SlideShare ist ein Scribd-Unternehmen logo
1 von 49
To EV or not to EV
Prepared by. G.Kabbara
Date: November 15th 2016
Are we ready in the organization for EV?
•Before we embark on an EV program we
need to make an assessment if we will be
able to successfully complete this project;
and to use EV in the company.
Where are we in the PROJECT MATURITY
MATRIX?
Where are we in the PROJECT MATURITY
MATRIX?
Where are we in the PROJECT MATURITY
MATRIX?
Where are we in the PROJECT MATURITY
MATRIX?
Where are we in the PROJECT MATURITY
MATRIX?
• If we are not at least a level 3 maturity level we should not be using
Earned Value. (EV).
• An analogy:-
• If you are learning to dive you would dive off a board close to water surface to
learn the basics. Once your become proficient, you would move to a 3 meter
diving height, then later to a 10 meter diving height to learn advanced skills.
• If you are new to diving you would not start with the 10 meter diving height
unless you are looking to fail!
•The same applies to the use of earned value
analysis. If you don’t have a project organization
with maturity level of 3 or higher, trying to apply
EVA will only lead to failure.
EV in Action
Lets however proceed to understand EV simply
Lets look at a sample project
• This project has an authorized budget of $1,000,000 to be completed
in 1 year. (4 quarters).
• The planned cost for the first quarter is $300,000
• And Actual cost spent at the end of the 1st Quarter is $300,000
Traditional Cost Management
250
500
750
Authorized Budget
$1,000,000
Planned
Cost =
$300k
Actual Costs =
$300k
Quarter 1 Quarter 2 Quarter 3 Quarter 4
Using a traditional
cost management
approach, at the end
of the first quarter
the project manager
would display the
cost performance for
the benefit of
management.
Traditional Cost Management
250
500
750
Authorized Budget
$1,000,000
Planned
Cost =
$300k
Actual Costs =
$300k
Quarter 1 Quarter 2 Quarter 3 Quarter 4
The approved spend
plan called for an
expenditure of
$300,000 for the first
quarter and actual
results thus far show
an expenditure of
exactly $300,000.
Traditional Cost Management
250
500
750
Authorized Budget
$1,000,000
Planned
Cost =
$300k
Actual Costs =
$300k
Quarter 1 Quarter 2 Quarter 3 Quarter 4
One could conclude
without further
review that the
project was
performing exactly to
its financial plan:
$300,000 planned
and $300,000 spent.
Traditional Cost Management
250
500
750
Authorized Budget
$1,000,000
Planned
Cost =
$300k
Actual Costs =
$300k
Quarter 1 Quarter 2 Quarter 3 Quarter 4
•Perfect cost performance.
•Life is good.
Traditional Cost Management
250
500
750
Authorized Budget
$1,000,000
Planned
Cost =
$300k
Actual Costs =
$300k
Quarter 1 Quarter 2 Quarter 3 Quarter 4
A fairly typical, but
unfortunately potentially
deceptive, approach to
understanding project cost
performance.
Traditional Cost Management
250
500
750
Authorized Budget
$1,000,000
Planned
Cost =
$300k
Actual Costs =
$300k
Quarter 1 Quarter 2 Quarter 3 Quarter 4
In fact, looking at the
data as displayed
nobody could really
determine the projects
true cost performance.
To Determine the project’s true
cost performance, one would
need to compare the physical
schedule results in the same
format as the cost displays.
On the Road to EV
• There lies the beauty of Earned Value “EV”.
• EV project management requires an integrated baseline plan which relates
the defined scope of work to the budgeted costs.
• Let us now contrast the display with an earned value performance chart.
• Here the total budget of $1,000,000 will be made up from detailed bottom-
up planning that allows for performance to be measure throughout the life
of the project.
• There are ten milestones to be accomplished, and each milestone will have
a weighted value of $100,000. Each time a milestone is completed the
project will earn $100,000.
Earned value performance 1st Quarter.
250
500
750
Authorized Budget
$1,000,000
Planned
Cost =
$300k
Actual Costs =
$300k
Quarter 1 Quarter 2 Quarter 3 Quarter 4
Earned value performance 1st Quarter.
250
500
750
Authorized Budget
$1,000,000
Planned
Value =
$300k
Actual Costs =
$300k
Quarter 1 Quarter 2 Quarter 3 Quarter 4
Earned Value =
$200k
This chart reflects
actual physical
earned value of only
two milestones
completed,
representing an
earned value of
$200,000, against the
planned value of
$300,000
• The earned value also consist of two elements
• The scheduled work which was completed
• The original budget for the completed work.
Earned value performance 1st Quarter.
250
500
750
Authorized Budget
$1,000,000
Planned
Value =
$300k
Actual Costs =
$300k
Quarter 1 Quarter 2 Quarter 3 Quarter 4
Earned Value =
$200k
We can immediately
see that the project
is running behind the
work it set out to do
during the first
quarter.
It had planned to
accomplish $300,000
in and work, but had
accomplished only
$200,000.
Earned value performance 1st Quarter.
250
500
750
Authorized Budget
$1,000,000
Planned
Value =
$300k
Actual Costs =
$300k
Quarter 1 Quarter 2 Quarter 3 Quarter 4
Earned Value =
$200k
The project is
running a negative
$100,000 schedule
variance.
Which is defined as
the earned value
($200,000) less the
planned value
($300,000) which
equals schedule
variance (-$100,000)
Earned value performance 1st Quarter.
250
500
750
Authorized Budget
$1,000,000
Planned
Value =
$300k
Actual Costs =
$300k
Quarter 1 Quarter 2 Quarter 3 Quarter 4
Earned Value =
$200k
Also the cost actuals
of $300,000, an
amount greater than
the earned value of
physical work
performed of
$200,000.
Earned value performance 1st Quarter.
250
500
750
Authorized Budget
$1,000,000
Planned
Value =
$300k
Actual Costs =
$300k
Quarter 1 Quarter 2 Quarter 3 Quarter 4
Earned Value =
$200k
Conclusion
The project has spent
$300,000 in actual costs
to achieve only $200,000
worth of earned value.
An earned value cost
variance is defined as the
earned value
accomplished ($200,000)
less the actual costs
($300,000) which equals
the cost variance (-
$100,000).
Earned value performance 1st Quarter.
250
500
750
Authorized Budget
$1,000,000
Planned
Value =
$300k
Actual Costs =
$300k
Quarter 1 Quarter 2 Quarter 3 Quarter 4
