a     seminar Report On Practical Training Undergone At “Kota Super thermal Power Station” Submitted to RAJASTHAN technical university For the partial fulfilment of the requirement of the degree of  Bachelor of technology in  (electrical engineering) 2011        submitted to: 						Submitted By  : Er. Bharat Bhushan Jain					 Anil Singh (HOD of electrical Department)					B.Tech. IV year             AIET						Roll No- 04 							AIET Department of electrical engineering Arya  institute of engineering and technology kukas, jaipur
	Introduction of KSTPS In April 1973, Central Electricity Authority prepared a Project Report for power station comprising of the two units of each of capacity 110 MW The planning commission cleared the project report in Sept., 1976 for installation of two units each of 110 MW in first estimated cost of Rs. 143 Crores. These two units was manufactured by BHEL, Hyderabad.
Synchronising Date of units
SALIENT FEATURE OF K.S.T.P.S LOCATIONSakatpura, Kota. CAPACITY		1240MW A) 1ST Stage .      	2x110 MW. B) 2nd Stage.	       	2x210 MW. C) 3rd Stage.	       	1x210 MW. D) 4th Stage        		1x195 MW. E)  5th  Stage.       	1x195 MW.(to be commissioned in Sept 2009).
SOURCE OF WATER.	Chambal River. BOILER a) type			 water tube boiler. b )No. of units.		       6 c) Max. efficiency.  BHEL 	(86.6 + 1) % d) Capacity.	      		375 tonnes 1 Hr. e) Steam Pressure     		139 Kg./cm2 f) Steam Temp.		540oC g) No. of draft fans in		i) FD fans 2 Units ( Each boiler)                                     	ii) ID fan 2 Units ( Each boiler ). h) No. of Air fans in Service.    i) Primary	2 Units.                                                	ii) Seal Air fan.	1 Unit.                                               	iii) Scanner.	1 Unit. i)  No. of coal mills in service.     3 Units. j)  No. of Soot blower in service  68
FUELS A)	Coal. i) Type                                    	Stack Coal                       	ii) Calorific Value.		4450 K.Cal./Kg.                       	 iii) Qty. Used. 			3074 tonnes per day.           	 iv) Ash contents.		40%                       	v) Sulphur contents.		0.5%.                       	 vi) Type of Handling.		Belt Conveyor.                       	vii) Type of disposal of Ash.                                    	 a) Fly Ash. Wet                                    	 b) Bottom Ash. Wet. B)	OIL i) Type.	     	 HSD & Furnace Oil.      		ii) Qty. used.      As per requirement & draft 				              conditions.
GENERAL LAYOUT AND BASIC IDEA The conversion from coal to electricity takes place in three stages. Stage 1 The first conversion of energy takes place in the boiler. Coal is burnt in the boiler furnace to produce heat. Carbon in the coal and Oxygen in the air combine to produce Carbon Dioxide and heat. Stage 2 The second stage is the thermodynamic process. The heat from combustion of the coal boils water in the boiler to produce steam. In modern power plant, boilers produce steam at a high pressure and temperature.  The steam is then piped to a turbine.  The high pressure steam impinges and expands across a number of sets of blades in the turbine. 
The impulse and the thrust created rotates the turbine.  The steam is then condensed and pumped back into the boiler to repeat the cycle. Stage 3 In the third stage, rotation of the turbine rotates the generator rotor to produce electricity based of Faraday’s Principle of electromagnetic induction. Control system of station is based on Rankin Cycle. To increase the heat economy and efficiency we use number of modification in the plant.
COMPONENTS OF STEAM POWER PLANT Coal storage Coal handling plant Boiler Boiler furnace Super heater Economizer Air-Preheater Chimney Dust collector Induced draught fan
Forced draught fan Main valve Turbine Alternator Exciter Condenser Cooling tower Pumps Ash storage Ash handling plant
The Kota Super Thermal Power Station is divided into four main circuits:- Fuel and Ash Circuit. Air and Gas Circuit. Feed water and Steam Circuit. Cooling Water Circuit.
BOILERS ,[object Object]
CLASSIFICATION
HORIZONTAL , VERTICAL & INCLINED
FIRE TUBE & WATER TUBE
COMPONENTS:
SUPERHEATER
AIRPREHEATER
EVAPORATOR
ECONOMISER
DEAERATOR

