BOX JACKING
EXPLANATION
• It is the process in which a pre-cast R.C.C box or a rigid box
is pushed into the soil with the help of hydraulic jacks
• It is non-intrusive method beneath the existing surface.
• It is more often used when a subway or a aqueduct or a
underground structure is to be constructed.
• It enables the traffic flow without disruption.
R.C.C BOX JACKING
• First the box section is designed and cast at the site or can be
transported to the site according to the requirement.
• The foundation boxes are jacked into the ground designed to carry
the dead and the live loads.
• Then the high capacity jacks are placed at the back and it pushes
the box into the ground.
• A purpose designed tunneling shield is provided in the front end.
• Then the box is jacked carefully through the earth.
• Excavation and jacking are done in small increments in
advance.
• Measures should be taken to prevent the soil being dragged
towards the box.
R.C.C BOX JACKING Cont…
R.C.C BOX JACKING
ARCHED JACKING
THRUST BORING METHOD
• It is a process of simultaneously jacking the pipe through the
earth while removing the earth inside the box by means of a
rotating auger.
• Unstable conditions- the end of auger is kept retracted inside
the encasement so as not to cause voids.
• Stable conditions- the auger can be successfully extended
beyond the encasement.
• This can be successfully used in any kind of soil conditions.
PROBLEMS ENCOUNTERED IN
JACKING
• Settlement of the above ground.
• Seepage of ground water.
• Caving in of soil etc.
FREEZING OF GROUND
• This method is used when we encounter the problem of
ground water seepage and settlement of ground.
• In this method a brine solution is continuously passed through
the pipes fixed in the soil.
• The temperature of the brine would be -30°c.
• So when this brine solution is circulated through these pipes it
freezes the ground and the ground behaves like an ice block.
FREEZING OF GROUND Cont…
• The spacing of the freezing pipes will vary according to the
type of soil, its permeability and other factors.
• Generally it is kept at a spacing of 1.2 m
PROBLEMS IN FREEZING
• The main problem in the freezing method is the
UPHEAVING of the above ground.
• To avoid the upheavement problem we should be careful
in the ground freezing process and the temperature of the
brine solution.
CASE STUDY - SOUTHERN BOSTON
PIERS TRANSIT WAY
• The carriageway has to go
beneath – a Russian
building,100 year old
• 2m thick soil was frozen.
• Under pinning was also done
using mini piles.
PLAN OF THE RUSSIAN BUILDING
ADVANTAGES
• Timely completion of project.
• No disruption of traffic.
• No need to divert the traffic.
DISADVANTAGES
• Cost of project increases.
• Skilled personnel required.
• Safety precautions to be done properly.

Weitere ähnliche Inhalte

Was ist angesagt?

Was ist angesagt? (20)

Special Concretes
Special Concretes Special Concretes
Special Concretes
 
Repair and Rehabilitation
Repair and RehabilitationRepair and Rehabilitation
Repair and Rehabilitation
 
Coffer dam and its type
Coffer dam and its typeCoffer dam and its type
Coffer dam and its type
 
Shoring and underpinning
Shoring and underpinningShoring and underpinning
Shoring and underpinning
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundations
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 
Ground improvement technique
Ground improvement techniqueGround improvement technique
Ground improvement technique
 
Soil exploration part i
Soil exploration part  iSoil exploration part  i
Soil exploration part i
 
Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )
 
Diversion headwork
Diversion headwork Diversion headwork
Diversion headwork
 
Canal Fall
Canal FallCanal Fall
Canal Fall
 
Repair techniques : Grouting (RR&S)
Repair techniques : Grouting (RR&S)Repair techniques : Grouting (RR&S)
Repair techniques : Grouting (RR&S)
 
Cofferdam
CofferdamCofferdam
Cofferdam
 
Bituminous road construction
Bituminous road constructionBituminous road construction
Bituminous road construction
 
DEMOLITION AND DISMANTLING TECHNIQUES
DEMOLITION AND DISMANTLING TECHNIQUESDEMOLITION AND DISMANTLING TECHNIQUES
DEMOLITION AND DISMANTLING TECHNIQUES
 
demolition techniques
demolition techniquesdemolition techniques
demolition techniques
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
 