Earned Value =
$200k
This is an “Overrun” of
costs. This project can be
said to be running a
negative $100,000 cost
variance.
Earned value performance 1st Quarter.
250
500
750
Authorized Budget
$1,000,000
Planned
Value =
$300k
Actual Costs =
$300k
Quarter 1 Quarter 2 Quarter 3 Quarter 4
Earned Value =
$200k
Thus the delicate
relationships reflected
with these actual cost &
schedule performance
relationships can now be
used to predict the final
costs & schedule results
of the project.
Earned value performance 1st Quarter.
250
500
750
Authorized Budget
$1,000,000
Planned
Value =
$300k
Actual Costs =
$300k
Quarter 1 Quarter 2 Quarter 3 Quarter 4
Earned Value =
$200k
The Project is in
trouble.
But one could not have
discerned that condition
using a traditional cost
management approach.
Earned value performance 1st Quarter.
250
500
750
Authorized Budget
$1,000,000
Planned
Value =
$300k
Actual Costs =
$300k
Quarter 1 Quarter 2 Quarter 3 Quarter 4
Earned Value =
$200k
It is only when earned
value brings in the three
dimensions of
performance that we can
tell that the project is
experiencing problems.
Such issues need to be
addressed immediately in
order to avoid adverse
cost overruns & schedule
slippages.
The fundamental differences
Traditional Project Cost Management
Planned Funds = $300K
Actual Costs = $300K
Variance from an expenditure plan = (OK)
With a plan versus actual costs
comparison there is no way to
ascertain how much of the
physical work has been
accomplished.
Only has significance as a
reflection of whether a project
has stayed with the funds
authorized by management.
The fundamental differences
Traditional Project Cost Management
Planned Funds = $300K
Actual Costs = $300K
Variance from an expenditure plan = (OK)
This only reflects funding
performance, not true cost
performance. Yet most projects
today typically represent their
cost performance using similar
reporting.
The fundamental differences
Traditional Project Cost Management
Planned Funds = $300K
Actual Costs = $300K
Earned Value Project Management
Planned Value = $300K
Earned Value = $200K
Actual Costs = $300K
Variance from an expenditure plan = (OK)
Variance from the planned schedule =(-$100K)
The “true” cost variance = (-$100K)
Now looking at Project
performance using EV.
This displays three dimensions of
data:
1) The planned value of the
physical work authorized
2) The earned value of the
physical work accomplished
3) The actual costs incurred to
accomplish the earned value.
The fundamental differences
Traditional Project Cost Management
Planned Funds = $300K
Actual Costs = $300K
Earned Value Project Management
Planned Value = $300K
Earned Value = $200K
Actual Costs = $300K
Variance from an expenditure plan = (OK)
Variance from the planned schedule =(-$100K)
The “true” cost variance = (-$100K)
As you can see 2 critical variances
may be ascertained.
1) The project is experiencing a
negative schedule variance of -
$100,000 from its planned work.
Put in another way one third of
the work the project set out to do
was not accomplished in the
timeframe being measure. The
team is clearly behind its planned
schedule.
The fundamental differences
Traditional Project Cost Management
Planned Funds = $300K
Actual Costs = $300K
Earned Value Project Management
Planned Value = $300K
Earned Value = $200K
Actual Costs = $300K
Variance from an expenditure plan = (OK)
Variance from the planned schedule =(-$100K)
The “true” cost variance = (-$100K)
The Schedule variance in
conjunction with Critical Path
Method (CPM), provides
invaluable insights into the true
schedule status of the project.
The fundamental differences
Traditional Project Cost Management
Planned Funds = $300K
Actual Costs = $300K
Earned Value Project Management
Planned Value = $300K
Earned Value = $200K
Actual Costs = $300K
Variance from an expenditure plan = (OK)
Variance from the planned schedule =(-$100K)
The “true” cost variance = (-$100K)
The second critical variance 2)
Is the relation ship of value of the
work done, the earned value, to
the funds expended to
accomplish the work.
A total of $300,000 was expended
to accomplish only $200,000
worth of work. Thus the project
has experienced a cost overrun of
minus $100,000 for the work
performed to date.
The fundamental differences
Traditional Project Cost Management
Planned Funds = $300K
Actual Costs = $300K
Earned Value Project Management
Planned Value = $300K
Earned Value = $200K
Actual Costs = $300K
Variance from an expenditure plan = (OK)
Variance from the planned schedule =(-$100K)
The “true” cost variance = (-$100K)
This negative cost trend is of
critical importance to the project,
for experience has indicated that
such overruns of costs do not
correct themselves over time.
In fact, cost overruns
tend to get worse.
The fundamental differences
Traditional Project Cost Management
Planned Funds = $300K
Actual Costs = $300K
Earned Value Project Management
Planned Value = $300K
Earned Value = $200K
Actual Costs = $300K
Variance from an expenditure plan = (OK)
Variance from the planned schedule =(-$100K)
The “true” cost variance = (-$100K)
The actual cost & schedule
performance results can also be
used independently or jointly
forecast the final results of the
project with amazing accuracy.
Project Manager Needs to know
• As a given point in time, we need answers to these questions:
1. What work is scheduled to have been completed?
2. What was the cost estimate for the work scheduled?
3. What work has been accomplished?
4. What was the cost estimate of the completed work?
5. What have our costs been?
6. What are the variances?
Project Manager Needs to know
Planned Value
Earned Value
Actual Cost
CPI & SPI
• As a given point in time, we need answers to these questions:
1. What work is scheduled to have been completed?
2. What was the cost estimate for the work scheduled?
3. What work has been accomplished?
4. What was the cost estimate of the completed work?
5. What have our costs been?
6. What are the variances?
THE THREE DIFFERENT TYPES OF PROJECT
MANAGEMENT OFFICES
• 1. Supportive PMO
• 2. Controlling PMO
• 3. Directive PMO
1. Supportive PMO
