SlideShare ist ein Scribd-Unternehmen logo
1 von 27
Project control based on functional size
            Which method to use?




            Harold van Heeringen
             UKSMA conference
              (London, November 8, 2012)
Harold van Heeringen
• Short intro:
 − Sogeti Nederland BV senior consultant software metrics
 − ISBSG president
 − NESMA board member
 − NESMA working group chair COSMIC
 − NESMA working group chair Benchmarking
 − COSMIC IAC member


          Harold van Heeringen
          Sizing, Estimating & Control
          harold.van.heeringen@sogeti.nl
            @haroldveendam
            @Sogeti_SEC

                                               2
Agenda
• Parametric project control
• Product size ready
• Differences IFPUG vs. COSMIC relevant for
  Project control
• Experiment: Project control with two methods
• Conclusions




                                       3
Project Management
• Project Estimation
 − Parametric estimates based on (COSMIC) FP
 − Effort hours, duration, staff, defects
 − Galorath SEER-SEM / QSM SLIM Estimate / other tools
  Productivity (PDR = hours/FP) that is expected

• Project Planning
 − Transform the estimate into the plan

• Project Control
 − Track the status based on FP                                            FTE Staff
                                                                                                                              Staff & Effort Variance


                                                                                                                              8
                                                                                                                                                                                              Cum Effort Life Cycle
                                                                                                                                                                                                                                                                 3.500

                                                                                                                                                                                                                                                                 3.000
                                                                                                                              6
                                                                                                                                                                                                                                                                 2.500




 − Do we meet our expected PDR?
                                                                                                                                                                                                                                                                 2.000




                                                                                                                                                                                                                                                                         MHR
                                                                                                                                  ppl
                                                                                                                              4
                                                                                                                                                                                                                                                                 1.500

                                                                                                                                                                                                                                                                 1.000
                                                                                                                              2

                                                                                                                                                                                                                                                                 500

                                                                                                                              0                                                                                                                                  0
                                                       2       4       6       8       10       12        14         16                                                  2            4            6            8       10            12       14       16
                                               29-05   12-06   26-06   10-07   24-07    07-08    21-08     04-09      18-09                                    29-05     12-06        26-06        10-07        24-07    07-08         21-08    04-09    18-09




 − Forecasting based on actuals
                                                '10                                                                                                             '10




                                                                                                                                  Date 14-8-2010 (11,57 weeks)
                                                                                                                                                                              Plan                 Actual               Diff
                                                                                                                                    Avg Staff Life Cycle (ppl)                       5,2                   5,3                  0,1
                                                                                                                                    Cum Effort Life Cy cle (MHR)                 1.787,8               1.812,0                 24,2
                                                                                                                                    PI                                              20,8                  20,6                 -0,2
                                                                                                                                    MBI                                              5,3                   5,3                  0,0




                                                                                           Current Plan            Actuals              Green Control Bound    Yellow Control Bound           Project: Project XYZ




                                                                               4
Project Control
• How do Project managers manage their software
  realization project?
 − Administration of effort hours (weekly)
 − Compare effort hours against planned hours (weekly)


• Project status
 − If more hours than planned have been spent, we must be
   ahead of schedule, right?
 − If less hours than planned have been spent, the project is
   easier than expected, right?


• To measure hours is easy, but what about
  'product delivered'?
                                                  5
Inaccurate project status
• Most used:
 − How many hours do you need to finish ‘activity X’?
 − Expert estimate/judgment is used to assess the status of
   the ‘work done’
 − PM collects the status of all people and aggregates this info
   into a status report

• Problem:
 − experts are usually optimistic, underestimating the work
   that still needs to be done
   ◦ Documenting, bug fixing, 2nd round of testing, etcetera

• Result:
 − Inaccurate status until very late in the project !
                                                        6
Parametric project control
• Control the project, using functional size for the
  'product ready'
• Project status:
 − Effort hours spent vs. effort hours planned
 − Actual functional size ready vs. planned functional size
   ready
 − Forecasting based on the actuals
• Galorath SEER-SEM
 − Parametric Project Monitoring & Control tool (PPMC)

• QSM SLIM Control
 − Part of the QSM SLIM toolsuite


                                                   7
How the tools work

1. Put in the baseline plan
 −   Start and end date
 −   Milestone dates
 −   Effort hours planned
 −   Product size to be delivered in (C) FP

1. Record actuals (every week / 2 weeks)
 −   Effort hours
 −   Dates
 −   Defects
 −   Product size ready in (C) FP

1. Forecast project results
2. Calculate corrective actions               8
Project control
• Putting in the baseline plan is easy (project plan
  of the PL)
• Collecting actual hours, milestone dates and
  defects is also fairly easy
• Measuring the ‘product size ready’ is more
  complicated
 − When is an EI ready? When is an EIF ready?
 − How can we objectively assess a function point being ready?

• Function point ready – after the programmer
  reports it ready for systems testing
• Measuring the correct ‘product size ready’ is
  crucial for Project Control
                                                 9
Product size ready
• Multiple methods to measure ‘product size
  ready’
• Technical: SLOCs
 − Easy to measure actuals, but hard to predict/estimate total
 − Baseline plan slocs is inaccurate, but actuals are accurate

• Functional: (COSMIC) Function Points
 − Harder to measure, based on quality of documentation
 − Baseline plan and actuals can both be accurately measured


• Which functional size measurement method is
  most accurate?
                                                   10
NESMA/IFPUG vs. COSMIC
 Characteristic            NESMA/IFPUG FPA            COSMIC
 Applicable on domain      Business software           Business / Real-time /
                                                     Infrastructure software
 Data model required?      Required                   Not required (but very
                                                     handy)
  Measurement of           Not possible               Possible
separate components
 Size limit per function   Yes                        Size is not limited
 Benchmarking data         ISBSG (aug 12), n= 4316     ISBSG (aug 12),
                                                     n=446
  Measurement of           No                          No, but local extension
processing functionality                             is possible
 Early sizing              Based on data model        Based on process
                                                     model
                                                                 11
Functional complexity
• IFPUG/NESMA does not really measure
  differences in functional complexity
 − EI: 3,4 or 6 FP (never less than 3, never more than 6)
 − EO: 4,5 or 7 FP (never less than 4, never more than 7)
• But: in real life functions can differ from very
  low complexity
 − e.g. drop down list ‘Client’ (EO: 1 FTR, 2 DET, 4 FP)
 …to very complex
 − e.g. to make a new insurance contract perhaps clicking
   through 5 screens: (EI: 8 FTR, 121 DET, 6 FP)
• Difference in FP does not reflect difference in
  effort needed.
                                                  12
COSMIC and Project control
• Theoretically, COSMIC should be the better
  method to use for Project Control


• The data model does not explicitly get points.
 − In project control, it’s difficult to assess status regarding the
   realization of the data model (When is an EIF ready?).