Pile foundation ppt
Pile foundation pptPile foundation ppt
Pile foundation ppt
 
Earthen Dams
Earthen DamsEarthen Dams
Earthen Dams
 
Failures of a earthen dam
Failures of a earthen damFailures of a earthen dam
Failures of a earthen dam
 

Andere mochten auch

PPT ON TRENCHLESS TECHNOLOGY
PPT ON TRENCHLESS TECHNOLOGY PPT ON TRENCHLESS TECHNOLOGY
PPT ON TRENCHLESS TECHNOLOGY MD AMANULLAH
 
Procedure and construction of road under bridge by box pushing method
Procedure and construction of road under bridge by box pushing methodProcedure and construction of road under bridge by box pushing method
Procedure and construction of road under bridge by box pushing methodeSAT Journals
 
grouting and guniting
grouting and gunitinggrouting and guniting
grouting and gunitingVipul Kerni
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine mohammadsalikali
 
HOBAS PipeLine 2/15: Posa senza scavo sotto le ferrovie
HOBAS PipeLine 2/15: Posa senza scavo sotto le ferrovieHOBAS PipeLine 2/15: Posa senza scavo sotto le ferrovie
HOBAS PipeLine 2/15: Posa senza scavo sotto le ferrovieAmiblu Italia
 
TBRR Workshop, University of Washington
TBRR Workshop, University of WashingtonTBRR Workshop, University of Washington
TBRR Workshop, University of WashingtonAngelshoot
 
NAVIC (Navigation with Indian Constellation)
NAVIC (Navigation with Indian Constellation)NAVIC (Navigation with Indian Constellation)
NAVIC (Navigation with Indian Constellation)Mohan Kanni
 
Indian satellite based navigation system description and implementation status
Indian satellite based navigation system description and implementation statusIndian satellite based navigation system description and implementation status
Indian satellite based navigation system description and implementation statushuangxj73
 
IRNSS by Anish Raj Goyal
IRNSS by Anish Raj GoyalIRNSS by Anish Raj Goyal
IRNSS by Anish Raj GoyalAnish Raj Goyal
 
Indian Regional Navigational Satellite System (IRNSS)
Indian Regional Navigational Satellite System (IRNSS)Indian Regional Navigational Satellite System (IRNSS)
Indian Regional Navigational Satellite System (IRNSS)Yelendher Reddy
 
Silver Lake Reservoir Complex Storage Replacement; Construction Phase I Photo...
Silver Lake Reservoir Complex Storage Replacement; Construction Phase I Photo...Silver Lake Reservoir Complex Storage Replacement; Construction Phase I Photo...
Silver Lake Reservoir Complex Storage Replacement; Construction Phase I Photo...Tina Howell, MBA LEED AP
 

Andere mochten auch (20)

PPT ON TRENCHLESS TECHNOLOGY
PPT ON TRENCHLESS TECHNOLOGY PPT ON TRENCHLESS TECHNOLOGY
PPT ON TRENCHLESS TECHNOLOGY
 
Trenchless technolgy
Trenchless technolgyTrenchless technolgy
Trenchless technolgy
 
Procedure and construction of road under bridge by box pushing method
Procedure and construction of road under bridge by box pushing methodProcedure and construction of road under bridge by box pushing method
Procedure and construction of road under bridge by box pushing method
 
Diaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By GaganDiaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By Gagan
 
TRENCHLESS TECHNOLOGY
TRENCHLESS TECHNOLOGYTRENCHLESS TECHNOLOGY
TRENCHLESS TECHNOLOGY
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 
grouting and guniting
grouting and gunitinggrouting and guniting
grouting and guniting
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine
 
HOBAS PipeLine 2/15: Posa senza scavo sotto le ferrovie
HOBAS PipeLine 2/15: Posa senza scavo sotto le ferrovieHOBAS PipeLine 2/15: Posa senza scavo sotto le ferrovie
HOBAS PipeLine 2/15: Posa senza scavo sotto le ferrovie
 
Juice Jacking 101
Juice Jacking 101Juice Jacking 101
Juice Jacking 101
 
TBRR Workshop, University of Washington
TBRR Workshop, University of WashingtonTBRR Workshop, University of Washington
TBRR Workshop, University of Washington
 
NAVIC (Navigation with Indian Constellation)
NAVIC (Navigation with Indian Constellation)NAVIC (Navigation with Indian Constellation)
NAVIC (Navigation with Indian Constellation)
 
IRNSS ISRO
IRNSS ISROIRNSS ISRO
IRNSS ISRO
 
Irnss ppt.
Irnss ppt.Irnss ppt.
Irnss ppt.
 
