SlideShare ist ein Scribd-Unternehmen logo
1 von 42
Line balance
To be Help by
Bhuiyan Consultant Farm
Prepared By
Shamim Hasan
Bhuiyan Consultant Farm
What is Line balancing?
A production line is said to be in balance when every
worker's task takes the same amount of time. Line
balancing is a manufacturing-engineering function in
which whole collection of production-line tasks are
divided into equal portions. Well-balanced lines avoid
labor idealness and improve productivity.
This is an analysis process which tries to equally divide
work to be carried out in a production process among
workstations.
In production line workstations and work centers are
arranged in a sequence of task to be done along a
straight or curved line.
Bhuiyan Consultant Farm
What is a line of balance chart
The Line Of Balance (LOB) process is employed when a
repetitive process exists within the contract's work scope.
... Line Of Balance (LOB) is a management control
process for collecting, measuring and presenting facts
relating to time, cost and accomplishment - all measured
against a specific plan.
Bhuiyan Consultant Farm
What is meant by assembly line
balancing ?
to a workstation within an assembly line in
order to meet the required production rate and
to achieve a minimum amount of idle time.
Line balancing is the procedure in which
tasks along Assigning each task the assembly
line are assigned to work station so each has
approximately same amount of work.
Bhuiyan Consultant Farm
What is the cycle time in a
manufacturing operation?
Manufacturing Cycle Time. Share. Manufacturing
cycle time refers to the time required or spent to
convert raw materials into finished goods. It is also
known as throughput time. ... Process time refers
to the time used to actually work on the product.
Bhuiyan Consultant Farm
What is the difference between cycle time and
lead time.
Lead time clock starts when the request is
made and ends at delivery. Cycle time clock
starts when work begins on the request and
ends when the item is ready for delivery. Cycle
time is a more mechanical measure of process
capability. Lead time is what the customer
sees.
Bhuiyan Consultant Farm
What is the cycle time of a
process ?
Cycle time is the total time from the beginning
to the end of your process, as defined by you
and your customer. Cycle time includes
process time, during which a unit is acted upon
to bring it closer to an output, and delay time,
during which a unit of work is spent waiting to
take the next action.
Bhuiyan Consultant Farm
What is the value added time?
 Value added time is made up of processes
that improve products. The only value added
time process in the cycle time example is the
process time. This is the amount of time it
takes to actually produce the product.
Obviously, production time is a value added
time because it creates a product from raw
materials.
Bhuiyan Consultant Farm
What is value added and non
value added?
Any activity that doesn't add to the market form
or function of the product (things for which the
customer is willing to pay) is a non-value
added activity, or the "wastes" that lean seeks
to eliminate.
Bhuiyan Consultant Farm
How do you calculate process
cycle efficiency ?
 Once you have completed steps (1) – (4),
then you can simply calculate how much is
actually value-added, as a percentage. The
time for the entire process — end-to-end — is
called a cycle time. To identify the
Process Cycle Efficiency, you just divide the
value-added time by the cycle time for the
process.
Bhuiyan Consultant Farm
What is the meaning of takt time?
Takt time is the maximum amount of time in
which a product needs to be produced in order
to satisfy customer demand. The term comes
from the German word "takt," which means
"pulse."
Bhuiyan Consultant Farm
How do you calculate takt time?
 The classic calculation for takt time is:
 Available Minutes for Production / Required Units
of Production = Takt Time. ...
 8 hours x 60 minutes = 480 total minutes. ...
 480 – 45 = 435. ...
 435 available minutes / 50 required units of
production = 8.7 minutes (or 522 seconds) ...
 435 minutes x 5 days = 2175 total available
minutes.
Bhuiyan Consultant Farm
The flow rate usually is an average rate. Flow time: The amount
of time a flow unit spends in a business process from beginning to
end, also known as the total processing time. If there is more than
one path through the process, the flow time is equivalent to the
length of the longest path.
What is the meaning of flow time.
Bhuiyan Consultant Farm
What is time distance?
Speed is a measure of how quickly an object
moves from one place to another. It is equal to
the distance traveled divided by the time. ... To
find the speed, distance is over time in the
triangle, so speed is distance divided by time.
To find distance, speed is beside time,
so distance is speed multiplied by time.
Bhuiyan Consultant Farm
Tools and Equipment's to Be
used For Doing This Work :
•Calculator •Stopwatch •Scale •Pen •Paper
•Pencil •Graph paper •Time study sheet •Cutting
scissor •Inspection table •Input table
•Productivity improvement sheet.
Bhuiyan Consultant Farm
Important Terms
Tasks
Task Precedence
Task Times
Cycle Time
Productive Time Per Hour
Number of work stations working
Minimum number of workstations = sum of all tasks *
demand per hr / productive time per hour
Actual number of workstations
Utilization = min no of workstations / actual no of
stations Bhuiyan Consultant Farm
