Critical Chain Slides Part 2
1. Task 1 5 days Time Step 1 – “Normal” Project Plan - Construct the plan in the “Normal Way” Task 2 2 days Task 3 4 days Duration of Project = 11 Days
2. Time Step 2 - Start Constructing Critical Chain Plan – Get two estimates for each task. One is an “Aggressive Estimate”, the other a “100% Likely Estimate” Task 1 6 days Task 1 2 days Task 2 3 days Task 2 1 day Task 3 5 days Task 3 2 days Aggressive Estimate 100% Likely Estimate Key