GIS-Based Design for Effective
Smart Grid Strategies

Executive summary
An accurate, up-to-date model of a utility’s distribution
network is the backbone of Smart Grid technologies. But
a Schneider Electric survey shows that 74% of utilities
are concerned about the readiness of their network
model to support Smart Grid applications. This paper
presents a quantitative comparison of a Geographic
Information System (GIS)–based graphic work design
system vs. a CAD-based tool, demonstrating how the
GIS-based design approach is better able to keep up
with the continuous changes in a dynamic electrical
distribution network.

998-2095-05-20-12AR0
Summary
Executive Summary . ................................................................................... p	 1
Introduction ................................................................................................. p 	4
It’s all about the network . ............................................................................ p 	6
The state of the GIS . ................................................................................... p 	7
Graphic Work Design process can induce error............................................ p 	9
GIS-based GWD improves network data accuracy and completeness ......... p 	10
Quantitative comparison of design methodologies ....................................... p 	11
Conclusion................................................................................................... p 12
GIS-Based Design for Effective Smart Grid Strategies

Executive summary
The Distribution Management System (DMS) is a key smart grid technology; and
complete, up-to-date network asset information is mandatory in order to develop
and maintain the accurate network model on which the DMS is based. The utility’s
enterprise geographic information system (GIS) database stores and maintains
this network asset data and can manage the workflow for updating this vital
information.
In evaluating its readiness for Smart Grid implementation, the utility needs to
assess the completeness, accuracy and backlog of the data contained in its GIS.
One utility determined that inaccurate data accounted for a 50 percent deviation
between DMS-modeled load flow and observed load flow. This discrepancy made
it clear to the utility that its DMS is unusable to predict voltage reduction gains
and volt/VAR optimization – the very operational functions the utility targeted in its
smart grid strategy.
Many errors in the GIS data can be attributed to a complex or duplicative graphic
work design (GWD) process, from initiation, through design, review, lockdown,
posting and as-built updating. A GIS-based GWD works within the GIS database
and eliminates re-digitization of designs; takes advantage of network connectivity
for QA/QC checks to improve data accuracy and completeness; and significantly
reduces backlog and speeds network updates. This approach not only
streamlines the design process but also yields more accurate asset information
that supports network modeling, maintenance and vital planning and decision
making processes.
A quantitative comparison of the time involved in the typical workflow of a small
design project, completed by means of manual sketching and also with GISbased and CAD-based methodologies, shows the time savings related to the GISbased GWD are accountable and significant. The same productivity advantages
were seen when comparing typical workflows involved in a large design project.
GIS-based design provides faster update of the network model, making it more
appropriate for supporting DMS functionality – the heart of an effective smart grid
strategy.

White paper | 01
GIS-Based Design for Effective Smart Grid Strategies

Introduction
The industry’s experience and knowledge of smart grid capabilities and
benefits are growing rapidly, and utilities’ smart grid plans are becoming more
sophisticated every day. While AMI once was considered the ‘golden child’ of the
smart grid, utilities now see the Distribution Management System (DMS) as one
of the most important components of an effective smart grid strategy. Perhaps
not as readily acknowledged is the vital role an enterprise Geographic Information
System (GIS) plays in driving the accurate network model needed for DMS
implementations.
In this paper, we highlight the value of an enterprise GIS-based graphic work
design (GWD) system in maintaining an accurate distribution network model – the
heart of an effective smart grid strategy. Inefficient GWD processes do not keep
up with the network changes continuously being planned and executed in the
dynamic electric distribution network. The resulting out-of-date or inaccurate
network model can not drive mission-critical smart grid applications such as
OMS, DMS, DSDR and VVR and, consequently, compromises potential smart grid
efficiency enhancements and operational improvements. An efficient, GIS-based
GWD solution is key to building a robust smart grid foundation.

White paper on Energy Efficiency | 02
GIS-Based Design for
effective Smart Grid
Strategies
GIS-Based Design for Effective Smart Grid Strategies

It’s all about the network
DMS a key technology
In a survey conducted by Microsoft in 2010,
approximately 70 percent of the utilities responding
rated DMS as a very important technology in
implementing tomorrow’s smart grid.1 Indeed, the
Department of Energy identified2 five fundamental
technologies that will drive the smart grid; in addition
to communications, response capability and storage,
two DMS-related technologies make this list:
•  dvanced control methods, to monitor essential
A
components, enabling rapid diagnosis and precise
solutions appropriate to any event
• mproved interfaces and decision support, to
I
amplify human decision-making, transforming

Utilize existing asset and network data at the start of your
GIS-based design - perform advanced structural analyses,
sag, tension and clearance investigations ensuring
adherence to regulatory requirements.

grid operators and managers quite literally into
visionaries when it comes to seeing into their
systems

DMS needs accurate data
The DMS is based on a network model that must

DMS functionality is all about the network: accurate

accurately reflect:

up-to-date network data yields an accurate model
driving advanced DMS functions that deliver the

•  etwork asset information
N

network improvements expected. Conversely,
inaccurate or stale data results in a poor network

•  eal time data
R
•  ime series data
T

model yielding unexpected and often ineffective
results.

•  ransactional data
T

GIS key in network data integrity
It is the utility’s enterprise GIS database that not
only stores and maintains network asset data but
also manages the workflow for updating this vital
information. GIS data is the key to maintaining the
accurate and up-to-date network model that is fed to
all smart grid information systems, including SCADA,
DMS, OMS, MDM and others.
1
Microsoft, March 2010. Worldwide Utilities Industry Survey
2
Department of Energy, Office of Electricity Delivery and Energy Reliability, 2008. The Smart Grid: An Introduction.
White paper | 04
GIS-Based Design for Effective Smart Grid Strategies

The state of the GIS
GIS Readiness
A benchmark study conducted by Esri® queried
226 electric utility companies in the U.S. and
worldwide about their confidence in the accuracy and
completeness of the GIS serving their operations. The
results, made available by Esri to the public in a 2010

GIS data backlog – Only one-third of utilities say
they update their GIS data within ten days of field
work completion. One in four respondents reported
there is information older than six months that is not
reflected in their GIS; see Figure 2.

report,3 suggest many utilities might not be ready
to rely on their network model repository to support
smart grid applications –
GIS data completeness – Less than 70 percent
of respondents report having a complete model of
their primary distribution, because not all data related
to distribution assets has been converted to the
enterprise GIS.
GIS data accuracy – Respondents expressed they

Figure 2. Utilities report that work orders can be
outstanding for six months or more before GIS updates
reflect completion of the field work. Source: Esri, 2010.

have detected high rates of data error in their GIS
databases; see Figure 1.

Figure 1. When asked to assess GIS data error rate, only 15
percent of survey respondents reported high confidence
(less than 2 percent error) in the accuracy of their GIS data.
Source: Esri, 2010.

GIS data quality
Often, the problems with GIS data quality have to

•  hase mismatches; see Figure 3
P

do with information that should be part of any utility
GIS. Data errors exist because the data was entered
incorrectly or converted or migrated inaccurately. In
some cases, the data was managed by a system,
such as CAD, with a lack of network integrity rules;
in other cases, the information wasn’t entered at all.
Errors include –
•  ransformer/customer connectivity
T
3

Figure 3. This GIS map shows phase mismatch, with C-phase transformers and
A-phase transformers on the same C-phase line.

Esri, 2010. Is Your GIS Smart Grid Ready? A State-of-the-Industry Report.
White paper | 05
GIS-Based Design for Effective Smart Grid Strategies

-  hase changes between conductors
P
-  evices/conductors where phase is null
D
-  evices and conductors that are incorrectly
D
looped or multi-fed
•  oltage mismatches
V
-  onductor voltage changes without a tap or
C
transformer
-  evices and conductors where voltage is null
D
-  evices that have a different voltage than their
D
connected conductors
•  evices, particularly switches, with null or duplicate
D
IDs
•  tandard geometric problems such as
S
disconnected devices or conductors
Errors such as those identified above often can
be attributed to poor data management workflow
when graphic work design (GWD) is performed in a

+

Not all utilities are confident
Schneider Electric user surveys suggest that
the reliability of their network model might be
keeping many utility managers up at night –
W
•  hat is your network model’s readiness to
support Smart Grid applications?
-  1 percent – Missing data or
6
inaccuracies
-  percent – Many missing data elements/
4

inaccuracies
-  percent – Not ready
9
• What is the status of the data management

workflow to maintain this model to smart
grid requirements?
-  5 percent – Some gaps and
6
inaccuracies
-  percent – Poorly established
4
• What concerns are you focusing on?
-  1 percent – GIS Data Quality
8
Improvement

non-GIS-based system. Continuous data correction
results in backlog and a network model that is never
quite accurate.