Cycle Check example
Date:
Unit: Line:
M/P 210 SMV
1 2 3 4 5 6 7 8
1 30102 Body Tack S/N 7 8 7 7 7 8 7 7 7 514 90 15% 6.45 558
2 30021 CF Rolling S/N 32 34 34 36 35 42 36 35 34 106 100 15% 34.15 105
3 30078 CF Rolling S/N 52 52 50 51 52 51 53 50 50 72 120 15% 60.15 60
4 30066 Top CenterKansai K/S 20 18 21 22 21 20 22 21 20 180 115 12% 23.12 156
13293 Q.C Top Center/CF Rolling Q.C 27 28 28 32 27 27 33 29 27 133 100 27 133
5 13727 CF Placket Hole B/H 33 37 36 36 34 37 35 34 34 106 100 15% 34.15 105
Pocket Check Mach &Mark HP 33 28 30 32 33 29 31 28 28 129 90 15% 25.35 142
Pocket Cut HP 32 26 30 28 28 32 26 31 28 129 90 15% 25.35 142
Pocket Mach &Mark HP 29 30 30 32 34 34 32 30 30 120 85 15% 25.65 140
6 30078 Pocket Rolling S/N 47 48 47 47 49 48 48 48 47 77 80 18% 37.78 95
Pocket Iron IM 48 43 45 45 47 46 48 45 45 80 85 15% 38.4 93.75
Pocket Iron IM 50 52 50 51 50 53 51 50 50 72 85 15% 42.65 84.40797
7 30085 Pocket Attach DNLS 86 91 95 88 91 89 87 87 87 41 85 15% 74.1 48.583
Rating
Allowan
ce
SAM
Allowance
added
Capacity
Cycle Check Format
SL. ID No.
Lowest
Repeatable
time
Capacity
Garments Ltd.
Cycle Time
75,Askarabad.D.T. Road , Chittagong.
Process Machine
100%TARGET 2161
Capacity / Hr. 1621
5.83
BUYER: X Mart
ITEM: Shirt
STYLE:
Bhuiyan Consultant Farm
Unit: 5th Line: 7
M/P SMV
Date:
Sl. PROCESS M/C Avg.sec Avg Min
Mint+Al
lnc
Capacity
Min
Uti.
Min
Vari:
V/MP Freq
1 Body Tack SNLS 7 0.12 0.13 468 0 60 0.0 1
2 CF Rolling SNLS 34 0.57 0.62 96 0 60 0.0 1
2 CF Rolling SNLS 50 0.83 0.92 65 0 60 0.0 1
3 Top Center Kansai KS 20 0.33 0.37 164 0 60 0.0 1
4 Q.C Top Center/CF Rolling QC 27 0.45 0.50 121 0 60 0.0 1
5 CF Placket Hole BH 34 0.57 0.62 96 0 60 0.0 1
6 Pocket Check Mach & Mark HP 28 0.47 0.51 117 0 60 0.0 1
7 Pocket Cut HP 28 0.47 0.51 117 0 60 0.0 1
8 Pocket Mach & Mark HP 30 0.50 0.55 109 0 60 0.0 1
9 Pocket Rolling SNLS
47 0.78 0.86 70 0 60 0.0 1
10 Pocket Iron IM 45 0.75 0.83 73 0 60 0.0 1
10 Pocket Iron IM 50 0.83 0.92 65 0 60 0.0 1
11 Pocket Attach 2NLS 87 1.45 1.60 38 0 60 0.0 1
11 Pocket Attach 2NLS 96 1.60 1.76 34 0 60 0.0 1
11 Pocket Attach 2NLS 90 1.50 1.65 36 0 60 0.0 1
12 Flap Iron HP 67 1.12 1.23 49 0 60 0.0 1
CAPACITY CHECK REPORT
SewingSection
BUYER:
ITEM: Fannel Shirt 100%TARGET 0
Capacity / Hr.STYLE:FM47Y2029 0
29.5
Run Days:
Bhuiyan Consultant Farm
Line Balancing Graph
468
162
164
121
96
117
117
109
70
138
108
98
133
172
136
136
298
298
80
149
182
162
298
218
82
127
74
172
164
86
182
175
327
142
142
182
156
106
158
30
96
119
154
273
137
31
172
113
136
126
332221
0
100
200
300
400
Productivity
Process & Machine
Line Balancing Graph
Bhuiyan Consultant Farm
Imbalance Ratio Calculation
Style : Flannel Unit-2/Line-6
Fact: Mo Asian Date:
60 1.2
Seq Operation
Process
CycleTime
(7/5/2017)
Cycle time
(Min) with
Allowance
Numbe
r of
Operato
rs
allocate
d
Dedicated cycle
time for the
Line(Min)
Capacity
per hour
Possible
Out put
Time
Minutes
Lost per
hour
MC Csec Allow Total
1 Front Top Placket make 15 0.300 0.6 0.500 120 115 1 KS 25 5 30
2 Thread Cut 13 0.260 1 0.260 231 115 30 HP 22 4 26
3 Front lower plaket make+ front part joint 23 0.460 1 0.460 130 115 7 SN 38 8 46
4 Pocket position mark & neck shape cut 26 0.520 1 0.520 115 115 0 OL 43 9 52
5 Pocket marking 26 0.520 1 0.520 115 115 0 HP 43 9 52
6 Front pocket Hem 25 0.500 1 0.500 120 115 2 SN 42 8 50
7 Front pkt rowedge trim 13 0.260 1 0.260 231 115 30 OL 22 4 26
8 Pocket Iron 39 0.780 1.5 0.520 115 115 0 IRON 65 13 78
9 Front pkt flap iron 39 0.780 1.5 0.520 115 115 0 IRON 65 13 78
10 Front pkt attach 52 1.040 2 0.520 115 115 0 DNSB 87 17 104
11 Flap Topstitch 52 1.040 2 0.520 115 115 0 DNSB 87 17 104
12 Flap Button & Cuff Hole 23 0.460 1 0.460 130 115 7 BH 38 8 46
13 Pocket Flap Attach 25 0.500 1 0.500 120 115 2 DNLS 42 8 50
14 Thread Cut 24 0.480 1 0.480 125 115 5 HP 40 8 48
15 Brtk at front pkt with flap(2x4) 21 0.420 1 0.420 143 115 12 BRTK 35 7 42
16 Back yoke inner part lable att 8 0.160 0.5 0.320 188 115 12 LBL ATT 13 3 16
17 Back Yoke 1 part attach and pleat Make 22 0.440 1 0.440 136 115 9 SN 37 7 44
18 Back part & bk yoke att with topstitch 24 0.480 1 0.480 125 115 5 DNCS 40 8 48
19 Care labelattach 14 0.280 1 0.280 214 115 28 SN 23 5 28
20 Slv top placket shape make 18 0.360 1 0.360 167 115 18 PUSH 30 6 36
Sewing Analysis
7-May-17
Imbalance Calculation
Bhuiyan Consultant Farm
Line Balance Graph
120
231
130
214
144
115
115
118 115 115
0
50
100
150
200
250
Bhuiyan Consultant Farm
Layout comparison for balancing
Criteria Before
balance
After
balance
Machines 39 37
Work Station 43 45
Manpower 60 58
WIP 3400 300 Pcs
Defect 7.5% 3.5%
Lead Time 14Hrs 1 Hr. 42 Mins
First hour
output
80 pcs 140Pcs
Extra OT /
Work
Some person No man
power
Employee
Moral
Low High
Bhuiyan Consultant Farm
Initial Benefit’s
20% Production Up
25% Productivity Up
55% Defect Down
91% WIP Down
90% Lead time Down for
color change
100% Extra OT down
75% First Hr production
increase
Highest Ever
1st Hours
Production
Fastest
Ever
Color
Change
Immediate
Defect
CorrectionBhuiyan Consultant Farm
Why need line balancing ?
Good line balancing increase the rate of
production. Line balancing helps to compare
the required machinery with the existing one
and compare balance. It also helps in the
determination of labor requirement.
Good balancing reduces production time
Bhuiyan Consultant Farm
In garments industry, line balancing is the process
of- -Selecting an effective sewing line -With
competent machines regarding to worker -To