Weitere ähnliche Inhalte

Was ist angesagt?

kota Super Thermal Power Station training ppt
kota Super Thermal Power Station training pptkota Super Thermal Power Station training ppt
kota Super Thermal Power Station training pptEr. Aman Agrawal
 
Kota Thermal Training report by Abhishk mathur
Kota Thermal Training report by Abhishk mathurKota Thermal Training report by Abhishk mathur
Kota Thermal Training report by Abhishk mathurAbhishek Mathur
 
KOTA SUPER THERMAL POWER STATION (KSTPS) by RANJAN NAIK
KOTA SUPER THERMAL POWER STATION (KSTPS) by RANJAN NAIKKOTA SUPER THERMAL POWER STATION (KSTPS) by RANJAN NAIK
KOTA SUPER THERMAL POWER STATION (KSTPS) by RANJAN NAIKRanjan Naik
 
Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant pptPrakash Jarotia
 
Kota super thermal power plant seminar
Kota super thermal power plant seminarKota super thermal power plant seminar
Kota super thermal power plant seminarCentury Rayon
 
Kota super thermal power station
Kota super thermal power stationKota super thermal power station
Kota super thermal power stationAshish Agarwal
 
Kota super thermal power station, kota
Kota super thermal power station, kotaKota super thermal power station, kota
Kota super thermal power station, kotaSourabh Chourasiya
 
Suratgarh Super Thermal Power Plant
Suratgarh Super Thermal Power PlantSuratgarh Super Thermal Power Plant
Suratgarh Super Thermal Power PlantHarshit Madaan
 
Presentation on Kota super thermal power station (KSTPS)
Presentation on Kota super thermal power station (KSTPS)Presentation on Kota super thermal power station (KSTPS)
Presentation on Kota super thermal power station (KSTPS)Anurag Jindal
 
kota thermal power plant
kota thermal power plantkota thermal power plant
kota thermal power plantravi kant
 
Super thermal power station,suratgarh,by rajesh nayak
Super thermal power station,suratgarh,by rajesh nayakSuper thermal power station,suratgarh,by rajesh nayak
Super thermal power station,suratgarh,by rajesh nayakRajesh Nayak
 
SURATGARH SUPER THERMAL POWER STATION
SURATGARH  SUPER  THERMAL POWER    STATION SURATGARH  SUPER  THERMAL POWER    STATION
SURATGARH SUPER THERMAL POWER STATION Sagar Sharma
 
kstps summer training 36 slides
 kstps summer training 36 slides kstps summer training 36 slides
kstps summer training 36 slidesDanveer Singh
 
Kota super thermal power station ppt, rtu
Kota super thermal power station ppt, rtuKota super thermal power station ppt, rtu
Kota super thermal power station ppt, rtuRaghav Chittora
 
Kota super thermal power plant,kstps ppt,RTU
Kota super thermal power plant,kstps ppt,RTUKota super thermal power plant,kstps ppt,RTU
Kota super thermal power plant,kstps ppt,RTUManohar Nagar
 

Was ist angesagt? (20)

K.s.t.p.s. ppt
K.s.t.p.s.  pptK.s.t.p.s.  ppt
K.s.t.p.s. ppt
 
Dev
DevDev
Dev
 
kota Super Thermal Power Station training ppt
kota Super Thermal Power Station training pptkota Super Thermal Power Station training ppt
kota Super Thermal Power Station training ppt
 
Kota Thermal Training report by Abhishk mathur
Kota Thermal Training report by Abhishk mathurKota Thermal Training report by Abhishk mathur
Kota Thermal Training report by Abhishk mathur
 
KOTA SUPER THERMAL POWER STATION (KSTPS) by RANJAN NAIK
KOTA SUPER THERMAL POWER STATION (KSTPS) by RANJAN NAIKKOTA SUPER THERMAL POWER STATION (KSTPS) by RANJAN NAIK
KOTA SUPER THERMAL POWER STATION (KSTPS) by RANJAN NAIK
 
Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant ppt
 
Kota super thermal power plant seminar
Kota super thermal power plant seminarKota super thermal power plant seminar
Kota super thermal power plant seminar
 
