7 Themes of Prince 2 Barry Hodge
Theme 1: Business Case
• “The purpose of the Business Case theme is to establish
mechanisms to judge whether the project is (and remains) desirable,
viable and achievable as a means to support decision making in its
(continued) investment.”
What that means in plain English
• Why is it worth doing the project? As the project continues you are
supposed to check that it is still worth doing. For example imagine
your project was to launch a new tablet that treated a disease. Then
while you were doing the project someone finds a cure for the
disease. There would be no point continuing with the project as it
would no longer be viable. Also as part of the business case you
need to confirm whether the project can actually be done.
Purpose of Business Case is that the project is:
	 •	 Desirable (Worth doing)
	 •	 Viable (Still worth doing)
	 •	 Achievable (Is possible to do)
Prince2 States
“The business justification is documented in a Business Case describing the reasons for the
project based on estimated costs, risks and the expected benefits.”
What this means in plain English
It is WHY the project exists.
Rules of Prince2:
	 •	 A project should not start without a business case
	 •	 The project should be stopped or changed if the business case is no longer viable
4 Activities of the
Business Case Theme
•	 Develop – getting the right
information upon which decisions
can be made

•	 Verify – assessing whether
the project is (still) worthwhile

•	 Maintain – to update the
Business Case with actual costs
and benefits and current forecast
for costs and benefits

•	 Confirm – assessing whether
the intended benefits have been
(or will be) realized. Confirming
benefits will mostly take place
post project.
Contents of a
Business Case
A typical business case includes the following:

•	 Executive Summary

•	 Reasons – why the project is required

•	 Business Options – do nothing, do the
minimum, do something

•	 Expected Benefits – achieved
outcomes

•	 Expected Dis-Benefits – a negative
consequence of the project

•	 Timescale – how long it will take

•	 Costs – how much is it going to cost

•	 Investment Appraisal – when will the
project payback

•	 Major Risks – by doing this project
Theme 2: Organization
• “The purpose of the Organization theme is to define and
establish the project’s structure of accountability and
responsibilities (the who?).”
What that means in plain English
• This is identifying who the people are who make the
major decisions such as cost on the project. The project
manager answers to these people.
Project Interests
• Business – Is concerned with the
investment in the project. Appoints
an Executive to look after the
business interests

• User – Affected by what the
project produces. A Senior User is
appointed to make sure the project
delivers the desired output.

• Supplier – Responsible for
delivering the project. A Senior
Supplier is appointed to represent
the project delivery team

• The Executive, Senior User and
Senior Supplier make up the
project board
The project exists in the middle
where the three interests overlap.
Four Levels of
Management
Project Board – Responsible for the overall
management and direction of the project.

The Project Board will:

•	 Communicate with stakeholder who are
outside of the project

•	 Approve resources and plans

•	 Approve the completion of each stage

•	 Authorize the start of the next stage

•	 Authorize any changes that result in the
project exceeding set tolerances

Project Manager – Responsible for the day to day
management of the project. Prime responsibility for
the project manager is to ensure that the project
does not exceed the set tolerances of time, cost,
quality and scope.