Indian satellite based navigation system description and implementation status
Indian satellite based navigation system description and implementation statusIndian satellite based navigation system description and implementation status
Indian satellite based navigation system description and implementation status
 
IRNSS by Anish Raj Goyal
IRNSS by Anish Raj GoyalIRNSS by Anish Raj Goyal
IRNSS by Anish Raj Goyal
 
Irnss
IrnssIrnss
Irnss
 
Navic
NavicNavic
Navic
 
Indian Regional Navigational Satellite System (IRNSS)
Indian Regional Navigational Satellite System (IRNSS)Indian Regional Navigational Satellite System (IRNSS)
Indian Regional Navigational Satellite System (IRNSS)
 
Silver Lake Reservoir Complex Storage Replacement; Construction Phase I Photo...
Silver Lake Reservoir Complex Storage Replacement; Construction Phase I Photo...Silver Lake Reservoir Complex Storage Replacement; Construction Phase I Photo...
Silver Lake Reservoir Complex Storage Replacement; Construction Phase I Photo...
 

Ähnlich wie Box Jacking Process & Methods Explained in 40 Characters

Control of ground water in excavations_Advanced Construction Technology (Seme...
Control of ground water in excavations_Advanced Construction Technology (Seme...Control of ground water in excavations_Advanced Construction Technology (Seme...
Control of ground water in excavations_Advanced Construction Technology (Seme...A Makwana
 
Excavation and Ground water control1.pptx
Excavation and Ground water control1.pptxExcavation and Ground water control1.pptx
Excavation and Ground water control1.pptxssusercbae26
 
caissons and cofferdam in substructure construction
caissons and cofferdam in substructure constructioncaissons and cofferdam in substructure construction
caissons and cofferdam in substructure constructionChinnuNinan
 
NRCS Pond Construction
NRCS Pond ConstructionNRCS Pond Construction
NRCS Pond ConstructionGrant Schultz
 
Module 1 - Jacking techniques.pptx
Module 1 - Jacking techniques.pptxModule 1 - Jacking techniques.pptx
Module 1 - Jacking techniques.pptxChinnuNinan
 
Chapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsChapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsKHUSHBU SHAH
 
Underwater construction
Underwater constructionUnderwater construction
Underwater constructionHetviPatel58
 
Construction dewatering
Construction dewateringConstruction dewatering
Construction dewateringShubham Parab
 
dewateringtechniques 2.pptx
dewateringtechniques 2.pptxdewateringtechniques 2.pptx
dewateringtechniques 2.pptxCarolTumaneng
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt1971995
 
Presentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalPresentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalIEI GSC
 
tunnelsppt-170126104231-converted (1)-converted.pdf
tunnelsppt-170126104231-converted (1)-converted.pdftunnelsppt-170126104231-converted (1)-converted.pdf
tunnelsppt-170126104231-converted (1)-converted.pdfBalpreetSingh47890
 
Methos of irrigation
Methos  of  irrigationMethos  of  irrigation
Methos of irrigationBrijesh Patel
 
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTUVATSAL PATEL
 

Ähnlich wie Box Jacking Process & Methods Explained in 40 Characters (20)

CAISSON PPT.pptx
CAISSON PPT.pptxCAISSON PPT.pptx
CAISSON PPT.pptx
 
Control of ground water in excavations_Advanced Construction Technology (Seme...
Control of ground water in excavations_Advanced Construction Technology (Seme...Control of ground water in excavations_Advanced Construction Technology (Seme...
Control of ground water in excavations_Advanced Construction Technology (Seme...
 
