1. Collage of Engineering
Project Controlling and Project Monitoring
4/23/2010 Author: Dr. Tomas Ganiron Jr 1
2. Monitor and Control
During all of the phases and the process groups, regular
monitoring and controls are required. These include :
scope change management,
change management,
quality control,
time management,
budget management,
risk management
and contract administration.
4/23/2010 Author: Dr. Tomas Ganiron Jr 2
3. Monitor and Control
Activities in this group are:
Monitor and Control Project Work
Integrated Change Control
Scope Verification
Scope Control
Schedule Control
Cost Control
Perform Quality Control
Manage Project Team
Performance Reporting
Manage Stakeholders
Risk Monitoring and Control
Contract Administration
4/23/2010 Author: Dr. Tomas Ganiron Jr 3
4. What Are We Controlling?
Progress vs. plan:
Cost
Schedule
Scope
Stakeholder satisfaction
Changes:
To the progress measurement baselines
To the description of the product of the
project
4/23/2010 Author: Dr. Tomas Ganiron Jr 4
5. Elements of Project Control
Baseline
Development
Change Progress
Control Monitoring
4/23/2010 Author: Dr. Tomas Ganiron Jr 5
6. Baseline Development
Doubt is not a
pleasant condition,
but certainty is
absurd.
Voltaire
4/23/2010 Author: Dr. Tomas Ganiron Jr 6
7. Four Major Baselines
Scope baseline = product description
Stakeholder satisfaction baseline =
project success criteria
Cost baseline = budget
Accrual-based
Cash-based
Schedule baseline = schedule
4/23/2010 Author: Dr. Tomas Ganiron Jr 7
8. Change Control
Kelly’s Koncept
The Wright Brothers’ great insight
was that instability was necessary
for maneuverability. A ponderous
bird would not fly.
4/23/2010 Author: Dr. Tomas Ganiron Jr 8
9. Module Overview
Objectives of change management
Requirements for good change
management
4/23/2010 Author: Dr. Tomas Ganiron Jr 9
10. Types of Changes
Scope changes (modify product
documentation and often project plan):
Requirements change
Clarifications
Site emergencies
Work changes (modify project plan):
Resource change
Modified approach
Corrective action
4/23/2010 Author: Dr. Tomas Ganiron Jr 10
11. Definition:
Corrective Action
Steps taken to align future project
direction with the stakeholders’
success measures.
4/23/2010 Author: Dr. Tomas Ganiron Jr 11
12. Evaluating Change Requests
All change requests are documented:
Emergency changes are documented
after the fact.
Non-emergencies are documented by the
requestor before being considered.
Change requests should be documented
by the requestor.
4/23/2010 Author: Dr. Tomas Ganiron Jr 12
13. First Level Approval
of Change Requests
Usually provided by the project manager
or a senior team member:
Are the expected benefits significant
enough to merit further investigation?
Implications:
Must have budget for this work!
Benefits may include cost avoidance
Organizational politics must be
considered
4/23/2010 Author: Dr. Tomas Ganiron Jr 13
14. Second Level Approval of
Change Requests
Usually provided by a Change Control
Board (CCB):
Do the expected benefits outweigh the
costs?
Implications:
Must have budget for this work!
Benefits may include cost avoidance
Organizational politics must be
considered
4/23/2010 Author: Dr. Tomas Ganiron Jr 14
15. Other Considerations
Life cycle costing — purchase cost vs.
operating cost:
Three-lane bridge, two-lane road
Re-usable code
Item costing — for quantity-based
changes:
Fixed costs = cost to deliver first unit
Variable costs = cost per unit
4/23/2010 Author: Dr. Tomas Ganiron Jr 15
16. Tools and Techniques for
Change Control
Change control board (CCB)
Escalation procedures
Work authorization
Configuration management
4/23/2010 Author: Dr. Tomas Ganiron Jr 16
17. Change Control Board
A formally constituted group responsible
for approving or rejecting change
requests.
Powers and responsibilities should be
well-defined and agreed upon in
advance.
On larger, more complex projects, there
may be multiple CCBs.
4/23/2010 Author: Dr. Tomas Ganiron Jr 17
18. Escalation Procedures
How are differences within the team
handled?
Can a CCB decision be appealed? Can
other decisions be appealed?
To whom?
Under what circumstances?
4/23/2010 Author: Dr. Tomas Ganiron Jr 18
19. Configuration Management
A procedure for applying technical and
administrative direction and surveillance
to:
Identify and document the functional and physical
characteristics of an item or system.
Control any changes to such characteristics.
Record and report the change and its
implementation status.
Audit the items and system to verify conformance
to requirements.
4/23/2010 Author: Dr. Tomas Ganiron Jr 19
20. In Simpler Words
Is the document current and complete?
Can you prove it?
4/23/2010 Author: Dr. Tomas Ganiron Jr 20
21. Summary of
Key Points
Change control procedures must be
defined at the start of the project.
Project budgets must include funds for
evaluating change requests.
Approved changes should generally
result in updated baselines.
4/23/2010 Author: Dr. Tomas Ganiron Jr 21
22. 7-2 PM responsibility
The Project Manager needs to measure
performance to find out how progress
differs from plan in time to initiate corrective
action. The controlling activity often cause a
redefinition of project objectives
4/23/2010 Author: Dr. Tomas Ganiron Jr 22
23. 7-2 PM responsibility
PM produce a Status report including :
What did we plan to achieve this period?
What did we actually achieve?
Why is there a difference?
What do we plan to achieve next period?
How are we managing existing risks?
Are there any new risks?
What are the current major issues?
What are we doing about them?
Are there any change requests to be authorised?
4/23/2010 Author: Dr. Tomas Ganiron Jr 23