How to reduce
“Changeover time loss”
and improve plant utilization
www.winningmindssolutions.com
• Definition of “Changeover Time Loss”
• Business and Operational impact of “Changeover Time Loss”
• Concept of “SMED”( Single Minute Exchange Dies)
• Process steps in “SMED ” execution
• Case study Examples
Learning Objectives…
www.winningmindssolutions.com
Last good piece of
product A
First good piece of
product B
Changeover Time=3.5 hrs
6.15 am 10.45 am
Changeover Time-Definition
The time elapsed between when the last good piece of product A comes off and the first
good piece of product B starts.
www.winningmindssolutions.com
Typical Types of changeover in Operations
 Die Changeover in Press, Casting ,Moulding machines
Tool insert change in CNC, SPM machines
Colour change in Paint and Powder coating
 Model changeover in Assembly
All changeover leads to Equipment utilization loss in turn affects the
delivery, productivity and cost
www.winningmindssolutions.com
Significance of changeover loss..
 Increase in variety
Pressure on inventory reduction
Speed / Flexibility expectation
 Profitability through Utilization
Improvement
•Increase in lead-time ,managing
through WIP & increase in working
capital
•Large batch size –side effect on quality
issues ,space, handling etc
•Safety issues due to non standardized
process
•Low flexibility for servicing multiple
product
www.winningmindssolutions.com
Background & History
• SMED concept by Shigeo Shingo, Japanese consultant
• Concepts originated around 1950-60’s and internalized in Toyota
• Continuously evolved from SMED to OTED
www.winningmindssolutions.com
World-Class Quick Changeover Methodologies…
SMED: Single Minute Exchange of Die
Concept that says all setups should and can take less than 10 minutes
OTED: One Touch Exchange of Die
Concept that says all setups should and can take less than 100 seconds!
www.winningmindssolutions.com
Traditional vs SMED based
Changeover
Traditional changeover
SMED based changeover
Say 20 min per Tyre
Say 20 sec for four Tyre
www.winningmindssolutions.com
Traditional Changeover Process…
• Preparation of tools / dies and ensure in working condition
• Move to machine
• Removal of dies from machine
• Placing of dies
• Setting all process control
• First trial
• Adjustment
• Take trial
• Final good piece production
More of “Sequential”
Inconsistency in Process &Time
More Adjustment and Trial
www.winningmindssolutions.com
SMED Changeover Process…
• Emphasis more on parallel activities than sequential
• Changeover process by set of cross functional experts than one
• Predefined work and collaboration of cross functional team
• Focus more on housekeeping and visual management practices
• Standardization as much as possible
www.winningmindssolutions.com
SMED Methodology
Existing changeover process
Improvement steps
Observe and Record the elements
Identify Internal and External Elements
Convert Internal elements to External
elements
Improve External Elements
Improve Internal Elements
Document Internal & External
Elements and Standardize
www.winningmindssolutions.com
Observe and Record Elements…
 Video recording is ideal to understand and explain
Sample Elemental Recording data
Time on Element description Duration (Min)
9.15 am Machine stopped for die setting 0
9.15-9.30 am Operator is waiting for supervisor's instruction 15
9.30 am Temporary operator to clean flashes from machines/ die 2
9.32 am coolant hose removal 5
9.37 am
Temporary operator
stuck with removing hose removal ; need assistance 2
9.39 am Senior employee came in to assist 1
9.40 am Bring Chain / hook to lift 2
www.winningmindssolutions.com
Identify Internal and External Elements
Internal elements:
Activities that must be performed while the machine is stopped
Example :
 Placing the die inside the bed
Tightening the die with machine bed
External elements:
Activities that can be performed while the machine is running
Example :
Positioning the crane and tools in front of the machine for loading
www.winningmindssolutions.com
Identify Internal and External Elements (Example)
Remove 4 off bolts on rear side using spanner / pipe rod 5 Internal
Remove 4 off bolts on front side using spanner / pipe rod 3 Internal
completed removing ejector pin 4 Internal
Lifting starts Internal
perm employee removes bolt from machine guide ways 2 Internal
maintenance team checks on sprayer 10 Internal
CL removes flash from bolt guide ways and air clean 5 Internal
change plunger / sleeve by perm employee Internal
5 times went to get wooden block , screw driver , ejector rod , waste cloth 14 External
filing and removing flashes from plunger block - 1 min 1 External
completes fixing plunger block 1 Internal
Maintenance team removes sprayer 6 Internal
fixing plunge block with support of CL and remove wooden block 1 Internal
perm employees tries to fix hook in cyl head die which was kept in hand pallet 13 Internal
it is loose and call die maintenance person External
remove core / cavity die from hand pallet and joining both External
die maintenance person air clean the screw hole External
fixes 2 eye bolt in the die and connect with chain 2 Internal
www.winningmindssolutions.com
Convert Internal elements to External
Elements
Convert as much as possible Internal Elements into External Elements
 Proper Housekeeping –Location for everything
Eliminate Searching
 Pre Arrangement of tools / dies
 Spares Management
 All experts –Being near to machine when changeover takes place
Make Visual marks / identification as much as possible and avoid trials
www.winningmindssolutions.com
Improve External Elements
 Housekeeping-Location for all items
Visual Identification for all items
Colour Coding
Standard set up process
Checklist for each die setting
www.winningmindssolutions.com
Improve Internal Elements
• Create Parallel steps (eg removing bolts)
• Reduce complexity and eliminate waste
 Use functional fixtures and jigs
• levered or one-turn fasteners
• interlocking wedge or slot
 Eliminate adjustments
• use angle and flat
• use preset pins, guides, notches etc.
www.winningmindssolutions.com
Look for opportunities in Internal Elements..
www.winningmindssolutions.com
Document and standardize ..
 Create Checklist for each die change
 Document the process steps
Train and create more setting experts
www.winningmindssolutions.com
Case study examples
on changeover loss reduction using SMED concept
in our client’s process
www.winningmindssolutions.com
Examples of Changeover reduction in our Client's Operations
www.winningmindssolutions.com
Thank you for your Interest
To Know more about those case studies ,pl mail to us
ganesh@winningmindssolutions.com
mobile : +91 90259 33666
For Business and Life Excellence articles and case studies
pl visit website : www.winningmindssolutions.com