Excavation and Ground water control1.pptx
Excavation and Ground water control1.pptxExcavation and Ground water control1.pptx
Excavation and Ground water control1.pptx
 
caissons and cofferdam in substructure construction
caissons and cofferdam in substructure constructioncaissons and cofferdam in substructure construction
caissons and cofferdam in substructure construction
 
NRCS Pond Construction
NRCS Pond ConstructionNRCS Pond Construction
NRCS Pond Construction
 
Module 1 - Jacking techniques.pptx
Module 1 - Jacking techniques.pptxModule 1 - Jacking techniques.pptx
Module 1 - Jacking techniques.pptx
 
Chapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsChapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavations
 
5. Dewatering.pdf
5. Dewatering.pdf5. Dewatering.pdf
5. Dewatering.pdf
 
Underwater construction
Underwater constructionUnderwater construction
Underwater construction
 
UNIT 1a.pdf
UNIT 1a.pdfUNIT 1a.pdf
UNIT 1a.pdf
 
Construction dewatering
Construction dewateringConstruction dewatering
Construction dewatering
 
dewateringtechniques 2.pptx
dewateringtechniques 2.pptxdewateringtechniques 2.pptx
dewateringtechniques 2.pptx
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt
 
Presentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalPresentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canal
 
Wash boring
Wash boringWash boring
Wash boring
 
tunnelsppt-170126104231-converted (1)-converted.pdf
tunnelsppt-170126104231-converted (1)-converted.pdftunnelsppt-170126104231-converted (1)-converted.pdf
tunnelsppt-170126104231-converted (1)-converted.pdf
 
Methos of irrigation
Methos  of  irrigationMethos  of  irrigation
Methos of irrigation
 
5. Dewatering F1.pdf
5. Dewatering F1.pdf5. Dewatering F1.pdf
5. Dewatering F1.pdf
 
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
 
Akash verma.pptx
Akash verma.pptxAkash verma.pptx
Akash verma.pptx
 

Kürzlich hochgeladen

The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 

Kürzlich hochgeladen (20)

The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 

Box Jacking Process & Methods Explained in 40 Characters

  • 2. EXPLANATION • It is the process in which a pre-cast R.C.C box or a rigid box is pushed into the soil with the help of hydraulic jacks • It is non-intrusive method beneath the existing surface. • It is more often used when a subway or a aqueduct or a underground structure is to be constructed. • It enables the traffic flow without disruption.
  • 3. R.C.C BOX JACKING • First the box section is designed and cast at the site or can be transported to the site according to the requirement. • The foundation boxes are jacked into the ground designed to carry the dead and the live loads. • Then the high capacity jacks are placed at the back and it pushes the box into the ground. • A purpose designed tunneling shield is provided in the front end.
  • 4. • Then the box is jacked carefully through the earth. • Excavation and jacking are done in small increments in advance. • Measures should be taken to prevent the soil being dragged towards the box. R.C.C BOX JACKING Cont…
  • 7. THRUST BORING METHOD • It is a process of simultaneously jacking the pipe through the earth while removing the earth inside the box by means of a rotating auger. • Unstable conditions- the end of auger is kept retracted inside the encasement so as not to cause voids. • Stable conditions- the auger can be successfully extended beyond the encasement. • This can be successfully used in any kind of soil conditions.
  • 8. PROBLEMS ENCOUNTERED IN JACKING • Settlement of the above ground. • Seepage of ground water. • Caving in of soil etc.
  • 9. FREEZING OF GROUND • This method is used when we encounter the problem of ground water seepage and settlement of ground. • In this method a brine solution is continuously passed through the pipes fixed in the soil. • The temperature of the brine would be -30°c. • So when this brine solution is circulated through these pipes it freezes the ground and the ground behaves like an ice block.
  • 10. FREEZING OF GROUND Cont… • The spacing of the freezing pipes will vary according to the type of soil, its permeability and other factors. • Generally it is kept at a spacing of 1.2 m
  • 11. PROBLEMS IN FREEZING • The main problem in the freezing method is the UPHEAVING of the above ground. • To avoid the upheavement problem we should be careful in the ground freezing process and the temperature of the brine solution.
  • 12. CASE STUDY - SOUTHERN BOSTON PIERS TRANSIT WAY • The carriageway has to go beneath – a Russian building,100 year old • 2m thick soil was frozen. • Under pinning was also done using mini piles.
  • 13. PLAN OF THE RUSSIAN BUILDING
  • 14. ADVANTAGES • Timely completion of project. • No disruption of traffic. • No need to divert the traffic. DISADVANTAGES • Cost of project increases. • Skilled personnel required. • Safety precautions to be done properly.