SlideShare ist ein Scribd-Unternehmen logo
1 von 35
Downloaden Sie, um offline zu lesen
BRIDGES  AND  TUNNELS  ASIA  2014
20th March  2014
Procurement  and  Delivery  for  
Mega  Tunnel  Projects
© Steve TennantConsultancy Ltd2014 1
Procurementand Delivery for
Mega Tunnel Projects
OVERVIEW
§ Introduction
§ Some  Governments  have  been  
concerned  at  cost  of  infrastructure  
procurement    
§ Findings?
§ Some  Experiences  and  Thoughts
§ Questions
© Steve TennantConsultancy Ltd2014 2
Procurementand Delivery for
Mega Tunnel Projects
Introduction
§ Can  Procurement  and  Delivery  of  
Infrastructure  be  improved?
§ A  question  poised  by  more  and  more  
Governments  in  21st Century
© Steve TennantConsultancy Ltd2014 3
Procurementand Delivery for
Mega Tunnel Projects
Introduction
§ Application  to  Mega  Tunnels?
§ Improved  Tunneling  Technology
§ Water,  Sewage,  Road,  Utilities
§ Resurgence  of  Rail:
• Freight
• Urban  Mass  Transit
• High  Speed  etc.  
© Steve TennantConsultancy Ltd2014 4
Procurementand Delivery for
Mega Tunnel Projects
UK  Government
§ “1.15  The  
conclusion  of  the  
review  is  that  
infrastructure  costs  
can  be  reduced  by  
at  least  15  per  cent.”
Infrastructure  UK,  
‘Infrastructure  Cost  
Review:  Main  Report  
December  2010
© Steve TennantConsultancy Ltd2014 5
Procurementand Delivery for
Mega Tunnel Projects
UK  Government
§ “There  is  no  single  
overriding  factor  driving  
higher  costs.  However,  
the  investigation  has  
identified  that  higher  
costs  are  mainly  
generated  in  the  early  
project  formulation  and  
pre-­construction  phases  
…”
© Steve TennantConsultancy Ltd2014 6
Procurementand Delivery for
Mega Tunnel Projects
Australian  Government
Similar  Studies  by
§ New  Zealand
§ Germany
§ United  States
§ Canada
§ Hong  Kong
© Steve TennantConsultancy Ltd2014 7
Procurementand Delivery for
Mega Tunnel Projects
Findings?
§ Traditional  
Procurement
§ Engineer  Design  /  
Contractor  Build  or  
D&B
§ Based  on  adversarial  
contracting  methods
§ Not  focused  on  
lowest  outturn  cost
§ Promotes  (or  
responds  to?)  risk  
averse  attitude  by  
public  sector  clients
§ Box  ticking  culture
§ Evaluation  criteria  
favour  lower  price  
bid,  rather  than  
lowest  cost  outcome
§ Does  not  promote  
innovation
© Steve TennantConsultancy Ltd2014 8
Procurementand Delivery for
Mega Tunnel Projects
Findings?  cont’d
§ Traditional  
Procurement  cont’d
§ Client  and  business  
needs  not  at  core  of  
process
§ Projects  /  
programmes  within  
quoted  budget,  not  
lowest  price  for  
required  performance
§ Insufficient  
consideration  given  
to  assessment,  
placement  &  
management  of  
contingency  &  risk  
budgets
§ Over  specification  to  
detriment  of  cost
© Steve TennantConsultancy Ltd2014 9
Procurementand Delivery for
Mega Tunnel Projects
Findings?  cont’d
§ Traditional  procurement  methodology  ‘…  
estimated  to  cost  around  10%  of  annual  
construction  capital  spending  …  could  be  
saved’
UK  National  Audit  Office,  Improving  Public  Services  
through  better  construction, 15  March  2005,  p6
© Steve TennantConsultancy Ltd2014 10
Procurementand Delivery for
Mega Tunnel Projects
Findings?  cont’d
§ Recommended  ways  forward:
§ PPP/BOT  – Has  its  place  but  not  for  every  
project,  project  owner  or  contractor  
§ Early  Contractor  Involvement  Design  &  
Build  – Two  stage  tendering
§ Relationship  Contracting  – Contractual  
partnering,  no  blame  culture,  project  wide  
insurance,  fair  payments;;  shared  pain  /  
shared  gain
© Steve TennantConsultancy Ltd2014 11
Procurementand Delivery for
Mega Tunnel Projects
Findings?  cont’d
§ Recommended  ways  forward:
§ Target  Cost  Contract,  not  Cost  Plus  – All  
parties  have  to  earn  their  reward
