SlideShare ist ein Scribd-Unternehmen logo
1 von 6
Downloaden Sie, um offline zu lesen
®
Volume12Number02-February2012
WorldPipelines	FEBRUARY2012www.energyglobal.com
Figure 1. Crossing the Waupisoo River.
Scheduled
T
raditional planning and scheduling software for the
construction industry is dominated by Primavera
and Microsoft Project. Both solutions enable a
planner to develop a series of activities that are
logically connected, to provide a sequence of events from
project start to finish. While these tools are designed for
the construction of buildings and other facilities (power
generating stations, refineries, etc.), they are not adequate
for the constructability issues and demands of building a
linear project such as a pipeline, high voltage power lines, rail
system or roadway.
The Gantt chart, with tasks grouped and sorted in different
ways, is the most common approach these programmes use
to present schedules. Using traditional planning software, the
project execution can only be represented by increasing the
number of tasks to split the work of a crew into many small
parts to reflect the constructability issues (i.e., reverse lays,
environmental restrictions) of the project. The end result is
forsuccess
Hubert Geier,
Managing Director,
Linear Project,
Germany, explains
the advantages
of linear
scheduling for
pipeline projects.
58
Reprinted from FEBRUARY 2012 | World pipelines
large schedules that do not readily provide an overview of the
interaction between site and schedule.
The difference in a linear project, such as a pipeline, is
that the work is highly repetitive, with the crews moving
along a defined right‑of‑way (ROW). Changing site conditions,
environmental and regulatory constraints impact the
production methods, work rate and the logistics of building
the pipeline along the length of the project. The planner
always needs to be aware of these conditions when planning
the tasks and resource usage, as well as the sequencing and
direction of the work.
This article introduces TILOS, a linear planning and
management tool that through the use of march charts (also
known as time distance diagrams), enables a pipeline planner
to integrate the schedule with the site data and logistical
constraints. Rather than presenting the plan as a series of
Gantt bars, this approach allows the planner to integrate
and print as much detail as required about the schedule on
a single page. This detail
can include elevation
profiles, land acquisition,
environmental windows,
crossings and crew
movement and direction of
travel.
The key is the use of
two axes: the time and the
location axis in a 2D grid. In
Figure 2, the location axis
is horizontal and the time
axis is vertical, but this can
be changed on demand.
Each task is defined by the
start and end co‑ordinates
in both time and location.
The line between these
points defines the task and
describes when the crew
is at a specific location.
The slope of the line
indicates the speed of
each crew in the different
segments. The steeper the
slope, the slower the crew
is moving. Furthermore,
the sequence of tasks in
pipeline construction is
strongly determined by
the production processes,
one crew cannot overtake
the other. Using TILOS,
any lines that cross
immediately indicate
clashes.
Activities such as
horizontal directional drills,
road bores or mainline
block valves are typically
shown as rectangles
because the crews are
working in one location.
Environmental constraints
and hydrotest segments are
also typically represented
by rectangles, as these are
clearly defined in time and
distance.
Figure 2. An example of a TILOS 1 page time-distance plan.
Figure 3. Linear schedule with ribbons.
Reprinted from FEBRUARY 2012 | World pipelines
Connecting alignment sheets with the schedule
In the pipeline industry, detailed information about the ROW
is documented in the alignment sheets that are typically
prepared with CAD systems. This information includes:
elevation, crossings, pipe thickness and type, pipe weight
requirements, environmental restrictions, land permitting, and
municipal districts that the pipeline is traversing.
This type of information is added in a TILOS view as a
ribbon along the distance axis that represents the ROW. These
ribbons can contain graphs that are generated using TILOS
profile data, which are easily imported from Excel or other
data files. Thus, a time distance diagram looks similar to an
alignment sheet but also has an extra ROW that displays the
schedule in a march chart form.
Figure 3 shows the main crew movements as different
coloured lines. The road bores and the hydrotest tasks are
shown as rectangles. The area between KP 59+000 and 62+600
(where the pipeline is crossing a valley) is represented in the
overview plan by just a single summary task. This section is
performed by a special crew and is detailed in another time
distance diagram using a different scale to show more details.
Environmental restrictions and land tracks that have not
been acquired are monitored as rectangles to indicate that
there is no access to these areas. Each crew line touching
these objects represents a clash and the planner is notified of
these events during a reschedule in TILOS. In Figure 3, the blue
rectangle indicates a weather restriction that the planner has
had to consider in developing the project execution strategy.
Figure 4 shows a portion of the entire schedule discussed
earlier. In this view, a filter has been applied to display
only the clearing activity. The different clearing work rates
(here m/d) along the ROW are indicated by the changing slope
of the task line and the differential work rate is generated