• The functional processes are not restricted in
  size
 − E.g. drop down list Client: 3 CFP (EO: 4 FP)
 − Make a new insurance contract: 38 CFP (EI: 6 FP)
• Difference in size reflects the difference in effort
  needed more realistically                          13
Some examples

User Function   IFPUG   IFPUG   COSMIC            COSMIC
                 type    size     type              size
                                Functional         8 CFP
Add customer     EI      3 FP    Process
   Change                       Functional         7 CFP
  customer       EI      4 FP    Process
    Delete                      Functional         4 CFP
  customer       EI      3 FP    Process
Show revenue                    Functional        12 CFP
per customer                     Process
 and region      EO      7 FP
  Customer       ILF     7 FP       -                0
                                             14
Case: Government agency
• Project name: XYZ
• Programming language: Java
• Development method: waterfall
• Functional size:
 − 371 FP (IFPUG)
 − 494 CFP (COSMIC)
• Effort hours planned: 2.505 hours
• Planned start date: 26-05-2010
• Planned end date: 12-09-2010
  CONST. &    IFPUG   COSMIC     Hours
    TEST       FP       FP     planned   Start date    End date
Project XYZ     371     494      2505    26-5-2010    12-09-2010
                                                 15
The IFPUG plan
                                                                                                                       SEI Core Metrics

                                                           Schedule                                                                                                                                            Size
                                                                                                                                                                                                                                                                      500

                                                                                                                                                                                                                                                                      400

                                                                                                                                                                                                                                                                      300




                                                                                                                       Phases




                                                                                                                                                                                                                                                                            FP
Construct & Test
                                                                                                                                                                                                                                                                      200

                                                                                                                                                                                                                                                                      100

                                                                                                                                                                                                                                                                      0
                            2          4           6           8           10           12           14       16                                                              2         4            6         8           10           12          14        16
                   29-05    12-06      26-06       10-07       24-07        07-08        21-08        04-09    18-09                                             29-05        12-06     26-06        10-07     24-07       07-08        21-08       04-09     18-09
                    '10                                                                                                                                           '10



                                                                                                              Cum Effort Life Cycle
                                                                                                                                                                                                                                                3.500
                                                                                                                                                                                                                                                3.000
                                                                                                                                                                                                                                                2.500
                                                                                                                                                                                                                                                2.000




                                                                                                                                                                                                                                                            MHR
                                                                                                                                                                                                                                                1.500
                                                                                                                                                                                                                                                1.000
                                                                                                                                                                                                                                                500
                                                                                                                                                                                                                                                0
                                   1           2           3           4            5            6            7           8             9           10           11           12           13           14           15           16
                           29-05       05-06       12-06       19-06       26-06         03-07        10-07       17-07         24-07       31-07        07-08        14-08        21-08        28-08        04-09        11-09         18-09
                            '10


                                                     Current Plan                   Actuals                        Current Forecast          Green Control Bound              Yellow Control Bound               Project: Project XYZ



                                                                                                                                                                                                                                        16
The COSMIC plan
                                                                                                                        SEI Core Metrics

                                                            Schedule                                                                                                                                            Size
                                                                                                                                                                                                                                                                         700
                                                                                                                                                                                                                                                                         600
                                                                                                                                                                                                                                                                         500
                                                                                                                                                                                                                                                                         400




                                                                                                                        Phases




                                                                                                                                                                                                                                                                               FP
Construct & Test                                                                                                                                                                                                                                                         300
                                                                                                                                                                                                                                                                         200
                                                                                                                                                                                                                                                                         100
                                                                                                                                                                                                                                                                         0
                            2           4           6           8           10           12           14       16                                                          2             4            6         8           10           12           14        16
                   29-05    12-06       26-06       10-07       24-07        07-08        21-08        04-09    18-09                                             29-05    12-06         26-06        10-07     24-07       07-08         21-08       04-09      18-09
                    '10                                                                                                                                            '10



                                                                                                               Cum Effort Life Cycle
                                                                                                                                                                                                                                                  3.500
                                                                                                                                                                                                                                                  3.000
                                                                                                                                                                                                                                                  2.500
                                                                                                                                                                                                                                                  2.000




                                                                                                                                                                                                                                                              MHR
                                                                                                                                                                                                                                                  1.500
                                                                                                                                                                                                                                                  1.000
                                                                                                                                                                                                                                                  500
                                                                                                                                                                                                                                                  0
                                    1           2           3           4            5            6            7           8             9           10           11           12           13           14           15           16
                           29-05        05-06       12-06       19-06       26-06         03-07        10-07       17-07         24-07       31-07        07-08        14-08        21-08        28-08        04-09        11-09         18-09
                            '10


                                                      Current Plan                   Actuals                        Current Forecast          Green Control Bound              Yellow Control Bound               Project: Project XYZ



                                                                                                                                                                                                                                        17
After 4 weeks: forecast IFPUG
• First Actuals
Metric          Plan                                                                                            Actual                                                          Difference
Hours spent       238                                                                                               294                                                             +56
IFPUG FP ready     99                                                                                                80                                                              -19
COSMIC FP ready   132                                                                                               130                                                               -2
                                                                                                                              SEI Core Metrics

                                                          Schedule                                                                                                                                                                  Size
                                                                                                                                                                                                                                                                                   500

                                                                                                                                                                                                                                                                                   400

                                                                                                                                                                                                                                                                                   300
                                                                                                                               Phases




                                                                                                                                                                                                                                                                                         FP
Construct &...
                                                                                                                                                                                                                                                                                   200

                                                                                                                                                                                                                                                                                   100

                                                                                                                                                                                                                                                                                   0
                         2        4           6           8     10    12    14                            16          18                                                              2     4     6     8     10    12    14    16    18
                 29-05   12-06    26-06       10-07       24-07 07-08 21-08 04-09                         18-09       02-10                                                     29-05 12-06 26-06 10-07 24-07 07-08 21-08 04-09 18-09 02-10
                  '10                                                                                                                                                            '10



                                                                                                                  Cum Effort Life Cycle
                                                                                                                                                                                                                                                                     3.500
                                                                                                                                                                                                                                                                     3.000
                                                                                                                                                                                                                                                                     2.500
                                                                                                                                                                                                                                                                     2.000




                                                                                                                                                                                                                                                                             MHR
                                                                                                                                                                                                                                                                     1.500
                                                                                                                                                                                                                                                                     1.000
                                                                                                                                                                                                                                                                     500
                                                                                                                                                                                                                                                                     0
                                  1           2           3           4           5           6           7           8           9             10           11           12           13           14           15           16           17           18
                          29-05       05-06       12-06       19-06       26-06       03-07       10-07       17-07       24-07         31-07        07-08        14-08        21-08        28-08        04-09        11-09        18-09        25-09        02-10
                           '10
                                                                                                                                                                                                                                                                                         18

                                                      Current Plan                      Actuals                           Current Forecast             Green Control Bound                  Yellow Control Bound                      Project: Project XYZ
After 4 weeks: forecast COSMIC
• First Actuals
Metric          Plan                                                                                       Actual                                                  Difference
Hours spent       238                                                                                          294                                                     +56
IFPUG FP ready     99                                                                                           80                                                      -19
COSMIC FP ready   132                                                                                          130                                                       -2
                                                                                                                       SEI Core Metrics

                                                            Schedule                                                                                                                                           Size
                                                                                                                                                                                                                                                                       700
                                                                                                                                                                                                                                                                       600
                                                                                                                                                                                                                                                                       500
                                                                                                                                                                                                                                                                       400
                                                                                                                       Phases




                                                                                                                                                                                                                                                                             FP
Construct & Test                                                                                                                                                                                                                                                       300
                                                                                                                                                                                                                                                                       200
                                                                                                                                                                                                                                                                       100
                                                                                                                                                                                                                                                                       0
                            2           4           6           8           10           12       14          16                                                          2             4            6         8           10           12           14        16
                   29-05    12-06       26-06       10-07       24-07        07-08        21-08    04-09       18-09                                             29-05    12-06         26-06        10-07     24-07        07-08        21-08       04-09     18-09
                    '10                                                                                                                                           '10



                                                                                                              Cum Effort Life Cycle
                                                                                                                                                                                                                                                 3.500
                                                                                                                                                                                                                                                 3.000
                                                                                                                                                                                                                                                 2.500
                                                                                                                                                                                                                                                 2.000




                                                                                                                                                                                                                                                             MHR
                                                                                                                                                                                                                                                 1.500
                                                                                                                                                                                                                                                 1.000
                                                                                                                                                                                                                                                 500
                                                                                                                                                                                                                                                 0
                                    1           2           3           4            5            6           7           8             9           10           11           12           13           14           15           16
                           29-05        05-06       12-06       19-06       26-06         03-07       10-07       17-07         24-07       31-07        07-08        14-08        21-08        28-08        04-09        11-09         18-09
                            '10
                                                                                                                                                                                                                                                                             19