• The Supportive PMO generally provides support in the form of on-
demand expertise, templates, best practices, access to information
and expertise on other projects, and the like. This can work in an
organisation where projects are done successfully in a loosely
controlled manner and where additional control is deemed
unnecessary. Also, if the objective is to have a sort of "clearing-house"
of project management information across the enterprise to be used
freely by project managers, then the Supportive PMO is the right
type.
2. Controlling PMO
• In organisations where there is a desire to "rein in" the activities,
processes, procedures, documentation, and more - a controlling PMO can
accomplish that. Not only does the organisation provide support, but it
also requires that the support be used. Requirements might include
adoption of specific methodologies, templates, forms, conformance to
governance, and application of other PMO controlled sets of rules. In
addition, project offices might need to pass regular reviews by the
controlling PMO, and this may represent a risk factor on the project. This
works if a) there is a clear case that compliance with project management
organisation offerings will bring improvements in the organisation and how
it executes on projects, and b) the PMO has sufficient executive support to
stand behind the controls the PMO puts in place.
3. Directive PMO
• This type goes beyond control and actually "takes over" the projects by providing the project
management experience and resources to manage the project. As organisations undertake
projects, professional project managers from the PMO are assigned to the projects. This injects a
great deal of professionalism into the projects, and, since each of the project managers originates
and reports back to the directive PMO, it guarantees a high level of consistency of practice across
all projects. This is effective in larger organisations that often matrix out support in various areas,
and where this setup would fit the culture.
• The best type is very specific to the organisation, culture, and history of what works and what
does not. But the objectives are - more or less - to:
• Implement a common methodology
• Standardise terminology
• Introduce effective repeatable project management processes
• Provide common supporting tools
• Ultimately, the objective is to improve levels of project success within the organisation
EIA-748 Guidelines
• Guideline 1 – Define Work Scope (WBS) .................................................................... 4
• Guideline 2 – Define Project Organization (OBS) ........................................................ 5
• Guideline 3 – Integrate Processes .............................................................................. 6
• Guideline 4 – Identify Overhead Management ............................................................ 7
• Guideline 5 – Integrate WBS/OBS to Create Control Accounts ................................... 8
• 2.2 Planning, Scheduling, and Budgeting .......................................................................10
• Guideline 6 – Schedule with Network Logic .............................................................. 10
• Guideline 7 – Set Measurement Indicators ............................................................... 12
• Guideline 8 – Establish Budgets for Authorized Work ............................................... 14
• Guideline 9 – Budget by Cost Elements .................................................................... 18
• Guideline 10 – Create Work Packages, Planning Packages ..................................... 20
• Guideline 11 – Sum Detail Budgets to Control Account ............................................ 22
• Guideline 12 – LOE Planning and Control ................................................................. 23
• Guideline 13 – Establish Overhead Budgets ............................................................. 24
• Guideline 14 – Identify Management Reserve and Undistributed Budget .................. 26
• Guideline 15 – Reconcile to Target Cost Goal .......................................................... 28
EIA-748 Guidelines
• Accounting Considerations
• Guideline 16 – Record Direct Costs
• Guideline 17 – Summarize Direct Costs by WBS Elements ...................................... 30
• Guideline 18 – Summarize Direct Costs by OBS Elements ....................................... 31
• Guideline 19 – Record/Allocate Indirect Costs .......................................................... 32
• Guideline 20 – Identify Unit and Lot Costs ................................................................ 33
• Guideline 21 – Track and Report Material Costs and Quantities ............................... 34
• 2.4 Analysis and Management Reports ..........................................................................36
• Guideline 22 – Calculate Schedule Variance and Cost Variance .............................. 36
• Guideline 23 – Identify Significant Variances for Analysis ......................................... 37
• Guideline 24 – Analyze Indirect Cost Variances ........................................................ 39
• Guideline 25 – Summarize Information for Management .......................................... 40
• Guideline 26 – Implement Corrective Actions............................................................ 41
• Guideline 27 – Revise Estimate at Completion (EAC) ............................................... 42
• 2.5 Revisions and Data Maintenance ..............................................................................44
• Guideline 28 – Incorporate Changes in a Timely Manner .......................................... 44
EIA-748 Guidelines
• Guideline 29 – Reconcile Current to Prior Budgets
• Guideline 30 – Control Retroactive Changes
• Guideline 31 – Prevent Unauthorized Revisions
• Guideline 32 – Document PMB Changes
Earned value cost & schedule performance
indices: The SPI and CPI
• To be determined.,.,
References used for presentation
• Articles on Earned Value
• Earned Value Project Management – Fourth Edition
• AAICP

