deadline and additional
compensation. Regarding excusable and inexcusable
delays, only excusable delays can be compensated.
Irreparable delays mean that although an excusable delay
may have occurred, the contractor is not entitled to any
additional compensation arising from the excusable delay.
1.14 Concurrent or non-concurrent
concurrent delays refer to delay situations where two or
more delays occur at the same time or overlap to a certain
extent. For example, if the owner denies access to the
project site for two weeks and a severe storm prevents
itone of these two weeks will work on the project
simultaneously for one week.
1.2 Effects of delay
The 7 effects of delays are
1. Time over runs.
2. Cost overruns have significantly reduced the
contractors’ profits.
3. Loss of owner unproductivity due to long stays in the
construction phase.
4. Distrust the contractor and damage the company’s
reputation.
5. Do not rely on owners to delay payments leading to
contractor cash flow.
6. A project stakeholder is in dispute, in arbitration, or in
litigation.
7. Finish the project.
2. OBJECTIVES
The purpose of this study is to identify and identify
various factors that cause delays in construction projects,
their impact, and solutions to delays. This research aims to
identify the main causes of delays. To achieve the goal, it is
identified as:
1. Determine the root cause of a project.
2. Effect of delay.
3. Recommendations for minimizing and controlling
construction projects.
3. LITERATURE REVIEW
[1] N. Hamezah, M.A. Khoiry, I. Arshad, N.M. Tawil
"Theoretical Framework for Construction Delays" In this
article, the formwork is developed by three different
authors. Here are the results of his research: Financial
difficulties and economic problems, financial problems,
late supervision and slow decision-making, late
instructions, lack of materials on the market, poor
construction management, lack of materials on the
construction site, construction errors work defects, delays
in delivery of materials to the site, and slow decision-
making.
[2] Cairo. Mohamed, M. Marzouk, Tarek, I., El Rasas (2014)
also examined the causes of construction delays in Egypt
and, according to his analysis, the main groups responsible
for delays were: project ownership; consultants;
developers; materials; workers and, machines; projects,
external related delay factors.
[3] Mega Desai and Rajiv Bhatt; 59 delay factors have been
identified in residential projects. These factors are divided
into nine main areas related to delays: projects, promoters
(users), consultants, design, design materials, equipment,
workers, external factors based on their nature and mode
of existence, and project-related.
Based on the literature review, this study has identified
various causes of delays in construction projects
nowadays. The results of the literature search showed the
ten most important factors in particular are; very poor site
management; lack of skilled labor; unrealistic project
planning; workers absence; design changes/rework due to
design defects; accidents due to poor site safety; delays of
subcontractors; lack of materials on site; late delivery of
building materials and the effect of bad weather on
construction activity. With these factors, the following
methods are recommended to reduce project delays,
providing detailed and realistic schedule of site works to
coordinate construction activities and stages; timely
delivery of construction materials; improving the
workforce and workforce through ongoing training;
selection of appropriate experts to control certain
activities; using technology to track workforce
performance; proper planning of activities so that they
prevail even in adverse weather conditions; defining plans
and goals to limit design changes; employment of
subcontractors with adequate experience and increased
qualifications; improvement of construction site
conditions to reduce the number of construction accidents
and sufficient funding from clients.
4. METHODOLOGY
First, a literature review was conducted to find factors
causing construction project delays. This helped conduct a
survey of his professionals in the professional and other
participants in his construction industry in India to find
out the causes related to the situation in India. Achieving
these goals requires a research methodology. These are
the main stages for conducting this study.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 10
• Identifying the problem
• Specifying scope and research objectives
• Data collection
• Literature review
• Questionnaire
• Data analysis
• Results and Conclusion
4.1 Designing and collecting data through a
questionnaire survey
A questionnaire survey was conducted as a source of
primary data. There are two ways to collect data from
surveys. One is called cross elevation and other one is
called longitudinal elevation. Cross-sectional studies are
designed to collect data over a short period of time, while
longitudinal studies are designed to collect data over a
long period of time. A cross-sectional survey method was
chosen due to the time limitation of this study.
4.2 Data collection
The survey was sent to 40 people, 30 peoples are
responded within three weeks of time, so the response
rate is 75%, these 30 people’s response used for the
analysis. So completed with 75% validity rate.
4.3 Rating scale
Each statement in these questions should be rated on a
scale from strongly agree to strongly disagree, starting
with the rating system was given as follow; Strongly agree
– 5 Agree – 4 Satisfactory – 3 Disagree – 2 strongly
disagree – 1
Table -1: Questionnaire Survey
CATEGORY FACTORS CAUSING DELAYS
OWNER
1.Delay in progress payments
2.Delay to furnish and deliver the site
3. Change orders (plan/design) & extra
orders by
owner during construction
4.Late in revising and approving design
documents
5.Slowness in decision-making process
6.Owner’s lack of experience and
involvement
7.Delay in handing over the site for
mobilization
8.Freequent repeated works
CONTRAC
TOR
9.Difficulties in financing project
10. Rework due to errors during
construction
11. Ineffective & inadequate early Planning
and Scheduling of project
12. Inadequate contractor's work &
experience & also Poor risk management
and ignorance
13. Poor supervision & managerial skills
and lack of training personnel
