Plan Schedule
management
Define
Activities
Sequence
Activities
Estimate
Activity
resource
Estimate
Activity
Duration
Develop
Schedule
Control
Schedule
Planning
Monitoring &
Controlling
Learn Project Management & prepare for PMP exam:
• Learn visually
• Detailed coverage of all PMP concepts
• Sample Questions
Chapter 6 :
Project Time Management
(Part 2)
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration
Estimate Activity Duration Definition
Important terms
Estimate Activity Duration : ITTO
Main activity estimation techniques
Data flow diagram
Review
Guidelines for exam questions
Self Assessment
6.1 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6. Project Time Management
6.1 Plan Schedule management:
The process of establishing policies, procedures, &
documentation for planning, developing, managing,
executing, & controlling the project schedule
6.2 Define Activities:
The process of identifying and documenting the
specific actions to be performed to produce the project
deliverables.
6.3 Sequence Activities:
The process of identifying and documenting
relationships among the project activities.
By: Anand Bobade (nmbobade@gmail.com)
6. Project Time Management
6.4: Estimate Activity resource:
Estimating the type and quantities of material, human resources,
equipment, or supplies required to perform each activity
6:5 Estimate Activity Duration:
Estimating the number of work periods needed to complete
individual activities with estimated resources
6:6 Develop Schedule:
Analysing activity sequences, durations, resource requirements,
and schedule constraints to create the project schedule model
6.7 Control Schedule:
Monitoring the status of project activities to update project
progress and manage changes to the schedule baseline to achieve
the plan.
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration-> Introduction
SME Technical Lead
Solution
Architect
Quality expert
Estimation is joint activity, respective experts has to estimate
their work. PM is responsible to aggregation.
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration
Estimating number of work periods needed to complete
each activity with estimated resources.
It is a major input to Develop Schedule process.
Activity
Estimating Work Periods per activity With estimated resources
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration-> Important Terms
Example: Painting a house
• 20 daysEfforts
• 10 days
• With 2 resources
Duration
• 15 days
• Includes (2 weekends & 1 day holiday by resources)
Elapsed Time
Day1 Day2 Day3 Day4 Day5 Day6 Day7 Day8 Day9 Day10 Day11 Day12 Day13 Day14 Day15
Work Started
1-Jan (Sunday)
Work completed
15-Jan (Sunday)
Weekend Weekend
Resource on
Holiday
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration-> Important Terms
Efforts:
• Labour units required to complete activity.
• Expressed in Hours, Days or Weeks.
Duration (work days or work weeks):
• Total time (work periods) to complete the activities
based on the resources availability.
• Does not include holidays & waiting periods.
Elapsed Time
• Calendar time required to complete activities based on
resource availability & including holidays.
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration
Inputs (10)
• Schedule management
plan
• Activity list
• Activity attributes
• Activity resource
requirements
• Resource calendars
• Project scope statement
• Risk register
• RBS (Resource breakdown Structure)
• EEF
• OPA
Tools &
Techniques (6)
• Expert judgment
• Analogous estimating
• Parametric estimating
• Three-point estimating
• Group decision-making
techniques
• Reserve analysis
Outputs (2)
• Activity duration
estimates
• Project documents
updates
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration -> Input
Schedule
Management
Plan
Activity list Activity
Attributes
Activity
resource req.
Resource
Calendars
Project Scope
Statement
Risk Register
Resource
breakdown
structure
EEF OPA
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration->Input->Schedule MP
Schedule
Management
plan
Estimation techniques & guidelines.
Project Schedule Model
Organizational Policies & procedure
Process Description
Establishes policies, procedures & documentation
for planning, developing, managing, executing &
controlling project schedule.
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration->Input->Activity List
Activity list
A list of all activities under each work package.
Activity ID WBS Id Name Description
501 W50 Compare Furniture brands
502 W50 Find showrooms
503 W50 Get Quotes
504 W50 Compare Quotes
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration->Input->Activity Attributes
Activity
attributes
Additional details of activities, which are useful for
estimation.
Activity description
Predecessor
activities
Successor activities
Logical relationships Leads and lags
Resource
requirements
Imposed dates Constraints Assumptions
Person responsible
Geographic area or
place
Calendar
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Dur.->Inputs->Activity Resource Req
Activity
Resource
Requirements
The types and quantities of resources required for
each activity in a work package.
Aggregated to determine resource estimation for
each work package.
Resource Type
Resource
Quantity
Total
Resources for
Work Package
Activity ID WBS Id Name Resource Type Quantity
601 W51 Unit Testing Developer 5
602 W51 System Testing Test Analyst 10
603 W51 Performance Testing Sr. Performance
Test Analyst
2
604 W51 Security testing Security expert 2
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration->Input->Resource Calendar
Identifies working days & shifts when each resource is
available.
Details about how long resource will be available.
Other details – Skill, Skill levels, location etc
Resource
Calendars
• Resource may be material, human resources, equipment etcRemember:
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Dur.->Input->Project Scope Statement
Project Scope
statement
Project scope statement provides description of the
Project scope
Major deliverables
Assumptions & Constraints
• Expect senior expert to work on the technical design due to
requirements complexity.
• Impact on estimation: Longer estimate; multiple resource
may not be able to reduce estimate proportionally.
Assumption
• Requirement has to be implemented before 1-Aug, due to
government legislation.
• Impact on estimation: Multiple resource may be added to
shorten the duration of activity.
Constraint
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration->Input->Risk Register
Risk
Register
Concerns with results of Risk analysis & response
planning.
List of Risks related to estimations & resources.
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration->Inputs-> RBS
Resource
Breakdown
Structure
Hierarchical representation of resources by category or
type.
Used for searching Resources.
Construction Project
Labor
Managers
Manager1
Manager2
Workers
Worker1
Worker2
Worker3
Material
Building
Office
setup
Equipment
Desktop
Laptop
Printer
Projector
Supplies
Printer
Cartridges
Papers
Stationary
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration -> Input -> EEF
EEF
Duration estimating databases & other reference data.
Productivity metrics.
Published commercial information.
Location of team members.
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration -> Input -> OPA
OPA
Historical duration information.
Project calendars.
Scheduling methodology.
Lessons learned.
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration ->Tools & Techniques
Expert Judgement
Analogues
estimation Parametric
estimation
Three point
estimation
Group decision
making
Reserve Analysis
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration -> T&T -> Expert Judgement
Expert
Judgement
All estimations should be done by Experts.
Expert can be internal or external.
Complex project need many experts.
Uses experience of similar projects or instinct.
SME Technical Lead
Solution Architect Quality expert
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration -> T&T
Estimation Techniques: Same in Time management & Cost management
Analogues
estimation
Parametric
estimation
Three point
estimation
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration -> T&T -> Analogues estimation
Analogues
estimation
Estimate duration of activity using historical data
from a similar activity or a project.
Uses historical information, expert judgment.
Think “analogy” – something similar
Relatively quick and low cost
It is gross value estimation approach.
Parameters used:
Duration Budget Size Weight Complexity
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration -> T&T -> Analogues estimation
Analogues
estimation
Computer Lab in School A Computer Lab in School B
Used when:
• Limited information is available.
• Similar project information
available.
• Experienced estimator.
In this scenarios - Information
available is
• Computer configurations
• Computer installation duration -
30 min
• No. of computer configured - 20
Similar
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration -> T&T -> Parametric estimation
Parametric
estimation
Algorithm is used to calculate duration based on
historical data & project parameters.
Uses statistical relationship between historical data
& other parameters.
Railroad Project Highway Project
• Accuracy of historical data.
• Sophistication & scalability of model.
• Quantifiable parameters
Can be highly
accurate
based on:
E.g., Construction
estimation software
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration->T&T->Three point estimation
Three point
estimation
Estimate duration by applying an average of optimistic, pessimistic
& most likely estimates when there is uncertainty in estimates.
This is also called as PERT techniques (Program Evaluation and
Review Technique).
• = (O + M + P) / 3Triangular Distribution
• = (O + 4M + P) / 6
Beta Distribution
(Weighted average)
What's efforts required for activity1:
Optimistic = 10 hours (coding guru)
Most likely = 12 hours (Regular prog.)
Pessimistic = 16 hours (New prog.)
Estimation Discussion meeting
• = 10+12+16 / 3
• = 12.66 hours
Triangular
• = [10 + (4X12) + 16] / 6
• = 12.33 hours
Beta
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration->T&T->Three point estimation
Question:
In software project, a module was estimated to take 25 hours for average
programmer as the most likely estimate. The pessimistic estimate of 35
hours may be based on the assumption for a newbie, whereas optimistic
estimate of 20 hours for a veteran programmer. Calculate the estimation
using the weighted average technique.
A. 25
B. 25.5
C. 25.83
D. 26
Weighted average
= (P + 4M + O)/6
= (20 + 4*25 + 35)/6 = 25.83 hours
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration->T&T->Three point estimation
Three point
estimation
• = ( P – O ) / 6Standard Deviation (SD)
Standard deviation represents the distance a given
point is from the mean. It is also called sigma, or s.
Standard
Deviation’s:
±1σ = 68.27%
±2σ = 95.45%
±3σ = 99.73%
This is really an approximation of standard deviation. SD
calculation/formula in Quality theories like Six Sigma is different.
mean, median, and
mode are all the
same.
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration->T&T->Three point estimation
Question:
In software project, a module was estimated to take 25 hours for average
programmer as the most likely estimate. The pessimistic estimate of 35
hours may be based on the assumption for a newbie, whereas optimistic
estimate of 20 hours for a veteran programmer. Using the weighted average
technique, you determine that there is a 95.5% probability that the module
will be completed in:
A. Between 25.83 and 28.33 hours
B. Between 23.33 and 28.33 hours
C. Between 25.83 and 30.33 hours
D. Between 20.83 and 30.33 hours
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration->T&T->Three point estimation
Step 1:
• Weighted average = (P + 4M + O)/6
• = (20 + 4*25 + 35)/6 = 25.83 hours
Step 2:
• Standard deviation = (P – O)/6
• = 2.5 hours
Step 3: What is the range?
• Upper end of the range equals the weighted average + (1, 2, or 3 SD)
• = weighted average + 2σ (Refer to SD 2σ values)
• = 25.83 + 2*2.5 = 30.83 hours
• Lower end of the range equals the weighted average – (1, 2, or 3 SD).
• = 25.83 – 2*2.5 hours = 20.83 hours
• The answer therefore is D
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration->T&T->Three point estimation
Three point
estimation Steps:
Get the total of the estimates for all activities along the critical path.
Take the variance for each activity.
Sum them up across the whole project.
Take the square root.
Variance Formula is used, if you trying to get the estimate
for the whole project.
• = SD ^ 2Activity Variance (AV)
AV is square root of sum of total activity variance.
SD for project as a whole is sum of all AV’s.
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration->T&T->Three point estimation
Three point
estimation
AV is square root of sum of total activity variance.
SD for project as a whole is sum of all AV’s.
4,356 + 0 + 1,089
+ 4,356 = 9,801
AV = √9801
AV= 99
Task1- If SD = 33, then 33 - 100 = -662=4,356
Task2- If SD = 100, then 100 - 100 = 02=0
Task3- If SD = 133, then 133 - 100 = 332=1,089
Task4- If SD = 166, then 166 - 100 = 662=4,356
If SD = 33, then 332 = 1,089.
If you sum those figures 1089 + 10,000 + 17,689 + 2,7556 = 56,334.
Then AV = √ 56,334 or 237.34.
The AV is not the mean. The mean would be 56,334 ÷ 4 = 14,083
The AV is also not the mean of the sum of the SD.
That would be 33 + 100 + 133 + 166 = 432 ÷ 4 = 108
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration->T&T-> Reserve Analysis
Reserve Analysis
Contingency reserves (time reserves or buffers) are
used in schedule to account schedule uncertainty.
PM has to use reserve to protect baseline & constantly
reduce or eliminate it.
Quantitative analysis like Monte Carlo can be used to
identify reserves.
Reserve can be @
Activity level
Work package
level
Can be fixed
amount
Can be % of the
estimates
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration->T&T->Group decision Making
Brainstorming: To generate and collect Multiple
ideas related to estimation.
Delphi Techniques: Structured
communication technique developed as
systematic, interactive forecasting method which
relies on a panel of experts.
Nominal group techniques: Enhances
brainstorming with a VOTING process used to
rank the most useful ideas for further
brainstorming or for prioritization
Group Decision
Making
Assessment process with multiple alternatives with
an expected outcome in the form of future actions.
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration -> Output
Activity duration
estimates
Project
Documents
update
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration->Output->Activity Duration estimates
Activity duration
estimates
• It is important to properly communicate estimates.
• Estimates should be given in range.
• State the confidence level.
Communicatin
g estimate:
Sr. No Activity Duration Description
1 Requirement Gathering 30 days
2 Development 90 days
3 System Testing 15 days
4 User acceptance Testing 20 days
5 Performance Testing 5 days
6 Handover 5 days
7 Project closure 5 days
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration->Outputs->Proj. doc. update
Project
Documents
update
• Duration estimates
• Basis of estimates
Activity
attributes
• Assumptions
• Contingencies
Risk
register
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration->Review
Estimate should be given by experts
Three estimating techniques - Analogues, Parametric & Three point
Estimation should be performed for each activity
Perform reserve analysis