Weitere ähnliche Inhalte

Ähnlich wie Culture Check on using Earned Value in Organization

case study in corporate finance npv irr arr
case study in corporate finance npv irr arrcase study in corporate finance npv irr arr
case study in corporate finance npv irr arrmanjhujayakumar
 
Earned Value fundamentals
Earned Value fundamentalsEarned Value fundamentals
Earned Value fundamentalsDenise Fotopoulou
 
Earned Value Management - Project Controls - Schedule Only.pptx
Earned Value Management - Project Controls - Schedule Only.pptxEarned Value Management - Project Controls - Schedule Only.pptx
Earned Value Management - Project Controls - Schedule Only.pptxssuser5fc1e7
 
Mark blum ubc tool box execution - powerpoint presentation
Mark blum   ubc tool box execution - powerpoint presentationMark blum   ubc tool box execution - powerpoint presentation
Mark blum ubc tool box execution - powerpoint presentationCDN_Irony
 
Evm class 02 1to15 by upad
Evm   class 02  1to15 by upadEvm   class 02  1to15 by upad
Evm class 02 1to15 by upadhvostik
 
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the NumbersSymposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the NumbersPMI-MontrĂŠal
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdfsajidkhan82714
 
Time Value of Money
Time Value of MoneyTime Value of Money
Time Value of MoneySajad Nazari
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)Ejaz Bhatti
 
Foundations for New Champlain Bridge Corridor Project
Foundations for New Champlain Bridge Corridor ProjectFoundations for New Champlain Bridge Corridor Project
Foundations for New Champlain Bridge Corridor ProjectDaksh Raj Chopra
 
Webinar: Earned value management pure common sense
Webinar: Earned value management pure common senseWebinar: Earned value management pure common sense
Webinar: Earned value management pure common senseAli Zeeshan
 
Earned value management
Earned value managementEarned value management
Earned value managementwhizkris
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)Harshit Mahajan
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value AnalysisDavid Edgeworth
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysisNikhil Raj
 
The A Team Property Group - Elite Joint Venture Property Development Program
The A Team Property Group - Elite Joint Venture Property Development ProgramThe A Team Property Group - Elite Joint Venture Property Development Program
The A Team Property Group - Elite Joint Venture Property Development ProgramSasha Hopkins
 

Ähnlich wie Culture Check on using Earned Value in Organization (20)

case study in corporate finance npv irr arr
case study in corporate finance npv irr arrcase study in corporate finance npv irr arr
case study in corporate finance npv irr arr
 
Earned Value fundamentals
Earned Value fundamentalsEarned Value fundamentals
Earned Value fundamentals
 
Earned Value Management - Project Controls - Schedule Only.pptx
Earned Value Management - Project Controls - Schedule Only.pptxEarned Value Management - Project Controls - Schedule Only.pptx
Earned Value Management - Project Controls - Schedule Only.pptx
 
Mark blum ubc tool box execution - powerpoint presentation
Mark blum   ubc tool box execution - powerpoint presentationMark blum   ubc tool box execution - powerpoint presentation
Mark blum ubc tool box execution - powerpoint presentation
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Evm class 02 1to15 by upad
Evm   class 02  1to15 by upadEvm   class 02  1to15 by upad
Evm class 02 1to15 by upad
 
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the NumbersSymposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdf
 
Time Value of Money
Time Value of MoneyTime Value of Money
Time Value of Money
 
D009452333
D009452333D009452333
D009452333
 
CAPM study session 4
CAPM study session 4CAPM study session 4
CAPM study session 4
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
Foundations for New Champlain Bridge Corridor Project
Foundations for New Champlain Bridge Corridor ProjectFoundations for New Champlain Bridge Corridor Project
Foundations for New Champlain Bridge Corridor Project
 