14. Poor estimation of project time and
quantities of material required before
contracting
15.Lack of arranging the resources
(manpower, materials, machines)
16.Error in the works
DESIGNER
17. Insufficient data collection and survey
before design
18. Inadequate design team experience &
delay in producing design documents
19.Using poor / old engineering design
software
20.Financial problems
21. Misunderstanding of owner’s
requirements by design engineer
LABOR
23.Shortage of labors
24. Low skilled/productivity level or
unqualified labors
25. High labor wages insists to hire low
amount of labors
26.Labor strikes at site
27. Language of labors
28. Lack of motivation
MATERIAL
S
29. Shortage of construction materials in
market
30. Changes in material types during
construction
31. Damage of sorted materials while they
are needed urgently due to improper
shortage of materials
32. Delay in manufacturing special-building
materials
33. Price fluctuation / inflation in material
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 11
prices
34. Sudden increase in quantity needed
EQUIPMEN
T
35. Equipment breakdown and their idle
time and lack of tool in market
36. Shortage of heavy equipment when
needed
37. Low level of equipment-operator's skill
38. Low productivity and efficiency of
equipment
EXTERNAL
FACTOR
39. Delay in obtaining permits from
municipality
40. Weather, climate (hot or cold) & rain
effects on construction activities
41. Heavy traffic, over-crowded & other
restriction at site
42. Accident during construction
43. Slow site clearance
44. Security
45. Problem with neighbor’s
46. Improper project document
management
5. RESULT AND ANALYSIS
Table-2: Result and Analysis Chart
Question
No.
Number of
companies
responds 4
& 5, Agree
Number of
companies
responds 3,
Satisfactory
Number of
companies
responds 1 & 2,
Disagree
1 21 6 3
2 14 12 4
3 18 10 2
4 18 7 5
5 14 9 7
7 13 13 4
9 15 14 1
10 19 8 3
11 11 11 8
12 15 11 4
13 13 13 4
14 12 11 7
15 17 9 4
17 17 9 4
18 8 16 6
19 10 11 9
20 13 10 7
21 17 9 4
22 10 11 9
23 21 8 1
24 18 8 4
25 14 9 7
26 9 13 8
27 12 4 14
28 17 3 10
29 18 6 6
30 13 11 6
31 18 9 3
32 15 12 3
33 15 11 4
34 14 15 1
35 15 12 3
36 15 10 5
37 13 14 3
38 16 9 5
39 21 8 1
40 16 9 4
41 9 16 5
42 5 16 6
43 12 13 5
44 8 15 6
45 11 16 3
46 13 13 4
47 9 20 1
Graph 1 - Number of Responses, 4 & 5
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 12
Graph 2 - Number of Responses, 3
Graph 3 - Number of Responses, 1 & 2
Graph 4 - Overall Result Analysis
6. CONCLUSION AND RECOMMENDATION
6.1 Conclusion:
The purpose of this study was to identify the factors
responsible for delays in construction projects in the state
of Kerala and their effects and solution. The study
identified the factors causing delays in construction
projects across various stakeholders and categories
including owner, contractor, designer, labor, materials,
equipment and external factors. Based on the research
carried out in Kerala, 15 common causes of delays were
identified as below:
1) Delay in progress due to the payment issues by the
owner, 2) Delay in revising and approving design
document, 3) Change in orders (plan/design) & extra
orders by owner during construction, 4) Rework due to
errors during construction, 5) Lack of arranging the
resources (manpower, materials, machines), 6)
Insufficient data collection and survey before design, 7)
Misunderstanding of owner’s requirements by design
engineers, 8)Low skilled/productivity level or unqualified
labours, 9) Lack of motivation - Shortage of construction
materials in market, 10) Damage of sorted material
while they are needed urgently due to improper storage of
materials, 11) Damage of sorted material while they are
needed urgently due to improper storage of materials,12)
Price fluctuation/inflation in material prices, 13)Low
productivity and efficiency of equipment, 14) Weather,
climate (hot or cold) & rain effect on construction
activities, 15) Delay in obtaining permits from
municipality.
Regarding the impact of delays in the Kerala construction
industry, the five most common impacts are: Cost
overruns, Acceleration of losses, Time overruns, Negative
social impacts, litigation.
Regarding the impact of delays in the Kerala construction
industry, the five most common impacts are:
• Cost overruns
• Acceleration of losses
• Time overruns
• Negative social impacts
• Litigation
As mentioned earlier, different countries have different
causes of construction delays, different impacts and
different risks, and different measures suitable for each
country are taken to eliminate these risks. To eliminate
the construction delays the project participants are
recommended some points and that points are:
• Proper sharing of information
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 13
• Total quality management
• Proper arrangement of materials
• Proper management of labors
• Continuous trainings
• Early involvement of contractor and
subcontractor
• Quality cycles
6.2 Recommendation:
Construction delays are an unavoidable phenomenon that
occurs in almost every country due to the combination of
factors considered above. However, construction delays
are very common in most developing countries. Therefore,
considering all the above and in order to reduce or
mitigate these factors, the following measures may be
implemented in Kerala:
• Indigenous domestic building material production plant
at local level: This will reduce some chances of delay
occurring of shortage of material. There is some chance of
reducing the cost of materials because there will no tax on
imports and excised duties.
• The government, in collaboration with other stake
holders, should invest heavily in human capital
development by training construction workers in the
appropriate technical skills to make them efficient. By this
we can construct quality infrastructure.
Factors that owners can consider;
• Owners / Clients are required to make
progressive payments to contractors on time.
• Owners consider minimizing the change in orders
during construction for avoiding delays.
• Factors that contractors can consider:
• Effective planning and scheduling of project by
considering all the risk factors may occur.
• Contractors should find an effective material
management system.
• Contractor should have a better communication