produce a specific order -A certain time deadline
we used line balancing technique to achieve: 1. The
minimization of the number of workstations 2. The
minimization of cycle time 3.The maximization of
workload smoothness 4. The maximization of work
relatedness.
Bhuiyan Consultant Farm
Goal & Objective
Goal of production line analysis:
Number of workstations needed.
Type of task should be assigned to each workstation.
To know the minimum number of workers, tools and machines that
can be used to provide the required amount of capacity.
Objective of line balancing:
- Assigning task to each workstation in such a way that there is only a
little idle time.
-To maximize the production.
-To improve per day production.
-To minimize the production cost.
-To find out the wasting time during a product making and to minimize
the wasting time.
-Find out the problem restricting the production, generating proper
solutions and implement them in a proper way.
-To analyze what affects productivity in respect to a garments factory.
-To develop the best method or work and motion ergonomics
-To balance the line for best utilization of men, machine and material.
Bhuiyan Consultant Farm
TERMINOLOGIES RELATED TO
PRODUCTION LINE ANALYSIS
TASKS: All the elements of work.
TASK PRECEDENCE: The sequence in which
tasks are performed.
TASK TIMES: Time required by a well-trained
worker or unattended machine to perform a task.
This is usually expressed in minutes.
CYCLE TIME: The time expressed in minutes
between two simultaneous products coming off the
end of a production line.
Bhuiyan Consultant Farm
PRODUCTIVE TIME PER HOUR: The average number
of minutes a workstation is working in an hour.
WORKSTATION: A physical area where a worker with
tools/ one or more machines, or an unattended machines
like a robot performs a particular set of task in a
production line.
WORK CENTER: A small group of identical
workstations, where each workstation performs the same
set of task.
NUMBER OF WORKSTATIONS WORKING: The
amount of work done at a work center expressed in
number of workstations.
Bhuiyan Consultant Farm
MINIMUM NUMBER OF WORKSTATIONS: The
least number of workstation that provides the
required production.
ACTUAL NUMBER OF WORKSTATIONS: This is
the total number of workstations required on the
entire production line. It is calculated as the next
higher integer of the number of workstations
working.
UTILIZATION: The percentage of time a
production line is working.
Bhuiyan Consultant Farm
LINE BALANCING PROCEDURE
1. Determination of tasks that must be performed to
complete one unit of a product. 2. Determining the
order or sequence of performing the whole set of
tasks. 3. Drawing precedence diagram. In this
flowchart circles represents task and joining arrows
represents precedence. 4. Estimation of task time.
5. Calculation of cycle time. 6. Determination of
minimum number of workstation required. 7. Using
one of the heuristics to assign tasks to workstations
for balancing production line.
Bhuiyan Consultant Farm
Line Balancing Heuristics
Two types
Incremental Utilization Heuristic
Longest Task Time Heuristic
Bhuiyan Consultant Farm
Incremental Heuristic
Tasks are added to each workstation in order
of task precedence one at a time until utilization
is 100 percent or is observed to fall.
Used when one or more task time is equal to
or greater than the cycle time.
Bhuiyan Consultant Farm
Bhuiyan Consultant Farm
Bhuiyan Consultant Farm
Longest-Task-Time Heuristic
Add tasks to a workstation one at a time in the
order of task precedence.
If a choice must be made between two or more
tasks, the one with the longest task time is added.
This has the effect of assigning as quickly as
possible the tasks that are the most difficult to fit into
a station.
Tasks with shorter times are then saved for fine-
tuning the solution.
Bhuiyan Consultant Farm
Conditions
1. It can be used only when each and every task
time is less than or equal to the cycle time.
2. There can be no duplicate work station
If each and every task time is less than or equal to
the cycle time, and if the primary focus of the analysis
of production lines is minimizing the number of
workstations and the amount of tools and equipment
required, then this heuristic would be appropriate.
Bhuiyan Consultant Farm
SOLUTION
Bhuiyan Consultant Farm
Bhuiyan Consultant Farm
LINE BALANCING ISSUES
Earlier conveyor belts are paced with the speed of
the employees work.
Now they are paced with the machine speed.
APPLICATIONS
The classic example is Henry Ford’s auto chassis
line.
• Before the “assembly line Balancing” was
introduced in 1913, each chassis was assembled by
one worker and required 12.5 hours.
• Once the new technology was installed, this time
was reduced to 93 minutes.
Bhuiyan Consultant Farm
Benefit of Proper Line balancing
1. Factory looking nice & House Keeping proper
2. Buyer & Auditor Satisfy
3. Through put time shortly
4. On time delivery for Shipment schedule achieve
5. Easily target met & Inspection date achieve
6. Quality improve & DHU reduce.
7. Easily SOP maintained with Customer/ Buyer Guideline
maintained.
8. Production Management & Op+ HP+ All are satisfy.
9. Rejection possibility low & All person busy for his
business/ job, so time waist control easy way.
10. Factory are always high productivity & more business
gain from customer
Bhuiyan Consultant Farm
Thank You
Prepared By
NM Shamim Hasan
Bhuiyan Consultant Farm