Team Manager – Responsible for the production of
the products that they have been assigned to do by
the Project Manager
The reason for having the four levels is to
separate the delivery parts of the project
from those that are making the decisions
about the direction of the project.
Theme 3: Quality
• “The purpose of the Quality theme is to define and
implement the means by which the project will verify
products that are fit for purpose”
What that means in plain English
• Are people going to get what they asked for, will it meet
their needs and how will you know that it will.
Prince2 States Quality is:
	 •	 Meet business expectations
	 •	 Enable the desired benefits to be achieved
The Prince2 Approach to Quality:
	 •	 Identify all the project’s products
	 •	 Include quality criteria within product description
	 •	 Implement and track quality methods throughout the project
To do this approach there is quality planning and quality control.
The first two in the approach is covered by quality planning and the
second is covered by quality control.
Quality Planning is:
	 •	 Understanding the customer’s quality expectations
	 •	 Define the project’s acceptance criteria
	 •	 Documenting the customer’s quality expectations
	 •	 Documenting the project’s acceptance criteria in the Project
Production Description
	 •	 Formulating a Quality Management Strategy
	 •	 Writing clear Product Descriptions containing quality criteria,
quality tolerances, quality method and quality responsibilities
	 •	 Setting up the Quality Register
Quality Control is:
	 •	 Carrying out the quality methods
	 •	 Maintaining quality and approval records
	 •	 Gaining acceptance
Theme 4: Plans
• “The purpose of the Plans theme is to facilitate
communication and control by defining the means of
delivering the products (the where and how, by whom,
and estimating the when and how much).”
What that means in plain English
• Who is going to do what and when are they going to do it
3 Levels of Planning
	 •	 Project Plan
	 •	 Stage Plans and Exception Plans
	 •	 Team Plans
Project Plan – shows at a high level what will be done and when
Stage Plan – a detailed plan about the stage that the project is at
Exception Plan – a plan to recover from a tolerance that has been
exceeded
Team Plan – an optional plan for team managers to allocate work
to team members
Theme 5: Risk
• “The purpose of the Risk theme is to identify and control
uncertainty and, as a result improve the ability of the
project to succeed.”
What that means in plain English
• Predict what might happen and do something to reduce
the chance of it happening
What is a Risk?
• Something that may happen that if it does will impact
on the project. If it is a negative then it is viewed as a
threat. If it is a positive then it is viewed as an
opportunity.
What is Risk Management Strategy?
• How the risks will be identified and managed during
the project.
Risk Management
Procedure
• Identify (context and risks)

• Assess (estimate and evaluate)

• Plan

• Implement

• Communicate
Identify
Context – Gather information about the
project to understand the specific
objectives that are at risk and produce a risk
management strategy for the project

Risks – Understand the threats and
opportunities that may affect the project’s
objectives

•	 Cause – Describe source of the risk

•	 Event – Describe area of uncertainty

•	 Effect – Describe impact on the project
Plan
Come up with a number of options for responding to threats and
opportunities
Threat Responses:
	 •	 Avoid
	 •	 Reduce (probability and/or impact)
	 •	 Fallback (reduces impact)
	 •	 Transfer (reduces impact and often only financial impact
	 •	 Share
	 •	 Accept
Opportunity Responses:
	 •	 Exploit
	 •	 Enhance
	 •	 Share
	 •	 Reject
Implement
Ensure that planned risk responses are actioned, effectiveness
monitored and corrective action taken when responses do not
match expectations.
	 •	 Risk Owner – responsible for making sure the risk is
monitored and managed
	 •	 Risk Actionee – Individual assigned to carry out the work
Risk Budget
Money set aside in the project budget to fund the response to
risks.
Communication
Happens continuously both internal and external to the project
Risks are communicated as part of the following products:
	 •	 Checkpoint reports
	 •	 Highlight reports
	 •	 End stage reports
	 •	 End project reports
	 •	 Lessons report
Theme 6: Change
• “The purpose of the change theme is to identify assess
and control any potential and approved changes to the
baseline.”
What that means in plain English
• Get permission before doing something that has not
already been agreed.
Prince 2 states
• “The Aim is not to prevent change but to ensure that
every change is agreed by the relevant authority
before it takes place.”
What that means in plain English
• Make sure the Executive says yes before you do
anything.
Types of Issues
Changes are considered a type of issue. The types of
issues are:
	 •	 Request for Change – Changes to what has
previously been agreed
	 •	 Off-Specification – Something that should be
delivered as part of the project but is forecast not to be
done
	 •	 Problem/Concern – Anything that the Project
Manager needs to resolve or escalate
Configuration Management
Configuration management is how products or items will be created,
maintained and controlled. There are 5 core activities:
	 •	 Planning – What level of configuration is required and how will it
be achieved
	 •	 Identification – Specifying and identifying all components of the
project’s products at the required level of control
	 •	 Control – Approve and baseline products and make only
authorized changes
	 •	 Status Accounting – The reporting of all past and present data
for each product through a product status account
	 •	 Verification and Audit – Conducting a configuration audit
Theme 7: Progress
• “The purpose of the progress theme is to establish
mechanisms to monitor and compare actual
achievements against those planned; provide a forecast
for the project objectives and the projects continued
viability; and control any unacceptable deviations.”
What that means in plain English
• To measure achievement against the plan and predict
how the project will continue to run
Progress Controls
Progress controls enable the next level of management to:
	 •	 Monitor progress
	 •	 Compare level of achievement with plan
	 •	 Review plans and options against future situations
	 •	 Detect problems and identify risks
	 •	 Initiate corrective action
	 •	 Authorize further work
Tolerances and Exceptions
Tolerances can be set so the project can run day to day without the need to
escalate to the next level of management if the plan is slightly exceeded.
There are six tolerance levels and these are:
	 •	 Time
	 •	 Cost
	 •	 Scope
	 •	 Risk
	 •	 Quality
	 •	 Benefits
An exception is when something is going to exceed the agreed tolerance level.
Management Stages
Management stages are divisions within the project
where management decisions can be made by:
	 •	 Facilitating review and decision points
	 •	 Enabling decisions to be made before work starts
	 •	 Giving time for clarification
	 •	 Delegating authority to the Project Manager to
manage the next stage by exception (escalate if
tolerances are going to be exceeded)
Summary
There are 7 themes within Prince2 and they run through the project linking common
items together. A theme is different to a principle in that the principles are like guidelines
for the project whereas a theme runs through the project. The 7 themes of Prince2 are:
	 •	 Business Case
	 •	 Organization
	 •	 Quality
	 •	 Plans
	 •	 Risk
	 •	 Change
	 •	 Progress