and coordination skills, then only they can
manage the labors and their productivity.
Factors that designer can consider:
• Designer should be a quick problem solver, which
can solve the problems arriving during execution
and finish the project on time.
• Designer make sure that all the documents are
approved properly otherwise the work progress
will affect
• Designer also make an eye for proper
arrangement of documents.
• Designer have to monitor the work frequently or
make inspections frequent times.
Delay in approval of contractor submission by the
engineer and that is the very important sector that the
contractor complaints from, and its second most
important reason in the contractor’s point of view. In
general, the contractor cannot start any work or finish any
work without approval of the engineer. So, in general that
process delay of the project. In some cases, out of 30
responses, we noticed that in some contractors the
engineers got specific time to give the approval to the
contractor for example 24hrs and that is a cause a lot
delay in the project because the contractor can’t work
before getting the approval. And in some of the cases the
contractors have started the work without the approval of
the engineer and in that case the engineer has right to
make the contractor does that work again as per the
contract condition.
Shortage of materials was one of the frequent causes
according to the data which is collected out of 30
responses where contractor consultant and owner and it’s
the most frequent reason among the owner’s point of view
and owners have indicated that this is the reason why
there was a delay in the construction as material was not
delivered on the right time and because of that work was
not carried out as per the project which is planned and
schedule before the start of the work.
The main objective of this research work was to find out
the causes of delays that produced greatest effects and
extend to which these effects can be compensated in the
private construction projects in Kerala. The detailed data
was collected from around 30 companies which have
indicated the critical areas where the delay have taken
place. The important index of these each cause is
calculated as an average of the frequency indices of each
cause. 47 causes of delays were identified throughout this
project work. The identified causes are combined and data
collected are analysed and it has found that whatever the
critical reasons of delay which were identified in our
project can be solved in latest stage or in the future by
proper consultation with the material suppliers, sub-
contractors, contractors, client, client representative and
engineers and all this delay can be mitigated if not fully
controlled or fully nullified.
During all the 30 projects were started after proper
planning and scheduling. However, as a planning was
flexible and there are many unforeseen problems and
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 14
unforeseen parameters have taken into consideration but
however in spite of having there are some critical issues
because of which delay has taken place. Hence whenever
there is a delay can be compensated by increasing the
work hour for example if the scheduled is 8 hrs so this can
be compensated by working 2 hrs extra in a day or by
employing more resources so that the overall delay for
example if the delay is 100 days the overall delay can be
brought to less than 50 days because every day when you
work for 2hrs extra or when you work on holydays or
even when you work with the more resources more man
power more machine’s more materials then automatically
the works will progress and the overall delay at the end of
the project can be controlled.
REFERENCES
[1] N. Hamzah, M.A. Khoiry, I. Arshad, N.M. Tawil, and A.I.
Che Ani (2011) “Causes of Construction Delay”
“Theoretical Frame work”, Procedia Engineering.
[2] Mohamed M. Marzouk *, Tarek I. El-Rasas, “Analysing
delay causes in Egyptian construction projects”,
Journal of Advanced Research (2014) 5,49–55.
[3] Megha Desai, Rajiv Bhatt P.G. Student, “Critical Causes
of Delay in Residential Construction Projects”,
International Journal of Emerging Technology and
Advanced Engineering, (ISSN 2250-2459, ISO
9001:2008 Certified Journal, Volume 3, Issue 3, March
2013).
[4] Ajibade Ayodeji Aibinu and Agboola Odeyinka (2006)
“Construction Delays and their causative factors in
Nigeria”, Journal of Construction Engineering and
Management, Vol.132, No.8, Page No.667-677
[5] Assaf SA, Al-Khalil M, Al-Hazmi M. “Causes of delays in
large building construction projects.” ASCE J Manage
Eng. 1995; 11(2):45–50.
[6] M.E. Abd EI-Razek, H.A. Bassioni, And A.M. Mobarak
(2008) “Causes of Delay in Building Construction
Projects in Egypt” Journal of Construction Engineering
and Management, Vol.134, No.11, Page No. 831-841.
[7] Pablo Gonzalez, Vicente Gonzalez, Keith Molenaar
Ph.D. M ASCE and Francisco Orozco Ph.D. (2013)
“Analysis of causes of delay and times performance in
construction projects”, Journal of Construction
Engineering and Management.
[8] Thillai A. Rajan, Govind Gopinath and Monalisa Behera
(2013) “PPPs and Project Overruns: Evidence from
Road Projects in India” Journal of Construction
Engineering and Management.
[9] Cecilia Gravina da Racha and Sergio Luiz Kemmer
(2013) “Method of Implement Delayed product
Differentiation in Construction of High-Rise
Apartment Building Projects” Journal of Construction
Engineering and Management.
[10] Hemant Doloi, Anil Sawhney, K.C. Iyer, Sameer Rentala
“Analysing factors affecting delays in Indian
construction projects”, International Journal of Project
Management 30 (2012) 479–4.
BIOGRAPHIES
Jidesh.K(jitheshkunnoth6@gmail.
com) is pursuing MTech
Construction Management at
Srinivas University Institute of
Engineering & Technology,
Mukka, Mangaluru. After
Bachelor Degree in Civil
Engineering, Jidesh has worked
as Civil Engineer at A Line Studio,
an Architectural Company, Kerala
for one year.
Shrinath Rao K is working as
Associate Professor in the Dept of
Civil Engg at Srinivas University
Institute of Engineering &
Technology, Mukka, Mangaluru.
He has 7 years of work
experience at Abroad and 14
years at India including Teaching,
Review & Re-Design of Syllabus,
Quality Assurance in Higher
Educational Institutions and
Construction Industry.