Weitere ähnliche Inhalte

Was ist angesagt?

Assembly Line Balancing
Assembly Line BalancingAssembly Line Balancing
Assembly Line BalancingAlan Wei Teck
 
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)Inter Alliance Werardt
 
Assembly Line Balancing | Case Study
Assembly Line Balancing | Case StudyAssembly Line Balancing | Case Study
Assembly Line Balancing | Case StudyMd Abu Bakar Siddique
 
Improving Productivity by Lean
Improving Productivity by LeanImproving Productivity by Lean
Improving Productivity by LeanANITHA BALA
 
Method study(abhishekkumar)
Method study(abhishekkumar)Method study(abhishekkumar)
Method study(abhishekkumar)Abhishek Kumar
 
History of Lean manufacturing & TPS 14 Principal
History of Lean manufacturing & TPS 14 PrincipalHistory of Lean manufacturing & TPS 14 Principal
History of Lean manufacturing & TPS 14 PrincipalSumon Kumar Kundu
 
Lead time takt time cycle time and throughput
Lead time takt time cycle time and throughputLead time takt time cycle time and throughput
Lead time takt time cycle time and throughputHpm India
 
SMED - Single Minute Exchange of Dies
SMED - Single Minute Exchange of DiesSMED - Single Minute Exchange of Dies
SMED - Single Minute Exchange of Dies5S BALAMURUGAN
 
Kaizen – Forms & Checklists
Kaizen – Forms & ChecklistsKaizen – Forms & Checklists
Kaizen – Forms & ChecklistsAnand Subramaniam
 
Lean Quick Changeover (SMED) Training Module
Lean Quick Changeover (SMED) Training ModuleLean Quick Changeover (SMED) Training Module
Lean Quick Changeover (SMED) Training ModuleFrank-G. Adler
 
Lean Manufacturing : Concept & Overview nkchawla@gmail.com
Lean Manufacturing : Concept & Overview nkchawla@gmail.comLean Manufacturing : Concept & Overview nkchawla@gmail.com
Lean Manufacturing : Concept & Overview nkchawla@gmail.comNareshChawla
 

Was ist angesagt? (20)

assembly line balancing
assembly line balancingassembly line balancing
assembly line balancing
 
SMED
SMEDSMED
SMED
 
Assembly Line Balancing
Assembly Line BalancingAssembly Line Balancing
Assembly Line Balancing
 
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
 
OEE
OEEOEE
OEE
 
Assembly Line Balancing | Case Study
Assembly Line Balancing | Case StudyAssembly Line Balancing | Case Study
Assembly Line Balancing | Case Study
 
Improving Productivity by Lean
Improving Productivity by LeanImproving Productivity by Lean
Improving Productivity by Lean
 
Method study(abhishekkumar)
Method study(abhishekkumar)Method study(abhishekkumar)
Method study(abhishekkumar)
 
Method study
Method studyMethod study
Method study
 
13 smed methodology_v2
13 smed methodology_v213 smed methodology_v2
13 smed methodology_v2
 
History of Lean manufacturing & TPS 14 Principal
History of Lean manufacturing & TPS 14 PrincipalHistory of Lean manufacturing & TPS 14 Principal
History of Lean manufacturing & TPS 14 Principal
 
Lean Manufacturing Training
Lean Manufacturing TrainingLean Manufacturing Training
Lean Manufacturing Training
 
Lead time takt time cycle time and throughput
Lead time takt time cycle time and throughputLead time takt time cycle time and throughput
Lead time takt time cycle time and throughput
 
Standardized Work
Standardized WorkStandardized Work
Standardized Work
 
SMED - Single Minute Exchange of Dies
SMED - Single Minute Exchange of DiesSMED - Single Minute Exchange of Dies
SMED - Single Minute Exchange of Dies
 
Kaizen – Forms & Checklists
Kaizen – Forms & ChecklistsKaizen – Forms & Checklists
Kaizen – Forms & Checklists
 
Lean Quick Changeover (SMED) Training Module
Lean Quick Changeover (SMED) Training ModuleLean Quick Changeover (SMED) Training Module
Lean Quick Changeover (SMED) Training Module
 
Quick Smed Sample
Quick Smed SampleQuick Smed Sample
Quick Smed Sample
 
Lean Manufacturing : Concept & Overview nkchawla@gmail.com
Lean Manufacturing : Concept & Overview nkchawla@gmail.comLean Manufacturing : Concept & Overview nkchawla@gmail.com
Lean Manufacturing : Concept & Overview nkchawla@gmail.com
 