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration-> Questions -1
Which one of the below is not a Three point estimation technique:
A. PERT estimation
B. Triangular Distribution
C. Beta Distribution
D. Standard Deviation
D - Standard Deviation
Both are estimation techniques (BETA distribution [also called as PERT] and Triangular
Distribution )
By: Anand Bobade (nmbobade@gmail.com)
6.5 Estimate Activity Duration-> Questions -2
Which one of the below is not a estimation technique that is used in both Duration & Cost estimates:
A. Analogues estimation
B. Parametric estimation
C. Three point estimate
D. Aggregation
D - Aggregation
All three are estimation techniques except aggregation
By: Nemanand Bobade (nmbobade@gmail.com)
Learn Project Management & prepare for PMP exam:
• Learn visually
• Detailed coverage of all PMP concepts
• Sample Questions
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule
Develop Schedule Definition
Develop Schedule : ITTO
What is PDM & schedule network diagram?
What is critical path? What is critical chain?
What is Float or Slack?
Review
Guidelines for exam questions
Self Assessment
6.1 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6. Project Time Management
6.1 Plan Schedule management:
The process of establishing policies, procedures, &
documentation for planning, developing, managing,
executing, & controlling the project schedule
6.2 Define Activities:
The process of identifying and documenting the
specific actions to be performed to produce the project
deliverables.
6.3 Sequence Activities:
The process of identifying and documenting
relationships among the project activities.
By: Anand Bobade (nmbobade@gmail.com)
6. Project Time Management
6.4: Estimate Activity resource:
Estimating the type and quantities of material, human resources,
equipment, or supplies required to perform each activity
6:5 Estimate Activity Duration:
Estimating the number of work periods needed to complete
individual activities with estimated resources
6:6 Develop Schedule:
Analysing activity sequences, durations, resource requirements,
and schedule constraints to create the project schedule model
6.7 Control Schedule:
Monitoring the status of project activities to update project
progress and manage changes to the schedule baseline to achieve
the plan.
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule -> Introduction
• Use existing Schedule model(template)
• Update with information from previous processes
(Activity, sequencing, resources, Duration etc)
Enter
• Developed Project schedule model
• Optimize schedule by Resource leveling/smoothing,
resource crashing/Fast tracking etc
Optimize
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule
Analysing activity sequences, durations, resource
requirements & schedule constraints to create project
schedule model.
Activity
sequences
Activity
Durations
Resource
Requirements
Schedule
Constraints
To create Project Schedule
Analyze
It generates schedule model with planned dates for completing
project activities.
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule
Inputs (13)
• Schedule management plan
• Activity list
• Activity attributes
• Project schedule network
diagram
• Activity resource
requirements
• Resource calendars
• Activity duration estimates
• Project scope statement
• Risk register
• Project staff assignments
• RBS
• EEF & OPA
Tools &
Techniques(8)
• Schedule network
analysis
• Critical path method
• Critical chain
method
• Resource
optimization
techniques
• Modelling
techniques
• Leads and lags
• Schedule
compression
• Scheduling tool
Outputs (6)
• Schedule baseline
• Project schedule
• Schedule data
• Project calendars
• Project management
plan updates
• Project documents
updates
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule -> Input
Schedule
Manag. plan
Activity list
Activity
Attributes
Proj. Schedule
Network
diagram
Activity
resource req.
Resource
Calendars
Activity
Duration
Estimates
Proj. scope
Statement
Risk Register
Project Staff
assignment
Resource
breakdown
structure
EEF & OPA
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule -> Input -> All
Schedule Management Plan:
• Scheduling method
• Tool to be used & Schedule model etc
Activity list:
• List of all activities to be included in the schedule model.
Activity Attributes:
• Detailed activity information that will be helpful to develop
schedule.
Project Schedule Network diagram:
• Graphically shows activity dependencies.
• Shows predecessors and successors.
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule -> Input -> All
Activity resource requirement:
• Resource type & quantity.
Resource Calendars:
• Holidays, resource vacations, resource availability.
Activity Duration Estimates:
• Work periods required to complete each activity.
Project scope Statement:
• Milestones
• Assumptions & Constraints.
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule -> Input -> All
Risk Register:
• Schedule, estimation & resources related risks.
Project Staff assignment:
• Resource allocations & commitment to specific activities.
Resource breakdown structure:
• Resource category, helpful for finding resources used during
resource analysis & Reporting
EEF:
• Communication channel details, Scheduling tool
OPA:
• Schedule methodology
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->Tools & Techniques
Schedule network
Analysis
Critical Path
method Critical chain
method
Resource
optimization
Technique
Modeling
Technique
Leads & Lag Schedule
Compression
Scheduling tool
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->T&T->Schedule Network Analysis
Schedule network
Analysis
Various analytical techniques are used to perform
Schedule Network Analysis & optimize schedule.
Critical path method Critical chain method
What-if analysis Resource optimization
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->T&T->Schedule Network Analysis
Schedule network
Analysis
Activity Activity Description Duration (days) Predecessor
A Collect Requirement 50 -
B System Design 25 A
C Build Module 1 40 B
D Build Module 2 50 C
E Build Module 3 10 B
F Build Module 4 15 E
G Build Module 5 30 B
H System Testing 25 D,F,G
Lets create Project schedule network diagram
based on below activities:
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->T&T->Schedule Network Analysis
Creatig a Project Schedule Network diagram:
Collect
Requirements
(A - 50days)
Start
System
Design
(B - 20d)
Build module 1
(C - 40 day)
Build module 2
(D - 50 day)
Build
module 3
(E - 10 day)
Build module 5
(G - 30 day)
Testing
(H-25 days)
Build
module 4
(F - 15 day)
End
• = A->B->C->D->H = 50+20+40+50+25 = 185Path1
• = A->B->E->F->H = 50+20+10+15+25 = 120Path2
• = A->B->G->H = 50+20+30 = 100Path3
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->T&T-> Schedule network Analysis
Critical Path:
• Sequence of activities that represents longest path
through the project.
Critical path is the shortest possible project duration.
Collect
Req.(50d)
Start
System
Design(20d)
Build module 1
(40 day)
Build module 2
(50 day)
Testing
(25 day)
End
All below
activities are on
critical path
Any delay to
activity on critical
path will delay
project
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->T&T->Critical Path Method
Critical Path
method
Calculates Early start, Early finish, Late start & Late
finish dates.
Performing a forward & backward pass analysis
through the schedule network.
Does not consider resource limitations.
• Defines how long non-critical activities can be delayed without
delaying project
Slack (Float)
Method used to estimate minimum project duration
Determine amount of scheduling flexibility (Float) on the
logical network paths.
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->T&T->Critical Path Method
ES
(Early Start)
Duration EF
(Early Finish)
Activity
LS
(Late Start)
Total Float LF
(Late Finish)
Early Start (ES)EF of
immediately
preceding
activity + 1
(ES+Duration)-1
(LS+Duration)-1
Latest activity
can start
without
delaying project
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->T&T->Critical Path Method
ES
Duration
(50 days)
EF
Collect Requirement (A)
LS Total Float LF
ES
Duration
(20 days)
EF
System Design (B)
LS Total Float LF
Start End
Calculate ES, EF, LS, LF using Forward & Backward pass:
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->T&T->Critical Path Method
ES Duration
(50 days)
EF
Collect Requirement (A)
LS Total Float
(0)
LF
Early Start (ES)
ES Duration
(20 days)
EF
System Design (B)
LS Total Float
(0)
LF
Start
First activity
start on day1
ES = 1
EF=(1+50)-1 = 50
Forward Pass
Backward Pass
ES = 50 +1 = 51 EF = (51+20)-1 = 70
LS = (70-20)+1 = 51LF = 51 -1 = 50LS = (50-50)+1 = 1
1 50 51 70
7051501
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->T&T->Critical Path Method
51 20 70
System Design (B)
51 0 70
40
Build – Module1(C)
50
Build – Module2(D)
25
Testing(H)
10
Build – Module3(E)
15
Build – Module4(F)
30
Build – Module4(G)
Lets calculate ES, EF, LS, LF for remaining activities:
By: Anand Bobade (nmbobade@gmail.com)
Lets calculate ES, EF, LS, LF for remaining activities:
6.6 Develop Schedule->T&T->Critical Path Method
51 20 70
System Design (B)
51 70
40
Build–Module1(C)
50
Build – Module2(D)
25
Testing(H)
10
Build – Module3 (E)
15
Build – Module4(F)
30
Build – Module4(G)
Select
largest no
71
71
71
110
100
80
111
81 95
160 161 185
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->T&T->Critical Path Method
51 20 70
System Design (B)
51
71 40 110
Build–Module1(C)
111 50 160
Build – Module2(D)
161 25 185
Testing(H)
71 10 80
Build – Module3 (E)
81 15 95
Build – Module4(F)
71 30 100
Build – Module4(G)
Select
smallest no
185161
160
160
160
146
111
145
110
136
71
131
70
Lets calculate ES, EF, LS, LF for remaining activities:
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->T&T->Critical Path Method
51 20 70
System Design (B)
51 70
71 40 110
Build–Module1(C)
71 110
111 50 160
Build – Module2(D)
111 160
161 25 185
Testing(H)
161 185
71 10 80
Build – Module3 (E)
136 145
81 15 95
Build – Module4(F)
146 160
71 30 100
Build – Module4(G)
131 160
• FF = Earliest ES of next Activity – ES of current
Activity – Duration of current activity
Amount of time activity can be delayed
Without delaying next activity.
Slack or Float are same. Total Float TF = LF - EF Total Float TF = LS - ES
65 65
TF = 136 - 71
= 65
60
0 0 0 0
TF =
51-51
= 0
TF of activities
on critical path
are Zero
FF for Activity F
161-81-15 = 65
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->T&T->Critical Path Method
• Total amount of time
activity can be delayed
Without delaying Project
finish date.
• TF= Late Start– Early Start
• TF= Late Finish– Early Finish
Total Float
• Amount of time activity can
be delayed Without
delaying next activity.
• FF = Earliest ES of next
Activity – ES of current
Activity – Duration of
current activity
Free Float
Critical Path
method
Difference between Total & Free float:
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->Questions
The following is a small section taken from a large network diagram of CRM project
schedule, which of the statements is true?
A) Task 1 has a free float of 3 days
B) Task 2 has a free float of 6 days
C) Task 3 has a free float of 9 days
D) Task 4 has a free float of 5 days.
Answer : Calculate TF for all Tasks: Task1 = 2, Task 2 = 8, Task 3 = 2 & Task 4 = 2
FF for Task1: ES of next – ES of current – Duration of current => 7 – 1 - 6 = 0
FF for Task2: ES of next – ES of current – Duration of current => 17-7-4 = 6
FF for Task3: ES of next – ES of current – Duration of current => 17-7-10 = 0
FF for Task4: ES of next – ES of current – Duration of current => ???? -17-8 = Can’t calculate
Hence Answer is B) Task 2 has a free float of 6 days
1 6 days 6
Task1
3 8
7 4 days 10
Task2
15 18
17 8 days 24
Task4
19 26
7 10 days 16
Task 3
9 18
FF = 0 FF = 6
FF = 0
2 8
2
2
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->T&T->Critical Chain Method
Critical chain
method
Two types:
Feeding Buffer Project Buffer
Placing buffers on any project schedule path to account
for limited resources & project uncertainties.
It considers effects of resource allocation, optimization,
levelling.
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->T&T->Critical Chain Method
• Placed at point where a chain of activities are not on critical chain.
• Feeds into the critical chain.
Feeding
buffers
• Single buffer.
• Placed at the end of the critical chain.
• Protect slippage along the critical chain.
Project
buffer
Feeding
Buffer
Feeding
Buffer
Project
Buffer
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->T&T-> Resource optimization
Resource Levelling:
• Start and finish dates are adjusted based
on resource constraints.
• Goal is to balance demand for resources
with the available supply.
Resource Smoothing:
• Adjusts schedule activities.
• Ensure requirements for resources do not
exceed certain predefined resource limits.
• May not be able to optimize all resources.
How to allocate resources in a way to bring
maximum output.
Resource
optimization
Technique
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->T&T-> Resource optimization
Resource Smoothing:
• Critical path is not changed & completion date is same
• Activities may be delayed within their free & total float.
Resource Levelling:
• Notice Change in Duration (Critical path changed)
• Timelines extended to adjust resource constraint
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->T&T-> Modeling Technique
Modeling
Technique
What-If Scenario Analysis:
• Evaluating scenarios to predict their effect on
schedule.
• Achieved by performing Network analysis.
• Used to assess feasibility of project schedule
under adverse conditions.
• Used in contingency & response planning.
Enter schedule
in Scheduling
tool
Enter various
scenarios
Simulate•Scenario1
•Scenario4
•Scenario3
•Scenario2
By: Anand Bobade (nmbobade@gmail.com)
Randomly
choose
parameters
Risk 1
Risk 2
Constraints -
Resource
Constraints -
Milestone
6.6 Develop Schedule->T&T-> Modeling Technique
Simulation (Monte Carlo):
• Monte Carlo is simulation technique.
• It calculate multiple project durations with
different sets of activity assumptions.
• Uses probability distributions constructed
from 3 Point estimates to account for
uncertainty.
Modeling
Technique
Develop the
analysis
Model
Generate
Multiple
options
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->T&T-> Modeling Technique
Business Requirement
(BRS)
System Requirement
(SRS)
Sign Contract
Team On-
board
Lead
1 week
Lag
3 week
Lead: It is amount of time where
successor activity can be advanced w.r.t.
predecessor activity.
Lag: It is amount of time whereby a
successor activity will be delayed w.r.t. a
predecessor activity.
Leads & lags
Business Requirement
(BRS – 4 weeks)
System Requirement
(SRS – 4 weeks)
W1 W2 W3 W4 W5 W6 W7 W8 W1 W2 W3 W4 W5 W6 W7 W8
Sign Contract
Team On-
board
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->T&T-> Schedule Compression
Schedule
Compression
Reduce schedule duration without reducing project
scope.
Adhere to schedule constraints, imposed dates, or
other schedule objectives.
Crashing Fast tracking
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->T&T-> Schedule Compression
Crashing:
Shorten schedule duration for least cost by adding
resources.
Fast tracking:
Activities done in sequence are performed in parallel for
at least some portion of their duration.
BRS (1 BA) SRS (1 SA)
BRS (2 BA) SRS (2 SA)
Design Testing
Design
Testing
W1 W2 W3 W4 W5 W6 W7 W8
Crashed
by adding
resources
W1 W2 W3 W4 W5 W6 W7 W8
Fast tracked by
executing
activities in
parallel
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->T&T-> Schedule Compression
Difference between Crashing & Fast tracking
• Adding resources.