Weitere ähnliche Inhalte

Was ist angesagt?

How to Reduce Changeover Time and Increase Throughput
How to Reduce Changeover Time and Increase ThroughputHow to Reduce Changeover Time and Increase Throughput
How to Reduce Changeover Time and Increase ThroughputOH!Manufacturing
 
History of Lean manufacturing & TPS 14 Principal
History of Lean manufacturing & TPS 14 PrincipalHistory of Lean manufacturing & TPS 14 Principal
History of Lean manufacturing & TPS 14 PrincipalSumon Kumar Kundu
 
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSLEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSJulian Kalac P.Eng
 
SMED or Single Minute Exchange of Dies and Set-up Reduction Process
SMED or Single Minute Exchange of Dies and Set-up Reduction ProcessSMED or Single Minute Exchange of Dies and Set-up Reduction Process
SMED or Single Minute Exchange of Dies and Set-up Reduction ProcessW3 Group Canada Inc.
 
5S Workshop &Visual management - Krishna Heda
5S Workshop &Visual management - Krishna Heda5S Workshop &Visual management - Krishna Heda
5S Workshop &Visual management - Krishna Hedakrishnaheda
 
SMED - Single Minute Exchange of Dies
SMED - Single Minute Exchange of DiesSMED - Single Minute Exchange of Dies
SMED - Single Minute Exchange of Dies5S BALAMURUGAN
 
Total productive maintenance(TPM)
Total productive maintenance(TPM)Total productive maintenance(TPM)
Total productive maintenance(TPM)Md.Muzahid Khan
 
Lean Manufacturing : Concept & Overview nkchawla@gmail.com
Lean Manufacturing : Concept & Overview nkchawla@gmail.comLean Manufacturing : Concept & Overview nkchawla@gmail.com
Lean Manufacturing : Concept & Overview nkchawla@gmail.comNareshChawla
 
5S AWARNESS TRAINING PROGRAM
5S AWARNESS  TRAINING  PROGRAM5S AWARNESS  TRAINING  PROGRAM
5S AWARNESS TRAINING PROGRAMDEEPAK SAHOO
 
TPM For lean manufacturing chp3 | kobetsu kaizen for production efficiency...
TPM For lean manufacturing  chp3 |   kobetsu kaizen for production efficiency...TPM For lean manufacturing  chp3 |   kobetsu kaizen for production efficiency...
TPM For lean manufacturing chp3 | kobetsu kaizen for production efficiency...博行 門眞
 

Was ist angesagt? (20)

How to Reduce Changeover Time and Increase Throughput
How to Reduce Changeover Time and Increase ThroughputHow to Reduce Changeover Time and Increase Throughput
How to Reduce Changeover Time and Increase Throughput
 
SMED
SMEDSMED
SMED
 
History of Lean manufacturing & TPS 14 Principal
History of Lean manufacturing & TPS 14 PrincipalHistory of Lean manufacturing & TPS 14 Principal
History of Lean manufacturing & TPS 14 Principal
 
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSLEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
 
Smed simulation game_intro
Smed simulation game_introSmed simulation game_intro
Smed simulation game_intro
 
16 major losses tng
16 major losses tng16 major losses tng
16 major losses tng
 
Lean manufacturing ppt
Lean manufacturing pptLean manufacturing ppt
Lean manufacturing ppt
 
SMED or Single Minute Exchange of Dies and Set-up Reduction Process
SMED or Single Minute Exchange of Dies and Set-up Reduction ProcessSMED or Single Minute Exchange of Dies and Set-up Reduction Process
SMED or Single Minute Exchange of Dies and Set-up Reduction Process
 
5S Workshop &Visual management - Krishna Heda
5S Workshop &Visual management - Krishna Heda5S Workshop &Visual management - Krishna Heda
5S Workshop &Visual management - Krishna Heda
 
SMED - Single Minute Exchange of Dies
SMED - Single Minute Exchange of DiesSMED - Single Minute Exchange of Dies
SMED - Single Minute Exchange of Dies
 
Single Minute Exchange of Dies
Single Minute Exchange of DiesSingle Minute Exchange of Dies
Single Minute Exchange of Dies
 