using the ‘clearing’ profile and is shown as a table. The table
also represents the land coverage showing each type as a
different colour. The work rate in the last column adjusts the
work rate of the clearing task for that segment.
Integrating GPS data
The integration of maps and satellite can further enhance
the time distance diagram. If GPS co-ordinates are available,
the ROW can be drawn as a route on a map and the pictures
can be added to the TILOS view. Locations of crossings,
camps, stockpiles and access roads to the ROW are important
components of the planning process. All of these can be
readily identified and located in TILOS using GPS data during
planning.
TILOS is able to slice the task data to any time period or
distance section. By mapping the KP values of the tasks to
the GPS co-ordinates of the ROW, each task can be shown in
the map view as well. Setting time filters, snap shots of the
progress can be shown. Furthermore, it allows a simulation of
the construction process by moving the time stepwise forward
and adding the built section for the time periods.
Reporting and controlling
During project execution, the time distance diagram is a
valuable tool as it provides all the necessary information
about stockpile sites, restricted access, crew locations, and
access roads to plan the daily construction.
Daily progress is typically recorded in worksheets that
are then entered into Excel or a company‑owned reporting
system. This progress data is easily imported into TILOS using
its extended import facilities and allows the construction team
to monitor the progress along the ROW. While traditional
project management systems report on a % completed for
each task, TILOS also records
the location and date where
the work has been executed.
Recording both the time
and location of completed
activities quickly identifies
where move arounds and work
stoppages have occurred.
Finally, a good progress
overview can be achieved
using the distance‑based
Gantt chart in TILOS. This is a
unique feature that show bars
along a distance axis (not using
a time axis that is typical of
Gantt charts). By grouping the
task by crew and filtering for
only performed sections, the
distance Gantt chart clearly
displays the sections that
each crew has completed.
Other information can also
include earned value analysis
on a crew or project basis.
This includes: % completed
Figure 4. Clearing crew with a variable work rate.
Figure 5. Satellite view with pipeline route, crossings and progress situation.
Reprinted from FEBRUARY 2012 | World pipelines
to date, % complete planned,
completed quantity, remaining
quantity, earned value and
schedule variance. A distance
Gantt chart is shown in
Figure 5.
TILOS calculates the
expected end date using the
actual work rate to date. After
rescheduling, any remaining
work can be easily planned
using a new work rate required
to recover the baseline end
date if necessary.
Integration concepts
Compiling all this information
into the plan does not
necessarily mean that a lot of effort is required. Most of the
information is already available and can be imported into
TILOS during the planning phase.
In TILOS, most graphs are not simply pictures but are
generated based on grid data that can be easily imported.
Spreadsheets, the most common tool used by engineers for
calculation and management, are easily imported into the
software by using the clipboard or importing XML data.
The TILOS template strategy allows a planner to setup
a project in a minimum amount of time. The layout of the
view, including ribbons, and the standard task templates
with predefined work rates can be predefined and saved as a
TILOS template. New projects are then created based on this
template. Setting the execution time and the distance axis
values adjusts all the views in the project automatically.
The planning starts by importing site data such as
crossings, county list and elevation to generate the ribbons
for the view. Activities can be added by drawing them directly
on the view or importing them from Excel or another project
management system.
Portfolio management
In many large organisations, TILOS is used to plan and control
individual projects because of its comprehensive schedule
presentation. In these organisations, TILOS is used to push
data to the company portfolio management tools, such as
Oracle’s Primavera using the API integration tools developed
for TILOS. The software exchange module can import the
whole project including WBS structures and resource usage
into Primavera Project management. For MS Project, a similar
integration is available using a VBA application that can build
the whole project from scratch.
Summary
This article has shown a new approach to the traditional
planning methodology. By visually developing the
project, while incorporating all known constraints and
constructability issues, the planner can readily develop a
feasible execution plan. Using the layer‑based cell system in
TILOS, as much detail as required by the planner and project
team can be incorporated into a TILOS view. Company
tailored templates reduce the work efforts and costs for
planning by providing more precision during the early
planning phase.
Many owner organisations now require a march chart
submission as part of the bid package so that the contractor
can demonstrate an understanding of the constructability
issues and constraints and to prove that the work can be
completed in the required timeframe.
Figure 6. Progress in a march chart and distance Gantt chart.
COMING NEXT MONTH
Reprinted from FEBRUARY 2012 | World pipelines