Earned Value
Earned ValueEarned Value
Earned Value
 
Webinar: Earned value management pure common sense
Webinar: Earned value management pure common senseWebinar: Earned value management pure common sense
Webinar: Earned value management pure common sense
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
The A Team Property Group - Elite Joint Venture Property Development Program
The A Team Property Group - Elite Joint Venture Property Development ProgramThe A Team Property Group - Elite Joint Venture Property Development Program
The A Team Property Group - Elite Joint Venture Property Development Program
 

Mehr von Ghassan Kabbara

Sourcing Functional Requirements for a Services Division. Transforming Digitally
Sourcing Functional Requirements for a Services Division. Transforming DigitallySourcing Functional Requirements for a Services Division. Transforming Digitally
Sourcing Functional Requirements for a Services Division. Transforming DigitallyGhassan Kabbara
 
Assessment Report of an Outdated Legacy Application
Assessment Report of an Outdated Legacy  ApplicationAssessment Report of an Outdated Legacy  Application
Assessment Report of an Outdated Legacy ApplicationGhassan Kabbara
 
Inventory stock reduction ultimatum
Inventory stock reduction ultimatumInventory stock reduction ultimatum
Inventory stock reduction ultimatumGhassan Kabbara
 
Assessment of ERP Implementation for a Car Dealership
Assessment of ERP Implementation for a Car DealershipAssessment of ERP Implementation for a Car Dealership
Assessment of ERP Implementation for a Car DealershipGhassan Kabbara
 
A brief on IT past present & what lies ahead
A brief on IT  past present & what lies aheadA brief on IT  past present & what lies ahead
A brief on IT past present & what lies aheadGhassan Kabbara
 
Proof of stock reduction
Proof of stock reduction Proof of stock reduction
Proof of stock reduction Ghassan Kabbara
 
Car sales prospecting review for year 2006
Car sales prospecting review for year 2006Car sales prospecting review for year 2006
Car sales prospecting review for year 2006Ghassan Kabbara
 
Fraud cases presentation
Fraud cases presentationFraud cases presentation
Fraud cases presentationGhassan Kabbara
 

Mehr von Ghassan Kabbara (8)

Sourcing Functional Requirements for a Services Division. Transforming Digitally
Sourcing Functional Requirements for a Services Division. Transforming DigitallySourcing Functional Requirements for a Services Division. Transforming Digitally
Sourcing Functional Requirements for a Services Division. Transforming Digitally
 
Assessment Report of an Outdated Legacy Application
Assessment Report of an Outdated Legacy  ApplicationAssessment Report of an Outdated Legacy  Application
Assessment Report of an Outdated Legacy Application
 
Inventory stock reduction ultimatum
Inventory stock reduction ultimatumInventory stock reduction ultimatum
Inventory stock reduction ultimatum
 
Assessment of ERP Implementation for a Car Dealership
Assessment of ERP Implementation for a Car DealershipAssessment of ERP Implementation for a Car Dealership
Assessment of ERP Implementation for a Car Dealership
 
A brief on IT past present & what lies ahead
A brief on IT  past present & what lies aheadA brief on IT  past present & what lies ahead
A brief on IT past present & what lies ahead
 
Proof of stock reduction
Proof of stock reduction Proof of stock reduction
Proof of stock reduction
 
Car sales prospecting review for year 2006
Car sales prospecting review for year 2006Car sales prospecting review for year 2006
Car sales prospecting review for year 2006
 
Fraud cases presentation
Fraud cases presentationFraud cases presentation
Fraud cases presentation
 

KĂźrzlich hochgeladen

How-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionHow-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionCIToolkit
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixCIToolkit
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
 
Motivational theories an leadership skills
Motivational theories an leadership skillsMotivational theories an leadership skills
Motivational theories an leadership skillskristinalimarenko7
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insightWayne Abrahams
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingCIToolkit
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramCIToolkit
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchRashtriya Kisan Manch
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentationcraig524401
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)jennyeacort
 
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsFrom Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsCIToolkit
 
Management and managerial skills training manual.pdf
Management and managerial skills training manual.pdfManagement and managerial skills training manual.pdf
Management and managerial skills training manual.pdffillmonipdc
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsCIToolkit
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证jdkhjh
 

KĂźrzlich hochgeladen (18)

How-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionHow-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem Resolution
 
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Servicesauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
 
Motivational theories an leadership skills
Motivational theories an leadership skillsMotivational theories an leadership skills
Motivational theories an leadership skills
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insight
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentation
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
 
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsFrom Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
 
Management and managerial skills training manual.pdf
Management and managerial skills training manual.pdfManagement and managerial skills training manual.pdf
Management and managerial skills training manual.pdf
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield Metrics
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
 