Weitere ähnliche Inhalte

Ähnlich wie A study on the analysis and evaluation of delays in private construction Projects in Kerala

IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET Journal
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET Journal
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTIRJET Journal
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsDr. Amarjeet Singh
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of timeJoseph Sangpang
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewIRJET Journal
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectseSAT Journals
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectseSAT Journals
 
Analysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims inAnalysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims ineSAT Publishing House
 
Management For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of DelayManagement For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of DelayIRJET Journal
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Sankalp Swarnkar
 
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...
IRJET - Investigating the Effectiveness of Construction Practices in Dela...IRJET Journal
 
Impact of delayness on construction projects
Impact of delayness on construction projectsImpact of delayness on construction projects
Impact of delayness on construction projectsIRJET Journal
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...IJERA Editor
 
A Study on the analysis of payment problems in private building sector in Ker...
A Study on the analysis of payment problems in private building sector in Ker...A Study on the analysis of payment problems in private building sector in Ker...
A Study on the analysis of payment problems in private building sector in Ker...IRJET Journal
 

Ähnlich wie A study on the analysis and evaluation of delays in private construction Projects in Kerala (20)

IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
B012140812
B012140812B012140812
B012140812
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projects
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projects
 
Analysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims inAnalysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims in
 
Management For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of DelayManagement For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of Delay
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
 
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
 
Impact of delayness on construction projects
Impact of delayness on construction projectsImpact of delayness on construction projects
Impact of delayness on construction projects
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...
 
A Study on the analysis of payment problems in private building sector in Ker...
A Study on the analysis of payment problems in private building sector in Ker...A Study on the analysis of payment problems in private building sector in Ker...
A Study on the analysis of payment problems in private building sector in Ker...
 