Weitere ähnliche Inhalte

Was ist angesagt?

Flood Map Desktop for ArcGIS
Flood Map Desktop for ArcGISFlood Map Desktop for ArcGIS
Flood Map Desktop for ArcGISEmilySzajna
 
Project synopsis for East West Gas Pipeline and Effective GIS Implementation
Project synopsis for East West Gas Pipeline and Effective GIS ImplementationProject synopsis for East West Gas Pipeline and Effective GIS Implementation
Project synopsis for East West Gas Pipeline and Effective GIS ImplementationSoumik Chakraborty
 
Q-GIS : Geo-referencing and Digitization
Q-GIS : Geo-referencing and DigitizationQ-GIS : Geo-referencing and Digitization
Q-GIS : Geo-referencing and DigitizationLakshya Pandit
 
Geographic information system and remote sensing
Geographic information system and remote sensingGeographic information system and remote sensing
Geographic information system and remote sensingchala hailu
 
Comparison among Height Observation of GPS, Total Station and Level and their...
Comparison among Height Observation of GPS, Total Station and Level and their...Comparison among Height Observation of GPS, Total Station and Level and their...
Comparison among Height Observation of GPS, Total Station and Level and their...IRJET Journal
 
Geographical Information System (GIS) Georeferencing and Digitization, Bihar ...
Geographical Information System (GIS) Georeferencing and Digitization, Bihar ...Geographical Information System (GIS) Georeferencing and Digitization, Bihar ...
Geographical Information System (GIS) Georeferencing and Digitization, Bihar ...Kamlesh Kumar
 
Subsurface utility engineering by Advance Scanning Services
Subsurface utility engineering  by Advance Scanning ServicesSubsurface utility engineering  by Advance Scanning Services
Subsurface utility engineering by Advance Scanning ServicesAdvanceScanningServices
 
2013 Peter Williams AIMS Mapping Presentation
2013 Peter Williams AIMS Mapping Presentation2013 Peter Williams AIMS Mapping Presentation
2013 Peter Williams AIMS Mapping PresentationPeter Williams
 
Visualization design case study 2 greenpeace mckinsey’s curve
Visualization design case study 2  greenpeace mckinsey’s curveVisualization design case study 2  greenpeace mckinsey’s curve
Visualization design case study 2 greenpeace mckinsey’s curvevisualization, ID, NCKU
 
Description of the project thesis at Fraunhofer ITWM
Description of the project thesis at Fraunhofer ITWMDescription of the project thesis at Fraunhofer ITWM
Description of the project thesis at Fraunhofer ITWMAditya Mahesh
 
Web Based Gis For Land Administration 20090629
Web Based Gis For Land Administration 20090629Web Based Gis For Land Administration 20090629
Web Based Gis For Land Administration 20090629John Reitsma
 
JKJ_SSRS PPS Excel Services Project.Documentation
JKJ_SSRS PPS Excel Services Project.DocumentationJKJ_SSRS PPS Excel Services Project.Documentation
JKJ_SSRS PPS Excel Services Project.DocumentationJeff Jacob
 
FISITA-F2006M035-Kerschbaum-Gruen
FISITA-F2006M035-Kerschbaum-GruenFISITA-F2006M035-Kerschbaum-Gruen
FISITA-F2006M035-Kerschbaum-GruenNorbert Gruen
 
Thompson & Alexander Dock Survey
Thompson & Alexander Dock SurveyThompson & Alexander Dock Survey
Thompson & Alexander Dock SurveyCiara MacManus
 
Geomorphology Maps
Geomorphology MapsGeomorphology Maps
Geomorphology Mapshaythemdinar
 
Resource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder MeetingResource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder MeetingMashilo Kabedi
 

Was ist angesagt? (20)

Flood plain mapping
Flood plain mappingFlood plain mapping
Flood plain mapping
 
Flood Map Desktop for ArcGIS
Flood Map Desktop for ArcGISFlood Map Desktop for ArcGIS
Flood Map Desktop for ArcGIS
 
Project synopsis for East West Gas Pipeline and Effective GIS Implementation
Project synopsis for East West Gas Pipeline and Effective GIS ImplementationProject synopsis for East West Gas Pipeline and Effective GIS Implementation
Project synopsis for East West Gas Pipeline and Effective GIS Implementation
 
Q-GIS : Geo-referencing and Digitization
Q-GIS : Geo-referencing and DigitizationQ-GIS : Geo-referencing and Digitization
Q-GIS : Geo-referencing and Digitization
 
Geographic information system and remote sensing
Geographic information system and remote sensingGeographic information system and remote sensing
Geographic information system and remote sensing
 
Comparison among Height Observation of GPS, Total Station and Level and their...
Comparison among Height Observation of GPS, Total Station and Level and their...Comparison among Height Observation of GPS, Total Station and Level and their...
Comparison among Height Observation of GPS, Total Station and Level and their...
 
Geographical Information System (GIS) Georeferencing and Digitization, Bihar ...
Geographical Information System (GIS) Georeferencing and Digitization, Bihar ...Geographical Information System (GIS) Georeferencing and Digitization, Bihar ...
Geographical Information System (GIS) Georeferencing and Digitization, Bihar ...
 