§ Replace  strict  lowest-­tender  selection  
criteria  to  value  for  money  -­ Contractor  
past  performance;;  whole  of  life  costs;;  Local  
development  and  value  adding;;  
Timeliness;;  Capacity;;  Innovation
© Steve TennantConsultancy Ltd2014 12
Procurementand Delivery for
Mega Tunnel Projects
Findings?  cont’d
§ Recommended  ways  forward:
§ Improved  construction  project  
management  capability  – Employer;;
Consultant;; Contractor;;  Sub-­contractor;;  
Supplier  sides
§ Keep  competitive  tension  during  project  
delivery,  not  just  tender  – benchmarking;;  
KPI’s;;  sanctions
© Steve TennantConsultancy Ltd2014 13
Procurementand Delivery for
Mega Tunnel Projects
Findings?  cont’d
§ Recommended  ways  forward:
§ Post  completion  and  occupancy  
performance  evaluations  – Not  just  
performance  during  construction
© Steve TennantConsultancy Ltd2014 14
Procurementand Delivery for
Mega Tunnel Projects
Some  Experiences  and  Thoughts
§ Procurement
§ Remember,  generally  the  Client  does  not  
want  the  Project  process,  only  the  end  
result.
§ Given  a  choice,  the  Client  would  always  
like  the  end  result  without  the  birthing  
process.
© Steve TennantConsultancy Ltd2014 15
Procurementand Delivery for
Mega Tunnel Projects
Some  Experiences  and  Thoughts
§ Procurement
§ “I  want  the  world’s  best  new  5  year  old  
railway”
Russell  Black  HK  MTR  Project  Director  1992-­
2010
§ Innovation  yes,  untested  no
© Steve TennantConsultancy Ltd2014 16
Procurementand Delivery for
Mega Tunnel Projects
Some  Experiences  and  Thoughts
§ Procurement
• ‘Evidence  from  European  and  Australian  
studies  suggests  that,  when  governments  
use  lowest-­price  tender  methods,  around  
70%  of  projects  are  late  and  a  similar  
percentage  are  over  budget…  This  does  not  
necessarily  mean  that  procurement  by  
tender  is  the  problem.’
Regan M,  Smith J,  Love P,  ‘Infrastructure  procurement:  learning  from  
private – public  partnership  experiences   ‘down  under’’ (2011)  29(2)
Environment  and  Planning  C:  Government   and  Policy  363,  366
© Steve TennantConsultancy Ltd2014 17
Procurementand Delivery for
Mega Tunnel Projects
Some  Experiences  and  Thoughts
§ Procurement  -­ Consultants
§ Consultant  appointment  decisions  should  
not  be  cost  based
§ As  part  of  selection  process  have  
workshops  between  proposed  consultant  
and  employer  teams
§ Look  for  experience,  competency,  
creativity  and  above  all  chemistry
© Steve TennantConsultancy Ltd2014 18
Procurementand Delivery for
Mega Tunnel Projects
Some  Experiences  and  Thoughts
§ Procurement-­ Consultants
§ Consultant  fees  a  small  %  of  CAPEX  but  
deterministic  of  project  outcome
§ Fee  must  be  enough  to  provide  required  
service
§ ‘…competitive  tendering  stimulates  design  
firms  to  opportunistic  and  unethical  
behaviors’  P.E.D.  Love  ‘’Plugging  the  Gaps’  Between  Optimum  
Bias  and  Strategic  Misrepresentation   and  Infrastructure  Cost  
Overruns’  EASEC12,  (January  2011)  Vol 14,  1197,  1203.  
© Steve TennantConsultancy Ltd2014 19
Procurementand Delivery for
Mega Tunnel Projects
A  Nomological  Framework  of  
Design  Error  and  Project  
Overruns  
From
P.E.D.  Love,  ‘’Plugging   the  Gaps’  
Between  Optimum  Bias  and  
Strategic  Misrepresentation   and  
Infrastructure  Cost  Overruns’  (The  
Twelfth  East  Asia-­Pacific  
Conference  on  Structural  
Engineering   and  Construction,  
EASEC12,  (January  2011)  Vol 14,  
1197,  1203.  
<www.sciencedirect.com/science/ar
ticle/pii/S1877705811012276>  
accessed  10  March  2014
NOTE:  Optimum  Bias  may  perhaps  
be  more  readily  understood  as  
‘Optimism  Bias’.  Larger  image  of  
graphic  on  next  slide.
© Steve TennantConsultancy Ltd2014 20
	