Mehr von IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

Mehr von IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Kürzlich hochgeladen

(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 

Kürzlich hochgeladen (20)

(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 

A study on the analysis and evaluation of delays in private construction Projects in Kerala

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 8 A study on the analysis and evaluation of delays in private construction Projects in Kerala Jidesh K1, Shrinath Rao K2 1 Student, M. Tech (Construction Management), Dept. of Civil Engineering, Srinivas University Institute of Engineering & Technology, Mukka, Mangalore 2 Associate Professor, Dept. of Civil Engineering, Srinivas University of Engineering & Technology, Mukka, Mangalore ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - Construction industry is one of the very prominent industries in India due to its huge contribution to the economic development of the country. Due to the geographical, political, social and financial situations, many of the construction projects in the country are prone to delays. These delay factors can only be avoided by identifying factors and their sources. The main objectives of this research are to find out the main causes of delays in the construction projects in the State of Kerala. The research design was quantitative where data was collected from owners, designers, and contractors. The questionnaire was prepared using Google form, included a list of reasons for delays factors, each of which respondents were asked to rank on a 5-point scale. Acquired data were analyzed using SPSS, the statistical program for social scientists. Questionnaire survey was conducted in order to find the top 15 delays occurred in the private projects in Kerala. Finally, recommendations are made to void delays in construction projects. Key Words: construction management, construction delays, construction industry, effects of delays, India, Kerala 1. INTRODUCTION Construction sector is one of the most important economic sectors that play an important role in economic development of a country. However, many projects had significant delays that exceeded original time and cost estimates. Construction delays are applied in terms of time, cost, quality and safety as project success. If the project duration (the actual duration of the work) is either above the final end date specified in the contract document or above the date the project owner and contractors agreed to transfer the project and exceeds the expected time, it is identified as a time delay. This is when project work is out of date and requires higher construction costs and additional labor time than what is agreed to be planned on the contract document. For project holders, the delay can be defined by the loss of income in the absence of construction services and rentable premises or dependence on side services. For contractors or developers of projects, the delay is a big financial loss due to the fact that the work takes a long time to progress, higher price of construction material due to inflation, increase in labor costs. Usually delays in the construction industry many factors related to time, quality and cost. A construction project is generally accepted as successful when it is completed on time, within budget, according to specifications and to the satisfaction of the parties involved. Delay increases work slippage and late project completion, client and contractor disagreement. This can cause project progress disruptions and loss of services, also increases time-bound costs and ultimately can result in the termination of project construction work and its contract. 1.1 Type of delays The type of delay may also impact activities that require a more detailed analysis to determine whether or not an additional extension is warranted. There are four basic ways to categorize delay types: 1.11 Critical or non-critical 1.12 Excusable or non-excusable • Excusable delay with compensation • Excusable delay without compensation • Non-excusable delay 1.13 Compensable or non-compensable 1.14 Concurrent or non-concurrent 1.11 Critical or non-critical Delays that affect the completion of the project or, in some cases, the milestone date are considered critical delays, and delays that do not affect the completion of the project or the milestone date are non-critical delays 1.12 Excusable or non-excusable An excusable delay is a delay that is caused by an unforeseeable event beyond the control of the contractor or subcontractor. For example, general strikes, fires and acts of God. Inexcusable delays are events that are within the supplier's control or that are foreseeable.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 9 1.13 Compensable or non-compensable A compensable delay is a delay in which the contractor is entitled to an extension of the deadline and additional compensation. Regarding excusable and inexcusable delays, only excusable delays can be compensated. Irreparable delays mean that although an excusable delay may have occurred, the contractor is not entitled to any additional compensation arising from the excusable delay. 1.14 Concurrent or non-concurrent concurrent delays refer to delay situations where two or more delays occur at the same time or overlap to a certain extent. For example, if the owner denies access to the project site for two weeks and a severe storm prevents itone of these two weeks will work on the project simultaneously for one week. 1.2 Effects of delay The 7 effects of delays are 1. Time over runs. 2. Cost overruns have significantly reduced the contractors’ profits. 3. Loss of owner unproductivity due to long stays in the construction phase. 4. Distrust the contractor and damage the company’s reputation. 5. Do not rely on owners to delay payments leading to contractor cash flow. 6. A project stakeholder is in dispute, in arbitration, or in litigation. 