Single Minute Exchange of Dies
Single Minute Exchange of DiesSingle Minute Exchange of Dies
Single Minute Exchange of Dies
 

Ähnlich wie Line balance

2.IE Presentation.pptx
2.IE Presentation.pptx2.IE Presentation.pptx
2.IE Presentation.pptxVarun Mehrotra
 
Increasing the productivity and efficiency of a sewing line in an apparel man...
Increasing the productivity and efficiency of a sewing line in an apparel man...Increasing the productivity and efficiency of a sewing line in an apparel man...
Increasing the productivity and efficiency of a sewing line in an apparel man...Mazedul Islam Soyeb
 
Industrial Engineering in Apparel Industry
Industrial Engineering in Apparel IndustryIndustrial Engineering in Apparel Industry
Industrial Engineering in Apparel IndustryPradeep Poornishankar
 
project-presentation
project-presentationproject-presentation
project-presentationronybste
 
standardised-work-overview-and-documents
standardised-work-overview-and-documentsstandardised-work-overview-and-documents
standardised-work-overview-and-documentsAngelo Del Grosso
 
CIM report - final
CIM report - finalCIM report - final
CIM report - finalPraveen S R
 
Micro Project - Design of Can Manufacturing Facility
Micro Project - Design of Can Manufacturing FacilityMicro Project - Design of Can Manufacturing Facility
Micro Project - Design of Can Manufacturing FacilityAmr El-Ganainy
 
Toyota Kata How to Use the Key Improvement Kata Forms
Toyota Kata How to Use the Key Improvement Kata FormsToyota Kata How to Use the Key Improvement Kata Forms
Toyota Kata How to Use the Key Improvement Kata FormsRichardCGreen
 
Industrial engineeering pli
Industrial engineeering   pliIndustrial engineeering   pli
Industrial engineeering pliDhyey Shukla
 
Ie microsoft office power point presentation
Ie  microsoft office power point presentationIe  microsoft office power point presentation
Ie microsoft office power point presentationShamim Hasan
 
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machine
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machineDevelopment of fixture_to_reduce_the_cycle_time_of_c_8_griding_machine
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machineLaukik Raut
 
Batch & Queue vs Lean Continuous Flow
Batch & Queue vs Lean Continuous FlowBatch & Queue vs Lean Continuous Flow
Batch & Queue vs Lean Continuous FlowJulian Kalac P.Eng
 
Analyzing and Monitoring Processes through Time Value Mapping
Analyzing and Monitoring Processes through Time Value MappingAnalyzing and Monitoring Processes through Time Value Mapping
Analyzing and Monitoring Processes through Time Value MappingCIToolkit
 

Ähnlich wie Line balance (20)

zone 3 ppt.pptx
zone 3 ppt.pptxzone 3 ppt.pptx
zone 3 ppt.pptx
 
2.IE Presentation.pptx
2.IE Presentation.pptx2.IE Presentation.pptx
2.IE Presentation.pptx
 
Increasing the productivity and efficiency of a sewing line in an apparel man...
Increasing the productivity and efficiency of a sewing line in an apparel man...Increasing the productivity and efficiency of a sewing line in an apparel man...
Increasing the productivity and efficiency of a sewing line in an apparel man...
 
A line in apparel
A line in apparelA line in apparel
A line in apparel
 
Line Balancing In Garments Industry
Line Balancing In Garments IndustryLine Balancing In Garments Industry
Line Balancing In Garments Industry
 
Industrial Engineering in Apparel Industry
Industrial Engineering in Apparel IndustryIndustrial Engineering in Apparel Industry
Industrial Engineering in Apparel Industry
 
project-presentation
project-presentationproject-presentation
project-presentation
 
standardised-work-overview-and-documents
standardised-work-overview-and-documentsstandardised-work-overview-and-documents
standardised-work-overview-and-documents
 
om
omom
om
 
CIM report - final
CIM report - finalCIM report - final
CIM report - final
 
CIM report - final
CIM report - finalCIM report - final
CIM report - final
 
CIM Report
CIM ReportCIM Report
CIM Report
 
Micro Project - Design of Can Manufacturing Facility
Micro Project - Design of Can Manufacturing FacilityMicro Project - Design of Can Manufacturing Facility
Micro Project - Design of Can Manufacturing Facility
 
Toyota Kata How to Use the Key Improvement Kata Forms
Toyota Kata How to Use the Key Improvement Kata FormsToyota Kata How to Use the Key Improvement Kata Forms
Toyota Kata How to Use the Key Improvement Kata Forms
 
Industrial engineeering pli
Industrial engineeering   pliIndustrial engineeering   pli
Industrial engineeering pli
 
Term Project
Term ProjectTerm Project
Term Project
 
Ie microsoft office power point presentation
Ie  microsoft office power point presentationIe  microsoft office power point presentation
Ie microsoft office power point presentation
 
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machine
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machineDevelopment of fixture_to_reduce_the_cycle_time_of_c_8_griding_machine
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machine
 
Batch & Queue vs Lean Continuous Flow
Batch & Queue vs Lean Continuous FlowBatch & Queue vs Lean Continuous Flow
Batch & Queue vs Lean Continuous Flow
 
Analyzing and Monitoring Processes through Time Value Mapping
Analyzing and Monitoring Processes through Time Value MappingAnalyzing and Monitoring Processes through Time Value Mapping
Analyzing and Monitoring Processes through Time Value Mapping
 

Kürzlich hochgeladen

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Kürzlich hochgeladen (20)