Weitere ähnliche Inhalte

Was ist angesagt?

The funkiest PRINCE2 Processes revision guide on the internet
The funkiest PRINCE2 Processes revision guide on the internetThe funkiest PRINCE2 Processes revision guide on the internet
The funkiest PRINCE2 Processes revision guide on the internet
Knowledge Train
 

Was ist angesagt? (20)

An introduction to prince2
An introduction to prince2An introduction to prince2
An introduction to prince2
 
PRINCE2 Foundation Classroom slides - Sample - Classic
PRINCE2 Foundation Classroom slides - Sample - ClassicPRINCE2 Foundation Classroom slides - Sample - Classic
PRINCE2 Foundation Classroom slides - Sample - Classic
 
PRINCE2 Foundation Slides - Sample
PRINCE2 Foundation Slides - Sample PRINCE2 Foundation Slides - Sample
PRINCE2 Foundation Slides - Sample
 
The funkiest PRINCE2 Processes revision guide on the internet
The funkiest PRINCE2 Processes revision guide on the internetThe funkiest PRINCE2 Processes revision guide on the internet
The funkiest PRINCE2 Processes revision guide on the internet
 
Project management
Project managementProject management
Project management
 
PRINCE2 Foundation Training Manual by Frank Turley
PRINCE2 Foundation Training Manual by Frank TurleyPRINCE2 Foundation Training Manual by Frank Turley
PRINCE2 Foundation Training Manual by Frank Turley
 
Prince2 - Wissen kompakt
Prince2 - Wissen kompaktPrince2 - Wissen kompakt
Prince2 - Wissen kompakt
 
The new PMP, what it is and how to get prepared for it
The new PMP, what it is and how to get prepared for itThe new PMP, what it is and how to get prepared for it
The new PMP, what it is and how to get prepared for it
 
Project Management Professional (PMP)
Project Management Professional (PMP) Project Management Professional (PMP)
Project Management Professional (PMP)
 
Pmp study-notes
Pmp study-notesPmp study-notes
Pmp study-notes
 
PMO Kick-Off Presentation
PMO Kick-Off PresentationPMO Kick-Off Presentation
PMO Kick-Off Presentation
 
PRINCE2 Sample Project by Frank Turley
PRINCE2 Sample Project by Frank TurleyPRINCE2 Sample Project by Frank Turley
PRINCE2 Sample Project by Frank Turley
 
PMP Exam Notes
PMP Exam NotesPMP Exam Notes
PMP Exam Notes
 
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
 
AXELOS - PRINCE2 Agile® Practitioner
AXELOS - PRINCE2 Agile® PractitionerAXELOS - PRINCE2 Agile® Practitioner
AXELOS - PRINCE2 Agile® Practitioner
 
Successful Project Presentation
Successful Project PresentationSuccessful Project Presentation
Successful Project Presentation
 
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
PMP® Training Video | PMBOK® Guide Sixth Edition Training | PMP® Certificatio...
 