                                                      Current Plan                   Actuals                       Current Forecast          Green Control Bound              Yellow Control Bound               Project: Project XYZ
Forecast after 4 weeks
Metric               Plan          Forecast     Overrun/underrun
Based on IFPUG FP
Hours                    2.505        2.933   +428 hours (+17%)
Schedule              12-09-2010   26-09-2010      2 weeks

Based on COSMIC FP
Hours                    2.505        2.601      +96 hours (+4%)
Schedule              12-09-2010   14-09-2010         2 days


• Project manager thinks everything is OK
• Team members agree



                                                        20
Actuals after week 8: Forecast IFPUG

  Metric          Plan                                                                                                                                    Actual                                                                        Difference
  Hours spent       941                                                                                                                                       982                                                                           +41
  FP ready          279                                                                                                                                       252                                                                            -27
  COSMIC FP ready   371                                                                                                                                       366                                                                             -5
                                                                                                                             SEI Core Metrics

                                                           Schedule                                                                                                                                                      Size
                                                                                                                                                                                                                                                                        500

                                                                                                                                                                                                                                                                        400

                                                                                                                                                                                                                                                                        300
                                                                                                                             Phases




                                                                                                                                                                                                                                                                              FP
Construct & T...
                                                                                                                                                                                                                                                                        200

                                                                                                                                                                                                                                                                        100

                                                                                                                                                                                                                                                                        0
                           2           4           6           8           10      12            14          16                                                                    2           4            6           8     10    12    14    16
                   29-05   12-06       26-06       10-07       24-07       07-08    21-08        04-09        18-09                                                    29-05       12-06       26-06        10-07       24-07 07-08 21-08 04-09 18-09
                    '10                                                                                                                                                 '10



                                                                                                                 Cum Effort Life Cycle
                                                                                                                                                                                                                                                          3.500
                                                                                                                                                                                                                                                          3.000
                                                                                                                                                                                                                                                          2.500
                                                                                                                                                                                                                                                          2.000




                                                                                                                                                                                                                                                                  MHR
                                                                                                                                                                                                                                                          1.500
                                                                                                                                                                                                                                                          1.000
                                                                                                                                                                                                                                                          500
                                                                                                                                                                                                                                                          0
                                   1           2           3           4           5             6           7           8            9           10           11           12           13           14           15           16           17
                           29-05       05-06       12-06       19-06       26-06       03-07         10-07       17-07       24-07        31-07        07-08        14-08        21-08        28-08        04-09        11-09        18-09        25-09
                            '10
                                                                                                                                                                                                                                                                                   21

                                                      Current Plan                     Actuals                           Current Forecast         Green Control Bound              Yellow Control Bound                    Project: Project XYZ
Forecast after 8 weeks
• PM still thinks everything is on track, but is
  getting a little nervous
• Team members still agree
 Metric               Plan          Forecast     Overrun/underrun
 Based on IFPUG FP
 Hours                    2.505        2.991   +486 hours (+19%)
 Schedule              12-09-2010   24-09-2010      12 days

 Based on COSMIC FP
 Hours                    2.505        2.690     +185 hours (+7%)
 Schedule              12-09-2010   15-09-2010        3 days




                                                         22
After 12 weeks
Metric                 Plan        Actual         Difference
Hours spent             1.788         1.812           +24
FP ready                 357           348             -9
COSMIC FP ready          471           470             -1
Metric               Plan            Forecast     Overrun/under run
Based on IFPUG FP
Hours                    2.505          3.009        +504 hours (+20%)
Schedule              12-09-2010     25-09-2010           13 days

Based on COSMIC FP
Hours                    2.505          2.730        +225 hours (+9 %)
Schedule              12-09-2010     16-09-2010           4 days



                                                               23
Final results
• Small overrun in time and effort


 Metric           Plan        Actual       Difference
 Hours spent         2.505       2.586        +81
 Project end date 12 -09-2010 16-09-2010    +4 days
 FP ready             371         371           0
 COSMIC FP ready      494         494           0




                                             24
The forecasts analyzed
• IFPUG forecasts show considerable overruns
  until late in the project
• COSMIC forecasts more conservative
• COSMIC forecasts more in line with the feeling of
  the team and the PM

Forecast              IFPUG FP                      COSMIC FP
           Hours overrun Schedule overrun Hours overrun Schedule overrun
4 weeks        +428          + 2 weeks         +96           +2 days
8 weeks        +486          +12 days         +185           +3 days
12 weeks       +504          +13 days         +225          + 4 days
Final           +81           +4 days          +81           +4 days


                                                         25
Conclusions
• In theory, COSMIC should be the better method
  to use in parametric project control
 − No size limit per function: more accurate product size ready
 − No explicit points for the data model: Easier to measure
   ‘project size ready’
• This experiment confirms this theory
 − COSMIC forecasts closer to reality than IFPUG forecasts
• More experiments are needed to support this
  conclusion




                                                  26
Sogeti Sizing, Estimating & Control
            Thanks for your attention !
             Harold van Heeringen
             Sizing, Estimating & Control
             harold.van.heeringen@sogeti.nl
               @haroldveendam
               @Sogeti_SEC

Sogeti Sizing, Estimating & Control
NESMA – board member
NESMA – chair working group COSMIC
NESMA – chair working group Benchmarking
NESMA – working group Sizing Packages
NESMA – working group Estimation maturity
COSMIC – International Advisory Counsil
COSMIC – Benchmarking Committee
ISBSG – President


                                              27

Weitere ähnliche Inhalte

Was ist angesagt?

Poster for setting reaction & compressive strength of GPC with and without MMT
Poster for setting reaction & compressive strength of GPC with and without MMTPoster for setting reaction & compressive strength of GPC with and without MMT
Poster for setting reaction & compressive strength of GPC with and without MMTMazlinda Sarihasan
 
Gregg Weiss, New York Life Presentation - BDI 4/14/11 Financial Services Soci...
Gregg Weiss, New York Life Presentation - BDI 4/14/11 Financial Services Soci...Gregg Weiss, New York Life Presentation - BDI 4/14/11 Financial Services Soci...
Gregg Weiss, New York Life Presentation - BDI 4/14/11 Financial Services Soci...Business Development Institute
 
Thong so ky thuat dan lanh fxdq +kich thuoc lo mo tran
Thong so ky thuat dan lanh fxdq +kich thuoc lo mo tranThong so ky thuat dan lanh fxdq +kich thuoc lo mo tran
Thong so ky thuat dan lanh fxdq +kich thuoc lo mo trantiger1202
 
Thong so ky thuat fxmq 200 250 + lo mo tran
Thong so ky thuat fxmq 200 250 + lo mo tranThong so ky thuat fxmq 200 250 + lo mo tran
Thong so ky thuat fxmq 200 250 + lo mo trantiger1202
 
Presentation Bernard Cools Space
Presentation Bernard Cools Space Presentation Bernard Cools Space
Presentation Bernard Cools Space Social Karma sa
 
Verification Metrics
Verification MetricsVerification Metrics
Verification MetricsDVClub
 
Business connectivityservices model
Business connectivityservices modelBusiness connectivityservices model
Business connectivityservices modelArd van Someren
 
Fareham College Aosec Presentation 7 Mar 2012
Fareham College   Aosec Presentation 7 Mar 2012Fareham College   Aosec Presentation 7 Mar 2012
Fareham College Aosec Presentation 7 Mar 2012Charles Whinney
 
Überblick Kommunikationsbranche
Überblick KommunikationsbrancheÜberblick Kommunikationsbranche
Überblick KommunikationsbrancheBrandDoctor
 
Practical business use for Linkedin: Women’s Forum 2012
Practical business use for Linkedin: Women’s Forum 2012Practical business use for Linkedin: Women’s Forum 2012
Practical business use for Linkedin: Women’s Forum 2012the bureau, digital agency
 
Ucd presentation template
Ucd presentation templateUcd presentation template
Ucd presentation templateLorrie Evans
 