Culture Check on using Earned Value in Organization

  • 1. To EV or not to EV Prepared by. G.Kabbara Date: November 15th 2016
  • 2. Are we ready in the organization for EV? •Before we embark on an EV program we need to make an assessment if we will be able to successfully complete this project; and to use EV in the company.
  • 3. Where are we in the PROJECT MATURITY MATRIX?
  • 4. Where are we in the PROJECT MATURITY MATRIX?
  • 5. Where are we in the PROJECT MATURITY MATRIX?
  • 6. Where are we in the PROJECT MATURITY MATRIX?
  • 7. Where are we in the PROJECT MATURITY MATRIX?
  • 8. • If we are not at least a level 3 maturity level we should not be using Earned Value. (EV). • An analogy:- • If you are learning to dive you would dive off a board close to water surface to learn the basics. Once your become proficient, you would move to a 3 meter diving height, then later to a 10 meter diving height to learn advanced skills. • If you are new to diving you would not start with the 10 meter diving height unless you are looking to fail!
  • 9. •The same applies to the use of earned value analysis. If you don’t have a project organization with maturity level of 3 or higher, trying to apply EVA will only lead to failure.
  • 10. EV in Action Lets however proceed to understand EV simply
  • 11. Lets look at a sample project • This project has an authorized budget of $1,000,000 to be completed in 1 year. (4 quarters). • The planned cost for the first quarter is $300,000 • And Actual cost spent at the end of the 1st Quarter is $300,000
  • 12. Traditional Cost Management 250 500 750 Authorized Budget $1,000,000 Planned Cost = $300k Actual Costs = $300k Quarter 1 Quarter 2 Quarter 3 Quarter 4 Using a traditional cost management approach, at the end of the first quarter the project manager would display the cost performance for the benefit of management.
  • 13. Traditional Cost Management 250 500 750 Authorized Budget $1,000,000 Planned Cost = $300k Actual Costs = $300k Quarter 1 Quarter 2 Quarter 3 Quarter 4 The approved spend plan called for an expenditure of $300,000 for the first quarter and actual results thus far show an expenditure of exactly $300,000.
  • 14. Traditional Cost Management 250 500 750 Authorized Budget $1,000,000 Planned Cost = $300k Actual Costs = $300k Quarter 1 Quarter 2 Quarter 3 Quarter 4 One could conclude without further review that the project was performing exactly to its financial plan: $300,000 planned and $300,000 spent.
  • 15. Traditional Cost Management 250 500 750 Authorized Budget $1,000,000 Planned Cost = $300k Actual Costs = $300k Quarter 1 Quarter 2 Quarter 3 Quarter 4 •Perfect cost performance. •Life is good.
  • 16. Traditional Cost Management 250 500 750 Authorized Budget $1,000,000 Planned Cost = $300k Actual Costs = $300k Quarter 1 Quarter 2 Quarter 3 Quarter 4 A fairly typical, but unfortunately potentially deceptive, approach to understanding project cost performance.
  • 17. Traditional Cost Management 250 500 750 Authorized Budget $1,000,000 Planned Cost = $300k Actual Costs = $300k Quarter 1 Quarter 2 Quarter 3 Quarter 4 In fact, looking at the data as displayed nobody could really determine the projects true cost performance. To Determine the project’s true cost performance, one would need to compare the physical schedule results in the same format as the cost displays.
  • 18. On the Road to EV • There lies the beauty of Earned Value “EV”. • EV project management requires an integrated baseline plan which relates the defined scope of work to the budgeted costs. • Let us now contrast the display with an earned value performance chart. • Here the total budget of $1,000,000 will be made up from detailed bottom- up planning that allows for performance to be measure throughout the life of the project. • There are ten milestones to be accomplished, and each milestone will have a weighted value of $100,000. Each time a milestone is completed the project will earn $100,000.
  • 19. Earned value performance 1st Quarter. 250 500 750 Authorized Budget $1,000,000 Planned Cost = $300k Actual Costs = $300k Quarter 1 Quarter 2 Quarter 3 Quarter 4
  • 20. Earned value performance 1st Quarter. 250 500 750 Authorized Budget $1,000,000 Planned Value = $300k Actual Costs = $300k Quarter 1 Quarter 2 Quarter 3 Quarter 4 Earned Value = $200k This chart reflects actual physical earned value of only two milestones completed, representing an earned value of $200,000, against the planned value of $300,000
  • 21. • The earned value also consist of two elements • The scheduled work which was completed • The original budget for the completed work.
  • 22. Earned value performance 1st Quarter. 250 500 750 Authorized Budget $1,000,000 Planned Value = $300k Actual Costs = $300k Quarter 1 Quarter 2 Quarter 3 Quarter 4 Earned Value = $200k We can immediately see that the project is running behind the work it set out to do during the first quarter. It had planned to accomplish $300,000 in and work, but had accomplished only $200,000.
  • 23. Earned value performance 1st Quarter. 250 500 750 Authorized Budget $1,000,000 Planned Value = $300k Actual Costs = $300k Quarter 1 Quarter 2 Quarter 3 Quarter 4 Earned Value = $200k The project is running a negative $100,000 schedule variance. Which is defined as the earned value ($200,000) less the planned value ($300,000) which equals schedule variance (-$100,000)
  • 24. Earned value performance 1st Quarter. 250 500 750 Authorized Budget $1,000,000 Planned Value = $300k Actual Costs = $300k Quarter 1 Quarter 2 Quarter 3 Quarter 4 Earned Value = $200k Also the cost actuals of $300,000, an amount greater than the earned value of physical work performed of $200,000.
  • 25. Earned value performance 1st Quarter. 250 500 750 Authorized Budget $1,000,000 Planned Value = $300k Actual Costs = $300k Quarter 1 Quarter 2 Quarter 3 Quarter 4 Earned Value = $200k Conclusion The project has spent $300,000 in actual costs to achieve only $200,000 worth of earned value. An earned value cost variance is defined as the earned value accomplished ($200,000) less the actual costs ($300,000) which equals the cost variance (- $100,000).