5 Steps to implementing Lean
5  Steps to implementing Lean5  Steps to implementing Lean
5 Steps to implementing Lean
 
SMED Kaizen Event
SMED Kaizen EventSMED Kaizen Event
SMED Kaizen Event
 
SMED Final
SMED FinalSMED Final
SMED Final
 
Total productive maintenance(TPM)
Total productive maintenance(TPM)Total productive maintenance(TPM)
Total productive maintenance(TPM)
 
TPM Implementation Strategy
TPM Implementation StrategyTPM Implementation Strategy
TPM Implementation Strategy
 
Lean Manufacturing : Concept & Overview nkchawla@gmail.com
Lean Manufacturing : Concept & Overview nkchawla@gmail.comLean Manufacturing : Concept & Overview nkchawla@gmail.com
Lean Manufacturing : Concept & Overview nkchawla@gmail.com
 
5S AWARNESS TRAINING PROGRAM
5S AWARNESS  TRAINING  PROGRAM5S AWARNESS  TRAINING  PROGRAM
5S AWARNESS TRAINING PROGRAM
 
OEE
OEEOEE
OEE
 
TPM For lean manufacturing chp3 | kobetsu kaizen for production efficiency...
TPM For lean manufacturing  chp3 |   kobetsu kaizen for production efficiency...TPM For lean manufacturing  chp3 |   kobetsu kaizen for production efficiency...
TPM For lean manufacturing chp3 | kobetsu kaizen for production efficiency...
 

Andere mochten auch

Reduce SMT Changeover Time
Reduce SMT Changeover TimeReduce SMT Changeover Time
Reduce SMT Changeover TimeDamian Denis
 
Improving SMT Equipment Utilization
Improving SMT Equipment UtilizationImproving SMT Equipment Utilization
Improving SMT Equipment Utilizationimdiven
 
Improve SMT Labor Margin Per Unit
Improve SMT Labor Margin Per UnitImprove SMT Labor Margin Per Unit
Improve SMT Labor Margin Per UnitDamian Denis
 
LEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
LEAN Setup Reduction (SMED) training for welding by JULIAN KALACLEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
LEAN Setup Reduction (SMED) training for welding by JULIAN KALACJulian Kalac P.Eng
 
CW43-KAIZEN Elimination of Waste Motion - Vacuum Seal
CW43-KAIZEN Elimination of Waste Motion - Vacuum SealCW43-KAIZEN Elimination of Waste Motion - Vacuum Seal
CW43-KAIZEN Elimination of Waste Motion - Vacuum SealDamian Denis
 
Smed Training Model Trainer Instructions[1]
Smed Training Model Trainer Instructions[1]Smed Training Model Trainer Instructions[1]
Smed Training Model Trainer Instructions[1]exerciselean
 
SMED Setup & Lead Time Reduction
SMED Setup & Lead Time ReductionSMED Setup & Lead Time Reduction
SMED Setup & Lead Time ReductionAnand Subramaniam
 
Lean Manufacturing SMED
Lean Manufacturing SMEDLean Manufacturing SMED
Lean Manufacturing SMEDLean Sigma
 
Schneider Case Study Challenge
Schneider Case Study ChallengeSchneider Case Study Challenge
Schneider Case Study ChallengeNikhil Kejriwal
 
Application of smed in small scale sheet metal
Application of smed in small scale sheet metalApplication of smed in small scale sheet metal
Application of smed in small scale sheet metalNikunj Rana
 
SMED - Single Minute Exchange Died
SMED - Single Minute Exchange DiedSMED - Single Minute Exchange Died
SMED - Single Minute Exchange DiedFigliolino Venanzio
 
CII Tourism Fest 2013 - An International Fest on Tourism & Hospitality (.ppt ...
CII Tourism Fest 2013 - An International Fest on Tourism & Hospitality (.ppt ...CII Tourism Fest 2013 - An International Fest on Tourism & Hospitality (.ppt ...
CII Tourism Fest 2013 - An International Fest on Tourism & Hospitality (.ppt ...Confederation of Indian Industry
 

Andere mochten auch (18)

Reduce SMT Changeover Time
Reduce SMT Changeover TimeReduce SMT Changeover Time
Reduce SMT Changeover Time
 
Improving SMT Equipment Utilization
Improving SMT Equipment UtilizationImproving SMT Equipment Utilization
Improving SMT Equipment Utilization
 
Improve SMT Labor Margin Per Unit
Improve SMT Labor Margin Per UnitImprove SMT Labor Margin Per Unit
Improve SMT Labor Margin Per Unit
 
LEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
LEAN Setup Reduction (SMED) training for welding by JULIAN KALACLEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
LEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
 
Do you SMED?
Do you SMED?Do you SMED?
Do you SMED?
 
