SlideShare ist ein Scribd-Unternehmen logo
1 von 1
WORK EXPERIENCE
Elring Klinger (Great Britain) Ltd – Redcar, United Kingdom Nov 2011 - Aug 2015
MASTER PRODUCTION SCHEDULLER/ PLANNER (automotive-sealing and shielding technology)
 Construct and update the MPS, evaluate changes to the MPS in terms of their impact an
capacity plans, process transactions (T-codes), convert planned orders to FPO, conduct
forecasting analysis, carry out a periodic review (rolling through time), manage backlog of
orders and ATP value (forecast consuming), execute trade-offs between customer needs and
MPC system objectives, further develop planning strategy management (aggregate planning,
level/chase/alternative strategies, JIT concept), analyze inventory levels to minimize
inventory costs, measure MPS effectiveness, undertake supervisory, review material supply
and demand.
 Prepare detailed production plans using the MRP to support the MPS (SAP/ERP), establish
priority sequencing and lead time of each operation to meet shipping dates, schedule
workflow, realising orders by converting the planned order to scheduled receipt, update
system planning factors such as changing lot sizes and safety stocks, using explicit timing and
discrete lot sizes to minimize WIP and storage time, examine CPA to reconcile errors or
inconsistencies to eliminate root causes, solve critical material shortage problems,
continuously monitor KPI and OEE.
 Analyze the CRP procedure-calculate time-phased capacity required to complete the MPS in
line the availability resources and requirements to avoid both deteriorating delivery
performance and escalating WIP or needless expense due to excess capacity, examine
input/output analysis by monitoring the actual consumption of capacity, indicate the need to
update capacity plans, control planned/actual shop performance deviation (actual lot sizes and
actual lead time).
 Implement JIT approaches to the MRP where required to reduce the complexity of detailed
planning, WIP inventories and minimize waste, use make-to-order MRP approach, introduce
pull visual system (Kanban), SPC, and continuous improvement concepts such as reduction
lead times, WIP, elimination of discrete batches, set-up time reduction, streamline execution
etc.
 Highlight areas of concern, resolve issues and ensure key potential problems are
communicated with key personnel to pursue total efficiency attainment, cost reduction,
regularly conduct team meetings to discuss the key issues and designate responsibility for
relevant action to be taken.

Weitere ähnliche Inhalte

Was ist angesagt?

Manufacturing plng and control
Manufacturing plng and controlManufacturing plng and control
Manufacturing plng and control
Karthik Yadav
 
Capacity Requirement Planning
Capacity Requirement PlanningCapacity Requirement Planning
Capacity Requirement Planning
senthil.G
 
Capacity planning
Capacity planningCapacity planning
Capacity planning
Akhil Lal
 
Om0017 advanced production planning and control
Om0017 advanced production planning and controlOm0017 advanced production planning and control
Om0017 advanced production planning and control
smumbahelp
 

Was ist angesagt? (20)

Manufacturing planning and control systems
Manufacturing planning and control systemsManufacturing planning and control systems
Manufacturing planning and control systems
 
Production planning hierarchy
Production planning hierarchy Production planning hierarchy
Production planning hierarchy
 
What is master production schedule
What is master production scheduleWhat is master production schedule
What is master production schedule
 
Manufacturing planning & control (mpc) system
Manufacturing planning & control (mpc) systemManufacturing planning & control (mpc) system
Manufacturing planning & control (mpc) system
 
Operations Planning
Operations PlanningOperations Planning
Operations Planning
 
Manufacturing plng and control
Manufacturing plng and controlManufacturing plng and control
Manufacturing plng and control
 
Production planning
Production planningProduction planning
Production planning
 
Capacity Requirement Planning
Capacity Requirement PlanningCapacity Requirement Planning
Capacity Requirement Planning
 
Scheduling
SchedulingScheduling
Scheduling
 
PulpPlan_IPW_2014
PulpPlan_IPW_2014PulpPlan_IPW_2014
PulpPlan_IPW_2014
 
Production planning and control - Basic concepts
Production planning and control - Basic conceptsProduction planning and control - Basic concepts
Production planning and control - Basic concepts
 
Capacity planning
Capacity planningCapacity planning
Capacity planning
 
Capacity Planning
Capacity PlanningCapacity Planning
Capacity Planning
 
Om0017 advanced production planning and control
Om0017 advanced production planning and controlOm0017 advanced production planning and control
Om0017 advanced production planning and control
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimation
 
Capacity planning
Capacity planningCapacity planning
Capacity planning
 
Ppc C1
Ppc C1Ppc C1
Ppc C1
 
Production Planning & Control
Production Planning & ControlProduction Planning & Control
Production Planning & Control
 
Rccp report
Rccp reportRccp report
Rccp report
 
Production planning
Production planningProduction planning
Production planning
 

Ähnlich wie WORK EXPERIENCE IN ELRING KLINGER (20)

Self Assessment 5 5.10
Self Assessment 5 5.10Self Assessment 5 5.10
Self Assessment 5 5.10
 