7. Finish the project. 2. OBJECTIVES The purpose of this study is to identify and identify various factors that cause delays in construction projects, their impact, and solutions to delays. This research aims to identify the main causes of delays. To achieve the goal, it is identified as: 1. Determine the root cause of a project. 2. Effect of delay. 3. Recommendations for minimizing and controlling construction projects. 3. LITERATURE REVIEW [1] N. Hamezah, M.A. Khoiry, I. Arshad, N.M. Tawil "Theoretical Framework for Construction Delays" In this article, the formwork is developed by three different authors. Here are the results of his research: Financial difficulties and economic problems, financial problems, late supervision and slow decision-making, late instructions, lack of materials on the market, poor construction management, lack of materials on the construction site, construction errors work defects, delays in delivery of materials to the site, and slow decision- making. [2] Cairo. Mohamed, M. Marzouk, Tarek, I., El Rasas (2014) also examined the causes of construction delays in Egypt and, according to his analysis, the main groups responsible for delays were: project ownership; consultants; developers; materials; workers and, machines; projects, external related delay factors. [3] Mega Desai and Rajiv Bhatt; 59 delay factors have been identified in residential projects. These factors are divided into nine main areas related to delays: projects, promoters (users), consultants, design, design materials, equipment, workers, external factors based on their nature and mode of existence, and project-related. Based on the literature review, this study has identified various causes of delays in construction projects nowadays. The results of the literature search showed the ten most important factors in particular are; very poor site management; lack of skilled labor; unrealistic project planning; workers absence; design changes/rework due to design defects; accidents due to poor site safety; delays of subcontractors; lack of materials on site; late delivery of building materials and the effect of bad weather on construction activity. With these factors, the following methods are recommended to reduce project delays, providing detailed and realistic schedule of site works to coordinate construction activities and stages; timely delivery of construction materials; improving the workforce and workforce through ongoing training; selection of appropriate experts to control certain activities; using technology to track workforce performance; proper planning of activities so that they prevail even in adverse weather conditions; defining plans and goals to limit design changes; employment of subcontractors with adequate experience and increased qualifications; improvement of construction site conditions to reduce the number of construction accidents and sufficient funding from clients. 4. METHODOLOGY First, a literature review was conducted to find factors causing construction project delays. This helped conduct a survey of his professionals in the professional and other participants in his construction industry in India to find out the causes related to the situation in India. Achieving these goals requires a research methodology. These are the main stages for conducting this study.
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 10 • Identifying the problem • Specifying scope and research objectives • Data collection • Literature review • Questionnaire • Data analysis • Results and Conclusion 4.1 Designing and collecting data through a questionnaire survey A questionnaire survey was conducted as a source of primary data. There are two ways to collect data from surveys. One is called cross elevation and other one is called longitudinal elevation. Cross-sectional studies are designed to collect data over a short period of time, while longitudinal studies are designed to collect data over a long period of time. A cross-sectional survey method was chosen due to the time limitation of this study. 4.2 Data collection The survey was sent to 40 people, 30 peoples are responded within three weeks of time, so the response rate is 75%, these 30 people’s response used for the analysis. So completed with 75% validity rate. 4.3 Rating scale Each statement in these questions should be rated on a scale from strongly agree to strongly disagree, starting with the rating system was given as follow; Strongly agree – 5 Agree – 4 Satisfactory – 3 Disagree – 2 strongly disagree – 1 Table -1: Questionnaire Survey CATEGORY FACTORS CAUSING DELAYS OWNER 1.Delay in progress payments 2.Delay to furnish and deliver the site 3. Change orders (plan/design) & extra orders by owner during construction 4.Late in revising and approving design documents 5.Slowness in decision-making process 6.Owner’s lack of experience and involvement 7.Delay in handing over the site for mobilization 8.Freequent repeated works CONTRAC TOR 9.Difficulties in financing project 10. Rework due to errors during construction 11. Ineffective & inadequate early Planning and Scheduling of project 12. Inadequate contractor's work & experience & also Poor risk management and ignorance 13. Poor supervision & managerial skills and lack of training personnel 14. Poor estimation of project time and quantities of material required before contracting 15.Lack of arranging the resources (manpower, materials, machines) 16.Error in the works DESIGNER 17. Insufficient data collection and survey before design 18. Inadequate design team experience & delay in producing design documents 19.Using poor / old engineering design software 20.Financial problems 21. Misunderstanding of owner’s requirements by design engineer LABOR 23.Shortage of labors 24. Low skilled/productivity level or unqualified labors 25. High labor wages insists to hire low amount of labors 26.Labor strikes at site 27. Language of labors 28. Lack of motivation MATERIAL S 29. Shortage of construction materials in market 30. Changes in material types during construction 31. Damage of sorted materials while they are needed urgently due to improper shortage of materials 32. Delay in manufacturing special-building materials 33. Price fluctuation / inflation in material