  
OPTIMUM	
  BIAS
	
  
	
  
PROJECT
	
  
	
  
ORGANIZATION
Schedule
Pressure
Project
Governance
Issue	
  of
erroneous	
  
documents
Project
Dissonance
Design	
  audits
&	
  reviews
Design
Co-­‐ordination
Response	
  for	
  
requests
For	
  information	
  
	
  Error
Identification	
  
Schedule
Pressure
Organization
Circumstance
Practice
(omissions)
Task
(mistakes,	
  mishaps,	
  
slips,	
  lapses)
Fee	
  LevelFee	
  Level
Time	
  BoxingTime	
  Boxing
Turn	
  overTurn	
  overStaff	
  MoraleStaff	
  Morale
ProductivityProductivity
Design	
  audits	
  
and	
  reviews
Design	
  audits	
  
and	
  reviews
Production	
  of	
  
erroneous	
  
documents
Production	
  of	
  
erroneous	
  
documents
Resource	
  
availability
Resource	
  
availability
Cognitive	
  
dissonance
Cognitive	
  
dissonance
Additional	
  
time
Additional	
  
time
Multi	
  taskingMulti	
  tasking
Skill	
  &	
  
experience
Skill	
  &	
  
experience
ReworkRework
Contractual	
  
variation/
claim
Contractual	
  
variation/
claim
Cost/schedule	
  
increase
Cost/schedule	
  
increase
Reduced	
  
profits
Reduced	
  
profits
DisputeDispute
Procurementand Delivery for
Mega Tunnel Projects
© Steve TennantConsultancy Ltd2014 21
	
  
OPTIMUM	
  BIAS
	
  
	
  
PROJECT
	
  
	
  
ORGANIZATION Schedule
Pressure
Project
Governance
Issue	
  of
erroneous	
  
documents
Project
Dissonance
Design	
  audits
&	
  reviews
Design
Co-­‐ordination
Response	
  for	
  
requests
For	
  information	
  
	
  Error
Identification	
  
Schedule
Pressure
Organization
Circumstance
Practice
(omissions)
Task
(mistakes,	
  mishaps,	
  
slips,	
  lapses)
Fee	
  LevelFee	
  Level
Time	
  BoxingTime	
  Boxing
Turn	
  overTurn	
  overStaff	
  MoraleStaff	
  Morale
ProductivityProductivity
Design	
  audits	
  
and	
  reviews
Design	
  audits	
  
and	
  reviews
Production	
  of	
  
erroneous	
  
documents
Production	
  of	
  
erroneous	
  
documents
Resource	
  
availability
Resource	
  
availability
Cognitive	
  
dissonance
Cognitive	
  
dissonance
Additional	
  
time
Additional	
  
time
Multi	
  taskingMulti	
  tasking
Skill	
  &	
  
experience
Skill	
  &	
  
experience
ReworkRework
Contractual	
  
variation/
claim
Contractual	
  
variation/
claim
Cost/schedule	
  
increase
Cost/schedule	
  
increase
Reduced	
  
profits
Reduced	
  
profits
DisputeDispute
Procurementand Delivery for
Mega Tunnel Projects
Some  Experiences  and  Thoughts
§ Procurement  -­ Contractors
§ Relationship  Contracting  – One  Size  fits  
all?
§ HKG  Government  apparently  yes.  NEC3  to  
be  preferred  Conditions  of  Contract  by  
2016  
§ HKG  MTR  No.  They  use  Target  Cost,  
Lump  Sum  D&B,  Eng Design  Lump  Sum/  
Remeasurement
© Steve TennantConsultancy Ltd2014 22
Procurementand Delivery for
Mega Tunnel Projects
Some  Experiences  and  Thoughts
§ Procurement  -­ Contractors
§ Pros  and  Cons?
• Eng Design  Lump  Sum/  Remeasurement
Adversarial  if  (when?)  things  go  wrong
• Lump  Sum  D&B
Lose  benefit  of  on  going  design  development
Design  development  vs  changed  requirement
© Steve TennantConsultancy Ltd2014 23
Procurementand Delivery for
Mega Tunnel Projects
Some  Experiences  and  Thoughts
§ Procurement  -­ Contractors
§ Pros  and  Cons?
• Target  Cost
Greater  PM  input  from  Owner,  Consultant,  
Contractor,  cost,  availability  of  resources
Different  way  of  thinking  &  acting.  True  Partnering
Can  still  have  disagreements  and  disputes
Shared  pain  shared  gain,  but  need  to  wary  of  cost  
manipulation  in  open  book  accounting
Bench  marking,  KPIs  to  maintain  competition    
© Steve TennantConsultancy Ltd2014 24
Procurementand Delivery for
Mega Tunnel Projects
Some  Experiences  and  Thoughts
§ Tate’s  Cairn  Tunnel,  Hong  Kong
§ 4  lanes,  twin  tube  4km  road  tunnel.  30  year  
BOT  franchise  awarded  July  1988,  opened  
June  1991
© Steve TennantConsultancy Ltd2014 25
Procurementand Delivery for
Mega Tunnel Projects
© Steve TennantConsultancy Ltd2014 26
Procurementand Delivery for
Mega Tunnel Projects
Some  Experiences  and  Thoughts
§ Tate’s  Cairn  Tunnel,  Hong  Kong
§ 4  lanes,  twin  tube  4km  road  tunnel.  30  year  
BOT  franchise  awarded  July  1988,  opened  
June  1991
§ Inclined  ventilation  adits
§ Overhead  ventilation  slab
© Steve TennantConsultancy Ltd2014 27
Procurementand Delivery for
Mega Tunnel Projects
Some  Experiences  and  Thoughts
§ HEC  Nam  Fung  Road  to  Parker  Cable  
Tunnel
§ 4.8m  dia,  5.7km  single  tube  TBM  driven  
tunnel
© Steve TennantConsultancy Ltd2014 28
Procurementand Delivery for
Mega Tunnel Projects
© Steve TennantConsultancy Ltd2014 29
Procurementand Delivery for
Mega Tunnel Projects
Some  Experiences  and  Thoughts
§ HEC  Nam  Fung  Road  to  Parker  Cable  
Tunnel
§ 4.8m  dia,  5.7km  single  tube  TBM  driven  
tunnel
§ Offered  as  alternative  (more  expensive)  
D&B  tender  to  trenched  cable  route
§ Why  did  HEC  accept  the  more  expensive  
alternative?
© Steve TennantConsultancy Ltd2014 30
Procurementand Delivery for
Mega Tunnel Projects
Some  Experiences  and  Thoughts
§ Route  3  Country  Park  Section
§ Dual  tube  3  lane  Road  tunnel.  3.8km  long
§ BOT  Concession
© Steve TennantConsultancy Ltd2014 31
Procurementand Delivery for
Mega Tunnel Projects
© Steve TennantConsultancy Ltd2014 32
Procurementand Delivery for
Mega Tunnel Projects
Some  Experiences  and  Thoughts
§ Route  3  Country  Park  Section
§ Dual  tube  3  lane  Road  tunnel.  3.8km  long
§ BOT  Concession
§ Ability  to  submit  alternative  engineering  
proposals  in  additional  to  minimum  
conforming  bid
§ Resulted  in  further  two  rounds  of  proposals  
being  invited!
© Steve TennantConsultancy Ltd2014 33
Procurementand Delivery for
Mega Tunnel Projects
Questions
§ As  a  Project  Owner,  do  you  procure  
tunnels  by  the  “Traditional  Method”  and  
if  so,  why?
§ As  a  Consultant,  do  you  recommend  
procurement  of  tunnels  by  the  
“Traditional  Method”  and  if  so,  why?
© Steve TennantConsultancy Ltd2014 34
Procurementand Delivery for
Mega Tunnel Projects
Thank  You
© Steve TennantConsultancy Ltd2014 35