Project Management Basics
Project Management BasicsProject Management Basics
Project Management Basics
 
Standard For Program Management Changes
Standard For Program Management ChangesStandard For Program Management Changes
Standard For Program Management Changes
 
PRINCE2 Grundlagen (Foundation Exam)
PRINCE2 Grundlagen (Foundation Exam)PRINCE2 Grundlagen (Foundation Exam)
PRINCE2 Grundlagen (Foundation Exam)
 

Andere mochten auch

Prince2 Practioner SX31982783
Prince2 Practioner SX31982783Prince2 Practioner SX31982783
Prince2 Practioner SX31982783
Jagannath Sahoo
 
Project management slide - Introduction
Project management slide - IntroductionProject management slide - Introduction
Project management slide - Introduction
Albert Poghosyan
 
Prince2 2009-process-model
Prince2 2009-process-modelPrince2 2009-process-model
Prince2 2009-process-model
Remella Suman
 

Andere mochten auch (18)

PRINCE2 Process Model
PRINCE2 Process ModelPRINCE2 Process Model
PRINCE2 Process Model
 
Prince2 Practioner SX31982783
Prince2 Practioner SX31982783Prince2 Practioner SX31982783
Prince2 Practioner SX31982783
 
Chapter 4
Chapter 4Chapter 4
Chapter 4
 
Project management slide - Introduction
Project management slide - IntroductionProject management slide - Introduction
Project management slide - Introduction
 
Framework for Project Layout Meeting
Framework for Project Layout MeetingFramework for Project Layout Meeting
Framework for Project Layout Meeting
 
Understanding PRINCE 2®
Understanding PRINCE 2®Understanding PRINCE 2®
Understanding PRINCE 2®
 
Prince2 2009-process-model
Prince2 2009-process-modelPrince2 2009-process-model
Prince2 2009-process-model
 
Prince 2 Pt 6
Prince 2 Pt 6Prince 2 Pt 6
Prince 2 Pt 6
 
Prince 2 Pt 5
Prince 2 Pt 5Prince 2 Pt 5
Prince 2 Pt 5
 
Prince 2 Pt 7
Prince 2 Pt 7Prince 2 Pt 7
Prince 2 Pt 7
 
Prince2@ Foundation Certification Course
Prince2@ Foundation Certification CoursePrince2@ Foundation Certification Course
Prince2@ Foundation Certification Course
 
Lessons from Machiavelli's The Prince
Lessons from Machiavelli's The PrinceLessons from Machiavelli's The Prince
Lessons from Machiavelli's The Prince
 
Prince 2 Pt 8
Prince 2 Pt 8Prince 2 Pt 8
Prince 2 Pt 8
 
Prince 2 Pt 3
Prince 2 Pt 3Prince 2 Pt 3
Prince 2 Pt 3
 
Prince 2 Pt 2
Prince 2 Pt 2Prince 2 Pt 2
Prince 2 Pt 2
 
Prince 2 Pt 1
Prince 2 Pt 1Prince 2 Pt 1
Prince 2 Pt 1
 
Prince 2 Pt 4
Prince 2 Pt 4Prince 2 Pt 4
Prince 2 Pt 4
 
Niccolò Machiavelli
Niccolò MachiavelliNiccolò Machiavelli
Niccolò Machiavelli
 

Ähnlich wie 7 Themes of Prince2

project-management.pdf
project-management.pdfproject-management.pdf
project-management.pdf
SAMPREET3
 
02.pptx
02.pptx02.pptx
02.pptx
Maryam522887
 

Ähnlich wie 7 Themes of Prince2 (20)

It project management and best practices
It project management and best practicesIt project management and best practices
It project management and best practices
 
APM Practitioner Qualification revision cards
APM Practitioner Qualification revision cardsAPM Practitioner Qualification revision cards
APM Practitioner Qualification revision cards
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
 
Project Planning and Approval Process
Project Planning and Approval ProcessProject Planning and Approval Process
Project Planning and Approval Process
 
Project Management Process
Project Management ProcessProject Management Process
Project Management Process
 