Subsurface utility engineering by Advance Scanning Services
Subsurface utility engineering  by Advance Scanning ServicesSubsurface utility engineering  by Advance Scanning Services
Subsurface utility engineering by Advance Scanning Services
 
Breakline
BreaklineBreakline
Breakline
 
2013 Peter Williams AIMS Mapping Presentation
2013 Peter Williams AIMS Mapping Presentation2013 Peter Williams AIMS Mapping Presentation
2013 Peter Williams AIMS Mapping Presentation
 
Visualization design case study 2 greenpeace mckinsey’s curve
Visualization design case study 2  greenpeace mckinsey’s curveVisualization design case study 2  greenpeace mckinsey’s curve
Visualization design case study 2 greenpeace mckinsey’s curve
 
Description of the project thesis at Fraunhofer ITWM
Description of the project thesis at Fraunhofer ITWMDescription of the project thesis at Fraunhofer ITWM
Description of the project thesis at Fraunhofer ITWM
 
Tanveer_Standard C.V_Out Side_2015
Tanveer_Standard C.V_Out Side_2015Tanveer_Standard C.V_Out Side_2015
Tanveer_Standard C.V_Out Side_2015
 
4D OVERVIEW-2016
4D OVERVIEW-20164D OVERVIEW-2016
4D OVERVIEW-2016
 
Web Based Gis For Land Administration 20090629
Web Based Gis For Land Administration 20090629Web Based Gis For Land Administration 20090629
Web Based Gis For Land Administration 20090629
 
JKJ_SSRS PPS Excel Services Project.Documentation
JKJ_SSRS PPS Excel Services Project.DocumentationJKJ_SSRS PPS Excel Services Project.Documentation
JKJ_SSRS PPS Excel Services Project.Documentation
 
FISITA-F2006M035-Kerschbaum-Gruen
FISITA-F2006M035-Kerschbaum-GruenFISITA-F2006M035-Kerschbaum-Gruen
FISITA-F2006M035-Kerschbaum-Gruen
 
Thompson & Alexander Dock Survey
Thompson & Alexander Dock SurveyThompson & Alexander Dock Survey
Thompson & Alexander Dock Survey
 
Geomorphology Maps
Geomorphology MapsGeomorphology Maps
Geomorphology Maps
 
Resource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder MeetingResource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder Meeting
 

Ähnlich wie TILOS: World Pipelines Article

TILOS, Plan Linear Projects with Confidence
TILOS, Plan Linear Projects with ConfidenceTILOS, Plan Linear Projects with Confidence
TILOS, Plan Linear Projects with ConfidenceM. Tuna
 
TILOS, Plan Linear Projects with Confidence
TILOS, Plan Linear Projects with ConfidenceTILOS, Plan Linear Projects with Confidence
TILOS, Plan Linear Projects with ConfidenceM. Tuna
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Programme evaluation and review technique &Gantt Chart
Programme evaluation and review technique &Gantt ChartProgramme evaluation and review technique &Gantt Chart
Programme evaluation and review technique &Gantt ChartMathew Varghese V
 
GANTT CHART nursing Management for Msc nursing
GANTT CHART nursing Management for Msc nursingGANTT CHART nursing Management for Msc nursing
GANTT CHART nursing Management for Msc nursingThangamjayarani
 
Project Management Techniques ( WBS & Critical Path Method )
Project Management Techniques ( WBS & Critical Path Method )Project Management Techniques ( WBS & Critical Path Method )
Project Management Techniques ( WBS & Critical Path Method )Surajkumar Sonar
 
Management operation system techniques (MOST) replaces PERT and CPM in constr...
Management operation system techniques (MOST) replaces PERT and CPM in constr...Management operation system techniques (MOST) replaces PERT and CPM in constr...
Management operation system techniques (MOST) replaces PERT and CPM in constr...IJMER
 
Application of GIS (Geographical information system)
Application of GIS (Geographical information system)Application of GIS (Geographical information system)
Application of GIS (Geographical information system)Fayaz Ahamed A P
 
A Review of _Urban Water Networks Management Using GIS
A Review of _Urban Water Networks Management Using GISA Review of _Urban Water Networks Management Using GIS
A Review of _Urban Water Networks Management Using GISIRJET Journal
 
Modelingprogramstructure
ModelingprogramstructureModelingprogramstructure
Modelingprogramstructurelearnt
 
IRJET- Bus Route Optimization in Jyothi Engineering College using ARC- GIS
IRJET- Bus Route Optimization in Jyothi Engineering College using ARC- GISIRJET- Bus Route Optimization in Jyothi Engineering College using ARC- GIS
IRJET- Bus Route Optimization in Jyothi Engineering College using ARC- GISIRJET Journal
 
Control techniques
Control techniquesControl techniques
Control techniquesAdnan Shakir
 