Weitere ähnliche Inhalte

Ähnlich wie Procurement and Delivery for Mega Tunnel Projects.ppt

Project Development Routemap UK – Caribbean Knowledge Exchange Programme
Project Development Routemap UK – Caribbean  Knowledge Exchange  ProgrammeProject Development Routemap UK – Caribbean  Knowledge Exchange  Programme
Project Development Routemap UK – Caribbean Knowledge Exchange ProgrammeCaribbean Development Bank
 
Cv master english 30-01-18 v.1
Cv   master english 30-01-18 v.1Cv   master english 30-01-18 v.1
Cv master english 30-01-18 v.1Ricardo F. Trenard
 
SMART Seminar Series: Public Infrastructure Investment in the 2000s: Lessons ...
SMART Seminar Series: Public Infrastructure Investment in the 2000s: Lessons ...SMART Seminar Series: Public Infrastructure Investment in the 2000s: Lessons ...
SMART Seminar Series: Public Infrastructure Investment in the 2000s: Lessons ...SMART Infrastructure Facility
 
Final Presentation for mock Defence December 2023.pdf
Final Presentation for mock Defence December 2023.pdfFinal Presentation for mock Defence December 2023.pdf
Final Presentation for mock Defence December 2023.pdfnitintkatti
 
Resume - Vikas Datta-v2
Resume - Vikas Datta-v2Resume - Vikas Datta-v2
Resume - Vikas Datta-v2VIKAS DATTA
 
2 seminar deloitte presentation_oda project_en_171212_v6
2 seminar deloitte presentation_oda project_en_171212_v62 seminar deloitte presentation_oda project_en_171212_v6
2 seminar deloitte presentation_oda project_en_171212_v6ADHITYA LESTARI
 
Study of Different Public-Private Partnership (PPP) Model for the Road Infras...
Study of Different Public-Private Partnership (PPP) Model for the Road Infras...Study of Different Public-Private Partnership (PPP) Model for the Road Infras...
Study of Different Public-Private Partnership (PPP) Model for the Road Infras...IRJET Journal
 
Iain Cameron CV presentation jun13
Iain Cameron CV presentation jun13Iain Cameron CV presentation jun13
Iain Cameron CV presentation jun13iain_cameron
 
Gensol group of companies corporate presentation
Gensol group of companies corporate presentationGensol group of companies corporate presentation
Gensol group of companies corporate presentationAshish Verma
 
Bridging the gap – meeting the needs of PPP projects
Bridging the gap – meeting the needs of PPP projectsBridging the gap – meeting the needs of PPP projects
Bridging the gap – meeting the needs of PPP projectsJumpingJaq
 