MODULE III - M.ARCH.pptx
MODULE III - M.ARCH.pptxMODULE III - M.ARCH.pptx
MODULE III - M.ARCH.pptx
 
Mpug 111208 generic
Mpug 111208 genericMpug 111208 generic
Mpug 111208 generic
 
MODULE II - M.ARCH.pptx
MODULE II - M.ARCH.pptxMODULE II - M.ARCH.pptx
MODULE II - M.ARCH.pptx
 
Project Life Cycle.pptx
Project Life Cycle.pptxProject Life Cycle.pptx
Project Life Cycle.pptx
 
ICB Competence, Project Standards
ICB Competence, Project StandardsICB Competence, Project Standards
ICB Competence, Project Standards
 
Logical frameworks
Logical frameworksLogical frameworks
Logical frameworks
 
project mgmt chapter 1.pptx
project mgmt chapter 1.pptxproject mgmt chapter 1.pptx
project mgmt chapter 1.pptx
 
project-management.pdf
project-management.pdfproject-management.pdf
project-management.pdf
 
SPM Unit 1.pptx
SPM Unit 1.pptxSPM Unit 1.pptx
SPM Unit 1.pptx
 
02.pptx
02.pptx02.pptx
02.pptx
 
3 project life cycle
3   project life cycle3   project life cycle
3 project life cycle
 
Module 1.pptx
Module 1.pptxModule 1.pptx
Module 1.pptx
 
Project Planning and Control
Project Planning and Control Project Planning and Control
Project Planning and Control
 
Post Project Evaluation
Post Project EvaluationPost Project Evaluation
Post Project Evaluation
 
Getting the basics right
Getting the basics rightGetting the basics right
Getting the basics right
 

Mehr von Barry Hodge

Mehr von Barry Hodge (8)

My first project
My first projectMy first project
My first project
 
Why projects are causing your organisation staff salary costs to go up
Why projects are causing your organisation staff salary costs to go up Why projects are causing your organisation staff salary costs to go up
Why projects are causing your organisation staff salary costs to go up
 
Why social housing transformation projects get stuck
Why social housing transformation projects get stuckWhy social housing transformation projects get stuck
Why social housing transformation projects get stuck
 
Why i care about social housing
Why i care about social housingWhy i care about social housing
Why i care about social housing
 
What is Great About Being a Virtual Project Manager
What is Great About Being a Virtual Project ManagerWhat is Great About Being a Virtual Project Manager
What is Great About Being a Virtual Project Manager
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
How to Get Stuff Delivered
How to Get Stuff DeliveredHow to Get Stuff Delivered
How to Get Stuff Delivered
 
How to Make a Good Idea Great
How to Make a Good Idea GreatHow to Make a Good Idea Great
How to Make a Good Idea Great
 

Kürzlich hochgeladen

Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
Nauman Safdar
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
daisycvs
 
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecJual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
ZurliaSoop
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
allensay1
 

Kürzlich hochgeladen (20)

Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation Final
 
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...
 
Kalyan Call Girl 98350*37198 Call Girls in Escort service book now
Kalyan Call Girl 98350*37198 Call Girls in Escort service book nowKalyan Call Girl 98350*37198 Call Girls in Escort service book now
Kalyan Call Girl 98350*37198 Call Girls in Escort service book now
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
Cannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 Updated
 
HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
 
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service AvailableNashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
 
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecJual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
 
Pre Engineered Building Manufacturers Hyderabad.pptx
Pre Engineered  Building Manufacturers Hyderabad.pptxPre Engineered  Building Manufacturers Hyderabad.pptx
Pre Engineered Building Manufacturers Hyderabad.pptx
 
joint cost.pptx COST ACCOUNTING Sixteenth Edition ...
joint cost.pptx  COST ACCOUNTING  Sixteenth Edition                          ...joint cost.pptx  COST ACCOUNTING  Sixteenth Edition                          ...
joint cost.pptx COST ACCOUNTING Sixteenth Edition ...
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 