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

Line balance

  • 1. Line balance To be Help by Bhuiyan Consultant Farm Prepared By Shamim Hasan
  • 3. What is Line balancing? A production line is said to be in balance when every worker's task takes the same amount of time. Line balancing is a manufacturing-engineering function in which whole collection of production-line tasks are divided into equal portions. Well-balanced lines avoid labor idealness and improve productivity. This is an analysis process which tries to equally divide work to be carried out in a production process among workstations. In production line workstations and work centers are arranged in a sequence of task to be done along a straight or curved line. Bhuiyan Consultant Farm
  • 4. What is a line of balance chart The Line Of Balance (LOB) process is employed when a repetitive process exists within the contract's work scope. ... Line Of Balance (LOB) is a management control process for collecting, measuring and presenting facts relating to time, cost and accomplishment - all measured against a specific plan. Bhuiyan Consultant Farm
  • 5. What is meant by assembly line balancing ? to a workstation within an assembly line in order to meet the required production rate and to achieve a minimum amount of idle time. Line balancing is the procedure in which tasks along Assigning each task the assembly line are assigned to work station so each has approximately same amount of work. Bhuiyan Consultant Farm
  • 6. What is the cycle time in a manufacturing operation? Manufacturing Cycle Time. Share. Manufacturing cycle time refers to the time required or spent to convert raw materials into finished goods. It is also known as throughput time. ... Process time refers to the time used to actually work on the product. Bhuiyan Consultant Farm
  • 7. What is the difference between cycle time and lead time. Lead time clock starts when the request is made and ends at delivery. Cycle time clock starts when work begins on the request and ends when the item is ready for delivery. Cycle time is a more mechanical measure of process capability. Lead time is what the customer sees. Bhuiyan Consultant Farm
  • 8. What is the cycle time of a process ? Cycle time is the total time from the beginning to the end of your process, as defined by you and your customer. Cycle time includes process time, during which a unit is acted upon to bring it closer to an output, and delay time, during which a unit of work is spent waiting to take the next action. Bhuiyan Consultant Farm
  • 9. What is the value added time?  Value added time is made up of processes that improve products. The only value added time process in the cycle time example is the process time. This is the amount of time it takes to actually produce the product. Obviously, production time is a value added time because it creates a product from raw materials. Bhuiyan Consultant Farm
  • 10. What is value added and non value added? Any activity that doesn't add to the market form or function of the product (things for which the customer is willing to pay) is a non-value added activity, or the "wastes" that lean seeks to eliminate. Bhuiyan Consultant Farm
  • 11. How do you calculate process cycle efficiency ?  Once you have completed steps (1) – (4), then you can simply calculate how much is actually value-added, as a percentage. The time for the entire process — end-to-end — is called a cycle time. To identify the Process Cycle Efficiency, you just divide the value-added time by the cycle time for the process. Bhuiyan Consultant Farm
  • 12. What is the meaning of takt time? Takt time is the maximum amount of time in which a product needs to be produced in order to satisfy customer demand. The term comes from the German word "takt," which means "pulse." Bhuiyan Consultant Farm
  • 13. How do you calculate takt time?  The classic calculation for takt time is:  Available Minutes for Production / Required Units of Production = Takt Time. ...  8 hours x 60 minutes = 480 total minutes. ...  480 – 45 = 435. ...  435 available minutes / 50 required units of production = 8.7 minutes (or 522 seconds) ...  435 minutes x 5 days = 2175 total available minutes. Bhuiyan Consultant Farm
  • 14. The flow rate usually is an average rate. Flow time: The amount of time a flow unit spends in a business process from beginning to end, also known as the total processing time. If there is more than one path through the process, the flow time is equivalent to the length of the longest path. What is the meaning of flow time. Bhuiyan Consultant Farm
  • 15. What is time distance? Speed is a measure of how quickly an object moves from one place to another. It is equal to the distance traveled divided by the time. ... To find the speed, distance is over time in the triangle, so speed is distance divided by time. To find distance, speed is beside time, so distance is speed multiplied by time. Bhuiyan Consultant Farm
  • 16. Tools and Equipment's to Be used For Doing This Work : •Calculator •Stopwatch •Scale •Pen •Paper •Pencil •Graph paper •Time study sheet •Cutting scissor •Inspection table •Input table •Productivity improvement sheet. Bhuiyan Consultant Farm
  • 17. Important Terms Tasks Task Precedence Task Times Cycle Time Productive Time Per Hour Number of work stations working Minimum number of workstations = sum of all tasks * demand per hr / productive time per hour Actual number of workstations Utilization = min no of workstations / actual no of stations Bhuiyan Consultant Farm