Phoenix, AZ – Real Estate Market Data – February 2013 - Coldwell Banker Resid...
Phoenix, AZ – Real Estate Market Data – February 2013 - Coldwell Banker Resid...Phoenix, AZ – Real Estate Market Data – February 2013 - Coldwell Banker Resid...
Phoenix, AZ – Real Estate Market Data – February 2013 - Coldwell Banker Resid...Marc Krebs
 
2011It's Not Just Student Support
2011It's Not Just Student Support2011It's Not Just Student Support
2011It's Not Just Student SupportWCET
 
Clustering of unhealthy behaviours over time: implications for policy and pra...
Clustering of unhealthy behaviours over time: implications for policy and pra...Clustering of unhealthy behaviours over time: implications for policy and pra...
Clustering of unhealthy behaviours over time: implications for policy and pra...The King's Fund
 
H sgp keynot
H sgp keynotH sgp keynot
H sgp keynot114970
 

Was ist angesagt? (20)

Poster for setting reaction & compressive strength of GPC with and without MMT
Poster for setting reaction & compressive strength of GPC with and without MMTPoster for setting reaction & compressive strength of GPC with and without MMT
Poster for setting reaction & compressive strength of GPC with and without MMT
 
Gregg Weiss, New York Life Presentation - BDI 4/14/11 Financial Services Soci...
Gregg Weiss, New York Life Presentation - BDI 4/14/11 Financial Services Soci...Gregg Weiss, New York Life Presentation - BDI 4/14/11 Financial Services Soci...
Gregg Weiss, New York Life Presentation - BDI 4/14/11 Financial Services Soci...
 
Thong so ky thuat dan lanh fxdq +kich thuoc lo mo tran
Thong so ky thuat dan lanh fxdq +kich thuoc lo mo tranThong so ky thuat dan lanh fxdq +kich thuoc lo mo tran
Thong so ky thuat dan lanh fxdq +kich thuoc lo mo tran
 
Peter Hofman
Peter HofmanPeter Hofman
Peter Hofman
 
Thong so ky thuat fxmq 200 250 + lo mo tran
Thong so ky thuat fxmq 200 250 + lo mo tranThong so ky thuat fxmq 200 250 + lo mo tran
Thong so ky thuat fxmq 200 250 + lo mo tran
 
Presentation Bernard Cools Space
Presentation Bernard Cools Space Presentation Bernard Cools Space
Presentation Bernard Cools Space
 
Verification Metrics
Verification MetricsVerification Metrics
Verification Metrics
 
Business connectivityservices model
Business connectivityservices modelBusiness connectivityservices model
Business connectivityservices model
 
Map metro a3
Map metro a3Map metro a3
Map metro a3
 
Mickposter Nuim
Mickposter NuimMickposter Nuim
Mickposter Nuim
 
Fareham College Aosec Presentation 7 Mar 2012
Fareham College   Aosec Presentation 7 Mar 2012Fareham College   Aosec Presentation 7 Mar 2012
Fareham College Aosec Presentation 7 Mar 2012
 
Überblick Kommunikationsbranche
Überblick KommunikationsbrancheÜberblick Kommunikationsbranche
Überblick Kommunikationsbranche
 
Practical business use for Linkedin: Women’s Forum 2012
Practical business use for Linkedin: Women’s Forum 2012Practical business use for Linkedin: Women’s Forum 2012
Practical business use for Linkedin: Women’s Forum 2012
 
Ucd presentation template
Ucd presentation templateUcd presentation template
Ucd presentation template
 
Bstk
BstkBstk
Bstk
 
Phoenix, AZ – Real Estate Market Data – February 2013 - Coldwell Banker Resid...
Phoenix, AZ – Real Estate Market Data – February 2013 - Coldwell Banker Resid...Phoenix, AZ – Real Estate Market Data – February 2013 - Coldwell Banker Resid...
Phoenix, AZ – Real Estate Market Data – February 2013 - Coldwell Banker Resid...
 
Snow White
Snow WhiteSnow White
Snow White
 
2011It's Not Just Student Support
2011It's Not Just Student Support2011It's Not Just Student Support
2011It's Not Just Student Support
 
Clustering of unhealthy behaviours over time: implications for policy and pra...
Clustering of unhealthy behaviours over time: implications for policy and pra...Clustering of unhealthy behaviours over time: implications for policy and pra...
Clustering of unhealthy behaviours over time: implications for policy and pra...
 
H sgp keynot
H sgp keynotH sgp keynot
H sgp keynot
 

Andere mochten auch

Issip bod 053113 presentation_final draft
Issip bod 053113 presentation_final draftIssip bod 053113 presentation_final draft
Issip bod 053113 presentation_final draftISSIP
 
Systemic Method Control and Organizational Improvement - Luciano Lujan ANTONI...
Systemic Method Control and Organizational Improvement - Luciano Lujan ANTONI...Systemic Method Control and Organizational Improvement - Luciano Lujan ANTONI...
Systemic Method Control and Organizational Improvement - Luciano Lujan ANTONI...Luciano L. Antonietti
 
Finance and audit committee minutes 19 bod_meeting_june 2016_english
Finance and audit committee minutes 19 bod_meeting_june 2016_englishFinance and audit committee minutes 19 bod_meeting_june 2016_english
Finance and audit committee minutes 19 bod_meeting_june 2016_englishValerie S. TABIOU - AKPLOGAN
 
Sw creative financing 2 25
Sw creative financing 2 25Sw creative financing 2 25
Sw creative financing 2 25Shelterwood LLC
 
Financial Management Lesson Notes
Financial Management Lesson NotesFinancial Management Lesson Notes
Financial Management Lesson NotesEkrem Tufan
 
OBJECTIVES OF FINANCIAL MANAGEMENT
OBJECTIVES OF FINANCIAL MANAGEMENTOBJECTIVES OF FINANCIAL MANAGEMENT
OBJECTIVES OF FINANCIAL MANAGEMENTAnurag Chakraborty
 
Financial management ppt
Financial management pptFinancial management ppt
Financial management pptRanal Nair
 
ppt on financial management
 ppt on financial management ppt on financial management
ppt on financial managementAanchal
 
Financial management complete note
Financial management complete noteFinancial management complete note
Financial management complete notekabul university
 
Financial Management
Financial ManagementFinancial Management
Financial Managementshart sood
 

Andere mochten auch (12)

Issip bod 053113 presentation_final draft
Issip bod 053113 presentation_final draftIssip bod 053113 presentation_final draft
Issip bod 053113 presentation_final draft
 
Systemic Method Control and Organizational Improvement - Luciano Lujan ANTONI...
Systemic Method Control and Organizational Improvement - Luciano Lujan ANTONI...Systemic Method Control and Organizational Improvement - Luciano Lujan ANTONI...
Systemic Method Control and Organizational Improvement - Luciano Lujan ANTONI...
 
Finance and audit committee minutes 19 bod_meeting_june 2016_english
Finance and audit committee minutes 19 bod_meeting_june 2016_englishFinance and audit committee minutes 19 bod_meeting_june 2016_english
Finance and audit committee minutes 19 bod_meeting_june 2016_english
 
10 06-03 veb annual spring bod meeting
10 06-03 veb annual spring bod meeting10 06-03 veb annual spring bod meeting
10 06-03 veb annual spring bod meeting
 
Sw creative financing 2 25
Sw creative financing 2 25Sw creative financing 2 25
Sw creative financing 2 25
 
Financial Management Lesson Notes
Financial Management Lesson NotesFinancial Management Lesson Notes
Financial Management Lesson Notes
 
OBJECTIVES OF FINANCIAL MANAGEMENT
OBJECTIVES OF FINANCIAL MANAGEMENTOBJECTIVES OF FINANCIAL MANAGEMENT
OBJECTIVES OF FINANCIAL MANAGEMENT
 
Financial management ppt
Financial management pptFinancial management ppt
Financial management ppt
 
Financial management
Financial managementFinancial management
Financial management
 
ppt on financial management
 ppt on financial management ppt on financial management
ppt on financial management
 
Financial management complete note
Financial management complete noteFinancial management complete note
Financial management complete note
 
Financial Management
Financial ManagementFinancial Management
Financial Management
 

Ähnlich wie Project Control using functional size - which method to use?