Scheduling minimizing the input while maximizing the output white paper
Scheduling   minimizing the input while maximizing the output white paperScheduling   minimizing the input while maximizing the output white paper
Scheduling minimizing the input while maximizing the output white paperp6academy
 
TID Chapter 6 Introduction To Microsoft Project
TID Chapter 6 Introduction To Microsoft ProjectTID Chapter 6 Introduction To Microsoft Project
TID Chapter 6 Introduction To Microsoft ProjectWanBK Leo
 
Gisapplicationincivilengineering 140227110022-phpapp02
Gisapplicationincivilengineering 140227110022-phpapp02Gisapplicationincivilengineering 140227110022-phpapp02
Gisapplicationincivilengineering 140227110022-phpapp02Antriksh Vatsyayana
 

Ähnlich wie TILOS: World Pipelines Article (20)

TILOS, Plan Linear Projects with Confidence
TILOS, Plan Linear Projects with ConfidenceTILOS, Plan Linear Projects with Confidence
TILOS, Plan Linear Projects with Confidence
 
TILOS, Plan Linear Projects with Confidence
TILOS, Plan Linear Projects with ConfidenceTILOS, Plan Linear Projects with Confidence
TILOS, Plan Linear Projects with Confidence
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Programme evaluation and review technique &Gantt Chart
Programme evaluation and review technique &Gantt ChartProgramme evaluation and review technique &Gantt Chart
Programme evaluation and review technique &Gantt Chart
 
GANTT CHART nursing Management for Msc nursing
GANTT CHART nursing Management for Msc nursingGANTT CHART nursing Management for Msc nursing
GANTT CHART nursing Management for Msc nursing
 
Project Management Techniques ( WBS & Critical Path Method )
Project Management Techniques ( WBS & Critical Path Method )Project Management Techniques ( WBS & Critical Path Method )
Project Management Techniques ( WBS & Critical Path Method )
 
Pert and gantt chart
Pert and gantt chartPert and gantt chart
Pert and gantt chart
 
Management operation system techniques (MOST) replaces PERT and CPM in constr...
Management operation system techniques (MOST) replaces PERT and CPM in constr...Management operation system techniques (MOST) replaces PERT and CPM in constr...
Management operation system techniques (MOST) replaces PERT and CPM in constr...
 
Application of GIS (Geographical information system)
Application of GIS (Geographical information system)Application of GIS (Geographical information system)
Application of GIS (Geographical information system)
 
A Review of _Urban Water Networks Management Using GIS
A Review of _Urban Water Networks Management Using GISA Review of _Urban Water Networks Management Using GIS
A Review of _Urban Water Networks Management Using GIS
 
Modelingprogramstructure
ModelingprogramstructureModelingprogramstructure
Modelingprogramstructure
 
IRJET- Bus Route Optimization in Jyothi Engineering College using ARC- GIS
IRJET- Bus Route Optimization in Jyothi Engineering College using ARC- GISIRJET- Bus Route Optimization in Jyothi Engineering College using ARC- GIS
IRJET- Bus Route Optimization in Jyothi Engineering College using ARC- GIS
 
Control techniques
Control techniquesControl techniques
Control techniques
 
PMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptxPMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptx
 
Scheduling minimizing the input while maximizing the output white paper
Scheduling   minimizing the input while maximizing the output white paperScheduling   minimizing the input while maximizing the output white paper
Scheduling minimizing the input while maximizing the output white paper
 
TID Chapter 6 Introduction To Microsoft Project
TID Chapter 6 Introduction To Microsoft ProjectTID Chapter 6 Introduction To Microsoft Project
TID Chapter 6 Introduction To Microsoft Project
 
02-Key Definitions .pdf
02-Key Definitions .pdf02-Key Definitions .pdf
02-Key Definitions .pdf
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Gisapplicationincivilengineering 140227110022-phpapp02
Gisapplicationincivilengineering 140227110022-phpapp02Gisapplicationincivilengineering 140227110022-phpapp02
Gisapplicationincivilengineering 140227110022-phpapp02
 
00 project control tools
00 project control tools00 project control tools
00 project control tools
 

Mehr von Cisco

CMCS Statement of Qualification
CMCS Statement of QualificationCMCS Statement of Qualification
CMCS Statement of QualificationCisco
 
Professional Development Catalogue 2014
Professional Development Catalogue 2014Professional Development Catalogue 2014
Professional Development Catalogue 2014Cisco
 
Project Management Diploma with Instructors
Project Management Diploma with InstructorsProject Management Diploma with Instructors
Project Management Diploma with InstructorsCisco
 
CMCS Reference Letters
CMCS Reference LettersCMCS Reference Letters
CMCS Reference LettersCisco
 
GPM: PRiSM Practitioner
GPM: PRiSM Practitioner GPM: PRiSM Practitioner
GPM: PRiSM Practitioner Cisco
 
