Program Evaluation Review Technique (PERT)
and its applications in Project Management
Submitted By-
Clayburn Calvert(26)
Shruti Mishra(27)
Amrit Mohanty(28)
Amit Raj(29)
Ravi Sunkara(30)
Submitted to:
Dr. Subhajit Bhattacharya
Objective of the presentation
• To understand the formula, the application and the benefits
of Program, Evaluation, and Review Technique (PERT)
analysis in Project Management.
Program (Project) Evaluation and Review Technique (PERT): is a
project management tool used to schedule, organize, and coordinate
tasks within a project. It is basically a method to analyse the tasks
involved in completing a given project, especially the time needed
to complete each task, and to identify the minimum time needed to
complete the total project.
What is PERT ?
Uses Of PERT in our daily lives
• PERT is used when activity times are uncertain.
• In many instances , managers have attempted to apply PERT
principles to other types of projects including:
 Hospital planning for such issues as costs and social security.
 Educational planning and development.
 Various Accounting Functions.
 Real Estate Development.
 PERT and Computer Project-Scheduling Software.
Uses Of PERT in our daily lives
Examples when PERT technique is used-
• A company decides to increase its production capacity by building a new
production unit . The project consists of separate tasks, some of which cannot
be started before others are completed. Thus PERT helps in listing the
activities along with the time expected for each activity.
• A company decides to launch a new product in the market. It requires several
steps. Some of these steps cannot begin until the others are completed. Thus
PERT helps in estimation of completion time and how much delay is possible
in the project completion.
PERT is applied to:
• Very large-scale
• One time
• Complex
• Non-routine infrastructure
• Research and Development Projects
Determine the duration of the project
• OPTIMISTIC TIME: Best time if everything goes perfectly
• REALISTIC TIME: Most likely time
• PESSIMISTIC TIME: A worst-case situation
B + 4M + P
Expected Time = -------------------
6
Three time estimates are required to compute the parameters of an
activity’s duration distribution:
Example:
Expected time for Excavation activity if B=12, M=18, P=60,
12 + 4(18) + 60
Expected Time = -------------------------
6
= 24 days
Determine the critical path
The critical path is
•Determined by adding the times for the activities in each sequence.
•Determining the longest path in the project.
The critical path determines the total calendar time required for the project. If
activities outside the critical path speed up or slow down (within limits), the
total project time does not change.
The amount of time that a non–critical path activity can be delayed without the
project is referred to as a slack time.
Project Crashing
Critical Path is helpful to determine
ES – Earliest Start time
EF - Earliest Finish time
LS – Latest Start time
LF - Latest Finish time
The project can be accelerated by adding the resources required to decrease the
time for the activities in the critical path.
Shortening of the project sometimes is referred to as Project Crashing.
•Make adjustments in the PERT chart as the project progresses.
•As the project unfolds, the estimated times can be replaced
with actual times.
In cases where
There are delays,
Additional resources may be needed to stay on schedule
The PERT chart may be modified to reflect the new situation.
Activity time
Crashing activity
Crash time
Crash cost
Normal Activity
Normal
time
Normal
cost
Slope = crash cost per unit time
Activity Crashing and Time-Cost Relationship
Time-Cost Relationship
 Crashing costs increase as project duration decreases
 Indirect costs increase as project duration increases
 Reduce project length as long as crashing costs are less than indirect costs
Time-Cost Tradeoff
time
Direct cost
Indirect cost
Total project costMin total cost =
optimal project time
Activity Crashing and Time-Cost Relationship
CASE STUDY
Analysis and Implementation of PERT in the Building of an
Aircraft
CASE STUDY
CONCLUSION
Organizations and the world in which they operate continue to
become more complex. Huge numbers of choices and relentless
time pressures and margin pressures make the decisions you face
more daunting and more difficult. Meanwhile, new enterprise
applications and software are generating massive amounts of data –
and it can seem like an overwhelming task to turn that data into
insight and answers.
But all that data and the availability of more and cheaper computing
power are creating an important opportunity for decision makers.
•O.R. is ideally designed to help you take advantage of. PERT.
•Professionals thrive on challenges that involve large numbers of
variables, complex systems, and significant risks.
As a result, PERT can help today’s executives with many of the
specific challenges.
Pert and its applications