Consequences of inaccurate GIS data
At one utility, inaccurate data accounted for a 50 percent deviation between DMS-modeled load flow and
observed load flow. The utility was not able to use DMS to predict voltage reduction gains and volt/VAR
optimization – the very operational functions targeted in its smart grid strategy. Just for the record: in this
instance, the model used inaccurate conductor material and size attribute data and other inaccurate device
information fed to it from the GIS database.
This utility used two different GWD systems with separate workflows, neither of which was GIS-based.

White paper | 06
GIS-Based Design for Effective Smart Grid Strategies

Graphic Work Design process can
induce error
The distribution network is dynamic and always changing
Subdivisions are added, businesses and homes

Projects like these add, remove and switch load

require more power, load shifts occur with seasonal

and change the network continuously. When the

variability, and outages occur. The GWD process

design is completed, the network model must be

by which a utility extends, maintains and upgrades

updated quickly and accurately so systems using that

its infrastructure is involved in nearly any daily work

information can perform as expected.

order:
• New Services
• Capital expansions
• Replacements
• Conversions/upgrades

Design issues vary widely
Designs can be simple or highly complex; and the

different designs can be occurring simultaneously,

workflow – from initiation, through design, review,

both involving a common asset such as a pole or

lockdown, posting and as-built updating – can be

fuse and requiring collaboration. Some designs might

simple or highly complex. Within the same utility,

take years to complete, with partial postings done as

different workflows involving different departments

each phase is complete.

might be applied on different projects. Further,

A poor data management workflow defeats the purpose
Performing inefficient and complex GWD workflows
independently of the network GIS database – while
being challenged by varying design complexity,
project overlap, long transactions and partial
postings – is a recipe for disaster. These conditions
increase the backlog, introduce core data errors and
contribute to an inaccurate and out-of-date network
model. All of this compromises the enhanced
efficiencies and operational improvements that any
smart grid strategy promises.

Figure above. ​Utilize accurate GIS landbase data to
perform advanced design optimization analyses.

White paper | 07
GIS-Based Design for Effective Smart Grid Strategies

GIS-based GWD improves network
data accuracy and completeness
Streamlines the overall GWD workflow
A GWD that works within the GIS database:

•  ignificantly reduces backlog – direct update of
S
the network model within minutes

•  oes away with re-digitization of designs into
D
the GIS – and the opportunity for error

•  ast turnaround of network update – preliminary
F
or even partial posting to publish design effects

•  nforces Network Integrity and QA/QC rules
E

before a design is energized; reduces the backlog

– maintains valid network connectivity and data

between completion of construction and network

integrity on the fly, using QA/QC checks to catch

model update

errors, ensuring data is entered properly from the
start

•  liminates custom CAD-GIS integration –
E
typically necessary to import designs from CAD
systems

Benefits tangible and intangible
Utilities report that GIS-based design returns tangible

Utilities also report the significance of the intangible

productivity benefits and significant operational cost

benefits –

savings –
•  educed labor involved in map preparation and
R
updates: cost savings from $40,000 to $160,000

• mproved customer satisfaction: allows better
I
response to service calls

a year
•  etter decision support: graphical display of work
B
• ncreased productivity due to improved access to
I

data for crew coordination and outage dispatch

information that supports network analysis and
operational studies: cost savings from $38,000 to
$360,000 a year
• mproved engineering and maintenance efficiency
I

•  etter safety practices: support for crew safety and
B
dig-safe activities, sharing data with other utilities
•  tandardized design practices – consistency of
S

in system upgrades, reducing necessary plant

materials; capturing the knowledge of experienced

investment: cost savings from $200,000 to $1.5

workforce

million
Most importantly, the GIS-based GWD process
•  educed overall cable for UG installation: cost
R
savings of 4 percent of total budget

provides a single point of entry and unified workflow
for asset data and network model management. The
central asset and network repository – the single
version of the truth, not five versions of the partial
truth – feeds an accurate, up-to-date network model
to mission-critical smart grid systems. Remember:
smart grid is all about the network.

White paper | 08
GIS-Based Design for Effective Smart Grid Strategies

Quantitative comparison of design
methodologies
GIS-based design vs. CAD
and manual sketching
To quantify some of the tangible benefits listed above,
Schneider Electric examined the productivity of using
a GIS-based design tool, Schneider Electric Designer,
compared to that of using manual sketching and
CAD-based tools. The purpose was to identify areas
where GIS-based design using Designer can improve
productivity and to quantify the overall efficiency gains
that can be achieved through implementing a GISbased design tool.
The comparison included both small and large
design jobs in typical design workflow. Small design
jobs involved new customer connections or minor
upgrades that averaged approximately 5.5 hours for

2. Gather preliminary design information: Before


completion and reflected small budgets of $2,600

the design layout, most projects require an

to $5,000. Large design jobs included network

assessment of the location of existing plant in

reinforcement, mains replacement, road widening or

service, customer requirements and other factors.

large residential or commercial subdivisions. Large

For smaller projects, this aspect of the design can

designs averaged 47.5 hours for completion and had

be a significant percentage of the total effort.

much larger budgets.
3. Layout design: This is the step in which the new

The term “typical design workflow” might seem like

facilities or modifications to the existing network

an oxymoron, because design workflows within a

are specified through the staking/sketching/

utility can vary greatly, as much as those among

engineering process.

different utilities. For some projects, certain steps
might be sequenced differently or even omitted.

4. Tabulate materials: In this step the materials


However, the nine tasks described below are useful

required to build the job are totaled and reported.

for this study.

In some work processes, these materials may be
reserved for use on the project through a materials

1. nitiate work: This step usually starts with a
I

management system.

service request, repair or maintenance requirement
or an internal capital improvement project

5. Prepare cost estimate: Nearly all workflows


and is often generated from a separate work

require the planner/designer/technician to estimate

management system (WMS).

the cost of the project before proceeding to
construct it.

White paper | 09
GIS-Based Design for Effective Smart Grid Strategies

6.  evelop work package and construction
D

8. Update design sketch for as-built changes:


sketch: Often the most time-consuming step,

Many designs are modified to meet field

the development of the work package is the

requirements, with the result that a drawing mark-

communication medium between the designer

up is needed to true up the original sketch to

and the construction crew. It might include permit

reflect the actual as-built conditions.

drawings, crew instructions, a report of the
9. Post as-built changes to enterprise


materials tabulation and other standard notes.

database(s): Most job closeout processes
7.  ubmit for approval, release for construction
S

require that facilities changes be documented in

and build: Depending on the cost of the estimate,

a mapping system (either manual or digital), and

most workflows require some form of approval

sometimes in tabular databases for plant or asset

before committing to construction of a design,

records systems.

either by a supervisor or customer or both. Then
the design is issued to crew and constructed.

Results
For both small and large jobs, an assessment of the

sketching showed a 48 percent reduction in overall

time for each task in the “typical design workflow”

time (about 2.64 hours); Designer vs. CAD showed a

was made for each of the three methods (manual,

40 percent reduction in overall time (about 1.9 hours).