CMCS Website Training Experience 2013
CMCS Website Training Experience 2013CMCS Website Training Experience 2013
CMCS Website Training Experience 2013Cisco
 
Our Awards and Achievements
Our Awards and AchievementsOur Awards and Achievements
Our Awards and AchievementsCisco
 
Our Partners
Our PartnersOur Partners
Our PartnersCisco
 
CMCS PMO Solution
CMCS PMO SolutionCMCS PMO Solution
CMCS PMO SolutionCisco
 
Can You Afford Not To Manage Your Project's Contracts?
Can You Afford Not To Manage Your Project's Contracts?Can You Afford Not To Manage Your Project's Contracts?
Can You Afford Not To Manage Your Project's Contracts?Cisco
 
Our 2,000+ Clients
Our 2,000+ ClientsOur 2,000+ Clients
Our 2,000+ ClientsCisco
 
Asta Powerproject: Business Case
Asta Powerproject: Business CaseAsta Powerproject: Business Case
Asta Powerproject: Business CaseCisco
 
CoSign Digital Signatures: General Presentation
CoSign Digital Signatures: General Presentation CoSign Digital Signatures: General Presentation
CoSign Digital Signatures: General Presentation Cisco
 
Acumen Fuse: Datasheet
Acumen Fuse: DatasheetAcumen Fuse: Datasheet
Acumen Fuse: DatasheetCisco
 
Acumen Risk: Data Sheet
Acumen Risk: Data SheetAcumen Risk: Data Sheet
Acumen Risk: Data SheetCisco
 
Acumen Risk: Brochure
Acumen Risk: BrochureAcumen Risk: Brochure
Acumen Risk: BrochureCisco
 
Acumen Fuse: Metrics
Acumen Fuse: MetricsAcumen Fuse: Metrics
Acumen Fuse: MetricsCisco
 
Acumen Fuse: Enterprise Project Analysis Datasheet
Acumen Fuse: Enterprise Project Analysis DatasheetAcumen Fuse: Enterprise Project Analysis Datasheet
Acumen Fuse: Enterprise Project Analysis DatasheetCisco
 
Nomitech: CostOs Estimating Product Overview
Nomitech: CostOs Estimating Product OverviewNomitech: CostOs Estimating Product Overview
Nomitech: CostOs Estimating Product OverviewCisco
 
Nomitech: CostOs Oil & Gas Estimating
Nomitech: CostOs Oil & Gas EstimatingNomitech: CostOs Oil & Gas Estimating
Nomitech: CostOs Oil & Gas EstimatingCisco
 

Mehr von Cisco (20)

CMCS Statement of Qualification
CMCS Statement of QualificationCMCS Statement of Qualification
CMCS Statement of Qualification
 
Professional Development Catalogue 2014
Professional Development Catalogue 2014Professional Development Catalogue 2014
Professional Development Catalogue 2014
 
Project Management Diploma with Instructors
Project Management Diploma with InstructorsProject Management Diploma with Instructors
Project Management Diploma with Instructors
 
CMCS Reference Letters
CMCS Reference LettersCMCS Reference Letters
CMCS Reference Letters
 
GPM: PRiSM Practitioner
GPM: PRiSM Practitioner GPM: PRiSM Practitioner
GPM: PRiSM Practitioner
 
CMCS Website Training Experience 2013
CMCS Website Training Experience 2013CMCS Website Training Experience 2013
CMCS Website Training Experience 2013
 
Our Awards and Achievements
Our Awards and AchievementsOur Awards and Achievements
Our Awards and Achievements
 
Our Partners
Our PartnersOur Partners
Our Partners
 
CMCS PMO Solution
CMCS PMO SolutionCMCS PMO Solution
CMCS PMO Solution
 
Can You Afford Not To Manage Your Project's Contracts?
Can You Afford Not To Manage Your Project's Contracts?Can You Afford Not To Manage Your Project's Contracts?
Can You Afford Not To Manage Your Project's Contracts?
 
Our 2,000+ Clients
Our 2,000+ ClientsOur 2,000+ Clients
Our 2,000+ Clients
 
Asta Powerproject: Business Case
Asta Powerproject: Business CaseAsta Powerproject: Business Case
Asta Powerproject: Business Case
 
CoSign Digital Signatures: General Presentation
CoSign Digital Signatures: General Presentation CoSign Digital Signatures: General Presentation
CoSign Digital Signatures: General Presentation
 
Acumen Fuse: Datasheet
Acumen Fuse: DatasheetAcumen Fuse: Datasheet
Acumen Fuse: Datasheet
 
Acumen Risk: Data Sheet
Acumen Risk: Data SheetAcumen Risk: Data Sheet
Acumen Risk: Data Sheet
 