• Increases cost.
• Works with activity on
critical path.
Crashing:
• May result in rework.
• Increase Risk.
• Assign activity with
negative float.
Fast tracking:
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->T&T->Scheduling Tool
Scheduling tool
It contain schedule model & expedite scheduling process.
It generate start and finish dates based on the inputs of
activities, resources, activity durations etc.
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule -> Output
Schedule
baseline
Project Schedule Schedule Data
Project
Calendars
PMP updates Project
Documents
update
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->Output-> Schedule Baseline
Schedule
baseline
The approved version of a schedule model that can be
changed only through formal change control procedures.
It is approved by stakeholders as the schedule baseline
Approved baseline dates are compared to the actual to
determine variance.
The schedule baseline is a component of the project
management plan.
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->Output-> Project Schedule
Project Schedule
Presents linked activities with planned dates, durations,
milestones, & resources in the form of Presentation.
It is not completed until resources are assigned
Should be completed along with PM plan
Schedule may be summary or in detail
Presented in Graphical formats - Below three forms
Milestone Chart Bar Chart or Gantt Chart Schedule network Diagram
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->Output-> Project Schedule
Milestone Chart
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->Output-> Project Schedule
Bar chart or Gantt Chart
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->Output-> Project Schedule
Project Schedule Network Diagram
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule->Output-> Schedule Data
Schedule Data
Resource requirements by time period - Resource
histogram.
Scheduling of contingency reserves.
Supporting data generated during preparation of the
schedule.
Milestones
Schedule
activities
Activity
attributes
Assumptions Constraints.
Alternative
schedules
Best-case or
worst-case
Not resource-
leveled or
resource-
leveled
With or
without
imposed dates
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule -> Output-> Project Calendars
Project Calendars
A calendar that identifies working days and
shifts that are available for scheduled activities.
Identify available work days
Marked holidays
Multiple Project calendars may be used
Get updated throughout the project
May identify need of maintaining resource calendars
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule -> Output -> PMP Updates
PMP updates
• If any change is identify in project
schedule management
Update Schedule
Management plan
• Scope changes
• Resources assigned to activities
Update Schedule
baselines
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule -> Output-> Project Documents update
Project
Documents
update
• Duration estimates
• Basis of estimates
Activity
attributes
• New recourse
Activity
Resource
requirements
• Assumptions
• Contingencies
Risk register
• Changes to CalendarCalendars
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule
By: Anand Bobade (nmbobade@gmail.com)
6.6 Develop Schedule -> Review
How to develop schedule & its inputs
Schedule network Analysis
Critical Path method (Total & Free float)
Critical chain method (Feeding Buffer & Project Buffer)
Resource optimization Technique (Resource levelling, Smoothing)
Modeling Technique (What if analysis, Simulations)
Schedule Compression (Crashing & Fast Tracking)
Scheduling tool
Project schedule (Presentation, Bar or Gantt chart, Milestone chart, Project Schedule Network
Diagram)
By: Nemanand Bobade (nmbobade@gmail.com)
Learn Project Management & prepare for PMP exam:
• Learn visually
• Detailed coverage of all PMP concepts
• Sample Questions
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule
Control Schedule Definition
Control Schedule & Integrated change Control
Control Schedule : ITTO
What is performance review?
What are schedule forecast?
Data flow diagram
Review
Guidelines for exam questions
Self Assessment
6.1 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule
• The current status of the project scheduleDetermine
• If the project schedule has changedMonitor
• The factors that create schedule changesInfluence
• The actual changes as they occur & minimize RisksManaging
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule
If any agile approach is utilized, control schedule is concerned with
below:
Determining current status of project schedule by comparing total amount of work
delivered & accepted against estimates of work completed for elapsed time cycle
Conducting retrospective reviews (scheduled reviews to record lessons learned) for
correcting processes and improving, if required
Reprioritizing the remaining work plan (backlog)
Determining the rate at which the deliverables are produced, validated, and
accepted (velocity) in given time per iteration
Determining that the project schedule has changed
Managing the actual changes as they occur.
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule-> Definition
Monitoring the status of project activities to update project
progress & manage changes to schedule baseline to achieve plan.
Monitoring status
of Project activities
Update
project
progress
Manage schedule
baseline changes
It provides the means to recognize the deviation from the plan, &
take corrective & preventive actions & thus minimize the risk.
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule
Inputs (6)
• Project management
plan
• Project schedule
• Work performance data
• Project calendars
• Schedule data
• Organizational process
assets
Tools & Techniques
(7)
• Performance reviews
• Project management
software
• Resource optimization
techniques
• Modelling techniques
• Leads and lags
• Schedule compression
• Scheduling tool
Outputs (6)
• Work performance
information
• Schedule forecasts
• Change requests
• Project management
plan updates
• Project documents
updates
• Organizational
process assets
updates
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule -> Input
PM Plan Project Schedule Work
performance
Data
Project
Calendars
Schedule Data OPA
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule -> Input ->PMP
PM Plan
• How to manage Schedule
• How to control Schedule
Schedule
Management
Plan
• Planned & actual dates
• Used for comparisons
Schedule
baselines
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule -> Input->Project Schedule
Project Schedule
Presents linked activities with planned dates, durations,
milestones, & resources in the form of Presentation.
Having most recent data is key to control the schedule
Latest version of the document
Latest activity details (start & completed activity dates)
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule -> Input->WPD
Work
performance
Data
It is the raw data of the project’s status.
Actual cost Actual duration
The raw observations & measurements identified
during execution of activities.
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule -> Input-> Project Calendars
Identify available work days
Marked holidays
Multiple Project calendars may be used
Get updated throughout the project
May identify need of maintaining resource calendars
Project Calendars
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule -> Input -> Schedule data
Schedule Data
All information which are useful to control schedule activities.
It is constantly reviewed & updated.
List of
activities &
attributes
Milestones Assumptions Constraints
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule -> Input ->OPA
OPA
Schedule control related organizational policies
Schedule control tools
Monitoring & reporting methods used in organization
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule->Tools & Techniques
Performance review
Project Management
Software
Resource optimization
Technique
Modeling Technique
Leads & Lag
Schedule
Compression Scheduling tool
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule->T&T->Performance Review
Performance review
It measure, compare, & analyze schedule performance
E.g., Actual start & finish dates, % complete & remaining duration for
work in progress.
Determine any Deviation from the plan
Help take corrective & preventive action
Trend Analysis Earn Value
Management
Critical chain
method
Critical path
method
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule->T&T->Performance Review
Trend Analysis
• Examines project performance over time
• Determine whether performance is improving or deteriorating.
Pattern
Trend
Valuable for understanding current performance & for comparison to future
performance goals.
Detect Trends in work performance data
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule->T&T->Performance Review
Earn value management
• Schedule & Cost performance measurements
• As per PMI this is best technique to measure project performance.
Percentage complete method:
• Comparing planned activity dates against actual dates.
• Identify variances between baseline & actuals
• Difficult to estimate & may not provide actual picture
Schedule performance measurements (SV & SPI)
• Schedule variance (SV)
• Schedule performance index (SPI)
• Assess the magnitude of variation to baseline.
Activity start : 1-Jan
Status: Not started(0%)
Status: 6- Jan (In progress)
(40% completed)
Activity complete: 15-Jan
Status : Completed (100%)
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule->T&T->Performance Review
Critical path Method
• Comparing progress along critical path can help
determine schedule status.
• The variance on critical path will have a direct
impact on the project end date.
Critical chain method:
• Comparing amount of buffer remaining to amount
of buffer needed to protect delivery dates.
• Difference between buffer needed & buffer
remaining can determine whether corrective action
is required or not.
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule->T&T->Project Management software
Project Management
Software
Software used for project planning, scheduling, resource
allocation, change management , communication etc.
Control costs and schedule
Baseline Comparison
SV, SPI and CV, CPI
Cash flow management
Monitor & Inform
Schedule progress
Missed milestones
Changes to Critical path
Also used for collaboration and communication.
Project
planning
Task
management
Document
sharing and
collaboration
Calendar and
contact sharing
Risk and issue
management
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule->T&T->Project Management software
Project Management
Software
Software used for project planning, scheduling, resource
allocation, change management , communication etc.
Example,
Microsoft Project
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule->T&T-> Leads & Lags
Leads & lags
Lead: It is amount of time where
successor activity can be advanced w.r.t.
predecessor activity.
Lag: It is amount of time whereby a
successor activity will be delayed w.r.t. a
predecessor activity.
Business Requirement
(BRS)
System Requirement
(SRS)
Sign Contract
Team On-
board
Lead
1 week
Lag
3 week
Business Requirement
(BRS – 4 weeks)
System Requirement
(SRS – 4 weeks)
W1 W2 W3 W4 W5 W6 W7 W8 W1 W2 W3 W4 W5 W6 W7 W8
Sign Contract
Team On-
board
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule->T&T-> Resource optimization
Resource
optimization
Technique
It primarily focus on how to allocate resources in a
way to bring maximum output.
Resource Levelling:
• Start and finish dates are adjusted based
on resource constraints
• Goal is to balance demand for resources
with the available supply.
Resource Smoothing:
• Adjusts activities of a schedule model
• Ensure requirements for resources on
project do not exceed certain predefined
resource limits.
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule->T&T-> Schedule Compression
BRS (1 BA) SRS (1 SA)
BRS (2 BA) SRS (2 SA)
Design Testing
Design
Testing
W1 W2 W3 W4 W5 W6 W7 W8
Crashed
by adding
resources
W1 W2 W3 W4 W5 W6 W7 W8
Fast tracked by
executing
activities in
parallel
Schedule
Compression
Crashing:
Shorten the schedule duration for the least
incremental cost by adding resources.
Fast tracking:
Activities or phases normally done in sequence are
performed in parallel for at least a portion of their
duration.
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule->T&T-> Modeling Technique
Modeling
Technique
What-If Scenario Analysis:
• Process of evaluating scenarios in order to
predict their effect
• This is achieved by performing Network analysis
• Used to assess the feasibility of project schedule
under adverse conditions,
• Also used in preparing contingency & response
plans.
Simulation:
• Calculating multiple project durations with
different sets of activity assumptions.
• Uses probability distributions constructed from 3
Point estimates to account for uncertainty.
• Common simulation technique is Monte Carlo
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule->T&T-> Scheduling Tool
Scheduling tool
It contain the schedule model and expedite the scheduling
process.
It generate project start and finish dates based on the inputs of
activities, network diagrams, resources and activity durations.
Can calculate floats and generate critical path.
Can create schedule baselines & preserve it.
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule -> Output
Work
Performance
Information
Schedule
Forecast
Change Request
PMP updates Project
Documents
update
OPA updates
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule->Output->WPI
Work
Performance
Information
The calculated SV and SPI for the WBS components
(Control account, work package)
Documented and communicated to stakeholders
SV
SPI
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule->Output->Schedule Forecast
Schedule
Forecast
Predictions of projects future conditions & events
Projects execution data is constantly analysed which
results in WPI.
Forecasts are updated and reissued based on WPI.
Performance
review
Trend Analysis
EVM WPI
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule->Output->Change Request
Change Request
Modifications to the project scope or project
schedule may result in change requests
Schedule
baseline
Scope baseline
Components
of PMP.
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule -> Output
PMP updates:
• Schedule baseline
• Schedule Management plan
• Cost Baseline
Project Documents update:
• Schedule Data
• Project Schedule
• Risk Register
OPA updates:
• Causes of variances
• Corrective action chosen and the reasons
• Other types of lessons learned from project schedule control
By: Anand Bobade (nmbobade@gmail.com)
• Executing PG ->Direct
& Manage process
• Generates WPD
• Monitor & Control PG -
> All Control process
• Generate WPI
•Monitoring & Controlling
PG-> Monitor & Control
Project work
6.7 Control Schedule->Output-> WPD & WPI
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule -> Data Flow Diagram
By: Anand Bobade (nmbobade@gmail.com)
6.7 Control Schedule -> Review
How to control schedule?
Schedule performance review?
Schedule forecast?
Schedule Compression (Crashing & Fast Tracking)
Scheduling tool
By: Nemanand Bobade (nmbobade@gmail.com)
Learn Project Management & prepare for PMP exam:
• Learn visually
• Detailed coverage of all PMP concepts
• Sample Questions
By: Anand Bobade (nmbobade@gmail.com)
To Learn Project Management, Contact Anand Bobade (055 5932004)
•nmbobade@gmail.com
•https://ae.linkedin.com/in/anandbobade
•http://www.slideshare.net/anandbobade
•Conduct Online training, Corporate Training, evening & weekend workshops.
Free learning resources