  • 26. Earned value performance 1st Quarter. 250 500 750 Authorized Budget $1,000,000 Planned Value = $300k Actual Costs = $300k Quarter 1 Quarter 2 Quarter 3 Quarter 4 Earned Value = $200k This is an “Overrun” of costs. This project can be said to be running a negative $100,000 cost variance.
  • 27. Earned value performance 1st Quarter. 250 500 750 Authorized Budget $1,000,000 Planned Value = $300k Actual Costs = $300k Quarter 1 Quarter 2 Quarter 3 Quarter 4 Earned Value = $200k Thus the delicate relationships reflected with these actual cost & schedule performance relationships can now be used to predict the final costs & schedule results of the project.
  • 28. Earned value performance 1st Quarter. 250 500 750 Authorized Budget $1,000,000 Planned Value = $300k Actual Costs = $300k Quarter 1 Quarter 2 Quarter 3 Quarter 4 Earned Value = $200k The Project is in trouble. But one could not have discerned that condition using a traditional cost management approach.
  • 29. Earned value performance 1st Quarter. 250 500 750 Authorized Budget $1,000,000 Planned Value = $300k Actual Costs = $300k Quarter 1 Quarter 2 Quarter 3 Quarter 4 Earned Value = $200k It is only when earned value brings in the three dimensions of performance that we can tell that the project is experiencing problems. Such issues need to be addressed immediately in order to avoid adverse cost overruns & schedule slippages.
  • 30. The fundamental differences Traditional Project Cost Management Planned Funds = $300K Actual Costs = $300K Variance from an expenditure plan = (OK) With a plan versus actual costs comparison there is no way to ascertain how much of the physical work has been accomplished. Only has significance as a reflection of whether a project has stayed with the funds authorized by management.
  • 31. The fundamental differences Traditional Project Cost Management Planned Funds = $300K Actual Costs = $300K Variance from an expenditure plan = (OK) This only reflects funding performance, not true cost performance. Yet most projects today typically represent their cost performance using similar reporting.
  • 32. The fundamental differences Traditional Project Cost Management Planned Funds = $300K Actual Costs = $300K Earned Value Project Management Planned Value = $300K Earned Value = $200K Actual Costs = $300K Variance from an expenditure plan = (OK) Variance from the planned schedule =(-$100K) The “true” cost variance = (-$100K) Now looking at Project performance using EV. This displays three dimensions of data: 1) The planned value of the physical work authorized 2) The earned value of the physical work accomplished 3) The actual costs incurred to accomplish the earned value.
  • 33. The fundamental differences Traditional Project Cost Management Planned Funds = $300K Actual Costs = $300K Earned Value Project Management Planned Value = $300K Earned Value = $200K Actual Costs = $300K Variance from an expenditure plan = (OK) Variance from the planned schedule =(-$100K) The “true” cost variance = (-$100K) As you can see 2 critical variances may be ascertained. 1) The project is experiencing a negative schedule variance of - $100,000 from its planned work. Put in another way one third of the work the project set out to do was not accomplished in the timeframe being measure. The team is clearly behind its planned schedule.
  • 34. The fundamental differences Traditional Project Cost Management Planned Funds = $300K Actual Costs = $300K Earned Value Project Management Planned Value = $300K Earned Value = $200K Actual Costs = $300K Variance from an expenditure plan = (OK) Variance from the planned schedule =(-$100K) The “true” cost variance = (-$100K) The Schedule variance in conjunction with Critical Path Method (CPM), provides invaluable insights into the true schedule status of the project.
  • 35. The fundamental differences Traditional Project Cost Management Planned Funds = $300K Actual Costs = $300K Earned Value Project Management Planned Value = $300K Earned Value = $200K Actual Costs = $300K Variance from an expenditure plan = (OK) Variance from the planned schedule =(-$100K) The “true” cost variance = (-$100K) The second critical variance 2) Is the relation ship of value of the work done, the earned value, to the funds expended to accomplish the work. A total of $300,000 was expended to accomplish only $200,000 worth of work. Thus the project has experienced a cost overrun of minus $100,000 for the work performed to date.
  • 36. The fundamental differences Traditional Project Cost Management Planned Funds = $300K Actual Costs = $300K Earned Value Project Management Planned Value = $300K Earned Value = $200K Actual Costs = $300K Variance from an expenditure plan = (OK) Variance from the planned schedule =(-$100K) The “true” cost variance = (-$100K) This negative cost trend is of critical importance to the project, for experience has indicated that such overruns of costs do not correct themselves over time. In fact, cost overruns tend to get worse.
  • 37. The fundamental differences Traditional Project Cost Management Planned Funds = $300K Actual Costs = $300K Earned Value Project Management Planned Value = $300K Earned Value = $200K Actual Costs = $300K Variance from an expenditure plan = (OK) Variance from the planned schedule =(-$100K) The “true” cost variance = (-$100K) The actual cost & schedule performance results can also be used independently or jointly forecast the final results of the project with amazing accuracy.
  • 38. Project Manager Needs to know • As a given point in time, we need answers to these questions: 1. What work is scheduled to have been completed? 2. What was the cost estimate for the work scheduled? 3. What work has been accomplished? 4. What was the cost estimate of the completed work? 5. What have our costs been? 6. What are the variances?
  • 39. Project Manager Needs to know Planned Value Earned Value Actual Cost CPI & SPI • As a given point in time, we need answers to these questions: 1. What work is scheduled to have been completed? 2. What was the cost estimate for the work scheduled? 3. What work has been accomplished? 4. What was the cost estimate of the completed work? 5. What have our costs been? 6. What are the variances?
  • 40. THE THREE DIFFERENT TYPES OF PROJECT MANAGEMENT OFFICES • 1. Supportive PMO • 2. Controlling PMO • 3. Directive PMO