7 Themes of Prince2

  • 1. 7 Themes of Prince 2 Barry Hodge
  • 2. Theme 1: Business Case • “The purpose of the Business Case theme is to establish mechanisms to judge whether the project is (and remains) desirable, viable and achievable as a means to support decision making in its (continued) investment.” What that means in plain English • Why is it worth doing the project? As the project continues you are supposed to check that it is still worth doing. For example imagine your project was to launch a new tablet that treated a disease. Then while you were doing the project someone finds a cure for the disease. There would be no point continuing with the project as it would no longer be viable. Also as part of the business case you need to confirm whether the project can actually be done.
  • 3. Purpose of Business Case is that the project is: • Desirable (Worth doing) • Viable (Still worth doing) • Achievable (Is possible to do) Prince2 States “The business justification is documented in a Business Case describing the reasons for the project based on estimated costs, risks and the expected benefits.” What this means in plain English It is WHY the project exists. Rules of Prince2: • A project should not start without a business case • The project should be stopped or changed if the business case is no longer viable
  • 4. 4 Activities of the Business Case Theme • Develop – getting the right information upon which decisions can be made • Verify – assessing whether the project is (still) worthwhile • Maintain – to update the Business Case with actual costs and benefits and current forecast for costs and benefits • Confirm – assessing whether the intended benefits have been (or will be) realized. Confirming benefits will mostly take place post project.
  • 5. Contents of a Business Case A typical business case includes the following: • Executive Summary • Reasons – why the project is required • Business Options – do nothing, do the minimum, do something • Expected Benefits – achieved outcomes • Expected Dis-Benefits – a negative consequence of the project • Timescale – how long it will take • Costs – how much is it going to cost • Investment Appraisal – when will the project payback • Major Risks – by doing this project
  • 6. Theme 2: Organization • “The purpose of the Organization theme is to define and establish the project’s structure of accountability and responsibilities (the who?).” What that means in plain English • This is identifying who the people are who make the major decisions such as cost on the project. The project manager answers to these people.
  • 7. Project Interests • Business – Is concerned with the investment in the project. Appoints an Executive to look after the business interests • User – Affected by what the project produces. A Senior User is appointed to make sure the project delivers the desired output. • Supplier – Responsible for delivering the project. A Senior Supplier is appointed to represent the project delivery team • The Executive, Senior User and Senior Supplier make up the project board The project exists in the middle where the three interests overlap.
  • 8. Four Levels of Management Project Board – Responsible for the overall management and direction of the project. The Project Board will: • Communicate with stakeholder who are outside of the project • Approve resources and plans • Approve the completion of each stage • Authorize the start of the next stage • Authorize any changes that result in the project exceeding set tolerances Project Manager – Responsible for the day to day management of the project. Prime responsibility for the project manager is to ensure that the project does not exceed the set tolerances of time, cost, quality and scope. Team Manager – Responsible for the production of the products that they have been assigned to do by the Project Manager The reason for having the four levels is to separate the delivery parts of the project from those that are making the decisions about the direction of the project.
  • 9. Theme 3: Quality • “The purpose of the Quality theme is to define and implement the means by which the project will verify products that are fit for purpose” What that means in plain English • Are people going to get what they asked for, will it meet their needs and how will you know that it will.
  • 10. Prince2 States Quality is: • Meet business expectations • Enable the desired benefits to be achieved The Prince2 Approach to Quality: • Identify all the project’s products • Include quality criteria within product description • Implement and track quality methods throughout the project To do this approach there is quality planning and quality control. The first two in the approach is covered by quality planning and the second is covered by quality control.
  • 11. Quality Planning is: • Understanding the customer’s quality expectations • Define the project’s acceptance criteria • Documenting the customer’s quality expectations • Documenting the project’s acceptance criteria in the Project Production Description • Formulating a Quality Management Strategy • Writing clear Product Descriptions containing quality criteria, quality tolerances, quality method and quality responsibilities • Setting up the Quality Register
  • 12. Quality Control is: • Carrying out the quality methods • Maintaining quality and approval records • Gaining acceptance
  • 13. Theme 4: Plans • “The purpose of the Plans theme is to facilitate communication and control by defining the means of delivering the products (the where and how, by whom, and estimating the when and how much).” What that means in plain English • Who is going to do what and when are they going to do it