Weitere ähnliche Inhalte

Was ist angesagt? (20)

PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
Social Cost Benefit Analysis
Social Cost Benefit Analysis Social Cost Benefit Analysis
Social Cost Benefit Analysis
 
Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysis
 
06 pert cpm
06 pert cpm06 pert cpm
06 pert cpm
 
Project planning and control
Project planning and controlProject planning and control
Project planning and control
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
 
Pert
PertPert
Pert
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
 
project management concepts
project management conceptsproject management concepts
project management concepts
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
 
Pert analysis
Pert analysisPert analysis
Pert analysis
 
Project Network project approaches and rules
Project Network  project approaches and rules Project Network  project approaches and rules
Project Network project approaches and rules
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Network analysis
Network analysisNetwork analysis
Network analysis
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 

Ähnlich wie Pert and its applications

Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)AnkitaKadam20
 
pert & CPM in production Engg an Operation Research
pert & CPM in production Engg an Operation Researchpert & CPM in production Engg an Operation Research
pert & CPM in production Engg an Operation ResearchBikash Choudhuri
 
PERT (Program evaluation review technique)
PERT (Program evaluation review technique) PERT (Program evaluation review technique)
PERT (Program evaluation review technique) Tanoj Patidar
 
Techniques of OR.pptx
Techniques of OR.pptxTechniques of OR.pptx
Techniques of OR.pptxArdraSabu
 
PERT-CPM for project management .pptx
PERT-CPM for project management    .pptxPERT-CPM for project management    .pptx
PERT-CPM for project management .pptxNaresh136982
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 
PERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingPERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingHariasha
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
unit-3 POM.pptx
unit-3 POM.pptxunit-3 POM.pptx
unit-3 POM.pptxjaya315652
 
NET WORK ANALYSIS.pptx
NET WORK ANALYSIS.pptxNET WORK ANALYSIS.pptx
NET WORK ANALYSIS.pptxpaulkinyua6
 
PERT VS CPM.docx
PERT VS CPM.docxPERT VS CPM.docx
PERT VS CPM.docxAshar Gill
 
Activity schedule and affective control of component based project
Activity schedule and affective control of component based projectActivity schedule and affective control of component based project
Activity schedule and affective control of component based projecteSAT Journals
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managersNaganna Chetty
 

Ähnlich wie Pert and its applications (20)

Unit IV-Project Management
Unit IV-Project ManagementUnit IV-Project Management
Unit IV-Project Management
 
Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
 
Seminar on pert
Seminar on pertSeminar on pert
Seminar on pert
 
Project time management
Project time managementProject time management
Project time management
 
PERT
PERTPERT
PERT
 
pert & CPM in production Engg an Operation Research
pert & CPM in production Engg an Operation Researchpert & CPM in production Engg an Operation Research
pert & CPM in production Engg an Operation Research
 
PERT (Program evaluation review technique)
PERT (Program evaluation review technique) PERT (Program evaluation review technique)
PERT (Program evaluation review technique)
 
Pert and mbo
Pert and mboPert and mbo
Pert and mbo
 
Techniques of OR.pptx
Techniques of OR.pptxTechniques of OR.pptx
Techniques of OR.pptx
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 
PERT-CPM for project management .pptx
PERT-CPM for project management    .pptxPERT-CPM for project management    .pptx
PERT-CPM for project management .pptx
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
PERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingPERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursing
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
unit-3 POM.pptx
unit-3 POM.pptxunit-3 POM.pptx
unit-3 POM.pptx
 
NET WORK ANALYSIS.pptx
NET WORK ANALYSIS.pptxNET WORK ANALYSIS.pptx
NET WORK ANALYSIS.pptx
 
PERT VS CPM.docx
PERT VS CPM.docxPERT VS CPM.docx
PERT VS CPM.docx
 
Activity schedule and affective control of component based project
Activity schedule and affective control of component based projectActivity schedule and affective control of component based project
Activity schedule and affective control of component based project
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
 

Kürzlich hochgeladen

Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...lizamodels9
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsMichael W. Hawkins
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxpriyanshujha201
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfAmzadHosen3
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 