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 11 prices 34. Sudden increase in quantity needed EQUIPMEN T 35. Equipment breakdown and their idle time and lack of tool in market 36. Shortage of heavy equipment when needed 37. Low level of equipment-operator's skill 38. Low productivity and efficiency of equipment EXTERNAL FACTOR 39. Delay in obtaining permits from municipality 40. Weather, climate (hot or cold) & rain effects on construction activities 41. Heavy traffic, over-crowded & other restriction at site 42. Accident during construction 43. Slow site clearance 44. Security 45. Problem with neighbor’s 46. Improper project document management 5. RESULT AND ANALYSIS Table-2: Result and Analysis Chart Question No. Number of companies responds 4 & 5, Agree Number of companies responds 3, Satisfactory Number of companies responds 1 & 2, Disagree 1 21 6 3 2 14 12 4 3 18 10 2 4 18 7 5 5 14 9 7 7 13 13 4 9 15 14 1 10 19 8 3 11 11 11 8 12 15 11 4 13 13 13 4 14 12 11 7 15 17 9 4 17 17 9 4 18 8 16 6 19 10 11 9 20 13 10 7 21 17 9 4 22 10 11 9 23 21 8 1 24 18 8 4 25 14 9 7 26 9 13 8 27 12 4 14 28 17 3 10 29 18 6 6 30 13 11 6 31 18 9 3 32 15 12 3 33 15 11 4 34 14 15 1 35 15 12 3 36 15 10 5 37 13 14 3 38 16 9 5 39 21 8 1 40 16 9 4 41 9 16 5 42 5 16 6 43 12 13 5 44 8 15 6 45 11 16 3 46 13 13 4 47 9 20 1 Graph 1 - Number of Responses, 4 & 5
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 12 Graph 2 - Number of Responses, 3 Graph 3 - Number of Responses, 1 & 2 Graph 4 - Overall Result Analysis 6. CONCLUSION AND RECOMMENDATION 6.1 Conclusion: The purpose of this study was to identify the factors responsible for delays in construction projects in the state of Kerala and their effects and solution. The study identified the factors causing delays in construction projects across various stakeholders and categories including owner, contractor, designer, labor, materials, equipment and external factors. Based on the research carried out in Kerala, 15 common causes of delays were identified as below: 1) Delay in progress due to the payment issues by the owner, 2) Delay in revising and approving design document, 3) Change in orders (plan/design) & extra orders by owner during construction, 4) Rework due to errors during construction, 5) Lack of arranging the resources (manpower, materials, machines), 6) Insufficient data collection and survey before design, 7) Misunderstanding of owner’s requirements by design engineers, 8)Low skilled/productivity level or unqualified labours, 9) Lack of motivation - Shortage of construction materials in market, 10) Damage of sorted material while they are needed urgently due to improper storage of materials, 11) Damage of sorted material while they are needed urgently due to improper storage of materials,12) Price fluctuation/inflation in material prices, 13)Low productivity and efficiency of equipment, 14) Weather, climate (hot or cold) & rain effect on construction activities, 15) Delay in obtaining permits from municipality. Regarding the impact of delays in the Kerala construction industry, the five most common impacts are: Cost overruns, Acceleration of losses, Time overruns, Negative social impacts, litigation. Regarding the impact of delays in the Kerala construction industry, the five most common impacts are: • Cost overruns • Acceleration of losses • Time overruns • Negative social impacts • Litigation As mentioned earlier, different countries have different causes of construction delays, different impacts and different risks, and different measures suitable for each country are taken to eliminate these risks. To eliminate the construction delays the project participants are recommended some points and that points are: • Proper sharing of information
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 13 • Total quality management • Proper arrangement of materials • Proper management of labors • Continuous trainings • Early involvement of contractor and subcontractor • Quality cycles 6.2 Recommendation: Construction delays are an unavoidable phenomenon that occurs in almost every country due to the combination of factors considered above. However, construction delays are very common in most developing countries. Therefore, considering all the above and in order to reduce or mitigate these factors, the following measures may be implemented in Kerala: • Indigenous domestic building material production plant at local level: This will reduce some chances of delay occurring of shortage of material. There is some chance of reducing the cost of materials because there will no tax on imports and excised duties. • The government, in collaboration with other stake holders, should invest heavily in human capital development by training construction workers in the appropriate technical skills to make them efficient. By this we can construct quality infrastructure. Factors that owners can consider; • Owners / Clients are required to make progressive payments to contractors on time. • Owners consider minimizing the change in orders during construction for avoiding delays. • Factors that contractors can consider: • Effective planning and scheduling of project by considering all the risk factors may occur. • Contractors should find an effective material management system. • Contractor should have a better communication and coordination skills, then only they can manage the labors and their productivity. Factors that designer can consider: • Designer should be a quick problem solver, which can solve the problems arriving during execution and finish the project on time. • Designer make sure that all the documents are approved properly otherwise the work progress will affect • Designer also make an eye for proper arrangement