PRIMARY STRUCTURAL STEELWORKS MEMBERS - WATER TREATMENT PLANT
PRIMARY STRUCTURAL STEELWORKS MEMBERS - WATER TREATMENT PLANTPRIMARY STRUCTURAL STEELWORKS MEMBERS - WATER TREATMENT PLANT
PRIMARY STRUCTURAL STEELWORKS MEMBERS - WATER TREATMENT PLANTJames Halun
 
Dharmesh Shah - Insider tips on inbound marketing - IMS Boston 2012
Dharmesh Shah - Insider tips on inbound marketing - IMS Boston 2012Dharmesh Shah - Insider tips on inbound marketing - IMS Boston 2012
Dharmesh Shah - Insider tips on inbound marketing - IMS Boston 2012thepulsenetwork
 
Gord Masiuk - Case Studies in Continuous Quality Improvement - WCQI Anaheim 2012
Gord Masiuk - Case Studies in Continuous Quality Improvement - WCQI Anaheim 2012Gord Masiuk - Case Studies in Continuous Quality Improvement - WCQI Anaheim 2012
Gord Masiuk - Case Studies in Continuous Quality Improvement - WCQI Anaheim 2012gmasiuk
 
Werenfried F.M. Spit - (Velocitat limitada per a la qualitat de l’aire, la si...
Werenfried F.M. Spit - (Velocitat limitada per a la qualitat de l’aire, la si...Werenfried F.M. Spit - (Velocitat limitada per a la qualitat de l’aire, la si...
Werenfried F.M. Spit - (Velocitat limitada per a la qualitat de l’aire, la si...Medi Ambient. Generalitat de Catalunya
 
Ethanol america s conference
Ethanol america s conferenceEthanol america s conference
Ethanol america s conferencePetrobras
 
MI School Demographics And Facilities
MI School Demographics And FacilitiesMI School Demographics And Facilities
MI School Demographics And FacilitiesChuck Eckenstahler
 
AVLM 2009 Toledo by Ilse Depré
AVLM 2009 Toledo by Ilse DepréAVLM 2009 Toledo by Ilse Depré
AVLM 2009 Toledo by Ilse Depréavlm2009avnet
 
L&t%20 investor%20presentation%20 %20feb%202013
L&t%20 investor%20presentation%20 %20feb%202013L&t%20 investor%20presentation%20 %20feb%202013
L&t%20 investor%20presentation%20 %20feb%202013Vikram Pushparaj
 
Entrepreneurship in action
Entrepreneurship in actionEntrepreneurship in action
Entrepreneurship in actionLoreVlerick
 

Ähnlich wie Project Control using functional size - which method to use? (20)

Business review templates
Business review templatesBusiness review templates
Business review templates
 
Antony allen
Antony allenAntony allen
Antony allen
 
PRIMARY STRUCTURAL STEELWORKS MEMBERS - WATER TREATMENT PLANT
PRIMARY STRUCTURAL STEELWORKS MEMBERS - WATER TREATMENT PLANTPRIMARY STRUCTURAL STEELWORKS MEMBERS - WATER TREATMENT PLANT
PRIMARY STRUCTURAL STEELWORKS MEMBERS - WATER TREATMENT PLANT
 
Dharmesh Shah - Insider tips on inbound marketing - IMS Boston 2012
Dharmesh Shah - Insider tips on inbound marketing - IMS Boston 2012Dharmesh Shah - Insider tips on inbound marketing - IMS Boston 2012
Dharmesh Shah - Insider tips on inbound marketing - IMS Boston 2012
 
NIPS 2011 Poster
NIPS 2011 PosterNIPS 2011 Poster
NIPS 2011 Poster
 
SunGard Cloud mini Brochure
SunGard Cloud mini BrochureSunGard Cloud mini Brochure
SunGard Cloud mini Brochure
 
Gord Masiuk - Case Studies in Continuous Quality Improvement - WCQI Anaheim 2012
Gord Masiuk - Case Studies in Continuous Quality Improvement - WCQI Anaheim 2012Gord Masiuk - Case Studies in Continuous Quality Improvement - WCQI Anaheim 2012
Gord Masiuk - Case Studies in Continuous Quality Improvement - WCQI Anaheim 2012
 
Werenfried F.M. Spit - (Velocitat limitada per a la qualitat de l’aire, la si...
Werenfried F.M. Spit - (Velocitat limitada per a la qualitat de l’aire, la si...Werenfried F.M. Spit - (Velocitat limitada per a la qualitat de l’aire, la si...
Werenfried F.M. Spit - (Velocitat limitada per a la qualitat de l’aire, la si...
 
Ethanol america s conference
Ethanol america s conferenceEthanol america s conference
Ethanol america s conference
 
Une080425
Une080425Une080425
Une080425
 
MI School Demographics And Facilities
MI School Demographics And FacilitiesMI School Demographics And Facilities
MI School Demographics And Facilities
 
Restaurant Project Part 1
Restaurant Project Part 1Restaurant Project Part 1
Restaurant Project Part 1
 
AVLM 2009 Toledo by Ilse Depré
AVLM 2009 Toledo by Ilse DepréAVLM 2009 Toledo by Ilse Depré
AVLM 2009 Toledo by Ilse Depré
 
クラウドコンピューティングと OSS
クラウドコンピューティングと OSSクラウドコンピューティングと OSS
クラウドコンピューティングと OSS
 
L&t%20 investor%20presentation%20 %20feb%202013
L&t%20 investor%20presentation%20 %20feb%202013L&t%20 investor%20presentation%20 %20feb%202013
L&t%20 investor%20presentation%20 %20feb%202013
 
Tc Demo Tces
Tc Demo TcesTc Demo Tces
Tc Demo Tces
 
Impact of Agricultural Activities on Groundwater Quality and its Suitability ...
Impact of Agricultural Activities on Groundwater Quality and its Suitability ...Impact of Agricultural Activities on Groundwater Quality and its Suitability ...
Impact of Agricultural Activities on Groundwater Quality and its Suitability ...
 
Blackberry Blossom
Blackberry BlossomBlackberry Blossom
Blackberry Blossom
 
Entrepreneurship in action
Entrepreneurship in actionEntrepreneurship in action
Entrepreneurship in action
 
Portfolio
PortfolioPortfolio
Portfolio
 

Mehr von Harold van Heeringen

Improve Estimation maturity using Functional Size Measurement and Historical ...
Improve Estimation maturity using Functional Size Measurement and Historical ...Improve Estimation maturity using Functional Size Measurement and Historical ...
Improve Estimation maturity using Functional Size Measurement and Historical ...Harold van Heeringen
 
Productivity measurement of agile teams (IWSM 2015)
Productivity measurement of agile teams (IWSM 2015)Productivity measurement of agile teams (IWSM 2015)
Productivity measurement of agile teams (IWSM 2015)Harold van Heeringen
 
Productivity measurement of agile teams (IWSM 2015)
Productivity measurement of agile teams (IWSM 2015)Productivity measurement of agile teams (IWSM 2015)
Productivity measurement of agile teams (IWSM 2015)Harold van Heeringen
 
Methodisch begroten van projecten hanzehogeschool groningen december2014
Methodisch begroten van projecten   hanzehogeschool groningen december2014Methodisch begroten van projecten   hanzehogeschool groningen december2014
Methodisch begroten van projecten hanzehogeschool groningen december2014Harold van Heeringen
 