Acumen Risk: Brochure
Acumen Risk: BrochureAcumen Risk: Brochure
Acumen Risk: Brochure
 
Acumen Fuse: Metrics
Acumen Fuse: MetricsAcumen Fuse: Metrics
Acumen Fuse: Metrics
 
Acumen Fuse: Enterprise Project Analysis Datasheet
Acumen Fuse: Enterprise Project Analysis DatasheetAcumen Fuse: Enterprise Project Analysis Datasheet
Acumen Fuse: Enterprise Project Analysis Datasheet
 
Nomitech: CostOs Estimating Product Overview
Nomitech: CostOs Estimating Product OverviewNomitech: CostOs Estimating Product Overview
Nomitech: CostOs Estimating Product Overview
 
Nomitech: CostOs Oil & Gas Estimating
Nomitech: CostOs Oil & Gas EstimatingNomitech: CostOs Oil & Gas Estimating
Nomitech: CostOs Oil & Gas Estimating
 

Kürzlich hochgeladen

Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture conceptP&CO
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...lizamodels9
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptxnandhinijagan9867
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLkapoorjyoti4444
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...daisycvs
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangaloreamitlee9823
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...lizamodels9
 

Kürzlich hochgeladen (20)

Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture concept
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
 

TILOS: World Pipelines Article

  • 2. Figure 1. Crossing the Waupisoo River.
  • 3. Scheduled T raditional planning and scheduling software for the construction industry is dominated by Primavera and Microsoft Project. Both solutions enable a planner to develop a series of activities that are logically connected, to provide a sequence of events from project start to finish. While these tools are designed for the construction of buildings and other facilities (power generating stations, refineries, etc.), they are not adequate for the constructability issues and demands of building a linear project such as a pipeline, high voltage power lines, rail system or roadway. The Gantt chart, with tasks grouped and sorted in different ways, is the most common approach these programmes use to present schedules. Using traditional planning software, the project execution can only be represented by increasing the number of tasks to split the work of a crew into many small parts to reflect the constructability issues (i.e., reverse lays, environmental restrictions) of the project. The end result is forsuccess Hubert Geier, Managing Director, Linear Project, Germany, explains the advantages of linear scheduling for pipeline projects. 58 Reprinted from FEBRUARY 2012 | World pipelines
  • 4. large schedules that do not readily provide an overview of the interaction between site and schedule. The difference in a linear project, such as a pipeline, is that the work is highly repetitive, with the crews moving along a defined right‑of‑way (ROW). Changing site conditions, environmental and regulatory constraints impact the production methods, work rate and the logistics of building the pipeline along the length of the project. The planner always needs to be aware of these conditions when planning the tasks and resource usage, as well as the sequencing and direction of the work. This article introduces TILOS, a linear planning and management tool that through the use of march charts (also known as time distance diagrams), enables a pipeline planner to integrate the schedule with the site data and logistical constraints. Rather than presenting the plan as a series of Gantt bars, this approach allows the planner to integrate and print as much detail as required about the schedule on a single page. This detail can include elevation profiles, land acquisition, environmental windows, crossings and crew movement and direction of travel. The key is the use of two axes: the time and the location axis in a 2D grid. In Figure 2, the location axis is horizontal and the time axis is vertical, but this can be changed on demand. Each task is defined by the start and end co‑ordinates in both time and location. The line between these points defines the task and describes when the crew is at a specific location. The slope of the line indicates the speed of each crew in the different segments. The steeper the slope, the slower the crew is moving. Furthermore, the sequence of tasks in pipeline construction is strongly determined by the production processes, one crew cannot overtake the other. Using TILOS, any lines that cross immediately indicate clashes. Activities such as horizontal directional drills, road bores or mainline block valves are typically shown as rectangles because the crews are working in one location. Environmental constraints and hydrotest segments are also typically represented by rectangles, as these are clearly defined in time and distance. Figure 2. An example of a TILOS 1 page time-distance plan. Figure 3. Linear schedule with ribbons. Reprinted from FEBRUARY 2012 | World pipelines
  • 5. Connecting alignment sheets with the schedule In the pipeline industry, detailed information about the ROW is documented in the alignment sheets that are typically prepared with CAD systems. This information includes: elevation, crossings, pipe thickness and type, pipe weight requirements, environmental restrictions, land permitting, and municipal districts that the pipeline is traversing. This type of information is added in a TILOS view as a ribbon along the distance axis that represents the ROW. These ribbons can contain graphs that are generated using TILOS profile data, which are easily imported from Excel or other data files. Thus, a time distance diagram looks similar to an alignment sheet but also has an extra ROW that displays the schedule in a march chart form. Figure 3 shows the main crew movements as different coloured lines. The road bores and the hydrotest tasks are shown as rectangles. The area between KP 59+000 and 62+600 (where the pipeline is crossing a valley) is represented in the overview plan by just a single summary task. This section is performed by a special crew and is detailed in another time distance diagram using a different scale to show more details. Environmental restrictions and land tracks that have not been acquired