CAD and GIS-Based). The results shown in Table 1

For large design jobs, Designer vs. manual sketching

and Table 2 clearly indicate that a GIS-based design

showed a 38 percent reduction in overall time (about

tool such as Designer is the much more productive

17.95 hours); Designer vs. CAD showed a 13 percent

method. For small design jobs, Designer vs. manual

reduction in overall time (about 4.4 hours).
TABLE 1

Design Productivity for Small Jobs

Workflow Task
1. Initiate Work
2.  ather preliminary design
G
information
3. Layout design
4. Tabulate material
5. Prepare cost estimate
6.  evelop work package
D
and construction sketch
7.  ubmit for approval,
S
release for construction,
and build
8.  pdate design sketch to
U
reflect as-built conditions
9.  ost as-built changes to
P
enterprise database(s)
Total Hours/Savings

Manual
Design
Hours
0.3
1.25

Percent
of Total
Project
5.43%
22.64%

CAD
Design
Hours
0.30
1.06

GIS-Based GIS-Based
GIS-Based
Design
Savings over Savings over
Hours
Manual, %
CAD, %
0.27
10%
10%
0.56
55%
47%

0.67
0.33
0.33
0.67

12.14%
5.98%
5.98%
12.14%

0.77
0.33
0.33
0.34

0.84
0.07
0.10
0.44

-25%
80%
70%
35%

-9%
80%
70%
-30%

0.17

3.08%

0.17

0.14

15%

15%

0.3

5.43%

0.20

0.17

45%

18%

1.5

27.17%

1.28

0.30

80%

76%

5.52

100.00%

4.77

2.88

48%

40%
White paper | 10
GIS-Based Design for Effective Smart Grid Strategies

TABLE 2
Design Productivity for Large Jobs

Workflow Task
1. Initiate Work
2.  ather preliminary design
G
information
3. Layout design
4. Tabulate material
5. Prepare cost estimate
6.  evelop work package
D
and construction sketch
7.  ubmit for approval,
S
release for construction,
and build
8.  pdate design sketch to
U
reflect as-built conditions
9.  ost as-built changes to
P
enterprise database(s)
Total Hours/Savings

Manual
Design
Hours
2
8

Percent
of Total
Project
4.21%
16.84%

GIS-Based
GIS-Based
Savings over Savings
Manual, %
over CAD, %
10%
10%
55%
47%

16
3
2
8

33.68%
6.32%
4.21%
16.84%

9.60
3.00
2.00
4.00

13.60
0.60
0.60
6.00

15%
80%
70%
25%

-42%
80%
70%
-50%

0.5

1.05%

0.43

0.35

30%

18%

4

8.42%

2.68

2.20

45%

18%

4

8.42%

3.40

0.80

80%

76%

47.5

100.00%

33.91

29.55

38%

13%

See the sidebar on this page describing one energy
company’s improved efficiency with GIS-based GWD.

What does this mean to
the smart grid?
The two most critical steps in the GWD workflow
tasks for efficient smart grid operations are Task 2:
Gather Preliminary Design Information and Task 9:
Post As-built Changes to Enterprise Database. In the
smart grid context, these tasks can be renamed Task
2: Start from Existing Network Model and Task 9:
Update the Network Model.
And in both of these key tasks, GIS-based design
with Designer saves considerable time:
• In Task 2, Designer is 47 percent faster than CAD.
• In Task 9, Designer is 76 percent faster than CAD.
In other words, GIS-Based design with Designer is
faster at updating the network model. It all starts and
ends with an accurate up to date network model – a
single version of the truth.

CAD
GIS-Based
Design Design
Hours Hours
2.00
1.80
6.80
3.60

Energy company improves workflow,
efficiency
DONG Energy, headquartered in Denmark,
obtains, produces, distributes, deals and
sells energy and associated products in
northern Europe. It specializes in the design
and documentation of new electrical facilities,
developing more than 6,000 sites annually. Prior
to instituting its GIS-based GWD, DONG project
staff worked with a less-than-efficient design
workflow that required hand-drawn sketches to
be transferred to the GIS database and materials
information to be entered into a separate file.
After project completion, the GIS typically was not
updated for five to six weeks.
Now, with a GWD application that integrates
seamlessly with the GIS, all the features selected
in the design phase are automatically saved in the
GIS immediately. The sketch is visible to everyone
in the organization throughout the process.
A formal work analysis has shown this GWD
workflow has reduced project drawing time by 60
percent a year – saving the company almost two
million DKK, or more than $350,000 USD. DONG
energy expects these savings to be consistent
going forward, as this process better positions the
company to support smart grid initiatives.

White paper | 11
GIS-Based Design for Effective Smart Grid Strategies

Conclusion
Increasingly, utilities are realizing the significance of
DMS in achieving success in their smart grid projects.
To realize the promise of advanced DMS functions,
however, the DMS needs a complete, accurate and
up-to-date network model. An enterprise GIS-based
GWD system is the proven solution for maintaining
network model data accuracy.
Progressive utilities targeting smart grid deployment –
or even looking to save design time and the additional
costs associated with asset and network data errors
– are implementing GIS-based GWD and seeing
significant benefits:

Figure above. Powerful construction sketch
generation tools in a GIS-based GWD application.

R
•  educed design time and backlog with direct and
immediate update to the GIS network model
E
•  fficient workflows, a unified data store and
streamlined business processes that eliminate
redundant tasks and data errors
I
• mproved availability of network information across
the utility, streamlining analysis, planning and
decision making
M
•  aking accurate network information available to
smart grid systems so they can deliver expected
results

White paper | 12
©2012 Schneider Electric. All rights reserved.

Schneider Electric USA, Inc.
4701 Royal Vista Circle
Fort Collins, CO 80528
Phone:  -866-537-1091
1
	
+ (34) 9-17-14-70-02
Fax: 1-970-223-5577
www.schneider-electric.com/us
June 2012

Weitere ähnliche Inhalte

Was ist angesagt?

MxVision WeatherSentry® Web Services for Utilities
MxVision WeatherSentry® Web Services for UtilitiesMxVision WeatherSentry® Web Services for Utilities
MxVision WeatherSentry® Web Services for UtilitiesSchneider Electric
 
The Mine Central Control Room: From Concept to Reality
The Mine Central Control Room: From Concept to Reality The Mine Central Control Room: From Concept to Reality
The Mine Central Control Room: From Concept to Reality Schneider Electric
 
How the Convergence of IT and OT Enables Smart Grid Development
How the Convergence of IT and OT Enables Smart Grid DevelopmentHow the Convergence of IT and OT Enables Smart Grid Development
How the Convergence of IT and OT Enables Smart Grid DevelopmentSchneider Electric
 
Preparing for the Future: How Asset Management Will Evolve in the Age of Smar...
Preparing for the Future: How Asset Management Will Evolve in the Age of Smar...Preparing for the Future: How Asset Management Will Evolve in the Age of Smar...
Preparing for the Future: How Asset Management Will Evolve in the Age of Smar...Schneider Electric
 
The Data Center Evolution and Pre-Fab Data Centers
The Data Center Evolution and Pre-Fab Data CentersThe Data Center Evolution and Pre-Fab Data Centers
The Data Center Evolution and Pre-Fab Data CentersSchneider Electric
 
Schneider Electric Facilities Management Survey
Schneider Electric Facilities Management SurveySchneider Electric Facilities Management Survey
Schneider Electric Facilities Management SurveySchneider Electric
 
Getting Started with Advanced Network Operations
Getting Started with Advanced Network OperationsGetting Started with Advanced Network Operations
Getting Started with Advanced Network OperationsSchneider Electric
 
Leveraging Cloud-based Building Management Systems for Multi-site Facilities
Leveraging Cloud-based Building Management Systems for Multi-site FacilitiesLeveraging Cloud-based Building Management Systems for Multi-site Facilities
Leveraging Cloud-based Building Management Systems for Multi-site FacilitiesSchneider Electric
 
Field Data Gathering Services — A Cloud-Based Approach
Field Data Gathering Services — A Cloud-Based ApproachField Data Gathering Services — A Cloud-Based Approach
Field Data Gathering Services — A Cloud-Based ApproachSchneider Electric
 
Schneider Electric Smart energy Presentation - Smart Gird domains
Schneider Electric Smart energy Presentation - Smart Gird domainsSchneider Electric Smart energy Presentation - Smart Gird domains
Schneider Electric Smart energy Presentation - Smart Gird domainsSchneider Electric India
 
Schneider Electric Smart City Success Stories (Worldwide)
Schneider Electric Smart City  Success Stories (Worldwide)Schneider Electric Smart City  Success Stories (Worldwide)
Schneider Electric Smart City Success Stories (Worldwide)Schneider Electric India
 
[Case Study] Stedin (The Netherlands) - Underground Self-Healing Network
[Case Study] Stedin (The Netherlands) - Underground Self-Healing Network[Case Study] Stedin (The Netherlands) - Underground Self-Healing Network
[Case Study] Stedin (The Netherlands) - Underground Self-Healing NetworkSchneider Electric
 
The Future of Machine Building is NOW!
The Future of Machine Building is NOW!The Future of Machine Building is NOW!
The Future of Machine Building is NOW!Schneider Electric
 
How Process Industry takes advantage of our solutions
How Process Industrytakes advantage of our solutionsHow Process Industrytakes advantage of our solutions
How Process Industry takes advantage of our solutionsSchneider Electric
 