Kota super thermal power station
Kota super thermal power stationKota super thermal power station
Kota super thermal power station
 
Kota super thermal power station, kota
Kota super thermal power station, kotaKota super thermal power station, kota
Kota super thermal power station, kota
 
kstps training report
kstps training reportkstps training report
kstps training report
 
Suratgarh Super Thermal Power Plant
Suratgarh Super Thermal Power PlantSuratgarh Super Thermal Power Plant
Suratgarh Super Thermal Power Plant
 
Presentation on Kota super thermal power station (KSTPS)
Presentation on Kota super thermal power station (KSTPS)Presentation on Kota super thermal power station (KSTPS)
Presentation on Kota super thermal power station (KSTPS)
 
kota thermal power plant
kota thermal power plantkota thermal power plant
kota thermal power plant
 
ppt on kstps 2016
ppt on kstps 2016ppt on kstps 2016
ppt on kstps 2016
 
Super thermal power station,suratgarh,by rajesh nayak
Super thermal power station,suratgarh,by rajesh nayakSuper thermal power station,suratgarh,by rajesh nayak
Super thermal power station,suratgarh,by rajesh nayak
 
SURATGARH SUPER THERMAL POWER STATION
SURATGARH  SUPER  THERMAL POWER    STATION SURATGARH  SUPER  THERMAL POWER    STATION
SURATGARH SUPER THERMAL POWER STATION
 
kstps summer training 36 slides
 kstps summer training 36 slides kstps summer training 36 slides
kstps summer training 36 slides
 
Kota super thermal power station ppt, rtu
Kota super thermal power station ppt, rtuKota super thermal power station ppt, rtu
Kota super thermal power station ppt, rtu
 
Mukesh 53
Mukesh 53Mukesh 53
Mukesh 53
 
Kota super thermal power plant,kstps ppt,RTU
Kota super thermal power plant,kstps ppt,RTUKota super thermal power plant,kstps ppt,RTU
Kota super thermal power plant,kstps ppt,RTU
 

Ähnlich wie Anil.ppt

Thermal power plant from A.I.C.E Jaipur
Thermal power plant from A.I.C.E JaipurThermal power plant from A.I.C.E Jaipur
Thermal power plant from A.I.C.E JaipurChandra veer singh
 
Ranjan NTPC KAHALGAON ppt
Ranjan  NTPC KAHALGAON pptRanjan  NTPC KAHALGAON ppt
Ranjan NTPC KAHALGAON pptRanjan kumar
 
Thermal Power Plants
Thermal Power PlantsThermal Power Plants
Thermal Power Plantspeeyush95
 
Urja thermal solutions
Urja thermal solutionsUrja thermal solutions
Urja thermal solutionsHemant Sharma
 
CESC SGS project report
CESC SGS project reportCESC SGS project report
CESC SGS project reportSayanSarkar55
 
Welcome to summer training presentation 2 (1)
Welcome to summer training presentation 2 (1)Welcome to summer training presentation 2 (1)
Welcome to summer training presentation 2 (1)SANDEEP YADAV
 
CSTPS training REPORT
CSTPS training REPORTCSTPS training REPORT
CSTPS training REPORTUday Wankar
 
Performance of the Boiler and To Improving the Boiler Efficiency Using Cfd Mo...
Performance of the Boiler and To Improving the Boiler Efficiency Using Cfd Mo...Performance of the Boiler and To Improving the Boiler Efficiency Using Cfd Mo...
Performance of the Boiler and To Improving the Boiler Efficiency Using Cfd Mo...IOSR Journals
 
Ppe unit 1 - part 1 - Steam power plant
Ppe   unit 1 - part 1 - Steam power plant Ppe   unit 1 - part 1 - Steam power plant
Ppe unit 1 - part 1 - Steam power plant Antwin Koshy
 
Generation of electricity from coal vol 1
Generation of electricity from coal vol 1Generation of electricity from coal vol 1
Generation of electricity from coal vol 1Sunil9009
 
Generation of electricity from coal parul
Generation of electricity from coal  parulGeneration of electricity from coal  parul
Generation of electricity from coal parulSwapnil Sharma
 