Weitere ähnliche Inhalte

Was ist angesagt?

Chap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewChap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewAnand Bobade
 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource ManagementAnand Bobade
 
Chap 8.3 Control Quality
Chap 8.3  Control QualityChap 8.3  Control Quality
Chap 8.3 Control QualityAnand Bobade
 
Pmp chap 11 - project risk management - Part 2
Pmp   chap 11 - project risk management - Part 2Pmp   chap 11 - project risk management - Part 2
Pmp chap 11 - project risk management - Part 2Anand Bobade
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesAnand Bobade
 
Pmp chap 11 - project risk management v0.1
Pmp   chap 11 - project risk management v0.1Pmp   chap 11 - project risk management v0.1
Pmp chap 11 - project risk management v0.1Anand Bobade
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control CostAnand Bobade
 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop TeamAnand Bobade
 
PMP Chap 10 - Project Communication Management Details
PMP  Chap 10 - Project Communication Management DetailsPMP  Chap 10 - Project Communication Management Details
PMP Chap 10 - Project Communication Management DetailsAnand Bobade
 
PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2Anand Bobade
 
Chap 5.3 define scope
Chap 5.3 define scopeChap 5.3 define scope
Chap 5.3 define scopeAnand Bobade
 
PMP Chap 5.0 Scope Management Overview
PMP Chap 5.0 Scope Management OverviewPMP Chap 5.0 Scope Management Overview
PMP Chap 5.0 Scope Management OverviewAnand Bobade
 
Chap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewChap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewAnand Bobade
 
Chap 8.1 Plan quality management
Chap 8.1 Plan quality managementChap 8.1 Plan quality management
Chap 8.1 Plan quality managementAnand Bobade
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage TeamAnand Bobade
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1Anand Bobade
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define ScheduleAnand Bobade
 
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...Anand Bobade
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate CostAnand Bobade
 
PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2Anand Bobade
 

Was ist angesagt? (20)

Chap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewChap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management Overview
 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource Management
 
Chap 8.3 Control Quality
Chap 8.3  Control QualityChap 8.3  Control Quality
Chap 8.3 Control Quality
 
Pmp chap 11 - project risk management - Part 2
Pmp   chap 11 - project risk management - Part 2Pmp   chap 11 - project risk management - Part 2
Pmp chap 11 - project risk management - Part 2
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management Processes
 
Pmp chap 11 - project risk management v0.1
Pmp   chap 11 - project risk management v0.1Pmp   chap 11 - project risk management v0.1
Pmp chap 11 - project risk management v0.1
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control Cost
 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop Team
 
PMP Chap 10 - Project Communication Management Details
PMP  Chap 10 - Project Communication Management DetailsPMP  Chap 10 - Project Communication Management Details
PMP Chap 10 - Project Communication Management Details
 
PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2
 
Chap 5.3 define scope
Chap 5.3 define scopeChap 5.3 define scope
Chap 5.3 define scope
 
PMP Chap 5.0 Scope Management Overview
PMP Chap 5.0 Scope Management OverviewPMP Chap 5.0 Scope Management Overview
PMP Chap 5.0 Scope Management Overview
 
Chap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewChap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management Overview
 
Chap 8.1 Plan quality management
Chap 8.1 Plan quality managementChap 8.1 Plan quality management
Chap 8.1 Plan quality management
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage Team
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define Schedule
 
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate Cost
 
PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2
 

Andere mochten auch

PMP - One stop shop for All 47 process areas
PMP - One stop shop for All 47 process areasPMP - One stop shop for All 47 process areas
PMP - One stop shop for All 47 process areassandeep sonkusale
 
Triple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & ScheduleTriple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & Scheduleshofiulalom
 
PMP 47 process definitions
PMP 47 process definitionsPMP 47 process definitions
PMP 47 process definitionsAnand Bobade
 
Financial Management for Capital Projects
Financial Management for Capital ProjectsFinancial Management for Capital Projects
Financial Management for Capital ProjectsCharles Cotter, PhD
 
Financial Project Management
Financial Project ManagementFinancial Project Management
Financial Project Managementmetamath
 
Financial Management Slides
Financial Management SlidesFinancial Management Slides
Financial Management SlidesUrban Strategies
 
Financial management of construction contracts
Financial management of construction contractsFinancial management of construction contracts
Financial management of construction contractsidnobleg77
 
Understanding Construction Financial Statements
Understanding Construction Financial StatementsUnderstanding Construction Financial Statements
Understanding Construction Financial StatementsTAG
 
financial management project- ratio analysis
financial management project- ratio analysisfinancial management project- ratio analysis
financial management project- ratio analysisyogita varma
 
Project Time Management
Project Time ManagementProject Time Management
Project Time ManagementSerdar Temiz
 
Financial management project
Financial management projectFinancial management project
Financial management projectsukesh gowda
 
Class Project Financial Management Final update
Class Project Financial Management Final updateClass Project Financial Management Final update
Class Project Financial Management Final updateerwinsumargo
 