CW43-KAIZEN Elimination of Waste Motion - Vacuum Seal
CW43-KAIZEN Elimination of Waste Motion - Vacuum SealCW43-KAIZEN Elimination of Waste Motion - Vacuum Seal
CW43-KAIZEN Elimination of Waste Motion - Vacuum Seal
 
Smed Training Model Trainer Instructions[1]
Smed Training Model Trainer Instructions[1]Smed Training Model Trainer Instructions[1]
Smed Training Model Trainer Instructions[1]
 
SMED Setup & Lead Time Reduction
SMED Setup & Lead Time ReductionSMED Setup & Lead Time Reduction
SMED Setup & Lead Time Reduction
 
Lean Manufacturing SMED
Lean Manufacturing SMEDLean Manufacturing SMED
Lean Manufacturing SMED
 
Set up reduction
Set up reductionSet up reduction
Set up reduction
 
Schneider Case Study Challenge
Schneider Case Study ChallengeSchneider Case Study Challenge
Schneider Case Study Challenge
 
Application of smed in small scale sheet metal
Application of smed in small scale sheet metalApplication of smed in small scale sheet metal
Application of smed in small scale sheet metal
 
Smed
SmedSmed
Smed
 
SMED
SMED SMED
SMED
 
Providing total SMT solutions
Providing total SMT solutionsProviding total SMT solutions
Providing total SMT solutions
 
SMED - Single Minute Exchange Died
SMED - Single Minute Exchange DiedSMED - Single Minute Exchange Died
SMED - Single Minute Exchange Died
 
CII Tourism Fest 2013 - An International Fest on Tourism & Hospitality (.ppt ...
CII Tourism Fest 2013 - An International Fest on Tourism & Hospitality (.ppt ...CII Tourism Fest 2013 - An International Fest on Tourism & Hospitality (.ppt ...
CII Tourism Fest 2013 - An International Fest on Tourism & Hospitality (.ppt ...
 
Sign king smt
Sign king smtSign king smt
Sign king smt
 

Ähnlich wie How to reduce changeover loss

SMED - 6.pptx.pptx
SMED - 6.pptx.pptxSMED - 6.pptx.pptx
SMED - 6.pptx.pptxssuser820b7a
 
Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)MohammedLahssaini1
 
Chandan CIA - 2.pptx
Chandan CIA - 2.pptxChandan CIA - 2.pptx
Chandan CIA - 2.pptxVasantAmbig
 
SMED implementation on Automated Stamping Line
SMED implementation on Automated Stamping LineSMED implementation on Automated Stamping Line
SMED implementation on Automated Stamping LineParth Patel
 
Smed implementation on manufacturing stamping line
Smed implementation on manufacturing stamping lineSmed implementation on manufacturing stamping line
Smed implementation on manufacturing stamping lineDhruvShah202
 
Generic Lean Overview For Future Employer Of Alan S Desrocher
Generic Lean Overview For Future Employer Of Alan S DesrocherGeneric Lean Overview For Future Employer Of Alan S Desrocher
Generic Lean Overview For Future Employer Of Alan S DesrocherAlan Desrocher
 
Single Minute Exchange of Die
Single Minute Exchange of DieSingle Minute Exchange of Die
Single Minute Exchange of DieManish Patil
 
SPE Injection Molding Training Presentation
SPE Injection Molding Training PresentationSPE Injection Molding Training Presentation
SPE Injection Molding Training PresentationPaulsonTraining
 
Just in time and Lean systems
Just in time and Lean systemsJust in time and Lean systems
Just in time and Lean systemsAyman Aljahdali
 
Production and Operations Management
Production and Operations ManagementProduction and Operations Management
Production and Operations ManagementNishant Agrawal
 
PMTF INTERNSHIP (9 june tp 25 june-2015)
PMTF INTERNSHIP (9 june tp 25 june-2015)PMTF INTERNSHIP (9 june tp 25 june-2015)
PMTF INTERNSHIP (9 june tp 25 june-2015)Asim Aslam
 
Machining time and costs
Machining time and costsMachining time and costs
Machining time and costsendika55
 
5 s and lean manufacturing
5 s and lean manufacturing5 s and lean manufacturing
5 s and lean manufacturingNouman Ali
 
Case Studies it is sbout honfs dfsdfsdjlfksldkfj
Case Studies it is sbout honfs dfsdfsdjlfksldkfjCase Studies it is sbout honfs dfsdfsdjlfksldkfj
Case Studies it is sbout honfs dfsdfsdjlfksldkfjTeproQC
 

Ähnlich wie How to reduce changeover loss (20)

SMED - 6.pptx.pptx
SMED - 6.pptx.pptxSMED - 6.pptx.pptx
SMED - 6.pptx.pptx
 
Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)
 
Chandan CIA - 2.pptx
Chandan CIA - 2.pptxChandan CIA - 2.pptx
Chandan CIA - 2.pptx
 
SMED implementation on Automated Stamping Line
SMED implementation on Automated Stamping LineSMED implementation on Automated Stamping Line
SMED implementation on Automated Stamping Line
 
Smed implementation on manufacturing stamping line
Smed implementation on manufacturing stamping lineSmed implementation on manufacturing stamping line
Smed implementation on manufacturing stamping line
 
ie450pp4.ppt
ie450pp4.pptie450pp4.ppt
ie450pp4.ppt
 
Generic Lean Overview For Future Employer Of Alan S Desrocher
Generic Lean Overview For Future Employer Of Alan S DesrocherGeneric Lean Overview For Future Employer Of Alan S Desrocher
Generic Lean Overview For Future Employer Of Alan S Desrocher
 
SMT Sales 2011
SMT Sales 2011SMT Sales 2011
SMT Sales 2011
 
SMT 2011
SMT  2011SMT  2011
SMT 2011
 
SMT 2011
SMT 2011SMT 2011
SMT 2011
 
Single Minute Exchange of Die
Single Minute Exchange of DieSingle Minute Exchange of Die
Single Minute Exchange of Die
 
SPE Injection Molding Training Presentation
SPE Injection Molding Training PresentationSPE Injection Molding Training Presentation
SPE Injection Molding Training Presentation
 