Simplifying Data Center Design/ Build
Simplifying Data Center Design/ BuildSimplifying Data Center Design/ Build
Simplifying Data Center Design/ BuildSchneider Electric
 
Energy efficiency for mid-size buildings
Energy efficiency for mid-size buildingsEnergy efficiency for mid-size buildings
Energy efficiency for mid-size buildingsSchneider Electric
 

Was ist angesagt? (20)

MxVision WeatherSentry® Web Services for Utilities
MxVision WeatherSentry® Web Services for UtilitiesMxVision WeatherSentry® Web Services for Utilities
MxVision WeatherSentry® Web Services for Utilities
 
The Mine Central Control Room: From Concept to Reality
The Mine Central Control Room: From Concept to Reality The Mine Central Control Room: From Concept to Reality
The Mine Central Control Room: From Concept to Reality
 
AspectCTRM For Fuel Marketers
AspectCTRM For Fuel MarketersAspectCTRM For Fuel Marketers
AspectCTRM For Fuel Marketers
 
Scada expert Clear Scada
Scada expert Clear ScadaScada expert Clear Scada
Scada expert Clear Scada
 
How the Convergence of IT and OT Enables Smart Grid Development
How the Convergence of IT and OT Enables Smart Grid DevelopmentHow the Convergence of IT and OT Enables Smart Grid Development
How the Convergence of IT and OT Enables Smart Grid Development
 
Preparing for the Future: How Asset Management Will Evolve in the Age of Smar...
Preparing for the Future: How Asset Management Will Evolve in the Age of Smar...Preparing for the Future: How Asset Management Will Evolve in the Age of Smar...
Preparing for the Future: How Asset Management Will Evolve in the Age of Smar...
 
The Data Center Evolution and Pre-Fab Data Centers
The Data Center Evolution and Pre-Fab Data CentersThe Data Center Evolution and Pre-Fab Data Centers
The Data Center Evolution and Pre-Fab Data Centers
 
Schneider Electric Facilities Management Survey
Schneider Electric Facilities Management SurveySchneider Electric Facilities Management Survey
Schneider Electric Facilities Management Survey
 
Getting Started with Advanced Network Operations
Getting Started with Advanced Network OperationsGetting Started with Advanced Network Operations
Getting Started with Advanced Network Operations
 
Leveraging Cloud-based Building Management Systems for Multi-site Facilities
Leveraging Cloud-based Building Management Systems for Multi-site FacilitiesLeveraging Cloud-based Building Management Systems for Multi-site Facilities
Leveraging Cloud-based Building Management Systems for Multi-site Facilities
 
Field Data Gathering Services — A Cloud-Based Approach
Field Data Gathering Services — A Cloud-Based ApproachField Data Gathering Services — A Cloud-Based Approach
Field Data Gathering Services — A Cloud-Based Approach
 
Schneider Electric Smart energy Presentation - Smart Gird domains
Schneider Electric Smart energy Presentation - Smart Gird domainsSchneider Electric Smart energy Presentation - Smart Gird domains
Schneider Electric Smart energy Presentation - Smart Gird domains
 
Schneider Electric Smart City Success Stories (Worldwide)
Schneider Electric Smart City  Success Stories (Worldwide)Schneider Electric Smart City  Success Stories (Worldwide)
Schneider Electric Smart City Success Stories (Worldwide)
 
[Case Study] Stedin (The Netherlands) - Underground Self-Healing Network
[Case Study] Stedin (The Netherlands) - Underground Self-Healing Network[Case Study] Stedin (The Netherlands) - Underground Self-Healing Network
[Case Study] Stedin (The Netherlands) - Underground Self-Healing Network
 
DTN Guardian3™
DTN Guardian3™DTN Guardian3™
DTN Guardian3™
 
The Future of Machine Building is NOW!
The Future of Machine Building is NOW!The Future of Machine Building is NOW!
The Future of Machine Building is NOW!
 
How Process Industry takes advantage of our solutions
How Process Industrytakes advantage of our solutionsHow Process Industrytakes advantage of our solutions
How Process Industry takes advantage of our solutions
 
Simplifying Data Center Design/ Build
Simplifying Data Center Design/ BuildSimplifying Data Center Design/ Build
Simplifying Data Center Design/ Build
 
Cloud computing
Cloud computing Cloud computing
Cloud computing
 
Energy efficiency for mid-size buildings
Energy efficiency for mid-size buildingsEnergy efficiency for mid-size buildings
Energy efficiency for mid-size buildings
 

Ähnlich wie GIS-Based Design for Effective Smart Grid Strategies

Best Practices for Creating Your Smart Grid Network Model
Best Practices for Creating Your Smart Grid Network ModelBest Practices for Creating Your Smart Grid Network Model
Best Practices for Creating Your Smart Grid Network ModelSchneider Electric
 
Capgemini ses - the gis centric enterprise pov (gr)
Capgemini   ses - the gis centric enterprise pov (gr)Capgemini   ses - the gis centric enterprise pov (gr)
Capgemini ses - the gis centric enterprise pov (gr)Gord Reynolds
 
World Pipelines - Better Together - SCADA and GIS
World Pipelines - Better Together - SCADA and GISWorld Pipelines - Better Together - SCADA and GIS
World Pipelines - Better Together - SCADA and GISsmrobb
 
Joep Luijten.pdf
Joep Luijten.pdfJoep Luijten.pdf
Joep Luijten.pdfGokhul2
 
Capgemini ses - smart grid operational services - where to start - five fou...
Capgemini   ses - smart grid operational services - where to start - five fou...Capgemini   ses - smart grid operational services - where to start - five fou...
Capgemini ses - smart grid operational services - where to start - five fou...Gord Reynolds
 
Infotech smart grid flyer 2010
Infotech smart grid flyer 2010Infotech smart grid flyer 2010
Infotech smart grid flyer 2010Maria H
 
IRJET- Recommendation System based on Graph Database Techniques
IRJET- Recommendation System based on Graph Database TechniquesIRJET- Recommendation System based on Graph Database Techniques
IRJET- Recommendation System based on Graph Database TechniquesIRJET Journal
 
Serving GIS Data To Electrical Distribution Analysis
Serving GIS Data To Electrical Distribution AnalysisServing GIS Data To Electrical Distribution Analysis
Serving GIS Data To Electrical Distribution Analysispdituri
 
Capgemini ses - smart grid operational services - gis pov (gr)
Capgemini   ses - smart grid operational services - gis pov (gr)Capgemini   ses - smart grid operational services - gis pov (gr)
Capgemini ses - smart grid operational services - gis pov (gr)Gord Reynolds
 
Redefining-Smart-Grid-Architectural-Thinking-Using-Stream-Computing
Redefining-Smart-Grid-Architectural-Thinking-Using-Stream-ComputingRedefining-Smart-Grid-Architectural-Thinking-Using-Stream-Computing
Redefining-Smart-Grid-Architectural-Thinking-Using-Stream-ComputingAjoy Kumar
 
Informi GIS hand-out used in connection with presentation at Esri UC 2014
Informi GIS hand-out used in connection with presentation at Esri UC 2014Informi GIS hand-out used in connection with presentation at Esri UC 2014
Informi GIS hand-out used in connection with presentation at Esri UC 2014Jens Dalsgaard
 
IRJET - A Research on Eloquent Salvation and Productive Outsourcing of Massiv...
IRJET - A Research on Eloquent Salvation and Productive Outsourcing of Massiv...IRJET - A Research on Eloquent Salvation and Productive Outsourcing of Massiv...
IRJET - A Research on Eloquent Salvation and Productive Outsourcing of Massiv...IRJET Journal
 
Smart Grid Operational Services Where To Start Five Foundational Elements POV
Smart Grid Operational Services Where To Start Five Foundational Elements POVSmart Grid Operational Services Where To Start Five Foundational Elements POV
Smart Grid Operational Services Where To Start Five Foundational Elements POVGord Reynolds
 
IRJET- Cost Effective Scheme for Delay Tolerant Data Transmission
IRJET- Cost Effective Scheme for Delay Tolerant Data TransmissionIRJET- Cost Effective Scheme for Delay Tolerant Data Transmission
IRJET- Cost Effective Scheme for Delay Tolerant Data TransmissionIRJET Journal
 
Demand Side management of smart grid using IoT
Demand Side management of smart grid using IoTDemand Side management of smart grid using IoT
Demand Side management of smart grid using IoTIRJET Journal
 