Bigger, larger, heavier
Bigger, larger, heavierBigger, larger, heavier
Bigger, larger, heavierBVG Associates
 
Anthony Nemeth_CV_180716v1
Anthony Nemeth_CV_180716v1Anthony Nemeth_CV_180716v1
Anthony Nemeth_CV_180716v1Anthony Nemeth
 
alan_morrison_resume (15)
alan_morrison_resume (15)alan_morrison_resume (15)
alan_morrison_resume (15)Alan Morrison
 

Ähnlich wie Procurement and Delivery for Mega Tunnel Projects.ppt (20)

Project Development Routemap UK – Caribbean Knowledge Exchange Programme
Project Development Routemap UK – Caribbean  Knowledge Exchange  ProgrammeProject Development Routemap UK – Caribbean  Knowledge Exchange  Programme
Project Development Routemap UK – Caribbean Knowledge Exchange Programme
 
Cv master english 30-01-18 v.1
Cv   master english 30-01-18 v.1Cv   master english 30-01-18 v.1
Cv master english 30-01-18 v.1
 
SMART Seminar Series: Public Infrastructure Investment in the 2000s: Lessons ...
SMART Seminar Series: Public Infrastructure Investment in the 2000s: Lessons ...SMART Seminar Series: Public Infrastructure Investment in the 2000s: Lessons ...
SMART Seminar Series: Public Infrastructure Investment in the 2000s: Lessons ...
 
Quantity Surveyor CV
Quantity Surveyor CVQuantity Surveyor CV
Quantity Surveyor CV
 
Final Presentation for mock Defence December 2023.pdf
Final Presentation for mock Defence December 2023.pdfFinal Presentation for mock Defence December 2023.pdf
Final Presentation for mock Defence December 2023.pdf
 
Resume - Vikas Datta-v2
Resume - Vikas Datta-v2Resume - Vikas Datta-v2
Resume - Vikas Datta-v2
 
EoI Nigeria-BRT
EoI Nigeria-BRTEoI Nigeria-BRT
EoI Nigeria-BRT
 
SRIDHARAN
SRIDHARANSRIDHARAN
SRIDHARAN
 
Australia's Experience with PPPs in Infrastructure
Australia's Experience with PPPs in InfrastructureAustralia's Experience with PPPs in Infrastructure
Australia's Experience with PPPs in Infrastructure
 
Benefits Highlight Report
Benefits Highlight ReportBenefits Highlight Report
Benefits Highlight Report
 
2 seminar deloitte presentation_oda project_en_171212_v6
2 seminar deloitte presentation_oda project_en_171212_v62 seminar deloitte presentation_oda project_en_171212_v6
2 seminar deloitte presentation_oda project_en_171212_v6
 
Study of Different Public-Private Partnership (PPP) Model for the Road Infras...
Study of Different Public-Private Partnership (PPP) Model for the Road Infras...Study of Different Public-Private Partnership (PPP) Model for the Road Infras...
Study of Different Public-Private Partnership (PPP) Model for the Road Infras...
 
Iain Cameron CV presentation jun13
Iain Cameron CV presentation jun13Iain Cameron CV presentation jun13
Iain Cameron CV presentation jun13
 
20320140503023
2032014050302320320140503023
20320140503023
 
Gensol group of companies corporate presentation
Gensol group of companies corporate presentationGensol group of companies corporate presentation
Gensol group of companies corporate presentation
 
Bridging the gap – meeting the needs of PPP projects
Bridging the gap – meeting the needs of PPP projectsBridging the gap – meeting the needs of PPP projects
Bridging the gap – meeting the needs of PPP projects
 
Bigger, larger, heavier
Bigger, larger, heavierBigger, larger, heavier
Bigger, larger, heavier
 
Anthony Nemeth_CV_180716v1
Anthony Nemeth_CV_180716v1Anthony Nemeth_CV_180716v1
Anthony Nemeth_CV_180716v1
 
alan_morrison_resume (15)
alan_morrison_resume (15)alan_morrison_resume (15)
alan_morrison_resume (15)
 