Tarun Project Report On NTPC Kanti
Tarun  Project Report On NTPC KantiTarun  Project Report On NTPC Kanti
Tarun Project Report On NTPC KantiTarun Kumar
 
Ae32626632
Ae32626632Ae32626632
Ae32626632IJMER
 
Indian scenario of super critical power plants issues and challenges by ntpc...
Indian scenario of super critical power plants  issues and challenges by ntpc...Indian scenario of super critical power plants  issues and challenges by ntpc...
Indian scenario of super critical power plants issues and challenges by ntpc...Ajay Singhal
 

Ähnlich wie Anil.ppt (20)

Thermal power plant from A.I.C.E Jaipur
Thermal power plant from A.I.C.E JaipurThermal power plant from A.I.C.E Jaipur
Thermal power plant from A.I.C.E Jaipur
 
Ranjan NTPC KAHALGAON ppt
Ranjan  NTPC KAHALGAON pptRanjan  NTPC KAHALGAON ppt
Ranjan NTPC KAHALGAON ppt
 
Thermal Power Plants
Thermal Power PlantsThermal Power Plants
Thermal Power Plants
 
Thermal power plants
Thermal power plantsThermal power plants
Thermal power plants
 
Urja thermal solutions
Urja thermal solutionsUrja thermal solutions
Urja thermal solutions
 
CESC SGS project report
CESC SGS project reportCESC SGS project report
CESC SGS project report
 
Welcome to summer training presentation 2 (1)
Welcome to summer training presentation 2 (1)Welcome to summer training presentation 2 (1)
Welcome to summer training presentation 2 (1)
 
Ntpc unchahar
Ntpc unchaharNtpc unchahar
Ntpc unchahar
 
Pintu raj
Pintu rajPintu raj
Pintu raj
 
CSTPS training REPORT
CSTPS training REPORTCSTPS training REPORT
CSTPS training REPORT
 
5_2019_02_04!01_18_39_AM.docx
5_2019_02_04!01_18_39_AM.docx5_2019_02_04!01_18_39_AM.docx
5_2019_02_04!01_18_39_AM.docx
 
Performance of the Boiler and To Improving the Boiler Efficiency Using Cfd Mo...
Performance of the Boiler and To Improving the Boiler Efficiency Using Cfd Mo...Performance of the Boiler and To Improving the Boiler Efficiency Using Cfd Mo...
Performance of the Boiler and To Improving the Boiler Efficiency Using Cfd Mo...
 
Power plant
Power plantPower plant
Power plant
 
Ppe unit 1 - part 1 - Steam power plant
Ppe   unit 1 - part 1 - Steam power plant Ppe   unit 1 - part 1 - Steam power plant
Ppe unit 1 - part 1 - Steam power plant
 
Generation of electricity from coal vol 1
Generation of electricity from coal vol 1Generation of electricity from coal vol 1
Generation of electricity from coal vol 1
 
Generation of electricity from coal parul
Generation of electricity from coal  parulGeneration of electricity from coal  parul
Generation of electricity from coal parul
 
Tarun Project Report On NTPC Kanti
Tarun  Project Report On NTPC KantiTarun  Project Report On NTPC Kanti
Tarun Project Report On NTPC Kanti
 
Ae32626632
Ae32626632Ae32626632
Ae32626632
 
Indian scenario of super critical power plants issues and challenges by ntpc...
Indian scenario of super critical power plants  issues and challenges by ntpc...Indian scenario of super critical power plants  issues and challenges by ntpc...
Indian scenario of super critical power plants issues and challenges by ntpc...
 
COAL FIRED BOILER -PRINCIPALS.pdf
COAL FIRED BOILER -PRINCIPALS.pdfCOAL FIRED BOILER -PRINCIPALS.pdf
COAL FIRED BOILER -PRINCIPALS.pdf
 

Kürzlich hochgeladen

Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Roland Driesen
 

Kürzlich hochgeladen (20)

Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...
 