Green Computing for Internet of Things
Green Computing for Internet of ThingsGreen Computing for Internet of Things
Green Computing for Internet of ThingsIRJET Journal
 

Ähnlich wie GIS-Based Design for Effective Smart Grid Strategies (20)

Best Practices for Creating Your Smart Grid Network Model
Best Practices for Creating Your Smart Grid Network ModelBest Practices for Creating Your Smart Grid Network Model
Best Practices for Creating Your Smart Grid Network Model
 
Capgemini ses - the gis centric enterprise pov (gr)
Capgemini   ses - the gis centric enterprise pov (gr)Capgemini   ses - the gis centric enterprise pov (gr)
Capgemini ses - the gis centric enterprise pov (gr)
 
GIS For Smart Grid
GIS For Smart GridGIS For Smart Grid
GIS For Smart Grid
 
World Pipelines - Better Together - SCADA and GIS
World Pipelines - Better Together - SCADA and GISWorld Pipelines - Better Together - SCADA and GIS
World Pipelines - Better Together - SCADA and GIS
 
Joep Luijten.pdf
Joep Luijten.pdfJoep Luijten.pdf
Joep Luijten.pdf
 
Capgemini ses - smart grid operational services - where to start - five fou...
Capgemini   ses - smart grid operational services - where to start - five fou...Capgemini   ses - smart grid operational services - where to start - five fou...
Capgemini ses - smart grid operational services - where to start - five fou...
 
Eu research
Eu researchEu research
Eu research
 
Infotech smart grid flyer 2010
Infotech smart grid flyer 2010Infotech smart grid flyer 2010
Infotech smart grid flyer 2010
 
IRJET- Recommendation System based on Graph Database Techniques
IRJET- Recommendation System based on Graph Database TechniquesIRJET- Recommendation System based on Graph Database Techniques
IRJET- Recommendation System based on Graph Database Techniques
 
Serving GIS Data To Electrical Distribution Analysis
Serving GIS Data To Electrical Distribution AnalysisServing GIS Data To Electrical Distribution Analysis
Serving GIS Data To Electrical Distribution Analysis
 
Cv4301566568
Cv4301566568Cv4301566568
Cv4301566568
 
Capgemini ses - smart grid operational services - gis pov (gr)
Capgemini   ses - smart grid operational services - gis pov (gr)Capgemini   ses - smart grid operational services - gis pov (gr)
Capgemini ses - smart grid operational services - gis pov (gr)
 
Redefining-Smart-Grid-Architectural-Thinking-Using-Stream-Computing
Redefining-Smart-Grid-Architectural-Thinking-Using-Stream-ComputingRedefining-Smart-Grid-Architectural-Thinking-Using-Stream-Computing
Redefining-Smart-Grid-Architectural-Thinking-Using-Stream-Computing
 
Informi GIS hand-out used in connection with presentation at Esri UC 2014
Informi GIS hand-out used in connection with presentation at Esri UC 2014Informi GIS hand-out used in connection with presentation at Esri UC 2014
Informi GIS hand-out used in connection with presentation at Esri UC 2014
 
IRJET - A Research on Eloquent Salvation and Productive Outsourcing of Massiv...
IRJET - A Research on Eloquent Salvation and Productive Outsourcing of Massiv...IRJET - A Research on Eloquent Salvation and Productive Outsourcing of Massiv...
IRJET - A Research on Eloquent Salvation and Productive Outsourcing of Massiv...
 
Smart Grid Operational Services Where To Start Five Foundational Elements POV
Smart Grid Operational Services Where To Start Five Foundational Elements POVSmart Grid Operational Services Where To Start Five Foundational Elements POV
Smart Grid Operational Services Where To Start Five Foundational Elements POV
 
IRJET- Cost Effective Scheme for Delay Tolerant Data Transmission
IRJET- Cost Effective Scheme for Delay Tolerant Data TransmissionIRJET- Cost Effective Scheme for Delay Tolerant Data Transmission
IRJET- Cost Effective Scheme for Delay Tolerant Data Transmission
 
GE-GridIQ_Insight
GE-GridIQ_InsightGE-GridIQ_Insight
GE-GridIQ_Insight
 
Demand Side management of smart grid using IoT
Demand Side management of smart grid using IoTDemand Side management of smart grid using IoT
Demand Side management of smart grid using IoT
 
Green Computing for Internet of Things
Green Computing for Internet of ThingsGreen Computing for Internet of Things
Green Computing for Internet of Things
 

Mehr von Schneider Electric

Secure Power Design Considerations
Secure Power Design ConsiderationsSecure Power Design Considerations
Secure Power Design ConsiderationsSchneider Electric
 
Digital International Colo Club: Attracting Investors
Digital International Colo Club: Attracting InvestorsDigital International Colo Club: Attracting Investors
Digital International Colo Club: Attracting InvestorsSchneider Electric
 
32 phaseo power supplies and transformers briefing
32 phaseo power supplies and transformers briefing 32 phaseo power supplies and transformers briefing
32 phaseo power supplies and transformers briefing Schneider Electric
 
Key Industry Trends, M&A Valuation Trends
Key Industry Trends, M&A Valuation TrendsKey Industry Trends, M&A Valuation Trends
Key Industry Trends, M&A Valuation TrendsSchneider Electric
 
EcoStruxure™ for Cloud & Service Providers
 EcoStruxure™ for Cloud & Service Providers EcoStruxure™ for Cloud & Service Providers
EcoStruxure™ for Cloud & Service ProvidersSchneider Electric
 
Zelio Time Electronic Relay Briefing
Zelio Time Electronic Relay BriefingZelio Time Electronic Relay Briefing
Zelio Time Electronic Relay BriefingSchneider Electric
 
Spacial, Thalassa, ClimaSys Universal enclosures Briefing
Spacial, Thalassa, ClimaSys Universal enclosures BriefingSpacial, Thalassa, ClimaSys Universal enclosures Briefing
Spacial, Thalassa, ClimaSys Universal enclosures BriefingSchneider Electric
 
Relay Control Zelio SSR Briefing
Relay Control Zelio SSR BriefingRelay Control Zelio SSR Briefing
Relay Control Zelio SSR BriefingSchneider Electric
 
Magelis HMI, iPC and software Briefing
Magelis HMI, iPC and software BriefingMagelis HMI, iPC and software Briefing
Magelis HMI, iPC and software BriefingSchneider Electric
 
Where will the next 80% improvement in data center performance come from?
Where will the next 80% improvement in data center performance come from?Where will the next 80% improvement in data center performance come from?
Where will the next 80% improvement in data center performance come from?Schneider Electric
 
EcoStruxure for Intuitive Industries
EcoStruxure for Intuitive IndustriesEcoStruxure for Intuitive Industries
EcoStruxure for Intuitive IndustriesSchneider Electric
 
Systems Integrator Alliance Program 2017
Systems Integrator Alliance Program 2017Systems Integrator Alliance Program 2017
Systems Integrator Alliance Program 2017Schneider Electric
 
EcoStruxure, IIoT-enabled architecture, delivering value in key segments.
EcoStruxure, IIoT-enabled architecture, delivering value in key segments.EcoStruxure, IIoT-enabled architecture, delivering value in key segments.
EcoStruxure, IIoT-enabled architecture, delivering value in key segments.Schneider Electric
 
It's time to modernize your industrial controls with Modicon M580
It's time to modernize your industrial controls with Modicon M580It's time to modernize your industrial controls with Modicon M580
It's time to modernize your industrial controls with Modicon M580Schneider Electric
 
A Practical Guide to Ensuring Business Continuity and High Performance in Hea...
A Practical Guide to Ensuring Business Continuity and High Performance in Hea...A Practical Guide to Ensuring Business Continuity and High Performance in Hea...
A Practical Guide to Ensuring Business Continuity and High Performance in Hea...Schneider Electric
 
Connected Services Study – Facility Managers Respond to IoT
Connected Services Study – Facility Managers Respond to IoTConnected Services Study – Facility Managers Respond to IoT
Connected Services Study – Facility Managers Respond to IoTSchneider Electric
 
Telemecanqiue Cabling and Accessories Briefing
Telemecanqiue Cabling and Accessories BriefingTelemecanqiue Cabling and Accessories Briefing
Telemecanqiue Cabling and Accessories BriefingSchneider Electric
 
Telemecanique Photoelectric Sensors Briefing
Telemecanique Photoelectric Sensors BriefingTelemecanique Photoelectric Sensors Briefing
Telemecanique Photoelectric Sensors BriefingSchneider Electric
 