Qs
QsQs
Qs
 

Procurement and Delivery for Mega Tunnel Projects.ppt

  • 1. BRIDGES  AND  TUNNELS  ASIA  2014 20th March  2014 Procurement  and  Delivery  for   Mega  Tunnel  Projects © Steve TennantConsultancy Ltd2014 1
  • 2. Procurementand Delivery for Mega Tunnel Projects OVERVIEW § Introduction § Some  Governments  have  been   concerned  at  cost  of  infrastructure   procurement     § Findings? § Some  Experiences  and  Thoughts § Questions © Steve TennantConsultancy Ltd2014 2
  • 3. Procurementand Delivery for Mega Tunnel Projects Introduction § Can  Procurement  and  Delivery  of   Infrastructure  be  improved? § A  question  poised  by  more  and  more   Governments  in  21st Century © Steve TennantConsultancy Ltd2014 3
  • 4. Procurementand Delivery for Mega Tunnel Projects Introduction § Application  to  Mega  Tunnels? § Improved  Tunneling  Technology § Water,  Sewage,  Road,  Utilities § Resurgence  of  Rail: • Freight • Urban  Mass  Transit • High  Speed  etc.   © Steve TennantConsultancy Ltd2014 4
  • 5. Procurementand Delivery for Mega Tunnel Projects UK  Government § “1.15  The   conclusion  of  the   review  is  that   infrastructure  costs   can  be  reduced  by   at  least  15  per  cent.” Infrastructure  UK,   ‘Infrastructure  Cost   Review:  Main  Report   December  2010 © Steve TennantConsultancy Ltd2014 5
  • 6. Procurementand Delivery for Mega Tunnel Projects UK  Government § “There  is  no  single   overriding  factor  driving   higher  costs.  However,   the  investigation  has   identified  that  higher   costs  are  mainly   generated  in  the  early   project  formulation  and   pre-­construction  phases   …” © Steve TennantConsultancy Ltd2014 6
  • 7. Procurementand Delivery for Mega Tunnel Projects Australian  Government Similar  Studies  by § New  Zealand § Germany § United  States § Canada § Hong  Kong © Steve TennantConsultancy Ltd2014 7
  • 8. Procurementand Delivery for Mega Tunnel Projects Findings? § Traditional   Procurement § Engineer  Design  /   Contractor  Build  or   D&B § Based  on  adversarial   contracting  methods § Not  focused  on   lowest  outturn  cost § Promotes  (or   responds  to?)  risk   averse  attitude  by   public  sector  clients § Box  ticking  culture § Evaluation  criteria   favour  lower  price   bid,  rather  than   lowest  cost  outcome § Does  not  promote   innovation © Steve TennantConsultancy Ltd2014 8
  • 9. Procurementand Delivery for Mega Tunnel Projects Findings?  cont’d § Traditional   Procurement  cont’d § Client  and  business   needs  not  at  core  of   process § Projects  /   programmes  within   quoted  budget,  not   lowest  price  for   required  performance § Insufficient   consideration  given   to  assessment,   placement  &   management  of   contingency  &  risk   budgets § Over  specification  to   detriment  of  cost © Steve TennantConsultancy Ltd2014 9
  • 10. Procurementand Delivery for Mega Tunnel Projects Findings?  cont’d § Traditional  procurement  methodology  ‘…   estimated  to  cost  around  10%  of  annual   construction  capital  spending  …  could  be   saved’ UK  National  Audit  Office,  Improving  Public  Services   through  better  construction, 15  March  2005,  p6 © Steve TennantConsultancy Ltd2014 10
  • 11. Procurementand Delivery for Mega Tunnel Projects Findings?  cont’d § Recommended  ways  forward: § PPP/BOT  – Has  its  place  but  not  for  every   project,  project  owner  or  contractor   § Early  Contractor  Involvement  Design  &   Build  – Two  stage  tendering § Relationship  Contracting  – Contractual   partnering,  no  blame  culture,  project  wide   insurance,  fair  payments;;  shared  pain  /   shared  gain © Steve TennantConsultancy Ltd2014 11
  • 12. Procurementand Delivery for Mega Tunnel Projects Findings?  cont’d § Recommended  ways  forward: § Target  Cost  Contract,  not  Cost  Plus  – All   parties  have  to  earn  their  reward § Replace  strict  lowest-­tender  selection   criteria  to  value  for  money  -­ Contractor   past  performance;;  whole  of  life  costs;;  Local   development  and  value  adding;;   Timeliness;;  Capacity;;  Innovation © Steve TennantConsultancy Ltd2014 12
  • 13. Procurementand Delivery for Mega Tunnel Projects Findings?  cont’d § Recommended  ways  forward: § Improved  construction  project   management  capability  – Employer;; Consultant;; Contractor;;  Sub-­contractor;;   Supplier  sides § Keep  competitive  tension  during  project   delivery,  not  just  tender  – benchmarking;;   KPI’s;;  sanctions © Steve TennantConsultancy Ltd2014 13