  • 18. Cycle Check example Date: Unit: Line: M/P 210 SMV 1 2 3 4 5 6 7 8 1 30102 Body Tack S/N 7 8 7 7 7 8 7 7 7 514 90 15% 6.45 558 2 30021 CF Rolling S/N 32 34 34 36 35 42 36 35 34 106 100 15% 34.15 105 3 30078 CF Rolling S/N 52 52 50 51 52 51 53 50 50 72 120 15% 60.15 60 4 30066 Top CenterKansai K/S 20 18 21 22 21 20 22 21 20 180 115 12% 23.12 156 13293 Q.C Top Center/CF Rolling Q.C 27 28 28 32 27 27 33 29 27 133 100 27 133 5 13727 CF Placket Hole B/H 33 37 36 36 34 37 35 34 34 106 100 15% 34.15 105 Pocket Check Mach &Mark HP 33 28 30 32 33 29 31 28 28 129 90 15% 25.35 142 Pocket Cut HP 32 26 30 28 28 32 26 31 28 129 90 15% 25.35 142 Pocket Mach &Mark HP 29 30 30 32 34 34 32 30 30 120 85 15% 25.65 140 6 30078 Pocket Rolling S/N 47 48 47 47 49 48 48 48 47 77 80 18% 37.78 95 Pocket Iron IM 48 43 45 45 47 46 48 45 45 80 85 15% 38.4 93.75 Pocket Iron IM 50 52 50 51 50 53 51 50 50 72 85 15% 42.65 84.40797 7 30085 Pocket Attach DNLS 86 91 95 88 91 89 87 87 87 41 85 15% 74.1 48.583 Rating Allowan ce SAM Allowance added Capacity Cycle Check Format SL. ID No. Lowest Repeatable time Capacity Garments Ltd. Cycle Time 75,Askarabad.D.T. Road , Chittagong. Process Machine 100%TARGET 2161 Capacity / Hr. 1621 5.83 BUYER: X Mart ITEM: Shirt STYLE: Bhuiyan Consultant Farm
  • 19. Unit: 5th Line: 7 M/P SMV Date: Sl. PROCESS M/C Avg.sec Avg Min Mint+Al lnc Capacity Min Uti. Min Vari: V/MP Freq 1 Body Tack SNLS 7 0.12 0.13 468 0 60 0.0 1 2 CF Rolling SNLS 34 0.57 0.62 96 0 60 0.0 1 2 CF Rolling SNLS 50 0.83 0.92 65 0 60 0.0 1 3 Top Center Kansai KS 20 0.33 0.37 164 0 60 0.0 1 4 Q.C Top Center/CF Rolling QC 27 0.45 0.50 121 0 60 0.0 1 5 CF Placket Hole BH 34 0.57 0.62 96 0 60 0.0 1 6 Pocket Check Mach & Mark HP 28 0.47 0.51 117 0 60 0.0 1 7 Pocket Cut HP 28 0.47 0.51 117 0 60 0.0 1 8 Pocket Mach & Mark HP 30 0.50 0.55 109 0 60 0.0 1 9 Pocket Rolling SNLS 47 0.78 0.86 70 0 60 0.0 1 10 Pocket Iron IM 45 0.75 0.83 73 0 60 0.0 1 10 Pocket Iron IM 50 0.83 0.92 65 0 60 0.0 1 11 Pocket Attach 2NLS 87 1.45 1.60 38 0 60 0.0 1 11 Pocket Attach 2NLS 96 1.60 1.76 34 0 60 0.0 1 11 Pocket Attach 2NLS 90 1.50 1.65 36 0 60 0.0 1 12 Flap Iron HP 67 1.12 1.23 49 0 60 0.0 1 CAPACITY CHECK REPORT SewingSection BUYER: ITEM: Fannel Shirt 100%TARGET 0 Capacity / Hr.STYLE:FM47Y2029 0 29.5 Run Days: Bhuiyan Consultant Farm
  • 21. Imbalance Ratio Calculation Style : Flannel Unit-2/Line-6 Fact: Mo Asian Date: 60 1.2 Seq Operation Process CycleTime (7/5/2017) Cycle time (Min) with Allowance Numbe r of Operato rs allocate d Dedicated cycle time for the Line(Min) Capacity per hour Possible Out put Time Minutes Lost per hour MC Csec Allow Total 1 Front Top Placket make 15 0.300 0.6 0.500 120 115 1 KS 25 5 30 2 Thread Cut 13 0.260 1 0.260 231 115 30 HP 22 4 26 3 Front lower plaket make+ front part joint 23 0.460 1 0.460 130 115 7 SN 38 8 46 4 Pocket position mark & neck shape cut 26 0.520 1 0.520 115 115 0 OL 43 9 52 5 Pocket marking 26 0.520 1 0.520 115 115 0 HP 43 9 52 6 Front pocket Hem 25 0.500 1 0.500 120 115 2 SN 42 8 50 7 Front pkt rowedge trim 13 0.260 1 0.260 231 115 30 OL 22 4 26 8 Pocket Iron 39 0.780 1.5 0.520 115 115 0 IRON 65 13 78 9 Front pkt flap iron 39 0.780 1.5 0.520 115 115 0 IRON 65 13 78 10 Front pkt attach 52 1.040 2 0.520 115 115 0 DNSB 87 17 104 11 Flap Topstitch 52 1.040 2 0.520 115 115 0 DNSB 87 17 104 12 Flap Button & Cuff Hole 23 0.460 1 0.460 130 115 7 BH 38 8 46 13 Pocket Flap Attach 25 0.500 1 0.500 120 115 2 DNLS 42 8 50 14 Thread Cut 24 0.480 1 0.480 125 115 5 HP 40 8 48 15 Brtk at front pkt with flap(2x4) 21 0.420 1 0.420 143 115 12 BRTK 35 7 42 16 Back yoke inner part lable att 8 0.160 0.5 0.320 188 115 12 LBL ATT 13 3 16 17 Back Yoke 1 part attach and pleat Make 22 0.440 1 0.440 136 115 9 SN 37 7 44 18 Back part & bk yoke att with topstitch 24 0.480 1 0.480 125 115 5 DNCS 40 8 48 19 Care labelattach 14 0.280 1 0.280 214 115 28 SN 23 5 28 20 Slv top placket shape make 18 0.360 1 0.360 167 115 18 PUSH 30 6 36 Sewing Analysis 7-May-17 Imbalance Calculation Bhuiyan Consultant Farm
  • 22. Line Balance Graph 120 231 130 214 144 115 115 118 115 115 0 50 100 150 200 250 Bhuiyan Consultant Farm
  • 23. Layout comparison for balancing Criteria Before balance After balance Machines 39 37 Work Station 43 45 Manpower 60 58 WIP 3400 300 Pcs Defect 7.5% 3.5% Lead Time 14Hrs 1 Hr. 42 Mins First hour output 80 pcs 140Pcs Extra OT / Work Some person No man power Employee Moral Low High Bhuiyan Consultant Farm
  • 24. Initial Benefit’s 20% Production Up 25% Productivity Up 55% Defect Down 91% WIP Down 90% Lead time Down for color change 100% Extra OT down 75% First Hr production increase Highest Ever 1st Hours Production Fastest Ever Color Change Immediate Defect CorrectionBhuiyan Consultant Farm
  • 25. Why need line balancing ? Good line balancing increase the rate of production. Line balancing helps to compare the required machinery with the existing one and compare balance. It also helps in the determination of labor requirement. Good balancing reduces production time Bhuiyan Consultant Farm