The importance of benchmarking software projects - Van Heeringen and Ogilvie
The importance of benchmarking software projects - Van Heeringen and OgilvieThe importance of benchmarking software projects - Van Heeringen and Ogilvie
The importance of benchmarking software projects - Van Heeringen and OgilvieHarold van Heeringen
 
Van Heeringen and van Gorp - Measure the functional size of a mobile app usi...
Van Heeringen and van Gorp  - Measure the functional size of a mobile app usi...Van Heeringen and van Gorp  - Measure the functional size of a mobile app usi...
Van Heeringen and van Gorp - Measure the functional size of a mobile app usi...Harold van Heeringen
 
Measuring the functional size of mobile apps with COSMIC FP
Measuring the functional size of mobile apps with COSMIC FPMeasuring the functional size of mobile apps with COSMIC FP
Measuring the functional size of mobile apps with COSMIC FPHarold van Heeringen
 
Avoid software project horror stories - check the reality value of the estima...
Avoid software project horror stories - check the reality value of the estima...Avoid software project horror stories - check the reality value of the estima...
Avoid software project horror stories - check the reality value of the estima...Harold van Heeringen
 
ISMA 9 - van Heeringen - Using IFPUG and ISBSG to improve organization success
ISMA 9 - van Heeringen - Using IFPUG and ISBSG to improve organization successISMA 9 - van Heeringen - Using IFPUG and ISBSG to improve organization success
ISMA 9 - van Heeringen - Using IFPUG and ISBSG to improve organization successHarold van Heeringen
 
Gastcollege Hanzehogeschool Groningen 10 januari 2014
Gastcollege Hanzehogeschool Groningen 10 januari 2014Gastcollege Hanzehogeschool Groningen 10 januari 2014
Gastcollege Hanzehogeschool Groningen 10 januari 2014Harold van Heeringen
 
The value of benchmarking software projects
The value of benchmarking software projectsThe value of benchmarking software projects
The value of benchmarking software projectsHarold van Heeringen
 
Using the ISBSG data to improve your organization success - van Heeringen (Me...
Using the ISBSG data to improve your organization success - van Heeringen (Me...Using the ISBSG data to improve your organization success - van Heeringen (Me...
Using the ISBSG data to improve your organization success - van Heeringen (Me...Harold van Heeringen
 
Asl bi sl metrics themasessie 2013 devops sogeti
Asl bi sl metrics themasessie 2013   devops sogetiAsl bi sl metrics themasessie 2013   devops sogeti
Asl bi sl metrics themasessie 2013 devops sogetiHarold van Heeringen
 
Begroten van software projecten - Hogeschool Rotterdam gastcollege 05-11-2013
Begroten van software projecten - Hogeschool Rotterdam gastcollege 05-11-2013Begroten van software projecten - Hogeschool Rotterdam gastcollege 05-11-2013
Begroten van software projecten - Hogeschool Rotterdam gastcollege 05-11-2013Harold van Heeringen
 
Van heeringen estimate faster, cheaper, better
Van heeringen   estimate faster, cheaper, betterVan heeringen   estimate faster, cheaper, better
Van heeringen estimate faster, cheaper, betterHarold van Heeringen
 
van Heeringen - estimate faster,cheaper and better!
van Heeringen - estimate faster,cheaper and better!van Heeringen - estimate faster,cheaper and better!
van Heeringen - estimate faster,cheaper and better!Harold van Heeringen
 
The value of benchmarking IT projects - H.S. van Heeringen
The value of benchmarking IT projects - H.S. van HeeringenThe value of benchmarking IT projects - H.S. van Heeringen
The value of benchmarking IT projects - H.S. van HeeringenHarold van Heeringen
 
Begroten van agile projecten, technical meeting Sogeti 2013-09
Begroten van agile projecten, technical meeting Sogeti 2013-09Begroten van agile projecten, technical meeting Sogeti 2013-09
Begroten van agile projecten, technical meeting Sogeti 2013-09Harold van Heeringen
 
Sogeti seminar Supplier Performance Measurement
Sogeti seminar Supplier Performance MeasurementSogeti seminar Supplier Performance Measurement
Sogeti seminar Supplier Performance MeasurementHarold van Heeringen
 
Software Estimating and Performance Measurement
Software Estimating and Performance MeasurementSoftware Estimating and Performance Measurement
Software Estimating and Performance MeasurementHarold van Heeringen
 

Mehr von Harold van Heeringen (20)

Improve Estimation maturity using Functional Size Measurement and Historical ...
Improve Estimation maturity using Functional Size Measurement and Historical ...Improve Estimation maturity using Functional Size Measurement and Historical ...
Improve Estimation maturity using Functional Size Measurement and Historical ...
 
Productivity measurement of agile teams (IWSM 2015)
Productivity measurement of agile teams (IWSM 2015)Productivity measurement of agile teams (IWSM 2015)
Productivity measurement of agile teams (IWSM 2015)
 
Productivity measurement of agile teams (IWSM 2015)
Productivity measurement of agile teams (IWSM 2015)Productivity measurement of agile teams (IWSM 2015)
Productivity measurement of agile teams (IWSM 2015)
 
Methodisch begroten van projecten hanzehogeschool groningen december2014
Methodisch begroten van projecten   hanzehogeschool groningen december2014Methodisch begroten van projecten   hanzehogeschool groningen december2014
Methodisch begroten van projecten hanzehogeschool groningen december2014
 
The importance of benchmarking software projects - Van Heeringen and Ogilvie
The importance of benchmarking software projects - Van Heeringen and OgilvieThe importance of benchmarking software projects - Van Heeringen and Ogilvie
The importance of benchmarking software projects - Van Heeringen and Ogilvie
 
Van Heeringen and van Gorp - Measure the functional size of a mobile app usi...
Van Heeringen and van Gorp  - Measure the functional size of a mobile app usi...Van Heeringen and van Gorp  - Measure the functional size of a mobile app usi...
Van Heeringen and van Gorp - Measure the functional size of a mobile app usi...
 
Measuring the functional size of mobile apps with COSMIC FP
Measuring the functional size of mobile apps with COSMIC FPMeasuring the functional size of mobile apps with COSMIC FP
Measuring the functional size of mobile apps with COSMIC FP
 
Avoid software project horror stories - check the reality value of the estima...
Avoid software project horror stories - check the reality value of the estima...Avoid software project horror stories - check the reality value of the estima...
Avoid software project horror stories - check the reality value of the estima...
 
ISMA 9 - van Heeringen - Using IFPUG and ISBSG to improve organization success
ISMA 9 - van Heeringen - Using IFPUG and ISBSG to improve organization successISMA 9 - van Heeringen - Using IFPUG and ISBSG to improve organization success
ISMA 9 - van Heeringen - Using IFPUG and ISBSG to improve organization success
 
Gastcollege Hanzehogeschool Groningen 10 januari 2014
Gastcollege Hanzehogeschool Groningen 10 januari 2014Gastcollege Hanzehogeschool Groningen 10 januari 2014
Gastcollege Hanzehogeschool Groningen 10 januari 2014
 
The value of benchmarking software projects
The value of benchmarking software projectsThe value of benchmarking software projects
The value of benchmarking software projects
 
Using the ISBSG data to improve your organization success - van Heeringen (Me...
Using the ISBSG data to improve your organization success - van Heeringen (Me...Using the ISBSG data to improve your organization success - van Heeringen (Me...
Using the ISBSG data to improve your organization success - van Heeringen (Me...
 
Asl bi sl metrics themasessie 2013 devops sogeti
Asl bi sl metrics themasessie 2013   devops sogetiAsl bi sl metrics themasessie 2013   devops sogeti
Asl bi sl metrics themasessie 2013 devops sogeti
 
Begroten van software projecten - Hogeschool Rotterdam gastcollege 05-11-2013
Begroten van software projecten - Hogeschool Rotterdam gastcollege 05-11-2013Begroten van software projecten - Hogeschool Rotterdam gastcollege 05-11-2013
Begroten van software projecten - Hogeschool Rotterdam gastcollege 05-11-2013
 
Van heeringen estimate faster, cheaper, better
Van heeringen   estimate faster, cheaper, betterVan heeringen   estimate faster, cheaper, better
Van heeringen estimate faster, cheaper, better
 
van Heeringen - estimate faster,cheaper and better!
van Heeringen - estimate faster,cheaper and better!van Heeringen - estimate faster,cheaper and better!
van Heeringen - estimate faster,cheaper and better!
 