Telemecanique Limit Switches Briefing
Telemecanique Limit Switches BriefingTelemecanique Limit Switches Briefing
Telemecanique Limit Switches BriefingSchneider Electric
 

Mehr von Schneider Electric (20)

Secure Power Design Considerations
Secure Power Design ConsiderationsSecure Power Design Considerations
Secure Power Design Considerations
 
Digital International Colo Club: Attracting Investors
Digital International Colo Club: Attracting InvestorsDigital International Colo Club: Attracting Investors
Digital International Colo Club: Attracting Investors
 
32 phaseo power supplies and transformers briefing
32 phaseo power supplies and transformers briefing 32 phaseo power supplies and transformers briefing
32 phaseo power supplies and transformers briefing
 
Key Industry Trends, M&A Valuation Trends
Key Industry Trends, M&A Valuation TrendsKey Industry Trends, M&A Valuation Trends
Key Industry Trends, M&A Valuation Trends
 
EcoStruxure™ for Cloud & Service Providers
 EcoStruxure™ for Cloud & Service Providers EcoStruxure™ for Cloud & Service Providers
EcoStruxure™ for Cloud & Service Providers
 
Magelis Basic HMI Briefing
Magelis Basic HMI Briefing Magelis Basic HMI Briefing
Magelis Basic HMI Briefing
 
Zelio Time Electronic Relay Briefing
Zelio Time Electronic Relay BriefingZelio Time Electronic Relay Briefing
Zelio Time Electronic Relay Briefing
 
Spacial, Thalassa, ClimaSys Universal enclosures Briefing
Spacial, Thalassa, ClimaSys Universal enclosures BriefingSpacial, Thalassa, ClimaSys Universal enclosures Briefing
Spacial, Thalassa, ClimaSys Universal enclosures Briefing
 
Relay Control Zelio SSR Briefing
Relay Control Zelio SSR BriefingRelay Control Zelio SSR Briefing
Relay Control Zelio SSR Briefing
 
Magelis HMI, iPC and software Briefing
Magelis HMI, iPC and software BriefingMagelis HMI, iPC and software Briefing
Magelis HMI, iPC and software Briefing
 
Where will the next 80% improvement in data center performance come from?
Where will the next 80% improvement in data center performance come from?Where will the next 80% improvement in data center performance come from?
Where will the next 80% improvement in data center performance come from?
 
EcoStruxure for Intuitive Industries
EcoStruxure for Intuitive IndustriesEcoStruxure for Intuitive Industries
EcoStruxure for Intuitive Industries
 
Systems Integrator Alliance Program 2017
Systems Integrator Alliance Program 2017Systems Integrator Alliance Program 2017
Systems Integrator Alliance Program 2017
 
EcoStruxure, IIoT-enabled architecture, delivering value in key segments.
EcoStruxure, IIoT-enabled architecture, delivering value in key segments.EcoStruxure, IIoT-enabled architecture, delivering value in key segments.
EcoStruxure, IIoT-enabled architecture, delivering value in key segments.
 
It's time to modernize your industrial controls with Modicon M580
It's time to modernize your industrial controls with Modicon M580It's time to modernize your industrial controls with Modicon M580
It's time to modernize your industrial controls with Modicon M580
 
A Practical Guide to Ensuring Business Continuity and High Performance in Hea...
A Practical Guide to Ensuring Business Continuity and High Performance in Hea...A Practical Guide to Ensuring Business Continuity and High Performance in Hea...
A Practical Guide to Ensuring Business Continuity and High Performance in Hea...
 
Connected Services Study – Facility Managers Respond to IoT
Connected Services Study – Facility Managers Respond to IoTConnected Services Study – Facility Managers Respond to IoT
Connected Services Study – Facility Managers Respond to IoT
 
Telemecanqiue Cabling and Accessories Briefing
Telemecanqiue Cabling and Accessories BriefingTelemecanqiue Cabling and Accessories Briefing
Telemecanqiue Cabling and Accessories Briefing
 
Telemecanique Photoelectric Sensors Briefing
Telemecanique Photoelectric Sensors BriefingTelemecanique Photoelectric Sensors Briefing
Telemecanique Photoelectric Sensors Briefing
 
Telemecanique Limit Switches Briefing
Telemecanique Limit Switches BriefingTelemecanique Limit Switches Briefing
Telemecanique Limit Switches Briefing
 

Kürzlich hochgeladen

DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDropbox
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native ApplicationsWSO2
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businesspanagenda
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...apidays
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MIND CTI
 
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWEREMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWERMadyBayot
 
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...apidays
 
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...Zilliz
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesrafiqahmad00786416
 
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...apidays
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAndrey Devyatkin
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processorsdebabhi2
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FMESafe Software
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdflior mazor
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodJuan lago vázquez
 

Kürzlich hochgeladen (20)

DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024
 
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWEREMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
 
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...
 
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challenges
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdf
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
 