Anil.ppt

  • 1. a seminar Report On Practical Training Undergone At “Kota Super thermal Power Station” Submitted to RAJASTHAN technical university For the partial fulfilment of the requirement of the degree of Bachelor of technology in (electrical engineering) 2011 submitted to: Submitted By : Er. Bharat Bhushan Jain Anil Singh (HOD of electrical Department) B.Tech. IV year AIET Roll No- 04 AIET Department of electrical engineering Arya institute of engineering and technology kukas, jaipur
  • 2. Introduction of KSTPS In April 1973, Central Electricity Authority prepared a Project Report for power station comprising of the two units of each of capacity 110 MW The planning commission cleared the project report in Sept., 1976 for installation of two units each of 110 MW in first estimated cost of Rs. 143 Crores. These two units was manufactured by BHEL, Hyderabad.
  • 4. SALIENT FEATURE OF K.S.T.P.S LOCATIONSakatpura, Kota. CAPACITY 1240MW A) 1ST Stage . 2x110 MW. B) 2nd Stage. 2x210 MW. C) 3rd Stage. 1x210 MW. D) 4th Stage 1x195 MW. E) 5th Stage. 1x195 MW.(to be commissioned in Sept 2009).
  • 5. SOURCE OF WATER. Chambal River. BOILER a) type water tube boiler. b )No. of units. 6 c) Max. efficiency. BHEL (86.6 + 1) % d) Capacity. 375 tonnes 1 Hr. e) Steam Pressure 139 Kg./cm2 f) Steam Temp. 540oC g) No. of draft fans in i) FD fans 2 Units ( Each boiler) ii) ID fan 2 Units ( Each boiler ). h) No. of Air fans in Service. i) Primary 2 Units. ii) Seal Air fan. 1 Unit. iii) Scanner. 1 Unit. i) No. of coal mills in service. 3 Units. j) No. of Soot blower in service 68
  • 6. FUELS A) Coal. i) Type Stack Coal ii) Calorific Value. 4450 K.Cal./Kg. iii) Qty. Used. 3074 tonnes per day. iv) Ash contents. 40% v) Sulphur contents. 0.5%. vi) Type of Handling. Belt Conveyor. vii) Type of disposal of Ash. a) Fly Ash. Wet b) Bottom Ash. Wet. B) OIL i) Type. HSD & Furnace Oil. ii) Qty. used. As per requirement & draft conditions.
  • 7. GENERAL LAYOUT AND BASIC IDEA The conversion from coal to electricity takes place in three stages. Stage 1 The first conversion of energy takes place in the boiler. Coal is burnt in the boiler furnace to produce heat. Carbon in the coal and Oxygen in the air combine to produce Carbon Dioxide and heat. Stage 2 The second stage is the thermodynamic process. The heat from combustion of the coal boils water in the boiler to produce steam. In modern power plant, boilers produce steam at a high pressure and temperature.  The steam is then piped to a turbine.  The high pressure steam impinges and expands across a number of sets of blades in the turbine. 
  • 8. The impulse and the thrust created rotates the turbine.  The steam is then condensed and pumped back into the boiler to repeat the cycle. Stage 3 In the third stage, rotation of the turbine rotates the generator rotor to produce electricity based of Faraday’s Principle of electromagnetic induction. Control system of station is based on Rankin Cycle. To increase the heat economy and efficiency we use number of modification in the plant.
  • 9.
  • 10. COMPONENTS OF STEAM POWER PLANT Coal storage Coal handling plant Boiler Boiler furnace Super heater Economizer Air-Preheater Chimney Dust collector Induced draught fan
  • 11. Forced draught fan Main valve Turbine Alternator Exciter Condenser Cooling tower Pumps Ash storage Ash handling plant
  • 12. The Kota Super Thermal Power Station is divided into four main circuits:- Fuel and Ash Circuit. Air and Gas Circuit. Feed water and Steam Circuit. Cooling Water Circuit.
  • 13.
  • 16. FIRE TUBE & WATER TUBE
  • 23.
  • 24. BLADE
  • 27. STEAM TEMPERATURE : - 535-545 0C
  • 28.
  • 29. Coal handling broadly divide into three sections: Wagon Unloading System. Crushing System. Conveying System.
  • 30. ASH HANDLING PLANT Fuel and Ash Plant. Air and Gas Plant. Ash Disposal and & Dust Collection Plant.
  • 31. Control Room In control room various controls are provided simultaneously various measurement are made various relays are provided here.