The value of benchmarking IT projects - H.S. van Heeringen
The value of benchmarking IT projects - H.S. van HeeringenThe value of benchmarking IT projects - H.S. van Heeringen
The value of benchmarking IT projects - H.S. van Heeringen
 
Begroten van agile projecten, technical meeting Sogeti 2013-09
Begroten van agile projecten, technical meeting Sogeti 2013-09Begroten van agile projecten, technical meeting Sogeti 2013-09
Begroten van agile projecten, technical meeting Sogeti 2013-09
 
Sogeti seminar Supplier Performance Measurement
Sogeti seminar Supplier Performance MeasurementSogeti seminar Supplier Performance Measurement
Sogeti seminar Supplier Performance Measurement
 
Software Estimating and Performance Measurement
Software Estimating and Performance MeasurementSoftware Estimating and Performance Measurement
Software Estimating and Performance Measurement
 

Kürzlich hochgeladen

BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLkapoorjyoti4444
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...amitlee9823
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756dollysharma2066
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfAmzadHosen3
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with CultureSeta Wicaksana
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Sheetaleventcompany
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...lizamodels9
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...amitlee9823
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876dlhescort
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...allensay1
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1kcpayne
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...daisycvs
 

Kürzlich hochgeladen (20)

BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdf
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 

Project Control using functional size - which method to use?