Project Time Management - PMBOK 5th Edition
Project  Time Management - PMBOK 5th EditionProject  Time Management - PMBOK 5th Edition
Project Time Management - PMBOK 5th Editionpankajsh10
 
Project Financing
Project FinancingProject Financing
Project Financingkhankm
 

Andere mochten auch (20)

PMP - One stop shop for All 47 process areas
PMP - One stop shop for All 47 process areasPMP - One stop shop for All 47 process areas
PMP - One stop shop for All 47 process areas
 
Triple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & ScheduleTriple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & Schedule
 
PMP 47 process definitions
PMP 47 process definitionsPMP 47 process definitions
PMP 47 process definitions
 
3. project time management
3. project time management3. project time management
3. project time management
 
Financial Management for Capital Projects
Financial Management for Capital ProjectsFinancial Management for Capital Projects
Financial Management for Capital Projects
 
Financial management intro
Financial management introFinancial management intro
Financial management intro
 
Financial Project Management
Financial Project ManagementFinancial Project Management
Financial Project Management
 
Financial Management Slides
Financial Management SlidesFinancial Management Slides
Financial Management Slides
 
Chap06 project time management
Chap06 project time managementChap06 project time management
Chap06 project time management
 
Financial management of construction contracts
Financial management of construction contractsFinancial management of construction contracts
Financial management of construction contracts
 
Understanding Construction Financial Statements
Understanding Construction Financial StatementsUnderstanding Construction Financial Statements
Understanding Construction Financial Statements
 
financial management project- ratio analysis
financial management project- ratio analysisfinancial management project- ratio analysis
financial management project- ratio analysis
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
PMP_Project Time Management
PMP_Project Time ManagementPMP_Project Time Management
PMP_Project Time Management
 
Financial management project
Financial management projectFinancial management project
Financial management project
 
Class Project Financial Management Final update
Class Project Financial Management Final updateClass Project Financial Management Final update
Class Project Financial Management Final update
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Project Time Management - PMBOK 5th Edition
Project  Time Management - PMBOK 5th EditionProject  Time Management - PMBOK 5th Edition
Project Time Management - PMBOK 5th Edition
 
Project Financing
Project FinancingProject Financing
Project Financing
 

Ähnlich wie PMP Chap 6 - Project Time management - Part2

Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationAnand Bobade
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagementDhamo daran
 
Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementAnand Bobade
 
Tracking and Controlling Technical Documentation Projects
Tracking and Controlling Technical Documentation ProjectsTracking and Controlling Technical Documentation Projects
Tracking and Controlling Technical Documentation ProjectsSaiff Solutions, Inc.
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control ScheduleAnand Bobade
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2Anand Bobade
 
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdf
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdfA PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdf
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdfssuserfc98db
 
General Project Management 2003
General Project Management 2003General Project Management 2003
General Project Management 2003Sidewinder2011
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Agus Suhanto
 
Day 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxDay 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxMohanadRabea1
 
2.02 project kick off_meeting (1)
2.02 project kick off_meeting (1)2.02 project kick off_meeting (1)
2.02 project kick off_meeting (1)Nguyen Toan
 

Ähnlich wie PMP Chap 6 - Project Time management - Part2 (20)

Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity Duration
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagement
 
Intro to PM.ppt
Intro to PM.pptIntro to PM.ppt
Intro to PM.ppt
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule Management
 
5. PMP Training - Time management
5. PMP Training - Time management5. PMP Training - Time management
5. PMP Training - Time management
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Tracking and Controlling Technical Documentation Projects
Tracking and Controlling Technical Documentation ProjectsTracking and Controlling Technical Documentation Projects
Tracking and Controlling Technical Documentation Projects
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control Schedule
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2
 
PS_PM_DMS_Utkarsh
PS_PM_DMS_UtkarshPS_PM_DMS_Utkarsh
PS_PM_DMS_Utkarsh
 
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdf
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdfA PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdf
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdf
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
 
Time management
Time managementTime management
Time management
 
General Project Management 2003
General Project Management 2003General Project Management 2003
General Project Management 2003
 
CAPM Week 2 Chapter 6
CAPM Week 2 Chapter 6CAPM Week 2 Chapter 6
CAPM Week 2 Chapter 6
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 
Day 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxDay 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptx
 
2.02 Project_Kick_Off_Meeting.ppt
2.02 Project_Kick_Off_Meeting.ppt2.02 Project_Kick_Off_Meeting.ppt
2.02 Project_Kick_Off_Meeting.ppt
 
2.02 project kick off_meeting (1)
2.02 project kick off_meeting (1)2.02 project kick off_meeting (1)
2.02 project kick off_meeting (1)
 

Mehr von Anand Bobade

Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control ProcurementAnand Bobade
 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementAnand Bobade
 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementAnand Bobade
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overviewAnand Bobade
 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor RisksAnand Bobade
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationAnand Bobade
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage CommunicationAnand Bobade
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication ManagementAnand Bobade
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire ResourcesAnand Bobade
 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budgetAnand Bobade
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost ManagementAnand Bobade
 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityAnand Bobade
 
Chap 6.2 Define Activity
Chap 6.2 Define ActivityChap 6.2 Define Activity
Chap 6.2 Define ActivityAnand Bobade
 
Chap 5.6 Control Scope
Chap 5.6 Control ScopeChap 5.6 Control Scope
Chap 5.6 Control ScopeAnand Bobade
 

Mehr von Anand Bobade (14)

Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control Procurement
 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct Procurement
 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement Management
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overview
 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor Risks
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor Communication
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage Communication
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication Management
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire Resources
 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budget
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost Management
 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence Activity
 
Chap 6.2 Define Activity
Chap 6.2 Define ActivityChap 6.2 Define Activity
Chap 6.2 Define Activity
 
Chap 5.6 Control Scope
Chap 5.6 Control ScopeChap 5.6 Control Scope
Chap 5.6 Control Scope
 

Kürzlich hochgeladen

Management and managerial skills training manual.pdf
Management and managerial skills training manual.pdfManagement and managerial skills training manual.pdf
Management and managerial skills training manual.pdffillmonipdc
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchRashtriya Kisan Manch
 
Motivational theories an leadership skills
Motivational theories an leadership skillsMotivational theories an leadership skills
Motivational theories an leadership skillskristinalimarenko7
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
 
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsFrom Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsCIToolkit
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证jdkhjh
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentationcraig524401
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insightWayne Abrahams
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)jennyeacort
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingCIToolkit
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixCIToolkit
 
How-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionHow-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionCIToolkit
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramCIToolkit
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsCIToolkit
 

Kürzlich hochgeladen (18)

Management and managerial skills training manual.pdf
Management and managerial skills training manual.pdfManagement and managerial skills training manual.pdf
Management and managerial skills training manual.pdf
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
 
Motivational theories an leadership skills
Motivational theories an leadership skillsMotivational theories an leadership skills
Motivational theories an leadership skills
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
 
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsFrom Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
 
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Servicesauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentation
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insight
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
 
How-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionHow-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem Resolution
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield Metrics
 