of documents. • Designer have to monitor the work frequently or make inspections frequent times. Delay in approval of contractor submission by the engineer and that is the very important sector that the contractor complaints from, and its second most important reason in the contractor’s point of view. In general, the contractor cannot start any work or finish any work without approval of the engineer. So, in general that process delay of the project. In some cases, out of 30 responses, we noticed that in some contractors the engineers got specific time to give the approval to the contractor for example 24hrs and that is a cause a lot delay in the project because the contractor can’t work before getting the approval. And in some of the cases the contractors have started the work without the approval of the engineer and in that case the engineer has right to make the contractor does that work again as per the contract condition. Shortage of materials was one of the frequent causes according to the data which is collected out of 30 responses where contractor consultant and owner and it’s the most frequent reason among the owner’s point of view and owners have indicated that this is the reason why there was a delay in the construction as material was not delivered on the right time and because of that work was not carried out as per the project which is planned and schedule before the start of the work. The main objective of this research work was to find out the causes of delays that produced greatest effects and extend to which these effects can be compensated in the private construction projects in Kerala. The detailed data was collected from around 30 companies which have indicated the critical areas where the delay have taken place. The important index of these each cause is calculated as an average of the frequency indices of each cause. 47 causes of delays were identified throughout this project work. The identified causes are combined and data collected are analysed and it has found that whatever the critical reasons of delay which were identified in our project can be solved in latest stage or in the future by proper consultation with the material suppliers, sub- contractors, contractors, client, client representative and engineers and all this delay can be mitigated if not fully controlled or fully nullified. During all the 30 projects were started after proper planning and scheduling. However, as a planning was flexible and there are many unforeseen problems and
  • 7. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 12 | Dec 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 14 unforeseen parameters have taken into consideration but however in spite of having there are some critical issues because of which delay has taken place. Hence whenever there is a delay can be compensated by increasing the work hour for example if the scheduled is 8 hrs so this can be compensated by working 2 hrs extra in a day or by employing more resources so that the overall delay for example if the delay is 100 days the overall delay can be brought to less than 50 days because every day when you work for 2hrs extra or when you work on holydays or even when you work with the more resources more man power more machine’s more materials then automatically the works will progress and the overall delay at the end of the project can be controlled. REFERENCES [1] N. Hamzah, M.A. Khoiry, I. Arshad, N.M. Tawil, and A.I. Che Ani (2011) “Causes of Construction Delay” “Theoretical Frame work”, Procedia Engineering. [2] Mohamed M. Marzouk *, Tarek I. El-Rasas, “Analysing delay causes in Egyptian construction projects”, Journal of Advanced Research (2014) 5,49–55. [3] Megha Desai, Rajiv Bhatt P.G. Student, “Critical Causes of Delay in Residential Construction Projects”, International Journal of Emerging Technology and Advanced Engineering, (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 3, Issue 3, March 2013). [4] Ajibade Ayodeji Aibinu and Agboola Odeyinka (2006) “Construction Delays and their causative factors in Nigeria”, Journal of Construction Engineering and Management, Vol.132, No.8, Page No.667-677 [5] Assaf SA, Al-Khalil M, Al-Hazmi M. “Causes of delays in large building construction projects.” ASCE J Manage Eng. 1995; 11(2):45–50. [6] M.E. Abd EI-Razek, H.A. Bassioni, And A.M. Mobarak (2008) “Causes of Delay in Building Construction Projects in Egypt” Journal of Construction Engineering and Management, Vol.134, No.11, Page No. 831-841. [7] Pablo Gonzalez, Vicente Gonzalez, Keith Molenaar Ph.D. M ASCE and Francisco Orozco Ph.D. (2013) “Analysis of causes of delay and times performance in construction projects”, Journal of Construction Engineering and Management. [8] Thillai A. Rajan, Govind Gopinath and Monalisa Behera (2013) “PPPs and Project Overruns: Evidence from Road Projects in India” Journal of Construction Engineering and Management. [9] Cecilia Gravina da Racha and Sergio Luiz Kemmer (2013) “Method of Implement Delayed product Differentiation in Construction of High-Rise Apartment Building Projects” Journal of Construction Engineering and Management. [10] Hemant Doloi, Anil Sawhney, K.C. Iyer, Sameer Rentala “Analysing factors affecting delays in Indian construction projects”, International Journal of Project Management 30 (2012) 479–4. BIOGRAPHIES Jidesh.K(jitheshkunnoth6@gmail. com) is pursuing MTech Construction Management at Srinivas University Institute of Engineering & Technology, Mukka, Mangaluru. After Bachelor Degree in Civil Engineering, Jidesh has worked as Civil Engineer at A Line Studio, an Architectural Company, Kerala for one year. Shrinath Rao K is working as Associate Professor in the Dept of Civil Engg at Srinivas University Institute of Engineering & Technology, Mukka, Mangaluru. He has 7 years of work experience at Abroad and 14 years at India including Teaching, Review & Re-Design of Syllabus, Quality Assurance in Higher Educational Institutions and Construction Industry.