  • 14. Procurementand Delivery for Mega Tunnel Projects Findings?  cont’d § Recommended  ways  forward: § Post  completion  and  occupancy   performance  evaluations  – Not  just   performance  during  construction © Steve TennantConsultancy Ltd2014 14
  • 15. Procurementand Delivery for Mega Tunnel Projects Some  Experiences  and  Thoughts § Procurement § Remember,  generally  the  Client  does  not   want  the  Project  process,  only  the  end   result. § Given  a  choice,  the  Client  would  always   like  the  end  result  without  the  birthing   process. © Steve TennantConsultancy Ltd2014 15
  • 16. Procurementand Delivery for Mega Tunnel Projects Some  Experiences  and  Thoughts § Procurement § “I  want  the  world’s  best  new  5  year  old   railway” Russell  Black  HK  MTR  Project  Director  1992-­ 2010 § Innovation  yes,  untested  no © Steve TennantConsultancy Ltd2014 16
  • 17. Procurementand Delivery for Mega Tunnel Projects Some  Experiences  and  Thoughts § Procurement • ‘Evidence  from  European  and  Australian   studies  suggests  that,  when  governments   use  lowest-­price  tender  methods,  around   70%  of  projects  are  late  and  a  similar   percentage  are  over  budget…  This  does  not   necessarily  mean  that  procurement  by   tender  is  the  problem.’ Regan M,  Smith J,  Love P,  ‘Infrastructure  procurement:  learning  from   private – public  partnership  experiences   ‘down  under’’ (2011)  29(2) Environment  and  Planning  C:  Government   and  Policy  363,  366 © Steve TennantConsultancy Ltd2014 17
  • 18. Procurementand Delivery for Mega Tunnel Projects Some  Experiences  and  Thoughts § Procurement  -­ Consultants § Consultant  appointment  decisions  should   not  be  cost  based § As  part  of  selection  process  have   workshops  between  proposed  consultant   and  employer  teams § Look  for  experience,  competency,   creativity  and  above  all  chemistry © Steve TennantConsultancy Ltd2014 18
  • 19. Procurementand Delivery for Mega Tunnel Projects Some  Experiences  and  Thoughts § Procurement-­ Consultants § Consultant  fees  a  small  %  of  CAPEX  but   deterministic  of  project  outcome § Fee  must  be  enough  to  provide  required   service § ‘…competitive  tendering  stimulates  design   firms  to  opportunistic  and  unethical   behaviors’  P.E.D.  Love  ‘’Plugging  the  Gaps’  Between  Optimum   Bias  and  Strategic  Misrepresentation   and  Infrastructure  Cost   Overruns’  EASEC12,  (January  2011)  Vol 14,  1197,  1203.   © Steve TennantConsultancy Ltd2014 19
  • 20. Procurementand Delivery for Mega Tunnel Projects A  Nomological  Framework  of   Design  Error  and  Project   Overruns   From P.E.D.  Love,  ‘’Plugging   the  Gaps’   Between  Optimum  Bias  and   Strategic  Misrepresentation   and   Infrastructure  Cost  Overruns’  (The   Twelfth  East  Asia-­Pacific   Conference  on  Structural   Engineering   and  Construction,   EASEC12,  (January  2011)  Vol 14,   1197,  1203.   <www.sciencedirect.com/science/ar ticle/pii/S1877705811012276>   accessed  10  March  2014 NOTE:  Optimum  Bias  may  perhaps   be  more  readily  understood  as   ‘Optimism  Bias’.  Larger  image  of   graphic  on  next  slide. © Steve TennantConsultancy Ltd2014 20   OPTIMUM  BIAS     PROJECT     ORGANIZATION Schedule Pressure Project Governance Issue  of erroneous   documents Project Dissonance Design  audits &  reviews Design Co-­‐ordination Response  for   requests For  information    Error Identification   Schedule Pressure Organization Circumstance Practice (omissions) Task (mistakes,  mishaps,   slips,  lapses) Fee  LevelFee  Level Time  BoxingTime  Boxing Turn  overTurn  overStaff  MoraleStaff  Morale ProductivityProductivity Design  audits   and  reviews Design  audits   and  reviews Production  of   erroneous   documents Production  of   erroneous   documents Resource   availability Resource   availability Cognitive   dissonance Cognitive   dissonance Additional   time Additional   time Multi  taskingMulti  tasking Skill  &   experience Skill  &   experience ReworkRework Contractual   variation/ claim Contractual   variation/ claim Cost/schedule   increase Cost/schedule   increase Reduced   profits Reduced   profits DisputeDispute