Resume 2.0
Resume 2.0Resume 2.0
Resume 2.0
 
Resume 2.0
Resume 2.0Resume 2.0
Resume 2.0
 
Just in time and Lean systems
Just in time and Lean systemsJust in time and Lean systems
Just in time and Lean systems
 
Production and Operations Management
Production and Operations ManagementProduction and Operations Management
Production and Operations Management
 
PMTF INTERNSHIP (9 june tp 25 june-2015)
PMTF INTERNSHIP (9 june tp 25 june-2015)PMTF INTERNSHIP (9 june tp 25 june-2015)
PMTF INTERNSHIP (9 june tp 25 june-2015)
 
Machining time and costs
Machining time and costsMachining time and costs
Machining time and costs
 
5 s and lean manufacturing
5 s and lean manufacturing5 s and lean manufacturing
5 s and lean manufacturing
 
Case Studies it is sbout honfs dfsdfsdjlfksldkfj
Case Studies it is sbout honfs dfsdfsdjlfksldkfjCase Studies it is sbout honfs dfsdfsdjlfksldkfj
Case Studies it is sbout honfs dfsdfsdjlfksldkfj
 

Mehr von Winning Minds Solutions

Holistic HR processes in small, emerging (sme's) organization
Holistic HR processes in small, emerging (sme's) organizationHolistic HR processes in small, emerging (sme's) organization
Holistic HR processes in small, emerging (sme's) organizationWinning Minds Solutions
 
Wealth creation through lean manufacturing concepts, tools and techniques
Wealth creation through  lean manufacturing  concepts, tools and techniquesWealth creation through  lean manufacturing  concepts, tools and techniques
Wealth creation through lean manufacturing concepts, tools and techniquesWinning Minds Solutions
 
People development and engagement in SME organizations-Perspective sharing
People development  and engagement in SME organizations-Perspective sharing People development  and engagement in SME organizations-Perspective sharing
People development and engagement in SME organizations-Perspective sharing Winning Minds Solutions
 
Application of ergonomics for SME workplace productivity and safety improvements
Application of ergonomics for SME workplace productivity and safety improvementsApplication of ergonomics for SME workplace productivity and safety improvements
Application of ergonomics for SME workplace productivity and safety improvementsWinning Minds Solutions
 
Holistic Lean system thinking approach for business profitability
Holistic Lean system thinking approach for business profitabilityHolistic Lean system thinking approach for business profitability
Holistic Lean system thinking approach for business profitabilityWinning Minds Solutions
 
Structured problem solving methodology,Tools and Techniques
Structured problem solving methodology,Tools and TechniquesStructured problem solving methodology,Tools and Techniques
Structured problem solving methodology,Tools and TechniquesWinning Minds Solutions
 
7 principles for sustainable business transformation
7 principles for sustainable business transformation7 principles for sustainable business transformation
7 principles for sustainable business transformationWinning Minds Solutions
 

Mehr von Winning Minds Solutions (8)

Holistic HR processes in small, emerging (sme's) organization
Holistic HR processes in small, emerging (sme's) organizationHolistic HR processes in small, emerging (sme's) organization
Holistic HR processes in small, emerging (sme's) organization
 
Wisdom on Managing Growth
Wisdom on Managing GrowthWisdom on Managing Growth
Wisdom on Managing Growth
 
Wealth creation through lean manufacturing concepts, tools and techniques
Wealth creation through  lean manufacturing  concepts, tools and techniquesWealth creation through  lean manufacturing  concepts, tools and techniques
Wealth creation through lean manufacturing concepts, tools and techniques
 
People development and engagement in SME organizations-Perspective sharing
People development  and engagement in SME organizations-Perspective sharing People development  and engagement in SME organizations-Perspective sharing
People development and engagement in SME organizations-Perspective sharing
 
Application of ergonomics for SME workplace productivity and safety improvements
Application of ergonomics for SME workplace productivity and safety improvementsApplication of ergonomics for SME workplace productivity and safety improvements
Application of ergonomics for SME workplace productivity and safety improvements
 
Holistic Lean system thinking approach for business profitability
Holistic Lean system thinking approach for business profitabilityHolistic Lean system thinking approach for business profitability
Holistic Lean system thinking approach for business profitability
 
Structured problem solving methodology,Tools and Techniques
Structured problem solving methodology,Tools and TechniquesStructured problem solving methodology,Tools and Techniques
Structured problem solving methodology,Tools and Techniques
 
7 principles for sustainable business transformation
7 principles for sustainable business transformation7 principles for sustainable business transformation
7 principles for sustainable business transformation
 

Kürzlich hochgeladen

About Entrepreneur ELON MUSK .pptx...
About  Entrepreneur  ELON  MUSK .pptx...About  Entrepreneur  ELON  MUSK .pptx...
About Entrepreneur ELON MUSK .pptx...lahiruherath654
 
Authentic No 1 Amil Baba In Pakistan Amil Baba In Faisalabad Amil Baba In Kar...
Authentic No 1 Amil Baba In Pakistan Amil Baba In Faisalabad Amil Baba In Kar...Authentic No 1 Amil Baba In Pakistan Amil Baba In Faisalabad Amil Baba In Kar...
Authentic No 1 Amil Baba In Pakistan Amil Baba In Faisalabad Amil Baba In Kar...Authentic No 1 Amil Baba In Pakistan
 