GIS-Based Design for Effective Smart Grid Strategies

  • 1. GIS-Based Design for Effective Smart Grid Strategies Executive summary An accurate, up-to-date model of a utility’s distribution network is the backbone of Smart Grid technologies. But a Schneider Electric survey shows that 74% of utilities are concerned about the readiness of their network model to support Smart Grid applications. This paper presents a quantitative comparison of a Geographic Information System (GIS)–based graphic work design system vs. a CAD-based tool, demonstrating how the GIS-based design approach is better able to keep up with the continuous changes in a dynamic electrical distribution network. 998-2095-05-20-12AR0
  • 2. Summary Executive Summary . ................................................................................... p 1 Introduction ................................................................................................. p 4 It’s all about the network . ............................................................................ p 6 The state of the GIS . ................................................................................... p 7 Graphic Work Design process can induce error............................................ p 9 GIS-based GWD improves network data accuracy and completeness ......... p 10 Quantitative comparison of design methodologies ....................................... p 11 Conclusion................................................................................................... p 12
  • 3. GIS-Based Design for Effective Smart Grid Strategies Executive summary The Distribution Management System (DMS) is a key smart grid technology; and complete, up-to-date network asset information is mandatory in order to develop and maintain the accurate network model on which the DMS is based. The utility’s enterprise geographic information system (GIS) database stores and maintains this network asset data and can manage the workflow for updating this vital information. In evaluating its readiness for Smart Grid implementation, the utility needs to assess the completeness, accuracy and backlog of the data contained in its GIS. One utility determined that inaccurate data accounted for a 50 percent deviation between DMS-modeled load flow and observed load flow. This discrepancy made it clear to the utility that its DMS is unusable to predict voltage reduction gains and volt/VAR optimization – the very operational functions the utility targeted in its smart grid strategy. Many errors in the GIS data can be attributed to a complex or duplicative graphic work design (GWD) process, from initiation, through design, review, lockdown, posting and as-built updating. A GIS-based GWD works within the GIS database and eliminates re-digitization of designs; takes advantage of network connectivity for QA/QC checks to improve data accuracy and completeness; and significantly reduces backlog and speeds network updates. This approach not only streamlines the design process but also yields more accurate asset information that supports network modeling, maintenance and vital planning and decision making processes. A quantitative comparison of the time involved in the typical workflow of a small design project, completed by means of manual sketching and also with GISbased and CAD-based methodologies, shows the time savings related to the GISbased GWD are accountable and significant. The same productivity advantages were seen when comparing typical workflows involved in a large design project. GIS-based design provides faster update of the network model, making it more appropriate for supporting DMS functionality – the heart of an effective smart grid strategy. White paper | 01
  • 4. GIS-Based Design for Effective Smart Grid Strategies Introduction The industry’s experience and knowledge of smart grid capabilities and benefits are growing rapidly, and utilities’ smart grid plans are becoming more sophisticated every day. While AMI once was considered the ‘golden child’ of the smart grid, utilities now see the Distribution Management System (DMS) as one of the most important components of an effective smart grid strategy. Perhaps not as readily acknowledged is the vital role an enterprise Geographic Information System (GIS) plays in driving the accurate network model needed for DMS implementations. In this paper, we highlight the value of an enterprise GIS-based graphic work design (GWD) system in maintaining an accurate distribution network model – the heart of an effective smart grid strategy. Inefficient GWD processes do not keep up with the network changes continuously being planned and executed in the dynamic electric distribution network. The resulting out-of-date or inaccurate network model can not drive mission-critical smart grid applications such as OMS, DMS, DSDR and VVR and, consequently, compromises potential smart grid efficiency enhancements and operational improvements. An efficient, GIS-based GWD solution is key to building a robust smart grid foundation. White paper on Energy Efficiency | 02
  • 5. GIS-Based Design for effective Smart Grid Strategies
  • 6. GIS-Based Design for Effective Smart Grid Strategies It’s all about the network DMS a key technology In a survey conducted by Microsoft in 2010, approximately 70 percent of the utilities responding rated DMS as a very important technology in implementing tomorrow’s smart grid.1 Indeed, the Department of Energy identified2 five fundamental technologies that will drive the smart grid; in addition to communications, response capability and storage, two DMS-related technologies make this list: • dvanced control methods, to monitor essential A components, enabling rapid diagnosis and precise solutions appropriate to any event • mproved interfaces and decision support, to I amplify human decision-making, transforming Utilize existing asset and network data at the start of your GIS-based design - perform advanced structural analyses, sag, tension and clearance investigations ensuring adherence to regulatory requirements. grid operators and managers quite literally into visionaries when it comes to seeing into their systems DMS needs accurate data The DMS is based on a network model that must DMS functionality is all about the network: accurate accurately reflect: up-to-date network data yields an accurate model driving advanced DMS functions that deliver the • etwork asset information N network improvements expected. Conversely, inaccurate or stale data results in a poor network • eal time data R • ime series data T model yielding unexpected and often ineffective results. • ransactional data T GIS key in network data integrity It is the utility’s enterprise GIS database that not only stores and maintains network asset data but also manages the workflow for updating this vital information. GIS data is the key to maintaining the accurate and up-to-date network model that is fed to all smart grid information systems, including SCADA, DMS, OMS, MDM and others. 1 Microsoft, March 2010. Worldwide Utilities Industry Survey 2 Department of Energy, Office of Electricity Delivery and Energy Reliability, 2008. The Smart Grid: An Introduction. White paper | 04
  • 7. GIS-Based Design for Effective Smart Grid Strategies The state of the GIS GIS Readiness A benchmark study conducted by Esri® queried 226 electric utility companies in the U.S. and worldwide about their confidence in the accuracy and completeness of the GIS serving their operations. The results, made available by Esri to the public in a 2010 GIS data backlog – Only one-third of utilities say they update their GIS data within ten days of field work completion. One in four respondents reported there is information older than six months that is not reflected in their GIS; see Figure 2. report,3 suggest many utilities might not be ready to rely on their network model repository to support smart grid applications – GIS data completeness – Less than 70 percent of respondents report having a complete model of their primary distribution, because not all data related to distribution assets has been converted to the enterprise GIS. GIS data accuracy – Respondents expressed they Figure 2. Utilities report that work orders can be outstanding for six months or more before GIS updates reflect completion of the field work. Source: Esri, 2010. have detected high rates of data error in their GIS databases; see Figure 1. Figure 1. When asked to assess GIS data error rate, only 15 percent of survey respondents reported high confidence (less than 2 percent error) in the accuracy of their GIS data. Source: Esri, 2010. GIS data quality Often, the problems with GIS data quality have to • hase mismatches; see Figure 3 P do with information that should be part of any utility GIS. Data errors exist because the data was entered incorrectly or converted or migrated inaccurately. In some cases, the data was managed by a system, such as CAD, with a lack of network integrity rules; in other cases, the information wasn’t entered at all. Errors include – • ransformer/customer connectivity T 3 Figure 3. This GIS map shows phase mismatch, with C-phase transformers and A-phase transformers on the same C-phase line. Esri, 2010. Is Your GIS Smart Grid Ready? A State-of-the-Industry Report. White paper | 05
  • 8. GIS-Based Design for Effective Smart Grid Strategies - hase changes between conductors P - evices/conductors where phase is null D - evices and conductors that are incorrectly D looped or multi-fed • oltage mismatches V - onductor voltage changes without a tap or C transformer - evices and conductors where voltage is null D - evices that have a different voltage than their D connected conductors • evices, particularly switches, with null or duplicate D IDs • tandard geometric problems such as S disconnected devices or conductors Errors such as those identified above often can be attributed to poor data management workflow when graphic work design (GWD) is performed in a + Not all utilities are confident Schneider Electric user surveys suggest that the reliability of their network model might be keeping many utility managers up at night – W • hat is your network model’s readiness to support Smart Grid applications? - 1 percent – Missing data or 6 inaccuracies - percent – Many missing data elements/ 4 inaccuracies - percent – Not ready 9 • What is the status of the data management workflow to maintain this model to smart grid requirements? - 5 percent – Some gaps and 6 inaccuracies - percent – Poorly established 4 • What concerns are you focusing on? - 1 percent – GIS Data Quality 8 Improvement non-GIS-based system. Continuous data correction results in backlog and a network model that is never quite accurate. Consequences of inaccurate GIS data At one utility, inaccurate data accounted for a 50 percent deviation between DMS-modeled load flow and observed load flow. The utility was not able to use DMS to predict voltage reduction gains and volt/VAR optimization – the very operational functions targeted in its smart grid strategy. Just for the record: in this instance, the model used inaccurate conductor material and size attribute data and other inaccurate device information fed to it from the GIS database. This utility used two different GWD systems with separate workflows, neither of which was GIS-based. White paper | 06
  • 9. GIS-Based Design for Effective Smart Grid Strategies Graphic Work Design process can induce error The distribution network is dynamic and always changing Subdivisions are added, businesses and homes Projects like these add, remove and switch load require more power, load shifts occur with seasonal and change the network continuously. When the variability, and outages occur. The GWD process design is completed, the network model must be by which a utility extends, maintains and upgrades updated quickly and accurately so systems using that its infrastructure is involved in nearly any daily work information can perform as expected. order: • New Services • Capital expansions • Replacements • Conversions/upgrades Design issues vary widely Designs can be simple or highly complex; and the different designs can be occurring simultaneously, workflow – from initiation, through design, review, both involving a common asset such as a pole or lockdown, posting and as-built updating – can be fuse and requiring collaboration. Some designs might simple or highly complex. Within the same utility, take years to complete, with partial postings done as different workflows involving different departments each phase is complete. might be applied on different projects. Further, A poor data management workflow defeats the purpose Performing inefficient and complex GWD workflows independently of the network GIS database – while being challenged by varying design complexity, project overlap, long transactions and partial postings – is a recipe for disaster. These conditions increase the backlog, introduce core data errors and contribute to an inaccurate and out-of-date network model. All of this compromises the enhanced efficiencies and operational improvements that any smart grid strategy promises. Figure above. ​Utilize accurate GIS landbase data to perform advanced design optimization analyses. White paper | 07