are monitored as rectangles to indicate that there is no access to these areas. Each crew line touching these objects represents a clash and the planner is notified of these events during a reschedule in TILOS. In Figure 3, the blue rectangle indicates a weather restriction that the planner has had to consider in developing the project execution strategy. Figure 4 shows a portion of the entire schedule discussed earlier. In this view, a filter has been applied to display only the clearing activity. The different clearing work rates (here m/d) along the ROW are indicated by the changing slope of the task line and the differential work rate is generated using the ‘clearing’ profile and is shown as a table. The table also represents the land coverage showing each type as a different colour. The work rate in the last column adjusts the work rate of the clearing task for that segment. Integrating GPS data The integration of maps and satellite can further enhance the time distance diagram. If GPS co-ordinates are available, the ROW can be drawn as a route on a map and the pictures can be added to the TILOS view. Locations of crossings, camps, stockpiles and access roads to the ROW are important components of the planning process. All of these can be readily identified and located in TILOS using GPS data during planning. TILOS is able to slice the task data to any time period or distance section. By mapping the KP values of the tasks to the GPS co-ordinates of the ROW, each task can be shown in the map view as well. Setting time filters, snap shots of the progress can be shown. Furthermore, it allows a simulation of the construction process by moving the time stepwise forward and adding the built section for the time periods. Reporting and controlling During project execution, the time distance diagram is a valuable tool as it provides all the necessary information about stockpile sites, restricted access, crew locations, and access roads to plan the daily construction. Daily progress is typically recorded in worksheets that are then entered into Excel or a company‑owned reporting system. This progress data is easily imported into TILOS using its extended import facilities and allows the construction team to monitor the progress along the ROW. While traditional project management systems report on a % completed for each task, TILOS also records the location and date where the work has been executed. Recording both the time and location of completed activities quickly identifies where move arounds and work stoppages have occurred. Finally, a good progress overview can be achieved using the distance‑based Gantt chart in TILOS. This is a unique feature that show bars along a distance axis (not using a time axis that is typical of Gantt charts). By grouping the task by crew and filtering for only performed sections, the distance Gantt chart clearly displays the sections that each crew has completed. Other information can also include earned value analysis on a crew or project basis. This includes: % completed Figure 4. Clearing crew with a variable work rate. Figure 5. Satellite view with pipeline route, crossings and progress situation. Reprinted from FEBRUARY 2012 | World pipelines
  • 6. to date, % complete planned, completed quantity, remaining quantity, earned value and schedule variance. A distance Gantt chart is shown in Figure 5. TILOS calculates the expected end date using the actual work rate to date. After rescheduling, any remaining work can be easily planned using a new work rate required to recover the baseline end date if necessary. Integration concepts Compiling all this information into the plan does not necessarily mean that a lot of effort is required. Most of the information is already available and can be imported into TILOS during the planning phase. In TILOS, most graphs are not simply pictures but are generated based on grid data that can be easily imported. Spreadsheets, the most common tool used by engineers for calculation and management, are easily imported into the software by using the clipboard or importing XML data. The TILOS template strategy allows a planner to setup a project in a minimum amount of time. The layout of the view, including ribbons, and the standard task templates with predefined work rates can be predefined and saved as a TILOS template. New projects are then created based on this template. Setting the execution time and the distance axis values adjusts all the views in the project automatically. The planning starts by importing site data such as crossings, county list and elevation to generate the ribbons for the view. Activities can be added by drawing them directly on the view or importing them from Excel or another project management system. Portfolio management In many large organisations, TILOS is used to plan and control individual projects because of its comprehensive schedule presentation. In these organisations, TILOS is used to push data to the company portfolio management tools, such as Oracle’s Primavera using the API integration tools developed for TILOS. The software exchange module can import the whole project including WBS structures and resource usage into Primavera Project management. For MS Project, a similar integration is available using a VBA application that can build the whole project from scratch. Summary This article has shown a new approach to the traditional planning methodology. By visually developing the project, while incorporating all known constraints and constructability issues, the planner can readily develop a feasible execution plan. Using the layer‑based cell system in TILOS, as much detail as required by the planner and project team can be incorporated into a TILOS view. Company tailored templates reduce the work efforts and costs for planning by providing more precision during the early planning phase. Many owner organisations now require a march chart submission as part of the bid package so that the contractor can demonstrate an understanding of the constructability issues and constraints and to prove that the work can be completed in the required timeframe. Figure 6. Progress in a march chart and distance Gantt chart. COMING NEXT MONTH Reprinted from FEBRUARY 2012 | World pipelines