  • 14. 3 Levels of Planning • Project Plan • Stage Plans and Exception Plans • Team Plans Project Plan – shows at a high level what will be done and when Stage Plan – a detailed plan about the stage that the project is at Exception Plan – a plan to recover from a tolerance that has been exceeded Team Plan – an optional plan for team managers to allocate work to team members
  • 15.
  • 16. Theme 5: Risk • “The purpose of the Risk theme is to identify and control uncertainty and, as a result improve the ability of the project to succeed.” What that means in plain English • Predict what might happen and do something to reduce the chance of it happening
  • 17. What is a Risk? • Something that may happen that if it does will impact on the project. If it is a negative then it is viewed as a threat. If it is a positive then it is viewed as an opportunity. What is Risk Management Strategy? • How the risks will be identified and managed during the project.
  • 18. Risk Management Procedure • Identify (context and risks) • Assess (estimate and evaluate) • Plan • Implement • Communicate
  • 19. Identify Context – Gather information about the project to understand the specific objectives that are at risk and produce a risk management strategy for the project Risks – Understand the threats and opportunities that may affect the project’s objectives • Cause – Describe source of the risk • Event – Describe area of uncertainty • Effect – Describe impact on the project
  • 20. Plan Come up with a number of options for responding to threats and opportunities Threat Responses: • Avoid • Reduce (probability and/or impact) • Fallback (reduces impact) • Transfer (reduces impact and often only financial impact • Share • Accept
  • 21. Opportunity Responses: • Exploit • Enhance • Share • Reject
  • 22. Implement Ensure that planned risk responses are actioned, effectiveness monitored and corrective action taken when responses do not match expectations. • Risk Owner – responsible for making sure the risk is monitored and managed • Risk Actionee – Individual assigned to carry out the work Risk Budget Money set aside in the project budget to fund the response to risks.
  • 23. Communication Happens continuously both internal and external to the project Risks are communicated as part of the following products: • Checkpoint reports • Highlight reports • End stage reports • End project reports • Lessons report
  • 24. Theme 6: Change • “The purpose of the change theme is to identify assess and control any potential and approved changes to the baseline.” What that means in plain English • Get permission before doing something that has not already been agreed.
  • 25. Prince 2 states • “The Aim is not to prevent change but to ensure that every change is agreed by the relevant authority before it takes place.” What that means in plain English • Make sure the Executive says yes before you do anything.
  • 26. Types of Issues Changes are considered a type of issue. The types of issues are: • Request for Change – Changes to what has previously been agreed • Off-Specification – Something that should be delivered as part of the project but is forecast not to be done • Problem/Concern – Anything that the Project Manager needs to resolve or escalate
  • 27. Configuration Management Configuration management is how products or items will be created, maintained and controlled. There are 5 core activities: • Planning – What level of configuration is required and how will it be achieved • Identification – Specifying and identifying all components of the project’s products at the required level of control • Control – Approve and baseline products and make only authorized changes • Status Accounting – The reporting of all past and present data for each product through a product status account • Verification and Audit – Conducting a configuration audit
  • 28.
  • 29. Theme 7: Progress • “The purpose of the progress theme is to establish mechanisms to monitor and compare actual achievements against those planned; provide a forecast for the project objectives and the projects continued viability; and control any unacceptable deviations.” What that means in plain English • To measure achievement against the plan and predict how the project will continue to run
  • 30. Progress Controls Progress controls enable the next level of management to: • Monitor progress • Compare level of achievement with plan • Review plans and options against future situations • Detect problems and identify risks • Initiate corrective action • Authorize further work
  • 31. Tolerances and Exceptions Tolerances can be set so the project can run day to day without the need to escalate to the next level of management if the plan is slightly exceeded. There are six tolerance levels and these are: • Time • Cost • Scope • Risk • Quality • Benefits An exception is when something is going to exceed the agreed tolerance level.
  • 32.
  • 33. Management Stages Management stages are divisions within the project where management decisions can be made by: • Facilitating review and decision points • Enabling decisions to be made before work starts • Giving time for clarification • Delegating authority to the Project Manager to manage the next stage by exception (escalate if tolerances are going to be exceeded)
  • 34.
  • 35. Summary There are 7 themes within Prince2 and they run through the project linking common items together. A theme is different to a principle in that the principles are like guidelines for the project whereas a theme runs through the project. The 7 themes of Prince2 are: • Business Case • Organization • Quality • Plans • Risk • Change • Progress