Report about the AHIABGA-UnityNet UNDRIPDay / Earth-Day 2024 Gathering in Mar...
Report about the AHIABGA-UnityNet UNDRIPDay / Earth-Day 2024 Gathering in Mar...Report about the AHIABGA-UnityNet UNDRIPDay / Earth-Day 2024 Gathering in Mar...
Report about the AHIABGA-UnityNet UNDRIPDay / Earth-Day 2024 Gathering in Mar...LHelferty
 
Viet Nam Inclusive Business Accreditation System
Viet Nam Inclusive Business Accreditation SystemViet Nam Inclusive Business Accreditation System
Viet Nam Inclusive Business Accreditation SystemTri Dung, Tran
 
(8264348440) 🔝 Call Girls In Babarpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Babarpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Babarpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Babarpur 🔝 Delhi NCRsoniya singh
 
(8264348440) 🔝 Call Girls In Safdarjung Enclave 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Safdarjung Enclave 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Safdarjung Enclave 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Safdarjung Enclave 🔝 Delhi NCRsoniya singh
 
Smart Traffic Management System presentation
Smart Traffic Management System presentationSmart Traffic Management System presentation
Smart Traffic Management System presentationFareeyaFaisal
 
办昆士兰大学UQ毕业证书/成绩单GPA修改 - 留学买假毕业证
办昆士兰大学UQ毕业证书/成绩单GPA修改 - 留学买假毕业证办昆士兰大学UQ毕业证书/成绩单GPA修改 - 留学买假毕业证
办昆士兰大学UQ毕业证书/成绩单GPA修改 - 留学买假毕业证0622mpom
 
Entrepreneur street first Edition is now out
Entrepreneur street first Edition is now outEntrepreneur street first Edition is now out
Entrepreneur street first Edition is now outentrepreneur street
 
(8264348440) 🔝 Call Girls In Green Park 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Green Park 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Green Park 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Green Park 🔝 Delhi NCRsoniya singh
 
Model Call Girl in Bawana Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Bawana Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Bawana Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Bawana Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Delhi Munirka 🔝 Call Girls Service 🔝 ( 8264348440 ) unlimited hard sex call girl
Delhi Munirka 🔝 Call Girls Service 🔝 ( 8264348440 ) unlimited hard sex call girlDelhi Munirka 🔝 Call Girls Service 🔝 ( 8264348440 ) unlimited hard sex call girl
Delhi Munirka 🔝 Call Girls Service 🔝 ( 8264348440 ) unlimited hard sex call girlsoniya singh
 
Call Girls At-( Nearby )-Bhikaji Cama Place, Delhi | ⑧③77⓿⑧76⓿7
Call Girls At-( Nearby )-Bhikaji Cama Place, Delhi | ⑧③77⓿⑧76⓿7Call Girls At-( Nearby )-Bhikaji Cama Place, Delhi | ⑧③77⓿⑧76⓿7
Call Girls At-( Nearby )-Bhikaji Cama Place, Delhi | ⑧③77⓿⑧76⓿7dollysharma2066
 
Guwahati Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Guwahati Call Girls 7001305949 WhatsApp Number 24x7 Best ServicesGuwahati Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Guwahati Call Girls 7001305949 WhatsApp Number 24x7 Best Servicesnajka9823
 
Call Girls in Tilak Nagar (DELHI-) 8377877756 Call Girls Service
Call Girls in Tilak Nagar (DELHI-) 8377877756 Call Girls ServiceCall Girls in Tilak Nagar (DELHI-) 8377877756 Call Girls Service
Call Girls in Tilak Nagar (DELHI-) 8377877756 Call Girls Servicedollysharma2066
 
(8264348440) 🔝 Call Girls In Sriniwaspuri 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Sriniwaspuri 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Sriniwaspuri 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Sriniwaspuri 🔝 Delhi NCRsoniya singh
 

Kürzlich hochgeladen (20)

About Entrepreneur ELON MUSK .pptx...
About  Entrepreneur  ELON  MUSK .pptx...About  Entrepreneur  ELON  MUSK .pptx...
About Entrepreneur ELON MUSK .pptx...
 
Authentic No 1 Amil Baba In Pakistan Amil Baba In Faisalabad Amil Baba In Kar...
Authentic No 1 Amil Baba In Pakistan Amil Baba In Faisalabad Amil Baba In Kar...Authentic No 1 Amil Baba In Pakistan Amil Baba In Faisalabad Amil Baba In Kar...
Authentic No 1 Amil Baba In Pakistan Amil Baba In Faisalabad Amil Baba In Kar...
 
Why Powderless DTF Printer is T-shirt Printing Game Changer.pptx
Why Powderless DTF Printer is T-shirt Printing Game Changer.pptxWhy Powderless DTF Printer is T-shirt Printing Game Changer.pptx
Why Powderless DTF Printer is T-shirt Printing Game Changer.pptx
 
Report about the AHIABGA-UnityNet UNDRIPDay / Earth-Day 2024 Gathering in Mar...
Report about the AHIABGA-UnityNet UNDRIPDay / Earth-Day 2024 Gathering in Mar...Report about the AHIABGA-UnityNet UNDRIPDay / Earth-Day 2024 Gathering in Mar...
Report about the AHIABGA-UnityNet UNDRIPDay / Earth-Day 2024 Gathering in Mar...
 