Kürzlich hochgeladen (20)

Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael Hawkins
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdf
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 

Pert and its applications

  • 1. Program Evaluation Review Technique (PERT) and its applications in Project Management Submitted By- Clayburn Calvert(26) Shruti Mishra(27) Amrit Mohanty(28) Amit Raj(29) Ravi Sunkara(30) Submitted to: Dr. Subhajit Bhattacharya
  • 2. Objective of the presentation • To understand the formula, the application and the benefits of Program, Evaluation, and Review Technique (PERT) analysis in Project Management. Program (Project) Evaluation and Review Technique (PERT): is a project management tool used to schedule, organize, and coordinate tasks within a project. It is basically a method to analyse the tasks involved in completing a given project, especially the time needed to complete each task, and to identify the minimum time needed to complete the total project. What is PERT ?
  • 3. Uses Of PERT in our daily lives • PERT is used when activity times are uncertain. • In many instances , managers have attempted to apply PERT principles to other types of projects including:  Hospital planning for such issues as costs and social security.  Educational planning and development.  Various Accounting Functions.  Real Estate Development.  PERT and Computer Project-Scheduling Software.
  • 4. Uses Of PERT in our daily lives Examples when PERT technique is used- • A company decides to increase its production capacity by building a new production unit . The project consists of separate tasks, some of which cannot be started before others are completed. Thus PERT helps in listing the activities along with the time expected for each activity. • A company decides to launch a new product in the market. It requires several steps. Some of these steps cannot begin until the others are completed. Thus PERT helps in estimation of completion time and how much delay is possible in the project completion. PERT is applied to: • Very large-scale • One time • Complex • Non-routine infrastructure • Research and Development Projects
  • 5. Determine the duration of the project • OPTIMISTIC TIME: Best time if everything goes perfectly • REALISTIC TIME: Most likely time • PESSIMISTIC TIME: A worst-case situation B + 4M + P Expected Time = ------------------- 6 Three time estimates are required to compute the parameters of an activity’s duration distribution: Example: Expected time for Excavation activity if B=12, M=18, P=60, 12 + 4(18) + 60 Expected Time = ------------------------- 6 = 24 days
  • 6. Determine the critical path The critical path is •Determined by adding the times for the activities in each sequence. •Determining the longest path in the project. The critical path determines the total calendar time required for the project. If activities outside the critical path speed up or slow down (within limits), the total project time does not change. The amount of time that a non–critical path activity can be delayed without the project is referred to as a slack time.
  • 7. Project Crashing Critical Path is helpful to determine ES – Earliest Start time EF - Earliest Finish time LS – Latest Start time LF - Latest Finish time The project can be accelerated by adding the resources required to decrease the time for the activities in the critical path. Shortening of the project sometimes is referred to as Project Crashing. •Make adjustments in the PERT chart as the project progresses. •As the project unfolds, the estimated times can be replaced with actual times. In cases where There are delays, Additional resources may be needed to stay on schedule The PERT chart may be modified to reflect the new situation.
  • 8. Activity time Crashing activity Crash time Crash cost Normal Activity Normal time Normal cost Slope = crash cost per unit time Activity Crashing and Time-Cost Relationship
  • 9. Time-Cost Relationship  Crashing costs increase as project duration decreases  Indirect costs increase as project duration increases  Reduce project length as long as crashing costs are less than indirect costs Time-Cost Tradeoff time Direct cost Indirect cost Total project costMin total cost = optimal project time Activity Crashing and Time-Cost Relationship
  • 10. CASE STUDY Analysis and Implementation of PERT in the Building of an Aircraft
  • 11.
  • 13. CONCLUSION Organizations and the world in which they operate continue to become more complex. Huge numbers of choices and relentless time pressures and margin pressures make the decisions you face more daunting and more difficult. Meanwhile, new enterprise applications and software are generating massive amounts of data – and it can seem like an overwhelming task to turn that data into insight and answers. But all that data and the availability of more and cheaper computing power are creating an important opportunity for decision makers. •O.R. is ideally designed to help you take advantage of. PERT. •Professionals thrive on challenges that involve large numbers of variables, complex systems, and significant risks. As a result, PERT can help today’s executives with many of the specific challenges.