1. E N E R G O Brasov
Cement Plants
Projects Completed
2. The process of production for
the cement
1. Quarry
2. Crushing
3. Raw material conveyor
4. Homogenization
5. Raw mill
6. Filter
7. Preheater
8. Kiln
9. Cooler
10. Clinker silo
11. Cement mill
12. Packaging and delivery
3. ENERGO on brief
Who we are
We are "ENERGO SA" a private company, proud to be among the companies recognized
by the quality of work done.
The company was founded in 1985 as a company specializing in supply of parts and
components for national power plants system. Since 1995, when it became a private
company was diversified range of products and services covering now different market
segments.
With over 25 years experience in the industrial, infrastructure and civil constructions
and with over 15 years of collaboration with major companies in the world of power
generation, we believe that we have the necessary strengths to add value to the projects
that you develop for your clients.
The company operates in an area of 41.000 square meters of which 13,000 square
meters are the production space, including metal construction department (cutting,
assembling and welding), machining department and department blasting / painting.
Capabilites includes Engineering, Fabrication, Supply and Erection of structural steel
for civil and industrial buildings, energy, environment and renewable energy, public
utility works (stadiums, sports arenas) and infrastructure (bridges), different metallic
confections (ducts, hoppers, silos) and is able to assimilate new products easily.
The company's production capacity amounts to 1000 tons / month after modernization
and upgrading of production line.
Employees are ENERGO characteristic: professionals, scrupulous and able to resolve
any requirement. Professionalism is certified by various organizations such as:
International Institute of Welding ,TÜV SÜDDEUTSCHLAND, SLV Munchen, ISCIR,
Aeronautical Authority , Railway Authority AFER
5. PROJECT 1
New production line and clinker storage
To achieve marketing objectives, client
investment consisted of expanding
production by building a new line with a
capacity of 4,000 tons of clinker / day,
watching all processes from raw material
preparation to storage clinker in silos of
45,000 tons
ENERGO was appointed to execute and
deliver steel structures necessary for
several objectives of Phase I:
6. PROJECT 1
New production line and clinker storage
1. Raw Mill Building
2. Bucket Elevator Tower
3. Kiln De-dusting Filter Air
4. Slide Support 1Air Slide Support 2
5. Cooler Building
6. Air Slide Tower
7. Supporting Structure Transfer Tower
8. Silo Roof 1Silo Roof 2
9. Control Room
10. Duct Support
11. Kiln Dust Bin Support
12. Clinker Cooler Dedusting
13. Staircase to Penthouse on Silo 2Steel Structure-Penthouse on Silo 1
14. Kiln Gangway and Stairs between piers
15. Steel Structure-Penthouse on Silo 2
16. Cable Bridge
17. Clinker Transport to Storage Conveyor between silos
18. Gypsum Hall
19. Beam for Correctives Hall
20. Support Stair and platform at electrical room
21. Airslide support between Sup tower &Preheater
22. Steel structure - Off spec clinker transport
23. Steel structure - Preheater reinforcement
24. Gas duct support
25. Support Conveyor
26. Lift Preheater structure
27. Filler transport
Total quantity executed and delivered for Phase I and II
was over 6,500 tons
7. PROJECT 1
New production line and clinker storage
Components have been delivered simultaneously
to several objectives following the installation
order established by the client
8. PROJECT 1
New production line and clinker storage
Logistics of Complete delivery was
provided by ENERGO
9. PROJECT 1
New production line and clinker storage
The accuracy of execution was essential in
order to achieve the best conditions of
installation
10. PROJECT 1
New production line and clinker storage
After completion of phase I,
ENERGO continued at customer
request execution and delivery for
objects belonging Phase II
12. PROJECT 2
Transportation and storage of 130,000 To clinker
Client investment purpose
was to build a new deposit
and transport to feed clinker
silo of 130,000 tons.
ENERGO was appointed to
carry out the work of design
- construction - installation
of conveyor and supply -
assembly of the roof silo .
13. PROJECT 2
Transportation and storage of 130,000 To clinker
Cylindrical part of the silo was built from
concrete.
The roof was made of:
• 3449 metallic elements assembled with
screws
• 30 trusses placed radially, forming a
truncated cone with a diameter of 80 m
at the base and a height of 22 m above
the 16 m of concrete cylinder.
• The structure was fixed in 30 mobile
supports.
14. PROJECT 2
Transportation and storage of 130,000 To clinker
For installation was designed, developed and installed in the
center of the silo, a temporary tower that helped to fix the
central tension ring
15. PROJECT 2
Transportation and storage of 130,000 To clinker
Petals was installed, pre-assembled on the ground
Installation was done by balancing the weights on cylinder diameter and
central ring tension
16. PROJECT 2
Transportation and storage of 130,000 To clinker
Final deviation resulting from installation on a
circumference of about 250 m was 0.01 m
17. PROJECT 2
Transportation and storage of 130,000 To clinker
Complete assembly of silo roof was done in 5 weeks
19. ENERGO
SUCCESS KEYS
for
CEMENT INDUSTRY PROJECTS
Guaranteeing of technical conditions and quality requirements of projects
Execution state-of-art
Delivery Just-in-Time
The promptness in identifying, analyzing and solving various situations created
The accuracy of of documents prepared
Therefore two major brands of cement:
"Power Passion Performance" and "For better building"
Were for ENERGO the way ahead to success and complete satisfaction of their customers