Project Risk Management Processes
Plan Risk management Identify Risk
Perform Qualitative
Risk Analysis
Perform Quantitative
Risk Analysis
Plan Risk Response Implement Risk Monitor Risk
P
MC
P P P
P E
4. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Implement Risk Responses
Implement Risk response
âą The process of implementing agreed-upon risk response plans.
The key benefit of this process is that it ensures that agreed-upon risk
responses are executed as planned throughout the project.
Risk Response plan
Implement
5. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Implement Risk Response -> ITTO
Expert Judgment
Interpersonal and team skills
Project Management
Information system
Project Management
Plan
Project documents
Organizational process
assets
Change request
Project document
updates
Inputs Tools & Techniques Outputs
6. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project
Management Plan
Project documents
Organizational
process assets
Implement Risk Response -> Inputs
7. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project
Management Plan
Implement Risk Response -> Inputs -> PMP
Risk Management plan
âą Roles & responsibilities of project team members and other
stakeholders who are involved in implementing risk responses.
âą Risk thresholds for the project, which define the acceptable target that
the implementation of risk responses is supposed to achieve.
8. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project documents
Implement Risk Response -> Inputs -> Project documents
âą Lessons learned during implementing risk responses from other similar
projects, and from same project can be applied.
Lessons
learned register
âą Contain the agreed-upon risk response strategy for the overall project,
as well as for major individual project risks.Risk register
âą Contains an assessment of the current overall project risk exposure as
well as the agreed-upon risk strategy for major individual project risks.Risk report
Lessons learned
register
Risk Register Risk Report
9. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Expert Judgment
Interpersonal and
team skills
Project Management
Information system
Implement Risk Response -> Tools & Techniques
10. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Expert Judgment
Implement Risk Responses ->T&T->Expert Judgement
Expertise from individuals or groups with expertise in implementing risk response
How to carry out the
risk responses
These are assigned Risk
owners
Or Risk action owners
11. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Interpersonal and
team skills
Encourage risk owners to take the necessary actions needed
PM may need to facilitate the risk process.
Similar to influencing skill required to get the work done on the project during
Direct and Manage Project Work
Implement Risk Response -> T&T -> Interpersonal and team skills
Influencing
12. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project Management
Information system
PMIS is used to monitor the schedule, cost and resources on a project
Integrate Risk response plans and their associated activities into the project along
with other activities.
Implement Risk Response -> Tools & Techniques -> PMIS
14. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Change request
Underlying risk
has been
triggered
Risk response
is
implemented
Change
request will be
raised
To update the
cost and
schedule
baselines
Implement Risk Response -> Output -> Change request