PMP Chap 6 - Project Time management - Part2

  • 1. By: Anand Bobade (nmbobade@gmail.com) Plan Schedule management Define Activities Sequence Activities Estimate Activity resource Estimate Activity Duration Develop Schedule Control Schedule Planning Monitoring & Controlling Learn Project Management & prepare for PMP exam: • Learn visually • Detailed coverage of all PMP concepts • Sample Questions Chapter 6 : Project Time Management (Part 2)
  • 2. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration Estimate Activity Duration Definition Important terms Estimate Activity Duration : ITTO Main activity estimation techniques Data flow diagram Review Guidelines for exam questions Self Assessment 6.1 I T&T O
  • 3. By: Anand Bobade (nmbobade@gmail.com) 6. Project Time Management 6.1 Plan Schedule management: The process of establishing policies, procedures, & documentation for planning, developing, managing, executing, & controlling the project schedule 6.2 Define Activities: The process of identifying and documenting the specific actions to be performed to produce the project deliverables. 6.3 Sequence Activities: The process of identifying and documenting relationships among the project activities.
  • 4. By: Anand Bobade (nmbobade@gmail.com) 6. Project Time Management 6.4: Estimate Activity resource: Estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity 6:5 Estimate Activity Duration: Estimating the number of work periods needed to complete individual activities with estimated resources 6:6 Develop Schedule: Analysing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model 6.7 Control Schedule: Monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan.
  • 5. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration-> Introduction SME Technical Lead Solution Architect Quality expert Estimation is joint activity, respective experts has to estimate their work. PM is responsible to aggregation.
  • 6. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration Estimating number of work periods needed to complete each activity with estimated resources. It is a major input to Develop Schedule process. Activity Estimating Work Periods per activity With estimated resources
  • 7. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration-> Important Terms Example: Painting a house • 20 daysEfforts • 10 days • With 2 resources Duration • 15 days • Includes (2 weekends & 1 day holiday by resources) Elapsed Time Day1 Day2 Day3 Day4 Day5 Day6 Day7 Day8 Day9 Day10 Day11 Day12 Day13 Day14 Day15 Work Started 1-Jan (Sunday) Work completed 15-Jan (Sunday) Weekend Weekend Resource on Holiday
  • 8. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration-> Important Terms Efforts: • Labour units required to complete activity. • Expressed in Hours, Days or Weeks. Duration (work days or work weeks): • Total time (work periods) to complete the activities based on the resources availability. • Does not include holidays & waiting periods. Elapsed Time • Calendar time required to complete activities based on resource availability & including holidays.
  • 9. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration Inputs (10) • Schedule management plan • Activity list • Activity attributes • Activity resource requirements • Resource calendars • Project scope statement • Risk register • RBS (Resource breakdown Structure) • EEF • OPA Tools & Techniques (6) • Expert judgment • Analogous estimating • Parametric estimating • Three-point estimating • Group decision-making techniques • Reserve analysis Outputs (2) • Activity duration estimates • Project documents updates
  • 10. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration -> Input Schedule Management Plan Activity list Activity Attributes Activity resource req. Resource Calendars Project Scope Statement Risk Register Resource breakdown structure EEF OPA
  • 11. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration->Input->Schedule MP Schedule Management plan Estimation techniques & guidelines. Project Schedule Model Organizational Policies & procedure Process Description Establishes policies, procedures & documentation for planning, developing, managing, executing & controlling project schedule.
  • 12. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration->Input->Activity List Activity list A list of all activities under each work package. Activity ID WBS Id Name Description 501 W50 Compare Furniture brands 502 W50 Find showrooms 503 W50 Get Quotes 504 W50 Compare Quotes
  • 13. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration->Input->Activity Attributes Activity attributes Additional details of activities, which are useful for estimation. Activity description Predecessor activities Successor activities Logical relationships Leads and lags Resource requirements Imposed dates Constraints Assumptions Person responsible Geographic area or place Calendar
  • 14. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Dur.->Inputs->Activity Resource Req Activity Resource Requirements The types and quantities of resources required for each activity in a work package. Aggregated to determine resource estimation for each work package. Resource Type Resource Quantity Total Resources for Work Package Activity ID WBS Id Name Resource Type Quantity 601 W51 Unit Testing Developer 5 602 W51 System Testing Test Analyst 10 603 W51 Performance Testing Sr. Performance Test Analyst 2 604 W51 Security testing Security expert 2
  • 15. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration->Input->Resource Calendar Identifies working days & shifts when each resource is available. Details about how long resource will be available. Other details – Skill, Skill levels, location etc Resource Calendars • Resource may be material, human resources, equipment etcRemember:
  • 16. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Dur.->Input->Project Scope Statement Project Scope statement Project scope statement provides description of the Project scope Major deliverables Assumptions & Constraints • Expect senior expert to work on the technical design due to requirements complexity. • Impact on estimation: Longer estimate; multiple resource may not be able to reduce estimate proportionally. Assumption • Requirement has to be implemented before 1-Aug, due to government legislation. • Impact on estimation: Multiple resource may be added to shorten the duration of activity. Constraint
  • 17. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration->Input->Risk Register Risk Register Concerns with results of Risk analysis & response planning. List of Risks related to estimations & resources.
  • 18. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration->Inputs-> RBS Resource Breakdown Structure Hierarchical representation of resources by category or type. Used for searching Resources. Construction Project Labor Managers Manager1 Manager2 Workers Worker1 Worker2 Worker3 Material Building Office setup Equipment Desktop Laptop Printer Projector Supplies Printer Cartridges Papers Stationary
  • 19. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration -> Input -> EEF EEF Duration estimating databases & other reference data. Productivity metrics. Published commercial information. Location of team members.
  • 20. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration -> Input -> OPA OPA Historical duration information. Project calendars. Scheduling methodology. Lessons learned.
  • 21. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration ->Tools & Techniques Expert Judgement Analogues estimation Parametric estimation Three point estimation Group decision making Reserve Analysis
  • 22. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration -> T&T -> Expert Judgement Expert Judgement All estimations should be done by Experts. Expert can be internal or external. Complex project need many experts. Uses experience of similar projects or instinct. SME Technical Lead Solution Architect Quality expert
  • 23. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration -> T&T Estimation Techniques: Same in Time management & Cost management Analogues estimation Parametric estimation Three point estimation
  • 24. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration -> T&T -> Analogues estimation Analogues estimation Estimate duration of activity using historical data from a similar activity or a project. Uses historical information, expert judgment. Think “analogy” – something similar Relatively quick and low cost It is gross value estimation approach. Parameters used: Duration Budget Size Weight Complexity
  • 25. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration -> T&T -> Analogues estimation Analogues estimation Computer Lab in School A Computer Lab in School B Used when: • Limited information is available. • Similar project information available. • Experienced estimator. In this scenarios - Information available is • Computer configurations • Computer installation duration - 30 min • No. of computer configured - 20 Similar
  • 26. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration -> T&T -> Parametric estimation Parametric estimation Algorithm is used to calculate duration based on historical data & project parameters. Uses statistical relationship between historical data & other parameters. Railroad Project Highway Project • Accuracy of historical data. • Sophistication & scalability of model. • Quantifiable parameters Can be highly accurate based on: E.g., Construction estimation software
  • 27. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration->T&T->Three point estimation Three point estimation Estimate duration by applying an average of optimistic, pessimistic & most likely estimates when there is uncertainty in estimates. This is also called as PERT techniques (Program Evaluation and Review Technique). • = (O + M + P) / 3Triangular Distribution • = (O + 4M + P) / 6 Beta Distribution (Weighted average) What's efforts required for activity1: Optimistic = 10 hours (coding guru) Most likely = 12 hours (Regular prog.) Pessimistic = 16 hours (New prog.) Estimation Discussion meeting • = 10+12+16 / 3 • = 12.66 hours Triangular • = [10 + (4X12) + 16] / 6 • = 12.33 hours Beta
  • 28. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration->T&T->Three point estimation Question: In software project, a module was estimated to take 25 hours for average programmer as the most likely estimate. The pessimistic estimate of 35 hours may be based on the assumption for a newbie, whereas optimistic estimate of 20 hours for a veteran programmer. Calculate the estimation using the weighted average technique. A. 25 B. 25.5 C. 25.83 D. 26 Weighted average = (P + 4M + O)/6 = (20 + 4*25 + 35)/6 = 25.83 hours
  • 29. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration->T&T->Three point estimation Three point estimation • = ( P – O ) / 6Standard Deviation (SD) Standard deviation represents the distance a given point is from the mean. It is also called sigma, or s. Standard Deviation’s: ±1σ = 68.27% ±2σ = 95.45% ±3σ = 99.73% This is really an approximation of standard deviation. SD calculation/formula in Quality theories like Six Sigma is different. mean, median, and mode are all the same.
  • 30. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration->T&T->Three point estimation Question: In software project, a module was estimated to take 25 hours for average programmer as the most likely estimate. The pessimistic estimate of 35 hours may be based on the assumption for a newbie, whereas optimistic estimate of 20 hours for a veteran programmer. Using the weighted average technique, you determine that there is a 95.5% probability that the module will be completed in: A. Between 25.83 and 28.33 hours B. Between 23.33 and 28.33 hours C. Between 25.83 and 30.33 hours D. Between 20.83 and 30.33 hours
  • 31. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration->T&T->Three point estimation Step 1: • Weighted average = (P + 4M + O)/6 • = (20 + 4*25 + 35)/6 = 25.83 hours Step 2: • Standard deviation = (P – O)/6 • = 2.5 hours Step 3: What is the range? • Upper end of the range equals the weighted average + (1, 2, or 3 SD) • = weighted average + 2σ (Refer to SD 2σ values) • = 25.83 + 2*2.5 = 30.83 hours • Lower end of the range equals the weighted average – (1, 2, or 3 SD). • = 25.83 – 2*2.5 hours = 20.83 hours • The answer therefore is D
  • 32. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration->T&T->Three point estimation Three point estimation Steps: Get the total of the estimates for all activities along the critical path. Take the variance for each activity. Sum them up across the whole project. Take the square root. Variance Formula is used, if you trying to get the estimate for the whole project. • = SD ^ 2Activity Variance (AV) AV is square root of sum of total activity variance. SD for project as a whole is sum of all AV’s.
  • 33. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration->T&T->Three point estimation Three point estimation AV is square root of sum of total activity variance. SD for project as a whole is sum of all AV’s. 4,356 + 0 + 1,089 + 4,356 = 9,801 AV = √9801 AV= 99 Task1- If SD = 33, then 33 - 100 = -662=4,356 Task2- If SD = 100, then 100 - 100 = 02=0 Task3- If SD = 133, then 133 - 100 = 332=1,089 Task4- If SD = 166, then 166 - 100 = 662=4,356 If SD = 33, then 332 = 1,089. If you sum those figures 1089 + 10,000 + 17,689 + 2,7556 = 56,334. Then AV = √ 56,334 or 237.34. The AV is not the mean. The mean would be 56,334 ÷ 4 = 14,083 The AV is also not the mean of the sum of the SD. That would be 33 + 100 + 133 + 166 = 432 ÷ 4 = 108
  • 34. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration->T&T-> Reserve Analysis Reserve Analysis Contingency reserves (time reserves or buffers) are used in schedule to account schedule uncertainty. PM has to use reserve to protect baseline & constantly reduce or eliminate it. Quantitative analysis like Monte Carlo can be used to identify reserves. Reserve can be @ Activity level Work package level Can be fixed amount Can be % of the estimates
  • 35. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration->T&T->Group decision Making Brainstorming: To generate and collect Multiple ideas related to estimation. Delphi Techniques: Structured communication technique developed as systematic, interactive forecasting method which relies on a panel of experts. Nominal group techniques: Enhances brainstorming with a VOTING process used to rank the most useful ideas for further brainstorming or for prioritization Group Decision Making Assessment process with multiple alternatives with an expected outcome in the form of future actions.
  • 36. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration -> Output Activity duration estimates Project Documents update
  • 37. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration->Output->Activity Duration estimates Activity duration estimates • It is important to properly communicate estimates. • Estimates should be given in range. • State the confidence level. Communicatin g estimate: Sr. No Activity Duration Description 1 Requirement Gathering 30 days 2 Development 90 days 3 System Testing 15 days 4 User acceptance Testing 20 days 5 Performance Testing 5 days 6 Handover 5 days 7 Project closure 5 days
  • 38. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration->Outputs->Proj. doc. update Project Documents update • Duration estimates • Basis of estimates Activity attributes • Assumptions • Contingencies Risk register
  • 39. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration
  • 40. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration->Review Estimate should be given by experts Three estimating techniques - Analogues, Parametric & Three point Estimation should be performed for each activity Perform reserve analysis