Viet Nam Inclusive Business Accreditation System
Viet Nam Inclusive Business Accreditation SystemViet Nam Inclusive Business Accreditation System
Viet Nam Inclusive Business Accreditation System
 
(8264348440) 🔝 Call Girls In Babarpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Babarpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Babarpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Babarpur 🔝 Delhi NCR
 
(8264348440) 🔝 Call Girls In Safdarjung Enclave 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Safdarjung Enclave 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Safdarjung Enclave 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Safdarjung Enclave 🔝 Delhi NCR
 
young call girls in kailash Nagar, 🔝 9953056974 🔝 escort Service
young call girls in kailash Nagar, 🔝 9953056974 🔝 escort Serviceyoung call girls in kailash Nagar, 🔝 9953056974 🔝 escort Service
young call girls in kailash Nagar, 🔝 9953056974 🔝 escort Service
 
Smart Traffic Management System presentation
Smart Traffic Management System presentationSmart Traffic Management System presentation
Smart Traffic Management System presentation
 
办昆士兰大学UQ毕业证书/成绩单GPA修改 - 留学买假毕业证
办昆士兰大学UQ毕业证书/成绩单GPA修改 - 留学买假毕业证办昆士兰大学UQ毕业证书/成绩单GPA修改 - 留学买假毕业证
办昆士兰大学UQ毕业证书/成绩单GPA修改 - 留学买假毕业证
 
Entrepreneur street first Edition is now out
Entrepreneur street first Edition is now outEntrepreneur street first Edition is now out
Entrepreneur street first Edition is now out
 
Pakistani Jumeirah Call Girls # +971559085003 # Pakistani Call Girls In Jumei...
Pakistani Jumeirah Call Girls # +971559085003 # Pakistani Call Girls In Jumei...Pakistani Jumeirah Call Girls # +971559085003 # Pakistani Call Girls In Jumei...
Pakistani Jumeirah Call Girls # +971559085003 # Pakistani Call Girls In Jumei...
 
(8264348440) 🔝 Call Girls In Green Park 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Green Park 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Green Park 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Green Park 🔝 Delhi NCR
 
Model Call Girl in Bawana Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Bawana Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Bawana Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Bawana Delhi reach out to us at 🔝8264348440🔝
 
Delhi Munirka 🔝 Call Girls Service 🔝 ( 8264348440 ) unlimited hard sex call girl
Delhi Munirka 🔝 Call Girls Service 🔝 ( 8264348440 ) unlimited hard sex call girlDelhi Munirka 🔝 Call Girls Service 🔝 ( 8264348440 ) unlimited hard sex call girl
Delhi Munirka 🔝 Call Girls Service 🔝 ( 8264348440 ) unlimited hard sex call girl
 
Call Girls At-( Nearby )-Bhikaji Cama Place, Delhi | ⑧③77⓿⑧76⓿7
Call Girls At-( Nearby )-Bhikaji Cama Place, Delhi | ⑧③77⓿⑧76⓿7Call Girls At-( Nearby )-Bhikaji Cama Place, Delhi | ⑧③77⓿⑧76⓿7
Call Girls At-( Nearby )-Bhikaji Cama Place, Delhi | ⑧③77⓿⑧76⓿7
 
Guwahati Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Guwahati Call Girls 7001305949 WhatsApp Number 24x7 Best ServicesGuwahati Call Girls 7001305949 WhatsApp Number 24x7 Best Services
Guwahati Call Girls 7001305949 WhatsApp Number 24x7 Best Services
 
Call Girls in Tilak Nagar (DELHI-) 8377877756 Call Girls Service
Call Girls in Tilak Nagar (DELHI-) 8377877756 Call Girls ServiceCall Girls in Tilak Nagar (DELHI-) 8377877756 Call Girls Service
Call Girls in Tilak Nagar (DELHI-) 8377877756 Call Girls Service
 
(8264348440) 🔝 Call Girls In Sriniwaspuri 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Sriniwaspuri 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Sriniwaspuri 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Sriniwaspuri 🔝 Delhi NCR
 
Hot Sexy call girls in Rajouri Garden🔝 9953056974 🔝 Delhi escort Service
Hot Sexy call girls in  Rajouri Garden🔝 9953056974 🔝 Delhi escort ServiceHot Sexy call girls in  Rajouri Garden🔝 9953056974 🔝 Delhi escort Service
Hot Sexy call girls in Rajouri Garden🔝 9953056974 🔝 Delhi escort Service
 