  • 10. GIS-Based Design for Effective Smart Grid Strategies GIS-based GWD improves network data accuracy and completeness Streamlines the overall GWD workflow A GWD that works within the GIS database: • ignificantly reduces backlog – direct update of S the network model within minutes • oes away with re-digitization of designs into D the GIS – and the opportunity for error • ast turnaround of network update – preliminary F or even partial posting to publish design effects • nforces Network Integrity and QA/QC rules E before a design is energized; reduces the backlog – maintains valid network connectivity and data between completion of construction and network integrity on the fly, using QA/QC checks to catch model update errors, ensuring data is entered properly from the start • liminates custom CAD-GIS integration – E typically necessary to import designs from CAD systems Benefits tangible and intangible Utilities report that GIS-based design returns tangible Utilities also report the significance of the intangible productivity benefits and significant operational cost benefits – savings – • educed labor involved in map preparation and R updates: cost savings from $40,000 to $160,000 • mproved customer satisfaction: allows better I response to service calls a year • etter decision support: graphical display of work B • ncreased productivity due to improved access to I data for crew coordination and outage dispatch information that supports network analysis and operational studies: cost savings from $38,000 to $360,000 a year • mproved engineering and maintenance efficiency I • etter safety practices: support for crew safety and B dig-safe activities, sharing data with other utilities • tandardized design practices – consistency of S in system upgrades, reducing necessary plant materials; capturing the knowledge of experienced investment: cost savings from $200,000 to $1.5 workforce million Most importantly, the GIS-based GWD process • educed overall cable for UG installation: cost R savings of 4 percent of total budget provides a single point of entry and unified workflow for asset data and network model management. The central asset and network repository – the single version of the truth, not five versions of the partial truth – feeds an accurate, up-to-date network model to mission-critical smart grid systems. Remember: smart grid is all about the network. White paper | 08
  • 11. GIS-Based Design for Effective Smart Grid Strategies Quantitative comparison of design methodologies GIS-based design vs. CAD and manual sketching To quantify some of the tangible benefits listed above, Schneider Electric examined the productivity of using a GIS-based design tool, Schneider Electric Designer, compared to that of using manual sketching and CAD-based tools. The purpose was to identify areas where GIS-based design using Designer can improve productivity and to quantify the overall efficiency gains that can be achieved through implementing a GISbased design tool. The comparison included both small and large design jobs in typical design workflow. Small design jobs involved new customer connections or minor upgrades that averaged approximately 5.5 hours for 2. Gather preliminary design information: Before completion and reflected small budgets of $2,600 the design layout, most projects require an to $5,000. Large design jobs included network assessment of the location of existing plant in reinforcement, mains replacement, road widening or service, customer requirements and other factors. large residential or commercial subdivisions. Large For smaller projects, this aspect of the design can designs averaged 47.5 hours for completion and had be a significant percentage of the total effort. much larger budgets. 3. Layout design: This is the step in which the new The term “typical design workflow” might seem like facilities or modifications to the existing network an oxymoron, because design workflows within a are specified through the staking/sketching/ utility can vary greatly, as much as those among engineering process. different utilities. For some projects, certain steps might be sequenced differently or even omitted. 4. Tabulate materials: In this step the materials However, the nine tasks described below are useful required to build the job are totaled and reported. for this study. In some work processes, these materials may be reserved for use on the project through a materials 1. nitiate work: This step usually starts with a I management system. service request, repair or maintenance requirement or an internal capital improvement project 5. Prepare cost estimate: Nearly all workflows and is often generated from a separate work require the planner/designer/technician to estimate management system (WMS). the cost of the project before proceeding to construct it. White paper | 09
  • 12. GIS-Based Design for Effective Smart Grid Strategies 6. evelop work package and construction D 8. Update design sketch for as-built changes: sketch: Often the most time-consuming step, Many designs are modified to meet field the development of the work package is the requirements, with the result that a drawing mark- communication medium between the designer up is needed to true up the original sketch to and the construction crew. It might include permit reflect the actual as-built conditions. drawings, crew instructions, a report of the 9. Post as-built changes to enterprise materials tabulation and other standard notes. database(s): Most job closeout processes 7. ubmit for approval, release for construction S require that facilities changes be documented in and build: Depending on the cost of the estimate, a mapping system (either manual or digital), and most workflows require some form of approval sometimes in tabular databases for plant or asset before committing to construction of a design, records systems. either by a supervisor or customer or both. Then the design is issued to crew and constructed. Results For both small and large jobs, an assessment of the sketching showed a 48 percent reduction in overall time for each task in the “typical design workflow” time (about 2.64 hours); Designer vs. CAD showed a was made for each of the three methods (manual, 40 percent reduction in overall time (about 1.9 hours). CAD and GIS-Based). The results shown in Table 1 For large design jobs, Designer vs. manual sketching and Table 2 clearly indicate that a GIS-based design showed a 38 percent reduction in overall time (about tool such as Designer is the much more productive 17.95 hours); Designer vs. CAD showed a 13 percent method. For small design jobs, Designer vs. manual reduction in overall time (about 4.4 hours). TABLE 1 Design Productivity for Small Jobs Workflow Task 1. Initiate Work 2. ather preliminary design G information 3. Layout design 4. Tabulate material 5. Prepare cost estimate 6. evelop work package D and construction sketch 7. ubmit for approval, S release for construction, and build 8. pdate design sketch to U reflect as-built conditions 9. ost as-built changes to P enterprise database(s) Total Hours/Savings Manual Design Hours 0.3 1.25 Percent of Total Project 5.43% 22.64% CAD Design Hours 0.30 1.06 GIS-Based GIS-Based GIS-Based Design Savings over Savings over Hours Manual, % CAD, % 0.27 10% 10% 0.56 55% 47% 0.67 0.33 0.33 0.67 12.14% 5.98% 5.98% 12.14% 0.77 0.33 0.33 0.34 0.84 0.07 0.10 0.44 -25% 80% 70% 35% -9% 80% 70% -30% 0.17 3.08% 0.17 0.14 15% 15% 0.3 5.43% 0.20 0.17 45% 18% 1.5 27.17% 1.28 0.30 80% 76% 5.52 100.00% 4.77 2.88 48% 40% White paper | 10
  • 13. GIS-Based Design for Effective Smart Grid Strategies TABLE 2 Design Productivity for Large Jobs Workflow Task 1. Initiate Work 2. ather preliminary design G information 3. Layout design 4. Tabulate material 5. Prepare cost estimate 6. evelop work package D and construction sketch 7. ubmit for approval, S release for construction, and build 8. pdate design sketch to U reflect as-built conditions 9. ost as-built changes to P enterprise database(s) Total Hours/Savings Manual Design Hours 2 8 Percent of Total Project 4.21% 16.84% GIS-Based GIS-Based Savings over Savings Manual, % over CAD, % 10% 10% 55% 47% 16 3 2 8 33.68% 6.32% 4.21% 16.84% 9.60 3.00 2.00 4.00 13.60 0.60 0.60 6.00 15% 80% 70% 25% -42% 80% 70% -50% 0.5 1.05% 0.43 0.35 30% 18% 4 8.42% 2.68 2.20 45% 18% 4 8.42% 3.40 0.80 80% 76% 47.5 100.00% 33.91 29.55 38% 13% See the sidebar on this page describing one energy company’s improved efficiency with GIS-based GWD. What does this mean to the smart grid? The two most critical steps in the GWD workflow tasks for efficient smart grid operations are Task 2: Gather Preliminary Design Information and Task 9: Post As-built Changes to Enterprise Database. In the smart grid context, these tasks can be renamed Task 2: Start from Existing Network Model and Task 9: Update the Network Model. And in both of these key tasks, GIS-based design with Designer saves considerable time: • In Task 2, Designer is 47 percent faster than CAD. • In Task 9, Designer is 76 percent faster than CAD. In other words, GIS-Based design with Designer is faster at updating the network model. It all starts and ends with an accurate up to date network model – a single version of the truth. CAD GIS-Based Design Design Hours Hours 2.00 1.80 6.80 3.60 Energy company improves workflow, efficiency DONG Energy, headquartered in Denmark, obtains, produces, distributes, deals and sells energy and associated products in northern Europe. It specializes in the design and documentation of new electrical facilities, developing more than 6,000 sites annually. Prior to instituting its GIS-based GWD, DONG project staff worked with a less-than-efficient design workflow that required hand-drawn sketches to be transferred to the GIS database and materials information to be entered into a separate file. After project completion, the GIS typically was not updated for five to six weeks. Now, with a GWD application that integrates seamlessly with the GIS, all the features selected in the design phase are automatically saved in the GIS immediately. The sketch is visible to everyone in the organization throughout the process. A formal work analysis has shown this GWD workflow has reduced project drawing time by 60 percent a year – saving the company almost two million DKK, or more than $350,000 USD. DONG energy expects these savings to be consistent going forward, as this process better positions the company to support smart grid initiatives. White paper | 11
  • 14. GIS-Based Design for Effective Smart Grid Strategies Conclusion Increasingly, utilities are realizing the significance of DMS in achieving success in their smart grid projects. To realize the promise of advanced DMS functions, however, the DMS needs a complete, accurate and up-to-date network model. An enterprise GIS-based GWD system is the proven solution for maintaining network model data accuracy. Progressive utilities targeting smart grid deployment – or even looking to save design time and the additional costs associated with asset and network data errors – are implementing GIS-based GWD and seeing significant benefits: Figure above. Powerful construction sketch generation tools in a GIS-based GWD application. R • educed design time and backlog with direct and immediate update to the GIS network model E • fficient workflows, a unified data store and streamlined business processes that eliminate redundant tasks and data errors I • mproved availability of network information across the utility, streamlining analysis, planning and decision making M • aking accurate network information available to smart grid systems so they can deliver expected results White paper | 12
  • 15. ©2012 Schneider Electric. All rights reserved. Schneider Electric USA, Inc. 4701 Royal Vista Circle Fort Collins, CO 80528 Phone: -866-537-1091 1 + (34) 9-17-14-70-02 Fax: 1-970-223-5577 www.schneider-electric.com/us June 2012