  • 41. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration-> Questions -1 Which one of the below is not a Three point estimation technique: A. PERT estimation B. Triangular Distribution C. Beta Distribution D. Standard Deviation D - Standard Deviation Both are estimation techniques (BETA distribution [also called as PERT] and Triangular Distribution )
  • 42. By: Anand Bobade (nmbobade@gmail.com) 6.5 Estimate Activity Duration-> Questions -2 Which one of the below is not a estimation technique that is used in both Duration & Cost estimates: A. Analogues estimation B. Parametric estimation C. Three point estimate D. Aggregation D - Aggregation All three are estimation techniques except aggregation
  • 43. By: Nemanand Bobade (nmbobade@gmail.com) Learn Project Management & prepare for PMP exam: • Learn visually • Detailed coverage of all PMP concepts • Sample Questions
  • 44. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule Develop Schedule Definition Develop Schedule : ITTO What is PDM & schedule network diagram? What is critical path? What is critical chain? What is Float or Slack? Review Guidelines for exam questions Self Assessment 6.1 I T&T O
  • 45. By: Anand Bobade (nmbobade@gmail.com) 6. Project Time Management 6.1 Plan Schedule management: The process of establishing policies, procedures, & documentation for planning, developing, managing, executing, & controlling the project schedule 6.2 Define Activities: The process of identifying and documenting the specific actions to be performed to produce the project deliverables. 6.3 Sequence Activities: The process of identifying and documenting relationships among the project activities.
  • 46. By: Anand Bobade (nmbobade@gmail.com) 6. Project Time Management 6.4: Estimate Activity resource: Estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity 6:5 Estimate Activity Duration: Estimating the number of work periods needed to complete individual activities with estimated resources 6:6 Develop Schedule: Analysing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model 6.7 Control Schedule: Monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan.
  • 47. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule -> Introduction • Use existing Schedule model(template) • Update with information from previous processes (Activity, sequencing, resources, Duration etc) Enter • Developed Project schedule model • Optimize schedule by Resource leveling/smoothing, resource crashing/Fast tracking etc Optimize
  • 48. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule Analysing activity sequences, durations, resource requirements & schedule constraints to create project schedule model. Activity sequences Activity Durations Resource Requirements Schedule Constraints To create Project Schedule Analyze It generates schedule model with planned dates for completing project activities.
  • 49. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule Inputs (13) • Schedule management plan • Activity list • Activity attributes • Project schedule network diagram • Activity resource requirements • Resource calendars • Activity duration estimates • Project scope statement • Risk register • Project staff assignments • RBS • EEF & OPA Tools & Techniques(8) • Schedule network analysis • Critical path method • Critical chain method • Resource optimization techniques • Modelling techniques • Leads and lags • Schedule compression • Scheduling tool Outputs (6) • Schedule baseline • Project schedule • Schedule data • Project calendars • Project management plan updates • Project documents updates
  • 50. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule -> Input Schedule Manag. plan Activity list Activity Attributes Proj. Schedule Network diagram Activity resource req. Resource Calendars Activity Duration Estimates Proj. scope Statement Risk Register Project Staff assignment Resource breakdown structure EEF & OPA
  • 51. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule -> Input -> All Schedule Management Plan: • Scheduling method • Tool to be used & Schedule model etc Activity list: • List of all activities to be included in the schedule model. Activity Attributes: • Detailed activity information that will be helpful to develop schedule. Project Schedule Network diagram: • Graphically shows activity dependencies. • Shows predecessors and successors.
  • 52. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule -> Input -> All Activity resource requirement: • Resource type & quantity. Resource Calendars: • Holidays, resource vacations, resource availability. Activity Duration Estimates: • Work periods required to complete each activity. Project scope Statement: • Milestones • Assumptions & Constraints.
  • 53. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule -> Input -> All Risk Register: • Schedule, estimation & resources related risks. Project Staff assignment: • Resource allocations & commitment to specific activities. Resource breakdown structure: • Resource category, helpful for finding resources used during resource analysis & Reporting EEF: • Communication channel details, Scheduling tool OPA: • Schedule methodology
  • 54. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->Tools & Techniques Schedule network Analysis Critical Path method Critical chain method Resource optimization Technique Modeling Technique Leads & Lag Schedule Compression Scheduling tool
  • 55. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->T&T->Schedule Network Analysis Schedule network Analysis Various analytical techniques are used to perform Schedule Network Analysis & optimize schedule. Critical path method Critical chain method What-if analysis Resource optimization
  • 56. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->T&T->Schedule Network Analysis Schedule network Analysis Activity Activity Description Duration (days) Predecessor A Collect Requirement 50 - B System Design 25 A C Build Module 1 40 B D Build Module 2 50 C E Build Module 3 10 B F Build Module 4 15 E G Build Module 5 30 B H System Testing 25 D,F,G Lets create Project schedule network diagram based on below activities:
  • 57. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->T&T->Schedule Network Analysis Creatig a Project Schedule Network diagram: Collect Requirements (A - 50days) Start System Design (B - 20d) Build module 1 (C - 40 day) Build module 2 (D - 50 day) Build module 3 (E - 10 day) Build module 5 (G - 30 day) Testing (H-25 days) Build module 4 (F - 15 day) End • = A->B->C->D->H = 50+20+40+50+25 = 185Path1 • = A->B->E->F->H = 50+20+10+15+25 = 120Path2 • = A->B->G->H = 50+20+30 = 100Path3
  • 58. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->T&T-> Schedule network Analysis Critical Path: • Sequence of activities that represents longest path through the project. Critical path is the shortest possible project duration. Collect Req.(50d) Start System Design(20d) Build module 1 (40 day) Build module 2 (50 day) Testing (25 day) End All below activities are on critical path Any delay to activity on critical path will delay project
  • 59. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->T&T->Critical Path Method Critical Path method Calculates Early start, Early finish, Late start & Late finish dates. Performing a forward & backward pass analysis through the schedule network. Does not consider resource limitations. • Defines how long non-critical activities can be delayed without delaying project Slack (Float) Method used to estimate minimum project duration Determine amount of scheduling flexibility (Float) on the logical network paths.
  • 60. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->T&T->Critical Path Method ES (Early Start) Duration EF (Early Finish) Activity LS (Late Start) Total Float LF (Late Finish) Early Start (ES)EF of immediately preceding activity + 1 (ES+Duration)-1 (LS+Duration)-1 Latest activity can start without delaying project
  • 61. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->T&T->Critical Path Method ES Duration (50 days) EF Collect Requirement (A) LS Total Float LF ES Duration (20 days) EF System Design (B) LS Total Float LF Start End Calculate ES, EF, LS, LF using Forward & Backward pass:
  • 62. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->T&T->Critical Path Method ES Duration (50 days) EF Collect Requirement (A) LS Total Float (0) LF Early Start (ES) ES Duration (20 days) EF System Design (B) LS Total Float (0) LF Start First activity start on day1 ES = 1 EF=(1+50)-1 = 50 Forward Pass Backward Pass ES = 50 +1 = 51 EF = (51+20)-1 = 70 LS = (70-20)+1 = 51LF = 51 -1 = 50LS = (50-50)+1 = 1 1 50 51 70 7051501
  • 63. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->T&T->Critical Path Method 51 20 70 System Design (B) 51 0 70 40 Build – Module1(C) 50 Build – Module2(D) 25 Testing(H) 10 Build – Module3(E) 15 Build – Module4(F) 30 Build – Module4(G) Lets calculate ES, EF, LS, LF for remaining activities:
  • 64. By: Anand Bobade (nmbobade@gmail.com) Lets calculate ES, EF, LS, LF for remaining activities: 6.6 Develop Schedule->T&T->Critical Path Method 51 20 70 System Design (B) 51 70 40 Build–Module1(C) 50 Build – Module2(D) 25 Testing(H) 10 Build – Module3 (E) 15 Build – Module4(F) 30 Build – Module4(G) Select largest no 71 71 71 110 100 80 111 81 95 160 161 185
  • 65. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->T&T->Critical Path Method 51 20 70 System Design (B) 51 71 40 110 Build–Module1(C) 111 50 160 Build – Module2(D) 161 25 185 Testing(H) 71 10 80 Build – Module3 (E) 81 15 95 Build – Module4(F) 71 30 100 Build – Module4(G) Select smallest no 185161 160 160 160 146 111 145 110 136 71 131 70 Lets calculate ES, EF, LS, LF for remaining activities:
  • 66. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->T&T->Critical Path Method 51 20 70 System Design (B) 51 70 71 40 110 Build–Module1(C) 71 110 111 50 160 Build – Module2(D) 111 160 161 25 185 Testing(H) 161 185 71 10 80 Build – Module3 (E) 136 145 81 15 95 Build – Module4(F) 146 160 71 30 100 Build – Module4(G) 131 160 • FF = Earliest ES of next Activity – ES of current Activity – Duration of current activity Amount of time activity can be delayed Without delaying next activity. Slack or Float are same. Total Float TF = LF - EF Total Float TF = LS - ES 65 65 TF = 136 - 71 = 65 60 0 0 0 0 TF = 51-51 = 0 TF of activities on critical path are Zero FF for Activity F 161-81-15 = 65
  • 67. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->T&T->Critical Path Method • Total amount of time activity can be delayed Without delaying Project finish date. • TF= Late Start– Early Start • TF= Late Finish– Early Finish Total Float • Amount of time activity can be delayed Without delaying next activity. • FF = Earliest ES of next Activity – ES of current Activity – Duration of current activity Free Float Critical Path method Difference between Total & Free float:
  • 68. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->Questions The following is a small section taken from a large network diagram of CRM project schedule, which of the statements is true? A) Task 1 has a free float of 3 days B) Task 2 has a free float of 6 days C) Task 3 has a free float of 9 days D) Task 4 has a free float of 5 days. Answer : Calculate TF for all Tasks: Task1 = 2, Task 2 = 8, Task 3 = 2 & Task 4 = 2 FF for Task1: ES of next – ES of current – Duration of current => 7 – 1 - 6 = 0 FF for Task2: ES of next – ES of current – Duration of current => 17-7-4 = 6 FF for Task3: ES of next – ES of current – Duration of current => 17-7-10 = 0 FF for Task4: ES of next – ES of current – Duration of current => ???? -17-8 = Can’t calculate Hence Answer is B) Task 2 has a free float of 6 days 1 6 days 6 Task1 3 8 7 4 days 10 Task2 15 18 17 8 days 24 Task4 19 26 7 10 days 16 Task 3 9 18 FF = 0 FF = 6 FF = 0 2 8 2 2
  • 69. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->T&T->Critical Chain Method Critical chain method Two types: Feeding Buffer Project Buffer Placing buffers on any project schedule path to account for limited resources & project uncertainties. It considers effects of resource allocation, optimization, levelling.
  • 70. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->T&T->Critical Chain Method • Placed at point where a chain of activities are not on critical chain. • Feeds into the critical chain. Feeding buffers • Single buffer. • Placed at the end of the critical chain. • Protect slippage along the critical chain. Project buffer Feeding Buffer Feeding Buffer Project Buffer
  • 71. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->T&T-> Resource optimization Resource Levelling: • Start and finish dates are adjusted based on resource constraints. • Goal is to balance demand for resources with the available supply. Resource Smoothing: • Adjusts schedule activities. • Ensure requirements for resources do not exceed certain predefined resource limits. • May not be able to optimize all resources. How to allocate resources in a way to bring maximum output. Resource optimization Technique
  • 72. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->T&T-> Resource optimization Resource Smoothing: • Critical path is not changed & completion date is same • Activities may be delayed within their free & total float. Resource Levelling: • Notice Change in Duration (Critical path changed) • Timelines extended to adjust resource constraint
  • 73. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->T&T-> Modeling Technique Modeling Technique What-If Scenario Analysis: • Evaluating scenarios to predict their effect on schedule. • Achieved by performing Network analysis. • Used to assess feasibility of project schedule under adverse conditions. • Used in contingency & response planning. Enter schedule in Scheduling tool Enter various scenarios Simulate•Scenario1 •Scenario4 •Scenario3 •Scenario2
  • 74. By: Anand Bobade (nmbobade@gmail.com) Randomly choose parameters Risk 1 Risk 2 Constraints - Resource Constraints - Milestone 6.6 Develop Schedule->T&T-> Modeling Technique Simulation (Monte Carlo): • Monte Carlo is simulation technique. • It calculate multiple project durations with different sets of activity assumptions. • Uses probability distributions constructed from 3 Point estimates to account for uncertainty. Modeling Technique Develop the analysis Model Generate Multiple options
  • 75. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->T&T-> Modeling Technique Business Requirement (BRS) System Requirement (SRS) Sign Contract Team On- board Lead 1 week Lag 3 week Lead: It is amount of time where successor activity can be advanced w.r.t. predecessor activity. Lag: It is amount of time whereby a successor activity will be delayed w.r.t. a predecessor activity. Leads & lags Business Requirement (BRS – 4 weeks) System Requirement (SRS – 4 weeks) W1 W2 W3 W4 W5 W6 W7 W8 W1 W2 W3 W4 W5 W6 W7 W8 Sign Contract Team On- board
  • 76. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->T&T-> Schedule Compression Schedule Compression Reduce schedule duration without reducing project scope. Adhere to schedule constraints, imposed dates, or other schedule objectives. Crashing Fast tracking
  • 77. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->T&T-> Schedule Compression Crashing: Shorten schedule duration for least cost by adding resources. Fast tracking: Activities done in sequence are performed in parallel for at least some portion of their duration. BRS (1 BA) SRS (1 SA) BRS (2 BA) SRS (2 SA) Design Testing Design Testing W1 W2 W3 W4 W5 W6 W7 W8 Crashed by adding resources W1 W2 W3 W4 W5 W6 W7 W8 Fast tracked by executing activities in parallel
  • 78. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->T&T-> Schedule Compression Difference between Crashing & Fast tracking • Adding resources. • Increases cost. • Works with activity on critical path. Crashing: • May result in rework. • Increase Risk. • Assign activity with negative float. Fast tracking:
  • 79. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->T&T->Scheduling Tool Scheduling tool It contain schedule model & expedite scheduling process. It generate start and finish dates based on the inputs of activities, resources, activity durations etc.
  • 80. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule -> Output Schedule baseline Project Schedule Schedule Data Project Calendars PMP updates Project Documents update
  • 81. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->Output-> Schedule Baseline Schedule baseline The approved version of a schedule model that can be changed only through formal change control procedures. It is approved by stakeholders as the schedule baseline Approved baseline dates are compared to the actual to determine variance. The schedule baseline is a component of the project management plan.
  • 82. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->Output-> Project Schedule Project Schedule Presents linked activities with planned dates, durations, milestones, & resources in the form of Presentation. It is not completed until resources are assigned Should be completed along with PM plan Schedule may be summary or in detail Presented in Graphical formats - Below three forms Milestone Chart Bar Chart or Gantt Chart Schedule network Diagram
  • 83. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->Output-> Project Schedule Milestone Chart
  • 84. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->Output-> Project Schedule Bar chart or Gantt Chart
  • 85. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->Output-> Project Schedule Project Schedule Network Diagram
  • 86. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule->Output-> Schedule Data Schedule Data Resource requirements by time period - Resource histogram. Scheduling of contingency reserves. Supporting data generated during preparation of the schedule. Milestones Schedule activities Activity attributes Assumptions Constraints. Alternative schedules Best-case or worst-case Not resource- leveled or resource- leveled With or without imposed dates
  • 87. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule -> Output-> Project Calendars Project Calendars A calendar that identifies working days and shifts that are available for scheduled activities. Identify available work days Marked holidays Multiple Project calendars may be used Get updated throughout the project May identify need of maintaining resource calendars
  • 88. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule -> Output -> PMP Updates PMP updates • If any change is identify in project schedule management Update Schedule Management plan • Scope changes • Resources assigned to activities Update Schedule baselines
  • 89. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule -> Output-> Project Documents update Project Documents update • Duration estimates • Basis of estimates Activity attributes • New recourse Activity Resource requirements • Assumptions • Contingencies Risk register • Changes to CalendarCalendars
  • 90. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule
  • 91. By: Anand Bobade (nmbobade@gmail.com) 6.6 Develop Schedule -> Review How to develop schedule & its inputs Schedule network Analysis Critical Path method (Total & Free float) Critical chain method (Feeding Buffer & Project Buffer) Resource optimization Technique (Resource levelling, Smoothing) Modeling Technique (What if analysis, Simulations) Schedule Compression (Crashing & Fast Tracking) Scheduling tool Project schedule (Presentation, Bar or Gantt chart, Milestone chart, Project Schedule Network Diagram)
  • 92. By: Nemanand Bobade (nmbobade@gmail.com) Learn Project Management & prepare for PMP exam: • Learn visually • Detailed coverage of all PMP concepts • Sample Questions
  • 93. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule Control Schedule Definition Control Schedule & Integrated change Control Control Schedule : ITTO What is performance review? What are schedule forecast? Data flow diagram Review Guidelines for exam questions Self Assessment 6.1 I T&T O
  • 94. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule • The current status of the project scheduleDetermine • If the project schedule has changedMonitor • The factors that create schedule changesInfluence • The actual changes as they occur & minimize RisksManaging
  • 95. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule If any agile approach is utilized, control schedule is concerned with below: Determining current status of project schedule by comparing total amount of work delivered & accepted against estimates of work completed for elapsed time cycle Conducting retrospective reviews (scheduled reviews to record lessons learned) for correcting processes and improving, if required Reprioritizing the remaining work plan (backlog) Determining the rate at which the deliverables are produced, validated, and accepted (velocity) in given time per iteration Determining that the project schedule has changed Managing the actual changes as they occur.
  • 96. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule-> Definition Monitoring the status of project activities to update project progress & manage changes to schedule baseline to achieve plan. Monitoring status of Project activities Update project progress Manage schedule baseline changes It provides the means to recognize the deviation from the plan, & take corrective & preventive actions & thus minimize the risk.
  • 97. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule Inputs (6) • Project management plan • Project schedule • Work performance data • Project calendars • Schedule data • Organizational process assets Tools & Techniques (7) • Performance reviews • Project management software • Resource optimization techniques • Modelling techniques • Leads and lags • Schedule compression • Scheduling tool Outputs (6) • Work performance information • Schedule forecasts • Change requests • Project management plan updates • Project documents updates • Organizational process assets updates
  • 98. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule -> Input PM Plan Project Schedule Work performance Data Project Calendars Schedule Data OPA
  • 99. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule -> Input ->PMP PM Plan • How to manage Schedule • How to control Schedule Schedule Management Plan • Planned & actual dates • Used for comparisons Schedule baselines
  • 100. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule -> Input->Project Schedule Project Schedule Presents linked activities with planned dates, durations, milestones, & resources in the form of Presentation. Having most recent data is key to control the schedule Latest version of the document Latest activity details (start & completed activity dates)
  • 101. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule -> Input->WPD Work performance Data It is the raw data of the project’s status. Actual cost Actual duration The raw observations & measurements identified during execution of activities.
  • 102. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule -> Input-> Project Calendars Identify available work days Marked holidays Multiple Project calendars may be used Get updated throughout the project May identify need of maintaining resource calendars Project Calendars
  • 103. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule -> Input -> Schedule data Schedule Data All information which are useful to control schedule activities. It is constantly reviewed & updated. List of activities & attributes Milestones Assumptions Constraints
  • 104. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule -> Input ->OPA OPA Schedule control related organizational policies Schedule control tools Monitoring & reporting methods used in organization
  • 105. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule->Tools & Techniques Performance review Project Management Software Resource optimization Technique Modeling Technique Leads & Lag Schedule Compression Scheduling tool
  • 106. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule->T&T->Performance Review Performance review It measure, compare, & analyze schedule performance E.g., Actual start & finish dates, % complete & remaining duration for work in progress. Determine any Deviation from the plan Help take corrective & preventive action Trend Analysis Earn Value Management Critical chain method Critical path method
  • 107. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule->T&T->Performance Review Trend Analysis • Examines project performance over time • Determine whether performance is improving or deteriorating. Pattern Trend Valuable for understanding current performance & for comparison to future performance goals. Detect Trends in work performance data
  • 108. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule->T&T->Performance Review Earn value management • Schedule & Cost performance measurements • As per PMI this is best technique to measure project performance. Percentage complete method: • Comparing planned activity dates against actual dates. • Identify variances between baseline & actuals • Difficult to estimate & may not provide actual picture Schedule performance measurements (SV & SPI) • Schedule variance (SV) • Schedule performance index (SPI) • Assess the magnitude of variation to baseline. Activity start : 1-Jan Status: Not started(0%) Status: 6- Jan (In progress) (40% completed) Activity complete: 15-Jan Status : Completed (100%)
  • 109. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule->T&T->Performance Review Critical path Method • Comparing progress along critical path can help determine schedule status. • The variance on critical path will have a direct impact on the project end date. Critical chain method: • Comparing amount of buffer remaining to amount of buffer needed to protect delivery dates. • Difference between buffer needed & buffer remaining can determine whether corrective action is required or not.
  • 110. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule->T&T->Project Management software Project Management Software Software used for project planning, scheduling, resource allocation, change management , communication etc. Control costs and schedule Baseline Comparison SV, SPI and CV, CPI Cash flow management Monitor & Inform Schedule progress Missed milestones Changes to Critical path Also used for collaboration and communication. Project planning Task management Document sharing and collaboration Calendar and contact sharing Risk and issue management
  • 111. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule->T&T->Project Management software Project Management Software Software used for project planning, scheduling, resource allocation, change management , communication etc. Example, Microsoft Project
  • 112. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule->T&T-> Leads & Lags Leads & lags Lead: It is amount of time where successor activity can be advanced w.r.t. predecessor activity. Lag: It is amount of time whereby a successor activity will be delayed w.r.t. a predecessor activity. Business Requirement (BRS) System Requirement (SRS) Sign Contract Team On- board Lead 1 week Lag 3 week Business Requirement (BRS – 4 weeks) System Requirement (SRS – 4 weeks) W1 W2 W3 W4 W5 W6 W7 W8 W1 W2 W3 W4 W5 W6 W7 W8 Sign Contract Team On- board
  • 113. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule->T&T-> Resource optimization Resource optimization Technique It primarily focus on how to allocate resources in a way to bring maximum output. Resource Levelling: • Start and finish dates are adjusted based on resource constraints • Goal is to balance demand for resources with the available supply. Resource Smoothing: • Adjusts activities of a schedule model • Ensure requirements for resources on project do not exceed certain predefined resource limits.
  • 114. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule->T&T-> Schedule Compression BRS (1 BA) SRS (1 SA) BRS (2 BA) SRS (2 SA) Design Testing Design Testing W1 W2 W3 W4 W5 W6 W7 W8 Crashed by adding resources W1 W2 W3 W4 W5 W6 W7 W8 Fast tracked by executing activities in parallel Schedule Compression Crashing: Shorten the schedule duration for the least incremental cost by adding resources. Fast tracking: Activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
  • 115. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule->T&T-> Modeling Technique Modeling Technique What-If Scenario Analysis: • Process of evaluating scenarios in order to predict their effect • This is achieved by performing Network analysis • Used to assess the feasibility of project schedule under adverse conditions, • Also used in preparing contingency & response plans. Simulation: • Calculating multiple project durations with different sets of activity assumptions. • Uses probability distributions constructed from 3 Point estimates to account for uncertainty. • Common simulation technique is Monte Carlo
  • 116. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule->T&T-> Scheduling Tool Scheduling tool It contain the schedule model and expedite the scheduling process. It generate project start and finish dates based on the inputs of activities, network diagrams, resources and activity durations. Can calculate floats and generate critical path. Can create schedule baselines & preserve it.
  • 117. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule -> Output Work Performance Information Schedule Forecast Change Request PMP updates Project Documents update OPA updates
  • 118. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule->Output->WPI Work Performance Information The calculated SV and SPI for the WBS components (Control account, work package) Documented and communicated to stakeholders SV SPI
  • 119. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule->Output->Schedule Forecast Schedule Forecast Predictions of projects future conditions & events Projects execution data is constantly analysed which results in WPI. Forecasts are updated and reissued based on WPI. Performance review Trend Analysis EVM WPI
  • 120. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule->Output->Change Request Change Request Modifications to the project scope or project schedule may result in change requests Schedule baseline Scope baseline Components of PMP.
  • 121. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule -> Output PMP updates: • Schedule baseline • Schedule Management plan • Cost Baseline Project Documents update: • Schedule Data • Project Schedule • Risk Register OPA updates: • Causes of variances • Corrective action chosen and the reasons • Other types of lessons learned from project schedule control
  • 122. By: Anand Bobade (nmbobade@gmail.com) • Executing PG ->Direct & Manage process • Generates WPD • Monitor & Control PG - > All Control process • Generate WPI •Monitoring & Controlling PG-> Monitor & Control Project work 6.7 Control Schedule->Output-> WPD & WPI
  • 123. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule -> Data Flow Diagram
  • 124. By: Anand Bobade (nmbobade@gmail.com) 6.7 Control Schedule -> Review How to control schedule? Schedule performance review? Schedule forecast? Schedule Compression (Crashing & Fast Tracking) Scheduling tool
  • 125. By: Nemanand Bobade (nmbobade@gmail.com) Learn Project Management & prepare for PMP exam: • Learn visually • Detailed coverage of all PMP concepts • Sample Questions
  • 126. By: Anand Bobade (nmbobade@gmail.com) To Learn Project Management, Contact Anand Bobade (055 5932004) •nmbobade@gmail.com •https://ae.linkedin.com/in/anandbobade •http://www.slideshare.net/anandbobade •Conduct Online training, Corporate Training, evening & weekend workshops. Free learning resources