  • 21. Procurementand Delivery for Mega Tunnel Projects © Steve TennantConsultancy Ltd2014 21   OPTIMUM  BIAS     PROJECT     ORGANIZATION Schedule Pressure Project Governance Issue  of erroneous   documents Project Dissonance Design  audits &  reviews Design Co-­‐ordination Response  for   requests For  information    Error Identification   Schedule Pressure Organization Circumstance Practice (omissions) Task (mistakes,  mishaps,   slips,  lapses) Fee  LevelFee  Level Time  BoxingTime  Boxing Turn  overTurn  overStaff  MoraleStaff  Morale ProductivityProductivity Design  audits   and  reviews Design  audits   and  reviews Production  of   erroneous   documents Production  of   erroneous   documents Resource   availability Resource   availability Cognitive   dissonance Cognitive   dissonance Additional   time Additional   time Multi  taskingMulti  tasking Skill  &   experience Skill  &   experience ReworkRework Contractual   variation/ claim Contractual   variation/ claim Cost/schedule   increase Cost/schedule   increase Reduced   profits Reduced   profits DisputeDispute
  • 22. Procurementand Delivery for Mega Tunnel Projects Some  Experiences  and  Thoughts § Procurement  -­ Contractors § Relationship  Contracting  – One  Size  fits   all? § HKG  Government  apparently  yes.  NEC3  to   be  preferred  Conditions  of  Contract  by   2016   § HKG  MTR  No.  They  use  Target  Cost,   Lump  Sum  D&B,  Eng Design  Lump  Sum/   Remeasurement © Steve TennantConsultancy Ltd2014 22
  • 23. Procurementand Delivery for Mega Tunnel Projects Some  Experiences  and  Thoughts § Procurement  -­ Contractors § Pros  and  Cons? • Eng Design  Lump  Sum/  Remeasurement Adversarial  if  (when?)  things  go  wrong • Lump  Sum  D&B Lose  benefit  of  on  going  design  development Design  development  vs  changed  requirement © Steve TennantConsultancy Ltd2014 23
  • 24. Procurementand Delivery for Mega Tunnel Projects Some  Experiences  and  Thoughts § Procurement  -­ Contractors § Pros  and  Cons? • Target  Cost Greater  PM  input  from  Owner,  Consultant,   Contractor,  cost,  availability  of  resources Different  way  of  thinking  &  acting.  True  Partnering Can  still  have  disagreements  and  disputes Shared  pain  shared  gain,  but  need  to  wary  of  cost   manipulation  in  open  book  accounting Bench  marking,  KPIs  to  maintain  competition     © Steve TennantConsultancy Ltd2014 24
  • 25. Procurementand Delivery for Mega Tunnel Projects Some  Experiences  and  Thoughts § Tate’s  Cairn  Tunnel,  Hong  Kong § 4  lanes,  twin  tube  4km  road  tunnel.  30  year   BOT  franchise  awarded  July  1988,  opened   June  1991 © Steve TennantConsultancy Ltd2014 25
  • 26. Procurementand Delivery for Mega Tunnel Projects © Steve TennantConsultancy Ltd2014 26
  • 27. Procurementand Delivery for Mega Tunnel Projects Some  Experiences  and  Thoughts § Tate’s  Cairn  Tunnel,  Hong  Kong § 4  lanes,  twin  tube  4km  road  tunnel.  30  year   BOT  franchise  awarded  July  1988,  opened   June  1991 § Inclined  ventilation  adits § Overhead  ventilation  slab © Steve TennantConsultancy Ltd2014 27
  • 28. Procurementand Delivery for Mega Tunnel Projects Some  Experiences  and  Thoughts § HEC  Nam  Fung  Road  to  Parker  Cable   Tunnel § 4.8m  dia,  5.7km  single  tube  TBM  driven   tunnel © Steve TennantConsultancy Ltd2014 28
  • 29. Procurementand Delivery for Mega Tunnel Projects © Steve TennantConsultancy Ltd2014 29
  • 30. Procurementand Delivery for Mega Tunnel Projects Some  Experiences  and  Thoughts § HEC  Nam  Fung  Road  to  Parker  Cable   Tunnel § 4.8m  dia,  5.7km  single  tube  TBM  driven   tunnel § Offered  as  alternative  (more  expensive)   D&B  tender  to  trenched  cable  route § Why  did  HEC  accept  the  more  expensive   alternative? © Steve TennantConsultancy Ltd2014 30
  • 31. Procurementand Delivery for Mega Tunnel Projects Some  Experiences  and  Thoughts § Route  3  Country  Park  Section § Dual  tube  3  lane  Road  tunnel.  3.8km  long § BOT  Concession © Steve TennantConsultancy Ltd2014 31
  • 32. Procurementand Delivery for Mega Tunnel Projects © Steve TennantConsultancy Ltd2014 32
  • 33. Procurementand Delivery for Mega Tunnel Projects Some  Experiences  and  Thoughts § Route  3  Country  Park  Section § Dual  tube  3  lane  Road  tunnel.  3.8km  long § BOT  Concession § Ability  to  submit  alternative  engineering   proposals  in  additional  to  minimum   conforming  bid § Resulted  in  further  two  rounds  of  proposals   being  invited! © Steve TennantConsultancy Ltd2014 33
  • 34. Procurementand Delivery for Mega Tunnel Projects Questions § As  a  Project  Owner,  do  you  procure   tunnels  by  the  “Traditional  Method”  and   if  so,  why? § As  a  Consultant,  do  you  recommend   procurement  of  tunnels  by  the   “Traditional  Method”  and  if  so,  why? © Steve TennantConsultancy Ltd2014 34
  • 35. Procurementand Delivery for Mega Tunnel Projects Thank  You © Steve TennantConsultancy Ltd2014 35