Resume sarang C Ghawde
Resume sarang C GhawdeResume sarang C Ghawde
Resume sarang C Ghawde
 
OM Unit_ IV.pptxucoxpuxofupupf Fuppfoufuflhlchjllh lh
OM Unit_ IV.pptxucoxpuxofupupf Fuppfoufuflhlchjllh lhOM Unit_ IV.pptxucoxpuxofupupf Fuppfoufuflhlchjllh lh
OM Unit_ IV.pptxucoxpuxofupupf Fuppfoufuflhlchjllh lh
 
Mrp MRPII Erp Implementation
Mrp MRPII Erp ImplementationMrp MRPII Erp Implementation
Mrp MRPII Erp Implementation
 
Rough cut planning
Rough cut planningRough cut planning
Rough cut planning
 
Resume -TARAK
Resume -TARAKResume -TARAK
Resume -TARAK
 
Resume_Piyush Agarwal-DM-IE
Resume_Piyush Agarwal-DM-IEResume_Piyush Agarwal-DM-IE
Resume_Piyush Agarwal-DM-IE
 
Resume Thomas Lajoie - Operations
Resume Thomas Lajoie - OperationsResume Thomas Lajoie - Operations
Resume Thomas Lajoie - Operations
 
OPERATIONS MANAGEMENT_jims.pptx
OPERATIONS MANAGEMENT_jims.pptxOPERATIONS MANAGEMENT_jims.pptx
OPERATIONS MANAGEMENT_jims.pptx
 
Resume naveen-SCM1
Resume naveen-SCM1Resume naveen-SCM1
Resume naveen-SCM1
 
01-Ahmed El Wazzan-Resume(Autosaved)
01-Ahmed El Wazzan-Resume(Autosaved)01-Ahmed El Wazzan-Resume(Autosaved)
01-Ahmed El Wazzan-Resume(Autosaved)
 
Erp viva
Erp  vivaErp  viva
Erp viva
 
Group_Manager_Demand_Planning
Group_Manager_Demand_PlanningGroup_Manager_Demand_Planning
Group_Manager_Demand_Planning
 
My Portfolio
My PortfolioMy Portfolio
My Portfolio
 
Anand_Kaulwar_Resume_V2[1]
Anand_Kaulwar_Resume_V2[1]Anand_Kaulwar_Resume_V2[1]
Anand_Kaulwar_Resume_V2[1]
 
Operations ppt
Operations pptOperations ppt
Operations ppt
 
Operations ppt
Operations pptOperations ppt
Operations ppt
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planning
 
xdoc.pl_meb.pdf
xdoc.pl_meb.pdfxdoc.pl_meb.pdf
xdoc.pl_meb.pdf
 
Unit 2
Unit 2Unit 2
Unit 2
 

WORK EXPERIENCE IN ELRING KLINGER

  • 1. WORK EXPERIENCE Elring Klinger (Great Britain) Ltd – Redcar, United Kingdom Nov 2011 - Aug 2015 MASTER PRODUCTION SCHEDULLER/ PLANNER (automotive-sealing and shielding technology)  Construct and update the MPS, evaluate changes to the MPS in terms of their impact an capacity plans, process transactions (T-codes), convert planned orders to FPO, conduct forecasting analysis, carry out a periodic review (rolling through time), manage backlog of orders and ATP value (forecast consuming), execute trade-offs between customer needs and MPC system objectives, further develop planning strategy management (aggregate planning, level/chase/alternative strategies, JIT concept), analyze inventory levels to minimize inventory costs, measure MPS effectiveness, undertake supervisory, review material supply and demand.  Prepare detailed production plans using the MRP to support the MPS (SAP/ERP), establish priority sequencing and lead time of each operation to meet shipping dates, schedule workflow, realising orders by converting the planned order to scheduled receipt, update system planning factors such as changing lot sizes and safety stocks, using explicit timing and discrete lot sizes to minimize WIP and storage time, examine CPA to reconcile errors or inconsistencies to eliminate root causes, solve critical material shortage problems, continuously monitor KPI and OEE.  Analyze the CRP procedure-calculate time-phased capacity required to complete the MPS in line the availability resources and requirements to avoid both deteriorating delivery performance and escalating WIP or needless expense due to excess capacity, examine input/output analysis by monitoring the actual consumption of capacity, indicate the need to update capacity plans, control planned/actual shop performance deviation (actual lot sizes and actual lead time).  Implement JIT approaches to the MRP where required to reduce the complexity of detailed planning, WIP inventories and minimize waste, use make-to-order MRP approach, introduce pull visual system (Kanban), SPC, and continuous improvement concepts such as reduction lead times, WIP, elimination of discrete batches, set-up time reduction, streamline execution etc.  Highlight areas of concern, resolve issues and ensure key potential problems are communicated with key personnel to pursue total efficiency attainment, cost reduction, regularly conduct team meetings to discuss the key issues and designate responsibility for relevant action to be taken.