  • 26. In garments industry, line balancing is the process of- -Selecting an effective sewing line -With competent machines regarding to worker -To produce a specific order -A certain time deadline we used line balancing technique to achieve: 1. The minimization of the number of workstations 2. The minimization of cycle time 3.The maximization of workload smoothness 4. The maximization of work relatedness. Bhuiyan Consultant Farm
  • 27. Goal & Objective Goal of production line analysis: Number of workstations needed. Type of task should be assigned to each workstation. To know the minimum number of workers, tools and machines that can be used to provide the required amount of capacity. Objective of line balancing: - Assigning task to each workstation in such a way that there is only a little idle time. -To maximize the production. -To improve per day production. -To minimize the production cost. -To find out the wasting time during a product making and to minimize the wasting time. -Find out the problem restricting the production, generating proper solutions and implement them in a proper way. -To analyze what affects productivity in respect to a garments factory. -To develop the best method or work and motion ergonomics -To balance the line for best utilization of men, machine and material. Bhuiyan Consultant Farm
  • 28. TERMINOLOGIES RELATED TO PRODUCTION LINE ANALYSIS TASKS: All the elements of work. TASK PRECEDENCE: The sequence in which tasks are performed. TASK TIMES: Time required by a well-trained worker or unattended machine to perform a task. This is usually expressed in minutes. CYCLE TIME: The time expressed in minutes between two simultaneous products coming off the end of a production line. Bhuiyan Consultant Farm
  • 29. PRODUCTIVE TIME PER HOUR: The average number of minutes a workstation is working in an hour. WORKSTATION: A physical area where a worker with tools/ one or more machines, or an unattended machines like a robot performs a particular set of task in a production line. WORK CENTER: A small group of identical workstations, where each workstation performs the same set of task. NUMBER OF WORKSTATIONS WORKING: The amount of work done at a work center expressed in number of workstations. Bhuiyan Consultant Farm
  • 30. MINIMUM NUMBER OF WORKSTATIONS: The least number of workstation that provides the required production. ACTUAL NUMBER OF WORKSTATIONS: This is the total number of workstations required on the entire production line. It is calculated as the next higher integer of the number of workstations working. UTILIZATION: The percentage of time a production line is working. Bhuiyan Consultant Farm
  • 31. LINE BALANCING PROCEDURE 1. Determination of tasks that must be performed to complete one unit of a product. 2. Determining the order or sequence of performing the whole set of tasks. 3. Drawing precedence diagram. In this flowchart circles represents task and joining arrows represents precedence. 4. Estimation of task time. 5. Calculation of cycle time. 6. Determination of minimum number of workstation required. 7. Using one of the heuristics to assign tasks to workstations for balancing production line. Bhuiyan Consultant Farm
  • 32. Line Balancing Heuristics Two types Incremental Utilization Heuristic Longest Task Time Heuristic Bhuiyan Consultant Farm
  • 33. Incremental Heuristic Tasks are added to each workstation in order of task precedence one at a time until utilization is 100 percent or is observed to fall. Used when one or more task time is equal to or greater than the cycle time. Bhuiyan Consultant Farm
  • 36. Longest-Task-Time Heuristic Add tasks to a workstation one at a time in the order of task precedence. If a choice must be made between two or more tasks, the one with the longest task time is added. This has the effect of assigning as quickly as possible the tasks that are the most difficult to fit into a station. Tasks with shorter times are then saved for fine- tuning the solution. Bhuiyan Consultant Farm
  • 37. Conditions 1. It can be used only when each and every task time is less than or equal to the cycle time. 2. There can be no duplicate work station If each and every task time is less than or equal to the cycle time, and if the primary focus of the analysis of production lines is minimizing the number of workstations and the amount of tools and equipment required, then this heuristic would be appropriate. Bhuiyan Consultant Farm
  • 40. LINE BALANCING ISSUES Earlier conveyor belts are paced with the speed of the employees work. Now they are paced with the machine speed. APPLICATIONS The classic example is Henry Ford’s auto chassis line. • Before the “assembly line Balancing” was introduced in 1913, each chassis was assembled by one worker and required 12.5 hours. • Once the new technology was installed, this time was reduced to 93 minutes. Bhuiyan Consultant Farm
  • 41. Benefit of Proper Line balancing 1. Factory looking nice & House Keeping proper 2. Buyer & Auditor Satisfy 3. Through put time shortly 4. On time delivery for Shipment schedule achieve 5. Easily target met & Inspection date achieve 6. Quality improve & DHU reduce. 7. Easily SOP maintained with Customer/ Buyer Guideline maintained. 8. Production Management & Op+ HP+ All are satisfy. 9. Rejection possibility low & All person busy for his business/ job, so time waist control easy way. 10. Factory are always high productivity & more business gain from customer Bhuiyan Consultant Farm
  • 42. Thank You Prepared By NM Shamim Hasan Bhuiyan Consultant Farm