How to reduce changeover loss

  • 1. How to reduce “Changeover time loss” and improve plant utilization
  • 2. www.winningmindssolutions.com • Definition of “Changeover Time Loss” • Business and Operational impact of “Changeover Time Loss” • Concept of “SMED”( Single Minute Exchange Dies) • Process steps in “SMED ” execution • Case study Examples Learning Objectives…
  • 3. www.winningmindssolutions.com Last good piece of product A First good piece of product B Changeover Time=3.5 hrs 6.15 am 10.45 am Changeover Time-Definition The time elapsed between when the last good piece of product A comes off and the first good piece of product B starts.
  • 4. www.winningmindssolutions.com Typical Types of changeover in Operations  Die Changeover in Press, Casting ,Moulding machines Tool insert change in CNC, SPM machines Colour change in Paint and Powder coating  Model changeover in Assembly All changeover leads to Equipment utilization loss in turn affects the delivery, productivity and cost
  • 5. www.winningmindssolutions.com Significance of changeover loss..  Increase in variety Pressure on inventory reduction Speed / Flexibility expectation  Profitability through Utilization Improvement •Increase in lead-time ,managing through WIP & increase in working capital •Large batch size –side effect on quality issues ,space, handling etc •Safety issues due to non standardized process •Low flexibility for servicing multiple product
  • 6. www.winningmindssolutions.com Background & History • SMED concept by Shigeo Shingo, Japanese consultant • Concepts originated around 1950-60’s and internalized in Toyota • Continuously evolved from SMED to OTED
  • 7. www.winningmindssolutions.com World-Class Quick Changeover Methodologies… SMED: Single Minute Exchange of Die Concept that says all setups should and can take less than 10 minutes OTED: One Touch Exchange of Die Concept that says all setups should and can take less than 100 seconds!
  • 8. www.winningmindssolutions.com Traditional vs SMED based Changeover Traditional changeover SMED based changeover Say 20 min per Tyre Say 20 sec for four Tyre
  • 9. www.winningmindssolutions.com Traditional Changeover Process… • Preparation of tools / dies and ensure in working condition • Move to machine • Removal of dies from machine • Placing of dies • Setting all process control • First trial • Adjustment • Take trial • Final good piece production More of “Sequential” Inconsistency in Process &Time More Adjustment and Trial
  • 10. www.winningmindssolutions.com SMED Changeover Process… • Emphasis more on parallel activities than sequential • Changeover process by set of cross functional experts than one • Predefined work and collaboration of cross functional team • Focus more on housekeeping and visual management practices • Standardization as much as possible
  • 11. www.winningmindssolutions.com SMED Methodology Existing changeover process Improvement steps Observe and Record the elements Identify Internal and External Elements Convert Internal elements to External elements Improve External Elements Improve Internal Elements Document Internal & External Elements and Standardize
  • 12. www.winningmindssolutions.com Observe and Record Elements…  Video recording is ideal to understand and explain Sample Elemental Recording data Time on Element description Duration (Min) 9.15 am Machine stopped for die setting 0 9.15-9.30 am Operator is waiting for supervisor's instruction 15 9.30 am Temporary operator to clean flashes from machines/ die 2 9.32 am coolant hose removal 5 9.37 am Temporary operator stuck with removing hose removal ; need assistance 2 9.39 am Senior employee came in to assist 1 9.40 am Bring Chain / hook to lift 2
  • 13. www.winningmindssolutions.com Identify Internal and External Elements Internal elements: Activities that must be performed while the machine is stopped Example :  Placing the die inside the bed Tightening the die with machine bed External elements: Activities that can be performed while the machine is running Example : Positioning the crane and tools in front of the machine for loading
  • 14. www.winningmindssolutions.com Identify Internal and External Elements (Example) Remove 4 off bolts on rear side using spanner / pipe rod 5 Internal Remove 4 off bolts on front side using spanner / pipe rod 3 Internal completed removing ejector pin 4 Internal Lifting starts Internal perm employee removes bolt from machine guide ways 2 Internal maintenance team checks on sprayer 10 Internal CL removes flash from bolt guide ways and air clean 5 Internal change plunger / sleeve by perm employee Internal 5 times went to get wooden block , screw driver , ejector rod , waste cloth 14 External filing and removing flashes from plunger block - 1 min 1 External completes fixing plunger block 1 Internal Maintenance team removes sprayer 6 Internal fixing plunge block with support of CL and remove wooden block 1 Internal perm employees tries to fix hook in cyl head die which was kept in hand pallet 13 Internal it is loose and call die maintenance person External remove core / cavity die from hand pallet and joining both External die maintenance person air clean the screw hole External fixes 2 eye bolt in the die and connect with chain 2 Internal
  • 15. www.winningmindssolutions.com Convert Internal elements to External Elements Convert as much as possible Internal Elements into External Elements  Proper Housekeeping –Location for everything Eliminate Searching  Pre Arrangement of tools / dies  Spares Management  All experts –Being near to machine when changeover takes place Make Visual marks / identification as much as possible and avoid trials
  • 16. www.winningmindssolutions.com Improve External Elements  Housekeeping-Location for all items Visual Identification for all items Colour Coding Standard set up process Checklist for each die setting
  • 17. www.winningmindssolutions.com Improve Internal Elements • Create Parallel steps (eg removing bolts) • Reduce complexity and eliminate waste  Use functional fixtures and jigs • levered or one-turn fasteners • interlocking wedge or slot  Eliminate adjustments • use angle and flat • use preset pins, guides, notches etc.
  • 19. www.winningmindssolutions.com Document and standardize ..  Create Checklist for each die change  Document the process steps Train and create more setting experts
  • 20. www.winningmindssolutions.com Case study examples on changeover loss reduction using SMED concept in our client’s process
  • 21. www.winningmindssolutions.com Examples of Changeover reduction in our Client's Operations
  • 22. www.winningmindssolutions.com Thank you for your Interest To Know more about those case studies ,pl mail to us ganesh@winningmindssolutions.com mobile : +91 90259 33666 For Business and Life Excellence articles and case studies pl visit website : www.winningmindssolutions.com