  • 41. 1. Supportive PMO • The Supportive PMO generally provides support in the form of on- demand expertise, templates, best practices, access to information and expertise on other projects, and the like. This can work in an organisation where projects are done successfully in a loosely controlled manner and where additional control is deemed unnecessary. Also, if the objective is to have a sort of "clearing-house" of project management information across the enterprise to be used freely by project managers, then the Supportive PMO is the right type.
  • 42. 2. Controlling PMO • In organisations where there is a desire to "rein in" the activities, processes, procedures, documentation, and more - a controlling PMO can accomplish that. Not only does the organisation provide support, but it also requires that the support be used. Requirements might include adoption of specific methodologies, templates, forms, conformance to governance, and application of other PMO controlled sets of rules. In addition, project offices might need to pass regular reviews by the controlling PMO, and this may represent a risk factor on the project. This works if a) there is a clear case that compliance with project management organisation offerings will bring improvements in the organisation and how it executes on projects, and b) the PMO has sufficient executive support to stand behind the controls the PMO puts in place.
  • 43. 3. Directive PMO • This type goes beyond control and actually "takes over" the projects by providing the project management experience and resources to manage the project. As organisations undertake projects, professional project managers from the PMO are assigned to the projects. This injects a great deal of professionalism into the projects, and, since each of the project managers originates and reports back to the directive PMO, it guarantees a high level of consistency of practice across all projects. This is effective in larger organisations that often matrix out support in various areas, and where this setup would fit the culture. • The best type is very specific to the organisation, culture, and history of what works and what does not. But the objectives are - more or less - to: • Implement a common methodology • Standardise terminology • Introduce effective repeatable project management processes • Provide common supporting tools • Ultimately, the objective is to improve levels of project success within the organisation
  • 44. EIA-748 Guidelines • Guideline 1 – Define Work Scope (WBS) .................................................................... 4 • Guideline 2 – Define Project Organization (OBS) ........................................................ 5 • Guideline 3 – Integrate Processes .............................................................................. 6 • Guideline 4 – Identify Overhead Management ............................................................ 7 • Guideline 5 – Integrate WBS/OBS to Create Control Accounts ................................... 8 • 2.2 Planning, Scheduling, and Budgeting .......................................................................10 • Guideline 6 – Schedule with Network Logic .............................................................. 10 • Guideline 7 – Set Measurement Indicators ............................................................... 12 • Guideline 8 – Establish Budgets for Authorized Work ............................................... 14 • Guideline 9 – Budget by Cost Elements .................................................................... 18 • Guideline 10 – Create Work Packages, Planning Packages ..................................... 20 • Guideline 11 – Sum Detail Budgets to Control Account ............................................ 22 • Guideline 12 – LOE Planning and Control ................................................................. 23 • Guideline 13 – Establish Overhead Budgets ............................................................. 24 • Guideline 14 – Identify Management Reserve and Undistributed Budget .................. 26 • Guideline 15 – Reconcile to Target Cost Goal .......................................................... 28
  • 45. EIA-748 Guidelines • Accounting Considerations • Guideline 16 – Record Direct Costs • Guideline 17 – Summarize Direct Costs by WBS Elements ...................................... 30 • Guideline 18 – Summarize Direct Costs by OBS Elements ....................................... 31 • Guideline 19 – Record/Allocate Indirect Costs .......................................................... 32 • Guideline 20 – Identify Unit and Lot Costs ................................................................ 33 • Guideline 21 – Track and Report Material Costs and Quantities ............................... 34 • 2.4 Analysis and Management Reports ..........................................................................36 • Guideline 22 – Calculate Schedule Variance and Cost Variance .............................. 36 • Guideline 23 – Identify Significant Variances for Analysis ......................................... 37 • Guideline 24 – Analyze Indirect Cost Variances ........................................................ 39 • Guideline 25 – Summarize Information for Management .......................................... 40 • Guideline 26 – Implement Corrective Actions............................................................ 41 • Guideline 27 – Revise Estimate at Completion (EAC) ............................................... 42 • 2.5 Revisions and Data Maintenance ..............................................................................44 • Guideline 28 – Incorporate Changes in a Timely Manner .......................................... 44
  • 46. EIA-748 Guidelines • Guideline 29 – Reconcile Current to Prior Budgets • Guideline 30 – Control Retroactive Changes • Guideline 31 – Prevent Unauthorized Revisions • Guideline 32 – Document PMB Changes
  • 47. Earned value cost & schedule performance indices: The SPI and CPI
  • 48. • To be determined.,.,
  • 49. References used for presentation • Articles on Earned Value • Earned Value Project Management – Fourth Edition • AAICP