  • 1. Project control based on functional size Which method to use? Harold van Heeringen UKSMA conference (London, November 8, 2012)
  • 2. Harold van Heeringen • Short intro: − Sogeti Nederland BV senior consultant software metrics − ISBSG president − NESMA board member − NESMA working group chair COSMIC − NESMA working group chair Benchmarking − COSMIC IAC member Harold van Heeringen Sizing, Estimating & Control harold.van.heeringen@sogeti.nl @haroldveendam @Sogeti_SEC 2
  • 3. Agenda • Parametric project control • Product size ready • Differences IFPUG vs. COSMIC relevant for Project control • Experiment: Project control with two methods • Conclusions 3
  • 4. Project Management • Project Estimation − Parametric estimates based on (COSMIC) FP − Effort hours, duration, staff, defects − Galorath SEER-SEM / QSM SLIM Estimate / other tools  Productivity (PDR = hours/FP) that is expected • Project Planning − Transform the estimate into the plan • Project Control − Track the status based on FP FTE Staff Staff & Effort Variance 8 Cum Effort Life Cycle 3.500 3.000 6 2.500 − Do we meet our expected PDR? 2.000 MHR ppl 4 1.500 1.000 2 500 0 0 2 4 6 8 10 12 14 16 2 4 6 8 10 12 14 16 29-05 12-06 26-06 10-07 24-07 07-08 21-08 04-09 18-09 29-05 12-06 26-06 10-07 24-07 07-08 21-08 04-09 18-09 − Forecasting based on actuals '10 '10 Date 14-8-2010 (11,57 weeks) Plan Actual Diff Avg Staff Life Cycle (ppl) 5,2 5,3 0,1 Cum Effort Life Cy cle (MHR) 1.787,8 1.812,0 24,2 PI 20,8 20,6 -0,2 MBI 5,3 5,3 0,0 Current Plan Actuals Green Control Bound Yellow Control Bound Project: Project XYZ 4
  • 5. Project Control • How do Project managers manage their software realization project? − Administration of effort hours (weekly) − Compare effort hours against planned hours (weekly) • Project status − If more hours than planned have been spent, we must be ahead of schedule, right? − If less hours than planned have been spent, the project is easier than expected, right? • To measure hours is easy, but what about 'product delivered'? 5
  • 6. Inaccurate project status • Most used: − How many hours do you need to finish ‘activity X’? − Expert estimate/judgment is used to assess the status of the ‘work done’ − PM collects the status of all people and aggregates this info into a status report • Problem: − experts are usually optimistic, underestimating the work that still needs to be done ◦ Documenting, bug fixing, 2nd round of testing, etcetera • Result: − Inaccurate status until very late in the project ! 6
  • 7. Parametric project control • Control the project, using functional size for the 'product ready' • Project status: − Effort hours spent vs. effort hours planned − Actual functional size ready vs. planned functional size ready − Forecasting based on the actuals • Galorath SEER-SEM − Parametric Project Monitoring & Control tool (PPMC) • QSM SLIM Control − Part of the QSM SLIM toolsuite 7
  • 8. How the tools work 1. Put in the baseline plan − Start and end date − Milestone dates − Effort hours planned − Product size to be delivered in (C) FP 1. Record actuals (every week / 2 weeks) − Effort hours − Dates − Defects − Product size ready in (C) FP 1. Forecast project results 2. Calculate corrective actions 8
  • 9. Project control • Putting in the baseline plan is easy (project plan of the PL) • Collecting actual hours, milestone dates and defects is also fairly easy • Measuring the ‘product size ready’ is more complicated − When is an EI ready? When is an EIF ready? − How can we objectively assess a function point being ready? • Function point ready – after the programmer reports it ready for systems testing • Measuring the correct ‘product size ready’ is crucial for Project Control 9
  • 10. Product size ready • Multiple methods to measure ‘product size ready’ • Technical: SLOCs − Easy to measure actuals, but hard to predict/estimate total − Baseline plan slocs is inaccurate, but actuals are accurate • Functional: (COSMIC) Function Points − Harder to measure, based on quality of documentation − Baseline plan and actuals can both be accurately measured • Which functional size measurement method is most accurate? 10
  • 11. NESMA/IFPUG vs. COSMIC Characteristic NESMA/IFPUG FPA COSMIC Applicable on domain Business software Business / Real-time / Infrastructure software Data model required? Required Not required (but very handy) Measurement of Not possible Possible separate components Size limit per function Yes Size is not limited Benchmarking data ISBSG (aug 12), n= 4316 ISBSG (aug 12), n=446 Measurement of No No, but local extension processing functionality is possible Early sizing Based on data model Based on process model 11
  • 12. Functional complexity • IFPUG/NESMA does not really measure differences in functional complexity − EI: 3,4 or 6 FP (never less than 3, never more than 6) − EO: 4,5 or 7 FP (never less than 4, never more than 7) • But: in real life functions can differ from very low complexity − e.g. drop down list ‘Client’ (EO: 1 FTR, 2 DET, 4 FP) …to very complex − e.g. to make a new insurance contract perhaps clicking through 5 screens: (EI: 8 FTR, 121 DET, 6 FP) • Difference in FP does not reflect difference in effort needed. 12
  • 13. COSMIC and Project control • Theoretically, COSMIC should be the better method to use for Project Control • The data model does not explicitly get points. − In project control, it’s difficult to assess status regarding the realization of the data model (When is an EIF ready?). • The functional processes are not restricted in size − E.g. drop down list Client: 3 CFP (EO: 4 FP) − Make a new insurance contract: 38 CFP (EI: 6 FP) • Difference in size reflects the difference in effort needed more realistically 13
  • 14. Some examples User Function IFPUG IFPUG COSMIC COSMIC type size type size Functional 8 CFP Add customer EI 3 FP Process Change Functional 7 CFP customer EI 4 FP Process Delete Functional 4 CFP customer EI 3 FP Process Show revenue Functional 12 CFP per customer Process and region EO 7 FP Customer ILF 7 FP - 0 14
  • 15. Case: Government agency • Project name: XYZ • Programming language: Java • Development method: waterfall • Functional size: − 371 FP (IFPUG) − 494 CFP (COSMIC) • Effort hours planned: 2.505 hours • Planned start date: 26-05-2010 • Planned end date: 12-09-2010 CONST. & IFPUG COSMIC Hours TEST FP FP planned Start date End date Project XYZ 371 494 2505 26-5-2010 12-09-2010 15
  • 16. The IFPUG plan SEI Core Metrics Schedule Size 500 400 300 Phases FP Construct & Test 200 100 0 2 4 6 8 10 12 14 16 2 4 6 8 10 12 14 16 29-05 12-06 26-06 10-07 24-07 07-08 21-08 04-09 18-09 29-05 12-06 26-06 10-07 24-07 07-08 21-08 04-09 18-09 '10 '10 Cum Effort Life Cycle 3.500 3.000 2.500 2.000 MHR 1.500 1.000 500 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 29-05 05-06 12-06 19-06 26-06 03-07 10-07 17-07 24-07 31-07 07-08 14-08 21-08 28-08 04-09 11-09 18-09 '10 Current Plan Actuals Current Forecast Green Control Bound Yellow Control Bound Project: Project XYZ 16
  • 17. The COSMIC plan SEI Core Metrics Schedule Size 700 600 500 400 Phases FP Construct & Test 300 200 100 0 2 4 6 8 10 12 14 16 2 4 6 8 10 12 14 16 29-05 12-06 26-06 10-07 24-07 07-08 21-08 04-09 18-09 29-05 12-06 26-06 10-07 24-07 07-08 21-08 04-09 18-09 '10 '10 Cum Effort Life Cycle 3.500 3.000 2.500 2.000 MHR 1.500 1.000 500 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 29-05 05-06 12-06 19-06 26-06 03-07 10-07 17-07 24-07 31-07 07-08 14-08 21-08 28-08 04-09 11-09 18-09 '10 Current Plan Actuals Current Forecast Green Control Bound Yellow Control Bound Project: Project XYZ 17
  • 18. After 4 weeks: forecast IFPUG • First Actuals Metric Plan Actual Difference Hours spent 238 294 +56 IFPUG FP ready 99 80 -19 COSMIC FP ready 132 130 -2 SEI Core Metrics Schedule Size 500 400 300 Phases FP Construct &... 200 100 0 2 4 6 8 10 12 14 16 18 2 4 6 8 10 12 14 16 18 29-05 12-06 26-06 10-07 24-07 07-08 21-08 04-09 18-09 02-10 29-05 12-06 26-06 10-07 24-07 07-08 21-08 04-09 18-09 02-10 '10 '10 Cum Effort Life Cycle 3.500 3.000 2.500 2.000 MHR 1.500 1.000 500 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 29-05 05-06 12-06 19-06 26-06 03-07 10-07 17-07 24-07 31-07 07-08 14-08 21-08 28-08 04-09 11-09 18-09 25-09 02-10 '10 18 Current Plan Actuals Current Forecast Green Control Bound Yellow Control Bound Project: Project XYZ
  • 19. After 4 weeks: forecast COSMIC • First Actuals Metric Plan Actual Difference Hours spent 238 294 +56 IFPUG FP ready 99 80 -19 COSMIC FP ready 132 130 -2 SEI Core Metrics Schedule Size 700 600 500 400 Phases FP Construct & Test 300 200 100 0 2 4 6 8 10 12 14 16 2 4 6 8 10 12 14 16 29-05 12-06 26-06 10-07 24-07 07-08 21-08 04-09 18-09 29-05 12-06 26-06 10-07 24-07 07-08 21-08 04-09 18-09 '10 '10 Cum Effort Life Cycle 3.500 3.000 2.500 2.000 MHR 1.500 1.000 500 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 29-05 05-06 12-06 19-06 26-06 03-07 10-07 17-07 24-07 31-07 07-08 14-08 21-08 28-08 04-09 11-09 18-09 '10 19 Current Plan Actuals Current Forecast Green Control Bound Yellow Control Bound Project: Project XYZ
  • 20. Forecast after 4 weeks Metric Plan Forecast Overrun/underrun Based on IFPUG FP Hours 2.505 2.933 +428 hours (+17%) Schedule 12-09-2010 26-09-2010 2 weeks Based on COSMIC FP Hours 2.505 2.601 +96 hours (+4%) Schedule 12-09-2010 14-09-2010 2 days • Project manager thinks everything is OK • Team members agree 20
  • 21. Actuals after week 8: Forecast IFPUG Metric Plan Actual Difference Hours spent 941 982 +41 FP ready 279 252 -27 COSMIC FP ready 371 366 -5 SEI Core Metrics Schedule Size 500 400 300 Phases FP Construct & T... 200 100 0 2 4 6 8 10 12 14 16 2 4 6 8 10 12 14 16 29-05 12-06 26-06 10-07 24-07 07-08 21-08 04-09 18-09 29-05 12-06 26-06 10-07 24-07 07-08 21-08 04-09 18-09 '10 '10 Cum Effort Life Cycle 3.500 3.000 2.500 2.000 MHR 1.500 1.000 500 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 29-05 05-06 12-06 19-06 26-06 03-07 10-07 17-07 24-07 31-07 07-08 14-08 21-08 28-08 04-09 11-09 18-09 25-09 '10 21 Current Plan Actuals Current Forecast Green Control Bound Yellow Control Bound Project: Project XYZ
  • 22. Forecast after 8 weeks • PM still thinks everything is on track, but is getting a little nervous • Team members still agree Metric Plan Forecast Overrun/underrun Based on IFPUG FP Hours 2.505 2.991 +486 hours (+19%) Schedule 12-09-2010 24-09-2010 12 days Based on COSMIC FP Hours 2.505 2.690 +185 hours (+7%) Schedule 12-09-2010 15-09-2010 3 days 22
  • 23. After 12 weeks Metric Plan Actual Difference Hours spent 1.788 1.812 +24 FP ready 357 348 -9 COSMIC FP ready 471 470 -1 Metric Plan Forecast Overrun/under run Based on IFPUG FP Hours 2.505 3.009 +504 hours (+20%) Schedule 12-09-2010 25-09-2010 13 days Based on COSMIC FP Hours 2.505 2.730 +225 hours (+9 %) Schedule 12-09-2010 16-09-2010 4 days 23
  • 24. Final results • Small overrun in time and effort Metric Plan Actual Difference Hours spent 2.505 2.586 +81 Project end date 12 -09-2010 16-09-2010 +4 days FP ready 371 371 0 COSMIC FP ready 494 494 0 24
  • 25. The forecasts analyzed • IFPUG forecasts show considerable overruns until late in the project • COSMIC forecasts more conservative • COSMIC forecasts more in line with the feeling of the team and the PM Forecast IFPUG FP COSMIC FP Hours overrun Schedule overrun Hours overrun Schedule overrun 4 weeks +428 + 2 weeks +96 +2 days 8 weeks +486 +12 days +185 +3 days 12 weeks +504 +13 days +225 + 4 days Final +81 +4 days +81 +4 days 25
  • 26. Conclusions • In theory, COSMIC should be the better method to use in parametric project control − No size limit per function: more accurate product size ready − No explicit points for the data model: Easier to measure ‘project size ready’ • This experiment confirms this theory − COSMIC forecasts closer to reality than IFPUG forecasts • More experiments are needed to support this conclusion 26
  • 27. Sogeti Sizing, Estimating & Control Thanks for your attention ! Harold van Heeringen Sizing, Estimating & Control harold.van.heeringen@sogeti.nl @haroldveendam @Sogeti_SEC Sogeti Sizing, Estimating & Control NESMA – board member NESMA – chair working group COSMIC NESMA – chair working group Benchmarking NESMA – working group Sizing Packages NESMA – working group Estimation maturity COSMIC – International Advisory Counsil COSMIC – Benchmarking Committee ISBSG – President 27

Hinweis der Redaktion

  1. Thank you very much for your attention!